PROGRAM MANAGEMENT REVIEW
Systems DeploymentJuly 13, 2011
![Page 2: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/2.jpg)
Program Management Review
![Page 3: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/3.jpg)
AEP Project Charter (Pete Gangl)
![Page 4: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/4.jpg)
AEP Project Plan (Pete Gangl)
![Page 5: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/5.jpg)
AEP Project Plan Cont. (Pete Gangl)
![Page 6: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/6.jpg)
AEP 4 Blocker(Pete Gangl)
AEP Program Update June 27, 2011
Deployment Summary Program Highlights
Challenges/ RisksProgram Schedule - Key Milestones
Meters Deployed: 317,758
Meters Normal: 307,148
Meter installation rate: 1,100/day
50 collectors deployed
2,105 routers deployed
Meter availability problem – Optimator slip and lack of Paulaner could cause meter shortage
GE kV2c issue, AEP would like to order 2k – 6k 9s meters, defect confirmed new FW & DCW needed
6.11 FW update under way, Encryption needs to be turned off in order to update from 5.65 to 6.11 – AEP security has give us 4 wksUn-Encryption 97% - 6.11 FW spread 98% completeZigbee FW update under way
C12.22 compliance testingFDOS testing MR2 released 4/15/11Additional defects identified due to be fixed in MR3 release, TBD
release dateGAP collector is critical to rural design success – Beta units have
been promised and risk build for production has been approved
Read Success ISR
99.9% 99.59%
March 2011
Enhanced Focus AX Modular release
July 2011
Enhanced Focus AX Integrated release
May 2011
Command Center 5.0 Production Deployment
August2011
Command Center MR2 Release to Production
Aug/Sept 2011
Advanced Security Enabled in Production
Q3 2011
GAP collector/CC5.5
Command Center 5.0C12.22 testing against MR2 underway, waiting for MR3 schedule release dateAdvanced Security Deployment – Initial L+G deployment to begin ~August based on network update to FW6.11Enhanced Focus AX Deployment – AEP approved modular metersCommand Center 5.5GAP collector is primary deliveryTransition to Customer OperationAEP has verbally agreed to premium support, contract negotiations under wayTransition under way
![Page 7: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/7.jpg)
CPS Program Charter– Robert Erickson
![Page 8: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/8.jpg)
CPS Program Charter (Robert Erickson)
![Page 9: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/9.jpg)
CPS Program Plan– Robert Erickson
![Page 10: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/10.jpg)
CPS Risk Plan (Robert Erickson)
![Page 11: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/11.jpg)
CPS 4 Blocker (Robert Erickson)
CPS Energy Program UpdateDeployment Summary Program Highlights
Challenges/ RisksProgram Schedule - Key Milestones
Program ManagementS4e Meter DeploymentDeploymentS4e Meter Deployment started. No Issues.IntegrationVentryx Integration Started 6/13MDM (eMeter) Integration Testing Continues w/o L+G IssuesPlanning/ ForecastInitial Network Estimate ProvidedWorkshops Planned for Q3
Meters: High-speed discussion, 2012 quantitiesNetwork: 2012 DesignCommand Center: 5.5 Upgrade, Advanced SecurityGas: Quantities and Deployment 2012
System Acceptance Testing: CPS is very resource constrained.
L+G Resource availability delaying the timeliness of response to questions/issues uncovered by SAT.Lack of TIM resources is felt; no particular issues, but team/SAT are not 100%. 85% estimated strength.
Q3 and Q4 activities are very dependent on Command Center release schedule.
5/25, 6/3, 6/10
S4e Meter Shipments
5/15
5/23System Acceptance Test Begin
6/1 – 6/16 System Integration Testing
Week of 6/20
Security and HAN SAT Testing
6/30 Scheduled SAT Completion
June 28, 2011
Deployment Residential meter deployment complete. Commercial meter deployment underway.
