productivity improvement through lean manufacturing

117
DSpace Institution DSpace Repository http://dspace.org Industrial Engineering Thesis 2021-02 Productivity Improvement through Lean Manufacturing Principles in Garment Section of Bahir Dar Textile Share Company. Abrham, Temesgen http://ir.bdu.edu.et/handle/123456789/12447 Downloaded from DSpace Repository, DSpace Institution's institutional repository

Upload: others

Post on 18-Jan-2022

15 views

Category:

Documents


0 download

TRANSCRIPT

DSpace Institution

DSpace Repository http://dspace.org

Industrial Engineering Thesis

2021-02

Productivity Improvement through Lean

Manufacturing Principles in Garment

Section of Bahir Dar Textile Share Company.

Abrham, Temesgen

http://ir.bdu.edu.et/handle/123456789/12447

Downloaded from DSpace Repository, DSpace Institution's institutional repository

BAHIR DAR UNIVERSITY

BAHIR DAR INSTITUTE OF TECHNOLOGY

SCHOOL OF RESEARCH AND GRADUATE STUDIES

FACULTY OF MECHANICAL AND INDUSTRIAL

ENGINEERING

Productivity Improvement through Lean Manufacturing Principles in

Garment Section of Bahir Dar Textile Share Company.

MSc. Thesis

By

Abrham Temesgen

Advisor Name: Bereket Haile Woldegiorgis, (PhD)

Co-Advisor Name: Atinkut Atinafu, (PhD candidate)

February, 2021

Bahir Dar, Ethiopia

i

PRODUCTIVITY IMPROVEMENT THROUGH LEAN MANUFACTURING

PRINCIPLES IN GARMENT SECTION OF BAHIR DAR TEXTILE SHARE

COMPANY.

Abrham Temesgen Belachew

A thesis progress submitted to the school of Research and Graduate Studies of Bahir

Dar Institute of Technology, BDU in partial fulfilment of the requirements for the

degree of

Masters of Science in the Production Engineering and Management in the Faculty of

Mechanical and Industrial Engineering.

Advisor Name: Bereket Haile Woldegiorgis, (PhD)

Co-Advisor Name: Atinkut Atinafu, (PhD candidate)

BahirDar, Ethiopia

February 15, 2020

ii

DECLARATION

I, the undersigned, declare that the thesis comprises my work. In compliance with

internationally accepted practices, I have acknowledged and refereed all materials

used in this work. I understand that non-adherence to the principles of academic

honesty and integrity, misrepresentation/ fabrication of any idea/data/fact/source

will constitute sufficient ground for disciplinary action by the University and can

also evoke penal action from the sources which have not been properly cited or

acknowledged.

Name of the student ______________________________Signature___________

Date of submission: ________________

Place: Bahir Dar

This thesis has been submitted for examination with my approval as a university

advisor.

Advisor Name: __________________________________

Advisor’s Signature: ______________________________

Co-Advisor Name: __________________________________

Co-Advisor’s Signature: ______________________________

iii

iv

ACKNOWLEDGMENTS

First of all, I would like to thank my God, for what he has done to me, and for his

willingness to conduct the study.

I am very great full to my advisor Dr. Bereket Haile Woldegiorgis who is the Assistant

Professor in the Faculty of Mechanical and Industrial Engineering for his unreserved

supports and patients along with the thesis work. His thoughts and critical comments

have greatly contributed to the thesis. Besides, I am great full to my Co. advisor Mr.

Atinkut Atinafu who is the Ph.D. candidate in the Faculty of Mechanical and Industrial

Engineering for his best supports and kindness. I believe that I have learned a lot during

the MSc thesis study will give me huge support for my future work.

I very thank full to my institution Bahir Dar Institute of Technology for facilitating such

an opportunity to study the most important area. Also, I would like to thank Bahir Dar

Textile Share Company crews for their willingness and support to conduct the study in

their company. During the study, I get continual collaboration and help from Mr. Esht

who is the garment section supervisor, so I am very thankful for your help.

Finally, I want to thank my mother Yeshitila Mersha for all you have done for me to

make me a better person and all of the achievements are the results of your continual

effort.

v

ABSTRACT

The production systems of manufacturing industries have a vital role in companies’

success. A less productive work station is one of the causes of lower production output

and profitability. The production system needs to be well organized and use effective

systems to be competitive in the global market. The case company used for this study

is Bahir Dar Textile Share Company. The garment section of BDTSC is one of the

bottlenecks for company profitability associated with poor manufacturing practice and

lower effort to address customer needs. Therefore, in this study, to improve productivity

the lean manufacturing principles are utilized. According to lean thinking, the

production process is a combination of value-adding and non-value-adding operations

and productivity improvement is achieved by eliminating non-value-adding operations.

Lean manufacturing has tools that are used to systematically study and analyze the

production process known as value stream mapping. The value stream mapping helps

to effectively implement lean manufacturing principles and model the new production

model. Some of the waste types identified in the production line were lower resource

utilization, excess inventories, waiting time, transportation, excess information flow,

and lower flexibility. The study reveals that the improved production system reduces

the lead time from 73.57 hours to 4.09 hours by 94.4 percent, non-value-added time

from 4183 min to 172 min by 96.2 %, and the inventory was reduced from 7050 pair to

750 pair of bed sheet by 89.35%. On the other hand, by using a flexible production

system the product variety is increased from one bed sheet to six bed sheet types per

day. Besides the customer-oriented production system increase the production output

by 16%, the utilization of the human resources increased by 10.3%. Lastly, the lean

production system is an effective tool to improve the productivity of garment

production in the textile industry.

Keywords: Productivity improvement; Lean Manufacturing; Value stream mapping;

Non-value-added activity; Waste elimination; Simulation.

vi

TABLE OF CONTENTS

ACKNOWLEDGMENTS ............................................................................................ iv

ABSTRACT ................................................................................................................... v

TABLE OF CONTENTS .............................................................................................. vi

LIST OF ABBREVIATIONS ........................................................................................ x

LIST OF SYMBOLS ..................................................................................................... x

LIST OF FIGURES ...................................................................................................... xi

LIST OF TABLES ....................................................................................................... xii

1. INTRODUCTION ..................................................................................................... 1

1.1. Background ......................................................................................................... 3

1.2. Statement of the Problem .................................................................................... 4

1.3. Objective of the Study ........................................................................................ 6

1.3.1 General objective .......................................................................................... 6

1.3.2 Specific objectives ........................................................................................ 6

1.4. Scope of the Study .............................................................................................. 7

1.5. Significance of the Study .................................................................................... 8

2. LITERATURE REVIEW .......................................................................................... 9

2.1. Concepts of Productivity ..................................................................................... 9

2.2. Historical Development of Lean Manufacturing .............................................. 10

2.3. Define the Company Purpose ........................................................................... 11

2.4. Waste Elimination ............................................................................................. 12

2.5. TPS House ........................................................................................................ 13

2.6. Total Framework of the Lean Production System ............................................ 15

2.6.1. Primary Purpose ......................................................................................... 15

2.6.2 Kanban ........................................................................................................ 15

2.6.3 Production Smoothing ................................................................................ 16

2.6.4 Shortening Setup Time ............................................................................... 16

vii

2.6.5 Process Layout for Shortened Lead Times and One-Piece Production ...... 16

2.6.6 Standardization of Operations ..................................................................... 17

2.6.7 Autonomation ............................................................................................. 17

2.6.8 Improvement Activities .............................................................................. 17

2.7. Value Stream Mapping ..................................................................................... 17

2.7.1 Benefits value stream mapping: .................................................................. 19

2.8. Simulating the Future State Value Stream Map ............................................... 20

2.9. Research Gaps ................................................................................................... 21

2.10. Overview of the Company .............................................................................. 22

2.10.1. Background of the Company ................................................................... 22

2.10.2. Organizational structure of BDTSC ......................................................... 22

2.10.3. Supply chain system ................................................................................ 22

2.10.4. Production system in BDTSC Garment Section ...................................... 24

3. METHODOLOGY .................................................................................................. 26

3.1. Research Problem ............................................................................................. 28

3.2. Research Design ................................................................................................ 29

3.3. Sample Design .................................................................................................. 29

3.4. Collecting data .................................................................................................. 29

3.4.1. Interview .................................................................................................... 29

3.4.2. Direct observations .................................................................................... 30

3.4.3. Questionnaire ............................................................................................. 30

4. RESULTS OF THE PRELIMINARY ANALYSIS ................................................ 31

4.1. Demographic Information ................................................................................. 31

4.2. Descriptive Analysis ......................................................................................... 32

4.2.1. Are there any activities for synchronizing customer need with the available

production rate? ................................................................................................... 32

4.2.2. Do your company producing finished goods to a supermarket/direct

shipment from which the customer pulls? ........................................................... 33

viii

4.2.3. Are you applying continuous flow in the manufacturing system?............. 33

4.2.4. Does your company's production output determine by customers' demand in

a supermarket? ..................................................................................................... 34

4.2.5. Do your company have a pacemaker process that used to schedule the rest

of the process? ...................................................................................................... 35

4.2.6. Are there leveling the production mix for fulfilling different customer

needs? ................................................................................................................... 36

4.2.7. Do your company use pitch increment of work? ....................................... 36

4.2.8. Are there techniques for reducing change over time?................................ 37

4.3. Summary of Lean Manufacturing Practice for Garment production ................ 37

4.4. Selected Product Family ................................................................................... 37

5. VALUE STREAM MAPPING ................................................................................ 38

5.1. The Current State Value Stream Map ............................................................... 38

5.1.1. Process ....................................................................................................... 39

5.1.2. Process Box ................................................................................................ 39

5.1.3. Lead Time .................................................................................................. 41

5.1.4. Travel Distance .......................................................................................... 41

5.1.5. Capturing the Communication Flow .......................................................... 42

5.1.6. Capturing Material Flow ............................................................................ 44

5.2. Creating the Future State Value Stream Map ................................................... 49

5.2.1. Icon Related with the Future State VSM ................................................... 49

5.2.2. Communication Flow in a future state VSM ............................................. 52

5.2.3. Synchronizing Customer Need with the Available Production Rate ......... 52

5.2.4. Should BDTSC Produce Bedsheets to a Finished Goods Supermarket or

Directly to Shipping? ........................................................................................... 54

5.2.5. Continuous Flow (One Piece Flow) ........................................................... 55

5.2.6. Supermarket Pull System ........................................................................... 60

5.2.7. Pacesetter ................................................................................................... 65

ix

5.2.8. Creating Flexible Production System ........................................................ 66

5.2.9. Pitch Increment and Removal of Work...................................................... 67

5.2.10. What Process Improvements will be necessary for BDTSC's? ............... 68

5.2.10. Allover Improvements Made by using Lean Principles........................... 72

5.2.11. Summary of Modelling the Future State VSM .................................. 73

5.3. Simulating the Future State VSM ..................................................................... 76

5.3.1 Simulation Result ........................................................................................ 76

5.3.2. Validating the Future State Model ............................................................. 78

6. CONCLUSIONS AND RECOMMENDATIONS .................................................. 80

6.1. Conclusions ....................................................................................................... 80

6.2. Recommendations ............................................................................................. 81

6.3. Future Work ...................................................................................................... 81

REFERENCES ............................................................................................................ 82

APPENDIX .................................................................................................................. 85

Appendix-1 Questionnaire ....................................................................................... 85

Appendix 1:1 Guidelines for implementing lean production............................... 86

Appendix 1:3 Descriptive analysis result for questionnaire ................................ 87

Appendix-2 More Findings ...................................................................................... 88

Appendix 2:1 Flow process chart (material) for production of bedsheet. ........... 88

Appendix 2:2 Flow diagram of the old layout. .................................................... 89

Appendix 2:3 Flow diagram of the future State layout. ....................................... 90

Appendix 2:4 Cycle time of operations for bed sheet production. ...................... 91

Appendix-3 Icons for Constructing the Value Stream Mapping ............................. 92

Appendix 3:1 Value stream mapping icons ......................................................... 94

Appendix-4 Simulation Analysis Result .................................................................. 95

Appendix 4:1 Arena input analyzer analysis result (Expression, Square error) .. 96

Appendix 4:2 Arena simulation analysis result ................................................. 103

x

LIST OF ABBREVIATIONS

4P Problem Solving, People and Partner, Process, Philosophy

BDTSC BahirDar Textile Share company

BiT Bahir Dar Institute of Technology

CO Change Over Time

CT Cycle Time

DES Discrete Event Simulation

FIFO First in First out

JIT Just-in-time

NVA Non-value-adding activity

OEE Overall Equipment Effectiveness

PIM Productivity improvement method

5S Seiri, Seiton, Seison, Seiketsu, and Shitsuke

TPM Total productive maintenance

TPS Toyota Production System

TQM Total quality management

VA Value-adding activity

VSM Value Stream Mapping

WIP Work in Process

LIST OF SYMBOLS

Kg Kilogram

M Meter

Min Minute

km Kilo Meter

sec Second

xi

LIST OF FIGURES

Figure 1.1: Example of value stream mapping .............................................................. 2

Figure 2.1: Toyota 4P Top Leadership commitment required ..................................... 12

Figure 2.2: The Toyota Production System ................................................................. 14

Figure 2.3: Supplier customer relationships at BahirDar Textile Share Company ...... 23

Figure 2.4: Orientation of operations in Garment Section. .......................................... 24

Figure 2.5: Operation process chart for Bedsheet 160 X 250 ...................................... 25

Figure 3.1: A modified approach to value stream map ................................................ 27

Figure 3.2: Framework Showing the Planning of Work .............................................. 28

Figure 4.1: Respondent information regarding lean practice. ...................................... 33

Figure 5.1: Availability for bailing machine ................................................................ 40

Figure 5.2; Documenting manual (verbal) and electronic communication ................. 43

Figure 5.3: Inventory three .......................................................................................... 45

Figure 5.4: Sewing work station with inventory four .................................................. 46

Figure 5.5: Inventory five ............................................................................................ 46

Figure 5.6: Inventory six .............................................................................................. 47

Figure 5.7: Current state value stream map for Garment Section ................................ 48

Figure 5.8: Current state value stream map with kaizen Burst icon. ........................... 50

Figure 5.9: Direct Shipment of finished goods to customers. ...................................... 54

Figure 5.10: Work cell formed by using first in first out lane ..................................... 56

Figure 5.11: Garment section current cycle times of operation ................................... 57

Figure 5.12: Cycle time after load sharing ................................................................... 58

Figure 5.13: The effect of continuous system in manpower utilization, time utilization,

and production output. ................................................................................................. 60

Figure 5.14: Super Market pull system for cutting operation ...................................... 63

Figure 5.15: Super Market pull system for dyeing Section ......................................... 63

Figure 5.16: Overall improvements in VA, NVA, Inventory, and WIP travel length

reduction ...................................................................................................................... 65

Figure 5.17: Andon visual control system ................................................................... 66

Figure 5.18: Load leveling box .................................................................................... 67

Figure 5.19: Future state value stream mapping with Kaizen burst............................. 74

Figure 5.20: The future state value stream mapping .................................................... 75

Figure 5.21: The future state VSM simulation result .................................................. 79

xii

LIST OF TABLES

Table 4.1: Value Added vs. Non-Value Added. .......................................................... 35

Table 5.1: Value stream mapping automatic data entry system .................................. 38

Table 5.2: Takt time data ............................................................................................. 58

Table 5.3: Withdrawal kanban. .................................................................................... 61

Table 5.4: Production-ordering kanban ....................................................................... 61

Table 5.5: Signal Kanban ............................................................................................. 62

Table 5.6: VA time, NVA time, and Inventory size reduction in the garment section 64

Table 5.7: Card for labeling different resources in the garment section. ..................... 70

Table 5.8: Allover improvements made by using value stream mapping. ................... 72

Table 5.9: Future state value stream mapping automatic data entry system................ 73

Table 5.10: Table for comparing the results of future state model and simulation model.

...................................................................................................................................... 78

1

1. INTRODUCTION

Lean manufacturing is first developed and used by Toyota Company in the 1940s.

Toyota Company is one of the leading auto sellers in the world market. The reason

behind their success in the global market is the company uses effective tools for the

production of goods. Starting from Toyota most of the lean tools (Cellular

manufacturing, Just-in-time, Total productive maintenance, Setup time reduction)

getting acceptance and implemented in discrete manufacturing (Abdulmalek F., &

Rajgopal J. 2007).

For countries like Ethiopia, the productivity of the garment industry is low. One of the

reasons for the lower productivity of the manufacturing sector is a way of production

is conventionally performed and does not use the standard way of the production system

(Tadesse A., 2011). Therefore there should be a way to use the strategy of the most

successful production system. Because this kind of change can give prosperity to

productivity if it is implemented correctly. But which kind of production system will

best fit our production system is the question.

The world has seen the crafts, mass, and lean production systems. Currently, the world

is using the lean production system and it is characterized by the production of goods

based on customer order. Lean manufacturing is a world-wide accepted philosophy of

production system that should be implemented in Ethiopian manufacturing industries

to remain a competitor in the local and global markets. The main target of the approach

is productivity improvement by enhancing the efficiency of lower productive value-

adding (VA) activities and by eliminating non-value-adding (NVA) activities. Lean

management uses these five core principles to get a productive working site. These are

valued, the value stream, flow, pull, and perfection( James P., & Daniel T., 2003).

The lean manufacturing technique is implemented with the help of value stream

mapping(VSM). Manufacturing system Value Stream is a combination of all value-

adding and non-value-adding operations, used to get finished output from a list of

inputs. In VSM there are two kinds of flow in a production line, these are information

and material flow. Like other process improvement methodology the VSM used to

sketch current and future state map this enables to see improvements made. In the

beginning, the current state of the production system is modeled which allows us to

2

detect system wastes (non-value-adding operations). In the analysis stage by using the

lean principle all wastes and system bottlenecks are identified and take action to

improve them. Then based on the analysis result improved future state map is sketched.

Finally, by comparing the two-state analysis result it’s possible to know improvements

make in shortening lead times and inventory reduction. For the final implementation of

the improved working model, the simulation software is available. Simulation software

can easily show how improved system run and detect system improvement areas with

reduced cost, time, and management intervention.

