proceeding of 122nd meeting of state level environment...
TRANSCRIPT
1
Proceeding of 122nd meeting of State Level Environment Impact Assessment Authority held on 02.05.2017 at 10:30 AM in Committee Room, Regional Office, Punjab Pollution Control Board, Mohali.
The following were present: 1. Sh. Darshan Singh Jaidka,
Chairman, SEIAA
2. Sh. Anil Kumar Sondhi, Member, SEIAA
3. Sh. Tejinder Singh Dhaliwal, IAS Member Secretary, SEIAA
At the outset, the Member Secretary (SEIAA) welcomed the
members of the State Environment Impact Assessment Authority (SEIAA) in
122nd meeting.
Item No.122.01: Confirmation of the minutes of 121st meeting of SEIAA held on 20.04.2017..
The SEIAA noted that the proceedings of 121st meeting of
SEIAA held on 20.04.2017, were circulated to all concerned vide letter no.
3663-64 dated 25.04.2017. No observation has been received from any of the
members. As such, SEIAA confirmed the said proceedings.
Item No.122.02: Action taken on the proceedings of 120th & 121st meeting of SEIAA held on 16.03.2017 & 20.04.2017 respectively.
The action taken report of 120th meeting of SEIAA held on
16.03.2017 was seen by the SEIAA. The SEIAA was apprised that the action on
the proceedings of 121st meeting of SEIAA held on 20.04.2017 is being taken
and the action taken report will be placed before the SEIAA in its next meeting.
Item No:122.03 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in the revenue estate of village Boont, Tehsil Ludhiana (E) District Ludhiana, Punjab of General Manager cum Mining Officer, District Industries Centre, Ludhiana. (Proposal No. SIA/PB/MIN/60652/2016)
The SEIAA observed that:-
2
The General Manager cum Mining Officer, District
Industries Centre, Ludhiana vide online application dated 06.04.2017, has
applied for obtaining environmental clearance under EIA notification dated
14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in
the revenue estate of village Boont, Tehsil Ludhiana (E) District Ludhiana,
Punjab. The project proponent submitted the Form-I, Pre-feasibility report,
DSR, Mining Plan ,EMP and other requisite documents
The case was considered by SEAC in its 157th meeting held on
12.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(ii) Sh. Paras Mahajan, Asst. Geologist.
(iii) Sh. S. Brahma, HOD-EIA & Shivani Duti, M/s Shivalik Solid Waste
Management Ltd., Environmental consultant of the project
proponent.
Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant presented the salient features of the mining project
site.
The SEAC observed that as per the jamabandi, the area of the
mining site is 22.74 hectares whereas in the application it has been mentioned
that mining of minor minerals (Sand) will be carried out in an area of 24.28
Hectare from the bed of river Satluj. Thus, the application is required to be
corrected with respect to the area and quantity of minor mineral. Further the
SEAC observed that as per the Google earth map attached with the application,
mining sites fall within the active channel. The project proponent contested
that at present active channel is away from the site. The project proponent
sought time to clarify the position and requested for deferment of the same.
After detailed deliberations, SEAC accepted the request of project
proponent and deferred the case.
3
The project proponent had submitted the corrected application
Form-I along with the Pre-Feasibility Report and Environmental Management
Plan. As per the corrected application, about 10,62,007 TPA of mining of minor
minerals (Sand) will be carried out in an area of 24.28 Hectare from the bed of
river Satluj in the revenue estate of village Boont, Tehsil Ludhiana (E) District
Ludhiana, Punjab in H.B. no. 63 bearing Khasra nos 5//11, 19, 20, 6//13, 14,
15, 16, 17, 18, 23, 24, 7/ /18, 19, 20, 21, 22, 23, 10//6, 14, 15, 16, 17, 11// 1,
2, 3, 4, 5, 6, 7, 8, 9, 10, 12//1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 14, 15, 13//1, 2, 3, 4,
5, 6, 7, 8, 9, 10, 14//1, 2, 3, 4, 5.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
Before allowing the presentation, SEAC queried that whether the
Environment Consultant of M/s Shivalik Solid Waste Management Ltd is a
NABET approved consultant as per the requirement of MoEF & CC Notification
dated 03.03.2016. In reply to this, Environmental Consultant of the project
proponent vide letter no. 0282 dated 28.05.2017 submitted a list of
organization obtained accreditation under NABET scheme, which is taken on
record by the SEAC. The SEAC observed that as per the list submitted, M/s
Shivalik Solid Waste Management Ltd. is a NABET approved consultant and Sh.
S. Brahma, HOD-EIA is the Environmental Co-coordinator of the consulted
company.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 10,62,007 TPA of mining of minor minerals (Sand) will be carried
out in an area of 24.28 Hectare from the bed of river Satluj in the
revenue estate of village Boont, Tehsil Ludhiana (E) District Ludhiana,
Punjab in H.B. no. 63 bearing Khasra nos 5//11, 19, 20, 6//13, 14, 15,
4
16, 17, 18, 23, 24, 7/ /18, 19, 20, 21, 22, 23, 10//6, 14, 15, 16, 17, 11//
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 12//1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 14, 15,
13//1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 14//1, 2, 3, 4, 5.
2) Mining Officer, DIC, Ludhiana vide no. 257 dated 01.03.2016 certified
that proposed river bed mining site have no other mining site existing
within 500 mtr periphery of the said mining lease.
3) NOC has been issued by the Department of Forest, Ludhiana vide letter
no. 11280 dated 13/03/2015 to the General Manager cum Mining
Officer, District Industries Centre, Ludhiana with certain condition.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 5,12,60,000 and the manpower
required will be 226 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 10.30 KLD out of
which 3.60 KLD will be used for domestic purpose and remaining 6.70
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 18 trucks/hr will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) During Mining activities, no solid & hazardous waste will be generated.
The Municipal waste generation shall be disposed off as per the Solid
Waste Management Rules, 2016. Segregation of bio-degradable waste
5
and non-bio degradable wastes shall be done at site and disposed off
accordingly.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 11,65,000 will be incurred as total capital cost & Rs.
2,33,000 per annum as recurring cost for the implementation of the EMP
on the following activities: -
(i) Management of Haulage Roads including Sprinkling, Tractor trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.). (iii) Plantation. (iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 10,25,200 will be spent for following activities under
Corporate Social Responsibility for the people residing in nearby villages:
(i) Toilets will be made in the nearby school. Items like desk, chair, storage bins & Almira, dari will be given to the nearby schools.
(ii) Organizing regular health check-up camps for the mine workers periodically to observe any contradictions due to exposure to dust and take corrective measures.
(iii) Medicines will be given in the nearby dispensaries. (iv) Common vocational training, awareness programme will be
organized in the nearby villages.
The SEAC raised certain queries to which the project proponent
submitted the reply, the details of which are as under: -
6
Sr. No.
Observations of SEAC Reply given by project proponent
1. As to whether mining site is a part of the active channel
General Manager, DIC, Ludhiana submitted an undertaking to the effect that he has visited the mining site on 17.04.2017 alongwith field staff and the mining site is situated in the riverbed of River Satluj but is not a part of active channel, which is taken on record by the SEAC.
2. As to whether land of the mining project involve private ownership land. If yes, whether consents of the concerned land owner(s) have been obtained for carried out the mining operation.
Project proponent informed that the mining is to be carried out from the private ownership land and consent has already been obtained from the land owner during the time of site appraisal. The project proponent submitted their consent for mining in areas to make their land fertile, which are taken on record by the SEAC.
General Manager, DIC, Ludhiana requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand) @ 10,62,007 TPA from the bed of river Satluj in total area of
24.28 Hectare having H.B. no. 63, bearing Khasra nos. 5//11, 19, 20, 6//13,
14, 15, 16, 17, 18, 23, 24, 7/ /18, 19, 20, 21, 22, 23, 10//6, 14, 15, 16, 17,
11// 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 12//1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 14, 15, 13//1,
2, 3, 4, 5, 6, 7, 8, 9, 10, 14//1, 2, 3, 4, 5 located in the revenue estate of
village Boont, Tehsil Ludhiana (E) District Ludhiana, Punjab, subject to the
conditions proposed at Annexure-A of the proceedings in addition to the
proposed measures and specific condition that project proponent shall comply
with the condition imposed by DFO Ludhiana while granting NOC vide no
11280 dated 13/03/2015.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
7
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC, Ludhiana.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Ludhiana replied that the haulage road
has already been marked on the 'Aks Sajra'.
During discussions, General Manager-cum-Mining officer, DIC,
Ludhiana agreed to comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures.
Item No:122.04 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in the revenue estate of village Chakli Kasab, Tehsil Samrala District Ludhiana, Punjab of General Manager cum Mining Officer, District Industries Centre, Ludhiana. (Proposal No. SIA/PB/MIN/60702/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District
Industries Centre, Ludhiana vide online application dated 06.04.2017, has
applied for obtaining environmental clearance under EIA notification dated
14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in
the revenue estate of village Chakli Kasab, Tehsil Samrala District Ludhiana,
Punjab. The project is covered under category 1 (a) of the Schedule appended
8
to the said notification. The project proponent submitted the Form-I, Pre-
feasibility report, DSR, Mining Plan ,EMP and other requisite documents.
The case was considered by SEAC in its 157th meeting held on
12.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(ii) Sh. Paras Mahajan, Asst. Geologist.
(iii) Sh. S. Brahma, HOD-EIA & Shivani Duti, M/s Shivalik Solid Waste
Management Ltd., Environmental consultant of the project
proponent.
Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant presented the salient features of the mining project
site.
The SEAC observed that as per the Google earth map imagery
on 24.02.2017 attached with the application, part of the site falls inside the
active channel. The project proponent contested that at present active channel
is away from the site. The project proponent sought time to clarify the position
and requested for deferment of the same.
After detailed deliberations, SEAC accepted the request of project
proponent and deferred the case.
The project proponent has submitted the corrected application
Form-I along with the Pre-Feasibility Report. As per the corrected application,
about 3,58,668 TPA of mining of minor minerals (Sand) will be carried out in
an area of 8.20 Hectare from the bed of river Satluj in the revenue estate of
village Chakli Kasab, Tehsil Samrala District Ludhiana, Punjab in H.B. no. 450
bearing Khasra nos 8//5/2, 5/3/16/2, 17/2, 18/2, 24, 25, 9//1, 15//22, 23,
16//8, 9, 10, 11/1, 17//4, 5/2, 7, 20//1, 2, 3/1, 3/2, 8/2, 9, 10, 11, 12.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
9
(i) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 3,58,668 TPA of mining of minor minerals (Sand) will be carried
out in an area of 8.20 Hectare from the bed of river Satluj in the
revenue estate of village Chakli Kasab, Tehsil Samrala District Ludhiana,
Punjab in H.B. no. 450 bearing Khasra nos 8//5/2, 5/3/16/2, 17/2, 18/2,
24, 25, 9//1, 15//22, 23, 16//8, 9, 10, 11/1, 17//4, 5/2, 7, 20//1, 2, 3/1,
3/2, 8/2, 9, 10, 11, 12.
2) Mining Officer, DIC, Ludhiana vide no.262 dated 01.03.2016 certified
that proposed river bed mining site have no other mining site existing
within 500 mtr periphery of the said mining lease.
3) NOC has been issued by the Department of Forest, Ludhiana vide letter
no. 11280 dated 13/03/2015 to the General Manager cum Mining
Officer, District Industries Centre, Ludhiana with certain condition.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 1,78,60,000 and the manpower
required will be 250 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 4.31 KLD out of
which 3.51 KLD will be used for domestic purpose and remaining 0.810
10
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 88 trucks/day will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) During Mining activities, no solid & hazardous waste will be generated.
The Municipal waste generation shall be disposed off as per the Solid
Waste Management Rules, 2016. Segregation of bio-degradable waste
and non-bio degradable wastes shall be done at site and disposed off
accordingly.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 7,45,000 will be incurred as total capital cost & Rs.
1,49,000 per annum as recurring cost for the implementation of the EMP
on the following activities: -
(i) Management of Haulage Roads including Sprinkling, Tractor trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.). (iii) Plantation. (iv) Occupational Health measure such as first aid and other
miscellaneous.
11
16) About Rs. 3,57,200 will be spent for following activities under Corporate
Social Responsibility for the people residing in nearby villages: -
(v) Toilets will be made in the nearby school. Items like desk, chair, storage bins & Almira, dari will be given to the nearby schools.
(vi) Organizing regular health check-up camps for the mine workers periodically to observe any contradictions due to exposure to dust and take corrective measures.
(vii) Medicines will be given in the nearby dispensaries. (viii) Common vocational training, awareness programme will be
organized in the nearby villages.
The SEAC raised certain queries to which the project proponent
submitted the reply, the details of which are as under: -
Sr. No.
Observations of SEAC Reply given by project proponent
1. As to whether mining site is a part of the active channel
General Manager, DIC, Ludhiana submitted an undertaking to the effect that he has visited the mining site on 18.04.2017 alongwith field staff and the mining site is situated in the riverbed of River Satluj but is not a part of active channel, which is taken on record by the SEAC.
2. As to whether land of the mining project involve private ownership land. If yes, whether consents of the concerned land owner(s) have been obtained for carried out the mining operation.
Project proponent informed that the mining is to be carried out from the private ownership land and consent has already been obtained from the land owner during the time of site appraisal. The project proponent submitted their consent for mining in areas to make their land fertile, which are taken on record by the SEAC.
General Manager, DIC, Ludhiana requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand) @ 3,58,668 TPA from the bed of river Satluj in total area of
8.20 Hectare having H.B. no. 450 bearing Khasra nos 8//5/2, 5/3/16/2, 17/2,
18/2, 24, 25, 9//1, 15//22, 23, 16//8, 9, 10, 11/1, 17//4, 5/2, 7, 20//1, 2, 3/1,
3/2, 8/2, 9, 10, 11, 12 located in the revenue estate of village Chakli Kasab,
12
Tehsil Samrala District Ludhiana, Punjab, subject to the conditions proposed at
Annexure-A of the proceedings in addition to the proposed measures and
specific condition that project proponent shall comply with the condition
imposed by DFO Ludhiana while granting NOC vide no 11280 dated
13/03/2015.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Ludhiana submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA.
During discussions, General Manager-cum-Mining officer, DIC,
Ludhiana agreed to comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures.
13
Item No:122.05 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the off river bed (Paleochannel of river Satluj) in the revenue estate of village Bounkar Gujran, Tehsil Ludhiana (E) District Ludhiana, Punjab of General Manager cum Mining Officer, District Industries Centre, Ludhiana. (Proposal No. SIA/PB/MIN/61265 /2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Ludhiana vide online application dated 06.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Sand) from the off river bed (Paleochannel of river
Satluj) in the revenue estate of village Bounkar Gujran, Tehsil Ludhiana (E)
District Ludhiana, Punjab. The project is covered under category 1 (a) of the
Schedule appended to the said notification. The project proponent submitted
the Form-I, Pre-feasibility report, DSR, Mining Plan ,EMP and other requisite
documents.
The case was considered by SEAC in its 157th meeting held on
12.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(ii) Sh. Paras Mahajan, Asst. Geologist.
(iii) Sh. S. Brahma, HOD-EIA & Shivani Duti, M/s Shivalik Solid Waste
Management Ltd., Environmental consultant of the project
proponent.
Before allowing Environmental consultant to present the case, the
SEAC queried that whether land of the mining project involve private ownership
land. In reply to this query, project proponent informed that the mining is to be
carried out from the private ownership land. To an another query of SEAC
whether consent of the concerned land owner(s) has been obtained for carried
out the mining operation, project proponent sought time to submit the consent
letter and requested for deferment.
14
After discussion, SEAC accepted the request of project proponent
and decided to defer the case.
The project proponent has submitted the corrected application
Form-I along with the Pre-Feasibility Report. As per the corrected application,
about 2,93,098 MT of mining of minor minerals (Sand) will be carried out in an
area of 7.5 Hectare from the off river bed (Paleochannel of river Satluj) in the
revenue estate of village Bounkar Gujran, Tehsil Ludhiana (E) District Ludhiana,
Punjab in H.B. no. 39 bearing Khasra nos 6//19, 20, 21, 22, 23, 7//16, 14//4,
5, 17/1, 23/ 1, 24/1, 22/2, 23/2, 24/2, 15//1, 2, 3, 9, 10, 12, 13, 4/1.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(iv) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(v) Sh. Sushminder Singh, State Geologist.
(vi) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 2,93,098 MT of mining of minor minerals (Sand) will be carried
out in an area of 7.5 Hectare ( Minable 6.7 ha) from the off river bed
(Paleochannel of river Satluj) in the revenue estate of village Bounkar
Gujran, Tehsil Ludhiana (E) District Ludhiana, Punjab in H.B. no. 39
bearing Khasra nos 6//19, 20, 21, 22, 23, 7//16, 14//4, 5, 17/1, 23/ 1,
24/1, 22/2, 23/2, 24/2, 15//1, 2, 3, 9, 10, 12, 13, 4/1.
2) The project proponent submitted an undertaking to the effect that no
mining site falls within radius of 1Km from the periphery from the
mining site for which application has been submitted.
3) NOC has been issued by the Department of Forest, Ludhiana vide letter
no. 11280 dated 13/03/2015 to the General Manager cum Mining
Officer, District Industries Centre, Ludhiana with certain condition.
15
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 1,56,10,000 and the manpower
required will be 63 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 3.71 KLD out of
which 2.83 KLD will be used for domestic purpose and remaining 0.88
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 16 trucks/hr will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) During Mining activities, no solid & hazardous waste will be generated.
The Municipal waste generation shall be disposed off as per the Solid
Waste Management Rules, 2016. Segregation of bio-degradable waste
and non-bio degradable wastes shall be done at site and disposed off
accordingly.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
16
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 7,07,500 will be incurred as total capital cost & Rs.
1,41,500 per annum as recurring cost for the implementation of the EMP
on the following activities: -
(i) Management of Haulage Roads including Sprinkling, Tractor trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.). (iii) Plantation. (iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 3,12,200 will be spent for following activities under Corporate
Social Responsibility for the people residing in nearby villages: -
(i) Toilets will be made in the nearby school. Items like desk, chair, storage bins & Almira, dari will be given to the nearby schools.
(ii) Organizing regular health check-up camps for the mine workers periodically to observe any contradictions due to exposure to dust and take corrective measures.
(iii) Medicines will be given in the nearby dispensaries. (iv) Common vocational training, awareness programme will be
organized in the nearby villages.
The SEAC queried to the project proponent as to whether land of
the mining project involve private ownership land. If yes, whether consents of
the concerned land owner(s) have been obtained for carried out the mining
operation. In reply to this query, project proponent informed that the mining is
to be carried out from the private ownership land and consent has already
been obtained from the land owner during the time of site appraisal. The
project proponent submitted their consent for mining in areas to make their
land fertile, which are taken on record by the SEAC
General Manager, DIC, Ludhiana requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
17
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand) @ 2,93,098 MT from the off river bed (Paleochannel of river
Satluj) in total area of 7.5 Hectare (Minable area :6.7 ha) having H.B. no. 39
bearing Khasra nos 6//19, 20, 21, 22, 23, 7//16, 14//4, 5, 17/1, 23/ 1, 24/1,
22/2, 23/2, 24/2, 15//1, 2, 3, 9, 10, 12, 13, 4/1 located in the revenue estate
of village Bounkar Gujran, Tehsil Ludhiana (E) District Ludhiana, Punjab,
subject to the conditions proposed at Annexure-A of the proceedings in
addition to the proposed measures and specific condition that project
proponent shall comply with the condition imposed by DFO Ludhiana while
granting NOC vide no 11280 dated 13/03/2015.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Ludhiana submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA.
During discussions, General Manager-cum-Mining officer, DIC,
Ludhiana agreed to comply with fully all the conditions as mentioned by SEAC.
18
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
The SEIAA observed that conditions for grant of environmental
clearance recommended by SEAC are same for river bed as well as off river
bed/flood plain mining sites as mentioned in Annexure-A. The conditions of
off river bed/flood plain mining sites are entirely different from conditions to
be imposed in river bed mining cases.
After deliberations, SEIAA decided that conditions recommended by
SEAC and accepted by SEIAA in earlier off river bed/flood plain cases (item
No. 122.05, 122.06, 122.08 & 122.09) be imposed with slight updation i.e.
requirement of sustainable sand mining guidelines, 2016 and monitoring
procedure to be adopted as per MoEF notification No. S.O. 141 (E) dated
15.01.2016. The SEIAA finalized the conditions, which are annexed with the
proceedings as Annexure-B.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Ludhiana submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA.
19
During discussions, General Manager-cum-Mining officer, DIC,
Ludhiana agreed to comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed at Annexure-B of the proceedings in addition to the
proposed measures.
Item No:122.06 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the off river bed (Paleochannel of river Satluj) in the revenue estate of village Balliewal, Tehsil Ludhiana (E) District Ludhiana, Punjab of General Manager cum Mining Officer, District Industries Centre, Ludhiana.(Proposal No. SIA/PB/MIN/60627/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District
Industries Centre, Ludhiana vide online application dated 05.04.2017, has
applied for obtaining environmental clearance under EIA notification dated
14.09.2006 for mining of minor minerals (Sand) from the off river bed
(Paleochannel of river Satluj) in the revenue estate of village Balliewal, Tehsil
Ludhiana (E) District Ludhiana, Punjab. The project is covered under category
1 (a) of the Schedule appended to the said notification. The project proponent
submitted the Form-I, Pre-feasibility report, DSR, Mining Plan ,EMP and other
requisite documents.
The case was considered by SEAC in its 157th meeting held on
12.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(ii) Sh. Paras Mahajan, Asst. Geologist.
20
(iii) Sh. S. Brahma, HOD-EIA & Shivani Duti, M/s Shivalik Solid Waste
Management Ltd., Environmental consultant of the project
proponent.
Before allowing Environmental consultant to present the case, the
SEAC queried that whether land of the mining project involve private ownership
land. In reply to this query, project proponent informed that the mining is to be
carried out from the private ownership land. To an another query of SEAC
whether consents of the concerned land owner(s) have been obtained for
carried out the mining operation, project proponent sought time to submit the
consent letter and requested for deferment.
After discussion, SEAC accepted the request of project proponent
and decided to defer the case.
The project proponent had submitted the corrected application
Form-I along with the Pre-Feasibility Report. As per the corrected application,
about 5,38,439 MT of mining of minor minerals (Sand) will be carried out in an
area of 16.20 Hectare from the off river bed (Paleochannel of river Satluj) in
the revenue estate of village Balliewal, Tehsil Ludhiana (E) District Ludhiana,
Punjab in H.B. no. 17 bearing Khasra nos 4//16, 7//2,3,8//1,10//2, 9, 40//2,
15, 16, 24/2, 25/2, 29/2, 51// 4/1/2, 5, 53//18, 19, 22, 23, 24, 56//16/2, 17/ 1,
18/2/2, 24, 25, 57//21/1, 60//4, 5/1, 62//3 /2/2, 8, 9, 10, 11, 11/2, 12, 18/2,
19, 20, 21, 22, 2 3, 63//2, 3, 4, 5, 6/1, 6/2, 7, 8, 9, 14/2, 15/1, 15/ 3, 18,
24/2, 25, 64//4, 6, 6, 7, 65//1, 2, 3, 9, 10, 11, 12, 67//14/1, 17/1, 18/1, 23/3.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(vii) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(viii) Sh. Sushminder Singh, State Geologist.
(ix) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
21
1) About 5,38,439 MT of mining of minor minerals (Sand) will be carried
out in an area of 16.20 Hectare from the off river bed (Paleochannel of
river Satluj) in the revenue estate of village Balliewal, Tehsil Ludhiana
(E) District Ludhiana, Punjab H.B. no. 17 bearing Khasra nos 4//16,
7//2,3,8//1,10//2, 9, 40//2, 15, 16, 24/2, 25/2, 29/2, 51// 4/1/2, 5,
53//18, 19, 22, 23, 24, 56//16/2, 17/ 1, 18/2/2, 24, 25, 57//21/1, 60//4,
5/1, 62//3 /2/2, 8, 9, 10, 11, 11/2, 12, 18/2, 19, 20, 21, 22, 2 3, 63//2,
3, 4, 5, 6/1, 6/2, 7, 8, 9, 14/2, 15/1, 15/ 3, 18, 24/2, 25, 64//4, 6, 6, 7,
65//1, 2, 3, 9, 10, 11, 12, 67//14/1, 17/1, 18/1, 23/3.
2) The project proponent submitted an undertaking to the effect that no
mining site falls within radius of 1Km from the periphery from the
mining site for which application has been submitted.
3) NOC has been issued by the Department of Forest, Ludhiana vide letter
no. 11280 dated 13/03/2015 to the General Manager cum Mining
Officer, District Industries Centre, Ludhiana with certain condition.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 4,82,21,244 and the manpower
required will be 89 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 6.45 KLD out of
which 5.17 KLD will be used for domestic purpose and remaining 1.28
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 11 trucks/hr will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
22
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) During Mining activities, no solid & hazardous waste will be generated.
The Municipal waste generation shall be disposed off as per the Solid
Waste Management Rules, 2016. Segregation of bio-degradable waste
and non-bio degradable wastes shall be done at site and disposed off
accordingly.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 7,72,500 will be incurred as total capital cost & Rs.
1,54,500 per annum as recurring cost for the implementation of the EMP
on the following activities: -
(i) Management of Haulage Roads including Sprinkling, Tractor trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.). (iii) Plantation. (iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 9,64,425 will be spent for following activities under Corporate
Social Responsibility for the people residing in nearby villages: -
(i) Toilets will be made in the nearby school. Items like desk, chair, storage bins & Almira, dari will be given to the nearby schools.
(ii) Organizing regular health check-up camps for the mine workers periodically to observe any contradictions due to exposure to dust
23
and take corrective measures. (iii) Medicines will be given in the nearby dispensaries. (iv) Common vocational training, awareness programme will be
organized in the nearby villages.
The SEAC queried to the project proponent as to whether land of
the mining project involve private ownership land. If yes, whether consents of
the concerned land owner(s) have been obtained for carried out the mining
operation. In reply to this query, project proponent informed that the mining is
to be carried out from the private ownership land and consent has already
been obtained from the land owner during the time of site appraisal. The
project proponent submitted their consent for mining in areas to make their
land fertile, which are taken on record by the SEAC
General Manager, DIC, Ludhiana requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand) @ 5,38,439 MT from the off river bed (Paleochannel of river
Satluj) in total area of 16.20 Hectare (Minable area: 12.31 hectare) having H.B.
no. 17 bearing Khasra nos 4//16, 7//2,3,8//1,10//2, 9, 40//2, 15, 16, 24/2,
25/2, 29/2, 51// 4/1/2, 5, 53//18, 19, 22, 23, 24, 56//16/2, 17/ 1, 18/2/2, 24,
25, 57//21/1, 60//4, 5/1, 62//3 /2/2, 8, 9, 10, 11, 11/2, 12, 18/2, 19, 20, 21,
22, 2 3, 63//2, 3, 4, 5, 6/1, 6/2, 7, 8, 9, 14/2, 15/1, 15/ 3, 18, 24/2, 25, 64//4,
6, 6, 7, 65//1, 2, 3, 9, 10, 11, 12, 67//14/1, 17/1, 18/1, 23/3 located in the
revenue estate of village Balliewal, Tehsil Ludhiana (E) District Ludhiana,
subject to the conditions proposed at Annexure-A of the proceedings in
addition to the proposed measures and specific condition that project
proponent shall comply with the condition imposed by DFO Ludhiana while
granting NOC vide no 11280 dated 13/03/2015.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
24
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Ludhiana submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA.
