Production Planning. Devaki Nadkarni. Decision Level. Decision Process. Forecasts needed. Allocates production among plants. Annual demand by item and by region. Corporate. Determines seasonal plan by product type. Monthly demand for 15 months by product type. Plant manager. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/1.jpg)
Production Planning
Devaki Nadkarni
![Page 2: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/2.jpg)
Production Planning
Annual demand byitem and by region
Monthly demandfor 15 months by
product type
Monthly demandfor 5 months by
item
Forecasts needed
Allocatesproduction
among plants
Determinesseasonal plan by
product type
Determines monthlyitem production
schedules
Decision ProcessDecision Level
Corporate
Plant manager
Shopsuperintendent
![Page 3: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/3.jpg)
Objectives of Production Planning
• To deliver quality goods in required quantities to the customer in the required delivery schedule – to achieve maximum customer satisfaction and minimum possible cost.
• To ensure maximum utilization of all resources.• To ensure production of quality products.• To minimize the product through-put time of
production/manufacturing cycle time.• To maintain optimum inventory level.• To maintain flexibility in manufacturing operations.• To co-ordinate between labour and machines and various
supporting departments.
![Page 4: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/4.jpg)
4
Production Planning Horizons
Master Production Scheduling
Production Planning and Control Systems
Pond DrainingSystems
Aggregate Planning
PushSystems (MRP)
PullSystems (JIT)
Focusing onBottlenecks
Long-Range Capacity Planning Long-Range(years)
Medium-Range(6-18 months)
Short-Range(weeks)
Very-Short-Range(hours - days)
![Page 5: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/5.jpg)
5
Production Planning: Units of Measure
Master Production Scheduling
Production Planning and Control Systems
Pond DrainingSystems
Aggregate Planning
PushSystems
PullSystems
Focusing onBottlenecks
Long-Range Capacity Planning Entire Product Line
ProductFamily
SpecificProduct Model
Labor, Materials,Machines
![Page 6: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/6.jpg)
Aggregate PlanningAggregate planning involves planning the best quantity
to produce during time periods in the intermediate-range horizon (often 3 months to 18 months) and planning the lowest cost method of providing the adjustable capacity to accommodate production requirements.
• It facilitates fully loaded facilities and minimizes overloading and under loading and keeps production cost low.
• Adequate production capacity is provided to meet expected aggregate demand.
• To manage change in production/ operations management by planning for production resources that adapt to the changes in customer demands.
![Page 7: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/7.jpg)
Market Environment
Forecast and customer order
Resource base and
technology
Capacity (facilities, material, labour and
capital)
Aggregate Production Plan
Master Production Schedule
Material Requirements
Capacity Requirements
Flowchart of Aggregate plan and Master Production Schedule
![Page 8: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/8.jpg)
Steps in Aggregate Capacity Planning• Prepare the sales forecast for each product
that indicates the quantities to be sold in each time period.
• Sum up the individual forecast into one aggregate demand.
• Transform the aggregate demand for each time period into labour, materials, machines and other elements of production capacity required to satisfy aggregate demand.
• Develop alternative resource schemes for supplying the necessary production to support the cumulative aggregate demand and choose the best that meets the objectives of the organisation.
![Page 9: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/9.jpg)
Master Production Scheduling
The master production scheduling sets the quantity of each end item(finished product) to be completed in each time period of the short range planning horizon.
Objectives:1. To schedule end items to be completed
promptly and when promised to customers.2. To avoid overloading or under-loading the
production facility so that production facility is efficiently utilized at the optimum cost.
![Page 10: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/10.jpg)
Functions of Master Production Schedule
• Translating aggregate plans into specific end items.
• Evaluating alternative schedules.• Generating material requirements.• Generating capacity requirements.• Facilitating information processing.• Maintaining valid priorities.• Utilizing capacity effectively.
![Page 11: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/11.jpg)
The elements of MPS:1. Demand management.2. Lot sizing.3. No. of products to be scheduled(product-
mix).Symptoms of poorly designed MPS:4. Overloaded facilities5. Under-loaded facilities6. Excessive inventory levels on some end
items and frequent stock out on others.7. Unrealistic schedules that production
personnel do not follow.8. Unreliable delivery promises to customers.9. Excessive expediting or follow-up.
![Page 12: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/12.jpg)
Capacity Requirement PlanningCapacity Requirement Planning is a techniques
for determining what labour/personnel and equipment capacities are needed to meet the production objectives.
