process flow map

18
JSTEPS Rev. No. 2 Rev. Date: June 1, 2005 Approved by: B. Herrington SM Page: Copyright © 2005 by Jacobs Engineering Group Inc. All rights reserved. The contents of this document are proprietary and produced for the exclusive benefit of Jacobs Engineering Group Inc. and its affiliated companies. No part of this document may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without the prior written approval of Jacobs Engineering Group Inc. The current applicable version of this publication resides on Jacobs' Intranet. All copies are considered to be uncontrolled. Macro Phase Map - Chemical Process Industry (CPI) PHASE PHASE 1 OPPORTUNITY ANALYSIS PHASE 3 PROJECT DEFINITION PHASE 4 DETAILED DESIGN / PROCUREMENT PHASE 5 CONSTRUCTION PHASE 6 START-UP PHASE 7 CLOSEOUT PHASE 2 CONCEPTUAL DESIGN Note: See Glossary following CPI Cross- Functional Maps for explanation of abbreviations and definitions. 1. Identify business opportunity 2. Assess market 3. Identify and evaluate options 4. Obtain key supplier input 5. Analyze risk and impacts (sociological, technological, economic, political, environmental) 6. Initiate Project Execution Strategy 7. Identify Gate Keeper 1. Select team and align to project objectives 2. Confirm preferred concepts, Design Basis and scope with client 3. Complete alternative analyses and testing studies 4. Develop concept(s) into preliminary scope documents 5. Identify regulatory and permitting requirements 6. Initiate environmental impact assessment 7. Conduct constructability and safety reviews, and initiate modular studies 8. Initiate Project Execution Plan including work sharing and modular opportunities, PQP 9. Identify long lead/critical equipment 10. Initiate geotechnical studies 1. Align team to project objectives 2. Confirm project objectives: scope, cost, schedule, etc. 3. Translate project concept into preliminary engineering and design documents 4. Conduct design reviews for constructability, safety, maintainability and operability 5. Finalize purchase order and contract terms and conditions 6. Prepare to procure critical and long lead equipment/materials 7. Prepare applications for necessary permits/licenses 8. Finalize modular application plans 9. Gate Keeper freezes scope 1. Align team to project objectives 2. Initiate change management 3. Procure, expedite, and inspect equipment and materials 4. Manage vendor data 5. Develop and issue construction documents (IFC) 6. Coordinate internal and external interfaces 7. Conduct design reviews (constructability, safety, maintainability, operability, etc.) and incorporate into the design 8. Obtain regulatory authority approval (e.g. FDA, environmental) 1. Align team to project objectives 2. Procure construction equipment, materials and construction services 3. Develop detailed, integrated project schedule 4. Manage construction site safety and environmental programs 5. Review submittals 6. Coordinate site activities 7. Manage QA/QC program 8. Manage labor relations program 9. Construct facilities in accordance with contract requirements 10. Continue change management 11. Red line construction documents 12. Achieve construction turn over 13. Provide technical support 1. Select and align team to project objectives 2. Coordinate inspections by regulatory authorities 3. Plan sequential testing and start-up of completed facilities 4. Assist with operator training 5. Record changes to construction documents 6. Continue change management 7. Complete Pre-startup Safety Review 8. Provide technical support 1. Conduct Lessons Learned sessions and compile for total project 2. Close purchase order and contract accounts 3. Assemble and archive project files 4. Return all client assets 5. Resolve any claims or disputes 6. Resolve any warranty issues 7. Obtain final acceptance certificate and final payment 8. Prepare project benchmarking data and feed back into system 9. Prepare final cost accounting 10. Conduct Operability Assessment KEY ACTIVITIES Ongoing activities: Progress Reports, Client Expectations, CSIPS, Client Surveys, Quality Audits and Measurements, Cost and Schedule Control, TIC Trending, Execution & Reporting of Jacobs VEPS/Innovation, Jacobs Value Plus, Lessons Learned KEY DELIVERABLES 1 of 2 Close-out may occur at the end of any phase PHASE OVERLAPS Opportunity Analysis Conceptual Design Project Definition Detailed Design/Procurement Construction Start-up Closeout OBJECTIVES Identify potentially beneficial business opportunity and perform initial analysis, scoping and Order of Magnitude Estimate to determine whether opportunity is worth further investigation. Select best of identified project approaches, analyze concept(s) and prepare Study Cost Estimate, to confirm project viability. Finalize technology, project objectives, process and design scope definition, major equipment pricing and Project Execution Plan to support a Budget Cost Estimate and funding request. Manage, coordinate and perform design activities and equipment procurement necessary for procurement, construction, commissioning and start- up. Mobilize and manage the construction forces and perform other activities including procurement necessary to construct the facility in accordance with the construction documents. Perform commissioning and operating activities required to achieve design performance levels. Perform regulatory, contractual, archival and Jacobs required activities to close the project in an orderly fashion. 1. Project Objectives 2. Phase 1 Report: -Market Study -Definition & Evaluation of Options -Alternative Analysis & Test Study Plan for Developmental Projects - Regulatory and Permitting Requirements Evaluation -Order-of-Magnitude Cost Estimate (+50% to -30%) - Economic Analysis -Risk Analysis - Project Execution Strategy -Milestone Schedule 3. Recommendations for Path Forward 1. Updated Project Objectives 2. Project Execution Plan 3. Project Procedures 4. Process Description 5. Process Design Guide & Criteria 6. Design Safety & Environmental Plan 7. Preliminary Site Plan & Plot Plan, PFDs, H&M Balance, Prelim. Building Sizes, Material Selection for Equipment and Pipe, Equipment List with Process Design Data, Long Lead / Critical Path Equipment Data Sheets, Preliminary Motor List 8. Control Systems Philosophy 9. Utility Summary & Infrastructure Requirements 10. Level II EPC Schedule 11. Study Estimate (+30% to -20%) 12. Overall Economic Analysis 13. Phase 2 Report 14. Recommendations for Path Forward 15. Catalyst & License Agreement 1. Updated Project Objectives 2. Updated Project Execution Plan 3. Updated Project Procedures 4. Updated Process Description 5. Design Basis 6. Site & Plot Plans, Equipment Location Plans, Preliminary Piping Layout Model (All lines on P&IDs), PFDs & H&M Balance (IFD), Material Selection Diagrams, Process & Utility P&IDs (IFD), Building Plans & Elevations, Equipment List & Data Sheets, Line Lists, Tie-in List, Fire Protection Rqmnts (for est.), Electrical Single Lines, Motor List, Area Classes, Control Systems Index & Specifications for Special Instrument or Control Rqmnts, Geotechnical Report. 7. Requests for Quotes & Bid/Bid Tab (Maj. Eq.) 8. Purchase Requisitions (Maj. Eq.) 9. Appropriate Regulatory and Permitting Documents 10. Resource Loaded EPC Schedule 11. Budget/Control Estimate (+10% to - 5%) 12. Updated Economic Analysis 13. Phase 3 Report (If Req.) 14. Recommendations for Path Forward 1. Updated Project Objectives 2. Updated Project Execution Plan 3. Updated Project Procedures 4. Request for Quotes & Bids/Bid Analysis 5. Purchase Order Documentation 6. Construction Documents (IFC) 7. Control Systems Programs/ Software 8. Appropriate Permit Applications 9. Detailed, Resource Loaded Construction Schedule 10. Project Data Books 11. Change Control Documents 12. Vendor Data 13. Subcontract Technical Documents and Packages 1. Procurement/Contract Documents 2. Updated Project Execution Plan 3. Updated Project Procedures 4. Construction Permits 5. Safety Program and Documentation 6. Updated Construction Schedule 7. Constructed Facility 8. QA/QC and Check-out/Completion Documentation 9. Red Line Documentation (As- Builts) 10. Change Control Documents 11. Turnover of Spare/Change Parts 12. Turnover Documentation 1. Commissioning/Start-up Plan and Procedure 2. Start-up Schedule 3. Operating, Maintenance and Training Manuals 4. Record Documentation (Completed As-Builts) 5. Pre-start-up Safety Review Report 6. Facility Operating at Specifications 7. Performance Plan and Test Documents 1. Closeout Plan 2. Project Closure Notice 3. Final Project Report 4. Project Completion Report 5. Lessons Learned 6. Warranty File 7. Archive Log 8. Final Acceptance Documents 9. Final Invoice 10. Benchmarking Data

Upload: cal

Post on 22-Oct-2015

170 views

Category:

Documents


11 download

DESCRIPTION

Process

TRANSCRIPT

Page 1: Process Flow Map

JSTEPS

Rev. No. 2Rev. Date: June 1, 2005Approved by: B. Herrington

SM

Page:

Copyright © 2005 by Jacobs Engineering Group Inc.All rights reserved. The contents of this document are proprietary and produced for the exclusive benefit of JacobsEngineering Group Inc. and its affiliated companies. No part of this document may be reproduced, stored in a retrievalsystem, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise,without the prior written approval of Jacobs Engineering Group Inc.

The current applicable version of this publication resides on Jacobs' Intranet. All copies are considered to be uncontrolled.

Macro Phase Map - Chemical Process Industry (CPI)

PHASE PHASE 1OPPORTUNITY

ANALYSIS

PHASE 3PROJECT

DEFINITION

PHASE 4DETAILED DESIGN /

PROCUREMENT

PHASE 5CONSTRUCTION

PHASE 6START-UP

PHASE 7CLOSEOUT

PHASE 2CONCEPTUAL

DESIGN

Note: See Glossary following CPI Cross-Functional Maps for explanation ofabbreviations and definitions.