During discussions, General Manager-cum-Mining officer, DIC,
Ludhiana agreed to comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as finalized in item No. 122.05 at Annexure-B of the proceedings
in addition to the proposed measures.
Item No:122.07 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in the revenue estate of village Kanian Hussaini, Tehsil Jagraon District Ludhiana, Punjab of General Manager cum Mining Officer, District Industries Centre, Ludhiana. (Proposal No. SIA/PB/MIN/60821/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Ludhiana vide online application dated 07.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Sand) from the bed of river Satluj in the revenue
estate of village Kanian Hussaini, Tehsil Jagraon District Ludhiana, Punjab. The
25
project is covered under category 1 (a) of the Schedule appended to the said
notification. The project proponent submitted the Form-I, Pre-feasibility report,
DSR, Mining Plan ,EMP and other requisite documents .
The case was considered by SEAC in its 157th meeting held on
12.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(ii) Sh. Paras Mahajan, Asst. Geologist.
(iii) Sh. S. Brahma, HOD-EIA & Shivani Duti, M/s Shivalik Solid Waste
Management Ltd., Environmental consultant of the project proponent.
Before allowing Environmental consultant to present the case, the
SEAC queried that whether land of the mining project involve private ownership
land. In reply to this query, project proponent informed that the private
ownership land is a part of the mining site. To an another query of SEAC
whether consent of the concerned land owner(s) has been obtained for carried
out the mining operation, project proponent sought time to submit the consent
letter and requested for deferment.
Further, SEAC observed that as per the application total area of
the khasra nos., area of the mining site is 20.5 hectare whereas in the DSR,
area of the mining site is 20.5 acres (8.30 hectares). Thus, the project
proponent is also required to clarify the same. In reply, the project proponent
again sought time to clarify the same and requested for deferment.
After discussion, SEAC accepted the request project proponent
and decided to defer the case.
The project proponent has submitted online request for the
withdrawal of the application.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Mahesh Khana, General Manager-cum-Mining officer, DIC,
Ludhiana.
(ii) Sh. Sushminder Singh, State Geologist.
26
(iii) Sh. S. Brahma, HOD-EIA & Shivani Duti, M/s Shivalik Solid Waste
Management Ltd., Environmental consultant of the project
proponent.
General Manager, DIC, Ludhiana requested for allowing him to
withdraw his application for sand mining as fresh application has been
submitted online.
After discussions, the SEAC decided to forward the case to the
SEIAA with the recommendation to allow the applicant to withdraw his
application.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
General Manager-cum-Mining officer, DIC, Ludhiana requested
for allowing him to withdraw his application for sand mining as fresh
application has been submitted online due to units of the area mentioned in
the DSR was in acres instead of hectares and not matching with the
application.
After detailed deliberations, the SEIAA decided to accept the
recommendation of SEAC and take the action as proposed by the SEAC.
Item No:122.08 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the off river bed (Paleochannel of river Satluj) in the revenue estate of village Ratangarh, Tehsil Ludhiana (E) District Ludhiana, Punjab of General Manager cum Mining Officer, District Industries Centre, Ludhiana. (Proposal No. SIA/PB/MIN/60844/2016)
The SEIAA observed that:-
27
The General Manager cum Mining Officer, District Industries
Centre, Ludhiana vide online application dated 07.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Sand) from the off river bed (Paleochannel of river
Satluj) in the revenue estate of village Ratangarh, Tehsil Ludhiana (E) District
Ludhiana, Punjab. The project is covered under category 1 (a) of the Schedule
appended to the said notification. The project proponent submitted the Form-I,
Pre-feasibility report, DSR, Mining Plan ,EMP and other requisite documents.
The case was considered by SEAC in its 157th meeting held on
12.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(ii) Sh. Paras Mahajan, Asst. Geologist.
(iii) Sh. S. Brahma, HOD-EIA & Shivani Duti, M/s Shivalik Solid Waste
Management Ltd., Environmental consultant of the project
proponent.
Before allowing Environmental consultant to present the case, the
SEAC queried that whether land of the mining project involve private ownership
land. In reply to this query, project proponent informed that the mining is to be
carried out from the private ownership land. To an another query of SEAC
whether consent of the concerned land owner(s) has been obtained for carried
out the mining operation, project proponent sought time to submit the consent
letter and requested for deferment.
After discussion, SEAC accepted the request project proponent
and decided to defer the case.
The project proponent has submitted the corrected application Form-I
along with the Pre-Feasibility Report. As per the corrected application, about 5,
52, 436 MT of mining of minor minerals (Sand) will be carried out in an area of
13.76 hectare from the off river bed (Paleochannel of river Satluj) in the
revenue estate of village Ratangarh, Tehsil Ludhiana (E) District Ludhiana,
Punjab in H.B. no. 19 bearing Khasra nos 6//24, 25, 7//19/2, 20, 21, 22, 17//1,
28
2, 7/1, 8/1, 9, 10, 12/1, 23/1/2, 18//5/1, 5/2, 6/1, 20//3/1, 3/2, 8/1, 8/2, 9,
10, 30//23, 31//24, 34//4, 5, 6, 7, 8, 13, 14, 15, 16, 35//1, 2, 9, 10, 11, 12, 13,
14, 17/2, 18, 19, 20.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 5, 52, 436 MT of mining of minor minerals (Sand) will be carried
out in an total area of 13.76 hectare (Minable area: 12.63 hectare) from
the off river bed (Paleochannel of river Satluj) in the revenue estate of
village Ratangarh, Tehsil Ludhiana (E) District Ludhiana, Punjab in H.B.
no. 19 bearing Khasra nos 6//24, 25, 7//19/2, 20, 21, 22, 17//1, 2, 7/1,
8/1, 9, 10, 12/1, 23/1/2, 18//5/1, 5/2, 6/1, 20//3/1, 3/2, 8/1, 8/2, 9, 10,
30//23, 31//24, 34//4, 5, 6, 7, 8, 13, 14, 15, 16, 35//1, 2, 9, 10, 11, 12,
13, 14, 17/2, 18, 19, 20.
2) The project proponent submitted an undertaking to the effect that no
mining site falls within radius of 1Km from the periphery from the
mining site for which application has been submitted.
3) NOC has been issued by the Department of Forest, Ludhiana vide letter
no. 11280 dated 13/03/2015 to the General Manager cum Mining
Officer, District Industries Centre, Ludhiana with certain condition.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
29
6) The total cost of project will be Rs. 6,00,23,088 and the manpower
required will be 111 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 5.83 KLD out of
which 5.35 KLD will be used for domestic purpose and remaining 0.48
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 18 trucks/hr will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) During Mining activities, no solid & hazardous waste will be generated.
The Municipal waste generation shall be disposed off as per the Solid
Waste Management Rules, 2016. Segregation of bio-degradable waste
and non-bio degradable wastes shall be done at site and disposed off
accordingly.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
30
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 8,27,500 will be incurred as total capital cost & Rs.
1,65,500 per annum as recurring cost for the implementation of the EMP
on the following activities: -
(i) Management of Haulage Roads including Sprinkling, Tractor trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.). (iii) Plantation. (iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 12,00,461 will be spent for following activities under
Corporate Social Responsibility for the people residing in nearby villages:
-
(i) Toilets will be made in the nearby school. Items like desk, chair, storage bins & Almira, dari will be given to the nearby schools.
(ii) Organizing regular health check-up camps for the mine workers periodically to observe any contradictions due to exposure to dust and take corrective measures.
(iii) Medicines will be given in the nearby dispensaries. (iv) Common vocational training, awareness programme will be
organized in the nearby villages.
The SEAC queried to the project proponent as to whether land of
the mining project involve private ownership land. If yes, whether consents of
the concerned land owner(s) have been obtained for carried out the mining
operation. In reply to this query, project proponent informed that the mining is
to be carried out from the private ownership land and consent has already
been obtained from the land owner during the time of site appraisal. The
project proponent submitted their consent for mining in areas to make their
land fertile, which are taken on record by the SEAC
General Manager, DIC, Ludhiana requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand) @ 5, 52, 436 MT from the off river bed (Paleochannel of river
31
Satluj) in total area of 13.76 hectare having H.B. no. 19 bearing Khasra nos
6//24, 25, 7//19/2, 20, 21, 22, 17//1, 2, 7/1, 8/1, 9, 10, 12/1, 23/1/2, 18//5/1,
5/2, 6/1, 20//3/1, 3/2, 8/1, 8/2, 9, 10, 30//23, 31//24, 34//4, 5, 6, 7, 8, 13, 14,
15, 16, 35//1, 2, 9, 10, 11, 12, 13, 14, 17/2, 18, 19, 20 located in the revenue
estate of village Ratangarh, Tehsil Ludhiana (E) District Ludhiana, Punjab,
subject to the conditions proposed at Annexure-A of the proceedings in
addition to the proposed measures and specific condition that project
proponent shall comply with the condition imposed by DFO Ludhiana while
granting NOC vide no 11280 dated 13/03/2015.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been marked
on the 'Aks Sajra', the GMDIC, Ludhiana submitted a copy of 'Aks Sajra' on
which haulage road has been marked, which was taken on record by SEIAA.
During discussions, General Manager-cum-Mining officer, DIC,
Ludhiana agreed to comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as finalized in item No. 122.05 at Annexure-B of the proceedings
in addition to the proposed measures.
32
Item No:122.09 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the off river bed (Paleochannel of river Satluj) in the revenue estate of village Bukhri Khurd, Tehsil Ludhiana (E) District Ludhiana, Punjab of General Manager cum Mining Officer, District Industries Centre, Ludhiana. (Proposal No. SIA/PB/MIN/60700/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Ludhiana vide online application dated 08.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Sand) from the off river bed (Paleochannel of river
Satluj) in the revenue estate of village Bukhri Khurd, Tehsil Ludhiana (E)
District Ludhiana, Punjab. The project is covered under category 1 (a) of the
Schedule appended to the said notification. The project proponent submitted
the Form-I, Pre-feasibility report, DSR, Mining Plan ,EMP and other requisite
documents.
The case was considered by SEAC in its 157th meeting held on
12.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(ii) Sh. Paras Mahajan, Asst. Geologist.
(iii) Sh. S. Brahma, HOD-EIA & Shivani Duti, M/s Shivalik Solid Waste
Management Ltd., Environmental consultant of the project
proponent.
Before allowing Environmental consultant to present the case, the
SEAC queried that whether land of the mining project involve private ownership
land. In reply to this query, project proponent informed that the mining is to be
carried out from the private ownership land. To an another query of SEAC
whether consent of the concerned land owner(s) has been obtained for carried
out the mining operation, project proponent sought time to submit the consent
letter and requested for deferment.
33
After discussion, SEAC accepted the request project proponent
and decided to defer the case.
The project proponent has submitted the corrected application Form-I
along with the Pre-Feasibility Report. As per the corrected application, about
7,58,452 MT of mining of minor minerals (Sand) will be carried out in an area
of 22.66 Hectare from the off river bed (Paleochannel of river Satluj) in the
revenue estate of village Bukhri Khurd, Tehsil Ludhiana (E) District Ludhiana,
Punjab in H.B. no. 185 bearing Khasra nos 1//16, 17, 18, 23, 24, 25, 3//3, 4, 5,
6, 7, 13, 14, 15, 16, 17, 18, 23/1, 23/2, 24/1, 24/2, 25, 100, 108, 8//6/2, 15/2,
16, 18, 23, 24, 25, 9//1/2, 2/2, 2/3/3, 3/1, 3/2, 4, 5, 6/1, 7/1/1, 8/1, 9/1/1/1,
1/2/1, 9/2, 10, 11, 12/1, 19/2, 20, 21, 22/1, 10//1, 10, 11//21, 12//12/2/3/2,
17/1, 13//2/2, 17//2, 18, 19/1, 22/2, 23, 24, 25/2, 17//14/2, 15/2, 16, 25,
18//5/2, 19/1/1, 4, 5, 5, 6, 7/1, 14/2, 15/1, 15/2, 16, 17/1, 20//1, 10, 11/1,
11/2, 20, 22//11, 20, 21, 23//8, 13/1, 13/2, 18, 23/1, 32//16/2, 17/1, 24/2,
32//25/1, 35//4/2, 5/1, 6/2, 7/1, 14/2, 17/1.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(iv) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(v) Sh. Sushminder Singh, State Geologist.
(vi) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 7, 58, 452 MT of mining of minor minerals (Sand) will be carried
out in an total area of 22.66 Hectare (Minable area: 17.34 hectare) from
the off river bed (Paleochannel of river Satluj) in the revenue estate of
village Bukhri Khurd, Tehsil Ludhiana (E) District Ludhiana, Punjab in
H.B. no. 185 bearing Khasra nos 1//16, 17, 18, 23, 24, 25, 3//3, 4, 5, 6,
7, 13, 14, 15, 16, 17, 18, 23/1, 23/2, 24/1, 24/2, 25, 100, 108, 8//6/2,
15/2, 16, 18, 23, 24, 25, 9//1/2, 2/2, 2/3/3, 3/1, 3/2, 4, 5, 6/1, 7/1/1,
8/1, 9/1/1/1, 1/2/1, 9/2, 10, 11, 12/1, 19/2, 20, 21, 22/1, 10//1, 10,
34
11//21, 12//12/2/3/2, 17/1, 13//2/2, 17//2, 18, 19/1, 22/2, 23, 24,
25/2, 17//14/2, 15/2, 16, 25, 18//5/2, 19/1/1, 4, 5, 5, 6, 7/1, 14/2,
15/1, 15/2, 16, 17/1, 20//1, 10, 11/1, 11/2, 20, 22//11, 20, 21, 23//8,
13/1, 13/2, 18, 23/1, 32//16/2, 17/1, 24/2, 32//25/1, 35//4/2, 5/1, 6/2,
7/1, 14/2, 17/1.
2) The project proponent submitted an undertaking to the effect that no
mining site falls within radius of 1Km from the periphery from the
mining site for which application has been submitted.
3) NOC has been issued by the Department of Forest, Ludhiana vide letter
no. 11280 dated 13/03/2015 to the General Manager cum Mining
Officer, District Industries Centre, Ludhiana with certain condition.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 6,77,77,955 and the manpower
required will be 125 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 12.38 KLD out of
which 9.0 KLD will be used for domestic purpose and remaining 3.38
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 16 trucks/hr will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
35
10) During Mining activities, no solid & hazardous waste will be generated.
The Municipal waste generation shall be disposed off as per the Solid
Waste Management Rules, 2016. Segregation of bio-degradable waste
and non-bio degradable wastes shall be done at site and disposed off
accordingly.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 8,62,500 will be incurred as total capital cost & Rs.
1,72,500 per annum as recurring cost for the implementation of the EMP
on the following activities: -
(i) Management of Haulage Roads including Sprinkling, Tractor trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.). (iii) Plantation. (iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 13,55,559 will be spent for following activities under
Corporate Social Responsibility for the people residing in nearby villages:
-
(v) Toilets will be made in the nearby school. Items like desk, chair, storage bins & Almira, dari will be given to the nearby schools.
(vi) Organizing regular health check-up camps for the mine workers periodically to observe any contradictions due to exposure to dust and take corrective measures.
(vii) Medicines will be given in the nearby dispensaries. (viii) Common vocational training, awareness programme will be
36
organized in the nearby villages.
The SEAC queried to the project proponent as to whether land of
the mining project involve private ownership land. If yes, whether consents of
the concerned land owner(s) have been obtained for carried out the mining
operation. In reply to this query, project proponent informed that the mining is
to be carried out from the private ownership land and consent has already
been obtained from the land owner during the time of site appraisal. The
project proponent submitted their consent for mining in areas to make their
land fertile, which are taken on record by the SEAC
General Manager, DIC, Ludhiana requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand) @ 7, 58, 452 MT from the off river bed (Paleochannel of river
Satluj) in total area of 22.66 Hectare (Minable area: 17.34 hectare) having H.B.
no. 185 bearing Khasra nos 1//16, 17, 18, 23, 24, 25, 3//3, 4, 5, 6, 7, 13, 14,
15, 16, 17, 18, 23/1, 23/2, 24/1, 24/2, 25, 100, 108, 8//6/2, 15/2, 16, 18, 23,
24, 25, 9//1/2, 2/2, 2/3/3, 3/1, 3/2, 4, 5, 6/1, 7/1/1, 8/1, 9/1/1/1, 1/2/1, 9/2,
10, 11, 12/1, 19/2, 20, 21, 22/1, 10//1, 10, 11//21, 12//12/2/3/2, 17/1,
13//2/2, 17//2, 18, 19/1, 22/2, 23, 24, 25/2, 17//14/2, 15/2, 16, 25, 18//5/2,
19/1/1, 4, 5, 5, 6, 7/1, 14/2, 15/1, 15/2, 16, 17/1, 20//1, 10, 11/1, 11/2, 20,
22//11, 20, 21, 23//8, 13/1, 13/2, 18, 23/1, 32//16/2, 17/1, 24/2, 32//25/1,
35//4/2, 5/1, 6/2, 7/1, 14/2, 17/1 located in the revenue estate of village
Bukhri Khurd, Tehsil Ludhiana (E) District Ludhiana, Punjab, subject to the
conditions proposed at Annexure-A of the proceedings in addition to the
proposed measures and specific condition that project proponent shall comply
with the condition imposed by DFO Ludhiana while granting NOC vide no
11280 dated 13/03/2015.
37
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Ludhiana replied that the haulage road
has already been marked on the 'Aks Sajra'.
During discussions, General Manager-cum-Mining officer, DIC,
Ludhiana agreed to comply with fully all the conditions as mentioned by SEAC.
Further, the SEIAA observed that khasra numbers 20//1, 10,
11/1, 11/2, 20, (total area 0.1125 hectares) on the 'Aks Sajra' formed a narrow
mining strip. The SEIAA queried to the project proponent that how the mining
will be carried out after leaving 7.5 m distance from both sides as no mining
area will be left out.
In reply to this query, the project proponent requested to grant
environmental clearance excluding above mentioned khasra numbers for
carrying out mining of minor minerals (Sand) reduced to 7,53,641 MT from the
off river bed (Paleochannel of river Satluj) in total area reduced to 22.54
hectares (Minable area reduced to 17.23 hectare).
The Authority accepted the recommendations of SEAC & the request of project
proponent and decided to grant environmental clearance to the project for
carrying out for mining of minor minerals (Sand) @ 7,53,641 MT from the off
river bed (Paleochannel of river Satluj) in total area of 22.54 hectares (Minable
area: 17.23 hectare) having H.B. no. 185 bearing Khasra nos 1//16, 17, 18, 23,
24, 25, 3//3, 4, 5, 6, 7, 13, 14, 15, 16, 17, 18, 23/1, 23/2, 24/1, 24/2, 25, 100,
38
108, 8//6/2, 15/2, 16, 18, 23, 24, 25, 9//1/2, 2/2, 2/3/3, 3/1, 3/2, 4, 5, 6/1,
7/1/1, 8/1, 9/1/1/1, 1/2/1, 9/2, 10, 11, 12/1, 19/2, 20, 21, 22/1, 10//1, 10,
11//21, 12//12/2/3/2, 17/1, 13//2/2, 17//2, 18, 19/1, 22/2, 23, 24, 25/2,
17//14/2, 15/2, 16, 25, 18//5/2, 19/1/1, 4, 5, 5, 6, 7/1, 14/2, 15/1, 15/2, 16,
17/1, 22//11, 20, 21, 23//8, 13/1, 13/2, 18, 23/1, 32//16/2, 17/1, 24/2,
32//25/1, 35//4/2, 5/1, 6/2, 7/1, 14/2, 17/1 located in the revenue estate of
village Bukhri Khurd, Tehsil Ludhiana (E) District Ludhiana, Punjab, subject to
the conditions as finalized in item No. 122.05 at Annexure-B of the
proceedings in addition to the proposed measures.
Item No:122.10 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand & Gravel) from the bed of river ujh, tributary of Ravi river in the revenue estate of village Muthi, Tehsil & District Pathankot, Punjab of General Manager cum Mining Officer, District Industries Centre, Pathankot. (Proposal No. SIA/PB/MIN/60093/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District
Industries Centre, Pathankot vide online application dated 06.04.2017, has
applied for obtaining environmental clearance under EIA notification dated
14.09.2006 for mining of minor minerals (Sand) from the bed of river Ujh,
tributary of Ravi river in the revenue estate of village Muthi, Tehsil & District
Pathankot, Punjab. The project is covered under category 1 (a) of the Schedule
appended to the said notification. The project proponent submitted the Form-I,
Pre-feasibility report, DSR, Mining Plan ,EMP and other requisite documents.
The case was considered by SEAC in its 157th meeting held on
12.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Balvinder Pal Singh, General Manager-cum-Mining officer, DIC,
Pathankot.
(ii) Sh. Paras Mahajan, Asst. Geologist.
39
(iii) Sh. S. Brahma, HOD-EIA & Shivani Duti, M/s Shivalik Solid Waste
Management Ltd., Environmental consultant of the project
proponent.
The case could not be taken up due to paucity of time and SEAC
deferred the same.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Balvinder Pal Singh, General Manager-cum-Mining officer, DIC,
Pathankot.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 6,94,918 TPA of mining of minor minerals (Sand & Gravel) will be
carried out in an area of 12.71 Hectare from the bed of river Ujh,
tributary of Ravi river in the revenue estate of village Muthi, Tehsil &
District Pathankot, Punjab in H.B. no. 33 bearing Khasra nos 2R//13(0-
17), 16(3-18), 17(4-9), 18(8-0), 22(1-0) 23/1(5-0), 23/2(3-0), 24(8-0),
6//1(4-4), 2(4-0), 3/1(6-2), 3/2(1-18), 4(8-0), 7(5-0), 8/1(6-12), 8/2(1-
8), 9(8-0), 11(4-0), 6//12(8-0), 13(8-0), 14(8-0), 17(8-0), 18(8-0), 19(8-
0), 20(7-4), 21(7-4), 22(8-0), 23(8-0), 24(8-0), 25(8-0), 9//2(7-2), 3(4-
2), 4(4-2), 6(3-2), 8(8-0), 9(8-0), 10(8-0), 11(8-0), 12(8-0), 13(8-0),
14(8-0), 16(4-0), 18(8-0)19(8-0), 20(8-0), 21(8-0), 22(8-0), 23(8-0).
2) Mining Officer, DIC, Pathankot certified that proposed river bed mining
site have no other mining site existing within 500 mtr periphery of the
said mining lease.
3) A copy of the proceedings of the meeting held on 31.01.2014 under the
chairmanship of SDM, Pathankot submitted to the effect that no
objection has been raised by DFO Wildlife, Pathankot & DFO Forest
Pathankot & other committee members for the Khasra Nos. of the
40
mining project and the mining site has been recommended to the Govt.
for the extraction of the mining minerals.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 3,41,10,000 and the manpower
required will be 150 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 10.52 KLD out of
which 6.75 KLD will be used for domestic purpose and remaining 3.77
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 29 trucks/day will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) Nominal Solid waste to be generated by the mining workers at the
mining site. Provisions of the dustbins will be made at mining site and
the waste will be collected on the regular basis to avoid their spillage.
Waste generated at the mine site by the workers will be disposed off as
per the Solid Waste Management Rules, 2016.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
41
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 9,25,000 will be incurred as total capital cost & Rs.
1,85,000 per annum as recurring cost for the implementation of the EMP
on the following activities: -
(i) Management of Haulage Roads including Sprinkling, Tractor trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.). (iii) Plantation. (iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 6,82,200 will be spent for following activities under Corporate
Social Responsibility for the people residing in nearby villages: -
i. Short awareness program will be conducted for labours prior to mining. ii. Regular health check-up camps for the workers engaged in mines shall
be organized. iii. Local needs of habitants like school, crèche, hospital, veterinary
hospital, sanitation, drinking water etc. shall be considered positively. iv. Common vocational training centre shall be setup at district level.
The SEAC raised certain queries to which the project proponent
submitted the reply, the details of which are as under: -
Sr. No.
Observations of SEAC Reply given by project proponent
3. As to whether mining site is a part of the active channel
General Manager, DIC, Pathankot submitted an undertaking to the effect that he has visited the mining site on 26.04.2017 alongwith field staff and the mining site is situated in the riverbed of River Satluj but is not a part of active channel, which is taken on record by the SEAC.
4. As to whether land of the mining project involve private
Project proponent informed that the mining is to be carried out from the private
42
ownership land. If yes, whether consents of the concerned land owner(s) have been obtained for carried out the mining operation.
ownership land and consent has already been obtained from the land owner during the time of site appraisal. The project proponent submitted their consent for mining in areas to make their land fertile, which are taken on record by the SEAC.
General Manager, DIC, Pathankot requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand & Gravel) @ 6,94,918 TPA rom the bed of river Ujh, tributary of
Ravi river in total area of 12.71 Hectare having H.B. no. 33 bearing Khasra nos
2R//13(0-17), 16(3-18), 17(4-9), 18(8-0), 22(1-0) 23/1(5-0), 23/2(3-0), 24(8-
0), 6//1(4-4), 2(4-0), 3/1(6-2), 3/2(1-18), 4(8-0), 7(5-0), 8/1(6-12), 8/2(1-8),
9(8-0), 11(4-0), 6//12(8-0), 13(8-0), 14(8-0), 17(8-0), 18(8-0), 19(8-0), 20(7-
4), 21(7-4), 22(8-0), 23(8-0), 24(8-0), 25(8-0), 9//2(7-2), 3(4-2), 4(4-2), 6(3-
2), 8(8-0), 9(8-0), 10(8-0), 11(8-0), 12(8-0), 13(8-0), 14(8-0), 16(4-0), 18(8-
0)19(8-0), 20(8-0), 21(8-0), 22(8-0), 23(8-0 located in the revenue estate of
village Muthi, Tehsil & District Pathankot, Punjab, subject to the conditions
proposed at Annexure-A of the proceedings in addition to the proposed
measures.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Balwinder Pal Singh, General Manager-cum-Mining officer, DIC,
Pathankot.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
43
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Pathankot submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA.
To another query of SEIAA regarding conversation factors of the
units of the mining area, the project proponent submitted that as per Punjab
Land Record Manual (Page 184) the conversation factor of 1 Kanal = 20
Marlas, 20 Marlas = 418.063 sqm. Hence, the total mining area of the site i.e
304.2 Kanal converted as 304.2 Kanal x 418.063 sqm = 127174.76 sqm i.e.
12.71 hectares for which application for obtaining environmental clearance has
been filed.
During discussions, General Manager-cum-Mining Officer, DIC,
Pathankot agreed to comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures.
Item No:122.11 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand & Gravel) from the bed of river ujh, tributary of Ravi river in the revenue estate of village Samrala, Tehsil & District Pathankot, Punjab of General Manager cum Mining Officer, District Industries Centre, Pathankot. (Proposal No. SIA/PB/MIN/60101/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Pathankot vide online application dated 06.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Sand) from the bed of river Ujh, tributary of Ravi
river in the revenue estate of village Samrala, Tehsil & District Pathankot,
44
Punjab. The project is covered under category 1 (a) of the Schedule appended
to the said notification. The project proponent submitted the Form-I, Pre-
feasibility report, DSR, Mining Plan ,EMP and other requisite documents.
The case was considered by SEAC in its 157th meeting held on
12.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Balvinder Pal Singh, General Manager-cum-Mining officer, DIC,
Pathankot.
(ii) Sh. Paras Mahajan, Asst. Geologist.