Source: (U.S. Patent No. CC BY-SA 3.0 US)

Figure 1.1: Example of value stream mapping

The lower performance is the characteristic of an inefficient production system(Tadesse

A., 2011). The high production cost is the characteristic of an inefficient production

system which increases the selling price so that it does not make the company

competitive to the global market (Derbe T., 2018). This kind of problem is solved by

following productivity improvement tools. The main objective of this study is to show

how the tools and techniques that are used to implement lean manufacturing for the

industrial system can help to eliminate wastes and improve productivity.

The study area used for our case is Bahir Dar Textile Share Company. The garment

section is the study area in the company that is used to produce bedsheets by receiving

3

fabrics from the dyeing section. The production processes consist of the following

operations; these are inspection, spreading, cutting, sewing, folding, packing, and

pressing. The study will be carried out by selecting one of the products in the process

line.

1.1. Background

The productivity of Ethiopian garment industries is near to the ground and there should

be a way to improve it to be competitive in the global market( Tadesse A., 2011). The

textile industries' lower competitiveness problem rise from both internal and external

factors. According to Rahel S. (2010) study on garment industries reveals that the

internal factors are lower capacity in performance measurement practice, financial

capacity, logistics handling as well as customer and supplier relation. On the other hand,

external factors include globalization, product short life cycle, changing market

demand, lower stability, and challenges from outside competitors are major ones.

Tadesse A. (2011) develop a method known as PIM that is used to improve productivity

from operation to firm level of Ethiopian garment industries.

Gebrehiwot A. (2017) combines value stream mapping with overall equipment

effectiveness(OEE) for improving the productivity of garment production in Knit to

Finish Garment PLC. The study reveals the combination of VSM and OEE reduces

non-value-added activity and improves OEE. The productivity improvement by using

lean manufacturing uses a simulation system to validate all the results and this will be

a new approach for studying garment production systems.

4

1.2. Statement of the Problem

Industry performance improvement is nowadays a major issue for the company’s

survival in this cost-competitive world. Like most of the textile industries in Ethiopia

BDTSC had productivity problems (Tadesse A., 2011). The garment section in BDTSC

is one of the bottlenecks for the company's productivity. The main reasons are lower

variety and quality of products, wasteful production systems, and lower capacity

utilization (Amare M., 2010). A problem like this is solved by knowing problems from

the source.

The garment section daily production report from 8/3/20 to 20/3/20 reveals that wastes

in a production site are categorized as overproduction, inventories, excess

transportation, and lower performance in line balancing (Bahir Dar Textile Share

Company, 2020). In the garment section, there were excess inventories as a result of

bottleneck operations. The fabrics in the production line have 5 delays with an

inventory amount of 7050 pairs of bed sheets. The company lead time was 5.25 days

and the percentage of NVA was 94.75% of lead time. The layout problems are the cause

for a long travel distance of work in process with a total of 7 transportation equivalent

to a travel length of 142 meters. There was an accumulation of tasks in sewing work

station but operators at a bailing operation idle for 1.5 days waiting for product.

As a garment shop, the factory had a lot of opportunities and resources to address

customer needs. In the garment industries, it's possible to produce products from cheap

to custom-made to high price products(Bruce M., 2006). Besides garment industries

produce products for different functions formal, casual, sports and uses men, women,

and children(Kunz G., 2007). To give rapid response to customer requirements the

production system needs to change from traditional producer-driven to customer-

focused strategy(Tyler D., & Heeley J., 2006). But currently, the section produces only

one-bed sheeting per shift and this was an inadequate performance in addressing

customer requirements.

Besides, the section has the attainable capacity of producing 6,000 pairs of bedsheets

per day(“https://www.bahirdartextile.com/en/,”). But currently, the factory daily

production amount shows only 1904 pairs of bedsheets. This indicates 68.3 % of

company resources are not utilized. There is a high cost of production-related to lower

resource utilization and makes the company less competitive (Mikell P., 2008). The

5

study mainly focuses on how to improve productivity by using lean manufacturing

principles. Therefore the improved production system is modeled with value stream

mapping procedures.

6

1.3. Objective of the Study

1.3.1 General objective

The main objective of the research is to improve the productivity of garment

production by using lean manufacturing principles in Bahir Dar Textile Share

Company.

1.3.2 Specific objectives

To measure the performance of garment production.

To identify the value-adding and non-value adding activities.

To model the production system by using value stream mapping.

To test the validity of the value stream mapping model.

7

1.4. Scope of the Study

This thesis work is conducted in Bahir Dar Textile Share Company located in Bahir

Dar. The thesis will focus on modeling the lean production system for garment section

by using value stream mapping. Therefore studying the current production system and

applying tools and techniques for improving productivity and finally modeling what

future state production looks like are the major tasks. The new production system is

finally simulated with the simulation software.

Besides, the performance measurement, analysis of data, interpretation, and

recommendations are the subtasks. The data required for the analysis are cycle time of

operation, inventory amount, and waiting times of inventory, equipment downtime due

to failure, equipment sharing time between operations, and so on. The data acquired are

used to sketch the current state value stream map. Then by using lean principles the

current production system is analyzed and activities the cause for lower performance

are then identified and eliminated. The analysis helps to construct a future state map.

The future state map and important recommendations are used as a blueprint of an

improved production system. Finally, the future state map is modeled with simulation

software to validate an improved system.

8

1.5. Significance of the Study

The thesis work can contribute positively by providing additional knowledge areas for

managing production systems and also by improving the productivity of manufacturing.

In the case of the former one, the validation of new production system use simulation

system and this is a new way of studying the production system. The study also gives

additional knowledge for managing the production process on an administrative level.

Whereas to the manufacturing line, the study will increase productivity by eliminating

wastes. The study is expected to eliminate wastes like unnecessary information flow

and scheduling tasks, unnecessary transportation, delays, accumulation of work in

process, and overproduction. The production process will follow the customer pull

system instead of the current shop push system. There will be a smooth flow of material

from suppliers through the production system to the customer. The production system

will be continuous instead of a batch. On the other hand, the shop manager and

supervisors are benefited from the improved working model because it reduces demand

forecasting and controlling tasks. Also for operators, the study will provide a balanced

workload and a safe working environment from an accident. The major effects of the

production system are an efficient production system, lower production cost, and

enhanced quality of goods. This in return makes the company productive and

competitive in the local and global markets.

9

2. LITERATURE REVIEW

2.1. Concepts of Productivity

Productivity is generally the ratio of the output generated by a production system and

the input. The inputs of production site are material employees, machines, capital,

space, energy, and so on while the outputs are goods and service (Ali S. et al. 2009).

The productivity measurement is affected by purpose and availability of data.

Consequently productivity is expressed with total productivity and partial productivity.

The former is the ratio of total outputs to the sum of all input while the latter is the ratio

between total outputs to one of the inputs (Kendrick J., & Creamer D., 1965).

𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑣𝑖𝑡𝑦 =𝑂𝑢𝑡𝑝𝑢𝑡

𝐼𝑛𝑝𝑢𝑡…………………………………(2.1)

Productivity is an attitude of mind to create continuous improvement (Anil K. et al.,

2008). Productivity improvement refers to the increase in output per work-hour or time

expended (Andris F., 2009). The enhancement in productivity is achieved by the

efficient use of resources employees, capital, space, materials, energy, information in

the production of various goods and services(Hans G., 2012). So far to improve

productivity so many productivity improvement methods are introduced some of them

are Six Sigma, Total Productive Maintenance, Just in Time, Lean Manufacturing,

Business Process Reengineering, Balanced Scorecard, Work-Study, Supply Chain

Management, Theory of Constraints, Five S, Kaizen, and Total Productivity

Management (Tadesse A., 2011).

Productivity is affected by different factors which will inhibit or enhance its growth.

There are so many reasons for the lower productivity of the manufacturing site. The

following listed below are all causes of wastes to eliminate in a poor production system

so that enhancement in productivity can be achieved. The first one is poor product

design which will cause high scrap amount, high cost of production, frequent design

change. The second is inefficient work design and poor method of production is the

cause for longer change over time, inappropriate tooling, poor workplace layout, large

inventory accumulation, and inefficient motion economy. The third is inappropriate

management practices, which include poor planning or scheduling practice, poor

material, and tool inventory handling, weak supervision, instruction, and training.

Lastly, waste is also created because of lower worker efficiency, including working

10

with lower pace, absenteeism, poor workmanship, and occupational hazard (Andris F.,

2009).

2.2. Historical Development of Lean Manufacturing

The world has seen three revolutionary stages in the production system; these are crafts,

mass production, and lean production. The origin of crafts production was in the 1880s

and this kind of production ends around 1915 and was replaced by mass production.

The third one begins around the 1950s. The former one is characterized by a small

quantity of production, capable of making one part in various forms, and are

decentralized but centralized within the city. Besides, the craftsmen are highly skilled

peoples responsible for design, manufacture, and assembling parts. Early Production of

Automobiles and other products are started by using crafts techniques. Mass production

is firstly used by Henry Ford for his model T automobile to produced two million

vehicles per year with moving assembly in 1920. This type of production is

characterized by specialization in specific tasks with the interchangeability of parts and

a reduction in the cost of production. But the mass production creates too much stock

of finished goods irrespective of customer order which intern caused a lower variety of

products. A problem of this kind needs new methods to regain market share(James P.,

& Daniel T., 1990).

In the 1950s after World War II, the Japanese automaker like Toyota was in great

trouble to make themselves competitor in the global auto market. The problem facing

Toyota and other Japanese factories is a material shortage for mass production, high

level of employment, difficulties to change over, difficulties to manage huge industries,

and their lower rank in the market are major ones among others. In order to solve this

kind of problems, the Toyota founder Eiji Toyoda and his chief production manager

Taiichi Ohno believes to change the mass production system. Their efforts to create a

new production system were born a lean manufacturing system (Toyota production

system). Lean manufacturing is the combined effect of crafts work and mass

production. From crafts work, it takes the advantages of producing a variety of products

and from mass production, it uses the concept of producing at a lower cost. The lean

producer is characterized by a highly skilled worker, a flexible manufacturing system,

a highly automated system, and produce a variety of products with customer

requirements (James P., & Daniel T., 1990). lean thinking is the process of identifying

11

value, make a flow of these value-creating actions in their order, perform these actions

without interruption whenever a customer needs them, and perform them more and

more effectively. Lean thinking is the process of providing more and more with less

and fewer resources, to give customers what exactly they need (James P., & Daniel T.,

2003).

Jeffrey Liker in his book of the Toyota way defines waste elimination as the heart of

lean production. Lean production is a practical system for improving the productivity

of the production system. Therefore the first thing is to articulate customer needs, what

customers need from the production site? This way if the requirements are defined the

next step will be classifying actual production system activities as value-adding(VA)

and non-value-adding(NVA) or wastes to customer wants. Finally eliminating those

wastes and implementing lean at full scale are major tasks among specific ones (Liker

J., 2004).

Deshkar et al. (2018) create a lean manufacturing framework suitable for small-scale

industries. The researcher applies lean manufacturing in the plastic bag manufacturing

industry by preparing a value stream mapping framework. The future state VSM

reduces the VA time by 74.5% and reduces Takt time from 46 minutes to 26.6 minutes.

Besides the production output increase from 28 to 50 and they recommend the VSM

framework will be applicable in small-scale industries.

Baysan et al. (2019) apply lean manufacturing in a real-life cable ladder manufacturing

system to minimize energy consumption. The method they utilize for analysis

composite of energy VSM, design of experiment, and simulation. The value stream

mapping tool helps to identify waste types but to determine the degree of contribution

for energy consumption they utilize the design of the experiment. They simulate the

result of experimental design and finally, an optimized lean production system is

modeled. The suggested model by using a lean production system reduces energy

consumption by 72.3%.

2.3. Define the Company Purpose

The Toyota production system has 4P rules which are the commitment required for

managers to effectively perform their work. These are problem-solving, people and

partner, process, and philosophy. The former one is achieved by understanding and

developing an attitude of continuous improvement in the workplace. The latter is

12

focused on creating long-term partners for the company. Besides, it works on

employees to develop a commitment to live their company philosophy. The third one

is used to create a commitment to implement a lean manufacturing system. Meanwhile,

managers also need a commitment to creating a reliable and automatic production

system. The last one works on the company long term contribution to society and

commitments for company growth(Monden Y., 2012).

2.4. Waste Elimination

Lean thinking is a philosophy that is based on the elimination of all wastes (i.e., non-

value-adding activities) to improve the performance of a production system or an

enterprise. Manufacturing system value stream composite of activities that are value-

adding and non-value adding. Value-adding activities are the ones that contribute and

part of the final product. Operations within the process that do not add value for final

Source (Monden Y., 2012)

Figure 2.1: Toyota 4P Top Leadership commitment required

output but supplement value-adding (VA) activities are known as non-value-adding

(NVA) activities. The technique focuses on enhancing the efficiency of value-adding

activities and discarding activities that are non-value adding. The Toyota production

system identifies seven types of wastes in the production system. By adding newly

found waste type the eighth waste types are listed as follow (Liker J., 2004).

Overproduction; producing items without customer order, this causes the need

for storage space, transportation, and human resource to manage.

Process (Eliminate Waste)

Philosophy (Long-Term Thinking)

Problem Solving

(Contineous Improvement & Learning)

People and Partner

(Respect, Challenge, & Grow them)

13

Waiting time; delays caused by waiting time for tools, work in process,

equipment, and human resource, or due to maintenance downtime, delay during

supply, bottleneck process, and scarcity of employees.

Transportation; transportation is a waste when there is traveling long-distance

and when it takes too much time.

Over-processing; are inappropriate practice inside the shop floor because of

poor product design, poor method of production (tooling, equipment used,

procedure, and so on), and poor management practice

Excess inventory; this includes raw material, work in process, and produced

item. Besides equipment, machines, tools, and spare parts needed for processing

excess inventory are wastes.

Unnecessary motion; this type of wastes takes place during different activities

at work, including looking, long reaches, transportation, and stocking

Defects; are produced defective items, resources wasted for rework, rejected

items, and cost of inspection are some them.

Unused employee talent; are experience, certificate, ideas, and skills of

employees not properly used due to lower involvement of employees at each

level.

In lean manufacturing, each operation needs to be arranged in cellular type, this will

enable to implement one piece flow based on the customer demand rate. In addition,

each operator, machine, and work station needs to close each other to reduce travel

distance and to effectively exchange information. The combined effect of this will

reduce lead time, space requirement, work in process, and cost of production(James P.

& Daniel T., 2003). The lean production system is in evolutionary progress in which

many improvements are made on it to get the ultimate results. The system is constructed

by combining the working principles of Frederick W.Taylor (scientific management)

and Ford (mass production)(Monden Y., 2012).

2.5. TPS House

TPS house is a simple representation of Toyota production system structural elements

that make it strong enough to withstand every wave that comes to it. It enables us to

produce with the lowest cost, short lead time, and at the required level of quality. The

two pillars are just-in-time and jidoka (autonomous defects free system and automation

system with no involvement of people). At the center of the house, there is a stable,

14

standard, reliable, and heijunka (production systems with leveling of variety and

volume of work in process) production system.

Source (Liker J., 2004)

Figure 2.2: The Toyota Production System

Stability is the main characteristic of the Toyota production system (TPS). This is due

to the continuous nature of it which is used to process one unit at a time. The errors like

a defective product, machine breakdown, and operator absenteeism cause instability in

the production system. Therefore, the production system needs urgent and preventive

measures to make available for production at all times. In order to resolve such kind of

problems, there should be systems like total productive maintenance, autonomous

defect control, and Andon signaling system. Peoples are the core of the TPM house and

they safeguard the stability of the system. Therefore skilled people always ask the

question why? to resolve complications happening from the source. Genchi Genbutsu

is to look at what happens during the process of problem-solving (Liker J., 2004).

Levelled production

Stable and Standard processes

Visual Management

Toyota way Philosophy

Just in Time

Right part, right

amount, right time,

*Takt time

planning

*Continuous flow

*Pull system

*Quick

changeover

*Integrated

logistics

Jidoka (In station quality)

Make Problems

Visible

*Automatic stops

*Andon

*Person machine

separation

*Error proofing

*In-station quality

control *Solve

root cause of

problem (5 Why’s)

Best Quality - Lowest Cost – Shortest Lead Time – Best safety –

High Moral

through shortening the production flow by eliminating waste

People and teamwork Selection, Common

goals, Ringi decision

making, Cross trained

Waste Reduction Genchi Genbutsu

5 Why’s, Eyes for Waste

Problem Solving

Continuous Improvement

15

2.6. Total Framework of the Lean Production System

2.6.1. Primary Purpose

Profit through cost reduction: The ultimate goal of productivity improvement is

making a profit by reducing cost. Lean manufacturing reduces the cost of production

by eliminating waste. There are four kinds of wastes Excessive production resources,

Overproduction, Excessive inventory, and unnecessary capital investment. The first

kind of waste includes excessive human resources, equipment, and machinery. These

kinds of wastes are causes for employees’ salaries, depreciation costs, and capital costs.

Excessive production resources create another type of waste known as overproduction

and inventory. Inventories and produced items are the cause for unnecessary capital

investment including; space requirement, cost of transportation, cost of hiring peoples

to manage inventory.

Quantity Control, Quality Assurance, and Respect for Humanity: The cost

reduction through improvement activity must meet other sub-goals. The first one

quantity control which enables an adaptation of daily and monthly fluctuation of

customer demand. While quality assurance allows producing products within

specification. Respect for humanity is another objective that a production system must

attain during cost reduction. When the production system is improved by using cost

reduction the employees must gain over time salaries when working for more than 8

hours. In addition, when employees must not be eliminated from work without gain

complementary salaries.

2.6.2 Kanban

Kanban is a signaling system for implementing JIT production. Kanban is a card like a

tag in it there are types, quantity, and pace of production for a particular product and

flow from one operation to another within the manufacturing site. There are two types

of kanban: these are withdrawal and production ordering kanban. The former one is a

detailed description of which type of product to withdraw. In the same way, the later

one is production ordering description to preceding operation. The kanban system is

supported by the following: Smoothing of production, Standardization of jobs,

Reduction of setup time, Improvement activities, Design of machine layout, and

Autonomation.

