procurement benchmarking volume 1 final

Upload: faraz-bin-shamshad

Post on 03-Apr-2018

223 views

Category:

Documents


1 download

TRANSCRIPT

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    1/43

    INFRASTRUCTURE AUSTRALIA

    Eciencies inMajor Project Procurement

    Benchmarks for Ecient Procurement of Major Infrastructure

    June 2012

    VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    2/43

    Ownership of Intellectual Property Rights in this PublicationUnless otherwise noted, copyright (and any other intellectual property rights, if any) in this publication is owned by the Commonwealth of Australia(referred to below as the Commonwealth).

    Indemnity StatementInfrastructure Australia has taken due care in preparing this report. However, noting that data used for the analyses have been provided by thirdparties, the Commonwealth gives no warranty to the accuracy, reliability, tness for purpose, or otherwise of the information.

    Published byInfrastructure AustraliaGPO Box 594 Canberra ACT 2601 AUSTRALIA

    Telephone (international) +61 2 8114 1900www.infrastructureaustralia.gov.au

    ISBN: 978-1-921769-77-1

    (C) Commonwealth of Australia June 2012

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    3/43

    Contents

    1 Introduction........................................................................................................................................................................................................................ 4

    2 Procurement Objectives .............................................................................................................................................................................. 5

    3 Benchmarks....................................................................................................................................................................................................................... 6

    4 Time Benchmarks ................................................................................................................................................................................................... 7

    5 Quantitative Benchmarks ....................................................................................................................................................................... 10

    6 Qualitative Benchmarks ............................................................................................................................................................................ 12

    7 Recommendations.............................................................................................................................................................................................. 14

    Attachment 1Terminology........................................................................................................................................................................................................................... 15

    Attachment 2Contract Models ........................................................................................................................................................................................................... 18

    Public Private Partnership (PPP) ..................................................................................................................................................................... 19

    Design and Construct (D&C) ............................................................................................................................................................................. 21

    Alliance ................................................................................................................................................................................................................................... 22

    Attachment 3

    Schedule of Enabling Actions for Qualitative Benchmarks .............................................................. 24

    Table 1: Time Benchmarks ..........................................................................................................................8

    Table 2: Quantitative Benchmarks ...........................................................................................................10

    Table 3: Qualitative Benchmarks ..............................................................................................................12

    Figure 1: Typical PPP Structure ................................................................................................................20

    Figure 2: Typical D&C Structure ...............................................................................................................21

    Figure 3: Typical Alliance Structure .........................................................................................................23

    Eciencies in Major Project Procurement | 3VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    4/43

    1 Introduction

    In December 2011, Infrastructure Australia initiated

    a consultative study to identify those measures

    which contribute to eciency in procurement of

    major infrastructure projects. Infrastructure Australia

    engaged Everything Infrastructure to develop, facili-

    tate and document the study. The terms of reference

    of the study were to:

    engage key Australian stakeholders to

    contribute to the study;

    review the contributions against international

    experience;

    direct the study at the Public Private

    Partnership (PPP), Design and Construct (D&C)

    and Alliance contract delivery models;

    not specically address business case, needs

    analysis, contract packaging and/or contract

    model selection, on the basis that these

    activities are undertaken separately to the

    procurement processes (which are the subject

    of this study); and

    identify benchmarks for best practice in major

    infrastructure procurement.

    This Volume of the Report identies the eciency

    benchmarks for best practice procurement derived

    from the consultation and analysis. Volume Two of

    the Report, Efciencies in Procurement of Major

    Infrastructure Consultation Outcomes Report, docu-

    ments the outcomes of the consultative process, the

    subsequent analysis and the review of contributions.

    There is some variability (between the various

    Australian jurisdictions) in the use of terminology

    in respect of major infrastructure procurement

    across the various Australian jurisdictions. Particular

    terminology used for the purposes of this study is

    included inAttachment 1.

    The terms of reference for the study identied three

    contract models:

    Public Private Partnership (PPP);

    Design and Construct (D&C); and Alliance.

    The contract models are more particularly described

    inAttachment 2.

    A fundamental characteristic of major infrastructure

    is the signicant costs, eort and business impact to

    potential proponents and proponents to participate

    in the procurement process. The key objective of

    the benchmarking in this paper is to consider those

    costs and impacts in the context of delivery of the

    procurement objectives.

    | Eciencies in Major Project Procurement4 VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    5/43

    2 Procurement Objectives

    In simple terms, the overall objective of major

    infrastructure project procurement is to execute a

    contract with a proponent which satises the project

    requirements and is most likely to deliver best value,

    while utilising processes which comply with relevant

    policy. Eciency in procurement seeks to optimise

    the balance between the various inputs and the

    certainty of delivery of project outcomes. The pro-

    ponents eort and incurred costs thus are balanced

    against the benets to the sponsor (for example, the

    relevant Government Agency).

    To deliver eciency in procurement, further particular

    objectives have been identied. The particular e-

    ciency objectives are that the procurement process:

    enables potential proponents to eectively

    engage and participate in the procurement

    process;

    reasonably minimises the eort required of

    potential proponents to participate in the

    procurement process;

    optimises the eort of the sponsor agencyand other agencies to support the procure-

    ment process;

    optimises the potential for proponents to

    develop and submit proposals which are most

    likely to deliver best value; and

    captures the value of the selected proposal in

    the contract with the successful proponent.

    Eciencies in Major Project Procurement | 5VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    6/43

    3 Benchmarks

    In respect of the above ecient procurement

    process objectives, benchmarks have been identi-

    ed (in consultation with infrastructure industry

    stakeholders) which represent best practice. The

    benchmarks consist of:

    time benchmarks;

    quantitative benchmarks; and

    qualitative benchmarks.

    The time benchmarks identied in this paper

    represent prescribed durations which provide theappropriate opportunity stakeholders to undertake

    particular functions while not causing unneces-

    sary delay (and extra costs) to other stakeholders,

    particularly to proponents or potential proponents.

    Time benchmarks are readily identied and readily

    measured. The time benchmarks are detailed in

    Section 4 of this paper.

    The consultative process relating to quantitative

    benchmarks involved the identication of numerical

    targets, generally involving event frequencies, event

    precedents and proponent costs. Event frequency

    and precedent quantitative benchmarks are detailedin Section 5 of this paper.

    In the case of proponent costs, the uncertainty

    of cost data, variations in method of measure -

    ment and the dierences in project circumstances

    signicantly limit the ecacy of numerous proponent

    cost comparisons and benchmarking in the context

    of this study. Consequently, proponent costs are

    expressed in qualitative terms and are consequently

    included in the collection of qualitative benchmarks.

    The qualitative benchmarks in this paper are

    somewhat more subjective in measurement than the

    time benchmarks and quantitative benchmarks. The

    qualitative benchmarks generally consist of outcomestatements, frequently relating to the character of an

    activity (such as the suciency of communication,

    the sensible minimisation of costs and eort or the

    completeness of planning). In the absence of abso-

    lute comparable measurements in respect of the

    qualitative benchmarks, various key process inputs,

    in the form of enabling actions, have been developed

    to assist assessment and improvement of these

    qualitative aspects of the procurement process. The

    qualitative benchmarks are detailed in Section 6 of

    this paper and the Schedules of Enabling Actions are

    included inAttachment 3.

    | Eciencies in Major Project Procurement6 VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    7/43

    4 Time Benchmarks

    The time benchmarks are expressed as a range in

    response to the dierences between more complex

    and less complex major infrastructure projects. For

    the purpose of the time benchmarks:

    more complex means a project value in

    excess of $1000M for D&C or over $2000M for

    PPP, generally requiring multiple participants

    and frequently incorporating specialist skills

    and/or involving international participants; and

    less complex means a project value in the

    order of $200M for D&C or Alliance or $1000Mfor PPP, with the necessary skills and capa-

    bility generally within single entity capability

    for Alliance and D&C and/or not particularly

    requiring international specialist participation.

    It was recognised that PPP projects valued at

    $2000M to $5000M are unique and require the

    development of particular market engagement and

    procurement processes in response to the specic

    Project circumstances.

    The time benchmarks are listed in Table 1 overleaf.