(iii) Sh. S. Brahma, HOD-EIA & Shivani Duti, M/s Shivalik Solid Waste
Management Ltd., Environmental consultant of the project
proponent.
The case could not be taken up due to paucity of time and
SEAC deferred the same.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Balvinder Pal Singh, General Manager-cum-Mining officer, DIC,
Pathankot.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 6,44,072 TPA of mining of minor minerals (Sand & Gravel) will be
carried out in an area of 11.78 Hectare from the bed of river Ujh,
tributary of Ravi river in the revenue estate of village Samrala, Tehsil &
District Pathankot, Punjab in H.B. no. 15 bearing Khasra nos 9//6/1(0-
15), 13(8-0), 14(7-18), 15(1-2), 16(5-7), 17/1 (1-18), 17/2(4-18),
18/1(4-0), 23(7-18), 24/1(1-3), 24/2 (5-18), 25(7-11), 10//1/1(1-17),
1/2 (5-4), 2(8-0), 9(5-410(5-0), 12(4-12), 18/2(2-0), 19(7-16), 21(7-
11), 26(32-14), 15//3(7-4), 4(8-0), 7(8-0), 8(7-4), 13(7-4), 14 (8-0),
45
17(8-0), 18(7-4), 19/1(2-0), 22(7-0), 23(7-4), 24/1 (2-0), 22//3(6-8),
4(8-0), 7/1(6-0), 8(7-4), 9(8-0), 11 (8-0), 12(8-0), 13(7-4), 18/1(6-0),
19/1(2-0).
2) Mining Officer, DIC, Pathankot certified that proposed river bed mining
site have no other mining site existing within 500 mtr periphery of the
said mining lease.
3) A copy of the proceedings of the meeting held on 31.01.2014 under the
chairmanship of SDM, Pathankot submitted to the effect that no
objection has been raised by DFO Wildlife, Pathankot & DFO Forest
Pathankot & other committee members for the Khasra Nos. of the
mining project and the mining site has been recommended to the Govt.
for the extraction of the mining minerals.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 3,18,60,000 and the manpower
required will be 140 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 8.02 KLD out of
which 6.30 KLD will be used for domestic purpose and remaining 1.72
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 29 trucks/day will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
46
10) Nominal Solid waste to be generated by the mining workers at the
mining site. Provisions of the dustbins will be made at mining site and
the waste will be collected on the regular basis to avoid their spillage.
Waste generated at the mine site by the workers will be disposed off as
per the Solid Waste Management Rules, 2016.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 9,00,000 will be incurred as total capital cost & Rs.
1,80,000 per annum as recurring cost for the implementation of the EMP
on the following activities: -
(i) Management of Haulage Roads including Sprinkling, Tractor trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.). (iii) Plantation. (iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 6,37,200 will be spent for following activities under Corporate
Social Responsibility for the people residing in nearby villages: -
i. Short awareness program will be conducted for labours prior to mining. ii. Regular health check-up camps for the workers engaged in mines shall
be organized. iii. Local needs of habitants like school, crèche, hospital, veterinary
hospital, sanitation, drinking water etc. shall be considered positively. iv. Common vocational training centre shall be setup at district level.
47
The SEAC raised certain queries to which the project proponent
submitted the reply, the details of which are as under: -
Sr. No.
Observations of SEAC Reply given by project proponent
1. As to whether mining site is a part of the active channel
General Manager, DIC, Pathankot submitted an undertaking to the effect that he has visited the mining site on 26.04.2017 alongwith field staff and the mining site is situated in the riverbed of River Ujh but is not a part of active channel, which is taken on record by the SEAC.
2. As to whether land of the mining project involve private ownership land. If yes, whether consents of the concerned land owner(s) have been obtained for carried out the mining operation.
Project proponent informed that the mining is to be carried out from the private ownership land & submitted their consent for mining in areas to make their land fertile, which are taken on record by the SEAC.
General Manager, DIC, Pathankot requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand & Gravel) @ 6,44,072 TPA from the bed of river Ujh, tributary
of Ravi river in total area of 11.78 Hectare having H.B. no. 15 bearing Khasra
nos 9//6/1(0-15), 13(8-0), 14(7-18), 15(1-2), 16(5-7), 17/1 (1-18), 17/2(4-18),
18/1(4-0), 23(7-18), 24/1(1-3), 24/2 (5-18), 25(7-11), 10//1/1(1-17), 1/2 (5-
4), 2(8-0), 9(5-410(5-0), 12(4-12), 18/2(2-0), 19(7-16), 21(7-11), 26(32-14),
15//3(7-4), 4(8-0), 7(8-0), 8(7-4), 13(7-4), 14 (8-0), 17(8-0), 18(7-4), 19/1(2-
0), 22(7-0), 23(7-4), 24/1 (2-0), 22//3(6-8), 4(8-0), 7/1(6-0), 8(7-4), 9(8-0),
11 (8-0), 12(8-0), 13(7-4), 18/1(6-0), 19/1(2-0) located in the revenue estate
of village Samrala, Tehsil & District Pathankot, Punjab, subject to the
conditions proposed at Annexure-A of the proceedings in addition to the
proposed measures.
48
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Balwinder Pal Singh, General Manager-cum-Mining officer, DIC,
Pathankot.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Pathankot submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA.
To another query of SEIAA regarding conversation factors of the
units of the mining area, the project proponent submitted that as per Punjab
Land Record Manual (Page 184) the conversation factor of 1 Kanal = 20
Marlas, 20 Marlas = 418.063 sqm. Hence, the total mining area of the site i.e
282.2 Kanal converted as 282.2 Kanal x 418.063 sqm = 117977.3 sqm i.e.
11.79 hectares for which application for obtaining environmental clearance has
been filed.
During discussions, General Manager-cum-Mining officer, DIC,
Pathankot agreed to comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures.
49
Item No:122.12 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the bed of river Ravi in the revenue estate of village Raji Beli, Tehsil Dinanagar, District Gurdaspur, Punjab of General Manager cum Mining Officer, District Industries Centre, Gurdaspur. (Proposal No. SIA/PB/MIN/59087/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Gurdaspur vide online application dated 06.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Sand) from the bed of river Ravi in the revenue
estate of village Raji Beli, Tehsil Dinanagar, District Gurdaspur, Punjab. The
project is covered under category 1 (a) of the Schedule appended to the said
notification. The project proponent submitted the Form-I, Pre-feasibility report,
DSR, Mining Plan ,EMP and other requisite documents.
The case was considered by SEAC in its 157th meeting held on
12.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Balvinder Pal Singh, General Manager-cum-Mining officer, DIC,
Gurdaspu.
(ii) Sh. Paras Mahajan, Asst. Geologist.
(iii) Sh. S. Brahma, HOD-EIA & Shivani Duti, M/s Shivalik Solid Waste
Management Ltd., Environmental consultant of the project
proponent.
The case could not be taken up due to paucity of time and SEAC
deferred the same.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Balvinder Pal Singh, General Manager-cum-Mining officer, DIC,
Gurdaspur.
(ii) Sh. Sushminder Singh, State Geologist.
50
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 6, 36, 502 TPA of mining of minor minerals (Sand & Gravel) will
be carried out in an area of 14.5 Hectare or 349 Kanal 4 Marla from the
bed of river Ravi in the revenue estate of village Raji Beli, Tehsil
Dinanagar, District Gurdaspur, Punjab in H.B. no. 13 consist of five
blocks having details of Khasra no. as under:
Block I 2//12/3 (1-16), 18/4(0-9) (Area: 1Kanal 25 marla or 0.094 Ha)
Block II 6//5(5-10), 5//1/1 (2-18) (Area: 7Kanal 8 marla or 0.309 Ha)
Block III 5//4/1 (6-4) (Area: 6Kanal 4marla or 0.259Ha)
Block IV 7//5/1(4-4), 6(8-0), 16(8-0), 25/1(5-16), 25/2(0-0), 15(8-0),
5//21/1(3-8), 7//5/2(3-16), 8//1/1(3-12), 10/3(3-12), 11(7-9), 20(8-0),
21(8-0), 9//1(8-0), 10(5-2), 10//5(0-6), 6(0-9), 8//14(8-0), 6//15/2(6-
0), 16/1(7-16), 17/2(7-2), 18(7-12), 23(5-11), 24(7-11), 25(7-
11)2//19/1(3-8), 22/2(3-8), 23(8-0), 3/1(7-5), 7/3(6-4), 8/1(4-0), 12(5-
16), 19(8-0), 20/2(6-9), 5//3/2(0-16), 8/2(4-0), 21/2(4-0), 22(8-0),
8//1/2(0-16), 1/3(0-8), 1/4(2-16), 2(8-0), 9(8-0), 10/1(1-8), 10/2(2-12),
8//12/3(0-4), 18/2(5-4), 22(8-0), 23/1(5-4), 9//2(8-0), 9(3-13), 5//13(7-
6)(Area: 245kanal 310marla or 10.89ha)
Block V 8//5/2 (2-17), 14(8-0), 15(6-14), 5//14/3 (4-4), 15/1(2-8),
16/4(2-8), 17(5-16), 25/1(0-11), 8//8(8-0), 6(7-2), 7/1(3-16), 13(8-0),
7/2(3-1), 18/2(5-4), 5//14/1 (2-0), 8//14(8-0), 5//14/2 (1-16), 8//7/2
(3-1) (Area: 66kanal 117marla or 3.0 ha)
2) Mining Officer, DIC, Pathankot certified that proposed river bed mining
site have no other mining site existing within 500 mtr periphery of the
said mining lease.
3) A copy of the proceedings of the meeting held on 31.01.2014 under the
chairmanship of SDM, Pathankot submitted to the effect that no
objection has been raised by DFO Wildlife, Pathankot & DFO Forest
Pathankot & other committee members for the Khasra Nos. of the
51
mining project and the mining site has been recommended to the Govt.
for the extraction of the mining minerals.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 3,04,60,000 and the manpower
required will be 134 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 12 KLD out of
which 06 KLD will be used for domestic purpose and remaining 06 KLD
for dust suppression. water will be supplied through tankers from
nearby available source.
9) 70 trucks/day will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) Nominal Solid waste to be generated by the mining workers at the
mining site. Provisions of the dustbins will be made at mining site and
the waste will be collected on the regular basis to avoid their spillage.
Waste generated at the mine site by the workers will be disposed off as
per the Solid Waste Management Rules, 2016.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
52
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 8,35,000 will be incurred as total capital cost & Rs.
1,67,000 per annum as recurring cost for the implementation of the EMP
on the following activities: -
(i) Management of Haulage Roads including Sprinkling, Tractor
trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.).
(iii) Plantation.
(iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 6,09,200 will be spent for following activities under Corporate
Social Responsibility for the people residing in nearby villages: -
i. Short awareness program will be conducted for labours prior to mining.
ii. Regular health check-up camps for the workers engaged in mines shall
be organized.
iii. Local needs of habitants like school, crèche, hospital, veterinary
hospital, sanitation, drinking water etc. shall be considered positively.
iv. Common vocational training centre shall be setup at district level.
The SEAC raised certain queries to which the project proponent
submitted the reply, the details of which are as under: -
Sr.
No.
Observations of SEAC Reply given by project proponent
1. As to whether mining site is a
part of the active channel
General Manager, DIC, Pathankot
submitted an undertaking to the effect that
53
he has visited the mining site on
22.04.2017 alongwith field staff and the
mining site is situated in the riverbed of
River Ravi but is not a part of active
channel, which is taken on record by the
SEAC.
2. As to whether land of the mining
project involve private
ownership land. If yes, whether
consents of the concerned land
owner(s) have been obtained for
carried out the mining
operation.
Project proponent informed that the mining
is to be carried out from the private
ownership land & submitted their consent
for mining in areas to make their land
fertile, which are taken on record by the
SEAC.
General Manager, DIC, Gurdaspur requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand & Gravel) @ 6,36,502 TPA from the bed of river Ravi in total
area of 14.5 Hectare or 349 Kanal 4 Marla having H.B. no. 13 consist of five
blocks bearing Khasra no. 2//12/3 (1-16), 18/4(0-9) (Block I area: 1Kanal 25
marla or 0.094 Ha), 6//5(5-10), 5//1/1 (2-18) (Block II Area: 7Kanal 8 marla or
0.309 Ha), 5//4/1 (6-4) (Block III area: 6Kanal 4marla or 0.259Ha), 7//5/1(4-
4), 6(8-0), 16(8-0), 25/1(5-16), 25/2(0-0), 15(8-0), 5//21/1(3-8), 7//5/2(3-16),
8//1/1(3-12), 10/3(3-12), 11(7-9), 20(8-0), 21(8-0), 9//1(8-0), 10(5-2),
10//5(0-6), 6(0-9), 8//14(8-0), 6//15/2(6-0), 16/1(7-16), 17/2(7-2), 18(7-12),
23(5-11), 24(7-11), 25(7-11)2//19/1(3-8), 22/2(3-8), 23(8-0), 3/1(7-5), 7/3(6-
4), 8/1(4-0), 12(5-16), 19(8-0), 20/2(6-9), 5//3/2(0-16), 8/2(4-0), 21/2(4-0),
22(8-0), 8//1/2(0-16), 1/3(0-8), 1/4(2-16), 2(8-0), 9(8-0), 10/1(1-8), 10/2(2-
12), 8//12/3(0-4), 18/2(5-4), 22(8-0), 23/1(5-4), 9//2(8-0), 9(3-13), 5//13(7-
6)(Block-area-IV: 245kanal 310marla or 10.89ha), 8//5/2 (2-17), 14(8-0),
54
15(6-14), 5//14/3 (4-4), 15/1(2-8), 16/4(2-8), 17(5-16), 25/1(0-11), 8//8(8-0),
6(7-2), 7/1(3-16), 13(8-0), 7/2(3-1), 18/2(5-4), 5//14/1 (2-0), 8//14(8-0),
5//14/2 (1-16), 8//7/2 (3-1) (Block Area-V: 66kanal 117marla or 3.0 ha)
located in the revenue estate of village Raji Beli, Tehsil Dinanagar, District
Gurdaspur, Punjab, subject to the conditions proposed at Annexure-A of the
proceedings in addition to the proposed measures.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Balwinder Pal Singh, General Manager-cum-Mining Officer, DIC,
Gurdaspur.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Gurdaspur submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA. The SEIAA also observed that distance between active channel and
river bundh is also required to be marked on the 'Aks Sajra'. Accordingly, the
project proponent marked same on 'Aks Sajra'.
To another query of SEIAA regarding conversation factors of the
units of the mining area, the project proponent submitted that as per Punjab
Land Record Manual (Page 184) the conversation factor of 1 Kanal = 20
Marlas and 20 Marlas = 418.063 sqm. Hence, the total mining area of the site
i.e 349.2 Kanal converted as 349.2 Kanal x 418.063 sqm = 145987.5 sqm i.e.
14.5 hectares for which application for obtaining environmental clearance has
been filed.
55
During discussions, General Manager-cum-Mining officer, DIC,
Gurdaspur agreed to comply with fully all the conditions as mentioned by
SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures.
Item No:122.13 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the bed of river Ravi in the revenue estate of village Gurchak, Tehsil Dera Baba Nanak, District Gurdaspur, Punjab of General Manager cum Mining Officer, District Industries Centre, Gurdaspur. (Proposal No. SIA/PB/MIN/58917/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Gurdaspur vide online application dated 06.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Sand) from the bed of river Ravi in the revenue
estate of village Gurchak, Tehsil Dera Baba Nanak, District Gurdaspur, Punjab.
The project is covered under category 1 (a) of the Schedule appended to the
said notification. The project proponent submitted the Form-I, Pre-feasibility
report, DSR, Mining Plan , EMP and other requisite documents.
The case was considered by SEAC in its 157th meeting held on
12.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Balvinder Pal Singh, General Manager-cum-Mining officer, DIC,
Gurdaspur
(ii) Sh. Paras Mahajan, Asst. Geologist.
(iii) Sh. S. Brahma, HOD-EIA & Shivani Duti, M/s Shivalik Solid Waste
Management Ltd., Environmental consultant of the project
proponent.
56
The case could not be taken up due to paucity of time and SEAC
deferred the same.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Balvinder Pal Singh, General Manager-cum-Mining officer, DIC,
Gurdaspur.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 2,96,994 TPA of mining of minor minerals (Sand) will be carried
out in an area of 6.79 Hectare or 156 Kanal 219 from the bed of river in
the revenue estate of village Gurchak, Tehsil Dera Baba Nanak, District
Gurdaspur, Punjab in H.B. no. 492 bearing Khasra no. 1R/25(4-12),
7R/3(4-7), 4(7-9), 5/1(1-8), 5/2(1-12), 5/3(5-0), 6(8-0), 7(8-0), 8(7-12),
9(8 13), 10(4-18), 11(8-0), 12(8-0), 13(6-19), 14(7-07), 15(7 19), 16(6-
16), 17/1(4-0), 17/2(4-0), 18(8-0), 19/1(5-2), 19/2(1-12), 19/3(0-16),
8R/14(5-16), 15(9-11), 16(8-0), 17(8-0), 18(5-0).
2) Mining Officer, DIC, Pathankot certified that proposed river bed mining
site have no other mining site existing within 500 mtr periphery of the
said mining lease.
3) A copy of the proceedings of the meeting held on 31.01.2014 under the
chairmanship of SDM, Pathankot submitted to the effect that no
objection has been raised by DFO Wildlife, Pathankot & DFO Forest
Pathankot & other committee members for the Khasra Nos. of the
mining project and the mining site has been recommended to the Govt.
for the extraction of the mining minerals.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
57
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 1,44,85,000 and the manpower
required will be 63 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 6.83 KLD out of
which 2.83 KLD will be used for domestic purpose and remaining 4.0
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 14 trucks/day will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) Nominal Solid waste to be generated by the mining workers at the
mining site. Provisions of the dustbins will be made at mining site and
the waste will be collected on the regular basis to avoid their spillage.
Waste generated at the mine site by the workers will be disposed off as
per the Solid Waste Management Rules, 2016.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
58
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 6,57,500 will be incurred as total capital cost & Rs.
1,31,500 per annum as recurring cost for the implementation of the EMP
on the following activities: -
(i) Management of Haulage Roads including Sprinkling, Tractor trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.). (iii) Plantation. (iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 2,89,700 will be spent for following activities under Corporate
Social Responsibility for the people residing in nearby villages: -
i. Short awareness program will be conducted for labours prior to mining. ii. Regular health check-up camps for the workers engaged in mines shall
be organized. iii. Local needs of habitants like school, crèche, hospital, veterinary
hospital, sanitation, drinking water etc. shall be considered positively. iv. Common vocational training centre shall be setup at district level.
The SEAC raised certain queries to which the project proponent
submitted the reply, the details of which are as under: -
Sr. No.
Observations of SEAC Reply given by project proponent
1. As to whether mining site is a part of the active channel
General Manager, DIC, Batala submitted an undertaking to the effect that he has visited the mining site on 22.04.2017 alongwith field staff and the mining site is situated in the riverbed of River Ujh but is not a part of active channel, which is taken on record by the SEAC.
2. Khasra nos. of site mentioned in the application does not match with the khasra nos. of the consent letter.
Project proponent submitted certificate(s) issued by the Sarpanch of Gram Panchayat, Gurchak to the effect that owner (s) of the land not available, which were taken on record by the SEAC.
General Manager, DIC, Gurdaspur requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
59
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand) 2,96,994 TPA TPA from the bed of river Ravi in total area of
6.79 Hectare or 156 Kanal 219 having H.B. no. 492 bearing Khasra no.
1R/25(4-12), 7R/3(4-7), 4(7-9), 5/1(1-8), 5/2(1-12), 5/3(5-0), 6(8-0), 7(8-0),
8(7-12), 9(8 13), 10(4-18), 11(8-0), 12(8-0), 13(6-19), 14(7-07), 15(7 19),
16(6-16), 17/1(4-0), 17/2(4-0), 18(8-0), 19/1(5-2), 19/2(1-12), 19/3(0-16),
8R/14(5-16), 15(9-11), 16(8-0), 17(8-0), 18(5-0) located in the revenue estate
of village Gurchak, Tehsil Dera Baba Nanak, District Gurdaspur, Punjab, subject
to the conditions proposed at Annexure-A of the proceedings in addition to the
proposed measures.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Balwinder Pal Singh, General Manager-cum-Mining officer, DIC,
Gurdaspur.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
The SEIAA raised certain queries to which the project proponent
submitted the reply, the details of which are as under: -
Sr. No.
Observations of SEIAA Reply given by project proponent
1. As to whether haulage road has been marked on the 'Aks Sajra',
The GMDIC, Pathankot submitted a copy of 'Aks Sajra' on which haulage road has been marked, which was taken on record by SEIAA.
2. What is the conversation factor taken in the case to convert Kanal to hectare.
The project proponent submitted that as per Punjab Land Record Manual (Page 184) the conversation factor of 1 Kanal = 20
60
Marlas, 20 Marlas = 418.063 sqm. Hence, the total mining area of the site i.e 166.95 Kanal converted as 166.49 Kanal x 418.063 sqm=67956.5 sqm i.e. 6.79 hectares for which application for obtaining environmental clearance has been filed.
3. From which river mining of minor minerals (sand) has been carried out
The project proponent replied that mining of minor minerals (sand) will be carried out from the bed of River Ravi in the revenue estate of Village Gurchak, Tehsil Dera Baba Nanak, District Gurdaspur.
4. From the Aks Sajra, it was observed that 'Dhushi Bundh' is 1000 m away from the mining site, what safe guard will be taken.
The project proponent stated that the mining will be carried out strictly as per the mining guidelines .
During discussions, General Manager-cum-Mining Officer, DIC,
Gurdaspur agreed to comply with fully all the conditions as mentioned by
SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures and
special condition that the Mining Officer shall strictly follow sand mining
guidelines and maintain safe distance from 'Dhushi Bundh'.
Item No:122.14 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in the revenue estate of village Danewal, Tehsil Shahkot, District Jalandhar, Punjab of General Manager cum Mining Officer, District Industries Centre, Jalandhar. (Proposal no. SIA/PB/MIN/59467/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District
Industries Centre, Jalandhar vide online application dated 24.04.2017, has
61
applied for obtaining environmental clearance under EIA notification dated
14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in
the revenue estate of village Danewal, Tehsil Shahkot, District Jalandhar,
Punjab. The project is covered under category 1 (a) of the Schedule appended
to the said notification. The project proponent submitted the Form-I, Pre-
feasibility report, DSR, Mining Plan, EMP and other requisite documents.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Amarjit Singh, General Manager-cum-Mining officer, DIC, Jalandhar.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 4,42,649 TPA of mining of minor minerals (Sand) will be carried
out in an area of 10.12 Hectare from the bed of river Satluj in the
revenue estate of village Danewal, Tehsil Shahkot, District Jalandhar,
Punjab in H.B. no. 305 bearing Khasra nos 56//5, 6, 7, 8, 13, 14, 57//1,
2, 3, 8, 9, 11, 13, 18, 19, 20, 51//11, 12, 13, 14, 16, 17.
2) Mining Officer, DIC, Jalandhar certified that no mining lease is granted
within 500 mtr periphery from the area of said mining lease.
3) NOC has been issued by the Department of Forest, Jalandhar vide letter
no. 4463 dated 23/08/2016 to the General Manager cum Mining Officer,
District Industries Centre, Jalandhar.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 2,15,10,000 and the manpower
required will be 94 nos.
62
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 7.59 KLD out of
which 4.23 KLD will be used for domestic purpose and remaining 3.36
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 15 trucks/hr will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) Nominal Solid waste to be generated by the mining workers at the
mining site. Provisions of the dustbins will be made at mining site and
the waste will be collected on the regular basis to avoid their spillage.
Waste generated at the mine site by the workers will be disposed off as
per the Solid Waste Management Rules, 2016.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 7,85,000 will be incurred as total capital cost & Rs.
63
1,57,000 per annum as recurring cost for the implementation of the EMP
on the following activities: -
(i) Management of Haulage Roads including Sprinkling, Tractor
trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.).
(iii) Plantation.
(iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 4,30,200 will be spent for following activities under Corporate
Social Responsibility for the people residing in nearby villages: -
i. Short awareness program will be conducted for labours prior to mining.
ii. Regular health check-up camps for the workers engaged in mines shall be organized.
iii. Local needs of habitants like school, crèche, hospital, veterinary hospital, sanitation, drinking water etc. shall be considered positively.
iv. Common vocational training centre shall be setup at district level.
The SEAC raised certain queries to which the project proponent submitted the reply, the details of which are as under: -
Sr. No.
Observations of SEAC Reply given by project proponent
1. As to whether mining site is a part of the active channel
General Manager, DIC, Jalandhar submitted an undertaking to the effect that he has visited the mining site on 23.04.2017 alongwith field staff and the mining site is situated in the riverbed of River Satluj but is not a part of active channel, which is taken on record by the SEAC.
2. As to whether land of the mining project involve private ownership land. If yes, whether consents of the concerned land owner(s) have been obtained for carried out the mining operation.
Project proponent informed that the mining is also to be carried out from the private ownership land and consent has already been obtained from the land owner during the time of site appraisal. The project proponent submitted their consent for mining in areas to make their land fertile, which are taken on record by the SEAC.
General Manager, DIC, Jalandhar requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
64
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand) @ 4,42,649 TPA from the bed of river Satluj in total area of
10.12 Hectare having H.B. no. 305 bearing Khasra nos 56//5, 6, 7, 8, 13, 14,
57//1, 2, 3, 8, 9, 11, 13, 18, 19, 20, 51//11, 12, 13, 14, 16, 17 located in the
revenue estate of village Danewal, Tehsil Shahkot, District Jalandhar, Punjab,
subject to the conditions proposed at Annexure-A of the proceedings in
addition to the proposed measures.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Amarjit Singh, General Manager-cum-Mining officer, DIC, Jalandhar.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Jalandhar submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA.
During discussions, General Manager-cum-Mining officer, DIC,
Jalandhar agreed to comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures.
65
Item No:122.15 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in the revenue estate of village Chak Bahmanian, Tehsil Shahkot District Jalandhar, Punjab of General Manager cum Mining Officer, District Industries Centre, Jalandhar. (Proposal no. SIA\PB\MIN\59428\2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Jalandhar vide online application dated 23.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Sand) from the bed of river Satluj in the revenue
estate of village Chak Bahmanian, Tehsil Shahkot District Jalandhar. The
project is covered under category 1 (a) of the Schedule appended to the said
notification. The project proponent submitted the Form-I, Pre-feasibility report,
DSR, Mining Plan ,EMP and other requisite documents.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Amarjit Singh, General Manager-cum-Mining officer, DIC, Jalandhar.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 8,00,879 TPA of mining of minor minerals (Sand) will be carried
out in an area of 18.31 Hectare from the bed of river Satluj in the
revenue estate of village Chak Bahmanian, Tehsil Shahkot District
Jalandhar in H.B. no. 277 bearing Khasra nos 25//6, 4, 5, 7, 15, 16,
28//2, 3, 8, 9, 24//18, 19, 20, 21, 22, 23, 24, 25, 25//1, 2, 3, 8, 9, 10,
11, 12, 13, 14, 17, 18, 19, 20, 16//1, 9, 10, 11, 12, 13, 18, 19, 20, 21,
22, 23, 24, 25.
2) Mining Officer, DIC, Jalandhar certified that no mining lease is granted
within 500 mtr periphery from the area of said mining lease.
