processflow analysis of baylor institute of...
TRANSCRIPT
![Page 1: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/1.jpg)
I I I I I
PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF REHABILITATION
OCCUPATIONAL THERAPY SCHEDULING SYSTEM
I I
Amy S. Edmiston and
Christopher C. Raps
I I
Senior Design Project May 14, 1993
I I I Dr. Richard Barr
I
I
I
![Page 2: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/2.jpg)
TABLE OF CONTENTS
I. Management Summary
Page
II. Introduction ........................................1
Purpose ..........................................1
Problem Background .................................2
Constraints......................................... 5
Analysis of Situation .................................5
Technical Description ................................7
Conclusion ........................................9
Glossary ..........................................11
APPENDICES
Organizational Chart .................................A
Scheduling Board ....................................B
Magnet Example ....................................C
Data Record Information ..............................D
FlowChart.........................................E
Pseudo Code .......................................F
Therapy Teams .....................................G
Therapist Levels ....................................H
![Page 3: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/3.jpg)
I I
Process Flow Analysis of Baylor Institute of Rehabilitation
Occupational Therapy Scheduling System
Amy S. Edmiston & Christopher C. Raps
Management Summary
The patient treatment schedule for the Occupational Therapy Department
I at Baylor Institute for Rehabilitation is currently displayed on a large
magnetic board. This board is sufficient to display the necessary
information, but is outdated in comparison with the rest of the
• rehabilitation facility.
Each day the program specialists of each therapy team must reschedule
the patients who are seeing therapists who are off. The rescheduling is
now done by a manual trial and error system. This process could more
quickly and efficiently be completed by a computer system.
We chose to view this situation as a process flow analysis problem. First,
we documented the current system of scheduling. This documentation
outlined how the system is currently operated, what the constraints are
governing the rescheduling, and how it could be improved. We then
developed a flow chart and pseudo code that outlines the pattern that a
computer would follow in solving this model. The model is to be used in
order to help BIR in the implementation of a effective, reliable computer
system.
I I
![Page 4: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/4.jpg)
I As submitted to Dr. Richard Barr for CSE 4395 Senior Design project, Southern
Methodist University, May 14, 1993.
I PROCESS FLOW ANALYSIS OF BAYLOR INSTITUTE OF REHABILITATION
I OCCUPATIONAL THERAPY SCHEDULING SYSTEM
Amy S. Edmiston & Christopher C. Raps
I Introduction
In January, Mr. Tom Freeman came to our Senior Design class to discuss
Ipossible ideas for Senior Design projects at Baylor Hospital. He offered
a number of ideas, but one caught our attention. It was a scheduling task
in the Occupational Therapy Department at Baylor Institute for
Rehabilitation. This project seemed like a worthwhile effort and offered I a chance for us to use our knowledge of management science to get
Iinvolved in an application that would help the community.
I Purpose
The purpose of our study of the Baylor Institute of Rehabilitation was to
I help the Baylor Occupational Therapy Department develop a new process
Iby which to schedule the patient therapies. The current process consists
of a magnetic scheduling board which involves manually scheduling
patients for the next day. This is done by physically rearranging the
magnets that represent patient therapies. Our goal was to gather
information in order to understand the existing process, then to design a
I new, more efficient way for the Occupational Therapy Department to
schedule patients.
I I
1
I
![Page 5: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/5.jpg)
I I By developing a new system for rescheduling patients at BIR we hope to
save the department time and money, and to make the it run more
efficiently. The program specialists are the staff members most directly
affected by the current system, because they reschedule the patients every
afternoon. However, the entire therapy staff depends on the accuracy and
clarity of the schedule board in order for the department to operate in an
orderly manner. There were many constraints that had to be brought into
consideration before an accurate and feasible solution could be attained.
Our written analysis and recommendations, as well as an oral
presentation, will be presented to Mr. Tom Freeman and Ms. Tracey
Holden of the Management Engineering Department of Baylor Health
Care System.
