prince william county service authority · local prince william county landfill mou ... alternate...

23
Maureen O’Shaughnessy Prince William County Service Authority

Upload: dangnguyet

Post on 13-Aug-2019

213 views

Category:

Documents


0 download

TRANSCRIPT

Maureen O’Shaughnessy Prince William County Service Authority

Overview Facility Description

Operational Flexibility Liquids: Nitrogen Removal Power Solids

Summary

H.L. MooneyAdvanced Water Reclamation Facility (AWRF)

Preaeration

Featherstone Pump

Station

NeabscoPump

Station

Odor Control

Screening & Grit Removal

Equalization Basins

Activated Sludge

Nitrogen Removal

Denitrification/ Final Filters

Ultraviolet Irradiation

Cascade Aeration

Fluidized Bed

Incinerator

Ash Settling Drying

Effluent toNeabsco

Creek

Centrifuge Dewatering

Secondary Clarifiers

Gravity Thickenin

g

Sludge Holding

Primary Clarifiers

CEPT

RASFerric Lime

MeOH

1/28/2015

Polymer

Lime

Polymer

To Atmosphere

Hypochlorite

Landfill

Ash

Landfill

H.L. Mooney Plant

Solids Incineration

Biological Treatment

UV

Cascade Aeration

Primary Settling

Screens and GritAsh Flow

Equalization

FiltersFilters

HL Mooney AWRFRecent Changes

Expansion from 18 to 24 MGD

Enhanced Nutrient Removal Total effluent nitrogen from 8 to 3 mg/L (Annual) Total P remains at 0.18 mg/L (Monthly) Lower QL for CBOD5 2 mg/L

MACT Sewage Sludge Incinerator (SSI) Rule Mercury and Cadmium

Upgrades to achieve 24 mgd and Regulatory Requirements

New Screens and Grit removal

New step-feed BNR basins & secondary clarifiers

Denitrification filter expansion and methanol addition automation

Gravity thickener expansion

Dewatering expansion – 3rd centrifuge & pump

Chemical systems for nutrient removal

Electrical upgrades

Control upgrades – new Supervisory Control and Data Acquisition (SCADA)

Incinerator New Mercury Scrubber and WESP

Defining Flexibility of Design “Designs that can adapt when external changes occur”

Wikapedia for Engineering Flexibility

“Flexibility is a complex, multidimensional concept that refers to an organization's ability to respond to uncertainty in its environment. “

De Groote X. The flexibility of production processes: a general framework. Management Science. 1994;40(7):933–945

Operational flexibility is “…the ability to change or react with little penalty in time, effort, cost or performance.”

Upton DM. The Management of Manufacturing Flexibility. Calif Manage Rev Win. 1994;36(2):72–89.

Flexible and RobustFlexibility

Ability to respond to change by taking appropriate action (Mandelbaum, 1978)

Modular capacity

Designs that can adapt to external changes

Thought to have lower present cost, however adding flexibility can increase present cost.

Robustness The innate capacity to function

well in more than one state (Mandelbaum, 1978)

Large, reserve capacity

Designs that endure external changes.

Thought to have higher present cost and lower future cost

“Prevention rather than cure”

Increase System Robustness by containing Flexible elements

Liquids Treatment

Biological Treatment

Filters

H.L. Mooney ENR Process

Return Activated Sludge

Waste Activated Sludge to Gravity

Thickeners

Process Air

Aerobic Zones 5 –

9

Aerobic Zone 10

Aer. Zone 12

Primary Effluent

Swing Zone 4

Anoxic Zones 1-

3

Swing Zone 11

Internal Nitrate Recycle

Lime

Methanol

Return Activated Sludge

Waste Activated Sludge to Gravity

Thickeners

Process Air

Aerobic Zones 5 –

9

Aerobic Zone 10

Aer. Zone 12

Primary Effluent

Swing Zone 4

Anoxic Zones 1-

3

Swing Zone 11

Internal Nitrate Recycle

Lime

Methanol

1) 4-Stage Bardenpho – Effluent TN < 3 mg/L

2) MLE Process - Effluent TN < 8 mg/L

Denitrification Filters

Denitrification Filters1) Denitrification Filter:

– with methanol2) Conventional Filter

- without methanol

Two ChemScan units- Operate side by side- Reduce risk:

- Methanol overdose- Permit violation- CBOD5 QL 2 mg/L

Liquids Operational FlexibilityDesign Conditions: 24 mgdMLE + Denitrification Filters

Current Operating Conditions: 4-stage Bardenpho + Conventional Filters- Simpler to operate one control point for nitrogen- Reduces risk of permit violation due to

methanol overdose- Simpler filter operation

Liquids Treatment – Test Train

Test Train ModificationsD

O =

hig

h se

tpoi

ntfr

om m

odel

DO = high setpoint from model

Install NH3 probe (ISE?)

NH3 reading controls DO setpoint

NH3 reading controls DO setpoint

NH3 reading controls DO setpoint

Can mixers be run during aeration? Evaluate low DO mixing

options for this zone (rolling aeration)

Install DO probe (LDO?)

Reduce methanol feed

Change NRCY rate and/or intake?

Try alternative configurations before implement in other tanks

Stand-by Generators2.5 MW each

2 diesel generators each can operate plant

2 power feeds into the plant from separate substations

A third generator for UV Disinfection

Note: both feeds have been lost and generators were needed!

FBI

Full load: 2200 to 2800 dry

pounds per hour (up to 45 dry tons/day)

Existing Emission Controls: Venturi and

Impingement tray scrubber

Solids Treatment

WESP (Cd)

Caustic Addition(SO2)

Mercury Scrubber

Ammonia(NOx) not installed

Solids Treatment Upgrade for MACT SSI

Biosolids ChangesBTU/lb increasing - capacity

Solids Flexibility – FBI Backup FBI down for maintenance ~1 month/year

2011 – Landfills rejected hauled dewatered cake due to ODORS

Approach: Expanded Options for Solids

Regulatory: Added land application of lime stabilized solids to our VPDES permit by piloting a Bioset Lime Stabilization Unit

External Options: Added more destinations to reduce reliance on large landfills Off-site incineration at Hopewell Regional Facility Local Prince William County Landfill MOU Discussions with local composting facilities

H.L. Mooney AWRF Solids Management

Incineration

Land Application

Off-site Incinerator

Landfill Disposal

Biosolids(Class B, Class A)

Ash (~90% wt reduction)

Dewatered Cake

Lime Stabilization

Other Process? (future evaluation)

Centrifuge Dewatering

Current Incinerator Back-up

Alternate Incinerator Back-up

Summary

Regulatory and capacity changes lead to 12 years of construction projects affecting all aspects of the plant.

Implemented flexible operational strategy: Uncertainty in regulatory environment Uncertainty in flows, loads, rate of growth

Expanded solids options in permit and building a “menu” of destinations. Uncertainty in future regulations affecting incineration Many options increase reliability beyond that of individual

off-site destinations

Thank you!Maureen O’Shaughnessy

[email protected]