1. Identify business opportunity2. Assess market3. Identify and evaluate options4. Obtain key supplier input5. Analyze risk and impacts

(sociological, technological,economic, political, environmental)

6. Initiate Project Execution Strategy7. Identify Gate Keeper

1. Select team and align to projectobjectives

2. Confirm preferred concepts, DesignBasis and scope with client

3. Complete alternative analyses andtesting studies

4. Develop concept(s) into preliminaryscope documents

5. Identify regulatory and permittingrequirements

6. Initiate environmental impact assessment7. Conduct constructability and safety

reviews, and initiate modularstudies

8. Initiate Project Execution Planincluding work sharing and modularopportunities, PQP

9. Identify long lead/critical equipment10. Initiate geotechnical studies

1. Align team to project objectives2. Confirm project objectives: scope,

cost, schedule, etc.3. Translate project concept into

preliminary engineering anddesign documents

4. Conduct design reviews forconstructability, safety,maintainability and operability

5. Finalize purchase order andcontract terms and conditions

6. Prepare to procure critical and longlead equipment/materials

7. Prepare applications for necessary permits/licenses8. Finalize modular application plans9. Gate Keeper freezes scope

1. Align team to project objectives2. Initiate change management3. Procure, expedite, and inspect

equipment and materials4. Manage vendor data5. Develop and issue construction

documents (IFC)6. Coordinate internal and external

interfaces7. Conduct design reviews

(constructability, safety,maintainability, operability, etc.) andincorporate into the design

8. Obtain regulatory authorityapproval (e.g. FDA, environmental)

1. Align team to project objectives2. Procure construction equipment,

materials and construction services3. Develop detailed, integrated project

schedule4. Manage construction site safety

and environmental programs5. Review submittals6. Coordinate site activities7. Manage QA/QC program8. Manage labor relations program9. Construct facilities in accordance

with contract requirements10. Continue change management11. Red line construction documents12. Achieve construction turn over13. Provide technical support

1. Select and align team to projectobjectives

2. Coordinate inspections byregulatory authorities

3. Plan sequential testing and start-upof completed facilities

4. Assist with operator training5. Record changes to construction

documents6. Continue change management7. Complete Pre-startup Safety

Review8. Provide technical support

1. Conduct Lessons Learnedsessions and compile for totalproject

2. Close purchase order andcontract accounts

3. Assemble and archive project files4. Return all client assets5. Resolve any claims or disputes6. Resolve any warranty issues7. Obtain final acceptance certificate

and final payment8. Prepare project benchmarking

data and feed back into system9. Prepare final cost accounting10. Conduct Operability Assessment

KEYACTIVITIES

Ongoing activities: Progress Reports, Client Expectations, CSIPS, Client Surveys, Quality Audits and Measurements, Cost and Schedule Control, TIC Trending, Execution & Reporting of Jacobs VEPS/Innovation, Jacobs Value Plus, Lessons Learned

KEYDELIVERABLES

1 of 2

Close-out may occur atthe end of any phase

PHASEOVERLAPS

Opportunity AnalysisConceptual Design

Project DefinitionDetailed Design/Procurement

ConstructionStart-up

Closeout

OBJECTIVES Identify potentially beneficial businessopportunity and perform initial analysis,scoping and Order of MagnitudeEstimate to determine whetheropportunity is worth furtherinvestigation.

Select best of identified projectapproaches, analyze concept(s) andprepare Study Cost Estimate, to confirmproject viability.

Finalize technology, project objectives,process and design scope definition,major equipment pricing and ProjectExecution Plan to support a BudgetCost Estimate and funding request.

Manage, coordinate and perform designactivities and equipment procurementnecessary for procurement,construction, commissioning and start-up.

Mobilize and manage the constructionforces and perform other activitiesincluding procurement necessary toconstruct the facility in accordancewith the construction documents.

Perform commissioning and operatingactivities required to achieve designperformance levels.

Perform regulatory, contractual,archival and Jacobs requiredactivities to close the project in anorderly fashion.

1. Project Objectives2. Phase 1 Report:

-Market Study-Definition & Evaluation of Options-Alternative Analysis & Test StudyPlan for Developmental Projects

-Regulatory and PermittingRequirements Evaluation

-Order-of-Magnitude Cost Estimate(+50% to -30%)

-Economic Analysis-Risk Analysis-Project Execution Strategy-Milestone Schedule

3. Recommendations for PathForward

1. Updated Project Objectives2. Project Execution Plan3. Project Procedures4. Process Description5. Process Design Guide & Criteria6. Design Safety & Environmental Plan7. Preliminary Site Plan & Plot Plan,

PFDs, H&M Balance, Prelim. BuildingSizes, Material Selection forEquipment and Pipe, Equipment Listwith Process Design Data, LongLead / Critical Path Equipment DataSheets, Preliminary Motor List

8. Control Systems Philosophy9. Utility Summary & Infrastructure

Requirements10. Level II EPC Schedule11. Study Estimate (+30% to -20%)

12. Overall Economic Analysis13. Phase 2 Report14. Recommendations for Path

Forward15. Catalyst & License Agreement

1. Updated Project Objectives2. Updated Project Execution Plan3. Updated Project Procedures4. Updated Process Description5. Design Basis6. Site & Plot Plans, Equipment

Location Plans, Preliminary PipingLayout Model (All lines on P&IDs),PFDs & H&M Balance (IFD), MaterialSelection Diagrams, Process &Utility P&IDs (IFD), Building Plans &Elevations, Equipment List & DataSheets, Line Lists, Tie-in List, FireProtection Rqmnts (for est.),Electrical Single Lines, Motor List,Area Classes, Control SystemsIndex & Specifications for SpecialInstrument or Control Rqmnts,Geotechnical Report.

7. Requests for Quotes & Bid/Bid Tab(Maj. Eq.)

8. Purchase Requisitions (Maj. Eq.)9. Appropriate Regulatory and

Permitting Documents10. Resource Loaded EPC Schedule11. Budget/Control Estimate (+10% to - 5%)

12. Updated Economic Analysis13. Phase 3 Report (If Req.)14. Recommendations for Path

Forward

1. Updated Project Objectives2. Updated Project Execution Plan3. Updated Project Procedures4. Request for Quotes & Bids/Bid Analysis5. Purchase Order Documentation6. Construction Documents (IFC)7. Control Systems Programs/

Software8. Appropriate Permit Applications9. Detailed, Resource Loaded

Construction Schedule10. Project Data Books11. Change Control Documents12. Vendor Data13. Subcontract Technical Documents

and Packages

1. Procurement/Contract Documents2. Updated Project Execution Plan3. Updated Project Procedures4. Construction Permits5. Safety Program and Documentation6. Updated Construction Schedule7. Constructed Facility8. QA/QC and Check-out/Completion

Documentation9. Red Line Documentation (As-

Builts)10. Change Control Documents11. Turnover of Spare/Change Parts12. Turnover Documentation

1. Commissioning/Start-up Plan andProcedure

2. Start-up Schedule3. Operating, Maintenance and

Training Manuals4. Record Documentation (Completed

As-Builts)5. Pre-start-up Safety Review Report6. Facility Operating at Specifications7. Performance Plan and Test

Documents

1. Closeout Plan2. Project Closure Notice3. Final Project Report4. Project Completion Report5. Lessons Learned6. Warranty File7. Archive Log8. Final Acceptance Documents9. Final Invoice10. Benchmarking Data

Page 2: Process Flow Map

JSTEPS

Rev. No. 2Rev. Date: June 1, 2005Approved by: B. Herrington

SM

Page:Copyright©Jacobs EngineeringGroup Inc., 2005

Phase 1 Phase 2 Phase 3 Phase 4

Front End Loading

Concept Set &Constructability

Review

FormalConstructability

Review

Opportunity Analysis Conceptual Design Project Definition Detail Design / Procurement

Classof Plant(V-13)

ProcessSimplification

(V-18) Energy Optimization (V-15)

Design to Capacity (V-4)Operability &

Maintainability

Customized Standards & Specifications (V-14)

Predictive Maintenance (V-16)

Order ofMagnitude

CostEstimate

PFD DevelopmentStudyCost

Estimate

P & ID / PFD Developmentthrough IFD

DefinitiveCost

Estimate

ValueEngineering

(V-11)

Constructability & Modular Studies (V-3)

Technology Selection (V-19)

PDRIAssessment

(V-9)

PDS Modeling (V-21)

PDRIAssessment

(V-9) orIPA

Evaluation

P & ID / Detailed DesignDevelopment through IFC

ConstructabilityValidated

Change Management (V-22)

Client Expectations (V-1), Client Surveys (V-2), Project Execution Planning (V-5), Interactive Planning (V-6), Lessons Learned (V-7), Team Alignment (V-8), Owner's Objectives (V-10), Value Plus (V-12)

2 of 2

Note: JVEPSSM V-1, V-2, V-5 through V-8, V-10 and V-12 continue through project closure, as applicable. Constructability (V-3), PDS Modeling (V-21) & Change Management (V-22) continue through Phase 5, Construction, as applicable.

Process Reliability Modeling (V-17)

Waste Minimization (V-20)

Jacobs Value Enhancing PracticesSM - Intentional Innovation ProcessJSTEPSSM Macro Phase Map - Chemical Process Industry (CPI)

Page 3: Process Flow Map

JSTEPS

Rev. No. 2Rev. Date: June 1, 2005Approved by: B. Herrington

SM

Page:Copyright©Jacobs EngineeringGroup Inc., 2005

Cross-Functional Map - Chemical Process Industry (CPI)

DESIGNDISCIPLINES

SUPPLYMANAGEMENT

CONSTRUCTION

SUPPLIERS

OTHERS(EXTERNAL)

PROCESSENGINEERING/ENVIRON-MENTAL

OTHERS(INTERNAL)

PROJECTMANAGEMENT/SERVICES

CLIENT

Process Connectoror TerminatorKEY: Decision InvolvementP202 V3 M2

ProcessIndustriesStandardOperatingProcedure

JacobsValueEnhancingPracticeSM

Measurement

See Glossary for explanation ofterms; and definitions of StandardOperating Procedures, ValueEnhancing PracticesSM, andMeasures.

Task(s)

� BusinessObjectives� Client Information� Phase I

- Plan- Budget- Schedule- Deliverables

� Report� Recommendations� Phase 2 Cost

Estimate (Pro-Services)

PHASE 1Opportunity Analysis

� Market Study� Definition & Evaluation

of Options� Alternative Analysis &

Test Study Plan� Regulatory &

Permitting Evaluation� Order of Magnitude

Cost Estimate� Economic Analysis� Risk Analysis� Project Execution

Strategy� Milestone Schedule

� Drawings� Documents

SelectedOptions

PurchaseOrder/Contract

MarketStudy Yes

No

List ofOptions

§ Business Opportunity Identified§ Objectives

Defined

OpportunityEvaluationInitiated

§ BusinessObjectives

§ ClientExpectationsEstablished

§ TeamAlignment

§ LessonsLearnedReview

§ Identify GateKeeper

OptionsAnalyzed &Screened

Market StudyPrepared

EvaluationCompleted &

ExecutionStrategy

Developed

§ Sociological§ Technological§ Economic§ Political§ Environmental

Phase 1Report

Completed

Proceed?

1-9

To Phase 2Task 2-1

Stop or Recycle

1-81-7

1-6

1-41-2

1-1

OngoingActivities

§ Client Survey§ Accounting

QualityAccountingV2

M2 P310M1

M5

V8

V1

V10

V5

P100P131P132

Authorization

1 of 16

V19

OptionsIdentified

§ TechnologySelectionInitiated

1-3

Pilot PlantStudies

V7

To Phase 2Task 2-2

1-10

SelectedOptions

Developed

1-5

Page 4: Process Flow Map

JSTEPS

Rev. No. 2Rev. Date: June 1, 2005Approved by: B. Herrington

SM

Page:Copyright©Jacobs EngineeringGroup Inc., 2005

Cross-Functional Map - Chemical Process Industry (CPI)

DESIGNDISCIPLINES

SUPPLYMANAGEMENT

CONSTRUCTION

SUPPLIERS

OTHERS(EXTERNAL)

PROCESSENGINEERING/ENVIRON-MENTAL

OTHERS(INTERNAL)

PROJECTMANAGEMENT/SERVICES

CLIENT

Process Connectoror TerminatorKEY: Decision InvolvementP202 V3 M2

ProcessIndustriesStandardOperatingProcedure

JacobsValueEnhancingPracticeSM

Measurement

See Glossary for explanation ofterms; and definitions of StandardOperating Procedures, ValueEnhancing PracticesSM, andMeasures.