    Eciencies in Major Project Procurement | 7VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    8/43

    Table 1: Time Benchmarks

    Procurement

    Phase

    Benchmark

    Event Measure

    Time Benchmarks (weeks or months)

    D&C PPP Alliance

    More

    Complex

    Less

    Complex

    More

    Complex

    Less

    Complex

    More

    Complex

    Less

    Complex

    Procurement

    Phase

    Initial advance

    notice of project

    and market

    engagement.

    Months before

    issue of EOI12 6 24 9 12 6

    Commence the

    market interaction

    with specic

    notice of likely

    scope, value,

    roles, contract

    models andpackaging.

    Months before

    issue of EOI6 2 12 6 6 2

    Formal discus-

    sions, specic

    project details

    advised in terms

    of scope, contract

    models, risk,

    value, turnover,

    roles, timing,

    Agency objectives.

    Months before

    issue of EOI2 2 3 3 2 2

    EOI Phase EOI preparation

    Weeks from

    release of EOI

    document to

    submission ofEOI responses.

    6* 4* 8* 6* 4* 3*

    Evaluation of EOI

    responses

    Weeks

    duration3 3 4 3 3 3

    Alignment

    sessions and

    evaluation

    workshops

    Weeks

    durationN/A N/A N/A N/A 4 3

    Approval of evalu-

    ation outcomes

    Weeks from

    completion of

    evaluation to

    announcement

    of selectedrespondents.

    1 1 2 2 1 1

    Issue of Request

    for Price (RFP)

    documents.

    Weeks after

    announcement

    of EOI evalua-

    tion outcomes.

    4 2 4 2 4 2

    Note: * assumes effective engagement during Pre-Procurement Phase.

    ** maximum 34 weeks for unique complex PPP and subject to specic market feedback at the Pre-

    Procurement Phase.

    | Eciencies in Major Project Procurement8 VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    9/43

    Procurement

    Phase

    Benchmark

    Event Measure

    Time Benchmarks (weeks or months)

    D&C PPP Alliance

    More

    Complex

    Less

    Complex

    More

    Complex

    Less

    Complex

    More

    Complex

    Less

    Complex

    RFP PhaseDuration RFP

    period

    Weeks from

    issue of RFP

    documents to

    submission of

    proposals.

    12 to 16 8 to 12 24** 18** 12 8

    Duration of inter-

    active process.

    Weeks from

    issue of RFP.8 4 20 10 6 4

    Latest time for

    material changes

    (time, cost, risk)

    issued in addenda.

    Weeks before

    RFP close. 6 6 12 12 4 4

    Latest time for

    minor changes

    (clarication

    without material

    impacts) issued in

    addenda.

    Weeks before

    RFP close.4 4 9 8 2 2

    Latest issue of

    marked up project

    documents to

    proponents

    following specic

    early proponentsubmissions (i.e.

    Deed) during the

    RFP preparation.

    Weeks before

    RFP close.6 6 12 12 2 2

    Evaluation /

    Finalisation

    Phase

    Earliest technical

    submissions

    Weeks before

    RFP close.4 2 8 4 3 1

    Duration of

    evaluation

    Weeks from

    submission

    close to

    selection.

    6 4 12 8 4 2

    Duration ofnalisation

    Weeks (selec-

    tion to nal

    documentation)assuming all

    material issues

    are resolved.

    3 3 4 4 3 3

    Approval durationWeeks

    duration2 2 2 2 2 2

    Approval to

    nancial close

    Weeks

    durationN/A N/A 10 6 N/A N/A

    Eciencies in Major Project Procurement | 9VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    10/43

    5 Quantitative Benchmarks

    The quantitative benchmarks are expressed as a

    target frequency (or quantity) of the occurrence of

    particular events or as precedent events. The quanti-

    tative benchmarks are listed on Table 2 below.

    Table 2: Quantitative Benchmarks

    Benchmark Event Benchmark Precedent Benchmark Frequency/Quantity

    Divergences of planned procurement

    program from the time benchmarks in

    Table 1

    Nil, except as specically changed in

    response to market feedback.

    Completion of full procurement plan

    (see section 6 for more details of full

    procurement plan)

    Prior to announcing EOI invitations.

    Divergences of actual procurement

    program from planned procurement

    program

    Nil, except as specically changed in

    response to market feedback or from

    market issues outside the Agencys control.

    EOI response requirements for informa-

    tion relating to the project solution

    Nil, except as specically required in

    relation to o the shelf items or specic

    interface issues.

    Divergences from the information

    provided (during pre-procurement, EOI

    or RFP Phases) to potential proponents

    or proponents

    Nil, except as specically changed in

    response to market feedback or form

    market issues outside the Agencys control.

    Planned addenda for changes or for the

    issue of missing information during RFP

    Phase

    Nil

    Material changes to contract terms or

    scope during the RFP Phase

    Nil

    Number of proponents selected from

    the EOI process to participate in the RFP

    process

    2 for Alliance.

    Preferably 2 for PPP.

    No more than 3 for PPP or D&C.

    | Eciencies in Major Project Procurement10 VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    11/43

    Benchmark Event Benchmark Precedent Benchmark Frequency/Quantity

    RFP evaluation methodology complete Prior to RFP document issue.

    RFP evaluation plan complete Prior to Proposal submission.

    Number of proponents required to fully

    document their proposals during the

    Evaluation/Finalisation Phase

    Preferably 1, but no more than 2.

    Physical, contractual and agency

    interfaces resolvedPrior to RFP document issue.

    Commitment of proponents to RFP

    rules, including condentiality, probity

    and reliance on information

    Prior to issue of RFP documents to

    proponent.

    RFP requirements for project plans

    in excess of that which is specically

    required to address material Agency

    risks

    Nil

    RFP requirements for design in excess

    of that which represents material risk to

    the Agency

    Nil

    Eciencies in Major Project Procurement | 11VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    12/43

    6 Qualitative Benchmarks

    The qualitative benchmarks with supporting

    descriptions are listed on Table 3 below. Enabling

    actions which contribute to achievement of the

    qualitative benchmarks are detailed inAttachment

    3. Timing requirements in respect of the delivery of

    the qualitative benchmarks are included in the time

    benchmarks in Section 4 of this paper.

    Table 3: Qualitative Benchmarks

    Procurement Phase Qualitative Benchmark Benchmark Description

    Pre-Procurement PhaseCommunication of accurate and suf-

    cient Project Information.

    The communication fully informs potential

    Participants decisions and undertake plan-

    ning in the Pre-Procurement Phase.

    Comprehensive procurement planning is

    undertaken.

    Procurement planning fully addresses:

    the project scope and commercial

    arrangements;

    the procurement process;

    procurement resources;

    procurement risks and opportunities; stakeholder interfaces; and

    alignment with market capability and

    capacity.

    EOI Phase Clear and complete EOI documentation.

    The EOI documents fully address:

    Project requirements;

    Response requirements;

    Procurement process;

    issues aecting Responses; and

    Response evaluation.

    EOI requirements reasonably minimise

    respondents eort and cost.

    The EOI response requirements focus on:

    existing prequalication material

    predetermined minimum standards of

    experience and expertise;

    Proponents internal standard documen-

    tation; and

    only key dierentiating information.

    EOI process is undertaken in accor-

    dance with information issued.

    The EOI process has nil divergences from

    issued information, except as specically

    changed in response to market feedback

    or form market issues outside the Agencys

    control (as identied in quantitative

    benchmarks).

    | Eciencies in Major Project Procurement12 VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    13/43

    Procurement Phase Qualitative Benchmark Benchmark Description

    RFP Phase Clear and complete RFP documentation.

    The RFP documents require proponents to

    submit:

    only essential design elements whichrepresent material risks to the Agency;

    only essential statements of systems or

    methods (project plans) which represent

    material risks to the Agency;

    Responses structured to facilitate

    incorporation of proposal features into a

    Contract; and

    documentation only of essential

    Contract elements.

    Commercial Terms represent value for

    money.

    The design of the Commercial Terms

    incorporate to:

    precedent jurisdictional Contracts

    structure and terms;

    the contemporary evolution of Contractterms;

    precise mechanisms to deal with known

    uncertainties;

    precise and direct connection between

    performance and payment; and

    resolution of physical and contractual

    interfaces.

    RFP process is undertaken in

    accordance with information issued to

    proponents.

