progress report – 20 th november 2013. objective to complete the fund raising for a community...

Download Progress Report – 20 th November 2013. OBJECTIVE To complete the fund raising for a community hydro scheme at Harlaw Reservoir and ‘make it happen’

If you can't read please download the document

Upload: randall-greer

Post on 18-Dec-2015

213 views

Category:

Documents


0 download

TRANSCRIPT

  • Slide 1
  • Progress Report 20 th November 2013
  • Slide 2
  • OBJECTIVE To complete the fund raising for a community hydro scheme at Harlaw Reservoir and make it happen.
  • Slide 3
  • Agenda Whats happened since June Our Finances Your Finances Provisional Schedule Questions Wine, juice and nibbles
  • Slide 4
  • Whats happened since June Expanded team 5 members with substantial engineering and project experience Technical team meeting fortnightly Meetings with CEC Flood Prevention / Panel Engineer Grid Connection offered and accepted Hydrology re-analysed VAT Registration Design Contract Awarded Pipe Liner Repaired
  • Slide 5
  • Design Contract Awarded 5 Designers Approached 3 Quotations Received Potential Designers Met the committee Unanimous selection of Adrian Laycock Limited Extensive experience with micro-hydro schemes, dams, canals, irrigation.. Both in Scotland and across the World http://www.adrianlaycock.com/index.htm
  • Slide 6
  • Slide 7
  • Slide 8
  • Slide 9
  • Slide 10
  • Slide 11
  • Slide 12
  • Slide 13
  • Slide 14
  • Slide 15
  • Slide 16
  • Another idyllic country scene or potential for another hydro scheme?
  • Slide 17
  • The Finances
  • Slide 18
  • Seed Enterprise Investment Scheme (SEIS) Harlaw Hydro Limited SEIS is administered by the Small Companies Enterprise Centre (SCEC) in HM Revenue & Customs (HMRC) The company must submit form SEIS1 to the SCEC The company cannot submit an SEIS1 until either: it has been trading for at least four months or it has spent at least 70 per cent of the monies raised by the relevant issue of shares If the SCEC accepts that the company, its activities, and the shares all meet the requirements of the scheme, it will issue the company with a certificate to that effect, and will supply claim forms (SEIS3s) for the company to send to the investors so they can claim tax relief The company issues SEIS3s to qualifying Investors.
  • Slide 19
  • Seed Enterprise Investment Scheme (SEIS) The Investor Using the SEIS3 supplied by the company the investor claims on their Self Assessment tax return for the tax year in which the shares were issued (i.e. 2013/2014) Investors can claim relief up to five years after the 31 January following the tax year in which the investment was made.
  • Slide 20
  • Enterprise Investment Scheme (EIS) Harlaw Hydro Limited EIS is administered by the Small Companies Enterprise Centre (SCEC) in HM Revenue & Customs (HMRC) The company must submit form EIS1 to the SCEC The company cannot submit an EIS1 until it has been trading for at least four months (confirmed using form EIS2). The company then has 2 years to submit the form If the SCEC accepts that the company, its activities, and the shares all meet the requirements of the scheme, it will issue the company with a certificate to that effect, and will supply claim forms (EIS3s) The company issues EIS3s to qualifying Investors.
  • Slide 21
  • Enterprise Investment Scheme (EIS) The Investor Using the EIS3 supplied by the company the investor claims on their Self Assessment tax return for the tax year in which the shares were issued (i.e. 2013/2014) Investors can claim relief up to five years after the 31 January following the tax year in which the investment was made.
  • Slide 22
  • Who are our investors? 241 investors in total: Average size of investment - 1,588 Investments range from 250 to 10,000 Most Common - 500 or 1000 Just over half from immediate Balerno area 17% from surrounding area 17% from wider Edinburgh Area 14% anywhere else
  • Slide 23
  • Where we Live Shareholders / Society Members
  • Slide 24
  • What next? Apply to pre-accredit FiT (Feed in Tariff) for 67kw Design accepted by CECs Panel Engineer Order Turbine / generator December 2013 Lease Formalised Select contractor January 2014 Submit SEIS1 Spring 2014 Start Build Spring 2014 1 st AGM May/June 2014 Generate Electricity Autumn 2014
  • Slide 25
  • Slide 26
  • Questions Wine and nibbles