Network Performance CC 4.1 SP2, MTR 5.65, DCW 1B01.05.10
PeriodTotal Number
End-pointsBillable Read Success % Read Success %
CurrentNormal: 37,359
Disc: 791Overall: 99.77%
SAT: 99.95%Overall: 99.73%
SAT: 99.95%
PreviousNormal: 36,921
Disc: 113Overall: 99.64%
SAT: 99.96%Overall: 99.67%
SAT: 99.96%
![Page 12: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/12.jpg)
Hydro Quebec Project Plan (Faisal Khan)
![Page 13: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/13.jpg)
Hydro Quebec Project Plan (Faisal Khan)
![Page 14: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/14.jpg)
Hydro Quebec Project Plan (Faisal Khan)
![Page 15: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/15.jpg)
Hydro Quebec Project Plan (Faisal Khan)
![Page 16: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/16.jpg)
Hydro Quebec 4 Blocker (Faisal Khan)
Hydro Quebec Program Update July 8, 2011
Deployment Summary Program Highlights
Challenges/RisksProgram Schedule - Key Milestones
EICT/Ericson Integration Workshop – 6/27 to 6/29
DR Best Practices – First Draft Submitted 7/6
Integration SOW – Complete by 7/30
Broadcast Module Firmware (AX) – 6/30 (96.6%)
RCA & RMA for Meter Quality Issues – In Progress
Returned Shipments – Pending Resolution
Advanced Security Reconfiguration (Disabled )
QA Environment Setup & Lefty Perch – In Progress
HQ PROD MEE/Hardening Procedures – 90% Complete
Business Process Definition & Integration Support – In Progress
SAP Part List – PO Generation & Invoicing – In Progress
Hydro Quebec Dependency:
Collector & Router Locations (infrastructure)
Meter Installer Selection –TBD
Mass Production of high-speed meters (Workaround) On-Site Metrology Support (Resource Needed)
Plan for the Center of Excellence (CoE) – POC: Jerry Figurilli
Quality Issues & RMA – ASD Report Submitted
Advanced Security OFF/High Availability OFF
Continued Impact of FW 6.11 & High-Speed – 11,310
meters. Plan for future shipments ~ 6.17 rollout Pending Contract Transfer – Letter on Intent
6/ 27 – 7/ 29 Boucherville Meter Deployment (Total 5776)
7/ 8 Broadcast Module Firmware 6.17
7/ 11 Go/No-Go – Deployment & Meter Quality
6/ 15 – 7/ 22 Rural Magog Router Installation (116 Routers)
7/ 25 – 8/ 5 Magog NW Packet Stress Test
7/ 19 – 7/ 21 HQ to visit Lafayette Facility
8/ 2 – 8/ 7 Security High-Availability Test/MEE Completion
Boucherville Pilot Deployment with GridstreamRF CC5.0, layer based, VM, Advanced Security with ECC.
Target Boucherville Deployment 5776 by 7/29 (~40%)
Endpoints Deployed: 2356 (349 S4e + 2007 Focus AX)
Network: 1 Collector & 9 Routers
System Snapshot
Discovered: 7, Normal: 2349 & Adv. Security 346 (OFF)
System Performance: CUM Read 98.5% / LP: TBD
S4e: 94.7% & Focus AX: 99.2%
FW 6. 17 (58.6% Upgrade – AX 67% & S4e 10%)
PS. Deployment in progress and FW 6.17 broadcasted weekly
![Page 17: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/17.jpg)
UI Project Charter (Joe Merritt)
![Page 18: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/18.jpg)
UI Project Charter (Joe Merritt)
![Page 19: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/19.jpg)
UI Project Plan (Joe Merritt)
![Page 20: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/20.jpg)
UI Project Plan (Joe Merritt)
![Page 21: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/21.jpg)
UI Project Charter (Joe Merritt)
![Page 22: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/22.jpg)
UI Project Plan (Joe Merritt)
![Page 23: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/23.jpg)
UI Risk Plan (Joe Merritt)
![Page 24: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/24.jpg)
UI 4 Blocker (Joe Merritt)
UI Program Update June 27, 2011
Deployment Summary- 06/ 24 data Key Highlights
CURRENT ISSUES
Meters Qty Installed Normal Billable%
ISR%
Budget2012 38,964 NA NA NA NA
FRCST 2012 38,964 NA NA NA NA
DeployTTLS 80,000 62,702 63,345 100% 100%
Spreader – 34 meters (Local Office)Meters with incorrect FW – 135 metersMeters with incorrect DCW – 5 metersZigbee – 645
DOA & RCA issues w/5.65fw will require a patch and new FW -5.67 5S& 9S meters failed UI’s FAT; Impacting May & July
Customer deliveries / Revenue Forecast, 384 meters ( $92k)
KEY MILESTONES- Meter Deliveries as of 5/ 23/ 11
1. As of May 2011, we retired (Billed) 49,553 meter.2. 5S and 9S FAT failure analysis reported internally. 3. 5S and 9S FAT samples replacements will ship June 30, 2011 –
slipped six days..4. UI has implemented Data Power into production – no issues.5. 2,876, 25S Focus meters shipped 7/22/2001 early in-lieu-of the
projected July date.