    RFP process has nil divergences, (as identi-

    ed in quantitative benchmarks).

    Evaluation / Finalisation PhaseEective and ecient evaluation of

    proposals.

    The evaluation fully addresses:

    assessment of the relative value of eachproposal;

    resolution of material uncertainties in

    respect of proposals; and

    in the case of the selected proposal,

    inclusion of the relative value and

    the resolution of uncertainty in the

    Contract.

    The evaluation / nalisation process

    reasonably minimises Proponents eort

    and costs.

    The evaluation / nalisation processes

    address:

    minimisation of response times;

    minimisation of legal eort for (ulti-

    mately) non-successful proponents;

    legal eort; and

    the early release or suspension of

    unsuccessful proponents.

    Evaluation / nalisation is undertaken in

    accordance with information issued.

    The evaluation / nalisation has nil

    divergences, (as identied in Quantitative

    Benchmarks).

    Eciencies in Major Project Procurement | 13VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    14/43

    7 Recommendations

    The benchmarks documented in this paper identify

    those aspects of Procurement processes where

    improvements in performance are expected to

    provide improvements in eciency. In terms of the

    priorities, it is recommended that Agencies:

    adhere to the time benchmarks in planning

    and execution of procurement;

    adhere to the precedents and target the speci-

    ed frequency/quantities in the quantitative

    benchmarks;

    implement guidelines relating to delivery of the

    qualitative benchmarks; and

    audit compliance of procurement planning and

    delivery with the benchmarks.

    In terms of future improvements to the benchmarks,

    it is recommended that:

    target limits of the extent of RFP design

    requirements be further analysed;

    details of standards relating to underwriting of

    PPP projects be further developed; and

    meaningful and reliable participant cost

    benchmarks be considered, incorporating

    predetermined denitions of costs and

    sensible identication of the key projectparameters which aect those costs.

    | Eciencies in Major Project Procurement14 VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    15/43

    Attachment 1

    Terminology

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    16/43

    Term Description

    Agency

    Means the sponsor agency charged with responsibility for project

    procurement and is the counterparty to the Contractor under the

    Contract.

    AllianceMeans the contract model of that name, more particularly

    described in Attachment 2.

    ContractMeans the arrangement between the Agency and the Contractor

    for the Contractor to provide works and/or services.

    Contract ModelsMeans Alliance, Public Private Partnership (PPP) and Design and

    Construct (D&C).

    D&CMeans the contract model titled Design and Construct, more

    particularly described in Attachment 2.

    EOI

    Means the formal invitation issued to potential Contractors which

    advises information related to the expression of interest (EOI)

    Phase and information required in the EOI response.

    EOI Phase

    Means the expression of interest phase, which generally:

    commences with formal notication to invite potential

    Contractors to respond to the Agency in respect of a proposed

    Contract for works and for services;

    involves the submission of responses from potential

    Contractors which seek to be selected to submit a proposal in

    respect of the proposed Contract;

    culminates in a number of proponents being selected to submit

    proposals in respect of the proposed Contract; and

    is nalised when notication and de-briengs are completed

    for proponents and for the non-selected potential Contractors.

    EOI response Means the response submitted by a potential Contractor pursuantto the EOI.

    Evaluation/Finalisation Phase

    Means:

    in the case of Alliance, the evaluation and nalisation phase

    which:

    - commences with receipt of Proposals by the Agency;

    - involves evaluation of Proposals and selection of one or

    two more proponents to submit a Target Outturn Cost;

    - involves resolution of commercial terms and selection of a

    Contractor;

    - culminates in the execution of the Contract and debrieng

    proponents;

    in the case of D&C and PPP, the evaluation and na lisation

    phase which:- commences with receipt of proposals by the Agency;

    - involves evaluation of proposals and selection of

    one or more proponents to progress to full Contract

    documentation;

    - culminates in the execution of the Contract and debrieng

    proponents; and

    - is nalised when conditions precedent (if any) are satised

    (including, in the case of a PPP Contract, achievement of

    nancial close).

    | Eciencies in Major Project Procurement16 VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    17/43

    Term Description

    PPPMeans the contract model titled Public Private Partnership, more

    particularly described in Attachment 2.

    Pre-Procurement Phase Means the period prior to the EOI Phase.

    ProcurementMeans the process of engaging a Contractor under a Contract to

    perform works and/or services.

    Procurement Phases

    Means the:

    Pre-Procurement Phase;

    EOI Phase;

    RFP Phase; and

    Evaluation and Finalisation Phase.

    Project

    Means the entire project which, under the Contract, is required to

    deliver the required works and/or services and/or functions, and

    which may involve a number of separate Contracts.

    ProponentMeans the participant or participants which submit a Proposal in

    response to the RFT.

    ProposalMeans the proposal submitted by a proponent pursuant to the

    Request for Proposal (RFP).

    RespondentMeans the participant or participants which submit an EOI

    response.

    RFP

    Means the formal request issued to proponents which advises

    information related to the RFP and Evaluation/Finalisation Phases

    and which advises the information required in the proposals.

    RFP Phase

    means the Request for Proposal phase which: commences with notication to the Proponents of their

    selection;

    involves preparation of Proposals by each Proponent; and

    is completed when Proposals are submitted to the Agency.

    Eciencies in Major Project Procurement | 17VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    18/43

    Attachment 2

    Contract Models

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    19/43

    Public Private Partnership (PPP)

    A Public Private Partnership (PPP) contract is funda-

    mentally dierent from the models described below.

    Instead of contracting for the provision of a facility

    which the Agency will own, the Agency contracts for

    a service. The facility is used to provide the service.

    Therefore, the Agencys focus is less on the techni-

    cal aspects of the facility, and more on the quality of

    the output that the facility provides.

    The Agency species its high level requirements

    for the output. The Agency then appoints the

    Contractor to provide the output to meet the

    specication. The Contractor designs, constructs,

    commissions and operates a facility that will provide

    an output to meet the specications. Often the

    Contractor will engage its own separate Design and

    Construct (D&C) and Operation and Maintenance

    (O&M) subcontractors to deliver the facility. The

    facility is transferred to the Agency after a specied

    period of time for an agreed price.

    The provision of the service is paramount. If there

    are changes which aect the provision of the service

    (which are not Force Majeure or changes made

    by the Agency), the Contractor is responsible for

    managing those changes at its cost. If there are

    improvements in technology or eciencies, the

    Contractor is incentivised to implement changes at

    its own cost, to improve its performance or reduceits cost and, therefore, increase its prot margin.

    The PPP structure usually involves nance provided

    by a third party nancier. The nancier nances

    construction of the facility. As the Agency is buying a

    service from the Contractor, the Agency usually does

    not make any payments to the Contractor until the

    Contractor provides that service to the Agency (usu-

    ally after commissioning). The funding arrangements

    are set at the start of construction, which gives a

    known fee as at the date of commissioning. That fee

    can vary in accordance with an agreed mechanism

    i.e. to take account changes in the Consumer PriceIndex (CPI) but otherwise does not vary unless the

    Agency agrees.

    For the provision of an asset, the Agency often pays

    the Contractor on a take and/or pay or available

    capacity basis. In this way, the Contractor is guar-

    anteed a monthly payment during operation of the

    facility, which it uses to nance repayment of its debt

    and to pay its ongoing operating costs, and provide

    a return to equity investors.

    The transfer component of this structure can occur

    shortly after commissioning (e.g. 5 years) or towards

    the middle or end of the life of the facility (10 or

    20 years). The timing for transfer will aect the

    payment regime, either increasing the payment to

    the Contractor to ensure that the debt is repaid by

    the time the facility is transferred, or by requiring a

    lump sum payment on transfer to cover the debt and

    equity contributions that have been made to fund the

    facility. Usually, there is a mixture of both of these

    elements in the payment regime. If the Agency does

    not require ownership of the facility at any stage, it is

    not necessary to include a transfer component, and

    the debt repayment is structured over the whole of

    the operating period.

    A performance management component is included

    in the payment regime. The Contractors perfor-

    mance measured in key result areas can reduce or

    increase the fee that the Contractor is paid.

    The structure requires the Agency to enter into

    a tripartite agreement with the nanciers and

    potentially direct agreement with key contractors

    and suppliers of the Contractor.

