Procedures
MSC-PRO-WS-27075Hanford Site Public Water System Tie-In
Revision 1, Change 0
Published: 06/05/2014 Effective: 06/05/2014
Topic: Water & Sewer
Subject Matter Expert : Camp, SamuelFunctional Manager: Kon, Jonathan
Use Type: MCP-Management ControlProcedure
*MSAPS.MSC-PRO-WS-27075*
![Page 2: Procedure - Hanford Site Mission Support Contract Hanford Site Public Water System Tie-In ... NOTE: Process flow diagram is provided as Appendix B. Actionee Step Action](https://reader031.vdocuments.us/reader031/viewer/2022030418/5aa4d0f67f8b9a185d8c85b2/html5/thumbnails/2.jpg)
JHA: Periodic Review Due Date: 06/05/2019 Publication Correction: 05/22/2017 Rev. 1, Chg. 0 USQ Screen Number:
CHANGE SUMMARY
Description of Change
Revise process to add steps that ensure the project documents that allrequirements are met and inspections are performed prior to approving waterservice tie-ins to the Hanford Public Water System.
Add process flow diagram as Appendix B.
Publication corrections:4/10/17, update to MSAPS numbers7/13/16, Reassign FM per management review
Before each use, ensure this copy is the most current version. MCP-Management Control Procedure Use
Rev. 1, Chg. 0 MSC-PRO-WS-27075 Page i of i
Hanford Site Public Water System Tie-In Published Date: 06/05/14 MSC-PRO-WS-27075 Effective Date: 06/05/14
![Page 3: Procedure - Hanford Site Mission Support Contract Hanford Site Public Water System Tie-In ... NOTE: Process flow diagram is provided as Appendix B. Actionee Step Action](https://reader031.vdocuments.us/reader031/viewer/2022030418/5aa4d0f67f8b9a185d8c85b2/html5/thumbnails/3.jpg)
Hanford Mission Support Contract
Hanford Site Public Water System Tie-In
MSC-PRO-WS-27075, Rev. 1 Effective Date: June 5, 2014 Page 1 of 11
NOTE: Before each use, check MSC Docs Online to ensure this copy is current.
CHANGE SUMMARY
Rev 1
Description of Change:
Revise process to add steps that ensure the project documents that all requirements are met and
inspections are performed prior to approving water service tie-ins to the Hanford Public Water
System. Add process flow diagram as Appendix B.
![Page 4: Procedure - Hanford Site Mission Support Contract Hanford Site Public Water System Tie-In ... NOTE: Process flow diagram is provided as Appendix B. Actionee Step Action](https://reader031.vdocuments.us/reader031/viewer/2022030418/5aa4d0f67f8b9a185d8c85b2/html5/thumbnails/4.jpg)
Hanford Mission Support Contract
Hanford Site Public Water System Tie-In
MSC-PRO-WS-27075, Rev. 1 Effective Date: June 5, 2014 Page 2 of 11
NOTE: Before each use, check MSC Docs Online to ensure this copy is current.
1.0 PURPOSE
This procedure provides the basic design guidance and requirements for connecting to a Hanford
Site Public Water System. This procedure covers the raw and potable water distribution systems.
2.0 SCOPE
This Level 2 Management Control Procedure is applicable to Mission Support Alliance LLC
(MSA) employees and to other Site Contractors and subcontractors that have a need to obtain
raw or potable water from the Site Public Water System under the jurisdiction and control of
MSA Public Works/Water and Sewer Utilities.
3.0 IMPLEMENTATION
This document is effective upon publication.
4.0 REQUIREMENTS
4.1 General Requirements
NOTE: For the tables in this section under the requirement "type" column, “V” means
verbatim and “I” means interpreted.
# Requirement Type
V or I Source
1. Project Reports/Work Packages shall be submitted and
approved prior to initiating construction/repair activities.
I Washington
Administrative Code
[WAC 246-290-110
(2)]
2. Water Purveyor design reviews will include verification
that all requirements found in the design guidance
documents have been met.
I Washington
Administrative Code
(WAC 246-290-110,
-120)
3. Ensure design documents have been reviewed by the
Washington State Department of Health (WDOH) when
required, comments incorporated, and approval has been
obtained prior to requesting Construction Approval
Authorization for Water Service Tie-In.