16

Just in Time (JIT): In JIT production system suppliers deliver the required item, at the

right quantity and time when production begins. If the JIT is implemented the

production system will be free from inventory in return will save a tremendous amount

of capital from inventory cost. To implement JIT a production system needs to be

organized with a pull system. Therefore at first, there must be a supermarket to deliver

products to a customer. Then when there is space in the supermarket a production

system continuously works to fulfill each space. The second important tool to

implement JIT is Autonomation. Autonomation (in Japanese, “jidoka”) may be loosely

interpreted as autonomous defect control. It supports JIT by never allowing defective

units from a preceding process to flow and disrupt a subsequent process. Finally to

prevent the frequent breakdown of machinery the JIT production system uses Total

productive maintenance (TPM) is a maintenance technique focus on prevention rather

than breakdown maintenance aiming to have a continuous flow of work in process.

2.6.3 Production Smoothing

Production smoothing is the cornerstone of the Toyota production system to work using

kanban to adapt to changing market demand. The main advantage of this kind of system

is to produce a variety of products evenly in the production system, in small quantities,

and in accordance with daily Takt time. There are techniques for applying production

smoothing these are determining the daily production sequence and adapting to product

variety by utilizing general-purpose machines.

2.6.4 Shortening Setup Time

Set up time reduction is continuously trying to reduce the setup time on a machine. This

system helps to reduce change over time in machinery to produce a variety of products

quickly. To reduce set-up time in large press machine single minute exchange of dies

is used. Besides, preparing the setups for quick change over by using an automated

system and by reducing the size of work in process can also reduce the setup time.

2.6.5 Process Layout for Shortened Lead Times and One-Piece Production

In a multi-process handling line, an operator handles several types of machinery

processing one by one leads the foundation one-piece production. The one-piece

production has the following advantages reduce lead time, reduce unnecessary

inventory, and be used to create multi-skilled operators. One-piece production can also

17

be achieved by using cellular manufacturing. Cellular manufacturing is the arrangement

of machines and human resource in sequence to easily conduct activities

2.6.6 Standardization of Operations

The standard operation at Toyota mainly shows the sequential routine of various

operations taken by a worker who handles the multiple kinds of machines. There are

two types of sheets for standard operations: the standard operations routine sheet is

characterized by a man-machine chart, while the standard operation sheet, which is

posted in the factory for all workers to see. This latter sheet specifies the Takt time,

standard operations routine, and standard quantity of the work in process

2.6.7 Autonomation

The two pillars of Toyota Production System are JIT and Autonomation. To realize

perfect JIT, 100 percent of defect-free units must flow to the subsequent process, and

this flow must be rhythmic without interruption. Therefore, quality control must coexist

with the JIT operation throughout the kanban system. Autonomation is a mechanism to

prevent defects flow in a continuous production system.

Visible Control System: is an electric light board (Andon) that is used to detect

problems happening, by hanging high above employees so that it can be seen by

everyone. In a visual control system, there is a yellow light for help and delays and a

red light when there is trouble that stops machine work.

2.6.8 Improvement Activities

In the Toyota production system, there is a quality control circle in this group each

worker can contribute to improvement by providing their suggestion. Quality control

has the following benefits one, controlling production amount by using standard

operation routine sheet, two, quality assurance by providing defect-free production

system the third one is respect for humanity by accommodating individual thought in

improvement activity(Monden Y., 2012).

2.7. Value Stream Mapping

Value Stream Mapping is ‘a pencil and paper tool that helps you visualize and

understand the flow of material and information as a product makes its way through its

value stream (Mike R., 1999). The need to use value stream mapping is firstly used by

18

Taiichi Ohno in Toyota Company. He wants to teach Toyota production system (TPS)

for major Toyota projects to visualize process flow and learning by doing. Then they

created an effective system that is used to show material and information flow known

as value stream mapping. The value stream mapping is first documented by Mike

Rother and John Shook in their book known as learning to see. The technique is used

to sketch the current state map which enables us to see the non-value adding time from

lead time. On the other hand, this figure enables us to take major corrections on the

value stream by using lean principle. Finally, the improved material and information

flow are documented in the future state value stream. Besides, it used to make a relation

between the two states which enable us to show the system improvement area. (Monden

Y., 2012).

The expected outputs from value stream mapping are flexibility, short lead time,

connected process, flow loops, simplified information flow, awareness of the customer

requirement, and pacesetter. Less see them in detail;

Flexibility; is a characteristic used to produce a variety of products as much as

possible with a single loop structure. The first thing that needs to fulfill in this

case is a supermarket system used to know what customers want.

Short lead time; is the time expected after eliminating waste full activities,

besides, it respects customer need so as to deliver within the time given or Takt

time.

A connected process; is the result of narrowing the gap between each operation

and work station to create a one-piece flow. This way of production enables us

to have a pull system that functions with respect to Takt time.

Flow loops; come to life when the market and production system easily

communicate with each other without obstruction. This kind of information

exchange is possible when there is a supermarket.

Simplified information flow; simple information flow is one of the end goals of

value stream mapping within the production system as well as out of the

company. This will reduce the effort needed to manage a production system.

Awareness of the customer requirement, a card like Kanban flowing in each

operation creates awareness of the customer requirement. This will enable the

production system to produce items on time.

19

Pacesetter; is the operation used as a pacemaker for other operations which used

to produce at different paces.

Romero L., & Arce A. (2017) Study the application area of VSM in the manufacturing

sector by analyzing different studies carried out on Value Stream Map. In addition, they

can observe the VSM is applicable in fields of construction, health care, transport,

product development, service (call center, government), architecture, mining, and so

on. The Study recommends using VSM and it gives a better result when it is applied in

the manufacturing sector with lower performance.

Gebrehiwot A. (2017) combines value stream mapping with overall equipment

effectiveness(OEE) for improving the productivity of garment production in Knit to

Finish Garment PLC. The study reveals the combination of VSM and OEE reduces

non-value-added activity by 21 % and improves OEE by 8%.

Amdework G. (2019) improve the productivity of shaft and gear production line in

Hibret Manufacturing and Machine Building Industry. The result of the study shows

that production lead time can be reduced by 23.66%; process cycle efficiency can be

improved from 27.6% to 36.2%; waiting time can be reduced by 37.74%; total distance

traveled can be reduced by 61.2%, and the number of workers can be reduced by25%.

2.7.1 Benefits value stream mapping:

It helps to visualize the whole value stream in a single sheet.

It enables us to see the root causes of wastes in the production system

It reduces the complexity of studying the production system.

It is a common language for implementing the lean manufacturing system.

It is the easiest way for introducing the recent worldwide accepted

manufacturing system.

It helps to show both information and material flow in value stream at a time.

It enables us to see improvements by comparing current and future state value

stream.

It is a flexible system that enables to update value stream daily when input data

are varied and things go wrong (Mike R., & John S., 1999).

To improve the performance of VSM so many studies are carried out. Lugert et al.

(2018) develop a dynamic value stream mapping management (DVMM) to improve the

20

flexibility of the production system by considering digitalization technologies and

organizational structure. In this system, the value stream mapping is assisted by data

analysis and simulation which helps the value stream to give attention to all production

systems by referring to industry 4.

Value stream mapping is applied in the manufacturing line easily but when there is

merging operation or multiple manufacturing lines it's hard to make VSM. Braglia et

al. (2017) develop an improved VSM which was used to solve the above problem in

the refrigerator manufacturing process. The production process of the garment section

uses only a single line of the production process which is a good opportunity for the

researcher to use value stream mapping.

2.8. Simulating the Future State Value Stream Map

Implementing lean at full scale cannot be accomplished within a short period. It needs

to manipulate a vast amount of company resources including inventory, human

resources, and machinery. It is so hard to see change within a short period because the

implementation of lean needs gradual change of work habits of employees and working

conditions. Sometimes companies managers are not willing to make changes in their

production system or they are less committed. This kind of situation is common in

production sites the reasons are lower awareness of improved systems, reluctance to

make a change, fixed mindset, satisfaction with what already they have, and fears if the

thing is not working well. This kind of unwillingness to cooperate and make changes

are a challenge for the researcher. Therefore in this kind of situation, software like

simulation software is more important to create awareness, validate the performance of

an improved system, and eliminate uncertainties ( Abdulmalek F., & Rajgopal J., 2007).

The above reasons tell us there is a need for simulation software for visualizing all the

results. Simulation can be categorized as a discrete event or continuous. The former is

used for changes happening at separated points while the second one is used for a

process that changes continuously in time. The simulation software is developed to

examine the system responses for various levels of loading. For the maximum loading

of demand, the software shows system in capability. The system inefficiency in the

model can predict the problematic regions of the system. There are different techniques

for improving bottleneck operation in simulation software.

21

Stadnicka D., & Litwin P. (2019) study reveals that how the system dynamic model

combined with the VSM model to improve the productivity of the automotive industry.

They utilize vensim software and there is no additional information used beyond VSM

data to make a system dynamic model.

Neeraj et al. (2018) model the material flow of aluminum break brackets by using Arena

software. The discrete event simulation is utilized for determining system bottleneck,

the number of crews, and productivity. The cycle time is analyzed by the input analyzer

tool and process optimization is carried out by process analyzer and Opt Quest. The

results with an improved model are a 6% increase in productivity, and an 8.33%

decrease in the workforce relative to the present production model.

Sime et al. (2019) use arena software for line balancing in the apparel industry. Arena

software is used for modeling and analysis of garment style(ladies tunic). Their study

reveals that computer simulation is an effective system for analyzing the performance

of the production system. They also indicate that simulation software is helpful in

planning and scheduling tasks.

2.9. Research Gaps

Previously the research was done directly by implementing lean manufacturing in the

production line. This conventional way of experimenting will incur additional cost and

time. Besides, sometimes production managers are resistive to make changes during the

actual implementation phase. Amdework G. (2019) improves the productivity of shaft

and gear production by deploying lean manufacturing in the production line. There is

no study found that combines lean manufacturing or any other improvement tool with

a simulation system. This study will be new for garment production in a way that

combining value stream mapping with a simulation system. This will benefit the

researcher to conduct the implementation phase with reduced cost and time.

Gebrehiwot A. (2017) study on the garment industry shows a reduction in non-value-

added activity by 21 % but this study has a limitation in clearly identifying non-value-

added activity and stating improvements numerically. There are few studies is done on

improving the productivity of garment industries. Therefore the study will have a good

opportunity in filling the research gap.

22

2.10. Overview of the Company

2.10.1. Background of the Company

Bahir Dar Textile Share Company (BDTSC) was established in 1961 in the town of

Bahir Dar, 570 Km North West of Addis Ababa. The company produces Bed sheeting

export & local, Poplin, Drill, Twill, Flannel, Kutta Abujedid, and Yarn on hank. The

major inputs of production are lint cotton, chemical, and dyestuffs

(WWW.assolombarda.it,). The company produces most of the products for the local

market. The company have tremendous privilege to owners, employees, surrounding

peoples, and as a whole to the country in the following way;

The raw material used for production comes from the agriculture sector, so it

supports the life of cotton supplier farmers.

The short life cycle of the product and its basic necessity to man’s life provides

a large demand and makes investors profitable.

The textile industries are highly labor-intensive ways of production provide

wages to the employees and support the life of the surrounding people that

interact with the company.

The industry contributes to the country a lot by consuming agricultural products

and from taxation.

2.10.2. Organizational structure of BDTSC

The company was organized into five sections. The production and technique

department, quality control service, planning and programming department,

administration division.

2.10.3. Supply chain system

The main raw material used for bedsheet production is supplied from ginning factories

locally. The supply chain system looks like in figure 2.3 below. The supplying process

starts when cotton grower farmers sell their products to the ginning industries. The

ginning industries convert raw cotton fibers into lint cotton. There were limited

numbers of ginneries that can supply quality lint cotton according to specifications.

This will have an impact on the quality of finished goods. Therefore BDTSC should

work on improving the productivity of suppliers for quality input resources.

23

On the other hand, the flow of material inside the factory begins when the Wholesaler

orders products in person or with electronic fax in the Purchasing and Sales department.

Then the production control unit schedule to produce a variety of products with

available resources and sends orders to each section. Based on that information spinning

section converts lint cotton into yarn and the threads were transported to the weaving

section. In the weaving section with the help of weaving machines yarns transforms

into fabrics. Next to the weaving process, in the dyeing section fabrics are dyed with a

different color solution. Fabrics were then printed with different designs in the intaglio

roller printing machine. Finally, the dyeing section supplies the required type of fabrics

to the garment section.

Source (Amare M., 2010)

Figure 2.3: Supplier customer relationships at BahirDar Textile Share Company

The last shop in BDTSC is the garment section and the main output of the shop is

bedsheets. Inside the garment section, the shop managers schedule production resources

for a week and inform supervisors. The supervisors on the other hand inform the

operators about daily activities and the required outputs. Then operators produce goods

and are stored for a while and shipped to wholesalers. This way materials flow from

suppliers along the production process and finally to customers.

Weaving Process

Wholesalers Retailers Customer

Fabric Finishing

Garment Section

Retailers Customer

Spinning Process Ginning ProcessCotton Growing

Farmer

Cotton Fibre Lint Cotton Yarn

Fabric

Bed sheet

24

2.10.4. Production system in BDTSC Garment Section

Production is the use of machinery, human resources, technologies, and information for

changing input raw material into more value finished goods. The company consists of

machines that are general-purpose suited for multiple operations and controlled by

human intervention. The production system follows a batch production system which

is characterized by lower demand than the production capacity of the section and the

production method was traditionally adopted. In the batch production system, there was

an accumulation of inventory. The production system of BDTSC gives priority for

customer orders and follows batch repeated at an irregular time interval (make to order).

But when there was lower customer order the production system will have a high idle

time of company resources like machinery, operator, and material, and so on. In order

to prevent the company from lower productivity, the company uses batch repeated at

regular time intervals (make-to-stock). Therefore the production system of BDTSC was

a combination of made to order and make to stock.

Figure 2.4: Orientation of operations in Garment Section.

Productivity improvement refers to the increase in output per work-hour or time

expended(Andris F., 2009). The productivity improvement in the production site was

achieved by eliminating NVA activities. Non-value-adding activities related to the

production site were work content added by poor product design, inefficient method of

production, poor human resource utilization, and so on.

25

Operation process chart for Garment Section

Figure 2.5: Operation process chart for Bedsheet 160 X 250

Flow process chart

The product chart provides the details of the events involving work in process. The flow

process chart consists of operation, travel, delay, inspection, and storage icons and with

the help of icons, it’s possible to represent the flow of worker or materials. Next to the

process chart icon, there is value-adding and non-value-adding time and on the last

column, there is travel distance. Appendix 2:1 has 1 inspection, 5 operations, 5 delays,

7 transportation, and 1 storage.

Flow diagram

The flow diagram is a helpful supplement to the flow process chart because it indicates

backtracking and possible traffic congestion areas, and it facilitates developing an ideal

plant layout. In addition, the flow diagram can show the travel length which enables to

make improvements. The present and future state value stream flow diagram can be

found in appendix 2:2 and appendix 2:3.

Bed sheet 160× 250

12 sec Inspection

11 sec Cutting

155 sec Folding

97 sec Sewing

4 sec Unitizing

02

03

04

06

01

152 sec Packing 05

26

3. METHODOLOGY

The method of studying the production system is a sequential activity of data collection

and analysis of data based on techniques. Data collection is the process of extracting

useful information that was used in the analysis stage. The data were categorized into

quantitative and qualitative data. The quantitative data gives tangible data for

conducting the analysis. The data are numerical data from company reports, measuring

instruments and questionnaires. The qualitative data were taken from observation and

this data was observer point of view expressed by using pictures and words.

After data collection, the next main activity was an analysis of the collected data.

Therefore the first analysis stage was used to validate the necessity of the study. The

data were collected using a questionnaire. The analysis part was carried out by using

Microsoft Excel software. Besides the analysis result helps to identify the product type

and some improvement areas.

The second analysis stage was the Value stream mapping (VSM) procedure and it helps

for illustrating the process flow, analysis, and process improvement. The VSM was

carried out by using QI macros software. The current state value stream mapping was

sketched by measuring performance on the shop floor, by referring company reports,

and by direct observation on a production site. The current state map was helpful for

modelling the future state. The future state VSM was sketched by using lean

manufacturing tools and this tool helps to make improvements in current state VSM.

The future state VSM was used as a blueprint for the improved production system.

Finally, the simulation of a future state was carried out by using ARENA software and

it helps to validate all improvements made.

The conventional value stream mapping procedure was found in a book called Learning

to see value stream mapping to add value and eliminate MUDA(Mike R., & John S.,

1999). The modified VSM is found in a journal by (Deshkar et al., 2018) and they

prepare a value stream mapping framework for plastic bag manufacturing industry. The

main difference between modified approach and the conventional method was only on

the implementation phase. In the conventional method, the last phase is implementing

the future state VSM by preparing an implementation plan. But implementation is not

part of the study so there must be a validation tool for future state model. In the modified

27

approach uses only the software validation to mimic the real system, and this way the

study was conducted by using the modified approach.

Source (Deshkar et al., 2018)

Figure 3.1: A modified approach to value stream map

1. Select Product Family: From the product mix of the garment section by using the

first analysis result the product selection is carried out.

2. Draw Current State Map: Based on the selected product type data are collected. In

this process performance of each activity is measured including; Cycle time,

Changeover time, Uptime, Inventory level, batch size, available time, number of

operators, and so on. Then by using the QI macros software the current state VSM is

sketched.

3. Analyze current state map: In the analysis phase, the performance of each operation

was analyzed, and activities that need improvement were identified as system

bottlenecks. This way sources of wastes listed by lean techniques from the current state

map were eliminated. This stage was the core where improvements in all process took

place.

4. Eliminate wastes and draw a future state map: Future state map was drawn by using

information gathered in the analysis stage. In this stage all wastes were discarded, the

operation needs to be combined came to one operation, the process will have a cellular

type and a demand-pull type of production is used.

5. Simulate future state map: Simulation was carried out by using data from the future

state map.

Select Product

Type

SketchCurrent

State Map

Analyze Current

State Map for Wastes

Eliminate Wastes

and Draw Future

State Map

Simulate Future

State Map

28

Figure 3.2: Framework Showing the Planning of Work

3.1. Research Problem

The main purpose of this analysis was to know the current awareness of employees

toward lean practice and to find out the actual status of the company on lean practice

based on well-known principles. In addition, the research is also used to identify major

problems in the company. This will enable us to identify improvement areas in the

company and used to implement lean manufacturing at full scale.

29

From the research problem, it’s clear that if the research result indicates lower

awareness of employees and poor lean practice it will be the study improvement area.

