1 LEARN PRIMA LEARN PRIMA LEARN PRIMA LEARN PRIMAVERA IN 1 DA VERA IN 1 DA VERA IN 1 DA VERA IN 1 DAY (FOR PROJECT MANAGERS) Y (FOR PROJECT MANAGERS) Y (FOR PROJECT MANAGERS) Y (FOR PROJECT MANAGERS) Exercise No: 1 1. Create Main Project Project Group/Project Name: HIW1 Project Title: Highway Widening Number Version: Construction Company Name: C.M. Construction, Inc. Planning Unit: Day Decimal Places: 2 Project start Date: 24 th Sept, 2006 2. Create Sub Projects Project Name: PHS1 Project Title: Phase 1 – Southbound Company Name: C.M. Construction, Inc. Project ID: P1 Add this new project to a project group: HIW1 Project Name: PHS2 Project Title: Phase 2 - Northbound Company Name: C.M. Construction, Inc. Project ID: P2 Add this new project to a project group: HIW1 3. Create WORK BREAKDOWN STRUCTURE for HIY1 - Highway Widening (as shown in table) Enter Activities under the above WBS - refer to the WBS sheet provided to you. A Construction A.01 General A.01.0 Overhead A.01.5 Construction Facilities A.01.7 Contract Closeout A.02 Site Work A.02.1 Site Preparation A.02.1.100 Site Clearing A.02.1.200 Removals A.02.1.600 Underpinning A.02.2 Earthwork A.02.2.200 Excavation & Backfill A.02.2.700 Erosion Control A.02.2.800 Grading A.02.5 Paving & Resurfacing A.02.5.100 Asphaltic Concrete Pavement A.02.5.400 Surfacing A.02.7 Sewerage & Drainage A.02.7.100 Subdrainage Systems A.03 Concrete A.03.3 Cast-In-Place Concrete A.03.3.100 Structural Concrete A.16 Electrical A.16.7 Electrical Utilities A.16.7.100 Electrical Utilities B Traffic Control B.01 General B.01.5 Construction Facilities & Temp. Controls B.01.5.300 Barriers & Enclosures B.01.5.500 Access Roads B.01.5.800 Project Signs B.02 Site Work B.02.8 Site Improvements B.02.8.400 Walk/Road/Parking Appurtenances

Upload: rama24x7

Post on 18-Dec-2014

1.807 views

Category:

Education


3 download

DESCRIPTION

Primavera Project Planner

TRANSCRIPT

Page 1: Primavera 3

1

LEARN PRIMALEARN PRIMALEARN PRIMALEARN PRIMAVERA IN 1 DAVERA IN 1 DAVERA IN 1 DAVERA IN 1 DAY (FOR PROJECT MANAGERS)Y (FOR PROJECT MANAGERS)Y (FOR PROJECT MANAGERS)Y (FOR PROJECT MANAGERS)

Exercise No: 1 1. Create Main Project

Project Group/Project Name: HIW1 Project Title: Highway Widening Number Version: Construction Company Name: C.M. Construction, Inc. Planning Unit: Day Decimal Places: 2 Project start Date: 24th Sept, 2006

2. Create Sub Projects

Project Name: PHS1 Project Title: Phase 1 – Southbound Company Name: C.M. Construction, Inc.

Project ID: P1 Add this new project to a project group: HIW1

Project Name: PHS2 Project Title: Phase 2 - Northbound Company Name: C.M. Construction, Inc.

Project ID: P2 Add this new project to a project group: HIW1 3. Create WORK BREAKDOWN STRUCTURE for

HIY1 - Highway Widening (as shown in table)

Enter Activities under the above WBS - refer to the WBS sheet provided to you.

A Construction A.01 General A.01.0 Overhead A.01.5 Construction Facilities A.01.7 Contract Closeout A.02 Site Work A.02.1 Site Preparation A.02.1.100 Site Clearing A.02.1.200 Removals A.02.1.600 Underpinning A.02.2 Earthwork A.02.2.200 Excavation & Backfill A.02.2.700 Erosion Control A.02.2.800 Grading A.02.5 Paving & Resurfacing A.02.5.100 Asphaltic Concrete Pavement A.02.5.400 Surfacing A.02.7 Sewerage & Drainage A.02.7.100 Subdrainage Systems A.03 Concrete A.03.3 Cast-In-Place Concrete A.03.3.100 Structural Concrete A.16 Electrical A.16.7 Electrical Utilities A.16.7.100 Electrical Utilities

