production and performance of srf cavities for the...

36
FNAL AP&T Seminar 052411 cer Production and Performance of SRF Cavities for the CEBAF 12 GeV Upgrade and JLab SRF Facilities Upgrade Plans C. Reece

Upload: others

Post on 27-Jun-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

FNAL AP&T Seminar 052411 cer

Production and Performance of SRF Cavities for the CEBAF 12 GeV Upgrade

and JLab SRF Facilities Upgrade Plans

C. Reece

Page 2: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

12 GeV Upgrade Cavities

• Project context• Requirements

• Production process• Sequence and key details

• EP illustration

• VTA test data

• Project status

• Plan for balance of project

Slide 2FNAL AP&T Seminar 052411 cer

Page 3: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

CEBAF 12 GeV Upgrade

6 GeV CEBAF11

CHL-2

12 Upgrade magnets and power supplies

First two cryomodules - installation summer 2011Eight more CMs in 2012

FNAL AP&T Seminar 052411 cer

Page 4: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

Key Project Parameters

New cryomodules : 10Voltage per cryomodule: ≥ 108 MV avg.Cavities per cryomodule: 8Heat budget:

• @ 2.07 K ≤ 300 W / CM• ≤ 29 W / cavity, avg.

Cavity: 1.497 GHz0.7 m “Low loss” cell shape

Higher order mode damping: • Transverse (R/Q)Qk < 2.4 x 1010 Ω/m • Longitudinal (R/Q)Q < 6.5 x 1011 Ω

Slide 4FNAL AP&T Seminar 052411 cer

Page 5: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

12 GeV Upgrade Cavities• Production process

• 160 µm BCP and pre-tuned by vendor• Receipt inspection – mechanical and rf• US >> Bake: 600 C, 10 hrs• US >> EP: 30 µm, @20°C regulated by external water spray• US >> Tune• Helium vessel welding• Flange lapping• HPR• Partial assembly• HPR >> dry in Class 10 cleanroom• Final assembly, leak check• Bake: 120 C, 24 hrs• Vertical test @ 2.07 K• HPR >> dry in Class 10• String assembly

Slide 5FNAL AP&T Seminar 052411 cer

Page 6: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

12 GeV Upgrade Cavities• Improved EP process is now standardized and controlled

Slide 7

Exploiting New Electrochemical Understanding of Niobium Electropolishing for Improved Performance of SRF Cavities for CEBAFC. E. Reece and H. Tian, LINAC10 THP010

FNAL AP&T Seminar 052411 cer

Page 7: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

In-house fabricated pre-production cavities

Slide 8

Critical Dipole Modes in JLab Upgrade CavitiesF. Marhauser et al. LINAC10 THP009

FNAL AP&T Seminar 052411 cer

Page 8: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

State-of-the-art production SRF cavity

Q is BCS-limitedSlide 9FNAL AP&T Seminar 052411 cer

Page 9: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

State-of-the-art production SRF cavity

Q is BCS-limitedSlide 10

♥Project specification

FNAL AP&T Seminar 052411 cer

Page 10: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

12 GeV Upgrade Cavities• Project specification: 19.2 MV/m average, with 29 W avg. heat• Operational limit in CEBAF, RF power: 25 MV/m• Project conservatism for first two CMs:

• To avoid any potential risk of degradation from “pushing,”• Limiting vertical cavity acceptance testing to 27 MV/m• (rather frustrating to us cavity people who look into the future)

• Vertical rf test only after HV attached• Piping size limits heat load to ~70 watts @ 2.07 K

Slide 11FNAL AP&T Seminar 052411 cer

Page 11: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

0

5

10

15

20

25

30

35

40

45

C100

-RI-0

01

C100

-RI-0

02

C100

-RI-0

03

C100

-RI-0

04

C100

-RI-0

05

C100

-RI-0

06

C100

-RI-0

08

C100

-RI-0

06

C100

-RI-0

10

C100

-RI-0

12

C100

-RI-0

07

C100

-RI-0

11

C100

-RI -0

14

C100

-RI-0

15

C100

-RI-0

13

C100

_RI_

018

C100

-RI-0

19

C100

-RI-0

17

C100

-RI-0

20

C100

-RI-0

21

C100

-RI-0

22

C100

-RI-0

23

C100

-RI-0

25

C100

-RI-0

28

C100

-RI-0

29

C100

-RI-0

30

C100

-RI-0

31

C100

-RI-0

34

C100

-RI-0

32

C100

-RI-0

27

C100

-RI-0

33

C100

-RI-0

35

Gacc(MV/m)

12 GeV Upgrade Production CavitiesAcceptance Test Maximum Gradient

Administrative limit @ 27 MV/m

Project Specification 19.2 MV/m avg.