    Both the nanciers and the shareholders monitor

    the Contractors performance to ensure that it is

    entitled to receive full payment and is not breaching

    the contract. Similarly, nanciers will undertake acomprehensive technical and nancial due diligence

    on the project prior to advancing funds to the

    Contractor necessary for the construction of the

    facility. Typically, a nancier will appoint an indepen-

    dent engineer to monitor performance. A reduction

    in payment can aect repayment of debt and equity.

    A breach of contract which leads to termination

    exposes the nanciers and equity providers to the

    risk of not recovering their investment. The Agency

    can use these third party pressures on the Contractor

    to its advantage to manage the Contractor.

    A PPP is often used for a facility which is able tobe separated from the Agencys core operations,

    allowing the Agency to focus on its core operations

    and the quality of the output that it receives from the

    facility. A PPP is also used to provide a service that

    the Agency does not have expertise in providing. The

    PPP structure allows the Agency to focus on whether

    its requirements for the provision of a service are

    being met. This diers from the structures above

    where the Agency owns the facility and so monitors

    Eciencies in Major Project Procurement | 19VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    20/43

    ProjectDeed

    Guarantees

    O&M Contract

    D&CContract

    DeedofCharge

    Lease

    Guarantees

    Side DeedsSide Deeds

    how a facility is being operated. The PPP structure

    is commonly used by government to take advantage

    of private sector innovation and eciencies and to

    bring forward the provision of a service that might

    otherwise be delayed due to the unavailability of

    government resources.In addition, under a PPP structure the facility can,

    depending on accounting treatment, be o-balance

    sheet for project owners.

    The PPP structure requires the nance arrange-

    ments, the term and scope of the project to be

    agreed and documented upfront. Whilst some

    exibility can be built in, this needs to be raised and

    priced in the procurement process and appropriate

    provision made in the project documentation. It

    should also be noted that the existence of non-

    recourse debt nancing also creates signicant

    unwind costs as other circumstances of contractor

    default break costs will, as a minimum, need to cover

    outstanding debt.The PPP project delivery structure involves

    signicant procurement costs given the level of

    documentation required and a longer tendering pro-

    cess than the other procurement methods described

    in this Attachment.

    A simplied typical PPP structure is illustrated in the

    diagram above.

    Figure 1: Typical PPP Structure

    Agency

    SpecialPurpose

    Vehicle

    Operations andMaintenance

    Contractor

    D&C Contractor

    Equity 1

    Equity 2

    Trustee

    Debt 1

    Debt 2

    Subcontracts similar to D&C

    Joint Venture Agreement

    | Eciencies in Major Project Procurement20 VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    21/43

    Design and Construct (D&C)

    The Design and Construct (D&C) model involves the

    engagement of a Contractor to design and construct

    the project, generally for a lump sum price.

    A typical D&C structure is illustrated in the diagram

    below.

    The inherent advantage of a D&C model is that

    it results in a signicant transfer of the price and

    delivery risk to a third party contractor. This in turn

    provides a signicant incentive for that contractor to

    deliver on time and on budget.

    The inherent disadvantage of the D&C model is thatit does not oer the exibility of the Alliance model

    for continued design renement by the Agency dur-

    ing development of the project.

    In summary, the inherent advantages of a D&C

    model are that:

    it provides comprehensive risk transfer and

    price certainty (subject, in the case of risk

    transfer, to caps on contractor liability);

    D&CCont

    ract

    Principal

    D&C Contractor

    Design Package

    In-House

    Resources

    Design &

    ConstructionPackage 1

    Design &Construction

    Package 2

    Construction

    Package 1

    ConstructionPackage 3

    Construction

    Package 2

    ConstructionPackage 4

    Joint Venture Agreement(if applicable)

    Figure 2: Typical D&C Structure

    it drives performance outcomes to the extent

    that such outcomes are dened;

    it drives whole of life outcomes only to the

    extent that particular standards are prescribed

    and measurable;

    it requires some management eort during

    delivery to ensure whole of life outcomes are

    delivered;

    it provides single point accountability for all

    site activities; and

    it requires limited management burden during

    delivery and commissioning.

    Eciencies in Major Project Procurement | 21VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    22/43

    The disadvantages of the D&C model are that:

    the project requirements (including interfaces)

    must be well dened (and better dened than

    under an Alliance delivery model) to enable

    contractors to eectively price the works;

    there must be comprehensive data to allow

    design and construction risks to be priced and

    managed;

    changes introduced during construction can

    create performance risk transfer back to the

    client and may be costly to implement;

    it does not directly drive whole of life outcomes

    because it relies on specied standards to

    provide such outcomes;

    the D&C model is widely used on civil projects,including PPPs;

    it does not have the same exibility as the

    Alliance model to enable design development

    to continue following engagement of the

    contractor;

    the front end procurement process generally

    requires signicant tenderer design eort;

    there must be capability and appetite in the

    market to undertake a project of the size and

    complexity; and

    it may involve the parent of the owner (Agency)

    providing a parent company guarantee where

    the Agency is not regarded as suciently

    credit-worthy on a stand alone basis in respect

    of its contractual obligations under the D&C

    contract. This scope of potential liability under

    this guarantee may be signicant (i.e. up to the

    construction cost under the D&C contract).

    Alliance

    An alliance is a relationship between the Agencies

    and the Contractor (or Contractors) that is intended

    to jointly share the risks of project delivery between

    the Participants. Customarily, however, the Agency

    carries full direct cost risk together with performance

    incentive payment obligations. The Participants cost

    risks are limited to an apportionment of margins and

    unachieved delivery incentives.

    Normally, alliancing is used to deliver larger, more

    complex and high-risk infrastructure projects.

    Projects suitable for delivery as alliances are gener-

    ally characterised by one or more of the following

    factors, which have been identied by the Victorian

    Department of Treasury and Finance (2009):

    1. the project has risks that cannot be adequatelydened or measured in the business case or

    prior to tendering;

    2. the cost of transferring risks is prohibitive;

    3. the project needs to start as early as possible

    before the risks can be fully identied and/or

    project scope can be nalised, and the owner

    is prepared to take the commercial risk of a

    sub-optimal price outcome;

    4. the owner has superior knowledge, skills,

    preference and capacity to inuence or

    participate in the development and deliveryof the project, including for example, in the

    development of the design solution and

    construction method; and

    5. a collective approach to assessing and

    managing risk will produce a better outcome,

    for example where the preservation of safety to

    the public / project is best served through the

    collaborative process of an alliance.

    The alliance is governed by an Alliance Board, com-

    prising senior members of each participant, and an

    Alliance Management Team, comprising membersof all participants selected on a best for project

    basis. The Alliance Board is responsible for strategic

    decisions, which must be made unanimously, giving

    each participant a right of veto over any decision.

    The Alliance Management Team is responsible for

    the day to day management of the project. The

    structure means that the Agency has a hands on

    involvement in the running of the project, through

    its representatives on the Alliance Board and the

    Alliance Management Team. In eect, the Agency

    has two distinct roles one as owner of the project

    | Eciencies in Major Project Procurement22 VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    23/43

    and the other as a participant in project delivery. A

    failure by the Agency to recognise this and perform

    accordingly can lead to substandard outcomes.

    Under an Alliance, there is a no-blame culture

    which means that risks are not assigned to any

    participant, but are the responsibility of all. If an

    issue arises, it must be resolved by all participants

    and the cost consequences are essentially carried

    by the Agency, with limited nancial incentives on

    the other participants to perform. This is regardless

    of the nature of the risk. The payment regime is used

    to crystallise risks, losses and gains and distribute

    them amongst all of the members of the Alliance.

    An alliance has a no litigation requirement. This

    means that the participants are not entitled to sue

    each other for breach of contract or breach of

    other obligations owed to each other. The theory

    behind the no litigation requirement is that if the

    participants do not have an entitlement to sue each

    other, they will focus on resolving an issue on a best

    for project basis. There are certain exceptions to the

    no litigation requirement, being wilful default, fraud

    and criminal activities.