66
3) NOC has been issued by the Department of Forest, Jalandhar vide letter
no. 4463 dated 23/08/2016 to the General Manager cum Mining Officer,
District Industries Centre, Jalandhar.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 7,49,30,000 and the manpower
required will be 138 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 9.55 KLD out of
which 3.34 KLD will be used for domestic purpose and remaining 6.21
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 16 trucks/hr will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) Nominal Solid waste to be generated by the mining workers at the
mining site. Provisions of the dustbins will be made at mining site and
the waste will be collected on the regular basis to avoid their spillage.
Waste generated at the mine site by the workers will be disposed off as
per the Solid Waste Management Rules, 2016.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
67
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 9,45,000 will be incurred as total capital cost & Rs.
1,89,000 per annum as recurring cost for the implementation of the EMP
on the following activities: -
(i) Management of Haulage Roads including Sprinkling, Tractor
trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.).
(iii) Plantation.
(iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 7,73,200 will be spent for following activities under Corporate
Social Responsibility for the people residing in nearby villages: -
i. Short awareness program will be conducted for labours prior to mining.
ii. Regular health check-up camps for the workers engaged in mines shall
be organized.
iii. Local needs of habitants like school, crèche, hospital, veterinary
hospital, sanitation, drinking water etc. shall be considered positively.
iv. Common vocational training centre shall be setup at district level.
The SEAC raised certain queries to which the project proponent submitted the reply, the details of which are as under: -
Sr. No.
Observations of SEAC Reply given by project proponent
1. As to whether mining site is a part of the active channel
General Manager, DIC, Jalandhar submitted an undertaking to the effect that he has visited the mining site on 23.04.2017 alongwith field staff and the
68
mining site is situated in the riverbed of River Satluj but is not a part of active channel, which is taken on record by the SEAC.
2. As to whether land of the mining project involve private ownership land. If yes, whether consents of the concerned land owner(s) have been obtained for carried out the mining operation.
Project proponent informed that project does not involve private ownership land. The entire mining is to be carried out from the Panchyat land.
General Manager, DIC, Jalandhar requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand) @ 8,00,879 TPA from the bed of river Satluj in total area of
18.31 Hectare having H.B. no. 277 bearing Khasra nos 25//6, 4, 5, 7, 15, 16,
28//2, 3, 8, 9, 24//18, 19, 20, 21, 22, 23, 24, 25, 25//1, 2, 3, 8, 9, 10, 11, 12,
13, 14, 17, 18, 19, 20, 16//1, 9, 10, 11, 12, 13, 18, 19, 20, 21, 22, 23, 24, 25
located in the revenue estate of village Chak Bahmanian, Tehsil Shahkot
District Jalandhar, Punjab subject to the conditions proposed at Annexure-A of
the proceedings in addition to the proposed measures.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Amarjit Singh, General Manager-cum-Mining officer, DIC, Jalandhar.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
69
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Jalandhar submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA.
During discussions, General Manager-cum-Mining officer, DIC,
Jalandhar agreed to comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures.
Item No:122.16 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in the revenue estate of village Rampur, Tehsil Shahkot, District Jalandhar, Punjab of General Manager cum Mining Officer, District Industries Centre, Jalandhar. (Proposal no. SIA/PB/MIN/59475/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Jalandhar vide online application dated 24.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Sand) from the bed of river Satluj in the revenue
estate of village Rampur, Tehsil Shahkot, District Jalandhar, Punjab. The
project is covered under category 1 (a) of the Schedule appended to the said
notification.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Amarjit Singh, General Manager-cum-Mining officer, DIC, Jalandhar.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
70
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 6,57,850 TPA of mining of minor minerals (Sand) will be carried
out in an area of 15.04 Hectare from the bed of river Satluj in the
revenue estate village Rampur, Tehsil Shahkot, District Jalandhar,
Punjab in H.B. no. 287 bearing Khasra nos 40/3, 4, 5, 6, 26//4, 5, 6, 7,
8, 13, 14, 15, 17, 18, 23, 24, 25, 37//5, 6, 7, 14, 15, 16, 39//1, 5, 6, 8,
9, 10, 11, 12, 18, 19, 23, 45//6, 7, 8, 9, 10.
2) Mining Officer, DIC, Jalandhar certified that no mining lease is granted
within 500 mtr periphery from the area of said mining lease.
3) NOC has been issued by the Department of Forest, Jalandhar vide letter
no. 4463 dated 23/08/2016 to the General Manager cum Mining Officer,
District Industries Centre, Jalandhar.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 1,33,60,000 and the manpower
required will be 125 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 6.31 KLD out of
which 3.64 KLD will be used for domestic purpose and remaining 2.67
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 13 trucks/hr will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
71
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) Nominal Solid waste to be generated by the mining workers at the
mining site. Provisions of the dustbins will be made at mining site and
the waste will be collected on the regular basis to avoid their spillage.
Waste generated at the mine site by the workers will be disposed off as
per the Solid Waste Management Rules, 2016.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 7,52,500 will be incurred as total capital cost & Rs.
1,50,500 per annum as recurring cost for the implementation of the EMP
on the following activities: -
(i) Management of Haulage Roads including Sprinkling, Tractor
trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.).
(iii) Plantation.
(iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 2,67,200 will be spent for following activities under Corporate
Social Responsibility for the people residing in nearby villages: -
i. Short awareness program will be conducted for labours prior to mining.
72
ii. Regular health check-up camps for the workers engaged in mines shall
be organized.
iii. Local needs of habitants like school, crèche, hospital, veterinary
hospital, sanitation, drinking water etc. shall be considered positively.
iv. Common vocational training centre shall be setup at district level.
The SEAC raised certain queries to which the project proponent submitted the reply, the details of which are as under: -
Sr. No.
Observations of SEAC Reply given by project proponent
1. As to whether mining site is a part of the active channel
General Manager, DIC, Jalandhar submitted an undertaking to the effect that he has visited the mining site on 23.04.2017 alongwith field staff and the mining site is situated in the riverbed of River Satluj but is not a part of active channel, which is taken on record by the SEAC.
2. As to whether land of the mining project involve private ownership land. If yes, whether consents of the concerned land owner(s) have been obtained for carried out the mining operation.
Project proponent informed that project does not involve private ownership land. The entire mining is to be carried out from the Government land.
3. As per the jamabandi the Hadbast no. of the village is 281 whereas as per the mining plan, H.B.No. is 287. The project proponent was asked to clarify the Hadbast No.
Project proponent clarified that Hadbast No. of village Rampur is 281. The project proponent stated that there is a clerical mistake in the mining plan and corrected the application, which is taken on record by the SEAC.
4. Khasra No. 26//8 and 39//6 mentioned in the application are not mentioned in the jamabandi.
The project proponent requested to grant Environment Clearance for the area except the Khasra nos. which are not mentioned in the jamabandi. The SEAC observed that after excluding the Khasra no. 26//8 and 39//6, the remaining mining area is 14.24 hectare. Accordingly, quantity of mining of minor minerals (Sand) in an area of 14.24 Hectare will be 6,22,858 TPA.
General Manager, DIC, Jalandhar requested to recommend the case to
SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
73
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand) @ 6,22,858 TPA from the bed of river Satluj in total area of
14.24 Hectare having H.B. no. 281 bearing Khasra nos 40/3, 4, 5, 6, 26//4, 5,
6, 7, 13, 14, 15, 17, 18, 23, 24, 25, 37//5, 6, 7, 14, 15, 16, 39//1, 5, 8, 9, 10,
11, 12, 18, 19, 23, 45//6, 7, 8, 9, 10 located in the revenue estate of village
Rampur, Tehsil Shahkot, District Jalandhar, Punjab subject to the conditions
proposed at Annexure-A of the proceedings in addition to the proposed
measures.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Amarjit Singh, General Manager-cum-Mining officer, DIC, Jalandhar.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Jalandhar submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA.
During discussions, General Manager-cum-Mining officer, DIC,
Jalandhar agreed to comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures.
74
Item No:122.17 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in the revenue estate of village Vehran, Tehsil Nakodar, District Jalandhar, Punjab of General Manager cum Mining Officer, District Industries Centre, Jalandhar. (Proposal no. SIA/PB/MIN/59446/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Jalandhar vide online application dated 23.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Sand) from the bed of river Satluj in the revenue
estate of village Vehran, Tehsil Nakodar, District Jalandhar, Punjab. The project
is covered under category 1 (a) of the Schedule appended to the said
notification. The project proponent submitted the Form-I, Pre-feasibility report,
DSR, Mining Plan, EMP and other requisite documents
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Amarjit Singh, General Manager-cum-Mining officer, DIC, Jalandhar.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 6,10,173 TPA of mining of minor minerals (Sand) will be carried
out in an area of 13.95 Hectare from the bed of river Satluj in the
revenue estate village Vehran, Tehsil Nakodar, District Jalandhar, Punjab
in H.B. no. 335 bearing Khasra nos 36//11(7-7), 12(7-11), 13(7-11),
14(7-11), 15(7-11), 16(8-0), 17(8-0), 18(8-0), 19(6-7), 20(2-2), 21(8-
0), 22(8-0), 23(2-11), 24(7-2), 25(8-0), 29//16(8-0), 17(8-0), 18(8-0),
19(8-0), 20(8-0), 21(-8-0), 22(8-0), 23(8-0), 24(8-0), 25(8-0), 36//1(8-
0), 2(8-0), 3(8-0), 4(8-0), 5(8-0), 8(8-0), 9(8-0), 10(8-0), 37//20Min(4-
0), 37//19(8-0), 21(8-0), 22(8-0).
75
2) Mining Officer, DIC, Jalandhar certified that no mining lease is granted
within 500 mtr periphery from the area of said mining lease.
3) NOC has been issued by the Department of Forest, Jalandhar vide letter
no. 4463 dated 23/08/2016 to the General Manager cum Mining Officer,
District Industries Centre, Jalandhar.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 7,75,80,000 and the manpower
required will be 143 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 7.95 KLD out of
which 6.43 KLD will be used for domestic purpose and remaining 1.52
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 20 trucks/hr will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) Nominal Solid waste to be generated by the mining workers at the
mining site. Provisions of the dustbins will be made at mining site and
the waste will be collected on the regular basis to avoid their spillage.
Waste generated at the mine site by the workers will be disposed off as
per the Solid Waste Management Rules, 2016.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
76
12) Adequate occupational health & safety measures shall be provided to
the workers.
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 7,20,000 will be incurred as total capital cost & Rs.
1,44,000 per annum as recurring cost for the implementation of the EMP
on the following activities: -
(i) Management of Haulage Roads including Sprinkling, Tractor
trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.).
(iii) Plantation.
(iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 2,67,200 will be spent for following activities under Corporate
Social Responsibility for the people residing in nearby villages: -
i. Short awareness program will be conducted for labours prior to mining.
ii. Regular health check-up camps for the workers engaged in mines shall
be organized.
iii. Local needs of habitants like school, crèche, hospital, veterinary
hospital, sanitation, drinking water etc. shall be considered positively.
iv. Common vocational training centre shall be setup at district level.
The SEAC raised certain queries to which the project proponent submitted the reply, the details of which are as under: -
Sr. No.
Observations of SEAC Reply given by project proponent
1. As to whether mining site is a part of the active channel
General Manager, DIC, Jalandhar submitted an undertaking alongwith the photographs to the effect that he has visited the mining
77
site on 23.04.2017 alongwith field staff and the mining site is situated in the riverbed of River Satluj but is not a part of active channel, which is taken on record by the SEAC.
2. As to whether land of the mining project involve private ownership land. If yes, whether consents of the concerned land owner(s) have been obtained for carried out the mining operation.
Project proponent informed that project does not involve private ownership land. The entire mining is to be carried out from the Government land.
3. Khasra No. of the mining site are not mentioned in the jamabandi, DSR and Joint Inspection Report.
The project proponent requested to grant Environment Clearance for the area except the Khasra nos. which are not mentioned in the jamabandi, DSR and Joint Inspection Rreport. The SEAC observed that after excluding the Khasra no. 36//21 (8-0), 22 (8-0), the remaining mining area is 13.15 hectare. Accordingly, quantity of mining of minor minerals (Sand) in an area of 13.15 Hectare will be 5,75,181 TPA
4. It was informed to the SEAC that a complaint has been received through email dated 27.04.2017 from [email protected]. In the said complaint Munish Gover & Co., Kot Ise Khan, Moga informed that his firm has contract of the mining site located in the village Chhoula, Tehsil Nakodar, Distt. Jalandhar for five years, which is upto 2021. General Manager Cum-Mining officer, Jalandhar & Ludhiana has requested SEIAA/SEAC to grant Environment Clearance for the three mining sites, out of which two sites falls in the village of village Vehra & Raipur Gujran , Tehsil Nakodar, Distt. Jalandhar, and one is in the village Hujran, Tehsil Jagraon, Distt. Ludhiana. All three mining sites are located within the radius of mining site Chhoula, Tehsil Nakodar. As per the rules of SEIAA/SEAC,there will be no auction for the new
General Manager, DIC, Jalandhar has submitted a certificate to the effect that distance between mining site of Village Chhoula, Vehran, Raipur Gujran & Hujran are more than 500 meter from each other and mining site Hujran falls in the boundary of Distt. Ludhiana and remaining three mining sites falls in the Distt. Jalandhar, which was taken on record by the SEAC.
78
mining site within the radius of 1 KM from the old mining site. The boundary of all three mining sites are in touch with the boundary of the mining site, village Chhoula. It is therefore, requested that Environment Clearance to the said three sites not be granted, so these three sites should not be auctioned. If these three mining site be granted Environment Clearance then he will have only option to take help of Hon’ble High Court, Punjab & Haryana
General Manager, DIC, Jalandhar requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand) @ 5,75,181 TPA from the bed of river Satluj in total area of
13.15 Hectare having H.B. no. 335 bearing Khasra nos 36//11(7-7), 12(7-11),
13(7-11), 14(7-11), 15(7-11), 16(8-0), 17(8-0), 18(8-0), 19(6-7), 20(2-2),
23(2-11), 24(7-2), 25(8-0), 29//16(8-0), 17(8-0), 18(8-0), 19(8-0), 20(8-0),
21(-8-0), 22(8-0), 23(8-0), 24(8-0), 25(8-0), 36//1(8-0), 2(8-0), 3(8-0), 4(8-
0), 5(8-0), 8(8-0), 9(8-0), 10(8-0), 37//20Min(4-0), 37//19(8-0), 21(8-0),
22(8-0) located in the revenue estate of village Vehran, Tehsil Nakodar, District
Jalandhar, Punjab subject to the conditions proposed at Annexure-A of the
proceedings in addition to the proposed measures.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Amarjit Singh, General Manager-cum-Mining officer, DIC, Jalandhar.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
79
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Jalandhar submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA.
Further, it was brought to the knowledge to the SEIAA that a
complaint of Munish Grover has been received through email
([email protected]) dated 27.04.2017. In the said complaint
Munish Gover & Co., Kot Ise Khan, Moga informed that his firm has contract of
the mining site located in the village Chhoula, Tehsil Nakodar, Distt. Jalandhar
for five years, which is upto 2021. The General Manager Cum-Mining officer,
Jalandhar & Ludhiana had applied SEIAA/SEAC for grant Environment
Clearance for three mining sites, out of which two sites falls in the village of
Vehran & Raipur Gujran, Tehsil Nakodar, Distt. Jalandhar and one falls in the
village Hujran, Tehsil Jagraon, Distt. Ludhiana. All three mining sites are
located within the 500 m radius of mining site Chhoula, Tehsil Nakodar. As per
the rules of SEIAA/SEAC, there will be no auction for the new mining site within
the radius of 1 KM from the old mining site. The boundaries of all three mining
sites are in touch with the boundary of the mining site, village Chhoula. He
requested that Environment Clearance to the said three sites not be granted,
so these three sites should not be auctioned.
In this regard, GMDIC, Jalandhar informed that the said
complaint has already been considered in 158th meeting of SEAC held on
27.04.2017 wherein an undertaking has also been submitted to the effect that
distance between mining site of Village Chhoula, Vehran, Raipur Gujran &
Hujran are more than 500 meter from each other and mining site Hujran falls
in the boundary of Distt. Ludhiana and remaining three mining sites falls in the
Distt. Jalandhar. He further stated that the said complaint is incorrect and
based on wrong facts as the site has been visited by himself and the distance
80
between the mining site mentioned in the complaint is more than 500 m from
the present site.
The SEIAA satisfied with the reply given by the GMDIC, Jalandhar
and also felt that the said complaint has already been considered while
appraising the case by the SEAC.
During discussions, General Manager-cum-Mining officer, DIC,
Jalandhar agreed to comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures.
Item No:122.18 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in the revenue estate of village Chak Budala, Tehsil Shahkot, District Jalandhar, Punjab of General Manager cum Mining Officer, District Industries Centre, Jalandhar. (Proposal no. SIA/PB/MIN/59433/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Jalandhar vide online application dated 24.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Sand) from the bed of river Satluj in the revenue
estate of village Chak Budala, Tehsil Shahkot, District Jalandhar, Punjab. The
project is covered under category 1 (a) of the Schedule appended to the said
notification. The project proponent submitted the Form-I, Pre-feasibility report,
DSR, Mining Plan ,EMP and other requisite documents.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Amarjit Singh, General Manager-cum-Mining officer, DIC, Jalandhar.
(ii) Sh. Sushminder Singh, State Geologist.
81
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 3,35,048 TPA of mining of minor minerals (Sand) will be carried
out in an area of 7.66 Hectare from the bed of river Satluj in the
revenue estate village Chak Budala, Tehsil Shahkot, District Jalandhar,
Punjab in H.B. no. 231 bearing Khasra nos 24//1, 2, 3, 4, 5, 6, 7, 8/1,
8/2, 9/1, 10, 11, 12, 13/3, 13/2, 14, 15, 16, 17, 18/1, 18/2, 19, 25//5,
6
2) Mining Officer, DIC, Jalandhar certified that no mining lease is granted
within 500 mtr periphery from the area of said mining lease.
3) NOC has been issued by the Department of Forest, Jalandhar vide letter
no. 4463 dated 23/08/2016 to the General Manager cum Mining Officer,
District Industries Centre, Jalandhar.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs 1,67,85,000 and the manpower
required will be 73 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 8.08 KLD out of
which 3.28 KLD will be used for domestic purpose and remaining 4.28
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 11 trucks/hr will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
82
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) Nominal Solid waste to be generated by the mining workers at the
mining site. Provisions of the dustbins will be made at mining site and
the waste will be collected on the regular basis to avoid their spillage.
Waste generated at the mine site by the workers will be disposed off as
per the Solid Waste Management Rules, 2016.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 7,32,500 will be incurred as total capital cost & Rs.
1,46,500 per annum as recurring cost for the implementation of the EMP
on the following activities: -
(i) Management of Haulage Roads including Sprinkling, Tractor
trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.).
(iii) Plantation.
(iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 3,35,700 will be spent for following activities under Corporate
Social Responsibility for the people residing in nearby villages: -
83
(i) Short awareness program will be conducted for labours prior to
mining.
(ii) Regular health check-up camps for the workers engaged in mines
shall be organized.
(iii) Local needs of habitants like school, crèche, hospital, veterinary
hospital, sanitation, drinking water etc. shall be considered positively.
(iv) Common vocational training centre shall be setup at district level.
The SEAC raised certain queries to which the project proponent submitted the reply, the details of which are as under: -
Sr. No.
Observations of SEAC Reply given by project proponent
1. As to whether mining site is a part of the active channel
General Manager, DIC, Jalandhar submitted an undertaking to the effect that he has visited the mining site on 23.04.2017 alongwith field staff and the mining site is situated in the riverbed of River Satluj but is not a part of active channel, which is taken on record by the SEAC.
2. As to whether land of the mining project involve private ownership land. If yes, whether consents of the concerned land owner(s) have been obtained for carried out the mining operation.
Project proponent informed that project does not involve private ownership land. The entire mining is to be carried out from the State Govt. land.
3. The project proponent has not submitted the copy of the Jamabandi for entire mining site.
The project proponent submitted the remaining copy of the jamabandi, which was earlier not submitted.
4. Khasra No.24//9/2 of the mining site is not matching with the application and the DSR.
The project proponent has corrected the application by adding khasra no.24// 9/2 in the application form and requested to grant Environment Clearance including the khasra no. 24//9/2. The quantity of mining of minor minerals (Sand) will remain same.
General Manager, DIC, Jalandhar requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
84
minerals (Sand) @ 3,35,048 TPA from the bed of river Satluj in total area of
7.66 Hectare having H.B. no. 231 bearing Khasra nos 24//1, 2, 3, 4, 5, 6, 7,
8/1, 8/2, 9/1, 9/2, 10, 11, 12, 13/3, 13/2, 14, 15, 16, 17, 18/1, 18/2, 19,
25//5, 6 located in the revenue estate of village Chak Budala, Tehsil Shahkot,
District Jalandhar, Punjab subject to the conditions proposed at Annexure-A of
the proceedings in addition to the proposed measures.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Amarjit Singh, General Manager-cum-Mining officer, DIC, Jalandhar.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Jalndhar submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA.
During discussions, General Manager-cum-Mining officer, DIC,
Jalandhar agreed to comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures.
85
Item No:122.19 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in the revenue estate of village Raipur Gujjran, Tehsil Nakodar, District Jalandhar, Punjab of General Manager cum Mining Officer, District Industries Centre, Jalandhar. (Proposal no. SIA/PB/MIN/59445/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Jalandhar vide online application dated 24.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Sand) from the bed of river Satluj in the revenue
estate of village Raipur Gujjran, Tehsil Nakodar, District Jalandhar, Punjab. The
project is covered under category 1 (a) of the Schedule appended to the said
notification. The project proponent submitted the Form-I, Pre-feasibility report,
DSR, Mining Plan,EMP and other requisite documents.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Amarjit Singh, General Manager-cum-Mining officer, DIC, Jalandhar.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 6,06,236 TPA of mining of minor minerals (Sand) will be carried
out in an area of 13.86 Hectare from the bed of river Satluj in the
revenue estate village Raipur Gujjran, Tehsil Nakodar, District Jalandhar,
Punjab in H.B. no. 342 bearing Khasra nos
41//1,2,3,4,5,6,7,8,9,10,11/2,12,13,37//11,12, 13,14,15, 16,17,
18,19,20,21,22,23,24,40//1,2,3,6,7/1,7/2,8/1,8/2,8/3,9,10
2) Mining Officer, DIC, Jalandhar certified that no mining lease is granted
within 500 mtr periphery from the area of said mining lease.
86
3) NOC has been issued by the Department of Forest, Jalandhar vide letter
no. 4463 dated 23/08/2016 to the General Manager cum Mining Officer,
District Industries Centre, Jalandhar.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 5,09,85,000 and the manpower
required will be 125 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 7.88 KLD out of
which 2.26 KLD will be used for domestic purpose and remaining 5.62
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 20 trucks/hr will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) Nominal Solid waste to be generated by the mining workers at the
mining site. Provisions of the dustbins will be made at mining site and
the waste will be collected on the regular basis to avoid their spillage.
Waste generated at the mine site by the workers will be disposed off as
per the Solid Waste Management Rules, 2016.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
87
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 8,62,500 will be incurred as total capital cost & Rs.
1,72,500 per annum as recurring cost for the implementation of the EMP
on the following activities: -
(i) Management of Haulage Roads including Sprinkling, Tractor
trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.).
(iii) Plantation.
(iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 2,67,200 will be spent for following activities under Corporate
Social Responsibility for the people residing in nearby villages: -
i. Short awareness program will be conducted for labours prior to mining.
ii. Regular health check-up camps for the workers engaged in mines shall
be organized.
iii. Local needs of habitants like school, crèche, hospital, veterinary
hospital, sanitation, drinking water etc. shall be considered positively.
iv. Common vocational training centre shall be setup at district level.
The SEAC raised certain queries to which the project proponent
submitted the reply, the details of which are as under: -
Sr.
No.
Observations of SEAC Reply given by project proponent
1. As to whether mining site is a
part of the active channel
General Manager, DIC, Jalandhar submitted
an undertaking to the effect that he has
visited the mining site on 23.04.2017
88
alongwith field staff and the mining site is
situated in the riverbed of River Satluj but
is not a part of active channel, which is
taken on record by the SEAC.
2. As to whether land of the mining
project involve private
ownership land. If yes, whether
consents of the concerned land
owner(s) have been obtained for
carried out the mining
operation.
Project proponent informed that project
does not involve private ownership land.
The entire mining is to be carried out from
the State Govt. land.
3. It was informed to the SEAC
that a complaint has been
received through email dated
27.04.2017 from
In the said complaint Munish
Gover & Co., Kot Ise Khan,
Moga informed that his firm has
contract of the mining site
located in the village Chhoula,
Tehsil Nakodar, Distt. Jalandhar
for five years, which is upto
2021. General Manager Cum-
Mining officer, Jalandhar &
Ludhiana has requested
SEIAA/SEAC to grant
Environment Clearance for the
three mining sites, out of which
two sites falls in the village of
village Vehra & Raipur Gujran ,
Tehsil Nakodar, Distt. Jalandhar,
and one is in the village Hujran,
General Manager, DIC, Jalandhar has
submitted a certificate to the effect that
distance between mining site of Village
Chhoula, Vehran, Raipur Gujran & Hujran
are more than 500 meter from each other
and mining site Hujran falls in the
boundary of Distt. Ludhiana and remaining
three mining sites falls in the Distt.
Jalandhar, which was taken on record by
the SEAC.
89
Tehsil Jagraon, Distt. Ludhiana.
All three mining sites are located
within the radius of mining site
Chhoula, Tehsil Nakodar. As per
the rules of SEIAA/SEAC,there
will be no auction for the new
mining site within the radius of 1
KM from the old mining site. The
boundary of all three mining
sites are in touch with the
boundary of the mining site,
village Chhoula. It is therefore,
requested that Environment
Clearance to the said three sites
not be granted, so these three
sites should not be auctioned. If
these three mining site be
granted Environment Clearance
then he will have only option to
take help of Hon’ble High Court,
Punjab & Haryana
General Manager, DIC, Jalandhar requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand) @ 6,06,236 TPA from the bed of river Satluj in total area of
13.86 Hectare having H.B. no. 342 bearing Khasra nos 41//1, 2, 3, 4, 5, 6, 7,
8, 9, 10, 11/2, 12, 13, 37//11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23,
24, 40//1, 2, 3, 6, 7/1, 7/2, 8/1, 8/2, 8/3, 9, 10 located in the revenue estate
of village Raipur Gujjran, Tehsil Nakodar, District Jalandhar, Punjab subject to
90
the conditions proposed at Annexure-A of the proceedings in addition to the
proposed measures.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Amarjit Singh, General Manager-cum-Mining officer, DIC, Jalandhar.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Jalandhar submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA.
Further, it was brought to the knowledge to the SEIAA that a
complaint of Munish Grover has been received through email
([email protected]) dated 27.04.2017. In the said complaint
Munish Gover & Co., Kot Ise Khan, Moga informed that his firm has contract of
the mining site located in the village Chhoula, Tehsil Nakodar, Distt. Jalandhar
for five years, which is upto 2021. The General Manager Cum-Mining officer,
Jalandhar & Ludhiana had applied SEIAA/SEAC for grant Environment
Clearance for three mining sites, out of which two sites falls in the village of
Vehran & Raipur Gujran, Tehsil Nakodar, Distt. Jalandhar and one falls in the
village Hujran, Tehsil Jagraon, Distt. Ludhiana. All three mining sites are
located within the 500 m radius of mining site Chhoula, Tehsil Nakodar. As per
the rules of SEIAA/SEAC, there will be no auction for the new mining site within
the radius of 1 KM from the old mining site. The boundaries of all three mining
sites are in touch with the boundary of the mining site, village Chhoula. He
requested that Environment Clearance to the said three sites not be granted,
so these three sites should not be auctioned.