Problem Background
At Baylor Institute for Rehabilitation the Occupational Therapy
Department is divided into four teams, each led by a specific doctor.
There is the Traumatic Brain Injury (TBI) team lead by Dr. Thomas; the
Cerebra-Vascular Accident (CVA) team, led by Dr. Rowe; the Spinal
Cbrd Injury (SCI) team, led by Dr. Bruce; and the General team which
is led by Dr. Porter. These doctors order the patients' therapies and also
collaborate with their teams once a week to discuss their patients'
progress. The therapy teams rotate each month so that the therapists
work with all the different doctors as well as the different types of
injuries. The structure of the Occupational Therapy Department itself is
shown in Appendix A. This structural chart does not include the doctors
I2
![Page 6: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/6.jpg)
as they are employed by the hospital and not by the Occupational
Therapy Department itself.
As shown in the chart, each team has a program specialist that leads the
team within the Occupational Therapy Department. The program
specialists, the OTR H's and the OTR I's are the staff who are regularly
scheduled with therapies. There is an Aquatics Program Coordinator on
board who performs therapies in the pool as they are ordered by the
doctor. There is also a Positioning Program Coordinator who performs
specialized therapies according to the patients needs. Both of these
therapists can do pick-ups as necessary. All the therapists are limited to a
certain number of therapy treatments per day. The different levels of
seniority determine the number of treatments a therapist is allowed in an
eight hour work day. The program specialists can see four patients, twice
a day; the OTR II can see five patients twice a day; and the OTR I can
see six patients twice a day. These limits are included in the constraints
over the rescheduling of patients within the department.
At Baylor Institute for Rehabilitation the scheduling is now done
manually. They have a large magnetic scheduling board along one wall.
Across the top of the schedule board are the names of the therapists,
organized by group. Down the left side of the schedule board are the
therapy times, from 8:00 a.m. to 5:00 p.m., staggered in half hour
increments. An example of what the board looks like, with sample
therapies, is found in Appendix B. The scheduling is now done by
attaching colored magnets to the scheduling board. These magnets
contain the patient's name, the therapy time, and the regular therapist. An
I 3
![Page 7: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/7.jpg)
example of the information on the magnet is found in Appendix C. The
magnet is placed on the space on the board corresponding to the
appropriate therapist and time. The color coding specifies the team to
which the patient is assigned.
Each afternoon two of the program specialists perform the rescheduling
of patients for the next day. The program director attaches a slip of paper
to the board telling the program specialists who will be off the next day
and when. It is then the program specialists job to reschedule these
therapists' patients to other available therapists. In an ideal situation the
patients would be treated at the same time that they normally see their
therapist. At the present time the program specialists complete the
rescheduling by a manual trial and error system. They take a patient's
magnet, find another open slot in the same half hour period, check to see
if the reschedule meets the constraints, and places the magnet on the
board in the new time. The magnet is placed at an angle to signify that it
is a pick-up. They repeat this process for all the patients who normally
see therapists who are going to be gone. The next day, the program
specialists take all the angled magnets and return them to their proper
time and therapist before beginning the rescheduling task again.
This process is quite time consuming and very inefficient. It does
however get the job task done correctly. It is imperative that all the
necessary constraints be incorporated into the scheduling model in order
to assure that the output it produces is legitimate. If the schedule
produced by a computer system is erroneous, it has not saved the
program specialists any time or energy.
I
![Page 8: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/8.jpg)
I I
Constraints
IThe constraints that direct the rescheduling of patients are as follows:
1. According to the individual therapist's training level, he/she has a limit to the number of therapies that can be performed in a given day.
2. On certain days, the therapists have hour-long team meetings and cannot see patients during these times.
3. Certain therapies require specific therapists, such as the aquatic therapy, and cannot simply be rescheduled to anyone.