    Payment is usually on a direct cost plus margin

    (overhead and prot) basis, with a pre-determined

    budget used to control costs and determine

    participants share of overruns or savings under the

    agreements risk/reward regime. Payment is on acost incurred and not an earned value basis. The

    Contractor participants performance against budget

    and other key performance indicators is measured,

    and alters the Contractor participants fee. For

    example, a cost overrun will be shared equally

    between the participants, thereby reducing the

    Contractor participants fee. The Contractor will usu-

    ally a require a limit on the extent of the reduction to

    its fee. That limit usually equates to the Contractors

    prot margin and, sometimes, its overhead margin.

    The limit means that the Contractor may only recover

    its costs of performance. However, beyond the limit,

    cost increases are the responsibility of the Agency.

    A typical alliance structure is illustrated in the

    diagram below.

    Figure 3: Typical Alliance Structure

    Agency(as client)

    Agency(as participant)

    Designer

    Alliance Management Team

    Alliance Leadership TeamAlliance

    Agreement

    ConstructorSystemProvider

    OperatorMaintainer

    Eciencies in Major Project Procurement | 23VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    24/43

    Attachment 3

    Schedule of EnablingActions for QualitativeBenchmarks

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    25/43

    Procurement

    Phase

    Qualitative

    BenchmarkDescription Enabling Actions

    Pre-Procurement

    Phase

    Communication

    of accurate andsucient project

    information.

    Available to potential

    proponents to makeinformed decisions

    and undertake

    planning in the Pre-

    Procurement Phase.

    Identify the specic market sectors / entities which have the

    capability, capacity and appetite to be a participant in theproject.

    Ensure that the relevant information is available to potential

    participants, either as part of an Agency communications

    program or on a project specic basis.

    Communicate information that is relevant to the potential

    participants, giving consideration to communicating

    information relating to:

    - Project objectives and key Agency issues and values;

    - Project scope and value, the contract model risk

    allocation, the payment regime and project programme

    including term, if relevant;

    - the procurement process and procurement programme;

    - intergovernment issues and Agency retained

    responsibilities;- approach to related entities;

    - Agency governance and approvals processes;

    - interfaces denition and obligations;

    - planning approvals status and strategy;

    - approach to contribution to bid costs;

    - consistency of processes, risks and terms within a

    jurisdiction and similar model projects;

    - expected prequalication levels or minimum capability/

    capacity hurdles.

    Ensure properly considered planning underpins all

    undertakings.

    Develop, implement, review and improve the communica-

    tions strategy.

    Ensure the accuracy and reliability of information issued.

    Ensure relevant Agency and intergovernment approvals are

    in place in relation to the content of information provided.

    Consider the importance and relevance of information in the

    context of each Procurement Phase.

    Ensure that the communicated strategy is delivered.

    Prepare, resource, manage and fund the planning and com-

    munication processes.

    Ensure Government agencies are aligned in respect of the

    project issues.

    Obtain all necessary Government approvals and endorse-

    ments to the Procurement process.

    Ensure that any changes to program and process are

    communicated as early as practicable and as accurately as

    possible.

    Eciencies in Major Project Procurement | 25VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    26/43

    Procurement

    Phase

    Qualitative

    BenchmarkDescription Enabling Actions

    Pre-Procurement

    Phase

    Comprehensive pro-

    curement planning isundertaken.

    Planning fully

    addresses: the project scope

    and commercial

    arrangements;

    the procurement

    process;

    procurement

    resources;

    procurement

    risks and

    opportunities;

    stakeholder

    interfaces; and

    alignment with

    market capabilityand capacity.

    Identify requirements for Agency and Ministerial approvals

    and incorporate in procurement planning. In dening the project requirements, consider and evaluate

    the consequences of project complexity including consid-

    eration of:

    - the number of separate participants;

    - the diversity of participants;

    - the relationship between the participants and the

    structure of the proponent; and

    - the role of participants in the performance of the

    Contract services over the life of the Contract.

    Ensure that the procurement process is appropriately

    understood, endorsed and approved within the Agency and

    within wider Government (as required).

    Understand the market issues aecting procurement,

    including diversity in Proponent teams, and align theprocurement strategy with market capacity, capability and

    appetite.

    Consider the costs of bidding, including considering bid

    cost contribution where it is warranted.

    Implement processes to capture lessons learned from

    similar projects and from the Procurement Phases, and to

    implement continuous improvement.

    Implement processes to capture Government and market/

    industry knowledge.

    Incorporate management of State retained obligations and

    State interfaces, including implementation of a strategy to

    resolve intergovernmental issues and provide for Agency

    relationship management.

    Ensure access to (and commitment from) appropriateGovernment resources throughout the Procurement

    processes.

    Provide particular planning for the level of Agency resources

    necessary for Alliance procurement and delivery.

    Provide a consistency of approach within the jurisdiction

    and incorporate jurisdiction procedures, including gateway

    processes.

    Develop comprehensive planning for each Procurement

    Phase and ensure planning for each subsequent phase is

    complete prior to commencement of that phase.

    Incorporate sound analysis of the project needs and busi-

    ness case.

    Identify appropriate resources and necessary capability of

    the procurement team with clear responsibilities within eachProcurement Phase.

    Develop robust procurement baseline budgets and

    programmes.

    Address contract packaging and contract models in the

    procurement planning.

    Incorporate overall risk and opportunity management

    throughout all Procurement Phases.

    Seeking and respond to feedback from within the sponsor

    Agency, from potential Proponents and from stakeholders

    (including central Agencies);

    | Eciencies in Major Project Procurement26 VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    27/43

    Procurement

    Phase

    Qualitative

    BenchmarkDescription Enabling Actions

    Pre-Procurement

    Phase

    Comprehensive pro-

    curement planning isundertaken.

    Planning fully

    addresses: the project scope

    and commercial

    arrangements;

    the procurement

    process;

    procurement

    resources;

    procurement

    risks and

    opportunities;

    stakeholder

    interfaces; and

    alignment with

    market capabilityand capacity.

    Provide detailed programming at each Procurement Phase

    recognising that Proponents:- often consist of separate participants, each with review /

    approval protocols;

    - require reasonable time to resolve inter-participant

    issues;

    - require sucient time (and information) to plan and

    commit resources; and

    - incur costs for holding and delays.

    Provide a strategy to resolve planning approvals, including

    addressing responsibilities, allocation, commercial conse-

    quences and management plans.

    Provide a strategy to resolve land access.

    Identify and resolve a statutory approvals strategy.

    Provide a strategy to resolve Project third-party interfaces. Understand the cost impact and consequences of risk

    allocation and provide a strategy to resolve risk allocation.

    Incorporate a clear and focused communications strategy

    with all relevant stakeholders;

    Ensure that the overall procurement strategy is suciently

    developed to ensure consistency throughout all subsequent

    Procurement Phases.

    Develop a comprehensive understanding of the skills

    required throughout procurement (including throughout

    each phase).

    Ensure team leadership is experienced in the planned

    contract models.

    Ensure team leadership is experienced in the particular

    services and/or infrastructure types contemplated in theproject and, if required, supplement the leadership with

    expert mentors.

    Ensure experienced leadership support (steering

    committee).

    Ensure appropriate talent and capability for appropriate

    activities and consider independent experts for particular

    project issues and tasks.

    Ensure eective relationship and process management

    within Government.

    Ensure process experience and capability in the procure -

    ment team.

    Ensure issue resolution capability in the procurement team.

    Ensure timely operator participation in the procurement

    processes.

    Ensure appropriate budgets are identied and approved for

    the procurement processes.

    Facilitate whole of Government alignment and support.

    Provide expertise to optimise eectiveness of bidder

    interaction.

    Ensure strong project/program management capability in

    the procurement team.

    Ensure clear responsibilities and accountabilities within the

    procurement team.

    Eciencies in Major Project Procurement | 27VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    28/43

    Procurement

    Phase

    Qualitative

    BenchmarkDescription Enabling Actions

    Pre-Procurement

    Phase

    Comprehensive pro-

    curement planning isundertaken.

    Planning fully

    addresses: the project scope

    and commercial

    arrangements;

    the procurement

    process;

    procurement

    resources;

    procurement

    risks and

    opportunities;

    stakeholder

    interfaces; and

    alignment with

    market capabilityand capacity.

    Ensure that the Procurement team understands the appetite,

    capability and capacity of the potential participants todeliver each part of the project scope, including considering:

    - a structured early market engagement and sounding;

    - communications between agencies and jurisdictions to

    obtain benets of experience and lessons learned; and

    - advice to the procurement team from potential

    proponents;

    Ensure that the procurement team understands (and the

    procurement planning responds to) the full scope of the

    project and the specic project and procurement risks and

    opportunities.