I Washington
Administrative Code
(WAC 246-290-110)
![Page 5: Procedure - Hanford Site Mission Support Contract Hanford Site Public Water System Tie-In ... NOTE: Process flow diagram is provided as Appendix B. Actionee Step Action](https://reader031.vdocuments.us/reader031/viewer/2022030418/5aa4d0f67f8b9a185d8c85b2/html5/thumbnails/5.jpg)
Hanford Mission Support Contract
Hanford Site Public Water System Tie-In
MSC-PRO-WS-27075, Rev. 1 Effective Date: June 5, 2014 Page 3 of 11
NOTE: Before each use, check MSC Docs Online to ensure this copy is current.
# Requirement Type
V or I Source
NOTE 1: Involvement of the Purveyor early in the
design process will help identify when WDOH reviews
are needed and avoid project delays due to
unanticipated review requirements.
NOTE 2: When WDOH approval is required allow,
adequate time to develop the Project Report and Design
documentation, reviews, MSA transmittal to DOE, DOE
transmittal to WDOH, and WDOH review/approval.
4. Water Purveyor approval is required on all documents
associated with the Hanford Water System that prescribe
activities, including construction projects and facilities
modifications, with potential to affect potable water or
raw water systems, including waste or hazardous
systems that cross or come near a potable system. These
documents include, but are not limited to: Statements of
Work, Facility Modification Permits (FMP), Design
Change Notices (DCN), Work Documents, Project
Completion Reports, etc.
I MSC-PRO-8635,
Appendix A
5. Ensure the design from service connections from the
water main to a building comply with the Uniform
Building Code and the Uniform Plumbing Code.
I Revised Code of
Washington (RCW)
19.27, 36.32.120(7),
36.43
6. Ensure all design drawings, Facility Modification
Packages, Engineering Change Notices, and
Specifications for any water systems are stamped by a
Washington State Licensed Professional Engineer.
I WAC 246-290-
120(5)
7. Ensure design documentation includes the requirement
to use only lead-free NSF listed materials for potable
water lines and appurtenances.
I WAC 246-290-220
8. Ensure design documentation includes the requirement
to use UL Listed or FM approved materials related to
fire protection systems.
WAC 246-290-200
![Page 6: Procedure - Hanford Site Mission Support Contract Hanford Site Public Water System Tie-In ... NOTE: Process flow diagram is provided as Appendix B. Actionee Step Action](https://reader031.vdocuments.us/reader031/viewer/2022030418/5aa4d0f67f8b9a185d8c85b2/html5/thumbnails/6.jpg)
Hanford Mission Support Contract
Hanford Site Public Water System Tie-In
MSC-PRO-WS-27075, Rev. 1 Effective Date: June 5, 2014 Page 4 of 11
NOTE: Before each use, check MSC Docs Online to ensure this copy is current.
# Requirement Type
V or I Source
9. Ensure design documentation includes all American
Water Works Association (AWWA) material
specifications and construction requirements.
I WAC 246-290-200
10. Ensure design documentation for potable water piping
includes the requirement to conform to
AWWA C651-05 Disinfection Water Mains (latest
edition) in the disinfection plan, and that plan is
provided for review as part of the request for Water
Service Request, Site Form A-6004-007.
I WAC 246-290-451
11. Ensure the design for fire protection systems that use
potable water have an approved backflow prevention
assembly, commensurate with the degree of hazard
assigned by the Site Water Purveyor designated Cross
Connection Control Specialist (CCCS).
I WAC 246-290-490
12. Ensure the design for fire protection systems that use
raw water have an approved backflow prevention
assembly commensurate with the degree of hazard
assigned by the Site Water Purveyor designated CCCS.
I WAC 246-290-135,
490
NOTE: Water Purveyor is identified on the
Environmental Integration Services, Subject Matter
Expert and Point-of-Contact List, found on the MSA
Environmental Integration Services website under
“Quick Links.”
13. Hanford Site contractors shall negotiate agreements for
water utility service
I MSC Contract (DE-
AC06-09RL14728),
Section J.3,
Interface Number 42
14. Construction Completion Reports shall be submitted per
the direction on the WDOH approval letter.
I WAC 246-290-
120(5)
![Page 7: Procedure - Hanford Site Mission Support Contract Hanford Site Public Water System Tie-In ... NOTE: Process flow diagram is provided as Appendix B. Actionee Step Action](https://reader031.vdocuments.us/reader031/viewer/2022030418/5aa4d0f67f8b9a185d8c85b2/html5/thumbnails/7.jpg)
Hanford Mission Support Contract
Hanford Site Public Water System Tie-In
MSC-PRO-WS-27075, Rev. 1 Effective Date: June 5, 2014 Page 5 of 11
NOTE: Before each use, check MSC Docs Online to ensure this copy is current.