4. Female therapists who are pregnant cannot see any patient who is possibly infectious.
I Analysis of Situation
During our first meeting at Baylor, we met with Tom Freeman, Director
I of the Management Engineering Department, Judy Waterston, Executive
Director of the Baylor Health Care System, Derrick Moore, Hospital
Controller, and Janna Irwin, the Director of Information Services. We
explained that we were considering BIR as the focus for our Senior
Design project. They informed us that the Occupational Therapy
Department had requested assistance in improving the department's
scheduling system. They admitted that the current system is somewhat
Iout of date and inefficient. On that note, we accompanied Tracey Holden
to the Occupational Therapy Department where we met with Julie
I Jordan, the Director of Occupational Therapy.
I5
I
![Page 9: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/9.jpg)
I I
Julie then introduced us to the scheduling board and gave us an idea of
how it works. She also gave us all the information about the various
teams within the Occupational Therapy Department and showed us how
the department is organized. Later we sat down to determine the best
way to view the problem so that we could develop a model to improve
the situation.
On another visit to BIR we met with the program specialists who were
doing the rescheduling for the next day. We talked with them about the
current method, and then observed as they completed the rescheduling
task. We made notes on the method to make our investigation of a new
implementation more complete. We had to be sure we covered
everything that needed to be included in the model
Upon review of our notes and further investigation of Baylor's therapy
department , we came to the conclusion to view this situation as a process
flow analysis problem. We found that the best way in which we could
help the therapists was to begin by documenting the current system of
scheduling that Baylor uses. Next we developed a flow chart and pseudo
code that together with the documentation, would be the necessary
groundwork that a private software company could use to develop a
working computer system for the Occupational Therapy Department of
Baylor Institute for Rehabilitation. The flow chart for the rescheduling
process is found in Appendix D and the pseudo code is found in
Appendix E.
I I I I I I I I I I I I El H I1 I
![Page 10: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/10.jpg)
[] [1
One important factor of the current scheduling board that a new system
Iwould need to match is the high visibility of it. Although to the novice
eye the board seems quite obscure and difficult to understand it does
represent the information well. Our solution to this obstacle is to display
I the daily therapy schedule on terminals around the therapy area in much
the same way that airlines display flight information in the airport. In
order to do this the database would need to sort the therapy schedule
information by therapy time and then send it to the display terminals.
This would create easy access to the necessary patient information, and
eliminate any drawbacks to implementing the new system.
Technical Description
The necessary information would be stored in a database containing the
Iinformation as described in the Data Record Information, Appendix D. I The program begins when the user inputs the therapist who is going to be
I off and for what length of time. The computer then goes to that I I
therapist's schedule and locates the first patient that needs to be
rescheduled. The computer then checks the patient's record for the team
Icode. The computer then locates the first therapist in the appropriate
team. First a check is made to see if the patient is possibly infectious,
and if so, then a second check is made to see if the therapist being I considered is pregnant. If both checks are positive then the search
continues to the next therapist.
I I I
7 1
![Page 11: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/11.jpg)
If the first constraint is met, the computer checks the therapist's schedule
to see if they have the necessary time slot free. If the time slot is
available the computer checks to see if the therapist is at their maximum
number of treatments for the day. If not, then the computer inserts the
patient into the new time slot, and starts over with the next rescheduling.
If the therapist is at the maximum number of treatments then the
computer goes on to the next therapist in the database.
If the computer does not find a match for the patient within their team,
then it moves on to the other therapists in the department. If no match
can be made the computer returns to the patients record and finds another
time slot in which the patient is free. Then it repeats the process as
described above with the new time.
When all the patients have been rescheduled, the computer sorts the
patient record information by therapy time and sends it to the display
monitors. The updated patient schedules are then printed out and sent to
each individual patient's floor, so the staff knows where the patients will
be during the day.
TO
I I I 1 I I I I I I I I I I I I I I I
![Page 12: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/12.jpg)
Conclusion
After working on our project, and spending a fair amount of time
postulating why this system was never revamped and updated before, we
gained a better understanding of the saying "if it ain't broke don't fix it".
For the therapy staff, their scheduling board had been a dependable
scheduling system for the last twenty years, so they saw no real reason to
change it. However as the number of patients increased, they saw that
their reliable way of scheduling was starting to show its imperfections.