On the contrary, the positive outcome of the research will allow us to look at other

improvement tools.

3.2. Research Design

The study area used for the research in Bahir Dar Textile Share Company was the

garment section. This was because of one, it used us as an incubation center for lean

practice. Lean production was a practical system used to enhance the performance of a

production system. So if we apply lean within the Garment section and if the results are

good it’s possible to implement it in the preceding section. 2, Most of the other stations

were uses automated machines compared to the Garment section. On the contrary, the

Garment section uses a manual operation system with lots of drawbacks. 3, besides, it’s

the most sensitive station for all stage because its finishing stage and wastage at this

stage will cost high compared to others. The research will be a descriptive research

type.

3.3. Sample Design

A total of 26 employees at a managerial level were sampled using the purposive

sampling method. Employees at the managerial level have a better understanding of the

factory production system and the topic of study.

3.4. Collecting data

The research was mainly carried` out with Interviews, Questionnaire, and Observation.

This data was then analyzed using Microsoft excel.

3.4.1. Interview

Interviews were conducted with the operators and production supervisor. The

researchers used the following questions.

1. Have you started implementing Lean Manufacturing Practices?

2. What are the activities for full filling customer need?

3. What are the activities for improving quality?

4. What is the source of wastes in your production site?

5. What are the activities for eliminating wastes?

30

3.4.2. Direct observations

The researchers observed the production activities and flows of activities. The study

was carried out by observing how each operation was carried out, the material handling

system, the layout, and how information and material flow in the production site. Direct

observations enabled the researchers to collect reliable data without relying on the

respondents’ willingness and abilities.

3.4.3. Questionnaire

The questionnaire was taken from guidelines in a book called Learning to See value

stream mapping (Mike R., & John S., 1999). The guidelines were broadly covered in

the later sections and were the determining factors for the company’s success in many

ways. The questions were also the prerequisite to implement lean at an organizational

level. The questions were distributed for managers at higher and middle level to know

their experience regarding lean practice. The questions were listed in appendix 1:2 and

each statement was assigned with a five-point Likert scale from very poor to very good.

These scales allow us to measure statements from 1 to 5. This data was then analyzed

using Microsoft Excel software by using simple descriptive data analysis.

31

4. RESULTS OF THE PRELIMINARY ANALYSIS

The preliminary analysis result had two sections. The first one deals with demographic

information of respondents and in it the employees' age, qualification, and working

experience were included. The later one was descriptive analysis and interpretation of

respondents reply for the guidelines and the mean for each question were broadly

elaborated.

Before the analysis part, the internal consistency of the questionnaire must be

determined to know the reliability of test items. The internal consistency of questioner

is a measure of how closely related a set of items are as a group. The coefficient of

alpha value was calculated by the following formula.

𝛼 =𝑘

𝑘−1(1 −

∑ 𝜎2𝑌𝑖

𝑘𝑖=1

𝜎2𝑋

)………………………… (4.1)

𝑌𝑖 = 𝑌1, 𝑌2, 𝑌3, , , , , 𝑌8 𝑖𝑠 𝑣𝑎𝑟𝑖𝑎𝑛𝑐𝑒 𝑜𝑓 components 𝑖,

𝑋𝑖=𝑋1, 𝑋2, 𝑋3, , , , , 𝑋26 the summation test score.

Where k is the sum of test items, 𝜎2𝑋 is the variance of the observed total test score,

and 𝜎2𝑌𝑖

is the variance of components 𝑖.

𝛼 =8

8 − 1(1 −

7.2

21.78)

𝛼 = 1.14 ∗ (1 − 0.33)

𝛼 = 0.76

The Cronbach's 𝛼 value was 0.76 and this value was between 0.8 > 𝛼 > 0.7 which

was acceptable internal consistency.

4.1. Demographic Information

This section deals with results and interpretation of questionnaires’ distributed for Bahir

Dar Textile Share Company employees. The qualifications of employees were also very

important elements for implementing lean at the organizational level. Based on the

research result, 69% of respondents had a first degree, 23% had a college diploma and

two employees had a 2nd-degree. From the above data, most of the respondents were

first-degree holders which will have great benefits for the company as well as for

research.

32

The employees' working experience compositions were 46% below 5year, 38% were

between 5-10 years and 7% were 10-15 years. The working experience of employees

had much better results for the performance of the company in a way that reducing

hazards, having better skills in operation, and in creating a multi-skilled operator. The

analysis result tells us 45% were below 5 years of experience and the rest 55% have

more than 5 years of experience which good composition of age for company success.

4.2. Descriptive Analysis

This section deals with the analysis and interpretation of collected data. As stated before

the analysis was descriptive and carried out using Microsoft Excel software. This

section deals with the employees’ response on eight guiding principles for

implementing lean at an organizational level. The output of the analysis consists of

data listed in Appendix 1:2. In the discussion part, the mean of each question was

broadly elaborated. The mean of each question was weighted from one up to five. These

are Very poor 1≤X≤1.8, Poor 1.8<X≤2.6, Average 2.6<X≤3.4, Good 3.4<X≤4.2,

and Very good 4.2<X≤5.

The value indicates respondents' attitudes on company practice related to each question.

The question with poor or very poor grade was lower company’s effectiveness

regarding lean implementation. This level of performance indicates the study

improvement area using lean principles. On the other hand, the average, good, and very

good performance had a positive impact on the future. The questionnaires were used

for making changes in the production system. Each guideline had its recommendation

for improving productivity and these questions were also used in future state mapping.

The respondent's results on each question were analyzed in detail in the next section.

4.2.1. Are there any activities for synchronizing customer need with the available

production rate?

The question was about know leaders' knowledge of Takt time. Therefore the mean

value of 2.42 is below moderate value and results show the BDTSC practice is not

enough on implementing Takt time. Takt time is the pace of the production system to

deliver the required product on time. The cycle time of each operation must be lowered

below Takt time. The company production rate is much more dependent on the daily

operator number. This indicates the daily production rate dependant on their daily

33

capacity rather than on Takt time. The production output is determined by forecasting

techniques.

Figure 4.1: Respondent information regarding lean practice.

4.2.2. Do your company producing finished goods to a supermarket/direct

shipment from which the customer pulls?

The main drawback of the company was the production of goods without customer

order which will cause overproduction. Overproduction was a source of wastage for

many resources like machines, capital, land, human resource, and so on. Currently, the

practice was producing finished goods to stock. In lean practice, the finished goods

were distributed in two ways. The first way is by using a supermarket pull system and

the other is direct shipment. The respondent result shows 2.03 which was below

moderate.

4.2.3. Are you applying continuous flow in the manufacturing system?

The main target of continuous flow in the manufacturing system is reducing inventory

to zero between two operations and making flow without interruption. A continuous

system is achieved by connecting operations in an automated system. It’s also possible

to create continuous flow is by applying FIFO lane and by letting one-piece flow in the

1 2 3 4 5 6 7 8

Mean 2.42 2.03 2.69 2.96 2.5 2.8 2.69 2.46

Median 2 2 3 3 2 3 2.5 2

Mode 2 1 3 3 2 3 2 2

SD 0.9 1 0.83 0.95 1.02 0.98 1.01 0.85

Minimum 1 1 1 1 1 1 1 1

Maximum 4 5 5 5 4 4 5 4

0

1

2

3

4

5

6

Questionnaire

34

production process. Therefore the continuous flow needs lots of creativity to improve

and the result is the most efficient production system. Some of the benefits gained from

continuous flow are reduced production lead time, zero inventories between each

operation, an easily manageable working environment, and lastly reduced production

cost because of the above reasons.

Employee’s attitudes toward continuous flow had a mean value of 2.69 which was an

average value. This figure indicates moderate performance but regarding the practice

on the floor, their activity towards continuous flow was low. This can be easily

determined by the amount of inventory, orientation of work stations, and NVA time.

There are about totally 7 transportation and with a travel length of 142 metre. Inventory

because of delays are 7050 pair of bed sheet. This entire hindrance can prove the

continuous flow was not properly used in the factory.

4.2.4. Does your company's production output determine by customers' demand

in a supermarket?

The 5th question is related to the supermarket pull system which is an information

exchange system for determining the production output. The continuous flow is

interrupted for many reasons. These are

Some operations might work at higher speeds above Takt time.

While others cannot produce one piece at a time or can produce only in batch.

Lastly, operations and suppliers may far away from the production site because

of this, transportation of goods in small quantities is not feasible.

Due to the above reasons, there must be a system that makes the production process

leaner. A supermarket pull system is an alternative next to the continuous system used

to control the flow of material in the production system. The main advantage of this

system is to reduce the effort required to forecast demand and control the production

system. Besides, the system was beneficial for companies to connect with customers so

that it’s easy to know the customer demand, Takt time, product type, and so on. With

the supermarket pull system, customer demand are send directly to suppliers and

production system to make a smooth flow of material and control the amount of work

in process.

35

Source (QI macros software., 2018)

Table 4.1: Value Added vs. Non-Value Added.

The garment shop was characterized by large work in process between operations and

no mechanism was used to control large work in process. The production lead time of

the company was 5.25 days while the value-adding time was 5.25% of lead time. The

main target in VSM was to eliminate NVA activity and reduce NVA time up to 5%.

Accumulations of inventories were the result of unbalanced cycle time between

operations, lack of a system that can reduce inventories, and lack of awareness on

wastage. Therefore this kind of problem needs good insight and a systematic way of

problem-solving.

In the BDTSC garment section, the practice to use supermarkets was almost zero

because the production system was controlled by the schedule from the production

control unit. This way of information exchange system was repetitive and time-

consuming and it needs a new way of the information exchange system. This indicates

the company practice regarding the supermarket pull system was below average value

and it needs some improvement. But the employee’s response toward the question

shows a moderate mean value of 2.96.

4.2.5. Do your company have a pacemaker process that used to schedule the rest

of the process?

The main target of this question is to know whether there was a pacemaker system in

the production system that was used to show of the pace for upstream operations. The

pacemaker process is influenced by different operating conditions. Here the pacemaker

process is applied on a continuous flow of work in process so that pace of production

system can be controlled. The trend inside the BDTSC garment shop was producing

maximum output with available capacity in each independent station without

considering the capacity of downstream operations. The supervisor tries to vary the

Minutes Typical Target

Value Added Time 232

Lead time 4414.3

Non-Value-Added Time 4182.3

Value Added % 5.25% 5% 95%

NVA % 94.75% 95% 5%

Value-added ratio 1:18 1:19 19:1

36

daily production amount by transferring employees from other operations on bottleneck

operations. Here employees identify bottleneck stations as sewing workstations which

were a good approach to meet daily customer demand. The respondent gives a mean

value of 2.5 which was below the average value.

4.2.6. Are there leveling the production mix for fulfilling different customer needs?

The concept behind this question is to know the practice regarding fulfilling different

customer need within the production system. Leveling the production mix is the process

of distributing different product types evenly overtime periods in a production flow. In

the current state value-stream, the product mixing was carried out only in bailing

operation. In bailing operation three types of bed sheets was pressed together to create

a variety of product for fulfilling different customer wants. Currently, the daily

production capacity was only one kind of product in a single manufacturing line. Due

to this production system will have to wait for three-shift works for the final bailing

operation. The waiting time for more than two days was one form of time waste. There

are many reasons for this to happen the first one was the production flow is arranged

for batch and flexibility in the batch system is cannot be attained. As a result, the

inventories and waiting time for different product variety was too large. The

respondent’s evaluation result regarding the questioner is about 2.8 which is a moderate

value representing activity in the unitizing section. On the contrary, the overall practice

to accommodate a variety of product inflow is very low.

4.2.7. Do your company use pitch increment of work?

The answer to this question was no because the production system was batch and it was

controlled by information sent once per day. The production control unit in the garment

section controls their manufacturing line pace was by using daily unit output. Two

operators in the sewing line were accountable to deliver 100 pairs of bed sheets per

shift. So at the end of the day, there was time-consuming work to count each output and

stocking temporary for bailing operation. Here there was uneven load distribution in

each work station for example operators on the sewing line has to produce 100 units

daily but operators on the bailing machine work two-three days per week. Unit

production was the only method available to regulate the daily production output.

Furthermore, the garment section production system is push-type, and controlling the

37

pace of batch production was a difficult task. The average value of 2.69 is too much

relative to practice on the floor and the current production needs some improvement.

4.2.8. Are there techniques for reducing change over time?

Change over time is machine downtime during product change from one product type

to another. The main use of reducing change over time and a lot size of the batch is to

respond quickly to the customer need. In return, it will reduce the inventory amount

and waiting time to be held on the shop floor. In the garment section, the change over

time was almost zero for all operations. The reason was machines are simple and

general-purpose besides most of the operations are manually done. Therefore the main

focus of the researcher was on reducing batch size instead of reducing set up time on

machines. On the other hand, the respondent’s response of 2.46 indicates poor

performance and needs some improvement.

4.3. Summary of Lean Manufacturing Practice for Garment production

The respondent's average mean value of 2.54 regarding the questions deviates a little

bit from the company's actual practice. This value indicates the company employees

had an awareness of lean manufacturing but the company practice in utilizing lean

manufacturing was almost poor. Based on my observation the company employees had

lower awareness in identifying wastes, ways of achieving a lean production system, and

understanding the benefits of lean production. The reasons will be many among them

lower consciousness on each question or keeping company image were a major one.

But the value 2.54 was between 1.8<X≤2.6 which indicates the poor performance of

the company on lean practice. The discreptive analysis result with poor grade shows

the needs of using lean manufacturing in the production system. Generally, the

interview questions, observation, and the questionaries’ results show that garment

production needs some improvements to maximize productivity.

4.4. Selected Product Family

Value stream mapping was carried out for the Garment section assigned to produce

bedsheet. The Section was producing Bed Sheeting in different sizes with a customer

order and for stock. At the time of study one of BDTSC customers, Amaga private

union order bedsheet type 160x250. Therefore for this study, the performance is

measured for the same product type.

38

5. VALUE STREAM MAPPING

5.1. The Current State Value Stream Map

The value stream is all activities inside the production site (value-adding and non-value-

adding) used to convert the raw material into finished goods. The value stream map

follows the value stream from the end customer back to a production process and

suppliers. Value stream mapping is the easiest way to show the reality of the production

system beyond employees’ traditional approaches of mapping. VSM will help to see

the invisible, which are things many people don’t see or others willing not to see. This

in return will help to see problems from their root causes and improve them to get

ultimate results. The VSM is the living document and anyone who wants to make

corrections can update it daily. In the current state VSM, it’s possible to detect easily

the following waste type. These are bottleneck operation, unnecessary information

flow, and the non-value adding activities.

No. Process Inventory

(pair) VA/

NVA

CT/

VA

(min)

NVA

(min) Crew CO Uptime

Waste

(kg) Available

WIP1 952 pair NVA 210

1 Quality

Inspection VA

4.02 2 0 100% 12.6 77%

WIP2 208 pair NVA 42.3 2

2 Cutting VA 222.69 6 0 91.3% 0 77%

WIP3 1193 pair NVA 420

3 Sewing VA 0.18 9 0 100% 0.97 77%

WIP4 0 NVA 0

4 Folding VA 0.287 9 0 100% 0 77%

WIP5 100 pair NVA 150

5 Packing VA 0.14 18 0 100% 0 77%

WIP6 952 pair NVA 1680

6 Unitizing VA 4 .67 3 0 100% 0 22%

WIP7 3645 pair NVA 1680 2

Table 5.1: Value stream mapping automatic data entry system

The sketching process of the current state map was carried out by looking at every

process in the door to door flow. To assist the sketching process software known as QI

macros were used. The software holds important tools for sketching current and future

state and also analytical tools to easily understand the performance of the production

system. The sketching process of the value stream was supported by the automatic data

39

entry method in the table. Inside the table the operation, inventory amount, value-

adding and NVA time, number of operators, the change over time, uptime, waste, and

availability are all included for each value-adding operation.

5.1.1. Process

The process represents material flow in operations and temporary storage areas. The

operations are value-adding in the value stream and are denoted by box shape and inside

it, there was an operator’s number. There were six value-adding operations. The delay

of fabrics was represented in VSM by using a triangle icon. From the value stream

perspective, the inventory between two operations was the NVA activity. The amount

of inventory is known by counting each output from the machine. Likewise, the time

spent as inventory is measured by the stopwatch. The temporary storage wastes time in

the form of waiting time.

5.1.2. Process Box

The process box consists of the following information; the number of operators, the

cycle time, changeover time, uptime (showing the reliability of your equipment), and

availability of equipment.

Cycle Time; Cycle time is the time taken for one item to complete

one operation. CT is the time elapse between the first completed

item and the next completed item. The cycle time in each

operation is the determining factor of whether to meet the Takt

time or not. The cycle time was recorded with a stopwatch and the

measurement process was iterated several times (usually 10 times)

for the specific operation and lastly, the average value was taken and documented in-

process box. The measurements were actual data recorded live in operation. The cycle

time data is found in Appendix 2:4.

Changeover Time (CO); CO is the time needed during the transition from one product

type to another. CO is a kind of waste for the production system and it needs to reduce

it to zero for a continuous production system. The change over time needs great

attention when it is too long and this kind of situation is an opportunity to make

improvements. On the contrary, when CO time is too small there is no need of including

it in improvement activity. In the case of the garment section, all of the operations have

CT = 15 sec

Crew = 1

CO = 10 min

Uptime = 100%

Waste = 5kg

Availability =

76%

40

very small changes over time nearly to zero. The reason was all the machines used in

the garment section can accommodate a variety of fabrics type without making any kind

of change to the system.

Uptime (U/T); Uptime is the percentage of time in which equipment is available when

needed for a particular task. The common reasons for equipment’s unavailability are

downtime due to equipment failure or maintenance activities and losing electric power

source. The uptime analysis is known by recording the time spent when the machine

fails and by dividing it by total available time. Inside the garment section, most of the

operations were manually performed and the rest of them uses simple machinery with

higher reliability due to this up time is 100%. Meanwhile in operations like cutting there

was downtime due to frequent straight knife cutting machine failure which reduces

availability to 91.3%.

Availability; Availability is the percentage of time in which a certain type of machine

is shared for two or more value streams. The purpose of this data is to show equipment

sharing and the impact on the value stream. In the value stream, the bailing machine is

shared for unitizing of bedsheet (160x250 and 156x210), Abay Shema, Abujedid, and

Dyed Poplin.