91
In this regard, GMDIC, Jalandhar informed that the said
complaint has already been considered in 158th meeting of SEAC held on
27.04.2017 wherein an undertaking has also been submitted to the effect that
distance between mining site of Village Chhoula, Vehran, Raipur Gujran &
Hujran are more than 500 meter from each other and mining site Hujran falls
in the boundary of Distt. Ludhiana and remaining three mining sites falls in the
Distt. Jalandhar. He further stated that the said complaint is incorrect and
based on wrong facts as the site has been visited by himself and the distance
between the mining site mentioned in the complaint is more than 500 m from
the present site.
The SEIAA satisfied with the reply given by the GMDIC, Jalandhar
and also felt that the said complaint has already been considered while
appraising the case by the SEAC.
During discussions, General Manager-cum-Mining officer, DIC,
Jalandhar agreed to comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures..
Item No:122.20 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in the revenue estate of village Miyanwal, Tehsil Phillaur, District Jalandhar, Punjab of General Manager cum Mining Officer, District Industries Centre, Jalandhar. (Proposal no. SIA/PB/MIN/59471/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Jalandhar vide online application dated 24.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Sand) from the bed of river Satluj in the revenue
92
estate of village Miyanwal, Tehsil Phillaur, District Jalandhar, Punjab. The
project is covered under category 1 (a) of the Schedule appended to the said
notification. The project proponent submitted the Form-I, Pre-feasibility report,
DSR, Mining Plan,EMP and other requisite documents.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Amarjit Singh, General Manager-cum-Mining officer, DIC, Jalandhar.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 2,69,001 TPA of mining of minor minerals (Sand) will be carried
out in an area of 6.15 Hectare from the bed of river Satluj in the
revenue estate village Miyanwal, Tehsil Phillaur, District Jalandhar,
Punjab in H.B. no. 122 bearing Khasra nos 70//6, 7, 8, 71//10, 11,
94//4, 7, 14, 15/1, 62//25, 63//20/2, 21/1, 21/2, 70//4, 81//1/10/1,
84//18, 23, 24.
2) Mining Officer, DIC, Jalandhar certified that no mining lease is granted
within 500 mtr periphery from the area of said mining lease.
3) NOC has been issued by the Department of Forest, Jalandhar vide letter
no. 4463 dated 23/08/2016 to the General Manager cum Mining Officer,
District Industries Centre, Jalandhar.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 1,33,60,000 and the manpower
required will be 58 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
93
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 6.89 KLD out of
which 2.61 KLD will be used for domestic purpose and remaining 4.28
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 11 trucks/hr will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) Nominal Solid waste to be generated by the mining workers at the
mining site. Provisions of the dustbins will be made at mining site and
the waste will be collected on the regular basis to avoid their spillage.
Waste generated at the mine site by the workers will be disposed off as
per the Solid Waste Management Rules, 2016.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 6,45,000 will be incurred as total capital cost & Rs.
1,29,000 per annum as recurring cost for the implementation of the EMP
on the following activities: -
94
(i) Management of Haulage Roads including Sprinkling, Tractor
trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.).
(iii) Plantation.
(iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 2,67,200 will be spent for following activities under Corporate
Social Responsibility for the people residing in nearby villages: -
i. Short awareness program will be conducted for labours prior to mining.
ii. Regular health check-up camps for the workers engaged in mines shall be organized.
iii. Local needs of habitants like school, crèche, hospital, veterinary hospital, sanitation, drinking water etc. shall be considered positively.
iv. Common vocational training centre shall be setup at district level.
The SEAC raised certain queries to which the project proponent submitted the reply, the details of which are as under: -
Sr. No.
Observations of SEAC Reply given by project proponent
1. As to whether mining site is a part of the active channel
General Manager, DIC, Jalandhar submitted an undertaking to the effect that he has visited the mining site on 23.04.2017 alongwith field staff and the mining site is situated in the riverbed of River Satluj but is not a part of active channel, which is taken on record by the SEAC.
2. As to whether land of the mining project involve private ownership land. If yes, whether consents of the concerned land owner(s) have been obtained for carried out the mining operation.
Project proponent informed that the mining is also to be carried out from the private ownership land and consent has been obtained from the land owner. The project proponent submitted their consent for mining areas, which are taken on record by the SEAC.
General Manager, DIC, Jalandhar requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
95
minerals (Sand) @ 2,69,001 TPA from the bed of river Satluj in total area of
6.15 Hectare having H.B. no. 122 bearing Khasra nos 70//6, 7, 8, 71//10, 11,
94//4, 7, 14, 15/1, 62//25, 63//20/2, 21/1, 21/2, 70//4, 81//1/10/1, 84//18,
23, 24 located in the revenue estate of village Miyanwal, Tehsil Phillaur, District
Jalandhar, Punjab, subject to the conditions proposed at Annexure-A of the
proceedings in addition to the proposed measures.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Amarjit Singh, General Manager-cum-Mining officer, DIC, Jalandhar.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Jalandhar submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA.
During discussions, General Manager-cum-Mining officer, DIC,
Jalandhar agreed to comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures.
96
Item No:122.21 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in the revenue estate of village Thumuwal, Tehsil Shahkot, District Jalandhar, Punjab of General Manager cum Mining Officer, District Industries Centre, Jalandhar. (Proposal no. SIA/PB/MIN/59468/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Jalandhar vide online application dated 25.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Sand) from the bed of river Satluj in the revenue
estate of village Thumuwal, Tehsil Shahkot, District Jalandhar, Punjab. The
project is covered under category 1 (a) of the Schedule appended to the said
notification. The project proponent submitted the Form-I, Pre-feasibility report,
DSR, Mining Plan, EMP and other requisite documents
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Amarjit Singh, General Manager-cum-Mining officer, DIC, Jalandhar.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 4,11,156 TPA of mining of minor minerals (Sand) will be carried
out in an area of 9.40 Hectare from the bed of river Satluj in the
revenue estate village Thumuwal, Tehsil Shahkot, District Jalandhar,
Punjab in H.B. no. 278 bearing Khasra nos 25//12, 19, 25, 11, 18, 21,
22, 23, 20, 40//9, 10, 11, 12, 13, 14, 22, 23, 29//10, 11Min, 17, 13Min,
21, 25Min, 12Min, 30//14.
2) Mining Officer, DIC, Jalandhar certified that no mining lease is granted
within 500 mtr periphery from the area of said mining lease.
97
3) NOC has been issued by the Department of Forest, Jalandhar vide letter
no. 4463 dated 23/08/2016 to the General Manager cum Mining Officer,
District Industries Centre, Jalandhar.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 2,01,10,000 and the manpower
required will be 125 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 6.55 KLD out of
which 3.96 KLD will be used for domestic purpose and remaining 2.59
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 17 trucks/hr will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) Nominal Solid waste to be generated by the mining workers at the
mining site. Provisions of the dustbins will be made at mining site and
the waste will be collected on the regular basis to avoid their spillage.
Waste generated at the mine site by the workers will be disposed off as
per the Solid Waste Management Rules, 2016.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
98
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 7,20,000 will be incurred as total capital cost & Rs.
1,44,000 per annum as recurring cost for the implementation of the EMP
on the following activities: -
(i) Management of Haulage Roads including Sprinkling, Tractor
trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.).
(iii) Plantation.
(iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 2,67,200 will be spent for following activities under Corporate
Social Responsibility for the people residing in nearby villages: -
i. Short awareness program will be conducted for labours prior to mining.
ii. Regular health check-up camps for the workers engaged in mines shall be organized.
iii. Local needs of habitants like school, crèche, hospital, veterinary hospital, sanitation, drinking water etc. shall be considered positively.
iv. Common vocational training centre shall be setup at district level.
The SEAC raised certain queries to which the project proponent submitted the reply, the details of which are as under: -
Sr. No.
Observations of SEAC Reply given by project proponent
1. As to whether mining site is a part of the active channel
General Manager, DIC, Jalandhar submitted an undertaking to the effect that he has visited the mining site on 23.04.2017 alongwith field staff and the mining site is situated in the riverbed of River Satluj but is not a part of active channel, which is taken on record by the SEAC.
99
2. As to whether land of the mining project involve private ownership land. If yes, whether consents of the concerned land owner(s) have been obtained for carried out the mining operation.
Project proponent informed that the mining is also to be carried out from the private ownership land and consent has been obtained from the land owner. The project proponent submitted their consent for mining areas, which are taken on record by the SEAC.
General Manager, DIC, Jalandhar requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand) @ 4,11,156 TPA from the bed of river Satluj in total area of
9.40 Hectare having H.B. no. 278 bearing Khasra nos 25//12, 19, 25, 11, 18,
21, 22, 23, 20, 40//9, 10, 11, 12, 13, 14, 22, 23, 29//10, 11Min, 17, 13Min, 21,
25Min, 12Min, 30//14 located in the revenue estate of village Thumuwal, Tehsil
Shahkot, District Jalandhar, subject to the conditions proposed at Annexure-A
of the proceedings in addition to the proposed measures.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(iv) Sh. Sushminder Singh, State Geologist.
(v) Sh. Amarjit Singh, General Manager-cum-Mining officer, DIC, Jalandhar.
(vi) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Jalandhar submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA. The SEIAA also observed that distance between active channel and
100
river bundh is also required to be marked on the 'Aks Sajra'. Accordingly, the
project proponent marked same on 'Aks Sajra'.
During discussions, General Manager-cum-Mining officer, DIC,
Jalandhar agreed to comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures.
Item No:122.22 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in the revenue estate of village Maun Sahib, Tehsil Phillaur, District Jalandhar, Punjab of General Manager cum Mining Officer, District Industries Centre, Jalandhar. (Proposal no. SIA/PB/MIN/64180/2017)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Jalandhar vide online application dated 24.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Sand) from the bed of river Satluj in the revenue
estate of village Maun Sahib, Tehsil Phillaur, District Jalandhar, Punjab. The
project is covered under category 1 (a) of the Schedule appended to the said
notification. The project proponent submitted the Form-I, Pre-feasibility report,
DSR, Mining Plan ,EMP and other requisite documents.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Amarjit Singh, General Manager-cum-Mining officer, DIC, Jalandhar.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
101
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 7,87,320 TPA of mining of minor minerals (Sand) will be carried
out in an area of 18 Hectare from the bed of river Satluj in the revenue
village Maun Sahib, Tehsil Phillaur, District Jalandhar, Punjab in H.B. no.
111 bearing Khasra nos 3248, 49, 50, 51, 72, 73, 88, 89, 92, 93, 3213,
14, 45, 46, 47, 74, 85, 86, 95, 96, 3305, 3308, 3306, 3315, 3316, 3333,
3334, 3335, 3338, 3330, 3331, 3191, 3212, 87, 93, 94, 3307, 3309, 12,
13, 14, 40, 43, 44, 56.
2) Mining Officer, DIC, Jalandhar certified that no mining lease is granted
within 500 mtr periphery from the area of said mining lease.
3) NOC has been issued by the Department of Forest, Jalandhar vide letter
no. 4463 dated 23/08/2016 to the General Manager cum Mining Officer,
District Industries Centre, Jalandhar.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 8,05,50,000 and the manpower
required will be 198 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 10.42 KLD out of
which 5.98 KLD will be used for domestic purpose and remaining 4.44
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 16 trucks/hr will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
102
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) Nominal Solid waste to be generated by the mining workers at the
mining site. Provisions of the dustbins will be made at mining site and
the waste will be collected on the regular basis to avoid their spillage.
Waste generated at the mine site by the workers will be disposed off as
per the Solid Waste Management Rules, 2016.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 8,82,500 will be incurred as total capital cost & Rs.
1,76,500 per annum as recurring cost for the implementation of the EMP
on the following activities: -
(i) Management of Haulage Roads including Sprinkling, Tractor
trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.).
(iii) Plantation.
(iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 16,11,000 will be spent for following activities under
Corporate Social Responsibility for the people residing in nearby villages:
-
i. Short awareness program will be conducted for labours prior to mining.
ii. Regular health check-up camps for the workers engaged in mines shall be organized.
103
iii. Local needs of habitants like school, crèche, hospital, veterinary hospital, sanitation, drinking water etc. shall be considered positively.
iv. Common vocational training centre shall be setup at district level.
The SEAC raised certain queries to which the project proponent submitted the reply, the details of which are as under: -
Sr. No.
Observations of SEAC Reply given by project proponent
3. As to whether mining site is a part of the active channel
General Manager, DIC, Jalandhar submitted an undertaking to the effect that he has visited the mining site on 23.04.2017 alongwith field staff and the mining site is situated in the riverbed of River Satluj but is not a part of active channel, which is taken on record by the SEAC.
4. As to whether land of the mining project involve private ownership land. If yes, whether consents of the concerned land owner(s) have been obtained for carried out the mining operation.
Project proponent informed that the mining is also to be carried out from the private ownership land and consent has been obtained from the land owner. The project proponent submitted their consent for mining areas, which are taken on record by the SEAC.
General Manager, DIC, Jalandhar requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand) @ 7,87,320 TPA from the bed of river Satluj in total area of
18.00 Hectare having H.B. no. 111 bearing Khasra nos 3248, 49, 50, 51, 72,
73, 88, 89, 92, 93, 3213, 14, 45, 46, 47, 74, 85, 86, 95, 96, 3305, 3308, 3306,
3315, 3316, 3333, 3334, 3335, 3338, 3330, 3331, 3191, 3212, 87, 93, 94,
3307, 3309, 12, 13, 14, 40, 43, 44, 56 located in the revenue estate of village
Maun Sahib, Tehsil Phillaur, District Jalandhar, subject to the conditions
proposed at Annexure-A of the proceedings in addition to the proposed
measures.
104
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Amarjit Singh, General Manager-cum-Mining officer, DIC, Jalandhar.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Jalandhar submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA.
During discussions, General Manager-cum-Mining officer, DIC,
Jalandhar agreed to comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures.
Item No:122.23 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in the revenue estate of village Gorsian Khan Mohammad, Tehsil Jagraon, District Ludhiana, Punjab of General Manager cum Mining Officer, District Industries Centre, Ludhiana. (Proposal no. SIA/PB/MIN/60719/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Jalandhar vide online application dated 22.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
105
mining of minor minerals (Sand) from the bed of river Satluj in the revenue
estate of village Gorsian Khan Mohammad, Tehsil Jagraon, District Ludhiana,
Punjab. The project is covered under category 1 (a) of the Schedule appended
to the said notification. The project proponent submitted the Form-I, Pre-
feasibility report, DSR, Mining Plan ,EMP and other requisite documents.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 10,79,941 TPA of mining of minor minerals (Sand) will be carried
out in an area of 24.69 Hectare from the bed of river Satluj in the
revenue estate village Gorsian Khan Mohammad, Tehsil Jagraon, District
Ludhiana, Punjab in H.B. no. 19 bearing Khasra nos 7//9, 10, 11, 12min,
16, 20, 21, 8//6, 7, 11, 11/1, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22,
23, 24, 9//14, 15, 16, 17, 24, 25, 10//4, 5, 6, 7, 14, 15, 24, 11//3, 4, 5,
6, 7, 8, 9, 12, 13, 14, 16, 17, 18, 19, 21, 22, 23, 12//2, 6, 7, 9, 13//1, 2,
3, 4, 6, 7, 8.
2) Mining Officer, DIC, Ludhiana vide no. 252 dated 01.03.2016 certified
that proposed river bed mining site have no other mining site existing
within 500 mtr periphery of the said mining lease.
3) NOC has been issued by the Department of Forest, Ludhiana vide letter
no. 11280 dated 13/03/2015 to the General Manager cum Mining
Officer, District Industries Centre, Ludhiana with certain condition.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
106
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 9,82,80,000 and the manpower
required will be 182 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 9.63 KLD out of
which 8.19 KLD will be used for domestic purpose and remaining 1.44
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 22 trucks/hr will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) During Mining activities, no solid & hazardous waste will be generated.
The Municipal waste generation shall be disposed off as per the Solid
Waste Management Rules, 2016. Segregation of bio-degradable waste
and non-bio degradable wastes shall be done at site and disposed off
accordingly.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
107
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 10,05,000 will be incurred as total capital cost & Rs.
2,01,000 per annum as recurring cost for the implementation of the EMP
on the following activities:
(i) Management of Haulage Roads including Sprinkling, Tractor trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.). (iii) Plantation. (iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 19,65,600 will be spent for following activities under
Corporate Social Responsibility for the people residing in nearby villages:
(i) Toilets will be made in the nearby school. Items like desk, chair, storage bins & Almira, dari will be given to the nearby schools.
(ii) Organizing regular health check-up camps for the mine workers periodically to observe any contradictions due to exposure to dust and take corrective measures.
(iii) Medicines will be given in the nearby dispensaries. (iv) Common vocational training, awareness programme will be
organized in the nearby villages.
The SEAC raised certain queries to which the project proponent
submitted the reply, the details of which are as under: -
Sr. No.
Observations of SEAC Reply given by project proponent
1. As to whether mining site is a part of the active channel
General Manager, DIC, Ludhiana submitted an undertaking to the effect that he has visited the mining site on 17.04.2017 alongwith field staff and the mining site is situated in the riverbed of River Satluj but is not a part of active channel, which is taken on record by the SEAC.
2. As to whether land of the mining project involve private ownership land. If yes, whether consents of the concerned land owner(s) have been obtained for carried out the mining operation.
Project proponent informed that the mining is to be carried out from the private ownership land and consent has already been obtained from the land owner during the time of site appraisal. The project proponent submitted their consent for mining in areas to make their land fertile, which are taken on record by the SEAC.
108
General Manager, DIC, Ludhiana requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand) @ 10,79,941 TPA from the bed of river Satluj in total area of
24.69 Hectare having H.B. no. 19 bearing Khasra nos 7//9, 10, 11, 12min, 16,
20, 21, 8//6, 7, 11, 11/1, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24,
9//14, 15, 16, 17, 24, 25, 10//4, 5, 6, 7, 14, 15, 24, 11//3, 4, 5, 6, 7, 8, 9, 12,
13, 14, 16, 17, 18, 19, 21, 22, 23, 12//2, 6, 7, 9, 13//1, 2, 3, 4, 6, 7, 8 located
in the revenue estate of village Gorsian Khan Mohammad, Tehsil Jagraon,
District Ludhiana, Punjab, subject to the conditions proposed at Annexure-A of
the proceedings in addition to the proposed measures and specific condition
that project proponent shall comply with the condition imposed by DFO
Ludhiana while granting NOC vide no 11280 dated 13/03/2015.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Ludhiana submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA.
109
During discussions, General Manager-cum-Mining officer, DIC,
Luhiana agreed to comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures.
Item No:122.24 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in the revenue estate of village Kanian Hussaini, Tehsil Jagraon District Ludhiana, Punjab of General Manager cum Mining Officer, District Industries Centre, Ludhiana. (Proposal No. SIA/PB/MIN/64179/2017)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Ludhiana vide online application dated 24.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Sand) from the bed of river Satluj in the revenue
estate of village Kanian Hussaini, Tehsil Jagraon District Ludhiana, Punjab. The
project is covered under category 1 (a) of the Schedule appended to the said
notification. The project proponent submitted the Form-I, Pre-feasibility report,
DSR, Mining Plan ,EMP and other requisite documents.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
110
1) About 9,11,979 TPA of mining of minor minerals (Sand) will be carried
out in an area of 20.85 Hectare from the bed of river Satluj in the
revenue estate of village Kanian Hussaini, Tehsil Jagraon District
Ludhiana, Punjab in H.B. no. 180 bearing Khasra nos 39//6, 7, 8, 9, 10,
11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22min, 23min, 24min, 25,
40//6, 7, 8, 9, 10, 11, 12, 13, 14, 15min, 16, 17, 18, 19, 20, 21, 22, 23,
24, 25, 41//6, 7, 8, 13, 1, 4, 15, 16, 17, 18, 23, 24, 25.
2) Mining Officer, DIC, Ludhiana vide no. 906 dated 10.04.2015 certified
that proposed river bed mining site have no other mining site existing
within 500 mtr periphery of the said mining lease.
3) NOC has been issued by the Department of Forest, Ludhiana vide letter
no. 11280 dated 13/03/2015 to the General Manager cum Mining
Officer, District Industries Centre, Ludhiana with certain condition.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 6,39,45,000 and the manpower
required will be 157 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 8.57 KLD out of
which 7.06 KLD will be used for domestic purpose and remaining 1.51
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 18 trucks/hr will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
111
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) During Mining activities, no solid & hazardous waste will be generated.
The Municipal waste generation shall be disposed off as per the Solid
Waste Management Rules, 2016. Segregation of bio-degradable waste
and non-bio degradable wastes shall be done at site and disposed off
accordingly.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 94,25,000 will be incurred as total capital cost & Rs.
1,88,500 per annum as recurring cost for the implementation of the EMP
on the following activities:
(i) Management of Haulage Roads including Sprinkling, Tractor trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.). (iii) Plantation. (iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 12,78,900 will be spent for following activities under
Corporate Social Responsibility for the people residing in nearby villages:
-
(i) Toilets will be made in the nearby school. Items like desk, chair, storage bins & Almira, dari will be given to the nearby schools.
(ii) Organizing regular health check-up camps for the mine workers periodically to observe any contradictions due to exposure to dust
112
and take corrective measures. (iii) Medicines will be given in the nearby dispensaries. (iv) Common vocational training, awareness programme will be
organized in the nearby villages.
The SEAC raised certain queries to which the project proponent
submitted the reply, the details of which are as under: -
Sr. No.
Observations of SEAC Reply given by project proponent
1. As to whether mining site is a part of the active channel
General Manager, DIC, Ludhiana submitted an undertaking to the effect that he has visited the mining site on 17.04.2017 alongwith field staff and the mining site is situated in the riverbed of River Satluj but is not a part of active channel, which is taken on record by the SEAC.
2. As to whether land of the mining project involve private ownership land. If yes, whether consents of the concerned land owner(s) have been obtained for carried out the mining operation.
Project proponent informed that the mining is to be carried out from the private ownership land and consent has already been obtained from the land owner during the time of site appraisal. The project proponent submitted their consent for mining in areas to make their land fertile, which are taken on record by the SEAC.
3. As per the application total area of the khasra nos., area of the mining site is 20.5 hectare whereas in the DSR, area of the mining site is 20.5 acres (8.30 hectares). Thus, the project proponent is also required to clarify the same.
The project proponent submitted that area correction has been made in the DSR. A copy of the letter no.625 dated 18.04.2017 addressed to the Director Mining, Department of Industries, Punjab, Chandigarh, wherein, it has been mentioned that actual area is 20.85 hectare instead of 20.5 acre. A correction of the clerical mistake has been approved by Deputy Commissioner cum-Chairman, DEIAA Ludhiana, and it is requested that area of the mining site should be read as 20.85 hectare instead of 20.5 acre. The said letter was taken on record by the SEAC.
General Manager, DIC, Ludhiana requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
113
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand) @ 9,11,979 TPA from the bed of river Satluj in total area of
20.85 Hectare having H.B. no. 180 bearing Khasra nos 39//6, 7, 8, 9, 10, 11,
12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22min, 23min, 24min, 25, 40//6, 7, 8, 9,
10, 11, 12, 13, 14, 15min, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 41//6, 7, 8,
13, 14, 15, 16, 17, 18, 23, 24, 25 located in the revenue estate of village
Kanian Hussaini, Tehsil Jagraon District Ludhiana Punjab, subject to the
conditions proposed at Annexure-A of the proceedings in addition to the
proposed measures and specific condition that project proponent shall comply
with the condition imposed by DFO Ludhiana while granting NOC vide no
11280 dated 13/03/2015.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Ludhiana submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA.
During discussions, General Manager-cum-Mining officer, DIC,
Ludhiana agreed to comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
114
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures.
Item No:122.25 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in the revenue estate of village Hujra, Tehsil Jagraon District Ludhiana, Punjab of General Manager cum Mining Officer, District Industries Centre, Ludhiana. (Proposal No. SIA/PB/MIN/60734/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Ludhiana vide online application dated 25.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Sand) from the bed of river Satluj in the revenue
estate of village Hujra, Tehsil Jagraon District Ludhiana, Punjab. The project is
covered under category 1 (a) of the Schedule appended to the said
notification. The project proponent submitted the Form-I, Pre-feasibility report,
DSR, Mining Plan,EMP and other requisite documents
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 9,73,652 TPA of mining of minor minerals (Sand) will be carried
out in an area of 22.26 Hectare from the bed of river Satluj in the
revenue estate of village Hujra, Tehsil Jagraon District Ludhiana, Punjab
in H.B. no. 184 bearing Khasra nos 3//18/1, 19/2, 20, 21, 22/1, 22/2,
4//1, 9, 10, 11, 12, 13, 14, 15, 16, 17/1, 17/2, 18, 19, 20, 21/1, 25,
115
25/3, 5//13, 14, 15, 17, 18, 21, 22, 23, 24, 9//5, 6, 7, 8, 9, 10, 11, 12,
13, 14, 15, 16, 17, 18/1, 18/2, 19, 20, 21, 22, 10//1, 2, 3, 4, 5, 9, 10,
11/2, 12, 13, 14, 15, 16/1 17, 11//17, 18/1, 12//1/2, 3.
2) Mining Officer, DIC, Ludhiana vide no. 252 dated 01.03.2016 certified
that proposed river bed mining site have no other mining site existing
within 500 mtr periphery of the said mining lease.
3) NOC has been issued by the Department of Forest, Ludhiana vide letter
no. 11280 dated 13/03/2015 to the General Manager cum Mining
Officer, District Industries Centre, Ludhiana with certain condition.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 6,71,85,000 and the manpower
required will be 141 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 10.54 KLD out of
which 7.42 KLD will be used for domestic purpose and remaining 3.12
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 17 trucks/hr will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) During Mining activities, no solid & hazardous waste will be generated.
The Municipal waste generation shall be disposed off as per the Solid
Waste Management Rules, 2016. Segregation of bio-degradable waste
116
and non-bio degradable wastes shall be done at site and disposed off
accordingly.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 9,62,500 will be incurred as total capital cost & Rs.
1,92,500 per annum as recurring cost for the implementation of the EMP
on the following activities: -
(i) Management of Haulage Roads including Sprinkling, Tractor trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.). (iii) Plantation. (iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 13,43,700 will be spent for following activities under
Corporate Social Responsibility for the people residing in nearby villages:
-
(i) Toilets will be made in the nearby school. Items like desk, chair, storage bins & Almira, dari will be given to the nearby schools.
(ii) Organizing regular health check-up camps for the mine workers periodically to observe any contradictions due to exposure to dust and take corrective measures.
(iii) Medicines will be given in the nearby dispensaries. (iv) Common vocational training, awareness programme will be
organized in the nearby villages.
The SEAC raised certain queries to which the project proponent
submitted the reply, the details of which are as under: -
117
Sr. No.
Observations of SEAC Reply given by project proponent
1. As to whether mining site is a part of the active channel
General Manager, DIC, Ludhiana submitted an undertaking to the effect that he has visited the mining site on 19.04.2017 alongwith field staff and the mining site is situated in the riverbed of River Satluj but is not a part of active channel, which is taken on record by the SEAC.
2. As to whether land of the mining project involve private ownership land. If yes, whether consents of the concerned land owner(s) have been obtained for carried out the mining operation.