The time that it took to reschedule all of the new patients, and
consequently the additional staff that would be required to handle this
increase was quickly becoming too large of a problem to ignore.
Since BIR had never documented the process, they did not have any real
Inotion of where to start the process of exploring a new way in which to
schedule the patients. With our process flow analysis, which includes the
complete documentation of how their present system works, the pseudo
code and flowchart that contains our suggestion of how to build a new
system that is very user friendly and much more efficient, they now have
the information to take to a software company for the final step of the
project to be done: the actual implementation of the new computerized
system with the display terminal readouts.
Throughout this project we never actually came across any type of
limitations that could stop BIR from implementing our suggestion for
creating a more efficient scheduling system. In the beginning Tom
Freeman related that we should not consider funding a constraint, as long
as the recommendations were reasonable. In fact, since our analysis
I I I I I I I I I
I I I U I I I I I
![Page 13: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/13.jpg)
I I I I I I I I I I I I I I I I I I I
completes the background work that a software company would have to
assess themselves, we have made any type of financial limitation that
Baylor might encounter, much less of a problem.
The staff at Baylor was extremely helpful and friendly. They seemed
open to whatever ideas we introduced to them and were very tolerate of
our "nosing around" in the Occupational Therapy Department. Everyone
we encountered was very patient in explaining any questions we had
regarding the department and how it was run. The staff does seem to
realize that the schedule board is outdated and seemed delighted that we
were working to help them improve their work environment.
10
![Page 14: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/14.jpg)
I I I I I I I I I I I I I I I I I I I
GLOSSARY
aide - staff member at BIR who assists with therapies as needed.
BIR - Baylor Institute for Rehabilitation.
CVA - cerebra vascular accident.
General - any therapy that does not fall under one of the other three
categories; i.e. bums, broken bones etc.
OTR I - occupational therapy resident; staff level.
OTR II - occupational therapy resident; senior therapist.
pick up - when a therapist treats a patient who is normally treated by
another therapist.
program specialist - leader of the therapy team; in charge of
rescheduling.
Sc! - spinal chord injury.
TBI - traumatic brain injury.
team - a group consisting of one program specialist and two or three
other therapists who work under one of the four doctors on
specific types of patients.
transporter - staff member at BIR who transports patients from their
rooms to the therapy area.
11
![Page 15: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/15.jpg)
APPENDICES
![Page 16: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/16.jpg)
Occupational Therapy Organizational Chart
I Gen. Program
I
CVA ProgramI
TBI Program SCI Program Specialist Specialist Specialist Specialist
0Th II OTR I 0Th I OTR I
0Th I LOTR I LOTR I —OTR I
OThI LOTRI
Ide
IAide _
Aide Aide _
Aquatics Positioning Program Program
Coordinator Coordinator (pick-ups) (pick-ups)
ro
— — — — — — — — — — — — — — — — — — —
![Page 17: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/17.jpg)
SD1
TEAM 1 (General Program Specialists)
PROG SPEC OTR II OTR I OTR I TIME
8:00 Pink DHF Pink DDS Pink ALL
8:30 Scheduled Team Meeting
9:00
9:30 Pink DDF Pink DDS Pink UYH Pink LKK
10:00 Pink CKL Pink UYI-1 Pink GYI-1
10:30 Pink GYH Pink UYH
11:00 Pink JGK Pink LHD Pink GYH
11:30 Pink TTH Pink LHD Pink ZVC