Figure 5.1: Availability for bailing machine

The pie chart given in figure 5.1 shows a shared percent of the time for the bailing

machine. From the total available time, 44.6% of the time wastes because of the scarcity

22

21.5

1.5

8.8

1.4

44.6

Bed Sheet 160x 250

Abujeded

Bed Sheet 156x 210

Abay Shema

Dayd Popllin

Not Scheduled

41

of resources, 22% of the time used for bedsheet type 160x250, and 21.5% of the time

is for 156x210 bedsheet and so on.

On the other hand, availability for operations like inspection, spreading, and sewing

was nearly the same. The reason was due to the same work in the process flow in each

process i.e. (160x250 and 156x210). Therefore the availability of bed sheet type

160x250 was 77% in operations like inspection, spreading, and sewing. The remaining

23% of the time was shared for 156x210 bedsheet type.

Waste; wastes in the value stream were in the form of cutting strips and rags from

inspection and sewing machines respectively. These wastes are because of lower fabric

quality like yarn defect, painting defect, or joint made. The amount of wastes is known

by measuring weight in kilograms.

5.1.3. Lead Time

Value-added times or cycle time is the time elapsed between one completed item and

the next completed item. While the non-value-added time is the time spend as inventory

in between each operation. The summation of time given in each operation gives the

lead time used to complete one item. The zigzag line in the current state VSM represents

the lead time where the upper part is the non-value-added time and the lower one is

value adding time. The value-adding time is the processing time for one product while.

5.1.4. Travel Distance

The travel distance refers to the travel length of the product, operator, or both within

the production site. In this study, the travel distance was measured by following the

product path along each process. Therefore the product path from the initial storage

area to the final shipment was sketched on the layout diagram.

The physical measurement of distance can be carried out in three ways; these are the

measuring wheel, pedometer, and the counting steps. The first one is the most accurate

while the second one uses a pedometer to count footsteps and feet. The last one is the

most common one to measure the travel distance and Carried out by simply counting

the footsteps and finally multiplying it by 0.762 m. For this study, the counting step

was used. The travel distance was represented in the value stream below lead time data.

42

5.1.5. Capturing the Communication Flow

Communication is any kind of information flow in value stream mapping within the

production system or to outside customers and suppliers. Communication problems are

one of the hindrances for an effective production system. Smooth flow of produced

items from suppliers through the production system and customer is achieved by

enhancing the flow of information.

The flow of information in the current state value stream starts

at the customer side and goes back to the production control

unit and finally to the suppliers. The customers were found on

the right side of the value stream map and represented by the

factory icon. The customer’s order for products was carried out

in person or sent through electronic fax or at the purchasing and

sales department. On the reverse side of the control point, the

supplier factory icon was found. Here the supplier was the dyeing section in BDTSC

which supplies painted fabrics in different colors. The information exchange system

between suppliers and the garment section was using manual information flow.

In between the supplier and customer factory icon, there was a control point icon. The

unit had the mandate to collect, organize and document the information from a different

source. Therefore at the end of the day from different workstations quantity of fabric

received, work in process in each operation, finished goods amount, and wastes were

sent to the control unit and documented. Besides, this point had a function to schedule,

control, and instruct work order inside the production compound. The production

control will answer in advance questions like what, when, how, and where to produce

items on the production floor.

The flow of information exchanges was manual and electronic represented by straight

and jagged lines respectively. For activities that were disruptive to the value stream

were identified by go see the icon. This icon was represented by eyeglasses in the value

stream. Disruptive activities were activities carried out beyond normal scheduling due

to some adjustments.

74,000 Pair

160 x250

Bundle = 70 pair

2 Shift

Customer

43

Figure 5.2; Documenting manual (verbal) and electronic communication

Instructions

© 2017 KnowWare

Quality

Inspection208 Cutting 1193 Sewing 0 Folding 100

Dyeing

Section

Packing 952 Bailing 3645

Production

Control

FIFO2 6 9 9 18 3

`Production Controlling

& Daily Work Order Shipping

Schedule

Shipping

Quality Reports

Fax

Purchase Order

1 X

daily

Daily Order5-Day

Forcast

Order Change

Amaga

74,000 Pair

160 x250

Unit =70

pair2 Shift

952

44

5.1.6. Capturing Material Flow

The flow of material inside the factory begins when the dyeing section supplies fabrics

to inspection operations. The input resources from suppliers to the inspection site were

transported by manually pulled trailers. An icon with a person pulling a trailer

represents how fabrics were transported to the inspection site. Inside the garment

section, the shop manager schedules the production process. The push arrows between

each operation in current state VSM represent the push production system which was

characterized by each independent workstation producing an output without

considering the successor work cell. The flow of material ends when finished goods

were distributed to customers. The pull icon was directed upward to customers and the

truck icon near the pull icon was the delivery icon used to represent how finished goods

were delivered to the customer.

At The time of data collection one of BDTSC customer Amaga private union order

bedsheet type 160x250 with a quantity of 74,000 pairs. By using the company schedule

dyeing section supplies a bedsheet type of 160x250 with different colors to the Garment

section.

Quality Inspection

The first process in Garment Section was the quality inspection of fabrics with skilled

labor. The VA operations are represented by box shape and the CT for this operation is

12 sec per pair. As the fabrics arrive the section operators immediately engage the

fabrics with the machine and start to observe different quality defects. When the

operator observes a defective area he immediately stops the machine and marks parts

of the defective area. Meanwhile, at the output side, the second operator cut out

defective fabrics and then make a roll-on a plastic tube for continuous operation. The

inspection processes make some downtime for making a standard roll size of 122 meter.

Generally, the operation needs two operators for machine control and two operators for

transporting of work in process.

When the roles were accumulated at the output side of the inspection machine (usually

10 roles) labor transport them by loading them on the truck. Each workstation had a

temporary storage area so when there were rolled fabrics they stored temporarily. But

when there was a customer order the fabrics were immediately transported to the

45

spreading section. In this case, the customer order was much more important than

making to stock.

Cutting Operation

Next to inspection, the second VA operation was cutting operation. As indicated earlier

in the value stream map the work station needs 6 workers and aiming to spread and

finally cut fabrics with a cycle time of 11.2 sec. In this process, each role of fabric was

loaded on the spreader and spread on the table making multiple layers of fabrics. After

spreading operation the empty plastic tube was discarded and replaced with a new one.

Finally when the spreading process is over the next process will be cutting with the size

of the pillowcase and bedsheets. The uptime of cutting operation is about 91.3%. The

spreading process currently produces two times per shift and can produce 1193 pairs of

bed sheets.

Figure 5.3: Inventory three

The spreading operation produces cut fabrics two times per shift. These cut components

are counted and bundled with units having ten pieces. The cut bundle was then sent to

a temporary storage area for next day use. The waiting time for inventory three was

around 420 min.

Sewing Work Station

The third VA operation was sewing and it was composed of stitching and sewing

activities on pillowcases and bedsheets respectively. The sewing operation was carried

out with a sewing machine and had a cycle time of 97 sec per pair. In addition, the

46

stitching machine was characterized by its waste as a cutting strip and weighs around

6.7 kg per shift.

Figure 5.4: Sewing work station with inventory four

The sewing, folding, and packing operation forms one workstation and they need two

operators. First fabrics were transported to the working area manually. Then two

operators take their position by closely seating with each other and then when the

sewing operation end for one piece the next operator starts to fold. This way the

production process goes in continuous flow and uses first in first out lane (FIFO). The

first two operations have nearly the same cycle time 94 sec and 155sec in their

respective order. After folding operation, the continuous flow was interrupted and

inventory was accumulated. The waiting time for inventory four was around one and a

half hours.

Figure 5.5: Inventory five

47

The fifth operation was packed with a polybag and takes a cycle time of 152 sec. when

the folding operation was completed two operators collaborate for packing operation.

This way one hundred pair of bedsheets was produced and finally transported to a

temporary storage area (inventory five). the daily production amount was around 952

pairs per shift.

Bailing Operation

The sixth VA operation was the bailing operation used for packing each piece for final

shipment. In this operation, seventy pairs of bed sheets with different colors were

arranged in one unit and pressed with a bailing machine. The bailing operation needs

three operators for pressing and an additional two operators for transporting work in

the process a cycle time was 4 sec per pair. Then materials were transported to a

temporary storage area (inventory six) and then counted. Finally, finished goods were

stored in the stock for two days and shipped to customers.

Figure 5.6: Inventory six

Generally, as stated earlier the company production is towards batch. BDTSC produce

goods directly for customer and when customer demand is off it produce for stock. The

main characteristics of the production system in the garment section looks like large

work in process, pushing work in process to finished good, group of machines

performing a similar function, the long travel distance between each process,

unnecessary information exchange between production control and operators, long lead

time for processing compared to shortest cycle time. The current state VSM was

sketched in Figure 5.7. For more information about value stream mapping icons it

possible to see Appendix-3:1.

48

Figure 5.7: Current state value stream map for Garment Section

Instructions

© 2017 KnowWare

CT 232 4.02 222.69 0.18 0.287 0.14 4.67

Crew 2 6 9 9 18 3

CO 0 0 0 0 0 0 0

Uptime 100% 91% 100 100 100 100

Waste 12.6 Kg 0% 0.97Kg 0 0 0

Seconds 77 77 77 77 77 22

Total

NVA 4182 210 42.3 420 0 150 1680 1680

VA 232 4.02 222.69 0.18 0.287 0.14 4.67

TotalDistanc

e 142 10 38 28 16 50

Quality

Inspection208 Cutting 1193 Sewing 0 Folding 100

Dyeing

Section

Packing 952 Bailing 3645

Production

Control

FIFO2 6 9 9 18 3

`Production Controlling

& Daily Work Order Shipping

Schedule

Shipping

Quality Reports

Fax

Purchase Order

1 X

daily

Daily Order5-Day

Forcast

Order Change

Amaga

74,000 Pair

160 x250

Unit =70

pair2 Shift

952

49

5.2. Creating the Future State Value Stream Map

The current state value stream mapping is the standing point for making a future state

value stream map. The main activities on future state VSM were identifying wastes,

eliminating those wastes, and improving overall production activities. Current state

VSM is the beginning to identify non-value adding activities, system bottleneck, and

so on. The future state VSM is a systematic application of lean concepts like Takt time,

kanban information exchanging system, smooth flow of material from suppliers to a

customer, continuous and one-piece flow work in process, supermarket inventory

control system, change-over-time reduction, a cellular arrangement of operation,

automatic defect-free system (autonomous), and total productive maintenance to get

system improvement.

5.2.1. Icon Related with the Future State VSM

For future state VSM, there were additional icons to effectively represent each

improvement made. These icons were listed below. The future state VSM is a blueprint

for improved VSM. However, when things go wrong it’s possible to make a change on

future state VSM and can also update improvements regularly.

Kaizen Burst Icon;

The VSM was conducted by forming a team and brainstorming to suggest a solution

for the weak part of the value stream. In doing so, any improvement area was marked

with kaizen burst to show kind of change. Therefore in a brainstorming session with a

kaizen burst icon every weak spot of the current state value

stream was marked and inside it a weakness of particular

activity and any possible solutions were documented.

Kaizen

50

Figure 5.8: Current state value stream map with kaizen Burst icon.

Instructions

© 2017 KnowWare

CT 232 4.02 222.69 0.18 0.287 0.14 4.67

Crew 2 6 9 9 18 3

CO 0 0 0 0 0 0 0

Uptime 100% 91% 100 100 100 100

Waste 12.6 Kg 0% 0.97Kg 0 0 0

Seconds 77 77 77 77 77 22

Total

NVA ### 210 42.3 420 0 150 1680 1680 NVA= 4182min

VA ### 4.02 222.69 0.18 0.287 0.14 4.67 VA= 232 min

Total

Distan ### 10 38 28 16 50 Distance=142m

Quality

Inspection208

Cutting1193

Sewing 0 Folding 100

CustomeDyeing

Section

Packing952 Bailing

3645

Production

Control

FIFO2 6 9 9 18 3

Fax

Purchase

Order

Shipping

Super market

Required to control

inventory amount

No need of

Forecasting supplies

1 X

daily

FIFO FIFO FIFO

Merge operations with

the same cycle time

Too much

waiting time

Too many

Inventory

Excess controlling &

scheduling activity

No need of shipping

schedule

Too much

waiting time

Supermarket Required to

connect with customer

Too many

Inventory,

Too much

waiting time

Too many

Inventory

long distance

transportation

FIFO

long distance

transportation

Merge operations

952

Amaga

51

The Supermarket icon

The Supermarket icon was related to the pull flow in which customer requirements were

necessary to continue the production. In lean practice, the pull flow needs to be

continuous but when the flow is disrupted due to the nature of operation the inventory

needs to be controlled. The supermarket pull is a system used to control the production

amount of supplier, operation, and output of the production system. Supermarket pull

system uses card like information exchange system known as kanban. The card is used

as a signal when the amount of inventory is depleted below a certain level in the

supermarket and in return to make an order of production (replenishment signal). The

production team had a mandate to control how to use this kanban system.

Withdrawal kanban icon

Facilitate the flow of work in process in the downstream operations. This card is

attached with work in process and passes in each operation up to the finishing line and

when the product is sent to other processes the withdrawal kanban sends back to the

supermarket to replenish the previous one.

Production kanban icon

The production kanban icon is the information required to continue production activity

in the supplying operation. The production order for successive operations is obtained

from the kanban box. The production kanban can go further to the upstream operations

and even outside of production to the suppliers for the smooth flow of material. The

information exchange system between the suppliers and the production system is

carried out using kanban posts.

Signal kanbans icon

The signal kanbans icon represents replenishment signals for the supplying process to

have more bins or boxes. Signal kanban is represented by an inverted triangle box.

First in first out (FIFO)

The FIFO system materials are flowing in each decoupled operation without the use of

a kanban system and can substitute the supermarket pull system. This is carried out by

using bins that can hold a small amount of work in process and by letting to pass in

52

each process in their respective order. The flow of work in process is stopped when the

finished goods are not further required by customers.

5.2.2. Communication Flow in a future state VSM

The flow of information begins when customers purchase goods from the supermarket.

in return sells representative daily count empty spaces on shelves and sent the order for

supplies electronically by using electronic data interchange) to a production control

unit. Here the need for a product was sent when the total amount of empty spaces were

reached one kanban. One kanban is equivalent to 70 pairs of bedsheets. Then the

production control unit schedule to produce products with available facilities as per

customer need. The production order was then sent immediately to each section

electronically and the sections need to produce with an improved system according to

customer needs.

The flow of material was assisted by kanban cards and this card initiates the flow of

work in process in the garment section. Inside the garment section, the shop manager

controls the production process by using information sent from the inspection site, work

cell 2, and shipping section. At the inspection site by using withdrawal kanban the

amount of fabric received was sent electronically to the control unit. The pace of overall

operation and the amount of produced items were controlled by pitch increment of work

at work cell 2. The amount of produced and shipped items are controlled by information

sent from the shipping site. The information exchange system listed above was

vertically between the control unit and each operation. The vertical information

exchange system must be assisted by a local area networking system. On the other hand,

there is also a lateral information exchange system between operations. This way of

information exchange system reduces unnecessary information flow and was carried

out by using kanban cards.

5.2.3. Synchronizing Customer Need with the Available Production Rate

The process of determining production output is a crucial thing for companies' success

to eliminate the overproduction and problem of stock out. There are many ways for

determining production output among them forecasting techniques and producing with

customer orders are commonly used. The former way uses a large amount of customer

requirement data collected previously and using that it predicts the future demand.

Although it can predict future demand it has a problem related to deviation from actual

53

demand. The second way uses recent and current customer demand, and by using that

it tries to know the daily production amount. In this way, the company's available time

is divided by the total customer demand with the same period which gives Takt time.

Takt time is the pace of a production system to deliver the required product on time.

Takt time is calculated by the following formula;

Takt time =𝑛𝑒𝑡 𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 𝑡𝑖𝑚𝑒 𝑓𝑜𝑟 𝑝𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛

𝑐𝑢𝑠𝑡𝑜𝑚𝑒𝑟 𝑑𝑒𝑚𝑎𝑛𝑑 𝑓𝑜𝑟 𝑡ℎ𝑒 𝑠𝑎𝑚𝑒 𝑡𝑖𝑚𝑒 𝑝𝑒𝑟𝑖𝑜𝑑….………….(5.1)

The product delivery date determines production capacity. The trend for determining

production output in the Garment section was forecasting techniques. In addition, the

production capacity of the company was depending on the current number of employees

rather than customer demand. Therefore the Takt time was calculated by using the

current capacity of the garment section and currently, they produce 952 pairs of bed

sheets per shift.

Where;

The net available time; time available for value stream excluding lunch,

meeting, and break time. From 8 hours of working time, the employees use 40

minutes for lunch, 10 min for rest, and 10 min for daily meetings. Thus

available time in BDTSC for each shift is around 420 min.

Working hour per

shift

Non-processing time Available

time Lunchtime Cleaning time Daily meeting

480 min 35 min 15 min 10 min 420 min

Customer demand for the same period; was the amount or quantity of produced

item needed within a specified period.

Customer = Amaga private union

Item type Quantity Delivery date Available time

Bed sheet 160X250 74,000 pair 40 day 420 min

Takt time =420 𝑚𝑖𝑛

952 𝑝𝑐𝑠 𝑠ℎ𝑖𝑓𝑡⁄

= 0.44 𝑚𝑖𝑛 ≈ 27 𝑠𝑒𝑐

54

The meaning of this result is the production system must produce one bedsheet every

27 sec. In other words, every operation within the production system must operate with

a cycle time of 27 seconds or below in order to meet the delivery date. The Takt time

was the time for one pair of bedsheets which excludes downtime due to maintenance,

setup time, inspection time, and reworking time. Therefore to meet the Takt time, the

production system must lower the cycle time of each operation below Takt time.

5.2.4. Should BDTSC Produce Bedsheets to a Finished Goods Supermarket or

Directly to Shipping?

BDTSC produces bed sheets in a different size but at the time of the study, the section

produces only 160x250 and 156x210 type. The first order 156x210 was from GINAD

and the second-order 160x250 was from Amaga private union. The orders were coming

irregularly in batch from wholesalers this is the cause for stoke out and over-production

problems in manufacturing faculties. This kind of situation was a challenge for a lean

production system. To prevent such kind of irregularity the company must use the

supermarket. The supermarket system eliminates overproduction and allows us to

deliver goods at the time of need. The garment section produces a bedsheet in a bundle

containing 70 pair and unit one bundle was enough to make a kanban order. The demand

from the supermarket was transmitted to the production site with the help of electronic

data interchange daily.