Task(s)

Preliminary Documents:� Site Plan� Plot Plan� Preliminary Building Sizes� PFDs� Material Selection for

Equipment and Pipe� H&M Balance� Equipment List� Motor List� Control System Philosophy� Utility Summary� Infrastructure Requirements� Catalyst/Chemicals Summary

PHASE 2Conceptual Design

Process Design Guide &Criteria� Class of Plant� Capacity� Product� Site Design Criteria/DataDS&E

Plan

§ Selected Concepts- Process- Technology- Layouts§ Economic Evaluation

ProcessDesignAlternatives

Request for Prices

From Phase 1Task 1-9

To Phase 2Task 2-10

To Phase 2Task 2-11

Phase Initiated

§ Select Team§ Strategy/Kick Off

Meetings§ Client

Expectations§ Class of Plant§ Project Execution

Planning§ Interactive

Planning§ Team Alignment§ Phase 1 Data and

Plant DataValidation§ Lessons Learned

DS&E PlansDeveloped

Design BasisDeveloped

ConceptsDeveloped,Simulated,

Screened &Selected

§ TechnologySelection

§ Relative Economic Evaluation

ConceptualDesign Prepared

§ DisciplineDesigns§ Design to

Capacity§ Process

SimplificationCompleted§ Initiate Process

ReliabilityModeling§ Modular Studies

andConstructabilityInitiated§ Energy

Optimization§ Waste

Minimization§ Commissioning /

Start-Up PlanInitiated

AlternativeAnalysis

Completed

§ Technology§ Licensing§ Market Study§ Pilot Plant

Testing§ Economics

2-3

2-5

2-1

2-7

2-2 2-6

OngoingActivities

§ Client Survey§ Accounting

QualityAccountingV2

M2P310M1

M5

Ongoing:§ Cost Mgt.§ Cost Trending§ Value Plus§ Schedule Mgt.§ Reports§ Lessons Lrnd.

V7V12

M3

M10

M6

P100P131P133

M13

V1V5

V10

V6

V8V7

P100

P202

P201 V4

P203P204

Authorization

2 of 16

Long Lead /Critical PathEquipment

Material PlanDeveloped

2-9

V18

V13

V19

V19

Long Lead / Critical PathEquipment Data Sheets

V3

V17

TechnologyLicensorProposal

2-4

P131

� Project Execution Plan- Project Objectives Updated� Phase 2:

- Budget and Schedule- Deliverables List- Project Procedures

V15

V20

To Phase 3Task 3-8

InitiateGeotechnical

Studies

2-8

Request forGeotechnicalStudies

Request forProposals

From Phase 1Task 1-10

P350

SafetySafety

Technology Licensor Proposal

Page 5: Process Flow Map

JSTEPS

Rev. No. 2Rev. Date: June 1, 2005Approved by: B. Herrington

SM

Page:Copyright©Jacobs EngineeringGroup Inc., 2005

Cross-Functional Map - Chemical Process Industry (CPI)

DESIGNDISCIPLINES

SUPPLYMANAGEMENT

CONSTRUCTION

SUPPLIERS

OTHERS(EXTERNAL)

PROCESSENGINEERING/ENVIRON-MENTAL

OTHERS(INTERNAL)

PROJECTMANAGEMENT/SERVICES

CLIENT

Process Connectoror TerminatorKEY: Decision InvolvementP202 V3 M2

ProcessIndustriesStandardOperatingProcedure

JacobsValueEnhancingPracticeSM

Measurement

See Glossary for explanation ofterms; and definitions of StandardOperating Procedures, ValueEnhancing PracticesSM, andMeasures.

Task(s)

§ Regulatoryand PermittingRequirementsIdentified§ Environmental

ImpactAssessmentInitiated

§ ProjectExecution Plan& ProceduresDeveloped§ Project

ScheduleDeveloped- InteractivePlanning

§ Receipt ofClientSpecifications§ Customized

Standards &SpecificationsInitiated§ Preliminary

Project Site &Labor StudiesDeveloped

� Cost Estimate� Basis of

Estimate� Economic

Analysis

� Report� Path

Forward

PHASE 2 - ContinuedConceptual Design

ConceptPermittingInformation

� Capital Costs� Operating Data

ConceptAgreement

RegulatoryAuthority

� Critical Path EquipmentSizing� Requests for Prices

Phase 2TechnicalDocuments

From Phase 2Task 2-7

From Phase 2Task 2-9

To Phase 3Task 3-1

Stop or Recycle

Reviews Heldfor:§ Constructability§ Design For Safety§ Design Documents§ Operability§ Maintainability§ Commissioning/

Start-Up

§ Study CostEstimate

(+30% to -20%)Prepared- IPA FEL

Assessment or

- PDRI Phase 2Report

Completed

MajorEquipment

Priced

InformationReviewed

2-10

2-11

2-14

2-162-12 2-15

OngoingActivities

§ Client Survey§ Accounting

QualityAccounting

V2

M1 P310

M2M5

Ongoing:§ Cost Mgt.§ Cost Trending§ Value Plus§ Schedule Mgt.§ Reports§ Lessons Lrnd.

V7V12

M3

M10

M6P100P131P133M13

V3

P201

M4

V9 P132PreliminaryDocuments

Proceed ?2-18

Yes

No

3 of 16

Authorization

V20

P203

� Study EstimateBasis� Project

Execution Plan� Project

Procedures� Project

Schedule

2-13

P131

V6

P100

V5

V14

Safety Safety

Project Execution Plan

§ Corporate / Business Goals§ Project Objectives§ Scope of Work§ Risk Management Plan§ Organization Plan§ Milestone Schedule§ Contracting Plan§ JVEPSM Plan§ Constructability Plan§ Design Management Plan§ Supply Management Plan§ Construction Mgmt Plan§ Startup Management Plan§ Environmental Plan§ Cost Management Plan§ Schedule Management Plan§ Project Quality Plan§ Safety Management Plan§ Information Management Plan§ Special Factors Management

Plan

Reference Only

Phase 2 PassGate Reviewand Approval

2-17

P350

Page 6: Process Flow Map

JSTEPS

Rev. No. 2Rev. Date: June 1, 2005Approved by: B. Herrington

SM

Page:Copyright©Jacobs EngineeringGroup Inc., 2005

Cross-Functional Map - Chemical Process Industry (CPI)

DESIGNDISCIPLINES

SUPPLYMANAGEMENT

CONSTRUCTION

SUPPLIERS

OTHERS(EXTERNAL)

PROCESSENGINEERING/ENVIRON-MENTAL

OTHERS(INTERNAL)

PROJECTMANAGEMENT/SERVICES

CLIENT

Process Connectoror TerminatorKEY: Decision InvolvementP202 V3 M2

ProcessIndustriesStandardOperatingProcedure

JacobsValueEnhancingPracticeSM

Measurement

See Glossary for explanation ofterms; and definitions of StandardOperating Procedures, ValueEnhancing PracticesSM, andMeasures.

Task(s)

Major/Long LeadEquipment Specs/Data Sheets

PHASE 3Project Definition

Requestfor Bids

TechnicalData

Permit Package

PreliminaryApplications

PreliminaryProcessDesign

Phase 3 Design Documents� Site Plan� Plot Plan� Preliminary Piping Layouts of

All Lines on P&IDs (One-Line 3-D Modeled on Sketches)� Building Plans & Elevations� PFDs� Material Selection Diagrams� H&M Balance� Process & Utility P&IDs, (Rev. C

IFD)� Equipment List� Data Sheets & Specifications

for Equipment� Line List� Tie-in List

From Phase 2Task 2-17

To Phase 3Task 3-15

Phase Initiated§ Strategy/Kick

Off Meetings§ Client

Expectations§ Project

ExecutionPlanning§ Interactive

Planning§ Team

Alignment§ Phase 2 Data

& Plant Data§ Lessons

Learned§ Commission-

ing / Start-UpPlanning

§ Major Equip.Defined§ Design Basis

Updated§ Preliminary

Process DesignCompleted§ Discipline Design

SpecificationDefined§ Initiate CAE

Activities§ Process Reliability

ModelingCompleted

Major/Long LeadEquipment Bids

and AllianceQuotes

Requested

Major/Long LeadEquipment Bids

and AllianceQuotes

Prepared

§ ProjectDefinitionFinalized

§ ProjectExecutionPlan Updated

EnvironmentalPermit

ApplicationsCompleted

To Phase 3Task 3-11

To Phase 4Task 4-5

To Phase 3Task 3-14

3-4

3 - 1

3-10

3-9

3-6

3-7

Authorization

Major/Long LeadEquipment Bids

Ongoing:§ Cost Mgt.§ Cost Trending§ Value Plus§ Schedule Mgt.§ Reports§ Lessons Lrnd.

V7V12

M3

M10M6

P100P131P133

OngoingActivities

§ Client Survey§ Audits§ Accounting

QualityAccountingV2

M1 P310M2 P320M5

M12

V8

V1

V6V7

V5

V10

P131

V4

P202M13

P401

P100

4 of 16

§ ValueEngineering

§ P&IDsReviewed

§ Plot PlansReviewed

V15

V20

V14

Process LicenseReceived

3-5

LicenseData

ProcessLicense

ProcessLicenseApplication

Process LicenseGranted

V16

� Project Execution Plan- Updated Project

Objectives� Phase 3:

- Budget- Schedule- Estimate Plan- Deliverables List- Project Procedures

3-2

3-3

§ Reviews HeldFor:-Safety-Process

Hazard-Operability-Constructability-Maintainability

-Reliability -Commissioning§ Preliminary 3D

Model InternalReview for MajorEquipmentLayout/Piping§ Cursory Stress

Analysis forCriticalEquipmentCompleted

3-8

P201

V3V5

P100

V21

V11

V17 Rev. BP&IDs &Plot Plans

Rev. AP&IDsand PlotPlan

Safety Safety

From Phase 2Task 2 - 8

V21

ReviewComments

§ Electrical Single Lines§ Motor List§ Area Classification§ Control System Index &

Specifications for SpecialInstruments or ControlRequirements§ Fire Protection Requirements

for Estimate§ Geotechnical Report§ Hydraulic Study§ Process Control Scheme§ Updated Project Execution Plan

P350

P310

P205P207

P204P203P134P100

P205P207

P204P203P134P100

Page 7: Process Flow Map

JSTEPS

Rev. No. 2Rev. Date: June 1, 2005Approved by: B. Herrington

SM

Page:Copyright©Jacobs EngineeringGroup Inc., 2005

Cross-Functional Map - Chemical Process Industry (CPI)

DESIGNDISCIPLINES

SUPPLYMANAGEMENT

CONSTRUCTION

SUPPLIERS

OTHERS(EXTERNAL)

PROCESSENGINEERING/ENVIRON-MENTAL

OTHERS(INTERNAL)

PROJECTMANAGEMENT/SERVICES

CLIENT

Process Connectoror TerminatorKEY: Decision InvolvementP202 V3 M2

ProcessIndustriesStandardOperatingProcedure

JacobsValueEnhancingPracticeSM

Measurement

See Glossary for explanation ofterms; and definitions of StandardOperating Procedures, ValueEnhancing PracticesSM, andMeasures.