    Ensure that the procurement is designed to best align the

    project requirements with the market characteristics, given

    consideration to:

    - capacity, capability and appetite of potential proponents;- the impact of project complexity, bundling on competi-

    tion and value;

    - the impact of project size (value) on competition;

    - the reduced eciency of joint ventures relative to a

    single suitable participant;

    - the value/benets/cost of project risk allocation;

    - the cost of bidding and the eect of the number of bid-

    ders on Proponents appetite;

    - uniformity in approach within jurisdictions;

    - the diversity and tensions within bid teams; and

    - reasonable procurement programming, including

    responding to other concurrent projects, international

    participation and the like. Establish a Procurement risk and opportunity management

    process.

    Ensure early resolution of project physical and contractual

    interfaces.

    Ensure early resolution of interagency issues.

    Ensure ongoing alignment of Government agencies in

    respect of issues.

    Ensure commitment of Government resources.

    Finalise procurement approval processes.

    Implement eective interagency communications.

    Clarify and agree interagency protocols.

    Establish transparent milestones and monitor progress to

    program for Procurement activities.

    Engage early intervention and/or implement remedial action

    to mitigate the impact of events or circumstances which

    aect procurement.

    Ensure clear understanding within Government of the project

    risks, including those related to Agency and Government

    retained obligations.

    Ensure early recognition and response to probity issues.

    | Eciencies in Major Project Procurement28 VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    29/43

    Procurement

    Phase

    Qualitative

    BenchmarkDescription Enabling Actions

    EOI Phase Clear and complete

    EOI documentation.

    The EOI document

    fully addresses: Project

    requirements;

    Response

    requirements;

    Procurement

    process;

    issues aecting

    responses; and

    Response

    evaluation.

    Ensure that the EOI documents describe:

    - the EOI processes;

    - the issues which have the potential to materially aect

    the EOI process or the Procurement process;

    - details of the EOI process and its context within the

    Procurement process;

    - the EOI Stage program and the procurement program;

    - the EOI evaluation methodology, criteria and any weight-

    ings which may apply;

    - the constraints, procedures and protocols for

    proponents to comply with throughout the procurement

    process, including probity obligations;

    - approach to related entities;

    - Agency governance and approvals processes;

    - approach to contribution to bid costs; and

    - expected prequalication levels or minimum capability/

    capacity hurdles.

    Ensure that the EOI response requirements include identi-

    cation and commitment of the proponent (and participants)

    to the RFP rules including commitment to submit a proposal,

    probity condentiality, conict of interest and related

    company procedures.

    Ensure that the EOI documents include details which enable

    participants to understand the project with consideration

    being given to:

    - Project objectives and key Agency issues and values;

    - all issues which have potential to aect the project;

    - Project scope and value, the contract model risk

    allocation, the payment regime and Project programmeincluding term, if relevant;

    - intergovernment issues and Agency retained

    responsibilities;

    - interfaces denition and obligations;

    - planning approvals status and strategy;

    - consistency of risks and terms within a jurisdiction and

    similar model projects; and

    - any limits on innovation.

    Ensure that the evaluation criteria align with the project

    objectives.

    Ensure that the information required aligns with the evalua-

    tion criteria.

    Ensure that the evaluation methodology measures the extent

    to which the EOI response information satises the relevant

    evaluation criteria.

    Ensure that the EOI responses are evaluated in accordance

    with the advised evaluation criteria and methodology.

    Eciencies in Major Project Procurement | 29VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    30/43

    Procurement

    Phase

    Qualitative

    BenchmarkDescription Enabling Actions

    EOI Phase EOI requirements

    reasonably minimiseRespondents eort

    and cost.

    The EOI Response

    requirements forlarger:

    existing prequali-

    cation material

    minimum levels of

    experience and

    expertise;

    Proponents

    internal standard

    documentation;

    and

    only key

    dierentiating

    information.

    Develop the EOI process program to allow reasonable time

    for the activities while avoiding unnecessary holding/stand-ing costs for participants.

    Utilise the Pre-Procurement Phase feedback from potential

    participants to inform the development of the EOI program.

    As far as practicable, reduce EOI response eort giving

    consideration to:

    - the use of existing relevant prequalication arrange-

    ments for relevant participants, (including the application

    of corporate management and corporate capability and

    performance) recognising that this may not be appropri-

    ate for particular services or where new participants are

    contemplated;

    - the utilisation of minimum experience, capability and

    capacity measures to mandate standards for relevant

    participation because this will guide the acceptable

    potential participants while discouraging unacceptableparties from seeking to participate;

    - requesting only dierentiating information and clearly

    dening the information requirements;

    - allocating specic criteria to specic returnable

    schedules;

    - requiring detailed participant business sustainability

    information (such as nancial reports) to be in the form in

    which it was originally produced;

    - focussing the EOI response requirements on the

    character / capability / commitment / interrelationships

    of participants to the Respondent; and

    - avoiding the inclusion of works or service solution,

    unless product issues aect evaluation.

    As far as practicable, simplify the EOI requirements andminimise documentation including considering:

    - maximising application of electronic submissions;

    - incorporating page limits on EOI Response specic

    documents; and

    - sensibly requiring schedules and point form summaries

    rather than text.

    | Eciencies in Major Project Procurement30 VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    31/43

    Procurement

    Phase

    Qualitative

    BenchmarkDescription Enabling Actions

    EOI Phase EOI process is under-

    taken in accordancewith information

    issued.

    The EOI

    process has nodivergences as iden-

    tied in Quantitative

    Benchmarks.

    Ensure the early undertaking of actions to resolve issues

    which have the potential to delay or alter the EOI process. Ensure that the Agency resources manages, coordinates

    and delivers the EOI process as planned, as previously

    advised and as contemplated in the EOI documents.

    To the extent that changes to the EOI program or to the

    EOI process become unavoidable, advise the potential

    participants as soon as possible.

    Ensure the accuracy and completeness of advice to poten -

    tial participants during the EOI Phase.

    Ensure that the Agency resources, manages coordinates,

    undertakes and concludes the EOI evaluation in the

    minimum reasonable time.

    In the case of Alliances, ensure that the procurement team

    has the expertise, support and availability to undertake the

    alignment/selection workshops.

    Evaluate the EOIs within the time advised in the prior

    information, the EOI Phase program and the EOI documents.

    Ensure the approval processes and announcement proto-

    cols are conrmed, planned and followed.

    Ensure that the procurement team recognises the

    waiting/holding costs for participants after EOI response

    submission.

    Eciencies in Major Project Procurement | 31VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    32/43

    Procurement

    Phase

    Qualitative

    BenchmarkDescription Enabling Actions

    RFP Phase Clear and complete

    RFP documentation

    The RFP documents

    fully addresses: Project

    requirements;

    Proposal

    requirements;

    Procurement

    process;

    issues aecting

    proposals; and

    Proposal

    evaluation.

    Ensure that the RFP documents clearly address all material

    aspects of the Project including:- the commercial terms, including the precise allocation of

    risk, payment terms, parties rights and remedies;

    - the structure and character of the Contract;

    - works and service requirements, including mechanisms

    for measurement of compliance;

    - details of issues aecting the performance of works and

    services (including land access, works approvals and

    interfaces); and

    - clear denition of any limitations on exibility and/or

    innovation.

    - Ensure that RFP documents clearly dene what is

    required to be submitted in the Proposal including:

    - clarity in the extent of detail, certainty and commitment

    of the various aspects of the Proposal; and

    - clear identication of mandatory requirements.

    For complex, major and/or unique Projects, engage in a

    planned and controlled interactive process between the

    Agency and Proponents during Proposal preparation to

    enable:

    - clarity and delivery certainty in relation to government

    retained obligations;

    - Proponents to test opportunities for innovation (or limits

    to innovation) and to optimise proposal team eort;

    - Proponents to raise issues without committing to formal

    clarication; and/or

    - the Agency to dene limits and consider clarications in

    an informed context.