12:00 Pink ZVC PinkRUl Pinc LHD
12:30 PinkRUl Pink ZVC
1:00 PInkGHT Pink 000 PinkRUl
1:30 Pink EER Pink QQO Pink OPU
2:00 Pink OPU Pink YOU Pink QQO
2:30 Pink YVW
3:00 Pink OWE Pink YVW Pink POL Pink YOU
3:30 Pink POL Pink YVW
4:00 Pink YOU Pink POL
4:30 Pink TTY Pink OPU
I I I I I I I I I I I I I I I I I II
![Page 18: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/18.jpg)
SD1
TEAM 2 CVA Group Therapy
Proa SDec OTR I OTR I
Blue DDS Blue TUR
BLue LKK Blue RYT
Blue EYR
Blue UYH Blue FHG
Blue TUR Blue GTh Blue SHD
Blue ASD
Blue AFS Blue LHD Blue WOl
Blue P01 Blue ZVC Blue VNB
Blue EJK Blue NCB
Scheduled Team
BLue FHG Blue ONB
Blue WTY Blue YOU Blue OPW
Blue QPL Blue YVW Blue WKJ
Blue THE Blue POL Blue GGG
Blue OPU
Blue TUR
Page 2
![Page 19: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/19.jpg)
SD1
TEAM 3 TBI Group Therapy
Pro g Spec OTR I OTR I
Green PLG Green DKJ
Green_QKL
Green_DKl
Scheduled Team Meeting
Green GSD Green QLO
Green IOJ Green TKJ
Green AKJ Green OlD
Green AHS Green HFD
Green P01 Green QKD
Green WEIR Green QHD Green OYT
Green VHF
Green FHG Green AJS Green FHS
Green YUI Green AKJ
Green OWE Green AQD
Green ASD Green GJF
Green JHS Green QKd Green JSA
Green 010 Green FHW
Page 3
![Page 20: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/20.jpg)
SD1
TEAM 4 SCI Group Therapy
Prog Spec OTR I OTR I OTR I
Yellow 1FF Yellow HSI
Yellow WIU Yellow IUH
Yellow FHJ Yellow WSD Yellow LLL
Yellow ALA Yellow JKD
Yellow JSH Yellow AAS Yellow UHG Yellow JGH
Scheduled Team Meeting
Yellow UWE Yellow USA Yellow KKH
Yellow JAS Yellow AAS Yellow JVV Yellow CCI
Yellow KAA Yellow CCH
Yellow KSI Yellow DUF Yellow HHD
Yellow DUI Yellow VHD
Yellow KHM Yellow DWI
Yellow JDS Yellow BUI
Yellow UIH Yellow YHD Yellow PPK
Yellow HDF Yellow HKD Yellow HFG Yellow PPO
Yellow QlO Yellow VHH Yellow 110
Yellow JNM Yellow VVH 1 Yellow DDJ
I I I I I [1 F^
I I I I I I I I I UI I Page 4
![Page 21: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/21.jpg)
I I I I I I
SD1
IAcivatics Director I
I Water TTT I I
I Water JFH I I
I Water LLL I I
I Water IF I I
I I I I I I I I I I I Page 5
![Page 22: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/22.jpg)
I •1 I I I I I I I I I I I I I I I I I
LI1
John Kasigan Johnson
9:30 A. M.
Judy Frangensin
Appendix C
![Page 23: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/23.jpg)
I I DATA RECORD INFORMATION
NEEDED FOR SOFTWARE I TO GENERATE DAILY PHYSICAL THERAPY SCHEDULES
I The data below will be read in from individual records to find a successful match of patient to therapist. Once a successful match has been found, then the new record generated, which includes the patients name, therapy type, I team assigned, time assigned and the physical therapist who will administer the therapy will be sent to the output screen.
PHYSICAL THERAPIST:
1. CLASSIFICATION LEVEL
a. Program Specialist b. OTR II Senior Therapist c. OTR I Staff Therapist
2. PREGNANT THERAPIST
a. Yes b. No
3. THERAPY TEAM
a. General Group Therapy b. CVA Group Therapy c. TEl Group Therapy d. SCI Group Therapy
4. THERAPISTS NAME
5. OPEN TIME SLOTS
Appendix D
I I
![Page 24: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/24.jpg)
I I
PATIENT
1. INJURY IS INFECTIOUS
a. Yes b. No
2. PATIENTS NAME
3. TYPE OF THERAPY NEEDED
4. WHAT TEAM THEY ARE ASSIGNED TO
a. General Group Therapy b. CVA Group Therapy c. TBI Group Therapy d. SCI Group Therapy
5. ADDITIONAL OPEN TIME SLOTS IF NO MATCH IS FOUND
I
![Page 25: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/25.jpg)
CODE IS GENERAL
CODE IS CODE IS CVA
I I TBICODE IS
SCI
User inputs Pt's I I that are off and locate 1st I Check and store ^Check patients
rp I when I I U LIent 111 I tnerapy time i I record for code
BEGIN SEARCH FLOW CHART FOR
IN DESIGNATED
B.I.R SOFTWARE TEAM SCHEDULE ro
GO TO FIRST AVAILABLE
P..T..