5.0 PROCESS
NOTE: Process flow diagram is provided as Appendix B.
Actionee Step Action
Requestor 1. Complete and provide Water Service Request, requester information
section of Site Form A-6004-007, and conceptual design scope
document (functional design, work package, statement of work, etc.)
to the Water Purveyor for a determination of the need for WDOH
approval prior to the commencement of project work.
Water
Purveyor
2. Determine if the conceptual design submitted will require a project
report submittal to the WDOH.
If no, proceed to Step 7.
If yes, request customer to develop and submit a project report for
Water Purveyor review, approval and submittal to DOE-RL/WDOH
for approval.
a. Ensure all drawings and specifications affecting tie-in approvals
are complete and have been approved by the Water Purveyor.
b. Ensure the project report satisfies the requirements and addresses
all elements required for project reports.
c. Ensure design documents have been reviewed and/or approved
by the Hanford Site Fire Marshal’s office where appropriate.
d. Provide comments to Requestor for resolution, if necessary.
Requestor 3. Submit the Project Report and Design Package to the Water Purveyor
for submittal to the WDOH for review and approval.
NOTE: Projects should allow 30 days for internal processing and
60 days for Department of Health review and approval.
Water
Purveyor
4. If comments are received from the WDOH, forward to Requester for
resolution and resubmit to the Department of Health when comments
have been incorporated.
Requestor 5. Resolve comments and incorporate WDOH comments and complete
design documents.
Water
Purveyor
6. When project approval is received from WDOH, complete and sign
Water Service Request, Part A of Site Form A-6004-007.
![Page 8: Procedure - Hanford Site Mission Support Contract Hanford Site Public Water System Tie-In ... NOTE: Process flow diagram is provided as Appendix B. Actionee Step Action](https://reader031.vdocuments.us/reader031/viewer/2022030418/5aa4d0f67f8b9a185d8c85b2/html5/thumbnails/8.jpg)
Hanford Mission Support Contract
Hanford Site Public Water System Tie-In
MSC-PRO-WS-27075, Rev. 1 Effective Date: June 5, 2014 Page 6 of 11
NOTE: Before each use, check MSC Docs Online to ensure this copy is current.
Actionee Step Action
Water
Purveyor
7. Develop Construction Approval Authorization for Water Service
Tie-In, Part B of Water Service Request Site Form A-6004-007, as
follows:
a. Assign a request number for each request.
b. Review project approval documents and identify any special
conditions or requirements.
c. Identify conditions or requirements to be satisfied prior to
providing authorization to proceed with construction and or final
authorization to tie-in to existing utility’s systems.
d. Review Construction Approval Authorization for Water System
Tie-In Request, Part B of Water Service Request Site Form
A-6004-007, with requester.
Requestor 8. Sign Construction Approval Authorization for Water System Tie-In
Request form, Part B of Water Service Request Site Form A-6004-007
acknowledging understanding of conditions and requirements.
Water
Purveyor
9. Sign Construction Approval Authorization for Water System Tie-In
Request form, Part B of Water Service Request Site Form
A-6004-007, authorizing construction activities to proceed.
Requestor 10. Submit design changes made after the Construction Approval
Authorization for Water Service Tie-In Request, Part B of Water
Service Request Site Form A-6004-007, to the Site Water Purveyor for
approval prior to implementing change via MSC review and approval
process. Use Site Form A-6002-913, MSC Comment Resolution Sheet
in accordance with MSC-PRO-8635.
NOTE: Design changes made without Water Purveyor review and
approval may invalidate the tie-in approval and if so, the approval will
be suspended and construction activities may be stopped.
CCCS 11. Review design changes that potentially affect tie-in approvals and
ensure approval remains valid in accordance with previous steps.
NOTE: Design changes, not requiring additional WDOH review, will
have a disposition in a timely manner, but no longer than 7 days from
the design change submittal.
Requester 12. Notify Water Purveyor whenever construction is completed on those
portions of the system requiring inspection as identified in the
construction approval.
![Page 9: Procedure - Hanford Site Mission Support Contract Hanford Site Public Water System Tie-In ... NOTE: Process flow diagram is provided as Appendix B. Actionee Step Action](https://reader031.vdocuments.us/reader031/viewer/2022030418/5aa4d0f67f8b9a185d8c85b2/html5/thumbnails/9.jpg)
Hanford Mission Support Contract
Hanford Site Public Water System Tie-In
MSC-PRO-WS-27075, Rev. 1 Effective Date: June 5, 2014 Page 7 of 11
NOTE: Before each use, check MSC Docs Online to ensure this copy is current.