Figure 5.9: Direct Shipment of finished goods to customers.

Sales Rep Customer

Supermark

et 8 hrs

Sales

Order

BDTSC

Control Unit

Garment

Section

Shipping

Fax

Amaga

Purchase

Order

74,000 Pair

160 x250

Unit =70 pair

2 Shift

55

On the other hand for the shipment of finished goods, it’s better to use direct shipping.

The finished goods from bailing operations were directly transported with truck at the

shipment area and loaded with finished goods and starts its journey to distribute them

based on previously sent orders. Here inventory six was eliminated.

5.2.5. Continuous Flow (One Piece Flow)

As the name indicates continuous flow is aiming to create a continuous flow of work in

the process without interruption. The cutting operation was one of the bottlenecks for

creating a continuous flow. The operation in the value stream was carried out two times

per shift and the BDTSC production system prefers to produce in large quantity. The

main reason behind this selection was that the system will have the advantage of

reducing cost per piece when producing in large quantities. Besides, the production

system can also save a tremendous duration of time by lowering frequent setup time.

On the contrary lean manufacturing, the continuous system will have the following

good opportunities; producing a variety of products at a time, reducing inventory size,

and reducing the lead time. Therefore due to the above reasons, it’s better to use a

continuous system to give quick responses to customer needs.

The continuous system between operations is achieved by balanced cycle time, one-

piece flow, and close arrangement of the work cell. The cycle time of quality inspection

and cutting operations were nearly the same. This was a good opportunity to form a

one-piece flow between two operations. Therefore operations need to be close to each

other for continuous flow. This will cause the transfer of cutting operation working

place from the previous place to the inspection room. Then the roll of fabrics was easily

transported between each operation using the first in first out lane. Here inventory two

eliminated

In the same way, the next three operations sewing, folding, and packing operations can

also make one-piece flow. This connection was a good opportunity to eliminate the

waiting time of inventory for packing operations. The remaining one last connection

was between the packing and bailing machine. The bailing operation had a relatively

lower cycle time compared to the upstream three operations. A relatively lower cycle

time of upstream operations will cause only starvation on that particular operation. This

was enough reason to connect the last operation with upstream operations using

continuous flow. On the other hand, the two operations need to be close to each other.

56

Therefore the easiest way to transfer was shifting the bailing operation near to packing

operation. Here the good result was inventory five with a waiting time of two days is

eliminated from the value stream. Besides the travel distance, 54meter is eliminated

between each operation. However, the flow of bin in continuous flow might get stacked

if the flow was not controlled. The flow of material beyond sewing operation can easily

be controlled by using FIFO lane.

Figure 5.10: Work cell formed by using first in first out lane

So let’s combine the above improvements and we have two work stations. The first

work cell was formed between inspection and cutting operation and the connection

between operations was first in first out lane. Whereas the second work cell was formed

between sewing, folding, packing, and bailing operations. These workstations were

represented in the future state value stream with the following icon. The main purpose

of continuous flow was to make cellular arrangements of operations to make zero

inventory between operations. primar

Line-Balancing

In the line balancing chart, it’s possible to distribute the load evenly by listing the cycle

time of each operation. This in return help to make a continuous flow of work in the

process. In the line balancing chart, Takt time was used as a range for cycle time to

determine whether to meet the delivery date or not. Figure 5.11 shows the cycle time in

the current state value stream was not within Takt time.

In operations like sewing, folding, and packing cycle time exceeded the Takt time.

Therefore the goal of this balancing chart was to reduce each cycle time below Takt

time and to create a balance between cycle times for continuous flow of material. The

continuous flow of material was achieved by hiring employees, merging activities, load

sharing, changing machine number or capacity and when it worse more than this it’s

possible to use over time and outsourcing work. The total time for sewing, folding, and

Work Cell 1 Work Cell 2

57

Figure 5.11: Garment section current cycle times of operation

packing was about 404 seconds and dividing this time by Takt time (27 sec) gives

around 15 people. This indicates 15 employees was enough to meet Takt time. When

15 operators were divided into three operations (cutting, folding, and packing) gives

five sewing machines or process lines were needed in parallel. This way the cycle time

was reduced to 19.4 sec, 31 sec, and 30 .4 sec in their respective order. Then the next

task will be load sharing to create a smooth flow of material.

Figure 5.12 illustrates the load sharing between each operation. The folding operation

had the highest cycle time and this time can be reduced below Takt time by sharing

some work with the neighboring operation. At the same time, the packing operation can

share the load to bailing operations. Besides, the first two operations have the same

cycle time but compared to the next four operations the cycle time was low. This kind

of condition was favorable to machine operations to create an allowance for set up time.

On the contrary, the large cycle time difference indicates the necessity of a supermarket

pull system for cutting operations to control the flow. Generally, the Takt time and

requirements for production 952 pairs of bed sheets per shift in continuous flow were

summarised in table 5.2.

12.2 11.2

97

155 152

4

0

20

40

60

80

100

120

140

160

180

Quality

Inspection

Cutting Sewing Folding Packing Unitizing

Cycl

e T

ime

(sec

)

Takt Time 27 sec

58

Figure 5.12: Cycle time after load sharing

So far the flow of material was improved from push to customer pull system and each

operation was close to each other for continuous flow. The next task will be eliminating

waste full activities in each operation by using kaizen. This will reduce the cycle time

of each operation below Takt time. If the use of kaizen fails it’s possible to use overtime

or transferring labor from other areas.

Time available Total Time

Breaks

(min)

Clean-up

(min)

Minutes

Available

Days/year 40

Hours/day 8 45 15 420

Takt Time Product 1 Total

Annual demand 38080 210392

Daily demand 952 952

Percent of total sales 100% 100%

Takt time (minutes per unit) 0.4 0.4

Cycle time/Operator 0.4 0.4

Number of Operators 1.0 1.0

Source (QI macros software., 2018)

Table 5.2: Takt time data

Achieved performance through the Continuous Flow

Here we can observe there was a reduction in an employee number from current to

future state value stream. In the current state value stream, 18 employees were utilized

in sewing workcell2 but in the future state value stream, this number was reduced to

15. This shows the manpower utilization was increased by 25%.

12.2 11.2

19.4

2520.4

4

6

10

0

5

10

15

20

25

30

Quality

Inspection

Cutting Sewing Folding Packing Unitizing

Cycl

e T

ime

(sec

)

Takt Time 27 sec

59

𝑀𝑎𝑛 𝑝𝑜𝑤𝑒𝑟 𝑟𝑒𝑑𝑢𝑐𝑡𝑖𝑜𝑛 =𝑛𝑜 𝑜𝑓 𝑤𝑜𝑟𝑘𝑒𝑟 𝑖𝑛 𝐹𝑆 − 𝑛𝑜 𝑜𝑓 𝑤𝑜𝑟𝑘𝑒𝑟 𝑖𝑛 𝐶𝑆

𝑛𝑜 𝑜𝑓 𝑤𝑜𝑟𝑘𝑒𝑟 𝑖𝑛 × 100

=29 − 26

29× 100

𝑇𝑜𝑡𝑎𝑙 𝑚𝑎𝑛 𝑝𝑜𝑤𝑒𝑟 𝑟𝑒𝑑𝑢𝑐𝑡𝑖𝑜𝑛 = 10.34%

𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑒 =1 𝑝𝑎𝑖𝑟

27 𝑠𝑒𝑐⁄ = 2.22 𝑝𝑎𝑖𝑟 𝑚𝑖𝑛⁄ Since there are 5

manufacturing lines.

𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑟𝑎𝑡𝑒 𝑝𝑒𝑟 𝑙𝑖𝑛𝑒 =2.22 𝑝𝑎𝑖𝑟/𝑚𝑖𝑛

5 𝑙𝑖𝑛𝑒⁄ = 0.44𝑝𝑎𝑖𝑟/𝑚𝑖𝑛/𝑙𝑖𝑛𝑒

𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑟𝑎𝑡𝑒 8 𝑚𝑎𝑛𝑓 𝑙𝑖𝑛𝑒 = 0.44 𝑝𝑎𝑖𝑟/ min/ line × 6 𝑙𝑖𝑛𝑒 = 2.64 𝑝𝑎𝑖𝑟/𝑚𝑖𝑛

𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑜/𝑝 𝑝𝑒𝑟 𝑠ℎ𝑖𝑓𝑡 = 2.64𝑝𝑎𝑖𝑟

𝑚𝑖𝑛× 420 𝑚𝑖𝑛 = 1108 𝑝𝑎𝑖𝑟

In the current state value stream with 5 manufacturing lines, the production rate was

2.22 pairs per minute. On the contrary, in the future state value stream 26 operator’s

forms, 6 manufacturing line and the production rate is 2.64 pair per minute. When we

multiply the above outputs with a daily available time of 420 minutes gives 933 pair

and 1108 pair respectively in two states. The production output was increased by 60 %.

𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑜/𝑝 =𝑂/𝑝 𝑖𝑛 𝑓𝑢𝑡𝑢𝑟𝑒 𝑠𝑡𝑎𝑡𝑒 − 𝑂/𝑝 𝑐𝑢𝑟𝑟𝑒𝑛𝑡 𝑠𝑡𝑎𝑡𝑒

𝑂/𝑝 𝑐𝑢𝑟𝑟𝑒𝑛𝑡 𝑠𝑡𝑎𝑡𝑒 × 100

𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑜/𝑝 =1108 − 952

952× 100

𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑜𝑢𝑡𝑝𝑢𝑡 = 16.4%

Likewise, an increase in output will have its effect on reducing the time. Based on future

state value stream if 1108 pair was produced in one shift then the current state

production output of 952 pair need only 360.9 minutes. Therefore the time utilization

was increased by 36.2 %. All the improvements were summarized in figure 5.13.

𝑇𝑖𝑚𝑒 𝑈𝑡𝑖𝑙𝑖𝑧𝑎𝑡𝑖𝑜𝑛

=𝑇𝑖𝑚𝑒 𝑢𝑠𝑒𝑑 𝑖𝑛 𝑓𝑢𝑡𝑢𝑟𝑒 𝑠𝑡𝑎𝑡𝑒 − 𝑇𝑖𝑚𝑒 𝑢𝑠𝑒𝑑 𝑖𝑛 𝑐𝑢𝑟𝑟𝑒𝑛𝑡 𝑠𝑡𝑎𝑡𝑒

𝑇𝑖𝑚𝑒 𝑢𝑠𝑒𝑑 𝑐𝑢𝑟𝑟𝑒𝑛𝑡 𝑠𝑡𝑎𝑡𝑒 × 100

𝑇𝑖𝑚𝑒 𝑈𝑡𝑖𝑙𝑖𝑧𝑎𝑡𝑖𝑜𝑛 =360 − 420

420× 100

𝑇𝑖𝑚𝑒 𝑈𝑡𝑖𝑙𝑖𝑧𝑎𝑡𝑖𝑜𝑛 = 14.07%

60

Figure 5.13: The effect of continuous system in manpower utilization, time utilization,

and production output.

5.2.6. Supermarket Pull System

Supermarket Pull System for Cutting Operation

The supermarket pull system was a means of connecting two operations or workstation

that cannot form a continuous flow. The easiest way to solve the continuity problem

was by producing only when the next operation was ready for production. The cutting

operation was one of the hindrances for making continuous flow of work in process.

The obvious reason behind the continuity problem was cutting operation produce only

in large quantities. The problem of this kind had a solution by using a controlled

inventory system between the two operations. This way of controlling inventory using

kanban cards and supermarkets for continuous flow of work in process was known as

the supermarket pull system.

The process of pulling starts with determining customers in our case the work cell two

was the customer. The sewing operation currently needs fabrics used for 952 pairs of

bedsheets in three designs per shift. The fabrics for bed sheets were then delivered using

small containers to make the change over frequently and conveniently. Therefore a

plastic bin that can hold 10 pair of bed sheets was required. This material handling bin

had a withdrawal kanban card in it and was used to initiate the flow of material in the

downstream process. The sewing operation begins by withdrawing fabrics from a

Man Power

Reduction

Production

OutputTime utilization

Room for Improvement 90% 84% 85.30%

Achieved Performance 10.30% 16% 14.70%

Man Power

Reduction ,

10.30%

Production

Output, 16%Time utilization,

14.70%

90%84% 85.30%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

61

supermarket using a withdrawal kanban. As the sewing operation goes the fabrics in

the first bin were completed and sent to folding operation. This causes the

replenishment of fabrics using a withdrawal card and the operator immediately goes

back to the supermarket and withdraw a new one.

Table 5.3: Withdrawal kanban.

Table 5.4: Production-ordering kanban

Likewise, on the supermarket shelf, withdrawal cards were collected on empty spaces

and their copies were sent in one card back to cutting operation in the form of

production ordering kanban. The withdrawal amount of fabrics was determined by

counting space on the supermarket shelf and each box on the shelf had a withdrawal

card. There are five shelves used for each production line in the downstream operation.

Therefore 25 kanban cards were enough to start the production process of cutting

operation. The cutting operation needs only 12 rolls X 122 meter which is around 1500

meters of fabrics with the allowance. This amount of fabric does not include an

allowance for waste and was sheared on a spreader for the pillowcase and bedsheets.

The outputs were 250 pairs of bed sheets in one round and there were four rounds per

shift for cutting operation. The next main activity was counting and grouping sheared

fabrics and finally place them in the shelf’s box. In each box, only ten pairs (with two

color types) of bedsheets and with their kanban are all together placed.

Store

Shelf No Item Back No.

Preceding

Process

Item No.

Item Name

Type Subsequent

Process

Box Capacity Box Type Issued No.

Store

Shelf No Item Back No.

Preceding Process

Item No. `

Item Name

Type

62

Generally, the production kanban initiates the production of goods while the withdrawal

kanban initiates movements of work in process. After all these changes there was no

need of using production scheduling to control inventory beyond cutting operation.

Moreover beyond the kanban system the production control unit can use signal kanban.

The signal kanban is used as a reminder for cutting operations to prevent the stockout

problem. Therefore when the inventory amount was below some level in the

supermarket the signal kanban was sent to cutting operation and this in return triggers

the production of fabrics.

Table 5.5: Signal Kanban

Although the supermarket had a lot of benefits it had also some drawbacks that make it

challenging for us. One of the challenges was frequent change over time but in the case

of cutting operation, it was low compare to other processes. So far inventory three 1193

pairs with a waiting time of one shift were reduced to 250 pairs and 52.5 minutes

respectively.

Supermarket Pull System between Fabric Supplier and Inspection Operation

The remaining lean connection will be between fabric suppliers and inspection

operation. Here also it’s possible to introduce a supermarket pull system. Currently, the

supplying process takes place once a day with manually pulled trailers. This makes the

setup work challenging to frequently change the fabrics. Therefore it’s better to reduce

the size of fabrics and trucks by half. The supplying process change from one time per

day to two times per day.

Lot Size Part Name Reorder Point

Pallet No. Part No. Pallet No.

Store

Machine for

Use

63

Figure 5.14: Super Market pull system for cutting operation

Figure 5.15: Super Market pull system for dyeing Section

Connecting the Dyeing and Garment section with a supermarket pull system will enable

the production of the required type of product as per customer need. Besides, it was

used as the beginning for distributing lean manufacturing to other sections in BDTSC.

Therefore the first task was the suppliers must deliver their output according to the

kanban order from the production control unit. The kanban card needs three different

kinds of bedsheet designs with a length of 500 meters. In addition, the card holds the

product type, width of bed sheet, length, and so on data.

Here the production order was scheduled from the BDTSC production control unit and

the garment section mangers duty will be controlling the progress. The production of

goods initiated when there were a customer need and empty spaces in the dyeing section

Every 250 pair

in three design Every 10 pair

Cutting Work Cell 2

Super Market for

5 production line

Daily order

Super Market for

Dyeing Section

Every 6 layer

of 500 meter

2X a shift

Inspection

Dyeing

Section

Production

Control

Garment

Daily Report

64

supermarket. The procedure to create a supermarket pull system was the same as with

previous cutting operations. Here it’s necessary to look at the procedure of how to use

the kanban supermarket to dyeing section.

Performance Achieved by Using Continuous and Supermarket Pull Systems

By using a value stream mapping procedure so many improvements were made with

fewer steps. So far the achievements in reducing VA time, NVA time, and inventory

size were listed in the table below.

Process CT/VA

(min)

Inventory

(pair)

NVA (min) Space

Required (m2)

Material travel

length (m)

Before After Before After Before After Before After Before After

WIP1 952 500 210 125 ---- ----- 10 10

QI 4.02 4.02 WIP2 208 0 42 ∅ 5 ----- 38 45

Cutting 222.69 46.6 WIP3 1193 250 420 52.5 20 30 28 ----

Sewing 0.18 0.42 WIP4 0 0 0 ∅ ----- ----- ----- ----

Folding 0.287 0.42 WIP5 100 0 150 ∅ ----- ----- ----- ----

Packing 0.14 0.34 WIP6 952 0 1680 ∅ 25 ----- 16 8

Unitizing 4 .67 16.2 WIP7 3645 0 1680 ∅ 50 ----- 50 35

Total 232 68.1 7050 750 4182 177.5 100 30 142 98

Table 5.6: VA time, NVA time, and Inventory size reduction in the garment section

𝑉𝐴 𝑡𝑖𝑚𝑒 𝑟𝑒𝑑𝑢𝑐𝑡𝑖𝑜𝑛 =𝑉𝐴 𝑖𝑛 𝑓𝑢𝑡𝑢𝑟𝑒 𝑠𝑡𝑎𝑡𝑒 – 𝑉𝐴 𝑖𝑛 𝑐𝑢𝑟𝑟𝑒𝑛𝑡 𝑠𝑡𝑎𝑡𝑒

𝑉𝐴 𝑖𝑛 𝑐𝑢𝑟𝑟𝑒𝑛𝑡 𝑠𝑡𝑎𝑡𝑒× 100

𝑉𝐴 𝑡𝑖𝑚𝑒 𝑟𝑒𝑑𝑢𝑐𝑡𝑖𝑜𝑛 =68.13 − 232

232× 100 = 70.6%

𝑁𝑉𝐴 𝑡𝑖𝑚𝑒 𝑟𝑒𝑑𝑢𝑐𝑡𝑖𝑜𝑛 =177.5 − 4182.3

4182.3× 100 = 95.7%

𝐼𝑛𝑣𝑒𝑛𝑡𝑜𝑟𝑦 𝑟𝑒𝑑𝑢𝑐𝑡𝑖𝑜𝑛 =750 − 7050

7050× 100 = 89.36%

𝐼𝑛𝑣𝑒𝑛𝑡𝑜𝑟𝑦 𝑠𝑝𝑎𝑐𝑒 𝑢𝑡𝑖𝑙𝑖𝑧𝑎𝑡𝑖𝑜𝑛 =100 − 30

100× 100 = 70%

𝑀𝑎𝑡𝑒𝑟𝑖𝑎𝑙 𝑡𝑟𝑎𝑣𝑒𝑙 𝑙𝑒𝑛𝑔𝑡ℎ =142 − 98

142× 100 = 30.98%

65

Figure 5.16: Overall improvements in VA, NVA, Inventory, and WIP travel length

reduction

5.2.7. Pacesetter

The improved production system was a good example of a lean production system but

this was not enough for its effectiveness. The progress up to now needs to regulate its

pace otherwise the performance will be going back to the previous state. Therefore this

was accomplished by assigning a pacemaker process that regulating the speed of a

particular process. The pacemaker process used for this case was work cell two which

holds operations like sewing, folding packing, and bailing operation. Work cell two

needs great attention because the operations in this cell had a relatively higher cycle

time compared to others. Therefore controlling the pace of this station will control the

pace of the upstream operations and create a great difference in production output.