Project proponent informed that the mining is to be carried out from the private ownership land and consent has already been obtained from the land owner during the time of site appraisal. The project proponent submitted their consent for mining in areas to make their land fertile, which are taken on record by the SEAC.
3. It was informed to the SEAC that a complaint has been received through email dated 27.04.2017 from [email protected]. In the said complaint Munish Gover & Co., Kot Ise Khan, Moga informed that his firm has contract of the mining site located in the village Chhoula, Tehsil Nakodar, Distt. Jalandhar for five years, which is upto 2021. General Manager Cum-Mining officer, Jalandhar & Ludhiana has requested SEIAA/SEAC to grant Environment Clearance for the three mining sites, out of which two sites falls in the village of village Vehra & Raipur Gujran , Tehsil Nakodar, Distt. Jalandhar, and one is in the village Hujran, Tehsil Jagraon, Distt. Ludhiana. All three mining sites are located within the radius of mining site Chhoula, Tehsil Nakodar. As per the rules of SEIAA/SEAC, there will be no auction for the new mining site within the radius of 1 KM from the old mining site. The boundary of all three mining sites are in touch with the boundary of the mining site, village Chhoula. It is therefore, requested that Environment Clearance to the said three sites not
General Manager, DIC, Jalandhar has submitted a certificate to the effect that distance between mining site of Village Chhoula, Vehran, Raipur Gujran & Hujran are more than 500 meter from each other and mining site Hujran falls in the boundary of Distt. Ludhiana and remaining three mining sites falls in the Distt. Jalandhar, which was taken on record by the SEAC. Further, the General Manager, DIC, Ludhiana has submitted a certificate to the effect that distance between mining site of Village Chhoula and mining site of village Hujran are more than 500 meter from each other, which was also taken on record by SEAC.
118
be granted, so these three sites should not be auctioned. If these three mining site be granted Environment Clearance then he will have only option to take help of Hon’ble High Court, Punjab & Haryana
General Manager, DIC, Ludhiana requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand) @ 9,73,652 MT from the bed of river Satluj in total area of
22.26 Hectare having H.B. no. 184 bearing Khasra nos 3//18/1, 19/2, 20, 21,
22/1, 22/2, 4//1, 9, 10, 11, 12, 13, 14, 15, 16, 17/1, 17/2, 18, 19, 20, 21/1,
25, 25/3, 5//13, 14, 15, 17, 18, 21, 22, 23, 24, 9//5, 6, 7, 8, 9, 10, 11, 12, 13,
14, 15, 16, 17, 18/1, 18/2, 19, 20, 21, 22, 10//1, 2, 3, 4, 5, 9, 10, 11/2, 12, 13,
14, 15, 16/1 17, 11//17, 18/1, 12//1/2, 3 located in the revenue estate of
village Hujra, Tehsil Jagraon District Ludhiana, Punjab, subject to the
conditions proposed at Annexure-A of the proceedings in addition to the
proposed measures and specific condition that project proponent shall comply
with the condition imposed by DFO Ludhiana while granting NOC vide no
11280 dated 13/03/2015.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
119
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Ludhiana submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA.
Further, it was brought to the knowledge to the SEIAA that a
complaint of Munish Grover has been received through email
([email protected]) dated 27.04.2017. In the said complaint
Munish Gover & Co., Kot Ise Khan, Moga informed that his firm has contract of
the mining site located in the village Chhoula, Tehsil Nakodar, Distt. Jalandhar
for five years, which is upto 2021. The General Manager Cum-Mining officer,
Jalandhar & Ludhiana had applied SEIAA/SEAC for grant Environment
Clearance for three mining sites, out of which two sites falls in the village of
Vehran & Raipur Gujran, Tehsil Nakodar, Distt. Jalandhar and one falls in the
village Hujran, Tehsil Jagraon, Distt. Ludhiana. All three mining sites are
located within the 500 m radius of mining site Chhoula, Tehsil Nakodar. As per
the rules of SEIAA/SEAC, there will be no auction for the new mining site within
the radius of 1 KM from the old mining site. The boundaries of all three mining
sites are in touch with the boundary of the mining site, village Chhoula. He
requested that Environment Clearance to the said three sites not be granted,
so these three sites should not be auctioned.
In this regard, GMDIC, Ludhiana informed that the said complaint
has already been considered in 158th meeting of SEAC held on 27.04.2017
wherein a certificate has also been submitted to the effect that distance
between mining site of Village Chhoula and mining site of village Hujran are
more than 500 meter from each other. Further, the General Manager, DIC,
Jalandhar has also submitted a certificate to the effect that distance between
mining site of Village Chhoula, Vehran, Raipur Gujran & Hujran are more than
500 meter from each other and mining site Hujran falls in the boundary of
120
Distt. Ludhiana and remaining three mining sites falls in the Distt. Jalandhar,
which was taken on record by the SEAC.
He further stated that the said complaint is incorrect and based
on wrong facts and also submitted a report dated 01.05.2017 obtained from
the Kanungo of the area, wherein it has been mentioned that the distance of
outskirt of Village Chhoule is more than 3960 ft from the outskirt of Village
Hujra, which was taken on record by the SEIAA. Thus, the distance between
the mining site mentioned in the complaint, is more than 500 m from the
present site.
The SEIAA satisfied with the reply given by the GMDIC, Ludhiana
and also felt that the said complaint has already been considered while
appraising the case by the SEAC.
During discussions, General Manager-cum-Mining officer, DIC,
Ludhiana agreed to comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures.
Item No:122.26 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in the revenue estate of Village Lubangarh, Tehsil Machhiwra, District Ludhiana, Punjab of General Manager cum Mining Officer, District Industries Centre, Ludhiana. (Proposal No. SIA/PB/MIN/58846/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Ludhiana vide online application dated 17.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Sand) from the bed of river Satluj in the revenue
estate of Village Lubangarh, Tehsil Machhiwra, District Ludhiana, Punjab. The
project is covered under category 1 (a) of the Schedule appended to the said
notification. The project proponent submitted the Form-I, Pre-feasibility report,
DSR, Mining Plan ,EMP and other requisite documents.
121
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 2,96,120 MT of mining of minor minerals (Sand) will be carried
out in an area of 6.77 Hectare from the bed of river Satluj in the
revenue estate of Village Lubangarh, Tehsil Machhiwra, District
Ludhiana, Punjab in H.B. no. 461 bearing Khasra nos 1//16(4-8),24(9-
13),25(8-0),2//21(4-2),4//1(7-3),2(2-13),9(9-8),10(8-0),11/1(2-
9),5//4(5-8),5(6-8),6(7-4),7(4-4),8/2(4-6),12(6-19),13(8-0),14(8-
0),15(8-0),16/1(6-13),17(9-4),18(3-13).
2) Mining Officer, DIC, Ludhiana certified that proposed river bed mining
site have no other mining site existing within 500 mtr periphery of the
said mining lease.
3) NOC has been issued by the Department of Forest, Ludhiana vide letter
no. 11280 dated 13/03/2015 to the General Manager cum Mining
Officer, District Industries Centre, Ludhiana with certain condition.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 1,57,00,000 and the manpower
required will be 68 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
122
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 3.7 KLD out of
which 3.06 KLD will be used for domestic purpose and remaining 0.64
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 6 trucks/hr will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) During Mining activities, no solid & hazardous waste will be generated.
The Municipal waste generation shall be disposed off as per the Solid
Waste Management Rules, 2016. Segregation of bio-degradable waste
and non-bio degradable wastes shall be done at site and disposed off
accordingly.
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 7,20,000 will be incurred as total capital cost & Rs.
1,44,000 per annum as recurring cost for the implementation of the EMP
on the following activities: -
123
(i) Management of Haulage Roads including Sprinkling, Tractor trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.). (iii) Plantation. (iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 3,14,000 will be spent for following activities under Corporate
Social Responsibility for the people residing in nearby villages: -
(i) Toilets will be made in the nearby school. Items like desk, chair, storage bins & Almira, dari will be given to the nearby schools.
(ii) Organizing regular health check-up camps for the mine workers periodically to observe any contradictions due to exposure to dust and take corrective measures.
(iii) Medicines will be given in the nearby dispensaries. (iv) Common vocational training, awareness programme will be
organized in the nearby villages.
The SEAC raised certain queries to which the project proponent
submitted the reply, the details of which are as under: -
Sr. No.
Observations of SEAC Reply given by project proponent
1. As to whether mining site is a part of the active channel
General Manager, DIC, Ludhiana submitted an undertaking to the effect that he has visited the mining site on 18.04.2017 alongwith field staff and the mining site is situated in the riverbed of River Satluj but is not a part of active channel, which is taken on record by the SEAC.
2. As to whether land of the mining project involve private ownership land. If yes, whether consents of the concerned land owner(s) have been obtained for carried out the mining operation.
Project proponent informed that the mining is to be carried out from the private ownership land and consent has already been obtained from the land owner during the time of site appraisal. The project proponent submitted their consent for mining in areas to make their land fertile, which are taken on record by the SEAC.
General Manager, DIC, Ludhiana requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
124
Clearance to the project promoter for carrying out for mining of minor
minerals (Sand) 2,96,120 MT from the bed of river Satluj in total area of 6.77
Hectare having H.B. no. 461 bearing Khasra nos 1//16(4-8), 24(9-13), 25(8-0),
2//21(4-2), 4//1(7-3), 2(2-13), 9(9-8), 10(8-0), 11/1(2-9), 5//4(5-8), 5(6-8),
6(7-4), 7(4-4), 8/2(4-6), 12(6-19), 13(8-0), 14(8-0), 15(8-0), 16/1(6-13), 17(9-
4), 18(3-13) located in the revenue estate of Village Lubangarh, Tehsil
Machhiwara, District Ludhiana, Punjab, subject to the conditions proposed at
Annexure-A of the proceedings in addition to the proposed measures and
specific condition that project proponent shall comply with the condition
imposed by DFO Ludhiana while granting NOC vide no 11280 dated
13/03/2015.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Mahesh Khanna, General Manager-cum-Mining officer, DIC,
Ludhiana.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, Ludhiana submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA.
During discussions, General Manager-cum-Mining officer, DIC,
Ludhiana agreed to comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
125
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures.
Item No:122.27 Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Gravel) from the bed of river Beas in the revenue estate of village Tagar Kalan, Tehsil Mukerian District Hoshiarpur, Punjab of General Manager cum Mining Officer, District Industries Centre, Hoshiarpur. (Proposal No. SIA/PB/MIN/59627/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Ludhiana vide online application dated 19.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Gravel) from the bed of river Beas in the revenue
estate of village Tagar Kalan, Tehsil Mukerian District Hoshiarpur, Punjab. The
project is covered under category 1 (a) of the Schedule appended to the said
notification. The project proponent submitted the Form-I, Pre-feasibility report,
DSR, Mining Plan ,EMP and other requisite documents.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Arun Kumar, General Manager-cum-Mining officer, DIC, Hoshiarpur.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd.,
Environmental consultant of the project proponent.
The Environmental Consultant presented the details of the project
proposal before the SEAC as under:
1) About 7,30,458 TPA of mining of minor minerals (Gravel) will be carried
out in an area of 13.36 Hectare from the bed of river Beas in the
revenue estate of village Tagar Kalan, Tehsil Mukerian District
Hoshiarpur, Punjab in H.B. no. 431 bearing Khasra nos 8//18(8-0), 19(8-
0), 20(8-0), 21(8-0), 22(8-0), 23(8-0), 17//1(8-0), 2(8-0), 3(8-0), 9(8-
0), 10(8-0), 11(8-0), 12(8-0), 19(8-0), 20(8-0), 22//1(8-0), 2(8-0, 9(8-
126
0), 10(8-0), 11(8-0), 12(8-0), 20(8-0), 21(8-0), 35//4(8-0), 5(8-0), 6(8-
0), 7(8-0), 14(8-0), 15(8-0), 16(8-0), 17(8-0), 24(8-0), 25(8-0).
2) Mining Officer, DIC, Hoshiarpur certified that no mining lease is granted
within 500 mtr periphery from the area of said mining lease.
3) NOC has been issued by the Department of Forest, Ludhiana vide letter
no. 988 dated 12/06/2015 to the Mining Officer, District Industries
Centre, Hoshiarpur with certain condition.
4) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first, using hand tools like shovel,
pan, sieve etc only during the day time.
5) No Mining activity will be carried out during monsoon season and at the
time of floods.
6) The total cost of project will be Rs. 1,66,80,000 and the manpower
required will be 72 nos.
7) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
8) Total amount of water required for the project will be 5.1 KLD out of
which 3.24 KLD will be used for domestic purpose and remaining 1.86
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
9) 20 trucks/hr will be plying during the working hours due to the mining
activities. Movement of the vehicle will be restricted during the peak
hour of the work. Only pollution check certificate vehicles will be used
for transportation purpose. For the transportation of minerals densely
populated areas, villages will be avoided & an alternate route will be
followed for evacuation purpose.
10) During Mining activities, no solid & hazardous waste will be generated.
The Municipal waste generation shall be disposed off as per the Solid
Waste Management Rules, 2016. Segregation of bio-degradable waste
and non-bio degradable wastes shall be done at site and disposed off
accordingly.
127
11) Plantation will be raised along both side of roads civic amenities in
consultation with the local authorities.
12) Adequate occupational health & safety measures shall be provided to
the workers.
13) Top soil generated as overburden will be used for the development of
green belt. Water sprinkling will be done on the roads regularly. Care
will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if material in dry form.
14) Mitigation measures such as regular maintenance of machinery,
minimum use of horns at the village area and plantation of the trees
along the bank will be done to maintain the noise level within the
prescribe limits.
15) Project proponent shall be responsible for the implementation of the
EMP and Rs. 8,50,000 will be incurred as total capital cost & Rs.
1,70,000 per annum as recurring cost for the implementation of the EMP
on the following activities: -
(i) Management of Haulage Roads including Sprinkling, Tractor trolley with sprinkler for the Protection of Environment.
(ii) Environmental Monitoring (Air, Water Soil etc.). (iii) Plantation. (iv) Occupational Health measure such as first aid and other
miscellaneous.
16) About Rs. 3,35,700 will be spent for following activities under Corporate
Social Responsibility for the people residing in nearby villages: -
(i) Toilets will be made in the nearby school. Items like desk, chair, storage bins & Almira, dari will be given to the nearby schools.
(ii) Organizing regular health check-up camps for the mine workers periodically to observe any contradictions due to exposure to dust and take corrective measures.
(iii) Medicines will be given in the nearby dispensaries. (iv) Common vocational training, awareness programme will be
organized in the nearby villages.
The SEAC raised certain queries to which the project proponent
submitted the reply, the details of which are as under: -
Sr. No.
Observations of SEAC Reply given by project proponent
1. As to whether mining site is a part of the active channel
General Manager, DIC, Hoshiarpur submitted an undertaking to the effect
128
that he has visited the mining site on 17.04.2017 alongwith field staff and the mining site is situated in the riverbed of River Beas but is not a part of active channel, which is taken on record by the SEAC.
2. As to whether land of the mining project involve private ownership land. If yes, whether consents of the concerned land owner(s) have been obtained for carried out the mining operation.
Project proponent informed that project does not involve private ownership land. The entire mining is to be carried out from the Panchayat land.
3. The project proponent has not submitted the Joint Inspection Report along with the application.
The project proponent submitted the Joint Inspection Report, which was taken on record by the SEAC.
General Manager, DIC, Hoshiarpur requested to recommend the
case to SEIAA for grant of environmental clearance to the project.
After detailed deliberations, the Committee observed that the
project proponent has provided adequate and satisfactory clarifications to the
observations raised by it. Therefore, the Committee decided that the case be
forwarded to the SEIAA with the recommendation to grant Environmental
Clearance to the project promoter for carrying out for mining of minor
minerals (Gravel) @ 7,30,458 TPA from the bed of river Beas in total area of
13.36 Hectare having H.B. no. 431 bearing Khasra nos 8//18(8-0), 19(8-0),
20(8-0), 21(8-0), 22(8-0), 23(8-0), 17//1(8-0), 2(8-0), 3(8-0), 9(8-0), 10(8-0),
11(8-0), 12(8-0), 19(8-0), 20(8-0), 22//1(8-0), 2(8-0, 9(8-0), 10(8-0), 11(8-0),
12(8-0), 20(8-0), 21(8-0), 35//4(8-0), 5(8-0), 6(8-0), 7(8-0), 14(8-0), 15(8-0),
16(8-0), 17(8-0), 24(8-0), 25(8-0). located in the revenue estate of village
Tagar Kalan, Tehsil Mukerian District Hoshiarpur Punjab, subject to the
conditions proposed at Annexure-A of the proceedings in addition to the
proposed measures.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Smt. Harjot Kaur, Mining officer, DIC, Hoshiarpur.
129
(iii) Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management Ltd., Environmental consultant of the project proponent.
Environmental Consultant of the project proponent presented the
salient features of the project before the SEIAA. The project proponent
submitted the signed copy of the presentation, which was taken on record by
the SEIAA.
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the Mining Officer, Hoshiarpur submitted a copy of
'Aks Sajra' on which haulage road has been marked, which was taken on
record by SEIAA.
During discussions, Mining officer, DIC, Hoshiarpur agreed to
comply with fully all the conditions as mentioned by SEAC.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC and grant environmental clearance to the project, subject to the
conditions as proposed by the SEAC in addition to the proposed measures.
Item No. 122.28: Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in the revenue estate of Village- Arzidarya Bramad Pragpur, Tehsil- Balachaur, District- SBS Nagar, Punjab of General Manager cum Mining Officer, District Industries Centre, SBS Nagar.(Proposal No. SIA/PB/MIN/52891/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Ludhiana vide online application dated 25.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Sand) from the bed of river Satluj in the revenue
estate of Village- Arzidarya Bramad Pragpur, Tehsil- Balachaur, District- SBS
Nagar, Punjab. The project is covered under category 1 (a) of the Schedule
appended to the said notification. The details of the project are as under:
130
1) About 1,27,880 TPA of mining of minor minerals (Sand) will be carried out
in an area of 11.376 Hectare from the bed of river Satluj in the revenue
estate of Village- Arzidarya Bramad Pragpur, Tehsil- Balachaur, District- SBS
Nagar in H.B. no. 437 bearing Khasra nos 21 min, 100/22 min, 101/23 min,
106/24 min
2) The project is an open-cast mining project, confined to excavation of Sand
from the proposed site. In the operation phase Sand will be excavated
semi-mechanically with the help of JCB and Poclain. These will be loaded
directly into trucks and transported to local markets.
3) The minerals will be collected in its existing form. Excavation will be carried
out only up to a depth of 3 m (Maximum) below ground level or above
water level, whichever is less. Excavation of Sand material will be done only
during the day time and completely stopped during the monsoon season.
4) Total amount of water required for the project will be 5.46 KLD out of
which 1.44 KLD will be used for domestic purpose, 3.3 KLD for Green belt
development and remaining 0.72 KLD for dust suppression. Water will be
supplied through private tankers from nearby available source.
5) The total cost of project will be Rs. 9,00,000.
6) All the activities will be carried out in a Semi-Mechanically. The material will
be excavated and loaded directly into tractors. The operation will be done
only from sun rise to sun set. 01 nos. Rounded off JCB machines is required
/day for loading Tippers to destination.
7) Approx. 2500 trees are to be planted within 5 years of the Plan Period. It is
proposed to plant local trees along the haul road and the available place
with consultation with concern Local authority or Gram Panchayat.
8) Insignificant amount of Domestic solid waste will be generated from the
proposed project. 1,27,880 tonnes of top soil will generated. The soil
covering the sand horizon commands good demand and may be distribute
to neighborhood farmers free of cost. The top soil cover should not be
wasted and disposed off anywhere else.
9) Liquid effluent will be generated and managed through Portable Bio-Toilet
shall be provided for the workers at the site. The sewage generated from
the toilet provided for the mine workers shall be collected and treated by
131
the inbuilt process of DRDO patented Bio technology using specially
cultured anaerobic bacteria.
10) The project proponent has submitted the following documents along with
Form-I:
(i) Pre- feasibility report
(ii) EMP
(iii) Mining Plan
(iv) Land Documents (Jamabandi)
(v) Surface Plan of Proposed Project.
(vi) 1 Km & 10 Km Buffer google map showing the sand mining site.
(vii) Location Plan on Latha Map.
(viii) Haul Road Map
(ix) Contour Map
(x) DFO Letter
(xi) Site Photographs
(xii) Undertaking
(xiii) Consent of Farmer
(xiv) Commissioner Certificate for land excavation
(xv) DSR, SBS Nagar
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Gurdev S. Mahal, General Manager-cum-Mining officer, DIC, SBS
Nagar.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. Rajesh Yadav, M/s Ascenso Enviro Private Ltd., Environmental
consultant of the project proponent.
Before allowing the presentation, SEAC observed that the project
is an open-cast mining project, confined to excavation of Sand from the
proposed site. In the operation phase Sand will be excavated semi-
mechanically with the help of JCB and Poclain and it will be loaded directly into
trucks and transported to local markets, which is not allowed
132
General Manager, DIC, SBS Nagar requested for allowing him to
withdraw his application for sand mining so as to submit fresh application after
considering the observation of the SEAC.
After discussions, the SEAC decided to forward the case to the
SEIAA with the recommendation to allow the applicant to withdraw his
application.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Gurdev S. Mahal, General Manager-cum-Mining officer, DIC, SBS
Nagar.
General Manager-cum-Mining officer, DIC, SBS Nagar requested
for allowing him to withdraw his application for sand mining as fresh
application has been submitted online
After detailed deliberations, the SEIAA decided to accept the
recommendation of SEAC and take the action as proposed by the SEAC.
Item No.122.29 Application for issuance of TOR under EIA notification dated 14.09.2006 for mining of minor minerals (sand) from River bed of Satluj in the revenue estate of Village- Arazi Darya Bramad Bela Tajowal, Tehsil- Balachaur, District- SBS Nagar, Punjab of General Manager cum Mining Officer, District Industries Centre, SBS Nagar. (Proposal no. SIA/PB/MIN/19185 /2017).
The SEIAA observed that: The General Manager cum Mining Officer, District Industries
Centre, SBS Nagar vide online application dated 18.04.2017, has applied for
issuance of TOR under EIA notification dated 14.09.2006 for mining of minor
minerals(sand) from river bed of Satluj in the revenue estate of Village- Arazi
Darya Bramad Bela Tajowal, Tehsil- Balachaur, District- SBS Nagar. The project
is covered under category 1 (a) of the Schedule appended to the said
notification. The project proponent has submitted the Form–I, Brief Summary
of the Project, Proposed TORs, Pre- feasibility report, Land Documents
(Jamabandi), 10 K.M. radius Topographic Map of Proposed Project, 1 Km
google map showing the sand mining site, Location Plan on Latha Map, Haul
133
Road Map, Contour Map, DFO Letter, Site Photographs, Undertaking, Consent
of Farmer, Commissioner Certificate for land excavation.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Gurdev S. Mahal, General Manager-cum-Mining officer, DIC, SBS
Nagar.
(ii) Sh. Sushminder Singh, State Geologist.
(iii) Sh. Rajesh Yadav, M/s Ascenso Enviro Private Ltd., Environmental
consultant of the project proponent.
Environmental Consultant, presented the case before the SEAC as
under:
1) About 205500 Tonnes Annually of mining of minor minerals(Sand) will
be carried out in an area 38.935 Ha from the river bed of Satluj in the
revenue estate of Village- Arazi Darya Bramad Bela Tajowal, Tehsil-
Balachaur, District- SBS Nagar in H.B. no. 421, bearing Khasra no /
Murba No. 18, 19, 20, 40, 41, 42, 44, 48, 49; Killa No.-11, 20, 21, 11,
12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 12/1, 12/2, 13,
14/1, 14/2, 16, 17, 18/8/2, 19, 23, 24, 25, 6/1, 6/2, 13/2, 13/3, 14,
15/1, 15/2, 16, 17, 18/1, 18/2, 19/1, 19/2, 21, 22, 23, 24/1, 24/2, 25/1,
25/2, 1, 2, 3/1, 3/2, 4, 5, 6, 7, 8, 9, 10/2, 11/2, 11/2, 12/1, 12/2, 13,
14, 15, 16, 17/1, 17/2, 18, 19, 20/2, 21, 22, 23, 24, 25, 1, 2, 3, 4, 5, 6,
7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 1, 1, 2, 3,
4, 5, ½, 2, 3/2, 4, 5, 6, 7, 8, 9, 12, 13, 14, 15
2) The entire mining lease area being part of river bed, there is no
vegetation in the lease area. Hence, there would be no clearance of
existing land, vegetation and buildings.
3) The mining activity will be confined to the lease area i.e. from the dry
bed of River Satluj, so no new land use will be created. Excavation will
be carried out only up to a depth of 3 m (Maximum) below ground level
or above water level, whichever is less. Excavation of Sand material will
be done only during the day time and completely stopped during the
monsoon season.
134
4) The work relates to only excavation of sand (River Bed Material) from
dry bed of the river during non-monsoon season. No construction work
is required for the proposed activity.
5) The proposed project is of open cast Sand (RBM) mining. There will not
be any underground mining or tunneling.
6) The minerals excavated during mining process will be replenished
naturally during the subsequent rainy seasons. Hence no reclamation
works are proposed.
7) Sand excavated will be loaded directly into trucks for transportation.
Hence no storage facility will be required.
8) The project is an open-cast mining project, confined to excavation of
Sand from the proposed site. In the operation phase Sand will be
excavated semi-mechanically with the help of JCB and Poclain. These
will be loaded directly into trucks and transported to local markets
9) Insignificant amount of Domestic solid waste will be generated from the
proposed project. 287525 tonnes of top soil will generated. The soil
covering the sand horizon commands good demand and may be
distribute to neighborhood farmers free of cost. The top soil cover
should not be wasted and disposed off anywhere else
10) Liquid effluent will be generated and managed through Portable Bio-
Toilet shall be provided for the workers at the site. The sewage
generated from the toilet provided for the mine workers shall be
collected and treated by the inbuilt process of DRDO patented Bio
technology using specially cultured anaerobic bacteria.
11) No new road, rail will be proposed. Only exiting transport network will
be used. There will be an increase in traffic because of movement of few
trucks for transportation of minerals
12) Total amount of water required for the project will be 3.5 KLD out of
which 0.67 KLD will be used for domestic purpose, 2.1 KLD for Green
belt development and remaining 0.66 KLD for dust suppression. Water
will be supplied through private tankers from nearby available source.
13) This project operation will not involve use of any materials hazardous to
human health or environment. Mining activity will be done semi-
135
mechanically by using JCB & Poclain. No hazardous and toxic material
will be used or to be generated during operational phase.
14) Proposed mining is for sand from inactive channel of riverbed. There is a
cover of approximately 50 cm thick of soil/overburden. The soil covering
the sand horizon commands good demand because of enriched soil
nutrients and may be distributed to villagers free of cost
15) No Municipal solid waste is expected to be generated.
16) Portable Bio-Toilet shall be provided for the workers at the site. The
sewage generated from the toilet provided for the mine workers shall be
collected and treated by the inbuilt process of DRDO patented Bio
technology using especially cultured anaerobic bacteria.
17) The emission will be due to operation of JCB/Poclain machine and by
movement of vehicles used in transportation (vehicular exhaust) which
will be minimized by using only PUC vehicles and Bharat-IV stage
vehicles in related to the project.
18) Some dust is likely to be emitted during transportation of minerals i.e.
dust, vehicular exhaust anticipated during loading, unloading of
excavated material. However adequate measures will be taken to
suppress the dust and preventing it to become airborne.