B Traffic Control B.01 General B.01.5 Construction Facilities & Temp. Controls B.01.5.300 Barriers & Enclosures B.01.5.500 Access Roads B.01.5.800 Project Signs B.02 Site Work B.02.8 Site Improvements B.02.8.400 Walk/Road/Parking Appurtenances

Page 2: Primavera 3

2

Page 3: Primavera 3

3

Page 4: Primavera 3

4

Page 5: Primavera 3

5

Page 6: Primavera 3

6

Exercise No: 2 (Please continue from the Exercise No: 1)

Creating Project Calendar (Data -����Calendar����Base Calendar) Base Calendar

1. Create a Base calendar with 5 days work week 2. Mark 1st May – repeating as holiday in the base calendar 3. Click on Standard to title the calendar and mark the working and non working week days for the base calendar.

Global Calendar

1. Mark 26th Jan and 15th Aug as repeating global holidays. 2. Mark two months starting from July and August (repeating) of Monsoon as non-working period with the exception from 16

th August to

25th August, repeating. 3. Click on Standard to mark the following in the global calendar

a. Week start day, b. Calendar start date – a date to from which the calendar will begin (usually calendars are started from one month before the

start date of the project). c. Project start date and imposed project finish date (you might have already entered these dates while creating projects.

They can be changed here) d. Data date to change the date on which progress is recorded.