IS P.T PREGNANT
no continue constraint chk
Does P.T have needed time?
yes GO TO NEXT IS PATIENT AVAIL P.T INFECTIOUS I
no TEAM
if no match anywhere
12 es
check patients sched
for next open time. if none found Drop patien I no Does this exceed therapy for day. I
maximum?I
INSERT 0 TO NEXT PATIENT IN heck P.T. rec for
NOPATIENT begin process again yes of pat. allowed
send vat & time to screen
- - - - - - - - - - - - - - - - - - -
![Page 26: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/26.jpg)
I I PSEUDO CODE FOR BAYLOR INSTITUTE
FOR REHABILITATION
User input s the therapist that is going to be off and when.
Starting at the beginning of that therapist's schedule, locate the first patient in the database.
Check patient's record for patient's code: Team 1 = General Team 2 = CVA Team 3=TBI Team 4 = SCI
Once patient's team is determined begin search in designated team's work schedule.
Within the team's schedule go to first available therapist's schedule.
First check for infectious patient and pregnant therapist.
Check the patient's record to see if he/she is possibly infectious
If yes then check therapist's record to see if she is pregnant
IIf the therapist is pregnant then move on to
next therapist's record
Else continue constraint check
Else continue constraint check
I Appendix F
I
![Page 27: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/27.jpg)
I I
Next check to see if therapist has time needed free and if so, check to see if the therapist has their maximum number of patients allotted for the day.
If therapist has the needed open time slot then
Read therapist's record to determine how many therapies they are allowed per day. (call this MAX)
Count number of scheduled patients therapist already has scheduled for that day.
If number >= MAX goto next therapist's schedule
Else if number < MAX insert patient into time slot.
Else goto next therapist's schedule until end of file is reached.
Search through other teams schedules.
If no match is found, repeat search through next team.
Search through specialized therapists schedules.
If no match is found within the regularly scheduled therapists check aquatics therapist and positioning program therapist's schedules.
II
![Page 28: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/28.jpg)
I I I I I I I I I I I I I I I I I I I
Search patient's schedule for new time.
If a match is still not found then check patient's schedule for open time slot.
Repeat search through regular team therapists for new open time.
Repeat until all patients have been rescheduled.
Display of data.
When all patients have been rescheduled, sort patient record files by time and send to display monitors.
![Page 29: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/29.jpg)
ITherapy Teams
General
• Dr. Porter
I Traumatic Brain Injury (TBI)
•
I Cerebra-Vascular Accident (CVA) Dr. Rowe
I Spinal Chord Injury (SCI) Dr. Bruce
jAppendix G
![Page 30: PROCESSFLOW ANALYSIS OF BAYLOR INSTITUTE OF …s2.smu.edu/emis/design/wp-content/uploads/93-01-baylorrehabilitation... · I As submitted to Dr. Richard Barr for CSE 4395 Senior Design](https://reader034.vdocuments.us/reader034/viewer/2022042022/5e79fde9e0173f1b98680168/html5/thumbnails/30.jpg)
1 Therapist Levels j i Program Specialist
• 4 patients - twice a day
OTR2 - Senior Therapist 5 patients - twice a day
• OTR1 - Staff Level
• 6 patients - twice a day
j Aide Iassists with therapies as needed
I Transporter I transports patients from their rooms to the therapy area
IAppendixH