19) Blasting and piling is not proposed for the proposed project.
20) Mining will be carried during day time and in open area. Thus there is no
need for lighting and cooling systems.
21) No discharge of sewage or other effluents will be generated.
22) No hazardous substance will be used or produced during the proposed
mining operations.
23) The proposed activity will be undertaken by the Department of
Industries & Commerce, Punjab and the General Manager-cum-Mining
Officer will be Incharge of the Mining site. The project proponent has
submitted the consents of the farmer of the land from where mining is
to be carried out.
24) NOC has been issued by the Department of Forest & Wildlife, SBS Nagar
vide letter no. 239 dated 10/04/2015 to the effect that the above said
khasra nos are not under the control of Department of forest & Wildlife,
136
SBS Nagar. Further, there is a Government Reserve Forest adjoining to
the said mining site and demarcation is required
25) The project proponent also presented the proposed TORs.
After detailed deliberations, the SEAC categorized the project as
category B-1 of the EIA Notification dated 14.9.2006 and the project
proponent is required to be issued 'Terms of Reference' (TOR) for
preparation of detailed draft Rapid EIA report. The Committee decided
to forward the following finalized "Terms of Reference" to the SEIAA
with a recommendation to convey the same to the project proponent for
preparation of rapid EIA study report:
1. EIA study report shall be prepared as per final District Survey Report
(DSR), which is to be prepared & finalized by respective DEIAAs.
However, the project proponent may carry out monitoring/collect
baseline data at his own risk & cost.
2. EIA study shall be carried out in accordance with the provisions of MoEF
& CC notification dated 15.01.2016 & Sustainable Sand Mining
Management Guidelines 2016 issued by MoEF&CC, New Delhi as
amended from time to time and guidelines issued by Geological Survey
of India
3. EIA study shall also cover the provision of OM NO.2-11013/57/2014-IA-
II(M) dated 29.10.2014 regarding Impact of mining activities on
habitations-Issues related to the mining projects where in Habitations
and villages are the part of the mine lease area or Habitations and
villages are surrounded by the mine lease area.
4. All documents including approved mine plan (eco friendly mine plan),
EIA report and public hearing should be compatible with one another in
terms of the mine lease area, production levels, waste generation and
its management and mining technology and should be in the name of
the lessee.
5. The terms and conditions imposed, if any, by the Competent Authority in
the State Government while granting mining lease/permit/contract
should be built into the mine plan (eco friendly mine plan) as well as the
EIA report. It may inter-alia include; area of working (length and
137
breadth of the river stretch), mode of working, working shift,
transportation of mineral, restriction, if any imposed for working etc.
6. Involvement of forestland, if any, in the project and status of forestry
clearance should be given.
7. The study area will comprise of 10 km zone around the mine lease from
lease periphery and the data contained in the EIA such as waste
generation etc should be for the life of the mine / lease period.
8. Land use of the study area delineating forest area, agricultural land,
grazing land, wildlife sanctuary and national park, migratory routes of
fauna, water bodies, human settlements and other ecological features.
9. Land use plan of the mine lease area should be prepared to encompass
pre-operational, operational and post operational phases.
10. Impact of the project on the wildlife in the surrounding and any other
protected area and accordingly detailed mitigation measures required
should be worked out with cost implications.
11. The vegetation in the reserved forest/protected forest in the study area,
if any, should be indicated.
12. A study shall be got done to ascertain the impact of the mining project
on wildlife of the area including aquatic life.
13. Location of National Parks, Sanctuaries, Biosphere Reserves, Wildlife
Corridors, Tiger/Elephant Reserves (existing as well as proposed) within
10 km of the mine lease should be clearly indicated supported by a
location map duly authenticated by Chief Wildlife Warden. Necessary
clearance from the Chief Wildlife Warden for operating the mine within
10 km of the National Park / Sanctuary, if any, should also be obtained
and furnished.
14. A detailed biological study for the study area [core zone and buffer zone
(10 km radius of the periphery of the mine lease)] including the aquatic
fauna in the riverine system shall be carried out. Details of flora and
fauna, duly authenticated, separately for core and buffer zone should be
furnished based on field survey clearly indicating the Schedule of the
fauna present. In case of any scheduled-I fauna found in the study area,
the necessary plan for their conservation should be prepared in
138
consultation with State Forest and Wildlife Department and details
furnished. Necessary allocation of funds for implementing the same
should be made as part of the project cost.
15. Impact of the project on land use including change of river course, if
any should be given.
16. Impact on topography, drainage, agricultural fields, cattle fields, wildlife,
water logging leading to water borne diseases, if any. It may also be
shown whether it will lead to change of watercourse of the river.
Modelling exercise should also be carried out through an expert agency
to show the change in river flow dynamics, if any.
17. Collection of one season (non-monsoon) primary baseline data on
ambient air quality (PM2.5, PM10, S02 and NOx), water quality, noise level,
soil and flora and fauna, site-specific meteorological data should also be
collected. The location of the monitoring stations should be justified.
Date wise collected baseline AAQ data should form part of EIA and EMP
report. The mineralogical composition of PM10 particularly for free silica
should be given. There should be at least one AAQ monitoring station
within 500 m of the mine lease in the pre-dominant downwind direction.
18. Air quality modelling should be carried out for prediction of impact of the
project on the air quality of the area. It should also take into account
the impact of movement of vehicles for transportation of mineral. The
details of the model used and input parameters used for modelling
should be provided. The air quality contours may be shown on a location
map clearly indicating the location of the site, location of sensitive
receptors, if any and the habitation. The wind roses showing pre-
dominant wind direction may also be indicated on the map. The water
requirement for the project, its availability and source to be furnished. A
detailed water balance should also be provided. Fresh water
requirement for the project should also be indicated.
19. Necessary clearance from the Competent Authority for withdrawal of
requisite quantity of water for the project should be provided.
20. Impact of the project on the water quality should be assessed and
necessary safeguard measures, if any required should be provided.
139
21. Information on site elevation, working depth, groundwater table should
be provided both in AMSL and BGL. A schematic diagram may also be
provided for the same.
22. Quantity of solid waste generation, if any, should be estimated and
details for its disposal and management should be provided.
23. Impact on local transport infrastructure due to the project should be
evaluated. Projected increase in truck traffic as a result of the project in
the present road network (including those outside the project area) and
whether it is capable of handling the increased load should be
estimated. Arrangement for improving the infrastructure, if
contemplated including action to be taken by other agencies such as
State Government, if any, should be covered.
24. Details of the infrastructure facilities to be provided for the mine workers
should be furnished.
25. Phase-wise plan of greenbelt development, plantation and compensatory
afforestation clearly indicating the area to be covered under plantation
and the species to be planted should be provided.
26. Occupational health impacts of the project activity should be anticipated
and reported and proposed preventive measures indicated. These
alongwith details of pre-placement medical examination and periodical
medical examination schedules and medical facilities proposed to be
provided should be incorporated in the EMP
27. Measures of socio economic influence to the local community, proposed
to be provided by project proponent should be spelt out. As far as
possible, quantitative dimensions should be given.
28. Detailed environmental management plan to mitigate the environmental
impacts. Specific safeguard measures to control PM10 as well as
pollution due to transportation should be given.
29. Public hearing points raised and commitment of the project proponent
on the same along with time bound action plan to implement the same
should be provided.
30. Details of litigation pending against the project, if any, with direction
order passed by any Court of Law against the project should be given.
140
31. The cost of the project (capital cost and recurring cost) as well as the
cost towards implementation of EMP should clearly be spelt out.
32. The prescribed TORs would be valid for a period of three years for
submission of the EIA/EMP reports, as per the O.M. No. J-
11013/41/2006-IA.II(I) Part dated 08.10.2014.
33. Other details as indicated in Appendix III of EIA Notification 2006 and
the manual titled as "EIA guidance Manual" published by the Ministry of
Environment & Forests, New Delhi for mining projects, should also be
attended.
34. The project proponent shall adopt and follow the procedure for
monitoring of sand mining or river bed mining as given in the Appendix-
xii of Notification No. S.O. 141 (E) dated 15.01.2016 issued by MoEF &
CC for streamlining the process of environmental clearance for mining of
minor mineral.
The project proponent should prepare draft rapid EIA / EMP
Report for its project based on above Terms of Reference and apply to the
Member Secretary, Punjab Pollution Control Board for conducting public
hearing as per the provisions of EIA Notification, 2006 as amended from time
to time on submitting EIA / EMP / Executive Summary Report prepared by the
project proponent as per TORs.
After completing the process of public hearing / public
consultation, the Department shall submit final EIA / EMP to the State Expert
Appraisal Committee after incorporating all the issues raised during public
hearing / public consultation for Appraisal of its project.
The case was considered by the SEIAA in its 122nd meeting held
on 02.05.2017, which was attended by the following: -
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Gurdev S. Mahal, General Manager-cum-Mining officer, DIC, SBS
Nagar.
General Manager-cum-Mining officer, DIC, SBS Nagar presented the
salient features of the project before the SEIAA and requested for issuance of
ToRs.
141
The SEIAA looked into the details of the case and was satisfied with
the same. Therefore, the Authority decided to accept the recommendations of
SEAC and to issue Terms of Reference as proposed by the SEAC. The SEIAA
also decided that the project proponent shall submit final EIA / EMP based
upon the ToRs after incorporating all the issues raised during public hearing /
public consultation for Appraisal of its project to the SEAC.
Item No122.30: Regarding amendment of environmental clearance granted under EIA notification dated 14.09.2006 to General Manager-cum-Mining Officer, Nawan Shahar for mining of minor minerals (Sand) in the revenue estate of Village Burj Tehal Dass, Tehsil Nawan Shahar, District SBS Nagar and transferred in the name of Sh. Jagvirinder Singh S/o Sh. Gulsher Singh R/o VPO Railon Khurd, Distt. RupNagar. (SIA/PB/MIN/19235/2014)
The SEIAA observed that
1. The General Manager-Cum-Mining Officer, Nawanshahar, was granted
environmental clearance under EIA notification dated 14.09.2006 vide
no. 7593 dated 31.01.2014 for carrying out the mining of minor minerals
(Sand) @ 1,00,310 Ton/year in River Sutlej in an area of 21.50 Hectares
in the revenue estate of Village Burj Tehal Dass (Hadbast no. 292),
Tehsil Nawan shahar, District S.B.S. Nagar, subject to certain conditions
including the following condition:
“The Mining Officer may apply for transfer of environmental clearance
under EIA notification dated 14.09.2006 to the contractor finalized by
the Department of Industries & Commerce to SEIAA, Punjab.
However, no activity shall be undertaken by the contractor till the
environmental clearance is transferred in his name and he is lawfully
bound to comply with the conditions of the environmental clearance.”
In compliance to the decision of 116th meeting of SEIAA held on
20.10.2016, environmental clearance has been transferred vide letter no. 3537
dated 07.11.2016 in the name of Sh. Jagvirinder Singh s/o Sh. Gulsher Singh
r/o VPO Railon Khurd, Distt. RupNagar, for the remaining validity period of
environmental clearance i.e. upto 30.01.2019 subject to the same conditions as
mentioned therein.
142
The project proponent has submitted an online application on
24.04.2017 and requested for amendment in Environment Clearance granted
to GM, DIC, SBS Nagar and transferred to Sh. Jagvirinder Singh S/o Gulsher
Singh VPO Railon Khurd, Distt. Roopnagar, Punjab. The GMDIC has requested
to amend environmental clearance for installation of a weighing bridge at site-
II and transport the material though through Gari Togar to the nearest bridge
joining NH-95 contending that the two mining site are across the active
channel and it is not possible to carry out mining on one of the site due to non-
availability of weighing bridge. He has requested allow him to install the second
weighing bridge and transport the mined material through another route. The
project proponent submitted updated Form-1, copy of Environment Clearance
letter, route plan and reply to the EDS.
The case was considered by SEAC in its 158th meeting held on
27.04.2017, which was attended by Sh. Sushminder Singh, State Geologist and
Sh. Gurdev S. Mahal, General Manager-cum-Mining officer, DIC, SBS Nagar.
The GMDIC, SBS Nagar presented the details of the case are as under: -
1) Environment Clearance has already been granted vide letter No. 7593
dated 31.01.2014 to the General Manager-Cum-Mining Officer,
Nawanshahar.
2) Environmental clearance has been transferred vide letter no. 3537 dated
07.11.2016 in the name of Sh. Jagvirinder Singh s/o Sh. Gulsher Singh
r/o VPO Railon Khurd, Distt. RupNagar, for the remaining validity period
of environmental clearance i.e. upto 30.01.2019.
3) Mining activity at site-I has been started and only 37,080.220 Tonne
sand have been extracted so far. However, due to physical barrier of the
river flowing between the two sites work could not be started at site-II.
4) The transport route map of the material through Gari Togar to the
nearest bridge joining NH-95 has been marked on the layout plan.
5) The procedure for monitoring of sand mining or river bed mining as
given in the Appendix-xii of MoEF Notification dated 15.01.2016 is being
followed and undertaking in this regard has been submitted.
6) The mining site is not a part of the active channel or the River. Images
from the google earth dated 11.01.2017 has been submitted
143
7) Environmental monitoring of the project site has already been conducted
from NABL accredited laboratory and the test reports of the same has
been submitted with six monthly compliance report of the conditions.
8) Mining of Sand will be carried out upto a depth of 3m bgl or above
ground water level whichever comes first by open cast manual without
drilling and blasting for 225 days in a year excluding monsoon season
9) The total cost of project will be Rs. 30.09 Lacs and total amount of
water demand for the project is 2.8 KLD
10) Total area under the Environment Clearance granted will remain the
same and all conditions of the same for safeguarding the environment of
the project will be implemented.
After deliberations, the SEAC decided to recommend the case to
SEIAA for amendment regarding installation of a weighing bridge at site-II and
transport the material though Gari Togar to the nearest bridge joining NH-95 in
the environmental clearance granted vide letter No. 7593 dated 31.01.2014 to
the General Manager-Cum-Mining Officer, Nawanshahar & subsequently
transferred vide letter no. 3537 dated 07.11.2016 in the name of Sh.
Jagvirinder Singh s/o Sh. Gulsher Singh r/o VPO Railon Khurd, Distt. RupNagar.
The case was considered by the SEIAA in its 122nd meeting held
on 02.05.2017, which was attended by the following: -
(i) Sh. Gurdev S. Mahal, General Manager-cum-Mining officer, DIC, SBS
Nagar.
(ii) Sh. Sushminder Singh, State Geologist.
GMDIC, SBS Nagar presented the details of the case and
requested to amend environmental clearance for installation of a weighing
bridge at site-II and transport the material though through Gari Togar to the
nearest bridge joining NH-95 contending that the two mining site are across
the active channel and it is not possible to carry out mining on one of the site
due to non-availability of weighing bridge. He has requested allow him to install
the second weighing bridge and transport the mined material through another
route.
144
To a query of SEIAA as to whether haulage road has been
marked on the 'Aks Sajra', the GMDIC, SBS Nagar submitted a copy of 'Aks
Sajra' on which haulage road has been marked, which was taken on record by
SEIAA.
The SEIAA observed that the case stands recommended by SEAC
and looked into the details of the case and was satisfied with the same.
Therefore, the Authority decided to accept the recommendations
of SEAC.
Item No:122.31: Application for obtaining environmental clearance under EIA notification dated 14.09.2006 for mining of minor minerals (Sand) from the bed of river Satluj in the revenue estate of village Majara Kalan, Tehsil Ludhiana (W) District Ludhiana, Punjab of General Manager cum Mining Officer, District Industries Centre, Ludhiana.(Proposal No.
SIA/PB/MIN/61269/2016)
The SEIAA observed that:-
The General Manager cum Mining Officer, District Industries
Centre, Ludhiana vide online application dated 06.04.2017, has applied for
obtaining environmental clearance under EIA notification dated 14.09.2006 for
mining of minor minerals (Sand) from the bed of river Satluj in the revenue
estate of village Majara Kalan, Tehsil Ludhiana (W) District Ludhiana, Punjab.
The project is covered under category 1 (a) of the Schedule appended to the
said notification. The details of the project are as under:
1) About 2,36,196 TPA of mining of minor minerals (Sand) will be carried out
in an area of 5.40 Hectare from the bed of river Satluj in the revenue estate
of village Majara Kalan, Tehsil Ludhiana (W) District Ludhiana, Punjab in
H.B. no. 119 bearing Khasra nos 1// 16/23/2,23/1,24,25,2// 20,21,3//
1,10,11/1,4// 1,2/1,2/2,3,4,8,13,9/2,10/1, 5// 6/1,17// 24,18// 21/2,23,25//
1/2,2/1.
2) During the lease period, the deposit will be worked from the top surface
to 3 m below ground level or above ground water table, whichever comes
first.
3) Total amount of water required for the project will be 3.44 KLD out of
which 3.06 KLD will be used for domestic purpose and remaining 0.38
145
KLD for dust suppression. water will be supplied through tankers from
nearby available source.
4) The total cost of project will be Rs. 1,56,10,000.
5) All the activities will be carried out manually using hand tools like shovel,
pan,
sieve etc. The operation will be done only from sun rise to sun set hence
there will be no power requirement for the project at site.
6) The existing roads will be utilized for the transport of sand from mine site
to market. However, the haul roads will be repaired & maintained
regularly.
7) Rs. 3,12,200 will be utilized for following activities under Corporate Social
Responsibility.
i. Regular health check-up camps for the workers engaged in mines
shall be organized.
ii. Occupational health surveillance program of the workers shall be
undertaken periodically to observe any contractions due to
exposure to dust and take corrective measures, if needed.
iii. Common vocational training centre shall be setup at district level.
iv. Local needs of habitants like school, crèche, hospital, veterinary
hospital, sanitation, drinking water etc. shall be considered
positively.
8) Status of documents submitted viz-a-viz required as per the check list is
as under:
Sr. No.
Documents required as per the check list Checklist submitted by the Project proponent
1. Properly filled Form-1 and pre-feasibility report Submitted with EIA report Form I -page no. 5-19 PFR – Page No. 20-35
2. Proof of ownership of land such as copy of latest jamabandi
Complied with the EIA report Page No. 94-102
3. Mining Plan duly approved by the State Geologist Complied with the EIA report Page No. 39-92
4. NOC from concerned DFO regarding forest land Complied with the EIA report, page No. 103-104
5. Exact distance of proposed mining site from nearest Wildlife Sanctuary and in case site falls within 10 kms radius of Wildlife Sanctuary, a copy of acknowledgement along with complete set of application submitted online for obtaining NBWL
DFO letter is attached in report stated that there is no Wildlife Sanctuary exists within 10 kms radius from the periphery of the proposed
146
permission be submitted. project, page No. 103-104
6. Status of mining at the site, if any, along with photographs from all the four sides.
Attached Page No. 37 – 38 & 91 -92 in the EIA report
7. 500 meter radius map of the area from periphery of project site clearly indicating the physical features.
Attached as Enclosure – I with EDS Reply
8. Mining lay out plan showing key distances of the mining site from the various features such river bank, active channels, bundh and other structures in the vicinity, if any, drawn on portion of 'Aks Sajra' of the mining site, so as to ensure that minimum statutory distances are maintained. The route map to be followed should also be marked on the layout plan.
Attached with EIA report Page No.108
9. Final District Survey Report for minor mineral, which should be the basis of application for EC, preparation of reports and appraisal of projects.
Attached as Enclosure – II with EDS Reply
10. An undertaking to the effect that: (i) No other mining site falls within a radius of 500 m from the periphery of proposed site to whom either environmental clearance has already been granted by SEIAA or MoEF or application has been submitted for obtaining environmental clearance with SEIAA/DEIAA/ MoEF&CC. (ii) In case any new mining site comes at any stage in future within a radius of 500 m of the above said site, the same will be informed to the SEIAA/DEIAA/MoEF&CC, immediately. (iii) Mining site is not located in stream as per the actual layout plan enclosed herewith and no in stream mining is involved. (iv) Mining will be carried out by manual opencast method by hand tools without use of drilling, blasting and JCB or any other mechanized means. All the stipulations provided in the OM dated 24.12.2013 issued by Ministry of Environment, Forests & Climate Change will be complied with in true letter & spirit.
Undertaking letter already attached with report Page No. 109
11. The declaration about Environmental Consultant engaged and who have prepared EIA/EMP report needs to be made. The Consultant has to be NABET approved as per MoEF&CC notification dated 03.03.2016 and necessary proof in this regard is required to be attached.
Attached as Enclosure – III with EDS Reply
12. Environmental Management Plan indicating the following:
Attached with EIA report Page No. 73-87
a) Plan to follow the sustainable sand and gravel mining guidelines, 2016 issued by MoEF&CC.
Complied in EMP Report Page No. 73-87
b) All mitigation measures for each item-wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project.
Complied in EMP Report Page No. 73-87
c) Compliance of various environmental regulations. Complied in EMP Report
147
Page No. 73-87
d) Steps to be taken in case of emergency such as accidents at the site including fire.
Not applicable
e) For how long period the project proponent will be responsible for implementation of EMP and the name of the person(s) responsible for implementation of EMP.
Project proponent shall be responsible for implementation of EMP till the validity of EC.
d) Capital & recurring cost for the EMP per year and the details of funds for the same.
Total capital cost for EMP in 5 year- Rs 6,70,000 Recurring cost per year for EMP- Rs 1,34,000
f) Name of the individual persons / organization, who will be responsible for implementation of EMP after the lapse of the period for which the project proponent is responsible.
Project proponent shall be responsible for implementation of EMP till the validity of EC
13. Whether the periphery of any other area of borrowing / excavation falls Within a radius of 500m from the periphery of this area borrowing/excavation or not? If yes, how much is the total area of all such Borrowing/ excavation sites? The project proponent shall submit an undertaking to the effect that the total area of all borrowing/excavation sites including the area of proposed project within a radius of 500 m from the proposed area of borrowing / excavation is less than 5 hectares.
Details given in Mining officer letter attached with the Report Page No.107
14. Mining sites located more than 1 km apart are to be considered as different block/cluster and are required to obtain separate environmental clearance under EIA notification dated 14.09.2006.
Mining officer letter attached with the report Page No.107
15. Complete transportation plan giving detailed procedure to be followed as per requirements of appendix-XII of the MoEF&CC notification dated 15.01.2016.
Integrated Mining and Minerals Management System (I3MS software) is under process to implement soon by Govt. of Punjab. To stop illegal mining attached as Enclosure – IV with EDS Reply
16. Status verification with regard to legal notice received/court case pending, if any.
Not applicable
The case was considered by SEAC in its 157th meeting held on
12.04.2017, which was attended by the following on behalf of project
proponent:
(iv) Sh. Mahesh Khanna General Manager-cum-Mining officer, DIC,
Ludhiana.
(v) Sh. Paras Mahajan, Asst. Geologist.
148
(vi) Sh. S. Brahma, HOD-EIA & Shivani Duti, M/s Shivalik Solid Waste
Management Ltd., Environmental consultant of the project
proponent.
Sh. S. Brahma, HOD-EIA, M/s Shivalik Solid Waste Management
Ltd., Environmental consultant presented the salient features of the mining
project site.
The SEAC queried that mining site is divided into two parts
located across the active channel and crossing the active channel is not
permitted. In reply, the project proponent requested that he intends to drop
one pocked of mine lease area. The SEAC observed that in case one pocket is
dropped, the mine lease area will get reduced to less than 5 hectares.
Moreover, both mine areas falls within 500 meter from periphery of each other
and thus form cluster. As per the amended notification dated 15.1.2016 issued
by the MoEF&CC, cluster area of mine leases less than 25 hectares no
individual lease more than 5 hectares, the authority to appraise/grant EC is
respective DEAC/DEIAA. Also, in case of individual mining projects have mine
lease area upto 5 hectare, the authority to appraise/grant lies with respective
DEAC/DEIAA.
After deliberation, SEAC decided to recommend to SEIAA to reject
the application of the project proponent.
The case was considered by SEIAA in its 122nd meeting held on
02.05.2017, which was attended by the following on behalf of project
proponent:
(i) Sh. Sushminder Singh, State Geologist.
(ii) Sh. Mahesh Khanna General Manager-cum-Mining officer, DIC,
Ludhiana.
(iii) Sh. S. Brahma, HOD-EIA & Shivani Duti, M/s Shivalik Solid Waste
Management Ltd., Environmental consultant of the project proponent
General Manager-cum-Mining officer, DIC, Ludhiana submitted a
request letter dated 02/05/2017 for withdrawal of his application for sand
mining since the area Majran Kalan has been reduced to less than 5.0 hectare.
Thus, appraisal of the project site falls in the preview of DEIAA/DEAC.
149
After detailed deliberations, the SEIAA decided to accept the
request of the project proponent and allow him to withdraw his application.
***
150
Annexure-A
Conditions to be imposed on Sand/Gravel Mining Projects
A. Specific conditions:
(i) The environmental clearance will be valid for a period of seven years
from the date of issuance, as per the provisions of the EIA Notification,
2006 as amended subsequently, for mining of minor minerals in the
above said location and khasra numbers.
(ii) The absolute elevation (Redline), below which no mining shall be
allowed to be carried out, shall be determined by the Department of
Industries & Commerce, Punjab along with Department of Irrigation,
Punjab after carrying out proper survey of the mining site, so as to avoid
impacts on structures such as bridges, piers and to avoid vegetation
impacts associated with down cutting due to excessive removal of
sediment. In no case mining shall be carried out below the redline.
Environmental clearance of mine lease area will be transferred to any
contractor only after defining the red line.
(iii) The Mining Officer shall demarcate the mining lease area in the
presence of revenue authorities and concerned Village Panchayat or
their representatives. Mining lease area will be demarcated on the
ground with pucca pillars with reference to some permanent bench mark
before starting any mining activity at site. The existing river bed level
will also be marked on the pillars to be erected before starting the
mining activities. Intimation with documentary evidence before starting
activity i.e. transfer of environmental clearance in the name of
contractor shall be submitted to SEIAA, Punjab.
(iv) Mining shall be as per the approved Development/Mining Plan prepared
for this project and as per the Mines & Mineral (Development &
Regulation) Act, 1957 and rules framed there under as amended from
time to time, other Acts/rules related with mining of minor minerals.
(v) The mining activity shall be carried out strictly as per guidelines
contained in the Office Memorandum dated 24.12.2013 & Sustainable
Sand Mining Management Guidelines 2016 issued by MoEF&CC, New
Delhi as amended from time to time and guidelines issued by Geological
Survey of India.
(vi) The Mining Officer shall obtain Consent to Establish and Consent to
Operate from the Punjab Pollution Control Board and effectively
implement all the conditions stipulated therein.
(vii) The Mining Officer shall observe the mining site after every 15 days and
in case, a Schedule-I or Schedule-II species as per Wildlife Act or any
rare or endangered species are reported, the Mining Officer will get a
151
conservation plan prepared in consultation with the Department of
Wildlife and ensure its implementation.
(viii) The mining of minor mineral (sand) shall be carried out only upto a
depth of 3.0 m of the demarcated riverbed level or above the
groundwater level, whichever is less.
(ix) The mining activity shall be restricted to the section of river bed where
there is no flow of water and no in stream mining shall be carried out in
any circumstances. Stream shall not be diverted under any
circumstances to form inactive channel.
(x) The Mining Officer shall ensure that the mining shall be carried out by
the contractor/lessor as per the EMP prepared and development /
mining plan prepared as per the Mines & Mineral (Development &
Regulation) Act, 1957 / other Acts/Rules related with mining of minor
minerals. It shall be ensured that no mining shall be carried out during
the monsoon season as defined by the Meteorological Department.
