Production Planning (PP)
- Overview -
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
2
Overview
• Components of Production Planning• Production Process Overview• Planning Process Overview• MRP• Elements of a Production Order
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
3
Components of Production Planning
ProductionPlanning
(PP)
ProductionPlanning
SOP
CapacityPlanning
MRP
ProductCost
Planning
RepetitiveMfg.
ProductionControl
KANBANMasterData
DRP
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
4
Planning Process
Execution
Execution
Detailed Planning
High Level Planning
ForecastingSales and Operations
Planning
Demand
ManagementMPS MRP
Sales Information
System
CO/PA
Manufacturing
Execution
Order
Settlement
Procurement
Process
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
5
Material Requirements Planning
• A set of techniques utilizing bills of materials, inventory data (lead times and current status) and the master production schedule to calculate requirements for raw materials, components, and subassemblies
• A time-phased planning tool with a defined, specific algorithm
• Balances supply and demand
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
6
Inventory
MasterSchedule
Planning Rules
Bill of Material
OrdersForecasts
MRP
Process
RecommendedProcurement
RecommendedProduction
Inputs Outputs
MRP Process
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
7
Material Requirements Planning Elements
• Requirement elements (demand)– Withdrawals from inventory– Maintenance must be done at source of demand– Two types of demand
• Replenishment elements (supply)– Receipts into inventory– Maintenance can be adjusted manually
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
8
Elements of A Production Order
Raw Materials & Sub-Components
Bill of Material
Components
(Production Parts
List)
Work Center
Operations
Production Routing
Production Order
Organizational Data
• Client• Company code• Plant (shipping plant)• Storage location
• Work center location
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
10
Scheduleand Release
Shop FloorDocuments
Goods Receipt
Order Settlement
GoodsIssue
ProductionProposal
(Planning/Other)
CompletionConfirmation
Capacity Planning
Production Process (Make-to-Stock)
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
11
Organization
• Plant specific organizational units– Materials Requirements Planning controller – Production controller/production scheduler/planner group – Person responsible (financially)
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
12
Organization
• Non-plant specific organizational units– Capacity planner
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
13
MRP Control Parameters
• Environment– Number range
• Master Data – Materials Requirements Planning controllers– Float times
• Planned Orders– Conversion order type– Dependant requirement availability
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
14
MRP Control Parameters (continued)
• Planning run – Bill of Material (BOM) selection – External procurement– Planning horizon
• Availability Check– Material– Production Resource/Tool (PRT )– Capacity
• Scheduling Control Parameters
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
15
General Planning Parameters
• Order Type Control Parameters– Types of routings, BOM’s per order type: manually or
automatically– Availability checking
• Create Confirmation Parameters – Reservations– Status Updates
• Define Valuation of Goods Received– Moving Average Price Control evaluation
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
16
Material Master Planning Parameters
• Materials Requirements Planning views for materials
• Work Scheduling views for manufactured products
Business Rules and Parameters
• Automatic postings (account determination)– COGS, Material consumption, inventory
• Activate MRP• Availability checks• Scheduling parameters• Order parameters• Confirmation parameters• Planning parameters
– Consumption based planning– MRP
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
18
Master Data
• Master data is relatively fixed– Material master data– Vendor master data– Purchasing information record– General Ledger master data
• Before making the master data configurations, you must have completely defined the organizational structures
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
19
Overview
• Material Group• Material Master• Material Types• Material Master Views• Purchasing Info Record• Source List
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
20
Material Group
• The material group field allows similar materials to be managed together
• Material group is used in reporting– Executive Information Systems (EIS)– Logistics Information Systems (LIS)– Etc.
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
21
Material Master
• Material master data can be related directly to all organizational levels
• General information of a material (description, number, base unit of measure) however has to be related to the highest level of organization - the client – Further tailor the material master at the plant level or
lower
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
22
Material Type
• Categorizes materials• Defines the material attributes
– Valuation– Procurement– Price control– Etc.