Actionee Step Action
CCCS 13. Perform inspections and notify requester of any noted deficiencies.
Requester 14. Review Water Service Tie-In Approval Request, Part C of Water
Service Request Site Form A-6004-007, and submit with applicable
documents to the Water Purveyor.
Water
Purveyor
15. Perform final inspection of the system and review construction
approval to ensure approval conditions/requirements have been
completed.
16. Approve tie-in by completing and signing Water Service Tie-In
Approval Request, Part C of Water Service Request Site Form
A-6004-007.
Requestor 17. Conduct system tie-in work in accordance with MSC-PRO-12115,
Work Management.
Water
Purveyor
18. Request the Requester to submit Construction Completion Report
prior to authorizing use of the system.
Requester 19. Submit Construction Completion Report to Water Purveyor.
Water
Purveyor
20. Submit Construction Completion Report to WDOH.
21. Provide approval for use by completing Water Service Use Approval,
Section D of Water Service Request Site Form A-6004-007.
22. Notify Requester that system is authorized for use.
6.0 FORMS
Form A-6004-007, Water Service Request
Form A-6002-913, MSC Comment Resolution Sheet
![Page 10: Procedure - Hanford Site Mission Support Contract Hanford Site Public Water System Tie-In ... NOTE: Process flow diagram is provided as Appendix B. Actionee Step Action](https://reader031.vdocuments.us/reader031/viewer/2022030418/5aa4d0f67f8b9a185d8c85b2/html5/thumbnails/10.jpg)
Hanford Mission Support Contract
Hanford Site Public Water System Tie-In
MSC-PRO-WS-27075, Rev. 1 Effective Date: June 5, 2014 Page 8 of 11
NOTE: Before each use, check MSC Docs Online to ensure this copy is current.
7.0 RECORD IDENTIFICATION
Records Capture Table
Name of Document Submittal
Responsibility
Retention
Responsibility
Water Service Request, Site Form A-6004-007
Project Report and Design Package (if applicable)
Construction Completion Report
Requestor Water & Sewer
Utilities
Completed and Signed Water Service Request, Site
Form A-6004-007
Water Purveyor Water & Sewer
Utilities
Construction Completion Report Water Purveyor WDOH
8.0 REFERENCES
8.1 Source References
MSC Contract (DE-AC06-09RL14728), Section J.3, Interface Number 42
MSC-PRO-8635, Review and Approval of Technical Documents
RCW 19.27, State Building Code
RCW 36.32.120(7), Adoption of Building, Electrical Codes, etc.
RCW Chapter 36.43, Building Codes
Washington Administrative Code (WAC) 246-290, -291, -292, -294
8.2 Working References
American Water Works Association (AWWA)
CRD O 420.1A (Supp Rev. 2)
MSC-IMP-00001, Hanford Site Interface Management Plan
MSC-PRO-589, Mission Support Contract Management System Documents
MSC-PRO-12115, Work Management
National Fire Protection Association (NFPA)
National Sanitation Foundation (NSF)
Latest edition of the PNWS-AWWA Cross-Connection Control Manual, or the University of
Southern California (USC) Manual of Cross-Connection Control
Recommended Standards for Water Works, A Committee Report of the Great Lakes – Upper
Mississippi River Board of State Public Health and Environmental Managers
Uniform Plumbing Code (UPC)
U0-A-00.63, MSC Water Systems Requirements Matrix
Washington State Department of Ecology Criteria for Sewage Works Design
Washington State Department of Health Water System Design Manual (WSDM)
![Page 11: Procedure - Hanford Site Mission Support Contract Hanford Site Public Water System Tie-In ... NOTE: Process flow diagram is provided as Appendix B. Actionee Step Action](https://reader031.vdocuments.us/reader031/viewer/2022030418/5aa4d0f67f8b9a185d8c85b2/html5/thumbnails/11.jpg)
Hanford Mission Support Contract
Hanford Site Public Water System Tie-In
MSC-PRO-WS-27075, Rev. 1 Effective Date: June 5, 2014 Page 9 of 11
NOTE: Before each use, check MSC Docs Online to ensure this copy is current.
APPENDIX A
Special Terms
Service connection A water line that provides water to one building. A service connection
may provide water for fire protection, domestic use, or a combination
of both in the same building. A service connection can also provide
water to a fire hydrant, truck fill station, or special purpose facility.
Water main A water line that provides water to more than one independent facility
or service connection regardless of size.