Task(s)

PHASE 3 - ContinuedProject Definition

FundingRequest

Yes

� Phase 3 DesignDocuments IFD� Project Execution Plan

No

� Budget CostEstimate� Updated Basis of

Estimate� Updated Economic

Analysis� Resource Loaded

EPC ProjectSchedule

From Phase 3Task 3-9

From Phase 3Task 3-7

To Ph. 4, 5, 64 -1, 5-1, 6-1

Stop or Recycle

Approved ?3-19

§ Definitive CostEstimate

(+10% to - 5%)Completed§ PDRI or IPA FEL

Assessment§ Process Risk, Cost &

Schedule Risk AnalysisCompleted§ Project Schedule

Developed - Interactive Planning§ Scope Frozen§ Change Management

Initiated§ Commissioning /

Start-Up Plan Updated

PreliminaryEngineering

Phase ReportCompleted

FundingRequested

3-16

3-18

3-14

Requestsfor Bids

� Bids� Prices

Basis ofEstimate

andMTOs

Completed

CriticalEquipment/

Materials Bidsand Alliance

QuotesRequested

3-12

Critical Equipment/Materials Bids and

Alliance QuotesPrepared

3-13

3-11

Major/Long LeadEquipment Bids/Alliance Quotes

� Data Sheets� Specifications� Quantities

OngoingActivities

§ Client Survey§ Audits§ Accounting

QualityAccountingV2

M1 P310M2 P320M5

M12

Ongoing:§ Cost Trending§ Cost Mgt.§ Value Plus§ Schedule Mgt.§ Reports§ Lessons Lrnd.

V7V12

M3

M10

M6 P100

P133P131M13

P403

P131P132

V9V6

M4Quantities

� Phase 3 DesignDocuments IFD� Project Execution Plan

5 of 16

Authorization

Phase III PassGate Reviewand Approval

From Phase 3Task 3 10

PreliminaryEnvironmentalApplications

Evaluated3-15

To Phase 4Task 4 - 14

3-17

P134

V22

Safety

PreliminaryApplications

� Report� Recommendations

Project Execution Plan

§ Corporate / Business Goals§ Project Objectives§ Scope of Work§ Risk Management Plan§ Organization Plan§ Milestone Schedule§ Contracting Plan§ JVEPSM Plan§ Constructability Plan§ Design Management Plan§ Supply Management Plan§ Construction Mgmt Plan§ Startup Management Plan§ Environmental Plan§ Cost Management Plan§ Schedule Management Plan§ Project Quality Plan§ Safety Management Plan§ Information Management Plan§ Special Factors Management

Plan

Reference Only

P401P402

P205

P402P401

Page 8: Process Flow Map

JSTEPS

Rev. No. 2Rev. Date: June 1, 2005Approved by: B. Herrington

SM

Page:Copyright©Jacobs EngineeringGroup Inc., 2005

Cross-Functional Map - Chemical Process Industry (CPI)

DESIGNDISCIPLINES

SUPPLYMANAGEMENT

CONSTRUCTION

SUPPLIERS

OTHERS(EXTERNAL)

PROCESSENGINEERING/ENVIRON-MENTAL

OTHERS(INTERNAL)

PROJECTMANAGEMENT/SERVICES

CLIENT

Process Connectoror TerminatorKEY: Decision InvolvementP202 V3 M2

ProcessIndustriesStandardOperatingProcedure

JacobsValueEnhancingPracticeSM

Measurement

See Glossary for explanation ofterms; and definitions of StandardOperating Procedures, ValueEnhancing PracticesSM, andMeasures.

Task(s)

ReviewsCompleted:§ Discipline

Design§ Design For

Safety- HAZOP

§ 3D ModelReviews§ Operations &

Maintenance§ Commissioning

/ Start-Up

Phase Initiated§ Strategy/Kick

Off Meetings§ Client

Expectations§ Project

ExecutionPlanning§ Interactive

Planning§ Team

Alignment§ Phase 3 Data

Validation§ Lessons

Learned

PHASE 4Detailed Design/Procurement

� Project Execution Plan- Updated Project

Objectives� Turnover Systems List� Phase 4:

- Budget- Schedule- Deliverables List- Project Procedures

IFDTechnicalDocuments

Permits

PermitApplication

Approved VendorData

DesignDocuments

� ConstructionDocuments� Approved

Vendor Data� Control System

Software

PurchaseOrders

ConstructabilityRecommendations

Equipment/MaterialRequisitions

Requestfor Bid

Major/Long LeadEquipment Bids

VendorData

Authorization

From Phase 3Task 3-19

From Phase 3Task 3-7

To Phase 4Task 4-19

To Phase 4Task 4-16

To Phase 5Task 5-12

Equipment/Material

Bids Prepared

Equipment/Materials

Purchased

Vendor DataExpedited and

Obtained

Vendor DataPrepared

External DesignCompleted

ConstructabilityValidated

Environmental and BuildingPermit Applications Approved by

Regulatory Authorities

Environmentaland Building

PermitApplicationCompleted

4-134-6

4-15

4-8

4-14

4-4

4-5 4-7

4 - 9

OngoingActivities

§ Client Survey§ Audits§ Accounting

QualityAccounting

P310P320

V8

V1

V6V7

V5

V10

4-1

P401

P401

P202P407

P500

V3

6 of 16

PermitPackage

V21

Major/Long LeadEquipment Bids

Ongoing:§ Cost Mgt.§ Change Mgt.§ Value Plus§ Schedule Mgt.§ Reports§ Lessons Lrnd.

V7V12

M3

M10M6

P100P131P133

M13P135P134

V22

§ P&IDsFinalized§ MOC Initiated

Rev. 0IFC P&IDs

Vendor Data

4-11

Detailed DesignInput Finalized

4-2

From Phase 3Task 3-15

M8

4 - 12

Bids

HAZOPReport

Equipment /Materials

RequisitionsPrepared and

Bids Requested

4-3

ClientReviews

Completed

4-12

DisciplineDetailed Design

Completed

P204P205

P403

P134P203P207

ModelInterdisciplineDesign Squad

Checks4-10

P203P350

P201

P131P202

P100

P310

V2

M1M2M5

M12

Safety

Page 9: Process Flow Map

JSTEPS

Rev. No. 2Rev. Date: June 1, 2005Approved by: B. Herrington

SM

Page:Copyright©Jacobs EngineeringGroup Inc., 2005

Cross-Functional Map - Chemical Process Industry (CPI)

DESIGNDISCIPLINES

SUPPLYMANAGEMENT

CONSTRUCTION

SUPPLIERS

OTHERS(EXTERNAL)

PROCESSENGINEERING/ENVIRON-MENTAL

OTHERS(INTERNAL)

PROJECTMANAGEMENT/SERVICES

CLIENT

Process Connectoror TerminatorKEY: Decision InvolvementP202 V3 M2

ProcessIndustriesStandardOperatingProcedure

JacobsValueEnhancingPracticeSM

Measurement

See Glossary for explanation ofterms; and definitions of StandardOperating Procedures, ValueEnhancing PracticesSM, andMeasures.

Task(s)

Project DataBooks

Expediting &Inspection Data

PHASE 4 - ContinuedDetailed Design/Procurement

� ConstructionDocuments� Vendor Data� Control

SystemSoftware

Equipment,Materials

� ConstructionDocuments� Approved

Vendor Data� Control System

Software

Approved Vendor Data

Project DataBooks

From Phase 4Task 4-10

To Phase 6Task 6-2

To Phase 5Task 5-5, 9, 10

To Phase 5Task 5-2

To Phase 5Task 5-12

Material &Equipment

Expedited &Inspected

Equipment/Materials

Manufactured

Project DataBooks and

Electronic FilesReceived

Project DataBooks and

Electronic FilesPrepared

From Phase 4Task 4 - 7

4-17

4-16

4-20

4-21

OngoingActivities

§ Client Survey§ Audits§ Accounting

QualityAccounting

P407P408

7 of 16

SubcontractTechnical

DocumentsPrepared &Packages

Assembled

Ongoing:§ Cost Mgt.§ Change Mgt.§ Value Plus§ Schedule Mgt.§ Reports§ Lessons Lrnd.

V7V12

M3

M10M6

P100P131P133M13 P135P134

V22

4-19� Requisitions� Subcontract

Packages

Project Execution Plan

§ Corporate / Business Goals§ Project Objectives§ Scope of Work§ Risk Management Plan§ Organization Plan§ Milestone Schedule§ Contracting Plan§ JVEPSM Plan§ Constructability Plan§ Design Management Plan§ Supply Management Plan§ Construction Management Plan§ Startup Management Plan§ Environmental Plan§ Cost Management Plan§ Schedule Management Plan§ Project Quality Plan§ Safety Management Plan§ Information Management Plan§ Special Factors Management

Plan

Reference Only

ConstructionReadinessReviews

4-18

P310P320

P500

V2

M1M2M5

M12

Safety

Page 10: Process Flow Map

JSTEPS

Rev. No. 2Rev. Date: June 1, 2005Approved by: B. Herrington

SM

Page:Copyright©Jacobs EngineeringGroup Inc., 2005

Cross-Functional Map - Chemical Process Industry (CPI)

DESIGNDISCIPLINES

SUPPLYMANAGEMENT

CONSTRUCTION

SUPPLIERS

OTHERS(EXTERNAL)

PROCESSENGINEERING/ENVIRON-MENTAL

OTHERS(INTERNAL)

PROJECTMANAGEMENT/SERVICES

CLIENT

Process Connectoror TerminatorKEY: Decision InvolvementP202 V3 M2

ProcessIndustriesStandardOperatingProcedure

JacobsValueEnhancingPracticeSM

Measurement

See Glossary for explanation ofterms; and definitions of StandardOperating Procedures, ValueEnhancing PracticesSM, andMeasures.