HPR wand accidental damage

9/23/2010 - 5/3/2011

Slide 12FNAL AP&T Seminar 052411 cer

12 GeV project cavities

w/ and w/o HV

Page 12: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

JLab CEBAF Upgrade Cavities - May 2011• C100 cavity – production system is running

• 84/86 cavities received

• 50/86 cavities EP’d (2/wk)

• 31/86 cavities VTA tested

• 30/86 cavities qualified in HV (1 damaged)

• 16/80 cavities = 2/10 strings completed, ready for #3

• Procedure suite established and tracked

• No SRF performance issues currently open

• Found weak spec on SS helium vessel material

• High permeability, degraded cavity Q

• Found early, material replaced

• Issue was resolved quickly

• Analyzing microphonic sensitivity in CM – (no stiffening rings)

Slide 13FNAL AP&T Seminar 052411 cer

Page 13: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

12 GeV Upgrade Cavities• Production cavity tracking screen

Slide 14FNAL AP&T Seminar 052411 cer

Page 14: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

JLab SRF Cavity Team - 2011

(B. Carpenter, T. Reilly, F. Marhauser, and R. Geng missing)Slide 15FNAL AP&T Seminar 052411 cer

Page 15: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

12 GeV Upgrade Cryomodule

Slide 16

First cavity string

Installation of super-insulation on upgrade cryomodule

FNAL AP&T Seminar 052411 cer

Page 16: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

“C100” cryomodule assembly and testing

FNAL AP&T Seminar 052411 cer

Cavity string with He piping

R100 cryomodule in test cave

Page 17: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

R100 Cryomodule Performance

FNAL AP&T Seminar 052411 cer

Static 2 K load: 22 WStatic 40 K shield load: 240 WIn-house fabricated upgrade-style cavities

Preliminary

2.07 K

Page 18: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

Baseline Work Plan Coordinated with TEDF

Now

6-Month Down

12-Month Down

Cryomodule Installation & CommissioningSRF Facility Downs

Slide 19FNAL AP&T Seminar 052411 cer

Page 19: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

JLab SRF Facilities Upgrade Plans

TEDF Project • Technology and Engineering Development Facility

• Motivations

• Overview

• SRF facility changes

• Overview

• Attention to chemical processing

• Photo album

Slide 20FNAL AP&T Seminar 052411 cer

Page 20: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

TEDF Project

Test Lab Renovation

Test Lab AdditionTED Building

Slide 21FNAL AP&T Seminar 052411 cer

Page 21: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

TEDF Project

• Department of Energy – “Science Laboratory Infrastructure” Project

• Investment in facilities for:

• Improved energy efficiency

• Improved life-safety code compliance

• Improved work-flow efficiency

• Improved facility sustainability

• Improved human work environment

• Improved technical quality of facilities for future work

• Increased build-out capacity

• Will provide new home for JLab orgs:• SRF Institute

• Engineering division

• Physics instrumentation groups

Slide 22FNAL AP&T Seminar 052411 cer

Page 22: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

TEDF• Pro

Slide 23FNAL AP&T Seminar 052411 cer

Page 23: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

TEDF• Pro

Slide 24FNAL AP&T Seminar 052411 cer

Page 24: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

Slide 25

TEDF

75 m

40 m

Present SRF Facilities

New SRF Facilities

FNAL AP&T Seminar 052411 cer

Page 25: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

SRF Facilities in JLab TEDFChemistry, cavity treatments, and support areas

Cavity and cryomodule cryo/RF testing

R&D

Cleanroom

Cryomodule assembly

Fabrication

SRF Facilities in TEDF ProjectAdvanced Conceptual Design 4/1/09

New

Page 26: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

Cavity testing – (VTA)

FNAL AP&T Seminar 052411 cer

April VTA activity

>3440 test cycles and counting…27 different styles of multi-cell cavities + uncounted single cells

Cryogenic supply system recently upgraded with help from FNAL ARRA “through-put” improvement contribution.Speeds fill and increases LHe draw capacity - thanks

VTA will survive the renovation with expanded staging area, otherwise unchanged.

Page 27: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

TEDF Infrastructure Design30,000 sf – new

Cavity fabrication (presses, EBW…)RF structure developmentProcess developmentQC/ InspectionClean analytical labProduction chemroomR&D chemroomFlexible ISO 4 cleanroom suiteDedicated CEBAF-support CM

assembly linesExpansion space for other DOE

project support

Slide 28FNAL AP&T Seminar 052411 cer

Page 28: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

IPC

BCP

HPR

US

EP

Dry

ICP (Integrated Cavity Processing) tool concept will integrate multiple process steps with minimum handling in new TEDF facilities

Other

Slide 29FNAL AP&T Seminar 052411 cer

Page 29: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

TEDF Infrastructure DesignIntegration of cleanroom/chem processing/waste collection

Architectural elevation through process support area

Slide 31FNAL AP&T Seminar 052411 cer

Page 30: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

TEDF Project PhasingPhase 1:Construct TED Bldg & Test Lab Addition

Phase 2:Prep Bldg 58 for Shutdown

Phase 3:Renovate Bldg 58

Phase 4:Restore TED Bldg for Final Occupancy

17Slide 32FNAL AP&T Seminar 052411 cer

Page 31: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

TEDF Summer 2010

Slide 33FNAL AP&T Seminar 052411 cer

Page 32: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

TEDF Feb 2011

Slide 34FNAL AP&T Seminar 052411 cer

Page 33: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

TEDF April 2011

Slide 35FNAL AP&T Seminar 052411 cer

Demolition of Acid Transfer building

Commissioning of new Process Support Building (PSB)

Page 34: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

TEDF May 2011

Slide 36FNAL AP&T Seminar 052411 cer

Page 35: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

TEDF Project Schedule

Slide 37FNAL AP&T Seminar 052411 cer

Page 36: Production and Performance of SRF Cavities for the …beamdocs.fnal.gov/AD/DocDB/0038/003873/001/Reece FNAL...HPR wand accidental damage 9/23/2010 -5/3/2011 Slide 12 FNAL AP&T Seminar

Ante-TEDF (First JLab cavity processing facility– 1988)

Slide 38

Progress continues …

FNAL AP&T Seminar 052411 cer