procurement system

16

Click here to load reader

Upload: syed-kashif-ali

Post on 21-Jun-2015

327 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Procurement system

Procurement Systems

“The organisational structure adopted by the client for the management of the design and construction of a building project”

Masterman, An introduction to building procurement systems.

PROCUREMENT OPTIONS

Page 2: Procurement system

The need for different procurement routes

Differing project objectives

Time, Cost and Quality aims

Differing clients

Degree of involvement, risk attitudes, experience

Operating in a changing environment

Political, economic, legal etc…

No single route will suit all circumstances

PROCUREMENT OPTIONS

Page 3: Procurement system

The key variables in the procurement process

Design control

Who employs/directs the designers?

Usually a choice between client & contractor

Constructors’ involvement

When do you employ the contractors?

Usual choice is between when outline design is complete or when design is finally complete

Contract to construct or to manage construction?

Who employs the subcontractors?

PROCUREMENT OPTIONS

Page 4: Procurement system

The key variables in the procurement process

Team selection

Competition or negotiation for selection?

Open or selected tendering?

Paying for the construction

Pay on “Price” or “Cost”?

Price – contractor tenders to do work for a total amount = estimated costs + profit + overheads +/- risk adjustments

Cost – contractor tenders to do the work for actual costs (calculated as work proceeds) + allowance for profit etc…

Pay in timed instalments or on completion of stages?

PROCUREMENT OPTIONS

Page 5: Procurement system

The key variables in the procurement process

Form of contract used

Contracts specify obligations of parties to one another – client & designers, client & contractor, contractor & subcontractor etc…

Main variation in client/contractor contract

Main choice influenced by basic procurement route used

“Standard” forms exist for most routes e.g. JCT Forms

Modification of contracts is common to suit “strong” party’s requirements

PROCUREMENT OPTIONS

Page 6: Procurement system

The available routes

The range of options

In excess of 100 recognised variants

In fact permutations are infinite

Better to treat options as lying on continuous spectra of the procurement variables

The most common routes

Four systems dominated the UK industry in recent times

Traditional, Design & Build, Management Contracting & Construction Management

PROCUREMENT OPTIONS

Page 7: Procurement system

The “Traditional” or conventional route

The process

Client employs designers to produce complete design

Contractor tenders on PRICE after design complete

Tenders sought typically on competitive, selected basis

Often lowest price wins

Winning contractor carries out construction through employed sub-contractors

Client pays price in monthly instalments based on amount of work done

PROCUREMENT OPTIONS

Page 8: Procurement system

The “Traditional” or conventional route

Advantages

Client retains good control of design process

Widely used - all parties understand roles etc…

Fairly even split of financial risk between main parties

Cost “certain” after tender and tenders easily comparable

Disadvantages

Slow because design and construction sequential

Contractor’s expertise not used in design

Creates “sides” – potential for adversarial attitudes, conflict

PROCUREMENT OPTIONS

Page 9: Procurement system

The “Traditional” or conventional route

Variants

Subcontractors may be “nominated” – specified by client – potential for divided loyalties, blurs responsibilities

“Accelerated” – tenders sought on outline design – may be quicker but cost certainty lost, time pressures on design etc

PROCUREMENT OPTIONS

Page 10: Procurement system

The design & build route

The process

Client employs designers to produce outline design

Contractor tenders PRICE to complete design and perform construction

Tendering usually competitive & selected & best “overall submission” should win – price, design, programme etc…

Winning contractor carries out design and construction through employed design consultants and sub-contractors

Client pays price in monthly instalments as traditional

Significant shift in risk to contractor c.f. Traditional

PROCUREMENT OPTIONS

Page 11: Procurement system

The design & build route

Advantages

Design & construction overlapped – rapid procurement

Contractor’s expertise influences design – cost savings

Early cost “certainty” possible

Client has single point of contact with team

Disadvantages

Client relinquishes control over design – quality problems?

Client changes difficult after contract let

Adversarial attitudes remain, perhaps worse than traditional

PROCUREMENT OPTIONS

Page 12: Procurement system

The design & build route

Variants

Client may require contractor to employ same design team as client employed – “Novation” – potential conflict of interest, blurs responsibility, authority etc…

Tenders may be sought on “Guaranteed Maximum Price” basis – redistributes risk as savings may be split between parties. Arriving at the right “Maximum” is the key issue.

Most extreme form – “Package” or “Turnkey” – approach. Contractor provides full service – ALL design, even finding site, finance etc in some cases.

PROCUREMENT OPTIONS

Page 13: Procurement system

The management contracting route

The process

Client employs designers to produce outline design

Contractor tenders on estimated COST to perform construction + fee to manage process

Tendering usually competitive & selected

Best “overall submission” should win – fee, management, programme, track record etc…

Winning contractor joins team – advises designers in completion of design, organises construction in parallel by employing “works package contractors”

Client pays COST of packages + fee on monthly basis

PROCUREMENT OPTIONS

Page 14: Procurement system

The management contracting route

Advantages

Design & construction overlapped – rapid procurement

Contractor’s expertise influences design – cost savings

Contractor in team reduces adversarial nature of process

Client retains control of design

Late changes in design can be accommodated

Disadvantages

Client assumes high level of TCQ performance risk

Client involvement high

Possible time pressures on design

PROCUREMENT OPTIONS

Page 15: Procurement system

The construction management route

The process

Same as management contracting except that client employs each package contractor directly

Advantages

Client can exercise high degree of control over entire procurement process

Disadvantages

Client share of risk is even higher than MC

Client commitment/involvement is very high

PROCUREMENT OPTIONS

Page 16: Procurement system

Further reading

PROCUREMENT OPTIONS

Many texts give general descriptions of the procurement routes and associated contracts as part of coverage of the industry: e.g. Chapters 7 & 8 of Harvey & Ashworth, The construction industry of GB, Newnes and Chapter 6 of Cadman & Topping, Property development, Spon.

More detailed consideration of the routes can be found in: Masterman, An introduction to building procurement systems, Spon and Franks, Building procurement systems, Spon.

Murdoch & Hughes, Construction contracts – law and management, Spon.As its name suggests gives an in-depth coverage of the legal aspects and case law etc…