Task(s) 8 of 16

� Requisitions� Contract

Packages

� Resources� Infrastructure

� Materials &Equipment� Contractor

Drawings� Project Execution Plan� Safety Program� QA/QC Plan� Schedule� Budget� Project Procedures� Mobilization Plan� Staffing Plan� Construction Equipment Plan� Subcontract Plan� Labor Relations Program� Vendor Support Plan for

Construction and Start-up

Turn OverPackages

Permits

PHASE 5Construction

From Phase 4Task 4-10

ConstructionContracts

IntegratedConstructionSchedule

Start-upSchedule

� ConstructionDocuments� Vendor Data� Control System

Programs

Requestsfor Bids

Bids

Authorization

ContractorSchedules

RegulatoryAuthorities

From Phase 3Task 3-19

From Phase 4Task 4-18

ConstructionSubcontracts

and BidsRequested

ConstructionContractsAwarded

ConstructionBids Prepared

From Phase 6Task 6 - 1

§ IntegratedConstructionSchedulePrepared§ Start-up

SequenceFinalized§ Vendor

Schedule forConstructionand Start-upFinalized

To Phase 6Task 6-2

ConstructionStart Notified

Site Set Up &Mobilized

Site Safety PlanInitiated

PermitsAwarded

To Phase 5Task 5-12

ContractorSubmittalsReviewed

§ ContractorDesignCompleted§ Field

Materials &EquipmentProcured§ Site

PreparationInitiated

Turn OverPackagesPrepared

To Phase 5Task 5-12

To Phase 5Task 5 - 12

To Phase 5Task 5-12

To Phase 5Task 5-12

5-10

5-7

5-8

5-95-65-5

5-2 5-4

5-3

RegulatoryAuthorities

Phase Initiated§ Kick Off

Meetings§ Client

Expectations§ Project

ExecutionPlanning§ Construction

ReadinessReview§ Interactive

Planning§ Team

Alignment§ Phase 5 Input

Data Validation§ Lessons

Learned§ Permit

ApplicationsCompleted§ Commission- ing / Start-Up

Plan Updated

V8

V1

V6V7

V5

V10

P131P202

P100

5-1

P405P401

P405

P202

P408P409

P401P407

Ongoing:§ Cost Mgt.§ Change Mgt.§ Value Plus§ Schedule Mgt.§ Reports§ Lessons Lrnd.§ QA/QC§ Safety Mgt.§ Rework

V7V12

M3

M10

M6P100P131P133

M13 P135P134

OngoingActivities

§ Client Survey§ Audits§ Accounting

QualityAccounting

P310P320

M9

V22

M8

P500

P403

P350P500

P500P131

P500

V2

M1M2M5

M12

Safety Safety Safety

Page 11: Process Flow Map

JSTEPS

Rev. No. 2Rev. Date: June 1, 2005Approved by: B. Herrington

SM

Page:Copyright©Jacobs EngineeringGroup Inc., 2005

Cross-Functional Map - Chemical Process Industry (CPI)

DESIGNDISCIPLINES

SUPPLYMANAGEMENT

CONSTRUCTION

SUPPLIERS

OTHERS(EXTERNAL)

PROCESSENGINEERING/ENVIRON-MENTAL

OTHERS(INTERNAL)

PROJECTMANAGEMENT/SERVICES

CLIENT

Process Connectoror TerminatorKEY: Decision InvolvementP202 V3 M2

ProcessIndustriesStandardOperatingProcedure

JacobsValueEnhancingPracticeSM

Measurement

See Glossary for explanation ofterms; and definitions of StandardOperating Procedures, ValueEnhancing PracticesSM, andMeasures.

Task(s)

Queries andResponses

PHASE 5 - ContinuedConstruction

Permits

IntegratedConstructionSchedule

� Test andAcceptanceReports� Construction/

Client PunchList

� Mechanical CompletionDocumentation� Spare and Change Parts

� Construction Turnover Certificate� Mechanically Complete Facility

Equipment,Materials Red Line

Documents

RegulatoryAuthorities

Turn Over Packages

� Material &Equipment� Contractor

Drawings

� Resources� Infrastructure

From Phase 5Task 5-6

RFIsAnswered

From Phase 5Task 5-10

From Phase 5Task 5-9

From Phase 5Task 5-5

From Phase 4Task 4-16

From Ph. 4, 5Task 4-15, 5-7

FacilityConstructed

To Phase 6Task 6-2

§ ConstructionCheck-outCompleted byPackage orSystem§ Demobilization

Initiated

§ Facility or SystemMechanicallyCompleted§ Spare and Change

Parts Assembled§ Facility or system

care, custody andcontrol presentedto client

To Phase 6Task 6-5

5-12

5-11

5-13 5-14

Constructed Facility

To Phase 6Task 6-4

From Phase 6Task 6-4

PSSR Request

Ongoing:§ Cost Mgt.§ Change Mgt.§ Value Plus§ Schedule Mgt.§ Reports§ Lessons Lrnd.§ QA/QC§ Safety Mgt.§ Rework

V7V12

M3

M10

M6

P100P131P133

M13

P135P134

M8

OngoingActivities

§ Client Survey§ Audits§ Accounting

QualityAccounting

P310P320

M8M9

M9

PSSR Punch List

9 of 16

V22

CCCApproved ?

5-15

Recycle Packages

YesNo

M9

Project Execution Plan

§ Corporate / Business Goals§ Project Objectives§ Scope of Work§ Risk Management Plan§ Organization Plan§ Milestone Schedule§ Contracting Plan§ JVEPSM Plan§ Constructability Plan§ Design Mgmt Plan§ Supply Mgmt Plan§ Construction Mgmt Plan§ Startup Mgmt Plan§ Environmental Plan§ Cost Mgmt Plan§ Schedule Mgmt Plan§ Project Quality Plan§ Safety Mgmt Plan§ Information Mgmt Plan§ Special Factors Mgmt Plan

Reference Only

P500P501

P500

V2

M1M2M5

M12

Page 12: Process Flow Map

JSTEPS

Rev. No. 2Rev. Date: June 1, 2005Approved by: B. Herrington

SM

Page:Copyright©Jacobs EngineeringGroup Inc., 2005

Cross-Functional Map - Chemical Process Industry (CPI)

DESIGNDISCIPLINES

SUPPLYMANAGEMENT

CONSTRUCTION

SUPPLIERS

OTHERS(EXTERNAL)

PROCESSENGINEERING/ENVIRON-MENTAL

OTHERS(INTERNAL)

PROJECTMANAGEMENT/SERVICES

CLIENT

Process Connectoror TerminatorKEY: Decision InvolvementP202 V3 M2

ProcessIndustriesStandardOperatingProcedure

JacobsValueEnhancingPracticeSM

Measurement

See Glossary for explanation ofterms; and definitions of StandardOperating Procedures, ValueEnhancing PracticesSM, andMeasures.

Task(s)

ConstructionContracts

Start-upSchedule

TrainedOperators

PHASE 6Start-up

Red LineConstructionDocuments

Project DataBooks

Facility OperatingOn Feed-stock

Updated ConstructionDocument Mark-ups

PSSRFrom Phase 3Task 3-19

From Phase 4Task 4-19

From Phase 5Task 5-12

DocumentsPrepared

To Phase 5Task 5-6

From Phase 5Task 5-4

Pre-Start-upSafety Review

Completed

From Phase 5Task 5-15

§ FacilityPrecom-missioningCompleted§ Engineering

Check-outCompleted

Feed-stockSupply

To Phase 6Task 6-7

To Phase 6Task 6-8

6-2

OperatorsTrained

6-4

6-5 6 - 6

� Construction TurnoverCertificates� Mechanically Complete

Facility

Authorization

� Commissioning/Start-upPlan� Performance Plan� Performance Test Docs� Safety Action Plan� Operating Plan� Training, Operation and

Maintenance Manuals� Updated Construction

Documents (As-Builts)

� Staffing Plan� Start-up Program� Start-up Schedule� Safety Program� Budget

6-3

ProcessFeed-stock

From Phase 5Task 5-13

To Phase 5Task 5-14

Start-up PhaseInitiated§ Kick Off

Meetings§ Client

Expectations§ Project

ExecutionPlanning§ Team

Alignment§ Prior Phase

Data Validation§ Lessons

Learned§ Commission-

ing / Start-UpPlanning

V8

V1

V7V5

V10

P100

P202P131

6-1

Ongoing:§ Cost Mgt.§ Change Mgt.§ Schedule Mgt.§ Reports§ Lessons Lrnd.

P100P131P133P134

OngoingActivities

§ Client Survey§ Accounting

QualityAccounting

P310

PSSRRequest

PSSRPunchlist

10 of 16

PrecommissionedFacility

P202

To Phase 7Task 7-2

§ FacilityCommissioned§ Facility

Start-upCompleted

6-6

V2

M1M2M5

V7

M3M6

M10

V22

Safety Safety Safety Safety

Page 13: Process Flow Map

JSTEPS

Rev. No. 2Rev. Date: June 1, 2005Approved by: B. Herrington

SM

Page:Copyright©Jacobs EngineeringGroup Inc., 2005

Cross-Functional Map - Chemical Process Industry (CPI)

DESIGNDISCIPLINES

SUPPLYMANAGEMENT

CONSTRUCTION

SUPPLIERS

OTHERS(EXTERNAL)

PROCESSENGINEERING/ENVIRON-MENTAL

OTHERS(INTERNAL)

PROJECTMANAGEMENT/SERVICES

CLIENT

Process Connectoror TerminatorKEY: Decision InvolvementP202 V3 M2

ProcessIndustriesStandardOperatingProcedure

JacobsValueEnhancingPracticeSM

Measurement

See Glossary for explanation ofterms; and definitions of StandardOperating Procedures, ValueEnhancing PracticesSM, andMeasures.

Task(s)

PHASE 6 - ContinuedStart-up

Facility Operatingon Feed-stock

Performance TestCertificate

RecordDocuments

AcceptanceDocumentation

Updated ConstructionDocument Markups(As-Builts)

AcceptedFacility

Regulatory AuthorityApproving Occupancy /Acceptance

From Phase 6Task 6-6

From Phase 6Task 6-6

RecordDocuments

Created

PerformanceTest

Completed

FacilityAccepted

Long TermCommercialPerformanceCommenced

To Phase 7Task 7-3 & 7-4

To Phase 7Task 7-4

6-96-8

OngoingActivities

§ Client Survey§ Accounting

QualityAccounting

P310

Ongoing:§ Cost Mgt.§ Change Mgt.§ Schedule Mgt.§ Reports§ Lessons Lrnd.V7

P100P131P133P134

6-7

6-10

M7 M7

11 of 16

P100

P202

M3M6

M10

V2

M1M2M5

Page 14: Process Flow Map

JSTEPS

Rev. No. 2Rev. Date: June 1, 2005Approved by: B. Herrington

SM

Page:Copyright©Jacobs EngineeringGroup Inc., 2005

Cross-Functional Map - Chemical Process Industry (CPI)

DESIGNDISCIPLINES

SUPPLYMANAGEMENT

CONSTRUCTION

SUPPLIERS

OTHERS(EXTERNAL)

PROCESSENGINEERING/ENVIRON-MENTAL

OTHERS(INTERNAL)

PROJECTMANAGEMENT/SERVICES

CLIENT

Process Connectoror TerminatorKEY: Decision InvolvementP202 V3 M2

ProcessIndustriesStandardOperatingProcedure

JacobsValueEnhancingPracticeSM

Measurement

See Glossary for explanation ofterms; and definitions of StandardOperating Procedures, ValueEnhancing PracticesSM, andMeasures.