![Page 25: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/25.jpg)
CoServ Project Plan (Dan Leger)
![Page 26: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/26.jpg)
CoServ Project Plan (Dan Leger)
![Page 27: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/27.jpg)
CoServ Project Plan (Dan Leger)
![Page 28: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/28.jpg)
CoServ Project Plan (Dan Leger)
![Page 29: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/29.jpg)
CoServ Project Plan (Dan Leger)
![Page 30: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/30.jpg)
CoServ Project Plan (Dan Leger)
![Page 31: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/31.jpg)
CoServ Project Plan (Dan Leger)
![Page 32: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/32.jpg)
CoServ Risk Plan (Dan Leger)
![Page 33: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/33.jpg)
CoServ Risk Plan (Dan Leger)
![Page 34: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/34.jpg)
CoServ 4 Blocker (Dan Leger)
CoServ Electric Program Update
Deployment Summary Current Program Highlights
Risks/ LowlightsProgram Schedule - Key Milestones
Turnkey, Onsite Program, Meter Installation IncludedPhase 1 POC: 20K meters, 3 Collectors, 60 Routers
June -August 2011 SATPhase 2 FDC: 130K meters, 13 Collectors, 600 Routers
January 2012-December 2012 Post Deployment ChecklistSelf Sufficiency: 2013, Deployment Program Complete
Security reconfig bug fixed; submitted to SQA
Conducted monthly program review
Shipped 4 routers ahead of plan in support of network
optimization
FW and DCW upgrade scheduled for coming weeks, with procedure insufficiently tested to provide confidence in plan; using encrypted broadcast method. Approach reviewed and approved both internally and externally
Technical risk realized manifested in 2 bug discovery during key reconfig. Cases opened, T IV task created.
SAT start now slipped 6 weeks minimum 4th quarter revenue at risk
Encountered known issues (multiple instances) to L+G but not known to CoServ Program team.
Performing systematic review (6/13) of all known issues/bugs
June 13, 2011
Network Performance (CC 5.0, MTR 5.65, DCW 1B01.05.10)
Period Total EPs Total EPs Normal Read Success % 6/3Read Success %
6/13
Current 19987 18610 99.7 99.54
2/18 Network Hardening Complete-this week √
3/1 First Meters Installed √
5/20 Last POC meter installed √
6/10 Pre SAT checklist complete
8/26 SAT complete /Go ahead for full deployment
8/5 Receive full deployment network order
9/6 Receive full deployment meter order
12/21 Ship network equipment
1/2012 Ship 1st full deployment meter order
![Page 35: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/35.jpg)
Xcel Energy Project Charter (Karl Hutchinson
![Page 36: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/36.jpg)
Xcel Project Charter (Karl Hutchinson)
![Page 37: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/37.jpg)
Xcel Project Plan (Karl Hutchinson)
![Page 38: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/38.jpg)
Xcel Project Plan (Karl Hutchinson)
![Page 39: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/39.jpg)
Xcel Project Plan (Karl Hutchinson)
![Page 40: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/40.jpg)
Xcel Risk Plan (Karl Hutchinson)
![Page 41: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/41.jpg)
Xcel Risk Plan (Karl Hutchinson)
![Page 42: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/42.jpg)
Xcel Risk Plan (Karl Hutchinson)
![Page 43: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/43.jpg)
Xcel Risk Plan (Karl Hutchinson)
![Page 44: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/44.jpg)
Xcel 4 Blocker (Karl Hutchinson)
Xcel Energy Program Update June 27, 2011
Deployment Summary Program Highlights
Challenges/ RisksProgram Schedule - Key Milestones
Total 2-way network deployed:
790 routers
147 TOPS
13,126 Concentrators
Total 2-way meters deployed:
33K Focus AL Universal – 13K deployed, 20K remaining
10K Elster A3 meters – deployment starting after Xcel FAT approval
SQA testing
Resource constrained. Using local program resources to assist in testing
Xcel LP businesses processes
Xcel taking longer to determine their LP business processes. Can impact start of LP testing
Delivery of network flags
Xcel insisting on delivery of network flags from server log. Investigating leveraging a report targeted for AE
Focus AL material shortage
Due to meter rework and material shortage in Japan, balance of delivery of Focus AL meters may be delayed. Working with supply chain.