Enter Duration and Relationship

Activity ID

Activity description

Original duration

Predecessor Connector + Lag

P1G098 BEGIN PROJECT 0

P1G100 MOBILIZATION 4 P1G098 FS

P1G105 CLEAR SITE 4 P1G098 FS

P1G110 GENERAL CONDITIONS 13 P1G100 , P1G105 FS, FS

P1N1140 PLACE TEMP. MARKING TAPE 1 P1G100 , P1G105 FS, FS

P1N1145 PLACE TEMP. CONST. BARRIER 1 P1N1140 FS

P1N1150 EXCAVATE 5 P1N1145 FS

Page 7: Primavera 3

7

P1N1170 PLACE AGGREGATE & ASPHALT BASE COURSE 6 P1N1150 FS

P1N1202 CONSTRUCT TEMP. BENT #1 & #2 20 FS

P1N1180 REMOVE TEMP. CONST. BARRIER 1 P1N1170 FS

P1N1185 PLACE 2" SURFACE COURSE 3 P1N1180 FS

P1N1190 DIVERT TRAFFIC ONTO TEMP. ROAD 1 P1N1185 , P1N1202 FS, FS

P1N1195 REMOVE TEMP. MARKING TAPE 1 P1N1190 FS

P1N1200 PLACE CONST. BARRIER & TEMP. STRIPING RAMP 4 P1N1195 FS

P1N1210 EXCAVATE RAMP & INSTALL 15" RCP PIPE WITH INLETS 10

P1N1200 FS

P1N1220 PLACE AGGREGATE & ASPHALT BASE COURSE 4 P1N1210 FS

P1G200B PROCUREMENT OF ESW/SL SIGNS 10 P1N1210 FS

P1N1230 PLACE 2" SURFACE COURSE 3 P1N1220 FS

P1NP200C PROCUREMENT OF SIGN STRUCTURES 10 P1G098 FS

P1N1235 REMOVE TEMP. CONSTR. BARRIER 1 P1N1230 FS

P1N1240 PLACE TEMP. STRIPING & DIVERT TRAFFIC 1 P1N1235 FS

P1NP100A PROCUREMENT OF NOISE BARRIER POST & PANELS 10

P1G098 FS

P1N2100 PLACE CONST. BARRIER 12 P1G098, P1N1210 FS, FS

P1N2190 INSTALL SIGN SUPPORT STRUCTURE 8 P1G200B, P1NP200C FS, FS

P1N2195 ERECT SIGNS 3 P1N2190 FS

P1N2115A GRUB & STRIP TOPSOIL 8 P1N2100 FS

P1N2105B INSTALL EROSION CONTROL DEVICES 15 P1N2100, P1N2115A FS, FS

P1N2200 INSTALL TEMP. SHEETING 12 P1N2105B ,P1N2115A FS, FS

Page 8: Primavera 3

8

P1N2210 EXCAVATE RETAINING WALL 12 P1N2200 FS

P1N2220 CONSTRUCT FOOTING 27 P1N2210 FS

P2N2115B REMOVE GUIDE RAIL 4 P1N2210 FS

P2N2125B INSTALL TEMP. ELECTRICS 15 P2N2115B FS

P2N2125A EXCAVATE FOR ELECTRICAL 10 P2N2115B FS

P2N3100 PLACE TEMP. CONST. BARRIER 6 P2N2115B FS

P2N3110 REMOVE TEMP. PAVEMENT 9 P2N3100 FS

P2N3225A REMOVE TEMP. CONST. BARRIER 5 P2N3100 FS

P1N2230 CONSTRUCT RETAINING WALL 27 P1N2220 SS

P2N2130 INSTALL ELECTRIC CONDUITS & STRUCTURES 19 P2N2125A , P2N2125B

FS, FS

P2N3120 REGRADE AREA 7 P2N3110 FS

P2N2140 INSTALL POWER & LIGHTING 15 P2N2130 FS

P1N2240 PLACE POUROUS FILL BEHIND WALL 9 P1N2230 FS

P1G5200 CONSTRUCT CONCRETE BARRIER AGAINST WALL 8 P1N2230 FS

P1N2250 BACKFILL RETAINING WALL 7

P1N2240

FS

P2N2150 SUBGRADE PREPARATION 14 P2N2140 FS

P1N2260 CONSTRUCT CONCRETE BARRIER AGAINST WALL 20 P1G5200 , P1N2250

FS, FS

P2N2170 PLACE AGGREGATE & ASPHALT BASE COURSE 10 P2N2115B, P2N2150 FS, FS

P1N2270 CONSTRUCT CONCRETE BARRIER AGAINST WALL 24 P1N2260

SS

P2N2180 PLACE ASPHALT STABILIZED COURSE 12 P2N2170 FS P1N2300 CONSTRUCT CONCRETE BARRIER AGAINST WALL 25 P1N2270 , P1NP100A SS +15, FS

Page 9: Primavera 3

9

P2N2185 PLACE 2" SURFACE COURSE 10 P2N2180

FS

P2N2196 STRIPE ROADWAY 9 P2N2185 FS

P1N2320 CONSTRUCT CONCRETE BARRIER AGAINST WALL 24 P1N2300

SS+15

P2N2198 REMOVE TEMP. BARRIER 4 P2N2196 FS

P1N3200 CONSTRUCT CONCRETE BARRIER AGAINST WALL 20 P1N2320 , P1NP100A SS+15, FS

P1N3220 CONSTRUCT CONCRETE BARRIER AGAINST WALL 6

P1N3200

FS

P1N3225B CONSTRUCT CONCRETE BARRIER AGAINST WALL 6 P1N3220 FS

P2G600 PROJECT COMPLETE 0 P1G110 , P1N3225B FS, FS

1. Schedule the Project: tool --> Schedule or press F9 function key or /click on schedule icon on the desk top. 2. Create the following layouts (hint you may apply filter and save the layout: click on filter icon on the desktop)

• Organized by WBS structure

• Activities on longest path (hint you may apply filter and save the layout: click on filter icon on the desktop)

• Critical activities by early start 3. Create Reports

• Classic Schedule Report - Sort by ES, TF

• Schedule Report - Sort by TF, ES

• Schedule Report - Predecessors

• Schedule Report Sorted By Total Float

• Sixty-Day Lookahead Sorted by Late Start Date Sort on Late Start and Total Float, Selection: Percentage complete Less than 100 (low value) and Early start within range (WR) DD + OD (low value) DD + 60D (high value).

Page 10: Primavera 3

10

Exercise No: 3 (Please continue from the Exercise No: 2) Activity Codes Dictionary: Allows you to create Activity Codes, Activity ID and Alias Activity codes is used to 1. Define codes that uniquely identify each activity in a project and group activities in similar categories. 2. Classify activities into specific groups such as responsibility, phase, system, or location. The Activity ID 1. Enables you to classify activity IDs in ways that are meaningful within your project. For example, in a project that is part of a group, the

first two characters of each activity ID are reserved for the SUBP (Project ID) code; this enables you to sort and summarize activities based on these codes.

2. Activity IDs can contain up to 10 alphanumeric characters, which can be divided into a maximum of four codes. Activity ID codes can be used for organizing and filtering data in the layout and in tabular reports and graphics.