Task(s)

CloseoutPlan

PHASE 7Closeout

AcceptanceDocumentation

LessonsLearned

RecordDocuments

Receipt

Procurement& ContractRecords

Outstanding Warranty Issues

From Phase 6Task 6-5

Prior PhaseCompletions

§ Final EPCSurveyObtained§ Lessons

LearnedConducted§ Lessons

LearnedCompiledFrom AllPhases

ProjectCloseoutPlanned

PurchaseOrders &Contracts

Closed

Data Assembly& Compilation Completed

From Phase 6Task 6-7

DocumentationReceived

Files ArchivedWarrantyIssues

Resolved

FinalAcceptance

Made

Financial &ContractualClose Out

Completed

Finish

� Benchmarking Data� Final Accounting� Project Closure

Notice

� Final Acceptance Certificate� Retention Release� Final Payment

FinalAcceptanceRequest

� Data/Document Files� Archive Log� Project Completion Report

� Final Project Report� Record Documents� Warranty File� Client Assets

7-8

7-2

7-3

7-1

7-4 7-6 7-7 7-9

7-5

� Lessons Learned� Final Client Survey

P100

M1M5

P100P202

P404P405

P100

M2

V2V7

P100P310

12 of 16

OperabilityAssessment

SurveyConducted

(Future)

From Phase 6Task 6-9

PrecommissioningDocuments

Safety Accounting

P401

P100P202

P100P401P404P405

IS

Page 15: Process Flow Map

JSTEPS

Rev. No. 2Rev. Date: June 1, 2005Approved by: B. Herrington

SM

Page:Copyright©Jacobs EngineeringGroup Inc., 2005

GlossaryChemical Process Industry (CPI)

Clarifications, Abbreviations,Definitions and Conventions

CCC Care, Custody and Control IS Information Systems cGMP Current Good Manufacturing

Practices MOC Management of Change

CII Construction Industry Institute MTO Material take-off CPI Chemical Process Industries P&ID Piping and Instrumentation Diagram CSIP Client Satisfaction Improvement

Plan PDRI Project Definition Rating Index

DS&E Design Safety and Environmental PFD Process Flow Diagram E Environmental PI-SOP Process industries Standard

Operating Procedure EU European Union PSSR Pre-Start-Up Safety Review FEL Front End Loading PQP Project Quality Plan H&M Heat and Material QA/QC Quality Assurance/Quality Control HAZOP Hazard and Operability RFI Request for Information IFC Issue for Construction S Safety IFD Issue for Design VIP Value Improving Practice IPA Independent Project Analysis VEP Value Enhancing Practice

CLARIFICATIONS

FUNCTIONS

ABBREVIATIONS PROCESS INDUSTRIES STANDARD OPERATING PROCEDURES

JACOBS VALUE ENHANCING PRACTICESSM (JVEPsSM)

MEASURES

EPC Representation: The map is constructed to represent a single EPC (engineer, procure, construct) project handled by Jacobs in its entirety. However, each phase closely represents the work process used when only that phase is handled by Jacobs. Sales Excluded: For simplicity, the sales function, including proposals, presentations and negotiations, is excluded. Support Groups Excluded: For clarity, the support groups, such as accounting, human resources, legal and information systems, are generally not shown. Owner/Management Involvement: Ongoing involvement by the owner and project management and others to perform their management and supervisory roles is not shown, but is implied in all steps. Activity Assignment: Activities have been assigned to the phases in which they most logically belong. For example, start-up document preparation is a phase 6, Start-up, activity even though its preparation may commence during phase 4, Engineering. Phases: Phases have been defined as portions of a project (a) generally considered by clients to be discrete scopes of work, (b) generally ending with a decision point and (c) often awarded to different firms (e.g. detailed design and construction to different companies). Phases frequently overlap, e.g. construction commences before detailed design is complete. Therefore, a phase 5, Construction, activity can start before phase 4, Engineering, activities are all complete.

CLIENT All client functions including management, engineering, operations, maintenance, etc.

PROJECT MANAGEMENT/ SERVICES

Project management, project engineering, estimating, scheduling, and cost engineering

PROCESS ENGINEERING/ ENVIRONMENTAL

The process and environmental group(s)

DESIGN DISCIPLINES All detailed design functions including architectural production, civil, structural, mechanical, HVAC/FP, piping, electrical, and control systems

SUPPLY MANAGEMENT Purchasing, subcontracts, expediting, and inspection

CONSTRUCTION Construction forces including constructibility, construction management and field staff; and craft personnel and labor on direct hire projects

OTHERS (INTERNAL) Internal Jacobs functions not mentioned above such as sales, safety, environmental, regulatory compliance, validation, information systems, accounting, human resources, quality and legal

SUPPLIERS All suppliers including equipment vendors, subcontractors, and consultants

OTHERS (EXTERNAL) Organizations outside Jacobs, other than suppliers, such as regulatory bodies, generally differentiated by not being paid for their services

V-1 Client Expectations V-12 Value Plus V-2 Client Surveys V-13* Class of Plant Quality V-3* Constructability V-14* Customized Standards/Specs V-4* Design to Capacity V-15* Energy Optimization V-5 Execution Planning V-16* Predictive Maintenance V-6 Interactive Planning V-17* Process Reliability Modeling V-7 Lessons Learned V-18* Process Simplification V-8 Team Alignment V-19* Technology Selection V-9 PDRI (Project Definition Rating

Index) V-20* Waste Minimization

V-10 Owner’s Project Objectives V-21* 3D CAD V-11* Value Engineering V-22 Change Management *IPA VIP Best Practices

M-1 Accounts Receivable Total of amounts due and payable by an owner that have not been paid

M-2 Client Survey See Client Survey in Definitions

M-3 Cost Measures of budgeted, actual and forecast cost for engineering, construction and total installed cost, as appropriate

M-4 PDRI See PDRI in Definitions

M-5 Project Gross Margin

The difference between the direct costs of the project and the revenues deriving from it to Jacobs

M-6 Productivity The ratio of earned work hours to spent work hours for either home office or field activities

M-7 Project Performance The project’s ability to meet established project objectives for items such as product quality, capacity, time to full production, efficiency, etc.

M-8 Rework Home office or field work that has to be re-performed (redone) due to client change, designer change, vendor change, constructor change, designer error, vendor error, or constructor error.

M-9 Safety The number of E1, OSHA recordable and other incidents in the home office and field versus the number of hours worked

M-10 Schedule Measures of performance against an agreed project schedule including forecast days early or late, percent complete versus scheduled, etc.

M-11 Schedule Milestones Met

The number of agreed, scheduled milestones met versus the number of milestones scheduled to have been met

M-12 SOP Audit Measure of a project’s compliance with it’s applicable SOP’s as defined in its quality plan

M-13 Value Plus See Value Plus in Definitions

PI-SOP NAME

PI-SOP-100 Project Management and Execution

PI-SOP-110 Business Risk Identification and Management

PI-SOP-111 Project Risk Identification and Management

PI-SOP-120 Multi-Office Project Execution & Planning

PI-SOP-130 Project Control Plan and Work Breakdown Structure

PI-SOP-131 Planning and Scheduling

PI-SOP-132 Estimating

PI-SOP-133 Cost Management

PI-SOP-134 Change Management

PI-SOP-135 Performance Measurement

PI-SOP-201 Design for Safety

PI-SOP-202 Document Management & Control

PI-SOP-203 Deliverable Verification

PI-SOP-204 Preparation of Specifications

PI-SOP-205 Engineering Requisitions

PI-SOP-206 cGMP Review/Consultation

PI-SOP-207 Computer Aided Design

PI-SOP-208 Control of Engineering Software

PI-SOP-300 Region/LOB Quality System Requirements

PI-SOP-310 Client Surveys

PI-SOP-311 Management Review of Quality System

PI-SOP-320 Project Audits

PI-SOP-350 HS&E Program

PI-SOP-401 Project Supply Management Procedure

PI-SOP-402 Inquiry Requisitions and Inquiry Documents

PI-SOP-403 Bid Opening, Evaluation and Award

PI-SOP-404 Administration and Closeout of Agreement for Equipment and Materials

PI-SOP-405 Administration and Closeout of Agreement for Services

PI-SOP-406 Field Materials Management

PI-SOP-407 Expediting

PI-SOP-408 Supplier Surveillance and Inspection

PI-SOP-409 Transportation

PI-SOP-500 Field Services

PI-SOP-501 Field Inspection and Testing

13 of 16

Page 16: Process Flow Map

JSTEPS

Rev. No. 2Rev. Date: June 1, 2005Approved by: B. Herrington

SM

Page:Copyright©Jacobs EngineeringGroup Inc., 2005

GlossaryChemical Process Industry (CPI)

Clarifications, Abbreviations,Definitions and Conventions

DEFINITIONS

14 of 16

3D CAD (V-21)

Extensive use of 3D Computer Aided Design (CAD) during FEL and detailed engineering. The objective is to model the project in the computer to reduce the frequency of dimensional errors and spatial conflicts that cause design changes during construction. The use of 3D CAD also improves visualization for operations input and training.

Area Classification Drawing identifying the level of hazard in different areas of the plant for purposes of electrical design in accordance with the appropriate electrical code.

Basis of Estimate Summary of the key methods and inputs upon which an estimate is based, including such items as level of engineering completed, source of equipment and material pricing, construction philosophy and significant assumptions and exclusions.

Benchmarking Data

Data used in a systematic process of measuring one’s performance against results from recognized leaders for purpose of determining best practices that lead to superior performance when adopted and utilized.

Beneficial Occupancy

Owner takes over some or all of the constructed facility for its own benefit and assumes the responsibility for its operations. The facility may not necessarily be completed but may be used for its intended purpose. The warranty period begins.

Bid Offer by a supplier to sell. In the maps, used interchangeably with quotes and proposals. Sometimes bids mean only pricing data.

Business Objectives

The underlying drivers behind identification of project opportunities.

CII Construction Industry Institute. An organization of owners, contractors and academia whose mission is to improve the safety, quality, schedule, and cost effectiveness of the capital investment process through research and implementation support.

Catalyst and License Agreements

Agreement or contract that grants to a licensee the right to use a catalyst and/or technology under specific terms and conditions including compensation.

Certificate of Occupancy

Document from a building regulatory agency that certifies a facility has been inspected, has no violations and meets the regulatory requirements and codes for occupancy for its intended purpose.

Change Management (V-22)

Process of controlling the scope of a project against a defined baseline by only allowing a change after it has been formally approved, taking into account its benefit to the project outcome, and its impact on cost and schedule.