It involves activities such as • Assessing existing capacity and forecasting
future capacity needs• Identifying alternative ways to modify capacity• Evaluating financial, economical and
technological capacity alternatives to avoid bottlenecks.
• Plan capacity to achieve the production schedule
![Page 13: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/13.jpg)
Material Requirements Planning (MRP)
Material Requirements Planning (MRP) is a system for planning the future
requirements of dependent demand items.
![Page 14: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/14.jpg)
Material Requirements Planning
Functions:• Order planning and control.• Priority planning and control.• Provision of a basis for planning capacity
requirements and development of broad business plans.
Successful implementation of MRP results into reduced levels of average inventory, optimum utilisation of human and capital resources, workforce planning, improved vendor relations, better capital investment decisions, reduced delivery lead times.
![Page 15: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/15.jpg)
Make or Buy Decision
Considerations• Economic considerations.• Non economic considerations
Availability of supply and alternative sources of supply for components and sub-units.
Control of trade secrets and design secrets.Quality and reliability considerations.Delivery schedules to be met.Reliability of supply of external suppliers.Availability of manufacturing capacity (in-house)
![Page 16: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/16.jpg)
A
Independent Demand Items
B(4) C(2)
D(2) E(1) D(3) F(2)
Dependent DemandItems
Independent vs. Dependent Demand
![Page 17: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/17.jpg)
Production Planning Hierarchy
Firm orders from knowncustomers
Forecast of demand
from random customers
Aggregate Product Plan
Master Production Schedule
(MPS)
Material Requirements
Planning (MRP)
Engineering design changes
Bill of Materials (BOM) file
Inventory transactions
Inventory records
file
Reports
![Page 18: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/18.jpg)
Materials Requirements Planning (MRP)
![Page 19: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/19.jpg)
Materials Requirements Planning (MRP)
• Computer based system• Explodes Master Schedule (MPS) into
required amounts of raw materials and subassemblies to support MPS
• Nets against current orders and inventories to develop production and purchased material ordering schedules
![Page 20: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/20.jpg)
Material Requirements Planning
• How much of an item is needed?
• When is an item needed to complete– a specified number of units...– in a specified period of time?
• Dependent demand drives MRP
![Page 21: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/21.jpg)
Objectives of MRP
• Improve customer service• Reduce inventory investment• Improve plant operating efficiency
![Page 22: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/22.jpg)
MRP Computer Program
• Begins with number of end items needed• Add service parts not included in MPS• Explode MPS into gross requirements by
consulting bill of materials file• Modify gross requirements to get net
requirements:• Net Requirements = Gross Requirements
+ Allocated Inventory+ Safety Stock
- Inventory On Hand• Offset orders to allow for lead time
![Page 23: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/23.jpg)
Outputs of MRP
• Planned order schedule - quantity of material to be ordered in each time period
• Changes to planned orders - modifications to previous planned orders
• Secondary outputs:– Exception reports – Performance reports– Planning reports
![Page 24: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/24.jpg)
More MRP Terminology• Gross Requirements
–These requirements are typically forecast for independent demand items
–Today’s trend is to replace forecasts with blanket orders in order to reduce variability and shorten lead-time
–The customer is offered a price discount for placing blanket orders
![Page 25: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/25.jpg)
More MRP Terminology• On-hand inventory
– The inventory physically present in the facility
• Allocated inventory – The inventory physically present in the facility
but allocated to a particular work order or purchase order
![Page 26: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/26.jpg)
More MRP Terminology
• Net requirements–A quantity of an item that must be purchased or
manufactured in order to be able to fully deliver independent demand requirements in a timely fashion
–Presence of positive net requirements signals that an order must be planned to be received in a given period
–Net requirement quantities are subject to adjustments due to lot sizes considerations. This may lead to some orders being received early (inventory is held) or late (order backlog)
![Page 27: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/27.jpg)
More MRP Terminology• Planned order released
– Quantities that must be planned to be released in some future periods in order to meet the requirements
![Page 28: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/28.jpg)
More MRP Terminology• Scheduled receipts
– Quantities that will be received in some future periods as their corresponding orders have been released in the past • Planned order receipts become scheduled receipts
at the time when they are released to the shop or to suppliers
![Page 29: Production Planning](https://reader035.vdocuments.us/reader035/viewer/2022062811/56816140550346895dd0ad0a/html5/thumbnails/29.jpg)
More MRP Terminology
• Gross to Net logic:
Net Requirements = Gross Requirements + Allocated Inventory + Safety Stock
- Inventory On Hand