Aliases Are combined activity codes that enable you to summarize and select activities for tabular reports and graphics at a more specific level than is possible with single codes. An alias is created by combining two to five activity codes or activity ID codes. For example, MNGR = PHASE + DEPARTMENT + RESPONSIBILITY creates an alias for MANAGER.

Create the following Activity Codes Activity Code DESCRIPTION ORDER AREA Area of Roadway Values GC General Construction 1 SNO Southbound Outer Lane 2 NSO Northbound Outer Lane 3 RESP Responsibility

RS Rajesh - Site Project Manager 1 AW Dinesh - Purchasing 2 GG Prakash - Sitework Crew Foreman 3 PR Praveen - Electrical Crew Foreman 4 JM Sameer - Structural Crew Foreman 5

Values

JAM Ramesh - Paving Crew Foreman 6 LANE Lane Closing

NO5 Northbound Lane 5 NO6 Northbound Lane 6

Values

NO7 Northbound Lane 7

Page 11: Primavera 3

11

SO2 Northbound Lane 8 SO3 Southbound Lane 2 SO4 Southbound Lane 4

WORK Type of Work

Values STRT Start-up 1 TRAF Traffic control 2 SIGN Signage 3 EART Earthwork 4 ELEC Electric and power elements 5 PREP Preparatory paving work 6

PAVE Sub surface and paving work 7 CONC Concrete 8 CLSE Closeout 9

Activity ID Codes: SUB Project ID P1 Phase 1 - Southbound P2 Phase 2 - Northbound Alias Codes:

PHS1 = AREA + LANE (AREA + LANE) Assign Activity Codes to Activities as follows

Activity ID Activity description Type of Work

Area of Roadway

Responsibility Lane Closing

P1G098 BEGIN PROJECT STRT GC RS P1G100 MOBILIZATION STRT GC RS P1G105 CLEAR SITE STRT GC GG P1G110 GENERAL CONDITIONS STRT GC RS P1N1140 PLACE TEMP. MARKING TAPE TRAF SNO GG NO7 P1N1145 PLACE TEMP. CONST. BARRIER TRAF SNO GG NO7 P1N1150 EXCAVATE EART SNO GG NO7 P1N1170 PLACE AGGREGATE & ASPHALT BASE COURSE PAVE SNO JAM NO7 P1N1202 CONSTRUCT TEMP. BENT #1 & #2 TRAF SNO GG NO8 P1N1180 REMOVE TEMP. CONST. BARRIER TRAF SNO GG NO7 P1N1185 PLACE 2" SURFACE COURSE PAVE SNO JAM NO7 P1N1190 DIVERT TRAFFIC ONTO TEMP. ROAD TRAF SNO GG NO7

P1N1195 REMOVE TEMP. MARKING TAPE TRAF SNO GG NO7

Page 12: Primavera 3

12

P1N1200 PLACE CONST. BARRIER & TEMP. STRIPING RAMP

TRAF SNO GG NO7

P1N1210 EXCAVATE RAMP & INSTALL 15" RCP PIPE WITH INLETS

EART SNO GG NO7

P1N1220 PLACE AGGREGATE & ASPHALT BASE COURSE PAVE SNO JAM NO7 P1G200B PROCUREMENT OF ESW/SL SIGNS SIGN GC AW

P1N1230 PLACE 2" SURFACE COURSE PAVE SNO JAM NO7 P1NP200C PROCUREMENT OF SIGN STRUCTURES SIGN GC AW P1N1235 REMOVE TEMP. CONSTR. BARRIER TRAF SNO GG NO7 P1N1240 PLACE TEMP. STRIPING & DIVERT TRAFFIC TRAF SNO GG NO7

P1NP100A PROCUREMENT OF NOISE BARRIER POST & PANELS

SIGN GC AW

P1N2100 PLACE CONST. BARRIER TRAF SNO GG NO7 P1N2190 INSTALL SIGN SUPPORT STRUCTURE SIGN GC GG NO5

P1N2195 ERECT SIGNS SIGN GC GG NO5 P1N2115A GRUB & STRIP TOPSOIL EART SNO GG NO7 P1N2105B INSTALL EROSION CONTROL DEVICES EART SNO GG NO7

P1N2200 INSTALL TEMP. SHEETING EART SNO GG NO7 P1N2210 EXCAVATE RETAINING WALL EART SNO GG NO8 P1N2220 CONSTRUCT FOOTING CONC SNO JM NO8