(xi) The Mining Officer shall ensure that wherever deployment of labour
attracts the Mines Act, the provision thereof shall be strictly followed.
(xii) The Mining Officer shall undertake plantation/afforestation work by
planting the native species in the nearby area adjacent to mine lease.
(xiii) The Mining Officer shall ensure that effective safeguard measures, such
as regular water sprinkling shall be carried out in critical areas prone to
air pollution and having high levels of particulate matter such as loading
and unloading point and all transfer points. Extensive water sprinkling
shall be carried out on haul roads. It should be ensured that the
Ambient Air Quality parameters conform to the norms prescribed by the
Ministry of Environment & Forests/Punjab Pollution Control Board in this
regard.
(xiv) The Mining Officer shall undertake adequate safeguard measures during
extraction of sand and ensure that due to this activity, the hydro-
geological and ecological regime of the surrounding area shall not be
affected. Regular monitoring of ground water level and quality shall
be carried out around the mine lease area by establishing a network
of existing wells, if any, and installing new piezometers during the
mining operation.
(xv) The periodic monitoring [(at least four times in a year- pre-monsoon
(April May), monsoon (August), post-monsoon (November) and winter
(January); once in each season)] shall be carried out in consultation
with the State Ground Water Board/Central Ground Water Authority and
the data thus collected may be sent regularly to the Ministry of
Environment and Forests and its Regional Office at Chandigarh, the
Central Ground Water Authority, the Regional Director, Central Ground
Water Board; SEIAA, Punjab and Punjab Pollution Control Board. If at
any stage, it is observed that the groundwater table is getting depleted
152
or rising due to the mining activity, necessary corrective measures shall
be carried out.
(xvi) The Mining Officer shall obtain necessary prior permission of the
competent authorities for drawl of requisite quantity of water (surface
water and groundwater), if any, required for the project.
(xvii) Appropriate mitigation measures shall be taken by the Mining Officer to
prevent pollution at the mining site in consultation with the State
Pollution Control Board. It shall be ensured that there is no leakage of
oil and grease at the mining site from the vehicles/mining equipments
used for transportation.
(xviii) The transportation route map will be prepared and finalized in such a
manner that no vehicle passes through the flowing water section /
channel of the river. Vehicular emissions shall be kept under control and
regularly monitored. The project proponent shall ensure that, as far as
possible, the transportation route will be away from the habitation area
and will not pass through any village. The transportation hours of mined
material shall be restricted to non-peak hours only.
(xix) The mineral transportation shall be carried out through the covered
trucks only and the vehicles carrying the mineral shall not be
overloaded. All the public roads as well as approach roads shall be
maintained by the Department and it shall be ensured that tippers
carrying mined material are not loaded beyond the permissible load as
per designed load bearing capacity of the road. Moreover, provision of
sufficient funds shall be made in the budget for the proper maintenance
of the roads.
(xx) Mining shall be carried out only by manual opencast method by hand
tools without use of drilling, blasting and JCB or any other mechanized
means.
(xxi) Mineral handling area shall be provided with the adequate number of
dust suppression systems. Loading and unloading areas including all the
transfer points should also have efficient dust control arrangements.
These should be properly maintained and operated.
(xxii) Periodical medical examination of the workers engaged in the project
shall be carried out and records maintained. For the purpose, schedule
of health examination of the workers should be drawn and followed
accordingly.
(xxiii) Provision shall be made for the housing of workers, if residing at site,
within the site with all necessary infrastructure and facilities such as fuel
for cooking, mobile toilets, mobile STP, safe drinking water, medical
health care, crèche etc. The housing may be in the form of temporary
structures to be removed after the completion of the project. In case of
non-residential/daily workers, provision of adequate bath rooms, mobile
153
toilets, and mobile STP shall be made to avoid open defecation and
treated domestic effluent shall be discharged onto land for plantation.
(xxiv) The municipal solid waste generated shall be disposed off as per Solid
Waste Management Rules, 2016. Segregation of bio-degradable and
non-biodegradable wastes shall be done at site and disposed off as per
provisions of Solid Waste Management Rules. Dustbins will be provided
at site and the workers will be guided to put the domestic waste and
plastic carry bags etc. if any, in the dustbin. No littering will be
permitted at the site as well as in the vicinity.
(xxv) The critical parameters such as RSPM (Particulate matter with size less
than 10 micron i.e., PM10) and NO in the ambient air within the impact
zone shall be monitored periodically. Further, quality of discharged
water shall also be monitored [(TDS, DO, PH, Faecal Coliform and Total
Suspended Solids (TSS)]. The monitored data shall be uploaded on the
website of the company as well as displayed on a display board at the
project site at a suitable location near the main gate of the Company in
public domain. The Circular No. J-20012/1/2006-IA.II(M) dated
27.05.2009 issued by Ministry of Environment and Forests, which is
available on the website of the Ministry www.envfor.nic.in shall also be
referred in this regard for its compliance.
(xxvi) The Mining Officer shall take all precautionary measures during mining
operation for conservation and protection of rare and endangered flora
& fauna found in the study area. Action plan for conservation of flora
and fauna shall be prepared in consultation with the State Forest and
Wildlife Department. All the safeguard measures brought out in the
Wildlife Conservation Plan so prepared specific to this project site shall
be effectively implemented. Necessary allocation of funds for
implementation of the conservation plan shall be made and the funds so
allocated shall be included in the project cost. A copy of action plan shall
be submitted to the Regional Office of the Ministry of Environment and
Forests, Chandigarh and SEIAA, Punjab.
(xxvii) The Mining Officer shall submit within 3 months their policy towards
Corporate Environment Responsibility which should inter-alia address (i)
Standard operating process/ procedure to bring into focus any
infringement/deviation/violation of environmental or forest norms/
conditions, (ii) Hierarchical system or Administrative order of the
company to deal with environmental issues and ensuring compliance of
EC conditions and (iii) System of reporting of non compliance/violation
of environmental norms to the Board of Directors of the company and/or
stakeholders or shareholders.
(xxviii) Vehicles hired to be used for transportation of mined material should be
in good condition and should conform to applicable air and noise
emission standards as provided in the Vehicular Act.
154
(xxix) Ambient noise levels should conform to prescribed standards both
during day and night. Incremental pollution loads on the ambient air and
noise quality should be closely monitored.
(xxx) The Risk assessment and disaster management plan should be
prepared.
(xxxi) The Mining Officer shall submit the site plan showing the earmarked
area for storage of mined material.
(xxxii) The Mining Officer shall ensure that the compensation to the private
land owner (s) for the mined area shall be made as per the prevalent
policy of the State Govt.
(xxxiii) No mining operation shall be carried out at any point within 75 m of
railway line, 60 m from national highway, 50 m from HT line/any public
works/reservoirs, tanks/canal/public roads and buildings or inhabited or
10 m of outer edge of any village road. No mining shall be carried out
within 500 m of upper side and lower side of high level bridge on the
rivers. Similarly, no mining shall be carried out within 250 m of upper
and lower side of other bridges. To prevent bank erosion, no mining at
the concave side of the river channel will be carried out. No mining shall
be carried out 100 m inside and 500 m outside of the flood protection
bund of river Satluj. A safety barrier of 7.5m width shall be left intact
around the mine lease boundary. Mining shall be restricted minimum 3
m away (inward) from the active channel bank and stream.
(xxxiv) The project proponent shall ensure that the quantum of material to be
mined does not exceed the annual replenishable rate and the original
bed level of the river shall be maintained.
(xxxv) The project proponent shall ensure the implementation of the post
closure mining plan as proposed by the project proponent in the mining
plan.
(xxxvi) The protection bundh is not permitted for use as transportation route for
the hauling of mined material. In case, use of small stretch of protection
bundh is un-avoidable for taking the final route, the said portion of the
protection bundh shall be maintained in good condition. The said portion
shall be used only after obtaining prior written permission of the
concerned department and a copy of the same be sent to the SEIAA,
Punjab.
(xxxvii) The project proponent shall adopt and follow the procedure for
monitoring of sand mining or river bed mining as given in the Appendix-
xii of Notification No. S.O. 141 (E) dated 15.01.2016 issued by MoEF &
CC for streamlining the process of environmental clearance for mining of
minor mineral.
155
B. General Conditions:
(i) No change in mining technology and scope of working should be made
without prior approval of the Ministry of Environment, Forests &
Climate Change.
(ii) No change in the calendar plan including excavation, quantum of
mineral sand/gravel (minor mineral) and waste should be made.
(iii) Four ambient air quality-monitoring stations should be established in the
core zone as well as in the buffer zone for RSPM (Particulate matter with
size less than 10micron i.e., PM) and NOx monitoring. Location of the
stations should be decided based on the meteorological data,
topographical features and environmentally and ecologically sensitive
targets and frequency of monitoring should be undertaken in
consultation with the State Pollution Control Board.
(iv) Data on ambient air quality RSPM (Particulate matter with size less than
10micron i.e., PM) & NOx should be regularly submitted to the Ministry
of Environment and Forests including its Regional office located at
Chandigarh and the Punjab Pollution Control Board / Central Pollution
Control Board once in six months and SEIAA, Punjab.
(v) Fugitive dust emissions from all the sources should be controlled
regularly. Water spraying arrangement on haul roads, loading and
unloading and at transfer points should be provided and properly
maintained.
(vi) Personnel working in dusty areas should wear protective respiratory
devices and they should also be provided with adequate training and
information on safety and health aspects. Occupational health
surveillance program of the workers should be undertaken periodically
to observe any contractions due to exposure to dust and take corrective
measures, if needed.
(vii) A separate environmental management cell with suitable qualified
personnel should be set-up under the control of a Senior Executive, who
will report directly to the Head of the Organization.
(viii) The funds earmarked for environmental protection measures should be
kept in separate account and should not be diverted for other purpose.
Year wise expenditure should be reported to the Ministry of Environment
and Forests and its Regional Office located at Chandigarh and SEIAA,
Punjab.
(ix) The Mining Officer should inform to the Regional Office of the Ministry of
Environment & Forests located at Chandigarh and SEIAA, Punjab
regarding date of financial closures and final approval of the project by
the concerned authorities and the date of start of land development
work.
(x) The Regional Office of Ministry of Environment & Forests located at
Chandigarh and SEIAA, Punjab shall monitor compliance of the
156
stipulated conditions. The project authorities should extend full
cooperation to the officer (s) of the Regional Office by furnishing the
requisite data / information / monitoring reports.
(xi) The Mining Officer shall submit six monthly reports on the status of
compliance of the stipulated environmental clearance conditions
including results of monitored data (both in hard copies as well as by e-
mail) to the Ministry of Environment and Forests, its Regional Office
Chandigarh, the respective Zonal Office of Central Pollution Control
Board and the State Pollution Control Board and SEIAA, Punjab. The
proponent shall upload the status of compliance of the environmental
clearance conditions, including results of monitored data on their
website and shall update the same periodically. It shall simultaneously
be sent to the Regional Office of the Ministry of Environment and
Forests, Chandigarh, the respective Zonal Office of Central Pollution
Control Board and the State Pollution Control Board and SEIAA, Punjab.
(xii) A copy of the clearance letter shall be sent by the proponent to
concerned Panchayat, Zila Parisad/ Municipal Corporation, Urban Local
Body and the Local NGO, if any, from whom suggestions/
representations, if any, were received while processing the proposal.
The clearance letter shall also be put on the website of the Company by
the proponent.
(xiii) The State Pollution Control Board should display a copy of the clearance
letter at the Regional office, District Industries Centre and the Collector’s
office/ Tehsildar’s office.
(xiv) The environmental statement for each financial year ending 31 March in
Form-V as is mandated to be submitted by the project proponent to the
concerned State Pollution Control Board as prescribed under the
Environment (Protection) Rules, 1986, as amended subsequently, shall
also be put on the website of the company along with the status of
compliance of environmental clearance conditions and shall also be sent
to the Regional Office of the Ministry of Environment and Forests,
Chandigarh and SEIAA, Punjab by e-mail.
(xv) The Mining Officer shall adhere to the commitments made in the
Environment Management Plan and Corporate Social Responsibility.
(xvi) The Mining Officer should advertise at least in two local newspapers
widely circulated, one of which shall be in the vernacular language of
the locality concerned, within 7 days of the issue of the clearance letter
informing that the project has been accorded environmental clearance
and a copy of the clearance letter is available with the State Pollution
Control Board and also at web site of the Ministry of Environment and
Forests at http://envfor.nic.in and a copy of the same should be
forwarded to the Regional Office of Ministry of Environment & Forests at
Chandigarh and SEIAA, Punjab.
157
(xvii) The Ministry of Environment, Forests & Climate Change and SEIAA,
Punjab or any other competent authority may alter/modify the above
conditions or stipulate any further condition in the interest of
environment protection.
(xviii) The SEIAA may cancel the environmental clearance granted to this
project under the provisions of EIA Notification, 2006, if, at any stage of
the validity of this environmental clearance, it is found/ come to the
knowledge of the SEIAA that the project proponent has deliberately
concealed and/or submitted false or misleading information or
inadequate data for obtaining the environmental clearance.
(xix) Digital processing of the entire lease area using remote sensing
technique should be done regularly once in three years for monitoring
the change of river course, if any and report submitted to the Ministry of
Environment, Forests & Climate Change & its Regional Office located at
Chandigarh and SEIAA, Punjab.
(xx) The Mining Officer shall get the micro chemical analysis of the mined
material done from an approved laboratory once in a year and shall
submit the analysis results to the Ministry of Environment &
Forests/Punjab Pollution Control Board and SEIAA, Punjab.
(xxi) The Mining Officer shall ensure that the contractor shall engage people
of local area for mining purpose as far as possible, so as to have
opportunities of employment for them.
(xxii) The Mining Officer may apply for transfer of environmental clearance
under EIA notification dated 14.09.2006 to the contractor finalized by
the Department of Industries & Commerce to SEIAA, Punjab. However,
no activity shall be undertaken by the contractor till the environmental
clearance is transferred in his name and he is lawfully bound to comply
with the conditions of the environmental clearance.
(xxiii) The monitoring of the mining project in respect of Environment
Management shall be carried out by the State/District Level Environment
Management Cells constituted by the Govt. of Punjab vide notifications
dated 03.12.2012.
(xxiv) Any appeal against this environmental clearance shall lie with the
National Green Tribunal, if preferred, within a period of 30 days as
prescribed under Section 16 of the National Green Tribunal Act,
2010.
****
158
Annexure-B A. Specific conditions:
(i) The environmental clearance will be valid for a period of seven years
from the date of issuance or for completion of excavation of sand/gravel @ ______( the quantity will be specified in each case) or up to a depth of 3m only whichever is reached earlier, as per the provisions of the EIA Notification, 2006 as amended subsequently, for mining of minor minerals in the above said location and khasra numbers.
(ii) Mining shall be as per the approved Development/Mining Plan prepared for this project and as per the Mines & Mineral (Development & Regulation) Act, 1957 / other Acts/rules related with mining of minor minerals.
(iii) The Mining Officer shall obtain Consent to Establish and Consent to Operate from the Punjab Pollution Control Board and effectively implement all the conditions stipulated therein.
(iv) The Mining Officer shall observe the mining site after every 15 days and in case, a Schedule-I or Schedule-II species as per Wildlife Act or any rare or endangered species are reported, the Mining Officer will get a conservation plan prepared in consultation with Department of Wildlife and ensure its implementation.
(v) The mining of minor mineral (sand) shall be carried out only upto a depth for which the sand strata is available, but not more than 3 meter below the natural ground level in any case or above the ground water table, whichever is less. The top over burden removed prior to starting the mining, shall be placed and it shall be ensured that no depression is created with respect to adjoining areas and natural drainage pattern of the area is not altered after mining.
(vi) The Mining Officer shall ensure that the mining shall be carried out by the contractor/lessor as per the EMP prepared and development / mining plan prepared as per the Mines & Mineral (Development & Regulation) Act, 1957 / other Acts/Rules related with mining of minor minerals. It shall be ensured that no mining shall be carried out during the monsoon season.
(vii) The mining activity shall be carried out strictly as per guidelines contained in the Office Memorandum dated 24.12.2013 & Sustainable Sand Mining Management Guidelines 2016 issued by MoEF&CC, New Delhi as amended from time to time and guidelines issued by Geological Survey of India as applicable for such projects.
(viii) Effective safeguard measures shall be taken by Mining Officer to ensure that the AAQ levels at various locations are within permissible limit as prescribed by MoEF/PPCB.
159
(ix) The Mining Officer shall ensure that wherever deployment of labour
attracts the Mines Act, the provision thereof shall be strictly followed. (x) The Mining Officer shall undertake plantation/afforestation work by
planting the native species in the nearby area adjacent to mine lease. (xi) The Mining Officer shall ensure that effective safeguard measures, such
as regular water sprinkling shall be carried out in critical areas prone to air pollution and having high levels of particulate matter such as loading and unloading point and all transfer points. Extensive water sprinkling shall be carried out on haul roads. It should be ensured that the Ambient Air Quality parameters conform to the norms prescribed by the Ministry of Environment & Forests/Punjab Pollution Control Board in this regard.
(xii) The Mining Officer shall undertake adequate safeguard measures during
extraction of sand and ensure that due to this activity the hydro-geological and ecological regime of the surrounding area shall not be affected. Regular monitoring of ground water level and quality shall be carried out around the mine lease area by establishing a network of existing wells and installing new piezometers during the mining operation.
(xiii) The periodic monitoring [(at least four times in a year- pre-monsoon
(April May), monsoon (August), post-monsoon (November) and winter (January); once in each season)] shall be carried out in consultation with the State Ground Water Board/Central Ground Water Authority and the data thus collected may be sent regularly to the Ministry of Environment and Forests and its Regional Office at Chandigarh, the Central Ground Water Authority, the Regional Director, Central Ground Water Board and Punjab Pollution Control Board. If at any stage, it is observed that the groundwater table is getting depleted or rising due to the mining activity, necessary corrective measures shall be carried out.
(xiv) The Mining Officer shall obtain necessary prior permission of the
competent authorities for drawl of requisite quantity of water (surface water and groundwater), if any, required for the project.
(xv) Appropriate mitigative measures shall be taken by the Mining Officer to
prevent pollution at the mining site in consultation with the State Pollution Control Board. It shall be ensured that there is no leakage of oil and grease at the mining site from the vehicles/mining equipments used for transportation.
(xvi) Vehicular emissions shall be kept under control and regularly monitored.
The project proponent shall ensure that, as far as possible, the transportation route will be away from the habitatin area.
160
(xvii) The mineral transportation shall be carried out through the covered trucks only and the vehicles carrying the mineral shall not be overloaded.
(xviii) No drilling and blasting operation shall be carried out. (xix) Mineral handling area shall be provided with the adequate number dust
suppression system. Loading and unloading areas including all the transfer points should also have efficient dust control arrangements. These should be properly maintained and operated.
(xx) Periodical medical examination of the workers engaged in the project
shall be carried out and records maintained. For the purpose, schedule of health examination of the workers should be drawn and followed accordingly.
(xxi) Provision shall be made for the housing of construction labour within the
site with all necessary infrastructure and facilities such as fuel for cooking, mobile toilets, mobile STP, safe drinking water, medical health care, crèche etc. The housing may be in the form of temporary structures to be removed after the completion of the project.
(xxii) The critical parameters such as RSPM (Particulate matter with size less
than 10micron i.e., PM10) and NO in the ambient air within the impact zone shall be monitored periodically. Further, quality of discharged water shall also be monitored [(TDS, DO, PH, Faecal Coliform and Total Suspended Solids (TSS)]. The monitored data shall be uploaded on the website of the company as well as displayed on a display board at the project site at a suitable location near the main gate of the Company in public domain. The Circular No. J-20012/1/2006-IA.II(M) dated 27.05.2009 issued by Ministry of Environment and Forests, which is available on the website of the Ministry www.envfor.nic.in shall also be referred in this regard for its compliance.
(xxiii) The Mining Officer shall take all precautionary measures during mining
operation for conservation and protection of rare and endangered flora & fauna found in the study area. Action plan for conservation of flora and fauna shall be prepared in consultation with the State Forest and Wildlife Department. All the safeguard measures brought out in the Wildlife Conservation Plan so prepared specific to this project site shall be effectively implemented. Necessary allocation of funds for implementation of the conservation plan shall be made and the funds so allocated shall be included in the project cost. A copy of action plan shall be submitted to the Regional Office of the Ministry of Environment and Forests, Chandigarh.
(xxiv) The Mining Officer shall submit within 3 months their policy towards
Corporate Environment Responsibility which should inter-alia address (i) Standard operating process/ procedure to bring into focus any infringement/deviation/violation of environmental or forest norms/
161
conditions, (ii) Hierarchical system or Administrative order of the company to deal with environmental issues and ensuring compliance of EC conditions and (iii) System of reporting of non compliance/violation of environmental norms to the Board of Directors of the company and/or stakeholders or shareholders.
(xxv) Vehicles hired to be used for transportation of mined material should be
in good condition and should conform to applicable air and noise emission standards.
(xxvi) Ambient noise levels should conform to prescribed standards both
during day and night. Incremental pollution loads on the ambient air and noise quality should be closely monitored.
(xxvii) The Risk assessment and disaster management plan should be
prepared. (xxviii) The Mining Officer shall submit the site plan showing the earmarked
area for storage of mined material. (xxix) The Mining Officer shall ensure that the compensation to the private
land owner (s) for the mined area shall be made as per the prevalent policy of the State Govt.
(xxx) The mining activity shall be done only manually.
(xxxi) The project proponent shall adopt and follow the procedure for
monitoring of sand mining or river bed mining as given in the Appendix-xii of Notification No. S.O. 141 (E) dated 15.01.2016 issued by MoEF & CC for streamlining the process of environmental clearance for mining of minor mineral.
B. General Conditions:
(i) No change in mining technology and scope of working should be made without prior approval of the Ministry of Environment & Forests.
(ii) No change in the calendar plan including excavation, quantum of mineral sand, bajri and boulders (minor mineral) and waste should be made.
(iii) Four ambient air quality-monitoring stations should be established in the
core zone as well as in the buffer zone for RSPM (Particulate matter with size less than 10micron i.e., PM) and NOx monitoring. Location of the stations should be decided based on the meteorological data, topographical features and environmentally and ecologically sensitive targets and frequency of monitoring should be undertaken in consultation with the State Pollution Control Board.
162
(iv) Data on ambient air quality RSPM (Particulate matter with size less than 10micron i.e., PM) & NOx should be regularly submitted to the Ministry of Environment and Forests including its Regional office located at Chandigarh and the Punjab Pollution Control Board / Central Pollution Control Board once in six months.
(v) Fugitive dust emissions from all the sources should be controlled
regularly. Water spraying arrangement on haul roads, loading and unloading and at transfer points should be provided and properly maintained.
(vi) Personnel working in dusty areas should wear protective respiratory
devices and they should also be provided with adequate training and information on safety and health aspects. Occupational health surveillance program of the workers should be undertaken periodically to observe any contractions due to exposure to dust and take corrective measures, if needed.
(vii) A separate environmental management cell with suitable qualified
personnel should be set-up under the control of a Senior Executive, who will report directly to the Head of the Organization.
(viii) The funds earmarked for environmental protection measures should be
kept in separate account and should not be diverted for other purpose. Year wise expenditure should be reported to the Ministry of Environment and Forests and its Regional Office located at Chandigarh.
(ix) The Mining Officer should inform to the Regional Office of the Ministry of
Environment & Forests located at Chandigarh regarding date of financial closures and final approval of the project by the concerned authorities and the date of start of land development work.
(x) The Regional Office of Ministry of Environment & Forests located at Chandigarh shall monitor compliance of the stipulated conditions. The project authorities should extend full cooperation to the officer (s) of the Regional Office by furnishing the requisite data / information / monitoring reports.
(xi) The Mining Officer shall submit six monthly reports on the status of
compliance of the stipulated environmental clearance conditions including results of monitored data (both in hard copies as well as by e-mail) to the Ministry of Environment and Forests, its Regional Office Chandigarh, the respective Zonal Office of Central Pollution Control Board and the State Pollution Control Board. The proponent shall upload the status of compliance of the environmental clearance conditions, including results of monitored data on their website and shall update the same periodically. It shall simultaneously be sent to the Regional Office of the Ministry of Environment and Forests, Chandigarh, the respective Zonal Office of Central Pollution Control Board and the State Pollution Control Board.
163
(xii) A copy of the clearance letter shall be sent by the proponent to concerned Panchayat, Zila Parisad/ Municipal Corporation, Urban Local Body and the Local NGO, if any, from whom suggestions/ representations, if any, were received while processing the proposal. The clearance letter shall also be put on the website of the Company by the proponent.
(xiii) The State Pollution Control Board should display a copy of the clearance
letter at the Regional office, District Industries Centre and the Collector’s office/ Tehsildar’s office.
(xiv) The environmental statement for each financial year ending 31 March in
Form-V as is mandated to be submitted by the project proponent to the concerned State Pollution Control Board as prescribed under the Environment (Protection) Rules, 1986, as amended subsequently, shall also be put on the website of the company along with the status of compliance of environmental clearance conditions and shall also be sent to the Regional Office of the Ministry of Environment and Forests, Chandigarh by e-mail.
(xv) The Mining Officer shall adhere to the commitments made in the
Environment Management Plan and Corporate Social Responsibility. (xvi) The Mining Officer should advertise at least in two local newspapers
widely circulated, one of which shall be in the vernacular language of the locality concerned, within 7 days of the issue of the clearance letter informing that the project has been accorded environmental clearance and a copy of the clearance letter is available with the State Pollution Control Board and also at web site of the Ministry of Environment and Forests at http://envfor.nic.in and a copy of the same should be forwarded to the Regional Office of Ministry of Environment & Forests at Chandigarh.
(xvii) The MoEF/SEIAA or any other competent authority may alter/modify the
above conditions or stipulate any further condition in the interest of environment protection.
(xviii) The SEIAA may cancel the environmental clearance granted to this project under the provisions of EIA Notification, 2006, if, at any stage of the validity of this environmental clearance, it is found/ come to the knowledge of the SEIAA that the project proponent has deliberately concealed and/or submitted false or misleading information or inadequate data for obtaining the environmental clearance.
(xix) The Mining Officer shall demarcate the mining lease area in the
presence of revenue authorities and concerned Village Panchayat or their representatives.
(xx) The Mining Officer shall get the micro chemical analysis of the mined
material done from an approved laboratory once in a year and shall
164
submit the analysis results to the Ministry of Environment & Forests/Punjab Pollution Control Board.
(xxi) The Mining Officer shall ensure that the contractor shall engage people
of local area for mining purpose as far as possible, so as to have opportunities of employment for them.
(xxii) The Mining Officer may apply for transfer of environmental clearance
under EIA notification dated 14.09.2006 to the contractor finalized by the Department of Industries & Commerce to SEIAA, Punjab. However, no activity shall be undertaken by the contractor till the environmental clearance is transferred in his name and he is lawfully bound to comply with the conditions of the environmental clearance.
(xxiii) The monitoring of the mining project in respect of Environment
Management shall be carried out by the State/District Level Environment Management Cells constituted by the Govt. of Punjab vide notifications dated 03.12.2012.
(xxiv) This environmental clearance will be valid for carrying out mining of
minor minerals (sand) only and not for river sand mining.
(xxv) Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under Section 16 of the National Green Tribunal Act, 2010.
(xxvi) The project proponent will plant only those species of plants as mentioned in the 'Guidelines for Plantation of Trees in Green Belt' for different zones of the State, which are available on the website of SEIAA i.e. seiaapunjab.co.in.
******