Plan Actual
5/15 5/25 9.4.2 Installed
5/18 5/27 Xcel testing begins
7/15 7/27 Xcel FAT approval
7/18 7/30 Xcel PO for Elster meters
8/26 9/8 Elster meters delivered
8/29 9/11 Xcel sample testing begins
9/12 9/25 Elster installation begins
Demand Reset TestingDemand reset testing under way. Corrected a demand reset
software issue
LP TestingInstalled fix for LP interval status flags. Can start initial
testing. See challengesTools
Update of ETM required
Completed Xcel FAT for residential
Focus 1s, 2s, 2se, 3s, 4s and 12s meters
![Page 45: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/45.jpg)
KCPL Project Charter (Tracy Jefferson)
![Page 46: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/46.jpg)
KCPL Project Charter (Tracy Jefferson)
![Page 47: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/47.jpg)
KCPL Project Plan(Tracy Jefferson)
![Page 48: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/48.jpg)
KCPL Project Plan(Tracy Jefferson)
![Page 49: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/49.jpg)
KCPL Risk Plan(Tracy Jefferson)
![Page 50: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/50.jpg)
KCPL Risk Plan(Tracy Jefferson)
![Page 51: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/51.jpg)
KCPL Risk Plan(Tracy Jefferson)
![Page 52: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/52.jpg)
KCPL 4 Blocker (Tracy Jefferson)
KCPL Smart Grid Program Update June 28, 2011
Deployment Summary Program Highlights
Challenges/ RisksProgram Schedule - Key Milestones
2 collectors and 14 routers – Entire network deployed early
Command Center deployed with geo based routing enabled
Meters to be deployed: 13,876 Focus AXSD & 595 S4e 3G
Meters installed to date – 13939
1500 Tendril Insight In-Home Displays were delivered to KCPL– 751 Have Been Provisioned (564 in Normal Status 187 in Find Pending Status)
Expected to deploy ~100 EcoMeters
Expected to deploy ~2000 TStat Thermostats
KCPL is slowly provisioning the In-Home Displays. There are two main defects – Join Window Closing Prematurely (Critical Issue for KCPL) – defect CQinf00010123 and IHD join even not registering in CC – defect CQinf00010739. Fixes are in Command Center 5.0 – KCPL installed and began testing CC 5.0 on Monday May 16.KCPL is having CC 5.0 installed in production today (6/ 27). They have a copy of CC 5.1 to implement in their test lab environment.
KCPL has identified some meters that are having some outage events and being logged in CC as such, but when KCPL goes out there the customer states there hasn’t been any outages. Also after this, the interval data keeps stopping and starting. These meters were thoroughly investigated in Lafayette and no issues were found. Alpharetta found these meters to be performing as expected. Asked KCPL for additional meters and they have not been able to provide any. If no more – we will close case July 1.
9/03 Entire Network Installed
10/18 Meter Installation Begins
3/18 Meter Installation Complete – Clean Up Remains
4/11Start SAT Testing – Postponed until they have their system upgrade to CC 5.0 or 5.1
6/27 Installing CC 5.0
8/01 Install CC 5.1 in Production
Focus AXSD 5.65 Firmware Delaying Install
All Smart Grid Meters received by the customer.