Class of Plant (V-13)

IPA VIP that established what quality facility is needed to meet business objectives. It adjusts reliability, expandability, automation, life of facility, etc. to recognize goals.

Client Expectations (V-1)

A proactive approach to identify, collect, and address client expectations, concerns, past issues and soft issues that can adversely or positively affect a client’s perception to our performance and attitude toward Jacobs Engineering.

Client Survey (V-2)

PI-SOP-310 process to obtain both a numerical rating and a narrative evaluation of a client’s satisfaction with our performance against standard headings.

Close-Out Plan Plan to perform all of those activities necessary to properly complete a project in accordance with the contract, SOPs, law, and other considerations.

Code Analysis Analysis, conducted by knowledgeable professionals, to ensure that a facility design meets the regulatory requirements applicable to its structure type, occupancy type, building siting, building size, set backs, etc.

Commissioning Process of putting a facility into operation after mechanical completion has been demonstrated. Includes such activities as starting equipment under operating conditions, pressurizing and heating up systems, introducing raw materials and reagents/catalyst, producing intermediate and final products, preparing product for shipment.

Commissioning / Start-up Plan

Plan for the safe and controlled putting of a plant into operation after mechanical completion has been demonstrated.

Concept(s) Technological and physical solutions that will satisfy the requirements specified in the Design Basis.

Constructability (V-3)

Optimum use of construction knowledge and experience in planning, design, procurement, and field operation to achieve overall project objectives.

Constructability Database

Jacobs database of value adding ideas created through the constructability process. The ideas can be accessed by search criteria such as discipline, project type, client.

Construction Check-out

Process to ensure that facility has been constructed and installed in accordance with construction documents. Includes such checks as those for completeness, structural bolting torque, drive alignment, hydrostatic testing of pipelines and systems, electrical insulation and continuity, and motor rotational direction.

Construction Documents

Drawings, specifications and other documents produced by the engineer to define the facility so that it can be built by a suitably qualified construction organization to meet the owner’s requirements and the design intent.

Construction Punch List

List of incomplete construction items that are the responsibility of the construction entity to complete under the construction contract.

Construction Turn Over Certificate

Certificate signed by the owner signifying that the latter is accepting care, custody and control of the facility. Sometimes signed prior to certificate of mechanical completion. Varies by contract.

Contract Package Set of documents defining the scope of work to be performed under a contract, usually including, as a minimum, a scope of work, specifications and drawings.

Control System Philosophy

Overall strategy adopted to control the process being designed. Includes selection of control system (DCS, PLC, etc,), degree of centralization, redundancy, etc.

Control System Programs

Process of inputting data and logic into distributed control systems (DCS), programmable logic controllers (PLCs) and other control components to enable them to perform their required system functions.

Cost Trending Process used during project development, prior to completion of a firm scope and control estimate, to track the impact of scope adjustments on the preliminary estimate by adding to or subtracting from it the order of magnitude cost of each.

Critical Equipment Equipment that, in the judgment of the project team, has the greatest potential for cost impact to the project.

Customized Standards/ Specifications (V-14)

An evaluation of the actual needs of the specific facility to be designed. Engineering standards and specifications can affect manufacturing efficiency, product quality, operating cost, and employee safety. However, sometimes the cost of a facility is increased by the application of codes, standards, and specifications that exceed the facility’s needs (IPA VIP).

Deed of Release and Waiver

Document under seal (or equivalent) whereby the supplier agrees not to claim any lien on the project property and to waive any claims related to the project.

Definitive Cost Estimate

Estimate produced during Phase 3, Preliminary Engineering, based on substantial documentation, typically having an accuracy of +10% to -5%.

Design Basis Formal statement of the foundation upon which subsequent design is to be based, including nature and quality of product(s), capacity to produce product(s), site location, existing facilities and utilities, allowance for expansion, standards, to be applied, etc.

Design Development Further development of the “schematic design” concepts to provide the basis for development of the “construction documents”.

Design Review Evaluation of design documents for specific purposes (e.g. safety, maintainability, reliability, constructability) to ensure that these have been properly considered.

Design Safety and Environmental Plan (DS&E)

Planning document to identify the organization related to safety; the safety and environmental objectives and acceptance criteria; statutory and engineering safety requirements; possible hazards and environmental problems; methods, reviews and audits (See PI-SOP-201, Design For Safety.)

Design Safety Review The process of ensuring that the proposed design satisfies the statutory, contractual, and procedural safety requirements applicable to the project.

Design to Capacity (V-4)

An evaluation of the maximum capacity of each major piece of equipment. Often equipment is designed with a "safety factor" to allow for additional catch up capacity of some production increases (IPA VIP).

Economic Analysis Analysis of the financial benefit of the project to the owner using such tools as return on investment, net present value, and economic value added.

Effective Front-end Loading

The process of ensuring that project scope definition in the Project Deliberation, Select Option, and Detail Option stages is complete enough to accurately predict cost and schedule for the remaining project phases. Tools used to measure the implementation of this process are the Front End Loading Index (IPA) and PDRI (Project Definition Rating index).

Energy Optimization (V-15)

A simulation methodology for optimizing the life cycle costs by examining power and heating requirements for a particular process. The objective is to maximize the total return based on selecting the most economical methods of heat and power recovery (IPA VIP).

Engineering Check-out Final checking and testing of systems by engineering personnel prior to start-up by operations personnel. Includes checking of controls loops and systems.

Environmental Impact Assessment

Identification of effect of project on air, water, flora and fauna, traffic, etc. Usually in a format defined by responsible regulatory body such as EPA, AQMD.

Equipment Location Plan

Drawings of portions of an operating unit that is of sufficient scale to allow coordinate locations and elevations to be given for all equipment, structures and buildings within a unit. It will normally take multiple Equipment Location Plans to cover an operating unit.

European Union Countries compromising the European Union. Identified on the maps because of the need to identify specific European Union regulatory requirements.

Execution Planning (V-5)

A process to obtain the input of all stakeholders and key participants to create the Project Execution Plan, including project approach and schedule, with the intent of obtaining ownership and commitment by all participants. The process follows a structured checklist to ensure the team has considered all pertinent aspects of the execution, and results in alignment of the execution plan with the business and project objectives.

Facility Started-up Plant has commenced full operation on final raw materials and is producing planned product, although not necessarily at full output rate.

Facility(ies) Generic term used to denote entire physical project or a part of it including infrastructure, buildings, and process plant.

Feedstock Raw materials such as crude oil, mined ore or chemical intermediates constituting the primary input to a process plant.

Final Acceptance Formal concurrence by the plant that all project requirements have been completed.

Final Project Report Last project report to the owner, covering total project performance and including such elements as total cost, final schedule, lessons learned, team, scope.

Financial/Contractual Close Out

All financial and contractual requirements to close the project have been completed including, as necessary, final payments made, final certificates signed, bonds, released or cancelled, claims settled.

Page 17: Process Flow Map

JSTEPS

Rev. No. 2Rev. Date: June 1, 2005Approved by: B. Herrington

SM

Page:Copyright©Jacobs EngineeringGroup Inc., 2005

GlossaryChemical Process Industry (CPI)

Clarifications, Abbreviations,Definitions and Conventions

DEFINITIONS (Continued)

15 of 16

Fit-up (also known as fit-out)

Phase of construction which provides the major interior construction (e.g. partitions, ceiling, HVAC, main process headers, electrical distribution, etc.) once the building shell or enclosure has been completed. It provides the working environment for the intended use of the facility.

GMP Review Design review to ensure compliance with cGMP requirements.

HAZOP Hazard and Operability (HAZOP) study is a comprehensive, systematic and structured examination of the proposed design. A HAZOP study is a forum in which the cause and hazardous consequences of potential deviation from normal plant status are considered and where operability problems are identified and ultimately resolved.

IFC Issue for Construction. All engineering documents issued to construct the project. Drawing revisions prior to IFC are letter revisions with the IFC initial issue being Rev “0” (zero). All revisions after IFC will be numbered revisions.

IFD Issue for Design. All engineering documents issued formally as a basis for design by others (intra- or inter- discipline).

IPA Independent Project Analysis. A for-profit organization that maintains a confidential database of project performance data against which it benchmarks the performance of owners’ projects.

IPA FEL Index IPA's developed index that ranks a project's completeness for definition and FEL. The index is scored from 3 – 12 with scores of 4 – 5 being described as "Best in Class" and higher scores indicating a greater degree of incompleteness.

Interactive Planning (V-6)

Meeting of all stakeholders and key participants to create a vision of the overall project schedule and approach, using a wall board presentation tool, with the intent of obtaining ownership and commitment by all participants.

Jacobs System to Ensure Project SuccessSM

JSTEPSSM. A system that incorporates work process maps into Jacobs management system as a tool for ensuring project success.

Jacobs Value Enhancing PracticesSM

JVEPsSM. Key practices that, when used consistently and collectively, significantly increase the value of Jacobs' services to its clients.

Labor Relations Program Program for evaluating labor availability, capability and cost; establishing relationships with local and national labor bodies for using labor resources, harmony and ongoing communications.

Lessons Learned (V-7)

Review of knowledge gained from past projects for the same client or for similar purposes or in the same location that could benefit the performance of the current project or knowledge gained from the current project that could be beneficially applied to future projects.

Line of Business An industry, or group of industries with similar characteristics, which Jacobs serves, e.g. Mining and Minerals, Chemical Process, Facilities.

Long Lead Equipment Equipment for which the time from order through delivery is so long as to be a determining factor in the overall project schedule and which may require to be purchased earlier than indicated by the normal process flow.

Long Term Commercial Performance

Output quantity and quality achieved once all necessary adjustments have been made and all operational learnings have been achieved. May be many years for some processes.

MTO Material Take-Off. A calculation of construction material quantities needed based on design drawings.

Management of Change (MOC)

An operational safety and operability review involving changes to an existing facility.

Market Study Analysis of the likely consumers of the product of the project including the likely level of consumption at various prices over a period of years.

Master Plan Overall plan for the future development of a project or facility site including site conditions, overall building layouts, traffic flow and future site improvements. Establishes the basis to which all project or site work conforms.

Mechanical Completion

Completion of construction in accordance with the contract documents as verified by the construction checkout documentation. Does not include starting equipment other than to verify direction of rotation.

Milestone Schedule High level schedule that identifies the points in time when major activities will be completed.

O&M Documentation Operations and maintenance manuals and other documents required for the operation of the facility, largely provided by equipment vendors but supplemented by engineering documentation.

Occupancy Time in the construction of the facility at which the owner or occupier moves into and begins using the facility for its intended purpose.

Opportunity Apparent chance for client to improve his business.

Option Technological and physical solutions that will satisfy the requirements specified in the design basis.

Order of Magnitude Estimate

Estimate produced during Phase 1, Feasibility, based on little documentation, typically having an accuracy of +50% to –35%.

Owner Generally used to mean the entity for which the work is being done, but occasionally refers to the strict legal owner of the project as determined by the context. Used herein interchangeably with client.