P2N2115B REMOVE GUIDE RAIL EART NSO GG SO4 P2N2125B INSTALL TEMP. ELECTRICS ELEC NSO PR SO4 P2N2125A EXCAVATE FOR ELECTRICAL EART NSO GG SO4

P2N3100 PLACE TEMP. CONST. BARRIER TRAF NSO GG SO3 P2N3110 REMOVE TEMP. PAVEMENT EART NSO GG SO3 P2N3225A REMOVE TEMP. CONST. BARRIER TRAF NSO GG SO3 P1N2230 CONSTRUCT RETAINING WALL CONC SNO JM NO8 P2N2130 INSTALL ELECTRIC CONDUITS & STRUCTURES ELEC NSO PR SO4 P2N3120 REGRADE AREA EART NSO GG SO3 P2N2140 INSTALL POWER & LIGHTING ELEC NSO PR SO4 P1N2240 PLACE POUROUS FILL BEHIND WALL EART SNO GG NO8 P1G5200 CONSTRUCT CONCRETE BARRIER AGAINST WAL CONC SNO JM NO8 P1N2250 BACKFILL RETAINING WALL EART SNO GG NO8 P2N2150 SUBGRADE PREPARATION PAVE NSO JAM SO4 P1N2260 CONSTRUCT CONCRETE BARRIER AGAINST WAL CONC SNO JM NO8 P2N2170 PLACE AGGREGATE & ASPHALT BASE COURSE PAVE NSO JAM SO4

P1N2270 CONSTRUCT CONCRETE BARRIER AGAINST WAL CONC SNO JM NO8

Page 13: Primavera 3

13

P2N2180 PLACE ASPHALT STABILIZED COURSE PAVE NSO JAM SO4

P1N2300 CONSTRUCT CONCRETE BARRIER AGAINST WALL

CONC SNO JM NO8

P2N2185 PLACE 2" SURFACE COURSE PAVE NSO JAM SO4 P2N2196 STRIPE ROADWAY TRAF NSO GG SO4

P1N2320 CONSTRUCT CONCRETE BARRIER AGAINST WALL

CONC SNO JM NO8

P2N2198 REMOVE TEMP. BARRIER TRAF NSO GG SO4

P1N3200 CONSTRUCT CONCRETE BARRIER AGAINST WALL

CONC SNO JM NO8

P1N3220 CONSTRUCT CONCRETE BARRIER AGAINST WALL

CONC SNO JM NO8

P1N3225B CONSTRUCT CONCRETE BARRIER AGAINST WALL

CONC SNO JM NO8

P2G600 PROJECT COMPLETE CLSE GC RS

Create following layout 1. Grouped by Work Type/ Area of Road/Responsibility 2. Grouped by WBS / Responsibility 3. PERT Organised by Lane Closing 4. PERT organized by Area of Road 5. Grouped by Project ID / WBS /Responsibility Create Following Reports 1. Schedule Report - Group By Alias 2. Schedule Report Organized By Responsibility 3. Schedule Report Sorted By Total Float 4. Sixty-Day Look ahead By Responsibility Create and Run the following Filters 1. Phase 1 Activities 2. Phase 2 Activities 3. Three-Month Look ahead 4. Critical Activities Assignment: Create all the above activity codes, layouts, reports and filter for your project

Page 14: Primavera 3

14

Exercise No: 4 (Please continue from the Exercise No: 3) Project Codes: Are created to define project codes and values at the project group level, and assign the project code values to your member projects. Use project codes to categorize member projects into groups, such as division, funding source, manager, team, and type of work. You can then organize member projects, combine multiple member projects in a single band, or summarize, sort, filter, or report using the codes from the project group. P3 supplies 10 default project codes that you can use and define your own values for, or replace with your own project code definitions that are better suited to your organization. For example, you may want to replace the default Project Manager code definition with Team Leader. Ten codes must always exist for a project group in the Project Codes Dictionary, so if you want to use a code that is not currently defined in the supplied list, you will need to change an existing code to fulfill your coding requirements. Create following Project Codes. Click on Data�Project Codes� Project Code Definition Enter the following values. Values for Project Manager Values Description Arun Kumar Project Manager Sr. Phase1, assign to sub project PHS1. (Close all projects and open PHS1) Sangeeta Project Manager Sr. Phase 2, assign to sub project PHS2. (Close main project and open PHS2)