Besides, the pacemaker process must be assisted by a signaling system (Andon) to give

information on whether to slow or stop production to the upstream process.

VA time

Reduction,

70.6%

NVA time

Reduction,

95.90%

Inventory

Reduction,

89.36%

WIP Travel

Length

Reduction, 31%0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

VA TIME REDUCTION

NVA TIME REDUCTION

INVENTORY REDUCTION

WIP TRAVEL LENGTH REDUCTION

66

Source: (www.leansixsigma.com, 2020)

Figure 5.17: Andon visual control system

5.2.8. Creating Flexible Production System

The future production system allows the production of 7 bundles (490pair) of 160 X

250-bedsheet type and 6 bundles (420pair) of 156 X 210-bedsheet per shift. The bundle

contains three different color types and such a variety of products needs a lot of

improvement in the production system. The process of improvement starts from the

supplying process and goes in each operation for producing as per customer wants.

The placement of fabrics in each truck will follow some pattern and the pattern will be

found in each kanban card. Leveling the product mix must start from the supplying

section and the main activities will be fabric preparation for the next process. The large

size fabrics when placed in trailers need to be cut with a length of 500meter. Therefore

each container should hold fabrics of different colors which allow us to produce

different size bed sheets in three or more different color. Previously there was the

capacity to produce only one type of color choice in one shift but with an improved

system, there was a possibility to produce two bundles of three variety of design.

Each layer of fabric makes four roles of fabrics these rolls are convenient for transport

and use in cutting operation. Here it’s better to determine the amount of work in process

that was transferred in the downstream process. The goal of the new production system

was to produce a bundle containing 70 pairs with three different color fabrics every

67

31.5 min. This was accomplished by letting to flow 10 pair of bedsheets with two kinds

of color. The leveling of sheared fabrics was carried out at supermarket two.

So far the new production system had an output of one bundle every 31.5 min and can

also produce two product types per shift. The old system of production produces only

one kind of color design in other words the system could not produce a bundle in each

shift. This tells us with few setup changes it’s possible to produce many product types,

within a short lead-time, in higher quality and reduced cost.

5.2.9. Pitch Increment and Removal of Work

This question was used to determine the fixed amount of work injected into the

production process. Therefore the first task will be answering the amount of work added

in the pacemaker process and the second was how frequently the production control

unit should give working instruction. Here there were two ways of work increment the

first one is adding all 1057 kanban orders at one time and the second way is paced

release of work or one bundle. The question was which way to go? The former is the

Source: (www.leanproducts.eu, 2020)

Figure 5.18: Load leveling box

same with batch production and it was not feasible as we can see in the previous sections

and the latter one was a controlled work injection method. It’s obvious to go in the

second way and the pitch increment amount in work cell two will look like 70 pair X

27 sec which was 30.5 minutes. This means the production control unit instructs tasks

to work cell two every 30.5 minutes. At the same time, the production output was

68

transferred to the shipment area. Therefore with this pitch increment, the production

capacity will be 13.33 bundles or 933pair per shift.

The process of paced release and take away of work was assisted by a load-leveling

box. In the load-leveling box, each box represents the paced release of work and in

every 30.5 minutes, there was a paced release of work to work cell two. If the unit

bundle was not completed within pitch time there was some problem at one of the

operations and need to be solved.

5.2.10. What Process Improvements will be necessary for BDTSC's?

The process improvement tools used for BDTSC garment sections were specified in the

previous sections. Some of the techniques used in the previous section were production

with Takt time, continuous system, supermarket pull system, kanban information

exchange system, flexible production system, cellular production system, and

pacesetting are major. Here one last main improvement technique is setup time

reduction. The major improvement elements were reducing the changeover time and

size of the batch. The setup time reduction was used to create a flexible manufacturing

system for changing customer demand. This in return allows producing every part every

day.

Let’s see the improvements made to create a flexible manufacturing system. At the

supplier's side, the truck size was reduced by half this will reduce the weight of the

trailer and was helpful for a convenient changeover. The truck must build from

lightweight material to make easier the transportation of goods. Operators in

downstream painting machines must use the equipment for automatic mark-up and

shearing of fabric. This will enable the downstream operation to produce the required

amount of products. Next to the shearing activity, the material handler must create a

product mix in each truck to produce a variety of products that can satisfy various

customer choices. This way materials were prepared for the garment section and

stocked in the supermarket.

Likewise, the same improvements were made at supermarket two which was the

preparation stage for creating a unit bundle. These changes were much more important

for producing each part each day. Here bin used for holding 10 items was required to

facilitate the flow and it must be lightweight and convenient for use. Here it’s better to

design bins by considering ergonomic factors.

69

5S

5S is a system used to create a favorable working condition in the production site by

removing unnecessary materials, arranging tools, and inventories in the production site.

Besides it improve the quality of the product by removing unnecessary dust. The

sources of wastes at the production site were first, long set-up time because of tools

arrangement, and space for an easy setup change. Second, inventory handling of

Defected materials (rags and cutting strip) was the cause for lower employee morale.

Third, a dirty working place was the cause of health-related problems for employees

also it reduces the quality of finished goods. 5S was a cleanup activity in the workplace

which represents Japanese words Seiri, Seiton, Seison, Seiketsu, and Shitsuke.

Seiri: was a way of separating necessary things from unnecessary ones. Some of the

activities required for separating necessary elements from unnecessary ones were the

following.

1. The establishment of a red label (usable) project; was the level of

undertaking a red label project (usable) which was at the workplace level daily

and the company level annually.

2. Determination of objects to be sealed; In this case fabrics in different places

must be separated from defective ones therefore defected fabrics were selected.

3. Determining leveling criteria; in the first level cutting strips, rags, and

defective fabrics that were not used for bedsheets were selected. In the second

round, noncritical defective fabrics that can be used for bedsheets were selected.

In the last round work in process with no defect was selected.

4. The preparation of labels; looked like in the figure below.

5. Evaluation of sealed items and recommended actions; In this step cutting

strips and defective fabrics were discarded or sold to customers as a rag.

Defected noncritical units were utilized for other rounds and were stored in red

label storage.

70

Classification 1. Cutting strips and defective fabrics

2. Noncritical units

3. Works in-process

Item name

Number

Quantity

Reasons Unnecessary, defective

Department

Date

Table 5.7: Card for labeling different resources in the garment section.

Seiton: to neatly arrange and identify things for ease of use. The following steps can be

used these were decided item placement, Prepare containers, Indicate the position for

each item, Indicate the item code and its quantity, Make Seiton a habit. Here work in

process was arranged well by using lean principles but unnecessary inventories need to

be arranged.

Seiso: was to always clean up; to maintain tidiness and cleanliness. Therefore there

should be a technical solution for reducing the amount of cutting strips and rag. Besides

the cutting strip and rags from the inspection machine need to be placed inside bins, not

on the floor. This one also has a benefit in improving employee’s health and safety also

it creates a harmonious working environment.

Seiketsu: to constantly maintain the 3S mentioned above, Seiri, Seiton, and Seiso.

Shitsuke: was a worker's habit of always conforming to rules. Here the employee’s

attitude toward the company was an important thing to create workers conforming to

rules. The employee's self-controlling was the best way that can provide good results

in the output. This will help to improve employee’s performance by competing with

themselves and by creating pride. Therefore employees need to know the Company’s

Mission and Vision statements and must be displayed in a visible area (Monden Y.,

2012).

Total Productive Maintenance

Total productive maintenance was a system used to create zero breakdown or minimum

loss in the production system. It was a combined work of the production system and

maintenance section for excellence in productivity. The result of TPM was to improve

71

uptime which increases the reliability and maintainability of equipment and the system

as a whole.

New Product Development

The invention is the act of realization of developing a solution to a problem. Innovation

is the economic use of the invention and this will lead to increased market share.

Product development was the same with innovation in which it was an effort to

introduce innovation to a market. A company like BDTSC can produce improved

products and compete for the market by looking at the demand.

Innovation and product portfolio management: here the strategic decision was either to

open a new business, introducing a new product, and entering into the market or exit

(i.e closing the business unit down). For BDTSC new product development was the

only option to stay in the market. Therefore the company can pursue an adaptive way

and in the future, it's possible to use the proactive move. The adaptive way was the easy

way to get market share by imitating the products available in the market. But to get a

high market share in the future it’s better to use a proactive move (Marco C., &

Francesca M., 2016).

BDTSC garment section can produce a variety of products with available company

output but if the input fabric type had lower variety it possible to buy and make different

product types. The company's lower competitiveness problem in a large market was a

rise from a lower quality product. Therefore BDTSC should produce products with

great care when it is required for export standard. On the other hand for a small market,

it’s possible to produce with a short time to manufacture and limited investment.

72

5.2.10. Allover Improvements Made by using Lean Principles

S.

no

Improvement factor Current state

VSM

Future state

VSM

Percentage of

improvement

1. Information flow Repetitive

controlling,

forecasting &

scheduling

activity

Assisted by Takt

time, Kanban

card, load-

leveling box and

Andon,

2. Production system Production Push Customer pull &

flexible

3. Human resource utilization

(crew no.)

29 26 10.3%

4. Production output (pair/shift) 952 1108 16.8%

5. Time consumption for 933

pair of bedsheet (minute)

420 360.8 14.7%

6. Line balancing, an operator in

bailing operation idle for

1.5 day Busy everyday

7. Product variety (per shift) 1 6

8. Controlling the pace of

production(daily)

Unit 100 pair

output per 2

operators.

Pitched release

& removal of

work every 30.5

minutes

9. Material flow Production Push One piece

(FIFO &

supermarket)

10. Delay 5 2

11. VA time reduction (min) 232 68.13 70.6%

12. NVA time reduction (min) 4183 172 96.2%

13. Inventory reduction (pair) 7050 750 89.35%

14. Inventory Space Utilization

(m2)

100 30 70%

15. Orientation of Operations A large gap

between

operations

Cellular

arrangement

16. Transportation 7 3

17. Material distance travel (m) 142 98 30.98%

Table 5.8: Allover improvements made by using value stream mapping.

When the improvements were summarized first there was an introduction of a

supermarket pulls system in a marketing system. Secondly, the operations were

arranged in a cellular form and the flow of material was changed to one-piece flow

73

(FIFO). Thirdly, the production system was changed from the production push system

to the customer pull system. Besides, every operator in each operation was occupied

for work every day. In the fourth position, the delivery system of finished goods was

changed from make to stock to a direct shipment system. Finally, the production-based

system was changed to a customer-oriented flexible production system.

5.2.11. Summary of Modelling the Future State VSM

To make the uptime 100 % on cutting operation it’s better to use preventive

maintenance techniques. To create a multi-skill operator it better to use a rotation of

operators on different machines weekly. Bailing machines need to be used only in a

continuous system and for work in the process out of the continuous system it’s possible

to use an alternative machine. Therefore the availability of the bailing machine will be

the same as the upstream operation.

The value-adding time for work cell one was the summation of cycle time in inspection

and cutting operation. Likewise, the value-adding time of work cell two was the

summation of cycle time for sewing, folding, packing, and bailing operations. The

number of operators in each work cell was the summation of operators in each

operation.

Supermarket two was controlled by two operators at the same time for supermarket one

also needs operators but since it was on the supplier's side and it was assigned by dyeing

section supervisors. Finally, the shipment process also needs operators for managing

finished goods.

Step Process Inventory

(pair)

VA/

NVA

CT/

VA

(sec)

CT/

NVA

(min)

Crew CO Uptime

(%)

Waste

(Kg)

Availability

(%)

WIP1 500 NVA 120

1 Work Cell 1 VA 50.62 8 0 100.% 12.6 77

WIP2 250 NVA 52.5 2

2 Work Cell 2 VA 17.38 18 0 100% 0.97 77

Shipping 1904 NVA 0 2

Table 5.9: Future state value stream mapping automatic data entry system.

74

Figure 5.19: Future state value stream mapping with Kaizen burst

© 2017 KnowWare

Dyeing

Section

Daily

27 Bunble

1 hour2 hour∅

Establish kanban size/

quantity & Leveling the

Product mix

Partner with

Suppliers on

S/M Pull System

Work Cell 1

FIFO lane in

work cell 1

Work Cell 2

FIFO lane in

work cell 2

Control Unit

Inspc

Dept.

Sche-

duler

Super-

visorFa

74,000 Pair

160 x250

Bundle = 70 pair

1904 pair per day

Amaga

Takt time = 27 sec

Electronic

Orders at

PacemakerClose

Order daily

Reduced

size trailer2 times

per Shft

Visual Control

System / Andon

6 layers of

500 meter

X 3Design

Establish kanban size/

quantity & Leveling

the Product mix

10 Bed

sheets X 2

Design

Need to

use bins

Pitch Increment of work

with every 31.5 min

Pitch Removal of

finished goods with

every 31.5 min

CT = 50.62 min CT =17.38 min

Dailly

Order

Purchase

Order

Supermarket Requierd to

connect with customer

Sales Rep

Supermarket

Customer

8 hrs

Sales

Order

Shipping

75

Figure 5.20: The future state value stream mapping

Instructions

© 2017 KnowWare

Takt Time 27 27

Cycle Time 68 50.62 17.38

Crew 8 18 #REF!

Chageover 0 0 0

Uptime 100% 100

Waste 12.6Kg 0.97Kg

Availability 77 77

Total NVA 120 52.5 0 NVA= 172.5 min

VA ###### 50.62 17.38 VA= 68 minTotal

Distance #### 38 33 45 Distan=116 m

500 250 0

Dyeing

Work Cell 1

8

74,000 Pair

160 x250

Bundle = 70

pair2 Shift

Amaga

Dailly

Order

Work Cell 2

18

Daily

27 Bunble

Fax

Purchas

e Order

2 times

per

Shft

Control Unit

Inspc

Dept.

Sche-

duler

Super

-visor

Electronic Orders

at Pacemaker Close Order

daily

Sales

Rep

Supermarket

Customer

8 hrs

Sales

Order

Shipping

76

5.3. Simulating the Future State VSM

This section of the study was aiming to validate the potential gain from the future state

production system. The simulation model was developed for the future state VSM

model found in section five. The model was developed by using the Arena version 14

simulation software. The first step to validate the future state map was determining the

best distribution for operations by using an input analyzer. In this step, the balanced

cycle time of each operation found in the future state map was used for analysis. The

analysis result shows the graph for different distribution among them the one with the

minimum square error is selected for arena simulation.

The simulation model helps to mimic the real production system so that each parameter

on the future state model was applied to simulation system. The verification process of

the future state model was accomplished by coding the flow of material from its

entrance point up to disposal from the organization. Then the model was run several

times and corrected until it replicates the future state model. The simulation result helps

to validate the future state model and to relate the performance of the future state model

with the simulation result.

The output of the simulation result includes inventories at bailing operation and the

total time utilized for daily production. The model was replicated one time and run for

seven-hour. All the simulation result shows that the data were within the range of future

state results.

5.3.1 Simulation Result

One replication was used and the replication length was 420 min. The output for this

replication was 13 bundles and the fabric used for 14.4 bundles was supplied. The

number of bedsheets out was 910 pairs which were the same as the future state model

result.

The average value-added time for the bundle was 1663.9 min and the maximum value-

added time was 2014 min. The waiting time for the bundle was 7538 min and the

maximum waiting time was 15,002 min. The average total time for the bundle was 238

min and the maximum total time was 419.6 min.

The number of fabric entering the production system per shift was 6048 meter or (1008

pair of bedsheet). This fabric was composed of 12 different designs and it was arranged

77

in supermarket 1. This number of fabrics forms 48 rolls of fabric in inspection

operation. Then in the cutting operation, each roll forms 21 bedsheets and at the end of

the day, 91box (910 cut fabric) passed the bailing operation. Here the number of cut

fabric passing the supermarket 2 were 100 boxes. The final output of the system for 7

hours available time was 13 bundles.

On the other hand, the average number of work in process formed by fabric arrival in

the line was 614 bedsheets (7.27 fabric) and the maximum value for this fabrics were

1008 pair (6048-meter fabric). In supermarket 1 and inspection operation the work in

process was 3.41 fabric and the maximum value was 12 fabric. The Work in process

formed by roll was one which was the result of the continuous system. Likewise, for

cut fabrics, the average number was 29 boxes (290 pairs) and the maximum number of

WIP formed by this sheared fabric was 58 boxes. Lastly, the maximum number of WIP

formed by bundles was 1.

The average waiting time for inspection and sewing operation was 101 min and 94 min.

respectively. These waiting times were higher up to 202 min and 186.6 min. The

average waiting number in inspection and sewing operation was 2.8 fabric and 23 boxes

of cut fabric (230 bedsheets). The maximum waiting number in inspection and sewing

operation was 11 fabric and 480 bedsheets.