• Controls transaction involving the material• Controls screen sequence, number assignment,
field selection, account determination
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
23
Material Types
Standard material types are used in all industries
• ROH: Raw Materials – Purchased externally only – No sales view
• HAWA: Trading Goods – Always purchased externally– Sold without any change to the material– No manufacturing views exist
• FERT: Finished Products– Are normally produced internally – No purchasing views exist
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
24
Additional Material Type
• HIBE: Operating Supplies• VERP: Customer returnable packaging• LEER: Empty containers• KMAT: Configurable material• ERSA: Spare parts • DIEN: Services
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
25
Material Master Views
• Basic data • Classification • Sales: sales organization data• Sales: general/plant data• Sales text• Purchasing• Purchase order text• Forecasting
Purchasing
View MRP 1View
Executive Pen
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
26
Material Master Views (continued)
• MRP 1, 2 • Work scheduling • Storage• Warehouse management• Quality management• Accounting• Costing
Purchasing
View MRP 1View
Executive Pen
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
27
Material Master Forecasting
• Number of Periods Required– Historical Periods
• The number of historical values the system uses for the forecast– Forecast Periods
• Number of period splits for which a forecast should be created
• Forecast Values– The numeric quantity for future periods
• Consumption Values– The sum of planned and unplanned consumption
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
28
Material Master MRP 1
• General Data– Purchasing Group
• The buyer(s) who are responsible for certain purchasing activities
• MRP Procedures– MRP Type
• Determines whether and how the material is planned– Reorder Point
• If stock falls below this point, the system is flagged to create a planned order
– MRP Controller• The person(s) responsible for the material planning
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
29
Material Master MRP 1 (cont.)
• Lot Size Data– Lot Size
• The lot sizing procedure to calculate the quantity to be produced or procured
– Minimum Lot Size• The smallest order quantity
– Fixed Lot Size• The quantity to be ordered
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
30
Material Master MRP 2
• Scheduling– Planned Delivery Time
• Number of calendar days needed to obtain the material– Scheduling Margin Key
• Used to determine the floats required for scheduling
• Net Requirement Calculation– Safety Stock
• Specifies the quantity whose purpose is to satisfy unexpectedly high demand in the coverage period
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
31
Material Master MRP 3
• Availability Check– Specifies whether and how the system checks
availability and generates requirements for materials planning
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
32
Production oriented Master data
• Bill of Material Master Data• Work Center Master Data• Work Center Control Key• Routing• Routing Use• Material Types and Production• Controlling Activities For Production• Activity Prices
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
33
Bill of Material Master Data
• Bill of Materials (BOM’s) are created as single-level relationships between one parent material and the sub-component material
EPEN
Barrel Cap Crown Cartridge Band Clip
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
34
Bill of Material Master Data
• Variant Bill of Material (BOM)– Several products with a large proportion of identical
parts.
EPEN - Red
RedCartridge
Band Etc.Black
CartridgeBand Etc.
EPEN - Black
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
35
Bill of Material Master Data
• Multiple Bill Of Materials (BOM)– One product produced from alternative components
or processes, where the differences are small (usually the quantity of a component).
– BOM 1 = lot size 1 - 100– BOM 2 = lot size 101 – 999
BlackCartridge
(Make)
BandEtc.
EPEN - Black
BlackCartridge
(Buy)
Band Etc.
EPEN - Black
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
36
Bill of Material Master Data
• Where is the Bill Of Material (BOM) used?– MRP uses the BOM to determine dependent
requirements– Controlling uses the Bill Of Material (BOM) to calculate
product costs– Production uses the Bill Of Material (BOM) to issue the
proper quantities of components and raw materials to the shop floor
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
37
Work Center Master Data
• Unique production or assembly area• May include
– Equipment – Groups of equipment– Production lines– Employees– Groups of employees
• Operations carried out at work center
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
38
Work Center Master Data
• Work center used to define capacities – Labor– Machine– Output– Emissions
• Capacities used in– Capacity requirements planning (CRP)
• Detailed scheduling• Costing
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
39
Work Center Master Data
• Assigned– Cost center
• Work Center only assigned to one cost center
– Human Resources (HR)• Qualifications• Positions• People
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
40
Work Center
• Work Centers have multiple views– Basic data– Default values– Capacity overview– Scheduling– Cost center assignment– Technical data
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
41
Work Center Control Key
• Scheduling• Determine capacity requirements• Inspection characteristics required• Automatic goods receipt by operation• Print time tickets & confirmations• Rework• Cost• Schedule external operations – std values• Confirmations
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
42
Routing
• Routings enable you to plan the production of materials
• Routings are used as a template for production orders and run schedules as well as a basis for product costing.