• Create a layout grouped on Project Manager and save. Enter the following Resources Use Base Calendar = 1

Limits Resource Unit Driving Description

Normal Max

Through Price /unit Through

ASPHALT SY Y Asphalt Surface Course 7500 8000 0.77

BASE SY Y Asphalt Base Course 7725 8200 2.20 CARP Hr. Carpenter 16 32 21.60 COMPR day Air Compressor & Hoses 3 3 10.00

CONCRETE day Y Concrete 35 40 90.00 CRANE day Truck Crane 1 1 1319.00

DOZER Hr. Dozer, 200 H.P. 1 1 762.60 DRIVER Hr. Truck Driver - Heavy 16 24 18.10 ELEC Hr. Electrician 24 32 23.00

FINISHER Hr. Y Cement Finisher 24 40 20 FOREMAN Hr. Foreman 8 8 20.16

Page 15: Primavera 3

15

GRADER Day Grader - Ripper 1 1 48 LABOR* Hr. Labor - All 00 00 0

LABOR-G Hr. General Laborer 24 32 15.50 LABOR-H Hr. Highway Laborer 24 32 17.15 LABOR-S Hr. Skilled Laborer 16 32 19.50

LOADER Day Loader/Backhoe 80 H.P. 1 1 281.00 NETTING Plastic Netting

OPERATOR Hr. Equipment Operator 24 32 22.90 OPERL Hr. Equipment Operator - Light 8 16 21.10 PAVER Day Asphalt Paver, 130 H.P. 2 2 1038.60

POSTDRVR Day Post Driver 1 1 244.00 ROLLER1 Day Roller, Tandem 2 3 250.00

ROLLER2 Day Roller, Steel Wheel 140 SHEETING Day Sheeting Driver 1 1 11

SPREADER Day Aggregate Spreader 98.00

STABL SY Y Asphalt Stabilized Course 6345 7000 3.15 STRIPPER Day Paint Stripper, S.P 1 1 54.00

TRUCK Day Truck - Flatbed, 3 Ton 140.00 TRUCKD Day Dump Truck 3 4 289 VIBRATOR Day Gas Engine Vibrator 2 4 24 WIRING CLF Wiring 22.60

Cost Accounts Cost Accounts are defined to track costs at different levels of detail. Build intelligence into cost account numbers by assigning codes that identify work elements (such as departments, responsibilities, and locations). Use these codes to roll up costs to the level of detail you want to examine. The Categories define the cost categories for the project. These categories describe the type of expenditure, such as labor, materials, or equipment, but contain no information about the cost account structure. You can define up to 36 cost categories for a project Create following Cost Accounts

Cost Categories:

Code Category Title E Equip L Labor G Gnl & OH M Material

Page 16: Primavera 3

16

Cost Account Titles:

Account # Account Title -------------- ---------------------------------------- 010100 General Field Conditions 010000 General Conditions 015300 Construction Facilities & Temp. Controls 015500 Access Roads 015800 Signs 021100 Site Clearing 021200 Site Removals 021600 Underpinning 021000 Site Preparation 022250 Excavation & Backfill 022270 Erosion Control

Account # Account Title -------------- ---------------------------------------- 022000 Earthwork 025100 Asphaltic Concrete Pavement 025400 Pavement Surfacing 025??? Paving and Surfacing 027100 Subdrainage Systems 028400 Site Improvements - Road Appurtenances 028000 Site Improvements 033100 Structural Concrete 033000 Cast-in-place Concrete 160100 Electric Conductors 160700 Underground Utilities 160000 Electrical

Resource Curves Resource curves refer to the allocation of resources and costs over the duration of an activity. P3 distributes resource usage and costs evenly during an activity unless you specify nonlinear distribution using curves. You can only apply a resource curve to a non driving resource. You can create up to 16 resource curves.

