Page 1: Progect Vigla_NEW

Project – 3 stars Hotel - 4 stories - ”Vigla”Consultancy, Supervising and Construction Management

2004-2006

Page 2: Progect Vigla_NEW

Owners

Vigla Touristic Company Ltd.

Consultants and Supervisor Engineers

Design and construction Management

Angelos Papavasileiou

Civil-Structural-Architectural Engineer

Angelos Papavasileiou Surveying and Geoinformatics Engineer

Georgios Iliopoulos Geologist Engineer

Euaggelos Mermigas Mechanical Engineer

Orestis Basileios Electrical Engineer

Vlachavas Dimitrios

Page 3: Progect Vigla_NEW

Project InformationLocation: Greece, Thessaly, Trikala, Pirra

Page 4: Progect Vigla_NEW

Building Information4 Stories -3 Stars Hotel

-2 Basement Level for general facilities use -1 Basement Level for spa and Gym facilities 0 Floor Level for Reception, Lobby, Restaurant, Bar, Coffee, Areas 1 Upper Floor for Rooms 2 Roof Level

417 m2 per Floor

1650 m2 all levels of Hotel Budget 2.250.000 Euros

Page 5: Progect Vigla_NEW

Technical Challenges

High falling gradient field

Unstable climate/weather conditions

Headwaters control

Rain water control

Rock falls in Construction site

Slow moving underground clay layers

Layers of earth fill in the area of excavation

Big rocks in the excavation area

Low Tension of ground σ=0,11MPa and Soil elastic modulus K=400 KPa/cm

Long distance of concrete construction site more than 60 Kilometres

Page 6: Progect Vigla_NEW

Construction Management challenges

Long distance of Supplies contractors of the construction materials .

High material transfer cost.

4 months stop in the winder period.

Health and Safety challenges

Long distance from Hospital in the accident conditions .

High falling gradient field.

Quick daily change of the weather conditions.

Page 7: Progect Vigla_NEW

Phase 1 - Excavation

Page 8: Progect Vigla_NEW

Phase 1 - Excavation

Page 9: Progect Vigla_NEW

Phase 2 – Setting out – Foundations

Page 10: Progect Vigla_NEW

Phase 2 –Foundations

Page 11: Progect Vigla_NEW

Phase 3 –

Roof Basement-2

Page 12: Progect Vigla_NEW

Phase 3 – Basement -2

Page 13: Progect Vigla_NEW

Phase 3 –

Roof Basement -1

Page 14: Progect Vigla_NEW

Phase 3 –

Roof Ground Floor

Page 15: Progect Vigla_NEW

Phase 3 –

Roof Floor 2 (2 parts)

Page 16: Progect Vigla_NEW

Phase 4 –