    Where interactive RFP processes are employed, Agencies

    should consider:

    - establishing subject matter streams for interactive ses -

    sions to ensure appropriate Agency representation and

    to enable ecient targeted interaction;

    - establishing protocols which enable the interactive pro-

    cess to be eective within sensible probity constraints;

    - process management to provide equal opportunity to

    proponents and to preserve the Proponents intellectual

    property;

    - the engagement of skilled experienced representatives

    to manage the Agency roles; and

    - appropriately skilled Agency / Government representa-

    tives participation in the relevant subject mattermeetings.

    | Eciencies in Major Project Procurement32 VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    33/43

    Procurement

    Phase

    Qualitative

    BenchmarkDescription Enabling Actions

    RFP Phase Clear and complete

    RFP documentation

    The RFP documents

    fully addresses: Project

    requirements;

    Proposal

    requirements;

    Procurement

    process;

    issues aecting

    proposals; and

    Proposal

    evaluation.

    Include details of the evaluation methodology in the RFP

    document incl uding (where applicable):- clarity of mandatory requirements;

    - clarity in respect of the assessment of value for money;

    - identication of issues relating to price point, aord-

    ability and/or the relevance of the PSC;

    - the circumstances which would justify adjustments to

    the PSC value (for PPPs);

    - the mechanism and application of comparative quantita-

    tive risk assessment;

    - the mechanism and value of relative economic benets;

    - clear evaluation benchmarks (including discount rates,

    economic benet costs/benets and whole of life costs);

    - mechanisms to deal with options, alternatives and

    innovation (including ranked preferred options up to avalue (PV) cap, if nominated);

    - clear and unambiguous evaluation criteria;

    - application of (and relationship between) relative value,

    non-price, economic and/or outturn cost analyses; and

    - weightings of non-price assessments if used.

    RFP Phase RFP requirements

    reasonably minimise

    Proponents eort and

    costs.

    The RFP requires:

    only essential

    design elements

    which represent

    material risks to

    the agency;

    only essential

    statements of

    intent (project

    plans) which

    represent material

    risks;

    Responses struc-

    tured to facilitate

    incorporation of

    Proposal features

    into a Contract;

    and

    documentation

    only of essential

    Contract

    elements.

    Proposal requirements should be focussed on that which

    has a material impact on the certainty of delivery of the

    project objectives, including information which:

    - is characteristic of the proponent (and will be inevitably

    captured by the engagement of that proponent in a

    Contract); or

    - represents relative value; or

    - represents value to the Agency and therefore shouldbe captured in a Contract with that proponent (if

    successful).

    Proposal technical requirements should be minimised where

    practicable, including considering:

    - elimination of documentation relating to Contractors

    corporate systems (i.e. management, safety and environ-

    ment), which most likely have been directly or indirectly

    dealt with in the EOI Phase;

    - limitation of project specic method statements (project

    plans) to those which are genuinely material to delivery

    of the project objectives; and

    - limitation of design documents to those which capture

    the relative value of the Proposal including those which

    are necessary for assurance of functional certainty and

    aesthetics.

    When considering proposal design, delivery and service

    documentation requirements, Agencies should recognise

    that:

    - documentation should be limited to that which provides

    certainty of outcomes; and

    - to the extent that elements of the successful proponent

    represent greater relative value or outcome certainty,

    then those elements should be incorporated in the

    Contract.

    The Procurement team should sensibly limit option pricing.

    Eciencies in Major Project Procurement | 33VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    34/43

    Procurement

    Phase

    Qualitative

    BenchmarkDescription Enabling Actions

    RFP Phase RFP requirements

    reasonably minimiseProponents eort and

    costs.

    The RFP requires:

    only essentialdesign elements

    which represent

    material risks to

    the agency;

    only essential

    statements of

    intent (project

    plans) which

    represent material

    risks;

    Responses struc-

    tured to facilitate

    incorporation of

    Proposal features

    into a Contract;

    and

    documentation

    only of essential

    Contract

    elements.

    The Procurement team should be aware that a certain

    level of design and delivery development by Proponentsis unavoidable to establish certainty of pricing (in PPP and

    D&C projects) during the RFP Phase and, consequently, the

    requirement to incorporate that level of design and delivery

    documentation in the proposal frequently has limited mate-

    rial impact on costs.

    As a minimum, technical documentation should include

    those documents necessary to provide functional, aesthetic

    and whole-of-life certainty.

    Agencies should consider receipt of technical aspects of

    (D&C and PPP) Proposals prior to the closing date and time

    to reduce the evaluation period and reduce the standby time

    for proponents technical resources.

    To facilitate evaluation of the various aspects of proposals,

    proposal requirements are structured to provide alignment

    between:

    - the required content of a specic returnable schedule;

    - the specic evaluation criteria for that returnable

    schedule;

    - the particular expertise of the Agency group engaged to

    evaluate that returnable schedule; and

    - the methodology for evaluation of that returnable

    schedule.

    To facilitate early and complete resolution of issues and

    evaluations, the Agency should:

    - concurrently plan, program and manage concurrent

    evaluation;

    - centralise issue identication, management and resolu-

    tion; and

    - ensure that the form of the issue resolution is able to be

    incorporated into the proposed Contract.

    To facilitate consolidated evaluation of all aspects of propos-

    als, the RFP generally (and the evaluation plan specically)

    describes how the evaluation of each proposal element

    (returnable schedule) contributes to the overall evaluation of

    the proposal.

    To facilitate the later Contract nalisation and to readily

    capture the relative value of the selected proposal, the RFP

    is structured so that key aspects of the selected proposal

    (particularly those which contribute to that proposals

    relative value) are able to be incorporated into the proposed

    Contract.

    To the extent practicable, hardcopy requirements should be

    minimised and electronic submissions should be employed.

    To the extent practicable, the structure and content of

    proposals should be consistent with similar projects within

    the jurisdiction.

    Proposal documentation requirements should be limited to

    that which has material impact on the certainty of delivery of

    the project objectives.

    | Eciencies in Major Project Procurement34 VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    35/43

    Procurement

    Phase

    Qualitative

    BenchmarkDescription Enabling Actions

    RFP Phase RFP requirements

    reasonably minimiseProponents eort and

    costs.

    The RFP requires:

    only essentialdesign elements

    which represent

    material risks to

    the agency;

    only essential

    statements of

    intent (project

    plans) which

    represent material

    risks;

    Responses struc-

    tured to facilitate

    incorporation of

    Proposal features

    into a Contract;

    and

    documentation

    only of essential

    Contract

    elements.

    Where appropriate, a contribution to bid costs should be

    considered in response to large and/or complex projectsrequiring signicant unique eort.

    If consideration is to be made in respect of bid costs, those

    considerations should be:

    - only in respect of unsuccessful proponents;

    - limited to a xed, predetermined amount;

    - subject to demonstrated third party expenses exceeding

    that xed amount; and

    - subject to submission of a bona de proposal.

    Ensure that procurement team resources are authorised,

    experienced and available to eectively respond to:

    - the interactive and clarication processes in PPP models

    and in D&C models (including early contractor involve -

    ment); and

    - the engagement for Alliance participation in TOC

    preparation.

    Fully documented commercial terms are necessary to

    provide certainty in respect of Proposal evaluation and in

    terms of Contract nalisation (for D&C and PPP Contracts).

    Fully documented commercial terms for options and alterna-

    tives are necessary to provide certainty (in respect of the

    known variables) for the purpose of evaluation of Proposals

    and for the purpose of Contract nalisation (for D&C and

    PPP Contracts).

    The Procurement team should recognise that the PPP

    Contracts invariably involve a suite of commercial/nancial

    documents at Contract Close due to the necessity to identify

    the relationships between the various participants, the

    Agency and (possibly) the government. In the context of

    minimising the Proponents eort and costs, it is prudent to

    consider the character and completeness of the commercial

    documentation required as part of the Proposal, including

    considering:

    - the use of precedent documents;

    - the use of term sheets where sucient certainty can be

    achieved, such that the resolution of outstanding issues

    will not result in adverse changes to the commercial

    terms (in the Contract documents) during nalisation; or

    - deferring nalisation of non-material documents with

    only a selected proponent while other proponents are

    held in reserve.

    The Procurement team should recognise the inherent

    uncertainty associated with validity periods which are less

    than the duration of the Evaluation/Finalisation Phase andshould require adequate realistic validity periods together

    with refresh protocols for extending the validity.