Assign Resources to the task with their Cost Accounts

ACTIVITY ID

Activity DESCRIPTION Resource UNITS per day

Budgeted quantity

COST account

COST

P1G098 BEGIN PROJECT P1G100 MOBILIZATION 0.00 0.00 015300 G P1G105 CLEAR SITE DOZER 0.00 4.00 021100 E LABOR-G 0.00 24.00 021100 L

FOREMAN 0.00 8.00 021100 L P1G110 GENERAL CONDITIONS 0.00 0.00 010100 G P1G200B PROCUREMENT OF ESW/SL SIGNS 0.00 0.00 028400 M P1G5200 CONSTRUCT CONCRETE BARRIER AGAINST WALL FOREMAN 2.00 16.00 033100 L VIBRATOR 2.00 16.00 033100 E LABOR-G 24.00 192.00 033100 L

Page 17: Primavera 3

17

FINISHER 24.00 192.00 033100 L CONCRETE 10.00 80.00 033100 M

P1N1140 PLACE TEMP. MARKING TAPE LABOR-G 0.00 16.00 015500 L FOREMAN 0.00 2.00 015500 L P1N1145 PLACE TEMP. CONST. BARRIER LABOR-G 0.00 16.00 015300 L

CRANE 0.00 1.00 015300 E OPERATOR 0.00 8.00 015300 L

FOREMAN 0.00 2.00 015300 L P1N1150 EXCAVATE LABOR-G 0.00 80.00 022250 L FOREMAN 0.00 10.00 022250 L

LOADER 0.00 5.00 022250 E P1N1170 PLACE AGGREGATE & ASPHALT BASE COURSE ROLLER1 0.00 4.00 025100 E

SPREADER 0.00 4.00 025100 E LABOR-H 0.00 48.00 025100 L

FOREMAN 0.00 12.00 025100 L

DOZER 0.00 4.00 025100 E BASE 0.00 46350.00 025100 M

P1N1180 REMOVE TEMP. CONST. BARRIER CRANE 0.00 1.00 015300 E FOREMAN 0.00 2.00 015300 L LABOR-G 0.00 16.00 015300 L OPERATOR 0.00 8.00 015300 L P1N1185 PLACE 2" SURFACE COURSE FOREMAN 0.00 6.00 025400 L

ASPHALT 0.00 22500.00 025400 M ROLLER2 0.00 3.00 025400 E OPERATOR 0.00 72.00 025400 L LABOR-H 0.00 72.00 025400 L PAVER 0.00 3.00 025400 E P1N1190 DIVERT TRAFFIC ONTO TEMP. ROAD LABOR-G 0.00 16.00 015500 L

P1N1195 REMOVE TEMP. MARKING TAPE FOREMAN 0.00 2.00 015500 L LABOR-G 0.00 16.00 015500 L P1N1200 PLACE CONST. BARRIER & TEMP. STRIPING RAMP OPERATOR 0.00 32.00 015300 L CRANE 0.00 1.00 015300 E LABOR-G 0.00 32.00 015300 L

FOREMAN 0.00 2.00 015300 L P1N1202 CONSTRUCT TEMP. BENT #1 & #2 LABOR-H 0.00 320.00 015500 L

FOREMAN 0.00 40.00 015500 L OPERATOR 0.00 20.00 015500 L DOZER 0.00 20.00 015500 E

P1N1210 EXCAVATE RAMP & INSTALL 15" RCP PIPE WITH INLETS FOREMAN 0.00 20.00 027100 L

Page 18: Primavera 3

18

DOZER 0.00 10.00 027100 E LABOR-S 0.00 160.00 027100 L

P1N1220 PLACE AGGREGATE & ASPHALT BASE COURSE FOREMAN 0.00 8.00 025100 L BASE 0.00 30900.00 025100 M ROLLER1 0.00 4.00 025100 E

SPREADER 0.00 4.00 025100 E DOZER 0.00 4.00 025100 E

OPERATOR 0.00 96.00 025100 L LABOR-G 0.00 64.00 025100 L P1N1230 PLACE 2" SURFACE COURSE FOREMAN 0.00 6.00 025100 L

LABOR-H 0.00 96.00 025100 L ASPHALT 0.00 22500.00 025400 M

ROLLER2 0.00 6.00 025400 E PAVER 0.00 3.00 025100 E

OPERATOR 0.00 48.00 025400 L

Create a layout on Resource Analysis (grouped on responsibility/Resource)

Use Report Writer to create following customized reports 1. Resource allocation report. 2. Resources with Budgeted quantity and budgeted cost. 3. Schedule of resources, Budgeted quantity and budgeted cost Types of Graphical reports A bar or Gantt chart is a line graph that depicts activities as bars with length proportional to the duration of each activity. The horizontal placement of the activity depends on its position in time. Normally, only one activity bar is shown per row; relationships between activities are not displayed. Create graphical report on Construction Summary by Phase (Summarize on SUBP-Project ID) Timescaled logic diagrams present the overall logic of a project according to time. Time scaled logic graphics can contain up to 2,750 activities. Horizontal and vertical line segments are limited to 16,000 each and you can produce up to 40 vertical sheets. Create a report on Logic by Responsibility (Group on responsibility and select the range of schedule dates)