PDRI (V-9)

Project Definition Rating Index. A tool created by CII to objectively measure the quality of the definition of the scope of a project at a particular point in time.

Path Forward Identification of activities needed to achieve progress and plan to perform them.

Performance Improvement Notice

A document used to initiate and monitor effective resolution of observations, suggestions, or nonconformances arising from the performance evaluation process.

Performance Plan Plan to demonstrate the performance of the project in accordance with its design objectives. Includes organization, contractor/supplier participation, duration of demonstration tests, production rates and specifications, verification methods.

Performance Test Operation of the facility for a predetermined period of time under specified conditions to demonstrate that it can achieve its design objective product quantity and quality. Frequently the basis for final acceptance of equipment and final payments to vendors.

Performance Test Documents

Documentation to be completed prior to, during and subsequent to performance tests as part of the performance plan to provide a formal record of the plant performance during the tests.

Permits Permits issued by authorities having jurisdiction over various aspects of the project construction which are required before some or all of the construction may commence. Examples include certain environmental permits, provisional use permits, and building (structural, electrical, plumbing, etc.) permits

Plot Plan A scaled drawing showing an overall unit within a facility with all major equipment, structures and building.

Precommissioning Activities performed after mechanical completion in preparation for introducing feed-stock into the plant and putting it into full operation. Precommissioning includes activities such as putting electrical, compressed air and plant water systems into operation, filling reactors with catalyst, running systems with no load or simulating operations with water, drying out refractory vessel linings, etc.

Predictive Maintenance V-16

An approach to maintaining a facility whereby equipment is monitored and repairs are made before failure. Typically, such an approach requires adding various measurement devices to evaluate operating characteristics.

Preliminary Engineering Phase Report

Report produced at the end of Phase 3, Preliminary Engineering.

Pre-Start-Up Safety Review

Formal review led by the client to confirm that the constructed facility is ready to start-up safely and to confirm that: 1) the unit has been designed and constructed in accordance with design specifications, 2) proper safety, maintenance and emergency procedures have been instituted, 3) appropriate training of personnel has been completed and 4) appropriate documentation has been updated. US law (OSHA 1910) requires that the review be held before the start-up of certain classes of new or modified facility. Also called Pre-Start-Up Change Management Review.

Process Industries Standard Operating Procedures (PI-SOPs)

PI-SOPs are standard operating procedures issued jointly by the Northern, Southern, and Western Regions to implement the GSOPs.

Process Reliability Modeling (V-17)

A simulation technique to examine operability targets for a facility. The objective is to determine the most economical sizing, spacing, and storage conditions that meet operability goals while minimizing cost. Typically, specialized computer software and/or a consultant are necessary (IPA VIP).

Process Simplification (V-18)

Disciplined analytical method for reducing investment of operating costs by combining or making unnecessary one or more chemical or physical processing steps (IPA VIP).

Project Objectives (V-10)

Clear statement of the project goals, drivers, and constraints that will enable the project management team to maintain its focus and make responsible decisions; including capital cost permitted, completion milestones required, cash-flow constraints, new technology application and purpose, environmental goals and operational considerations.

Process Simulation Simulation studies to optimize a design based on chosen optimization parameters using a computer based model of the process.

Project Data Books Compilation of information prepared for the plant at the end of a project. Contents vary with owner, industry and contract but can include calculations, drawings and specifications, test data, vendor drawings and manuals. They can be electronic (CD).

Project Execution Plan (V-5)

Overall plan for performing a defined scope of work including all necessary elements such as goals and objectives, scope of work, organization, schedule, and plans for risk management, contracting, design, material management, construction, start-up, quality, safety, etc.

RFI Request for Information. A request from the construction entity for additional information, clarification or direction to enable construction to proceed.

ROI Return on Investment. A financial method to compare the monetary outcome of the project against the owners expectations and against investing the required capital in a different opportunity.

Record Documents Construction documents updated to reflect changes made or errors found during construction and start-up.

Red Line Documents Construction documents marked up during construction to reflect the manner in which the project was actually constructed. Changes can result from errors, measurements being field determined, or as-found conditions being other than expected.

Regulatory and Permitting Requirements

Any and all legal and regulatory restrictions and constraints that may impact the project including those related to air and water emissions and quality, land usage, building code compliance, resource conservation, existing pollution including those of EPA, OSHA, FDA, Building Codes.

Page 18: Process Flow Map

JSTEPS

Rev. No. 2Rev. Date: June 1, 2005Approved by: B. Herrington

SM

Page:Copyright©Jacobs EngineeringGroup Inc., 2005

GlossaryChemical Process Industry (CPI)

Clarifications, Abbreviations,Definitions and Conventions

DEFINITIONS (Continued)

Major/Long LeadEquipment Specs/Data Sheets

SchematicDrawings

PreliminaryProcess Design

Estimate

Fac

§ Major Equip.Defined§ Design Basis

Updated§ Preliminary

ProcessDesignCompleted

SchematicDesign

EstimateCompleted

Major/LongLead

Equipment BidsRequested

PreliminaryEngineeringCompleted

3-2

SchematicDesign

Completed

3-6

DesignDevelopment

Completed

PhBFac

Fac

3-4

3-3

V4

P204P205

P100

P401

P203P204P403

DESIGNDISCIPLINES

SUPPLYMANAGEMENT

PROCESSENGINEERING/ARCHITECT

PROJECTMANAGEMENT

CLIENT

Non-primaryinvolvement byclient in task 3-2.

Preliminary EngineeringTask 3-6 completed byProcess Engineeringand Design Disciplineswith involvement byClient and MaterialsManagement.

Output fromtask 3-2 andinput to task3-6. SOPs

applicable totask 3-6.

Value EnhancingPractice applicableto task 3-6.

Line of Businessexception forPharma-Bio andFacilities which callthis task DesignDevelopment.

Task numberconsists of phasenumber followedby sequentialnumber.

Secondaryflow line.

Primaryflow line.

Work processtask(s) or activitiesidentified by nounand past tenseverb combination.

MAP DRAFTING CONVENTIONS

Functional groupsinvolved in projectexecution.

16 of 16

Dashed lines on a task boxindicate that functional groupdoes not participate.

Supplemental Investigations

Any additional work needed to be performed by the owner to progress the project such as laboratory or pilot plant testwork, geological or geotechnical investigation, technology demonstration, environmental studies, etc.

Supplier Generic term for any entity providing a supply or service to the project, including equipment and material vendors, construction contractors, and consultants of all types.

Team Alignment (V-8)

Process to ensure that all key team members—Client, Jacobs, and suppliers—have the same clear understanding of the project goals and objectives and the means for achieving them. This process includes elements of team building, facilitation, and planning, and incorporates methods to improve interpersonal skills, resulting in an aligned, focused, and motivated work team.

Technology Selection (V-19)

A formal systematic process by which a company searches for production technology outside of the company (or, in some instances, in other divisions within the company) that may be superior to that currently in its manufacturing plants (IPA VIP).

Test and Acceptance Report

Documentation completed during the process of construction check-out and signed by the owner to signify his acceptance of tests as having been satisfactorily completed.

Training, Operations and Maintenance Manuals

See “vendor data”. Training and operations plans and procedures are also prepared by the plant and engineer.

Turnover Package Package containing the documentation, such as inspection, test, reports that needs to be completed prior to turning over all or an element of the project to the owner.

Turn-over Systems List List of the systems to be separately handed over to the owner.

Updated Construction Documents

Construction documents revised to incorporate changes made or required during construction.

VEP See Jacobs Value Enhancing PracticesSM

VIP Value Improving Practices. A term coined by IPA for a practice which has been statistically demonstrated to improve project performance and outcome.

Value Enhancing Practices

SM

VEPs SM

. Best practices identified by CII and IPA that, when used consistently and collectively, significantly increase the value of the project.

Value Engineering (V-11)

A disciplined method of functional analysis used during design, often employing an internal or external consultant, aimed at eliminating or modifying items that do not contribute to meeting business needs.

Value Plus (V-12)

An organized system to recognize and report value added provided by the Project Team. It promotes a cultural change to increase value awareness by recording all value adding concepts and uses a wall chart to advertise progress towards goal. Total Value Added includes operational savings, capital avoidance, EPC savings, and other savings. Also known as EPCM Initiative Savings.

Vendor Data Drawings, documents, manuals and other information provided by suppliers of equipment and materials under purchase orders including design drawings, installation instructions, maintenance manuals and operating instructions.

Warranty File File containing documentation of and relating to warranties provided by suppliers.

Waste Minimization (V-20)

A disciplined approach used during design to minimize the production of waste products. Such an approach might add additional equipment or examine alternate process technologies that have lower waste side-streams (IPA VIP)

Regulatory Authorities Any agency or authority having jurisdiction over any aspect of the project, e.g. EPA, AQMD, OSHA, FDA, Building Officials.

Reliability Planning/Predictive Maintenance (V-16)

Disciplined approach in analyzing plant operations to improve mechanical reliability of equipment through improved design. For key critical equipment, equipment is monitored and repairs are made before failure. Typically, such an approach requires adding various measurement devices to evaluate operating characteristics (IPA VIP).

Risk Analysis Identification of those significant factors that could prevent the project from meeting its business objectives, such as labor unrest, weather, changing market conditions, new technology, poorly defined work scope, poor planning, etc.; together with an assessment of the probability of each; and means and cost of mitigation.

Room Requirements Definition of required environmental conditions such as cleanliness, relative humidity, temperature, lighting level, and special electrical, plumbing and HVAC requirements.

Room Schedule Listing of finishes (e.g. floors, walls, ceilings) and specialties (e.g. doors, windows, hardware) for each space in the building.

Safety File File containing all of the relevant health and safety characteristics of the project, updated throughout the project, which becomes the owner’s formal record on project completion. Also known as the Health and Safety File.

Safety Program Program employed to define the organization, procedures and methods that will be employed to ensure the safe execution of work.

Scale-up Criteria Chemical, unit operations and equipment variables, how they scale-up, and boundaries.

Single Line (Diagram) Drawing that schematically depicts the major elements of an electrical power distribution system including typically transformers, feeders, switchgear, motor control centers, motors and other significant loads.

Site Plan A scaled drawing showing the overall facility. This will normally include all operating units, administrative buildings and locations of all access into the plant.

Site Safety Program “Safety program” tailored for a specific site

Sociological, Technological, Economic, Political, Environmental

Major categories to be considered when evaluating the feasibility of a project opportunity for an owner. Includes review of regulatory agency issues; public acceptance issues; capital, operating, and other cost issues (including ROI, IRR, sensitivity and other cost analyses); trans-national, federal, national and local governmental issues; as well as environmental impact of proposed development.

Spare and Change Parts

Spare and interchangeable parts for project equipment that are provided under the contract.

Study Estimate Estimate produced during Phase 2, Conceptual Design, based on early documentation, typically having an accuracy of +30% to –20%.