    Eciencies in Major Project Procurement | 35VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    36/43

    Procurement

    Phase

    Qualitative

    BenchmarkDescription Enabling Actions

    RFP Phase RFP requirements

    reasonably minimiseProponents eort and

    costs.

    The RFP requires:

    only essentialdesign elements

    which represent

    material risks to

    the agency;

    only essential

    statements of

    intent (project

    plans) which

    represent material

    risks;

    Responses struc-

    tured to facilitate

    incorporation of

    Proposal features

    into a Contract;

    and

    documentation

    only of essential

    Contract

    elements.

    Agencies should consider resolving commercial terms

    (particularly PPP) with each proponent prior to the closingdate and time to reduce the evaluation period and reduce

    the standby time for proponents commercial / nancial

    resources.

    Ensure that the degree of proponent due diligence for

    proposal submission is to be appropriate for the project in

    understanding that:

    - incomplete due diligence results in uncertainty in the

    value of a Proposal and in terms of commercial and

    procurement program outcomes;

    - completed due diligence at submission provides

    certainty of the Proposal, however it requires proponents

    to expend greater eort and cost; and

    - Proponents may seek to delay full due diligence to

    be a contract condition precedent to be resolved after

    Contract execution, which could result in ongoingnegotiation following Contract award.

    | Eciencies in Major Project Procurement36 VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    37/43

    Procurement

    Phase

    Qualitative

    BenchmarkDescription Enabling Actions

    RFP Phase Commercial Terms

    represent value formoney.

    Full consideration is

    given to: precedent

    Contracts;

    evaluation of

    terms;

    mechanisms

    to deal with

    uncertainties;

    performance and

    payment; and

    interface

    resolution.

    As far as practicable, commercial terms should be:

    - consistent within the jurisdictions; and

    - consistent with similar projects.

    Where specic commercial terms are necessary to deal

    with a particular issue utilise precedent documents (from

    precedent projects) where practicable.

    Ensure that the Agency team are informed in respect of

    the evolution of terms over time in response to Agency and

    participant needs.

    Where particular uncertainty exists, mechanisms involving

    predetermined commercial outcomes for particular events

    should be considered.

    The Agencys approach to commercial terms in the RFP

    documents should be informed by the earlier market

    sounding.

    The Agency should recognise that the primary objective ofcontract terms is to drive Contractor behaviour and should

    consider:

    - a balance between nancial outcomes and contract

    performance; and

    - consistency between good performance incentives and

    poor performance remedies;

    The Agency should ensure that performance is linked to

    payments and that payment adjustment triggers:

    - are sensibly limited in number and actually and directly

    reect the Agencys required outcomes;

    - are readily measurable, not subjective and readily

    auditable;

    - are not scaled or structured so that reasonable

    performance is penalised (a feature which will encourage

    Proponents to provide for such adjustments in the

    nancial elements of their proposal).

    Recognise the cost / value of particular commercial posi-

    tions including:

    - the added cost of retentions;

    - potential value for insurance strategies;

    - the savings associated with resolution of project inter-

    faces and inter government agency issues; and

    - the pricing uncertainty in response to the transfer of risk

    to a proponent which cannot be managed or cannot be

    quantied (such as unlimited liability).

    Recognise that uncertainty increases both the price of a

    proposal and the proponents preparation cost.

    Eciencies in Major Project Procurement | 37VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    38/43

    Procurement

    Phase

    Qualitative

    BenchmarkDescription Enabling Actions

    RFP Phase RFP Process is

    undertaken inaccordance with

    information issued to

    Proponents.

    RFP process has no

    divergences, as iden-tied in Quantitative

    Benchmarks.

    Ensure that the RFP documents describe:

    - issues which have the potential to materially aect theRFP process;

    - details of the RFP process and its context in the

    Procurement process;

    - the RFP evaluation methodology;

    - constraints, procedures and protocols to be observed

    throughout the RFP Phase; and

    - eective arrangements for access to information includ-

    ing relevant data;

    Ensure that delay and disruption and wasted eort is

    avoided/minimised including:

    - delivering the RFP process in accordance with the

    advice to Proponents (including in the RFP document);

    - ensure the accuracy and completeness of all advice toProponents;

    - ensure that unavoidable changes to the RFP process are

    advised as early as possible including:

    requiring clarication requests to be submitted early in the

    RFP period;

    issuing any unavoidable material addenda early in the RFP

    period; and

    extending the Proposal closing date and time when material

    changes are not able to be eectively addressed in the

    remaining time.

    Prior to the closing date ensure that the Agency is fully

    prepared for the Evaluation / Finalisation Phase, including

    ensuring that it has:

    - developed its evaluation plan and contemplateddocumentation;

    - engaged and committed the evaluation resources;

    - developed and structured the evaluation team;

    - inducted and trained its evaluation resources;

    - nalised the evaluation program;

    - established receipt security and document control

    arrangements;

    - implemented centralised issue (identication, coordina-

    tion, clarication and resolution) management;

    - obtained endorsement of the evaluation processes as

    required; and

    - identied and planned evaluation reporting and approval

    processes.

    | Eciencies in Major Project Procurement38 VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    39/43

    Procurement

    Phase

    Qualitative

    BenchmarkDescription Enabling Actions

    Evaluation /

    Finalisation Phase

    Eective and

    ecient evaluation ofProposals.

    The evaluation fully

    addresses: assessment of

    the relative value

    of each proposal;

    resolution of

    material uncer-

    tainties in respect

    of proposals; and

    in the case of the

    selected pro-

    posal, inclusion of

    the relative value

    and the resolution

    of uncertainty in

    the Contract.

    Ensure eective management of material issues (aecting

    the value and/or uncertainty of Proposals) including:- coordination and centralisation of issue management

    (across disciplines) to recognise the interrelationships

    and materiality of issues;

    - implementation of eective cohesive issue resolution

    strategies;

    - design of clarications requests to ensure that the

    responses enable evaluation with certainty;

    - design of clarications requests to provide the precise

    Contract wording which would be employed to capture

    the outcomes; and

    - recognition of the occasional necessity to sequence

    clarication requests to consider responses prior to

    subsequent clarications.

    Recognise that validity periods have the potential toaect proposal certainty and implement processes to

    monitor, manage and refresh validity during the Evaluation/

    Finalisation Phase.

    Recognise that competition should be preserved until all

    material aspects of Proposals are resolved, to ensure:

    - minimum adverse shifts in commercial terms (deal

    creep);

    - minimum extended multi-party negotiations; and

    - minimum delays to execution of the Contract and/or to

    nancial close.

    Ensure that the evaluation/nalisation plan is fully consistent

    with the RFP and provides clear direction to the evaluation

    team in respect of precise criteria, evaluation tools, compara-

    tive measures, innovation and aesthetics measures, relative

    risk assessment, the application of the PSC and the like.

    Understand that certain options and alternatives may be

    mutually exclusive (or result in cumulative impacts) and

    evaluation nalisation should include consolidation of each

    proponents proposal inclusive of the selected options.

    The consolidated Contract document must accurately and

    comprehensively incorporate the particular value aspects of

    the proposal and the resolution of uncertainties during the

    Evaluation/Finalisation Phase.

    Eciencies in Major Project Procurement | 39VOLUME 1

  • 7/28/2019 Procurement Benchmarking Volume 1 Final

    40/43

    Procurement

    Phase

    Qualitative

    BenchmarkDescription Enabling Actions

    Evaluation /

    Finalisation Phase

    The Evaluation /

    Finalisation processreasonably minimises

    Proponents eort and

    costs.

    The Evaluation

    / Finalisationaddresses:

    timeliness;

    legal costs and

    eort; and

    release or

    suspension of

    unsuccessful

    Proponents.

    Ensure the early undertaking of actions to resolve issues

    which have the potential to delay or alter the Evaluation/Finalisation process.

    To the extent that changes to the Evaluation/Finalisation

    program or to the Evaluation/Finalisation process become

    unavoidable, advise the Proponents as soon as possible.

    Ensure that the Agency resources, manages coordinates,

    undertakes and concludes the EOI evaluation in the

    minimum reasonable time.

    Evaluate the Proposals within the time advised in the prior

    information, the Evaluatio