HAN Implementation in Demonstration Area
Next steps for the HAN is to get the TSTAT thermostat integrated and deployed. Need code fix in CC 5.1 MR1 to get these working properly. Tendril is currently testing CC 5.1 MR1 to see if issues were resolved.
eMeter Integration
KCPL is starting some training and workshops to map out what exactly they want to do with eMeter. Integration to start soon with L+G.
Read Success ISR
98.87% 98.89%
![Page 53: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/53.jpg)
Project Plant ( Taylor Torgerson)
![Page 54: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/54.jpg)
Project Plant ( Taylor Torgerson)
![Page 55: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/55.jpg)
Project Charter ( Taylor Torgerson)
![Page 56: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/56.jpg)
Project Plan(Taylor Torgerson)
![Page 57: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/57.jpg)
Project Plan(Taylor Torgerson)
![Page 58: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/58.jpg)
Project Plan(Taylor Torgerson)
![Page 59: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/59.jpg)
Risk Plan(Taylor Torgerson)
![Page 60: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/60.jpg)
Risk Plan(Taylor Torgerson)
![Page 61: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/61.jpg)
Risk Plan(Taylor Torgerson)
![Page 62: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/62.jpg)
Risk Plan(Taylor Torgerson)
![Page 63: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/63.jpg)
Risk Plan(Taylor Torgerson)
![Page 64: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/64.jpg)
Project Charter (Rick Ross)
1
Project Charter
Project Overview
NetworkDevelopmentOverview
Client Background
Customer Engagement Model
Key Metrics:Planning Phase
<Utility Name>, City, StatePhase 1 Resources Required Project Stakeholders
SDE Tim Weidenbach
PM • Rick Ross; PM
Project Team
Contractors
Key Customer Resources
Key Metrics:Service Level Agreements
<Take away statement>
![Page 65: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/65.jpg)
Oncor Risk Plan (Rick Ross)
![Page 66: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/66.jpg)
Oncor Risk Plan (Rick Ross)
![Page 67: Program management review presentation](https://reader036.vdocuments.us/reader036/viewer/2022062418/554f3fe0b4c905cd048b5377/html5/thumbnails/67.jpg)
Oncor Program Update May 14, 2011
Deployment Summary Program Highlights
Challenges/ RisksProgram Schedule - Key Milestones
Command Center Scalability IssuesSeries of environment changes have improved performance Load balancer next short term mitigation step – plan impacted by strategy to integrate Data Power appliances
Command Center 5.1 UAT BegunOperational impacts due to firmware changes and manufacturing versions have shifted target for qualification –goal is to stay in sync with mftg; options under evaluationPotential new firmware defect from IPF failures could impact
Reliant (REP) HAN Implementation StartedPerformance poor due to known LG defect (ST07 error)Oncor mitigating operationally; acceptable to REP
2011 orders reduced due to ongoing system issues (scalability, defect list, broadcast limitation, etc.)Q1 2011 meter order reduced by 2/3 (approx 160k)
Orders back to normal; risk remains but low
Operational transition impacted by broadcast limitations (LG requirement for services)
After upcoming FW spread, broadcast testing and implementation to be pursuedLayered routing implementation also in discussion
Two-way communication success rates below expectations and affecting Oncor operations90% success of demand resets impacting business
5/ 2/ 11CC5.1 M70 Release and Enhance Focus AX FAT sample delivered – UAT started
5/ 16/ 11 Upgrade to 5.67 firmware to start
7/ 1/ 11Transition to new enhanced Focus AX meters –dependent on prod implementation of 5.1
7/ 8/ 11 Upgrade production environment to CC5.1
Jan 2012Next planned upgrade in prod to 5.6 to complete final defect resolution and GWP
1,757,289 meters (21k weekly rate), 249 collectors and 6822 routers deployed
Meters Normal: 1,727,246; Billing Provisioned: 1,627,928
Performance impacted in Wichita Falls due to RF interference caused by local city services system
AES Encryption complete site wide
Firmware upgrades focused on last 2% preparing for 5.67 spread
Read Success ISR
99.51% 99.57%
* Wichita Falls meters excluded due to issue above
Oncor 4 Blocker (Rick Ross)