As we can see in the queue table, the waiting number for cutting, folding, packing, and

bailing operation were zero. Likewise, the waiting time on the above operation was 6

min, 1 min, and zero respectively. This indicates the continuous flow (first in first out

lane) in the future state value stream works well.

The instantaneous resource utilization was composed of operators and machine

utilization. The instantaneous operator utilization for inspection operator was 26.48%,

cutting operator 7.39%, sewing operator was 95.47, folding operator 93.2%, packing

operator 75.42%, and bailing was 16.7%. On the other hand, machine utilization looks

like an inspection machine 52.95%, cutting machine 44.35%, sewing machine 95.47%,

and bailing machine 49.99%.

When we see the number of resources scheduled in each operation in inspection

operation there were 2 operators and 1 machine was assigned, in cutting operation 6

operators and 1 machine was assigned, in sewing operation 5 operator and 5 machines,

in folding operation there were 5 folding operators, in packing operation 5 operators

78

and lastly, in Bailing operation there were 3 operators and 1 bailing machine were

assigned.

5.3.2. Validating the Future State Model

The simulation result in the previous section was helpful to know the reliability of data

in the future state model. The input data in both models was the same, and it looks like

26 operators and 420-minute available time. Table 5.10 was the comparison table and

the results from the two models reveal that the production output per shift was the same

which was 13 bundles. The output of the simulation result indicates all the

improvements achieved by the future state map were accurate results and if the

preconditions were fulfilled the results will be the same in a real environment. On the

other hand, the non-value added or (waiting) time was 195 min which was increased by

23 min from the future state model. The waiting time difference was little and as the

production output shows the time difference effect was negligible. The inventory

amount in the simulation was reduced by 284 pair below expected. This figure can

create a huge difference in production output but the amount was below value in the

future state model which will have a positive effect. This and the above information

joint effect validate the future state model and it will create a positive impact on the

production site by improving productivity.

S. no Improvement factor Future state VSM Simulation result

1. Available time (min) 420 420

2. Human resource utilization

(no of crew/shift)

26 26

3. Production output (pair/shift) 933

(13 bundle)

910 pair

(13 bundle)

4. NVA(waiting) time (min) 172 195

5. Inventory (pair) 750 466

Table 5.10: Table for comparing the results of future state model and simulation

model.

79

Figure 5.21: The future state VSM simulation result

80

6. CONCLUSIONS AND RECOMMENDATIONS

6.1. Conclusions

The case company used for this study is Bahir Dar Textile Share Company. The

garment section is one of the bottlenecks for company profitability associated with poor

manufacturing practice and lower effort to address a customer need. The waste type in

the current production system were overproduction, lower resource utilization, excess

inventories and waiting time, transportation, unnecessary information flow, and lower

flexibility are the main characteristics of the shop. Therefore the study mainly uses lean

manufacturing principles to overcame those wastes and improve productivity.

The case study integrates the value stream mapping with simulation system.

Throughout the study, the findings reveal that the simulation validation was an essential

and useful part of the study. The simulation part was helpful to reach a common

consensus about the future state VSM, and to visualize the VSM model.

The main aim of the study was to improve productivity by using lean manufacturing in

the production system. Productivity improvement had a direct relationship with

eliminating wastes. The study reveals that the improved production system reduces the

lead time from 73.57hour to 4.09hour by 94.4 percent, non-value-added time from 4183

min to 172 min by 96.2 %, the inventory was reduced from 7050 pair to 750 pair by

89.35%. Besides through connected operations, the distance travel was reduced from

142 m to 98 m (improved by 30.98%). On the other hand, by using a flexible production

system the product variety was increased from one to six bedsheet types per day.

Furthermore, the production system was changed from push to customer pull system,

and the number of human resources was reduced from 29 to 26 which is by 10.3 %, the

production output was increased from 952 to 1108 pair per shift by 16%.

81

6.2. Recommendations

The lean production system was an effective tool to improve the productivity of

garment production in textile industry. The study will give good results if it is applied

in less productive sections with unnecessary information exchange systems and

scheduling tasks, with lower resource utilization and flexibility, and lastly in a

production system with excess inventories, waiting time, and transportation.

This study recommends taking the following measure in the production system. The

multi-skill operator is an important thing to meet the dynamics of customer need

therefore it’s better to use a rotation of operator. The quality of the product can be

improved by using 5s. The uptime of equipment and availability can be improved by

using total productive maintenance. Lastly, for producing a variety of products

according to customer need and for better resource utilization it's better to use the new

product development approach known as the adaptive way.

6.3. Future Work

There are many future application areas associated with this study. Primarily, the VSM

can combine with other improvement tools to get better results on a process that was

not properly explained. Secondly, for different conditions, there is another simulation

software that can give good results when combined with VSM. The third application

area beyond the production system was in the supply chain system. Therefore future

studies can be carried out to improve the supply chain system.

82

REFERENCES

Abdulmalek F., & Rajgopal J. (2007). Analyzing the benefits of lean manufacturing

and value stream mapping via simulation: A process sector case study.

International Journal of Production Economics, 107(1), 223–236.

https://doi.org/10.1016/j.ijpe.2006.09.009

Ali S. et al. (2009). Productivity: MIS 517 Operations Management.

Amare M. (2010). Model Development of Quality Management System for Ethiopian

Textile Industries.

Amdework G. (2019). Production Lead Time Improvement through Lean

Manufacturing (Case Study in Hibiret Manufacturing & Machine Building

Industry).

Anil K. et al. (2008). Production and Operations Management (Second Edition), New

Age International, New Delhi.

Bahir Dar Textile Share Company. (2020). Daily Company Report.

Baysan S., Kabadurmus O., & Cevikcan E. (2019). A simulation-based methodology

for the analysis of the effect of lean tools on energy efficiency : An application in

power distribution industry. Journal of Cleaner Production, 211, 895–908.

https://doi.org/10.1016/j.jclepro.2018.11.217

Braglia M., Carmignani G., & Zammori F. (2017). A new value stream mapping

approach for complex production systems. 7543(August).

https://doi.org/10.1080/00207540600690545

Bruce M., (2006). Buyer behavior for fast fashion’, Journal of Fashion Marketing and

Management. Journal of Fashion Marketing and Management, Vol. 10(No. 3).

Retrieved from pp.329–344

Derbe T. (2018). Productivity Analysis and Improvement in Ethiopian Metal

Manufacturing Industries “ A Case of Yesu Metals Manufacturing .”

Daniel P. (2013). Diagram depicting the parts of a value stream map. U.S. Patent No.

CC BY-SA 3.0 US

Deshkar A., Kamle S., Giri J., & Vivek K. (2018). Mapping ( VSM ) for a plastic bag

manufacturing unit. Materials Today: Proceedings, 5(2), 7668–7677.

83

https://doi.org/10.1016/j.matpr.2017.11.442

Gebrehiwot A. (2017). Practicing Lean Manufacturing Tools For Productivity

Improvement. A Case study in Knit to Finish Garment PLC.”

Hans G. (2012). International productivity comparisons at the industry level. Alfred

Weber Institute. Universidad Heidelberg.

James P., & Daniel T., (1990). The Machine That Changed the World (1st ed.). New

York.

James P., & Daniel T. (2003). Lean Thinking: banish waste and create wealth in your

corporation. New York: FREE PRESS.

Kendrick J. and Creamer D., (1965), Measuring company productivity Handbook with

case studies, New York.

Kunz G. (2007). Going Global. The Textile and Apparel Industry.

Liker J. (2004). The Toyota Way Fieldbook-14 Management Principles from the

World’s Greatest Manufacturer. New York: McGraw-Hill.

Lugert et al. (2018). Dynamization of Value Stream Management by technical and

managerial approach. Procedia CIRP, 72, 701–706.

https://doi.org/10.1016/j.procir.2018.03.284

Marco C., & Francesca M. (2016). Management of Innovation and Product

Development. In Management of Innovation and Product Development.

https://doi.org/10.1007/978-1-4471-6723-5

Mike R., & John S. (1999). Learning to See Value Stream Mapping to Add Value and

Eliminate MUDA’.

Mikell P. (2008). Automation production system and computer integrated

manufacturing (3rd edition; P. NJ, Ed.). Prentince hall.

Monden Y. (2012). TOYOTA Production System: An Integrated Approach to Just-In-

Time (4th Edi). CRC Press.

Neeraj et al. (2018). Modeling and simulation of discrete manufacturing industry.

Science Direct, 5(11), 24971–24983. https://doi.org/10.1016/j.matpr.2018.10.298

Andris F., (2009). Methods, Standards, and Work Design, (12th Edition). Minnesota:

84

McGraw-Hill.

QI macros software, (2018). qimacros.com

Rahel S. (2010). Performance Measurement and Improvement of Ethiopian Garment

Industries.

Romero L., & Arce A. (2017). Applying Value Stream Mapping in Manufacturing: A

Systematic Literature Review. IFAC-PapersOnLine, 50(1), 1075–1086.

https://doi.org/10.1016/j.ifacol.2017.08.385

Sime H. (2019). Feasibility of using simulation technique for line balancing in apparel

industry. Procedia Manufacturing, 30, 300–307.

https://doi.org/10.1016/j.promfg.2019.02.043

Stadnicka D., & Litwin P. (2019). Value stream mapping and system dynamics

integration for manufacturing line modeling and analysis. International Journal of

Production Economics, 208(December 2018), 400–411.

https://doi.org/10.1016/j.ijpe.2018.12.011

Statistics, car sales. (2018). (full year) international: global top car brands.

Tadesse A. (2011). Design of Productivity Improvement Method for Ethiopian Garment

Industries.

Tyler D., & Heeley J. (2006). Supply chain influences on new product development in

fashion clothing. Journal of Fashion Marketing and Management, Vol. 10(No. 3).

Retrieved from pp.316–328

www.assolombarda.it. (2020). Bahir Dar Textile Share Company ’ s Profile. Retrieved

from www.assolombarda.it website: 200498175949-78

www.bahirdartextile.com/en/. (2020). Bahir Dar Textile Share Company.

www.leanproducts.eu (2020). system box-2

www.leansixsigma.com (2020). andon

85

APPENDIX

Appendix-1 Questionnaire

Dear respondent,

I am a postgraduate student in Bahir Dar Institute of Technology with a program of

production engineering and management, Bahir Dar University. Currently, I am

undertaking a study entitled “Productivity Improvement through Lean Manufacturing

principles in garment section of Bahir Dar Textile Share Company.” You are one of the

respondents selected to participate in this study. Please assist me by giving correct and

complete information to present a representative finding on the current status of the

Assessment on lean manufacturing Case of Bahir Dar Textile Share Company. Your

participation is entirely voluntary and the questionnaire is completely anonymous.

Finally, I confirm that the information that you share with me will be kept confidential

and will be used only for the academic purpose. No individual responses will be

identified and the identity of persons responding will not be published or released to

anyone. Thank you in advance for your kind cooperation.

Sincerely,

Abrham Temesgen

86

Instructions

No need of writing your name.

For multiple-choice, questions indicate your answers with a checkmark (√) in

the appropriate block.

GENERAL INFORMATION

1. Sex: Male Female

2. Age: 18-25 years 25-40 years 40-55 years above 55 years

4. Educational Qualification: Up to Grade 12 Certificate College diploma

First Degree Second Degree and above

5. Year of work experience in the organization: below 5 years 5-10 years

10-15 years 15-20 years above 20 years

No Questionaries’ Very

Good

Good

Average

Poor

Very

Poor

2 Are there any activities for

synchronizing customer need with the

available production rate?

3 Do your company producing finished

goods to a supermarket from which

the customer pulls?

4 Are you applying continuous flow in

the manufacturing system?

5 Does your company's production

output determine by customers'

demand in a supermarket?

6 Does your company have a

pacemaker process that used to

schedule the rest of the process?

7 Are there levelling the production

mix for fulfilling different customer

needs?

8 Does your company use pitch

increment and removal work?

9 Are there techniques for reducing

change over time?

Appendix 1:1 Guidelines for implementing lean production

87

Appendix 1:3 Descriptive analysis result for questionnaire

Row1 Row2 Row3 Row4 Row5 Row6 Row7 Row8

Mean 2.423077 2.038462 2.692308 2.961538 2.5 2.807692 2.692308 2.461538

Standard Error 0.176923 0.195965 0.164263 0.187951 0.201914 0.192308 0.198217 0.16853

Median 2 2 3 3 2 3 2.5 2

Mode 2 1 3 3 2 3 2 2

Standard Deviation 0.902134 0.99923 0.837579 0.958364 1.029563 0.980581 1.010712 0.859338

Sample Variance 0.813846 0.998462 0.701538 0.918462 1.06 0.961538 1.021538 0.738462

Kurtosis -0.46909 1.367885 1.235434 0.108473 -1.05948 -0.71458 -0.37562 -0.43495

Skewness 0.425372 0.960678 0.659796 -0.21411 0.23824 -0.41118 0.433608 0.12849

Range 3 4 4 4 3 3 4 3

Minimum 1 1 1 1 1 1 1 1

Maximum 4 5 5 5 4 4 5 4

Sum 63 53 70 77 65 73 70 64

Count 26 26 26 26 26 26 26 26

88

Appendix-2 More Findings

Loation; Bahir dar Summary

Activity; Garment Event Present Proposed Saving

Date;15-03-20 Operation 5 5

Supervisor; Eshet Analist; Abrham Transport 7 3

Circle appropriate method and type

Method; Present Proposed

Type; Worker Material Machine

Delay 6 2

Inspection 1 1

Storage 1 0

Remark; Time (min) 4204.29 240.5

Distance (m) 142 98

Event Description Symbol Time

(min)

Distance

(m)

Method

Recomendtion

Travel to Inspection O → D □ ∇ --- 10

Delay O → D □ ∇ 210

Inspection O → D □ ∇ 4.02

Delay O → D □ ∇ 42.3

Travel to Cutting section O → D □ ∇ --- 38

Cutting O → D □ ∇ 222.69

Travel to temporary storage O → D □ ∇ --- 23

Delay O → D □ ∇ 420

Travel to Sewing O → D □ ∇ --- 5

Sewing O → D □ ∇ 0.18

Folding O → D □ ∇ 0.287

Delay O → D □ ∇ 150

packing O → D □ ∇ 0.14

Travel to temporary storage O → D □ ∇ --- 9

Delay O → D □ ∇ 1680

Travel to Unitizing O → D □ ∇ --- 7

Unitizing O → D □ ∇ 4.67

Travel to temporary storage O → D □ ∇ -- 5

Delay O → D □ ∇ 1680

Travel to final stock area O → D □ ∇ 45

Final stock O → D □ ∇

Appendix 2:1 Flow process chart (material) for production of bedsheet.

89

Appendix 2:2 Flow diagram of the old layout.

90

Appendix 2:3 Flow diagram of the future State layout.

91

Appendix 2:4 Cycle time of operations for bed sheet production.

Study no; 2 Date; 15-03-20 Page; 1

Observer; Abrham

Element no and

Description

1 Inspection 2 Cutting 3 Sewing 4 Folding 5 Packing 6 Bailing

Note Cy OT OT OT OT OT OT

1 11.8 11.5 96 154 150 4.2

2 13.3 12.01 98 154.7 153 3.6

3 17.7 10.3 100 152.4 155 3.6

4 12.6 11.7 108 150.04 145 3.97

5 10.3 10.8 90 156 140 4.94

6 11.8 10.57 82 152.8 147 4.46

7 8.8 11.2 103 154 150 3.86

8 9 11.3 100 160 159 3.78

9 11.8 10.82 100 156 155 4.07

10 13.3 10.2 112 164.6 150 3.56

Total OT 120.5 110.4 971 1554 1522 40.04

NO Observe 10 10 10 10 10 10

Average OT 12.05 11 97.1 155.4 152.2 4

Out put 20 1193 0.111 0.111 0.0556 70

Cycle Time 241 13,123 10.8 17.3 8.4 280

92

Appendix-3 Icons for Constructing the Value Stream Mapping

Symbols Represents Notes

Outside Sources

(Customer/

Supplier)

Start or end point for material

flow

Process

Machine, operation or work cell

through which material flows

Data Box Used to record information

concerning a manufacturing

process, department, customer,

etc.

Inventory Work in process waiting for

process

Work Cell Operations arranged close to

each other.

Push Arrow Work in process that is produced

and moved forward before the

next process needs it;

NVA Delay

Supermarket

Used to create controlled

inventory.

Pull Symbols

(Withdrawal)

Pull of materials, usually from a

supermarket. Replenish stock in

supermarket

Internal Movement

In Box

Information Queues

93

Information

Icons

Represents Notes

Manual Information

flow

For example: production schedule

or shipping schedule.

Electronic

Information flow

For example via electronic data

interchange.

Withdrawal Kanban Facilitate the movement of

material in the downstream

operation.

Production Kanban

Initiate the production of goods

in the upstream operation.

Signal Kanban

Used as a reminder to prevent

stock out.

Kanban Post

Place where kanban are collected

and held for conveyance.

Sequenced-Pull Ball

Gives instruction to immediately

produce a predetermined type

and quantity, typically one unit.

A pull system for subassembly

processes without using a

supermarket.

Load Levelling Tool to intercept batches of

kanban and level the volume and

mix of them over a period of

time.

Go and See Adjusting schedules based on

checking inventory levels.

External Shipment

Shipments to or from suppliers

FIFO

First in, First out

lane

Indicates a device to limit

quantity and ensure FIFO flow of

material between processes.

Maximum quantity should be

noted.

94

General Icons Represents Notes

Kaizen Blitz

Area for

Improvement

Highlights improvement needs at

specific processes to achieve

future state value stream.

Buffer

Safety Stock

People, phones,

operators, etc.

Appendix 3:1 Value stream mapping icons

95

Appendix-4 Simulation Analysis Result

Inspection operations: NORM(17.04, 3.38), 0.033

Cutting operations: TRIA(3.36, 3.9, 4.41), 0.012

Sewing operations: NORM(4.23, 0.13), 0.078

96

Folding operations: NORM(4.71,0.657 ), 0.057

Packing operations: NORM(3.4, 0.87), 0.004

Bailing operations: TRIA(2.2, 2.33, 2.4), 0.046

Appendix 4:1 Arena input analyzer analysis result (Expression, Square error)

97

98

99

100

101

102

103

Appendix 4:2 Arena simulation analysis result