• Routing is a sequence of operations which detail the manufacture of a product
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
43
Routing
• Routing are used to determine:– Operations– Work centers– Material components – Production resources and tools– Quality Checks
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
44
Routing Use
• Routings will be used in– Scheduling (dates, times)– Costing– Capacity planning– Production orders
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
45
Routing
StandardSequence
AlternateSequence
ParallelSequence
Operation 10
Operation 20
Operation 30
Operation 40
Operation 10
Operation 20
Operation 30
Operation 40
Operation 25
Operation 20
Operation 10
Operation 30
Operation 40
Operation 25
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
46
Material Types Allowed In Production
• Multiple material types may be used in a routing/BOM– Raw materials– Semi-finished product– Trading goods are allowed but not standard– Text or Reference materials common
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
47
Display Routing List
• A collective report displaying the available routings and the material allocations to operations
• Four General Types– Operations Related– Component Related– PRT Related– General List (Operation Control Ticket)
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
48
Controlling Activities for Production
• Used to perform internal cost allocation, where activities by a cost center are measured– Labor time– Machine hours
• Output activities are valued• Allocation of an activity type is always made with
the allocation cost element created in activity type planning
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
49
Activity Prices
• Prices (costs) for planned activities– Fixed or Variable
• Labor = $$/hour• Machine = $/hour• Overhead = %
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
50
Transaction Data
• Includes transactions that describe business activities
• Unlike master data, aggregate transactional data is dynamic - it constantly changes, usually many times per day
• Transactions use organizational structure, master data, and rules
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
51
Scheduleand Release
Shop FloorDocuments
Goods Receipt
Order Settlement
GoodsIssue
ProductionProposal
(Planning/Other)
CompletionConfirmation
Capacity Planning
Production Process (Make-to-Stock)
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
52
Production Order
• Production Order Defines– Material is to be processed– At what location (work center)– At what time– How much work is required– Resources to be used– Order costs settlement
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
53
Production Order Standard Process
• Documents/Procedures used in the manufacture of material
– Order creation/Order Conversion– Capacity planning– Order scheduling– Order release/processing– Shop floor documents– Completion confirmation– Goods receipts– Order settlement
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
54
Production Order Release
• When a production order is created the following actions are carried out:– A routing selected: operations and sequences– The bill of materials transferred– Reservations generated for bill of material items in stock
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
55
Production Order Release (cont.)
• When a production order is created the following actions are carried out:– The planned costs are generated– The capacity requirements generated for the work centers– Purchase requisitions generated for non-stock items and externally-
processed operations
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
56
Production Order Elements
• Order header– Order number– Material produced– Plant– Quantity– Dates
• PRT– Tooling– Equipment
• Operations– Tasks – Work centers– Times– Dates– Control keys
• Components– Material components– Quantity
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
57
Production Order Completion and Settlement
• Completion confirmation – Quantities of material
used– Operations completed– Time– Personnel
• Costs – Planned costs and
actual costs
• Settlement rule for the order for accounts/cost centers– Settlement profile– Settlement receiver
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
58
Production Order Completions
• Completion confirmation:– Confirms both the yield and scrap quantities– Backflushing
• Can create goods movements • Reduction of component reservations
– Receipt of product if automatic Goods Receipt (G/R) set– Activity costs
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
59
Production Order Costs
• Planned costs– Primary Costs
• Material Costs (BOM)– Based on material master price for each component
• Cost for External Processing
– Secondary Cost• Production Costs (Routing)• Material Overhead Costs• Production Overhead Costs
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
60
Production Order Costs
• Actual costs– Primary Costs
• BOM components– Updated when goods are issued to order, or when purchased
materials are received
– Secondary Costs• Uses routing
– Time Cards from Operations
• May include activity costs• Material Overhead Costs• Production Overhead Costs
• Gets updated at completion confirmation
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
61
Production Order Status
• REL: Released• CRTD: Created• PRT: Printed• CNF: Confirmed• DLV: Delivered• PRC: Pre-costed
• GMPS: Goods movement
posted• MACM: Material
Committed• MANC: Mat.
Availability not checked
• NTUP:Dates are not updated
• SETC:Settlement rule created
January 2008 © SAP AG - University Alliances and The Rushmore Group, LLC 2007. All rights reserved.
62
Sales Order Process
Sales OrderEntry
Check Availability
ProductionProcess
Run MPS w/MRP
Convert ProductionProposal
Scheduleand Release
ProcurementProcess
Pick Materials
GoodsIssue
Purchase Requisition
Purchase Order
GoodsReceipt
InvoiceReceipt
Paymentto Vendor
CompletionConfirmation
Goods Receipt
QualityInspection
Order Settlement
Post Goods Issue
Invoice Customer
Receipt ofPayment
Overall Process