![Page 12: Procedure - Hanford Site Mission Support Contract Hanford Site Public Water System Tie-In ... NOTE: Process flow diagram is provided as Appendix B. Actionee Step Action](https://reader031.vdocuments.us/reader031/viewer/2022030418/5aa4d0f67f8b9a185d8c85b2/html5/thumbnails/12.jpg)
Hanford Mission Support Contract
Hanford Site Public Water System Tie-In
MSC-PRO-WS-27075, Rev. 1 Effective Date: June 5, 2014 Page 10 of 11
NOTE: Before each use, check MSC Docs Online to ensure this copy is current.
APPENDIX B Process Flow
Start
Water Purveyor:Will Conceptual Design require Project Report submittal to WDOH?
Yes
Water Purveyor:Approve Project
Report?No
Yes
WDOH:Approve Project?
60 Days
Water Purveyor:Forward comments
to Requestor for resolution
No
Requestor:Develop Project
Report and Design Package
Requestor:Submit Project
Report to Water Purveyor for review
30 Days
Water Purveyor:Submit Project
Report to WDOH
Requestor:Resolve/Incorporate
WDOH comments and complete design
documents
Water Purveyor:Assign a permit
number for each request
Water Purveyor:Review project
approval documents and identify any
special conditions or requirements
Water Purveyor:Identify conditions or
requirements to be satisfied prior to providing authorization
to proceed with construction and or final authorization to tie-
in to existing utility’s systems
Go To “Begin Construction”
Requestor:Complete Water Service
Request, Requestor Information Section of Site Form A-6004-007.
Submit form and conceptual design scope
document to Water Purveyor
Water Purveyor:Develop Construction
Approval Authorization for Water Service Tie-In, Section B of Site Form A-6004-007, Water Service
Request
No
Yes
Water Purveyor:Review Construction
Approval Authorization for Water System Tie-In
Request, Section B of Site Form A-6004-xx1, Water
Service Request
Requestor:Sign Construction Approval
Authorization for Water System Tie-In Request,
Section B of Site Form A-6004-007, Water Service Request, acknowledging
understanding of conditions and requirements
Water Purveyor:Sign Construction Approval
Authorization for Water System Tie-In Request,
Section B of Site Form A-6004-007, Water Service
Request, authorizing construction activities to
proceed
Water Purveyor:Complete and sign Water Service Request, Section A of Site Form A-6004-007,
Water Service Request
![Page 13: Procedure - Hanford Site Mission Support Contract Hanford Site Public Water System Tie-In ... NOTE: Process flow diagram is provided as Appendix B. Actionee Step Action](https://reader031.vdocuments.us/reader031/viewer/2022030418/5aa4d0f67f8b9a185d8c85b2/html5/thumbnails/13.jpg)
Hanford Mission Support Contract
Hanford Site Public Water System Tie-In
MSC-PRO-WS-27075, Rev. 1 Effective Date: June 5, 2014 Page 11 of 11
NOTE: Before each use, check MSC Docs Online to ensure this copy is current.
APPENDIX B Process Flow (Continued)
Requestor:Design changes
needed?
Requestor:Submit design
changes to Water Purveyor prior to
implementing change
Yes
Water Purveyor:Review design changes that
potentially affect tie-in approvals and ensure
approval remains valid in accordance with previous
steps
7 Days
WDOH:Approval needed
for design changes?
Water Purveyor:Submit design
changes to WDOH
Yes
Requestor:Notify Water Purveyor of construction
completion for portions requiring
inspection
No
No
WDOH:Approve design
changes?YesNo
Water Purveyor:Perform inspections
Water Purveyor:Perform final inspection
of the system and review construction approval to
ensure approval conditions/requirements
have been completed
Requester:Conduct system tie-
in in accordance with MSC-PRO-
12115 Work Management
Water Purveyor:Request the
Requestor to submit Construction
Completion Report prior to
authorization of use of the system
Requestor:Submit Construction Completion Report to Water Purveyor
Water Purveyor:Submit Construction Completion Report
to WDOH
Water Purveyor:Notify Requestor
that system is authorized for use
End
Water Purveyor:Are there
deficiencies?
Water Purveyor:Notify Permit Requestor of deficiencies
Yes
Begin Construction
Requestor:Review Water Service Tie-
In Approval Request, Section C of Site Form A-6004-007, Water Service
Request, and submit applicable documents to
Water Purveyor
No
Water Purveyor:Approve tie-in by
signing Water Service Tie-In Approval
Request, Section C of Site Form A-6004-007, Water Service Request
Water Purveyor:Provide approval for use
by completing Water Service Use Approval,
Section D of Site Form A-6004-007, Water Service
Request