Page 19: Primavera 3

19

A pure logic diagram shows the relationships between the activities in a project without consideration of time. Create a graphical report on Pure Logic Diagram – Northbound (Select Project ID=P2) Resource/cost graphics enable you to track a project's resource requirements and budget using histograms and cumulative curves. Histograms show use or cost per timeperiod, while cumulative curves show accumulated use or cost over a specific time interval. Create a graphical report on Cumulative and Monthly Costs (select all resources by putting ????????? in resource selection) Matrix Report is a grid containing columns and rows that enables you to compare several items to a single criterion. Use matrix reports to condense, compare, and summarize project data. Columns and rows of activity matrix reports are organized by activity codes. Choose from an extensive list of data items, such as dates, durations, and resource/cost data, for the cells in the center of the report. Display totals for columns and rows in matrix reports. Assignment: Create Resource dictionary with min and max limits and their appropriate price. Create appropriate Resource Curves, Cost accounts and assign to the task. Create Graphical and Tabular reports as stated in above exercise.

Page 20: Primavera 3

20

Exercise No: 5 (Please continue from the Exercise No: 4) RESOURCE LEVELING Forward: Forward leveling schedules the early dates (forward pass) of the project. P3 schedules activities in network sequence: predecessors are scheduled before their successors. If sufficient resources are unavailable for an activity's requirements, P3 postpones the activity. If necessary, P3 can delay the activity beyond its late dates; this delays the project's early finish date. During the forward leveling of tasks and independent activities, P3 provides other choices for resolving resource conflicts. You can specify another leveling method in the Leveling section of the Constraints form. Backward: Backward leveling schedules the late dates (backward pass) of the project. Leveling begins with the last activity in the network with no successors and ends at the beginning of the network. This enables you to determine the latest possible dates for scheduling activities without exceeding resource availability. In backward leveling, if sufficient resources are unavailable on the activity's late dates, P3 schedules the activity earlier. P3 reschedules the activity on the latest possible date that the necessary resources are available for the duration of the activity. Before P3 reschedules an activity, it schedules all of its successors. Leveling based on late dates can schedule activities to start earlier than their early start dates. Also, during forward leveling, if the latest early finish changes, and no finish date is imposed, P3 performs a backward pass to recalculate the late dates. Data Date: Click and select the date through which you have recorded progress. SMOOTHING

None: When you choose this option and an activity cannot be scheduled due to insufficient resources, and it cannot be delayed because all float has been used, P3 recalculates resource availability assuming the maximum limit from the resource dictionary. This can result in committing more resources than are required during certain time periods. Non-Time Constrained: When you choose this option, P3 attempts to obtain a more uniform profile of resource usage. To minimize sharp changes in resource use, P3 divides the difference between the normal and maximum resource availabilities into 10 increments. If P3 cannot schedule an activity due to insufficient resource supply, it reevaluates the resource supply assuming not the maximum availability, but only a one increment increase (10 percent of the difference between the normal and maximum limits). If this fails again, it assumes another one increment increase, until it reaches the maximum. Only then is the activity delayed beyond its available float. Time Constrained: Choose this option when the end date of a project is rigid, and additional resources must be sought to meet overload conditions. P3 initially sets the normal resource limit equal to 200 percent of the maximum limit, and never raises it further. P3 does not delay activities beyond their late finish dates when using this mode of smoothing.

Page 21: Primavera 3

21

PROJECT LEVELING

P3 levels projects if the Allow Scheduling And Leveling Of Individual Projects checkbox is marked in the Schedule/Level Calculation Options dialog box for the project group. Use Project Group's Limits: P3 assumes that the project group's availability limits for common resources are set to encompass all projects. When P3 levels only one project, and uses project group limits, these availability limits may not accurately reflect resource availability. Use Net Availability: P3 starts with the project group's limits and deducts usage from all other projects. The remaining amount is used as the availability for the project you are leveling. OPTIONS

Schedule Prior To Leveling: Mark this checkbox to have P3 calculate the schedule before leveling resources. Once you level resources, the leveled dates replace the schedule dates in a project. When forward leveling, P3 always calculates a schedule first. If you level based on late dates (backward level), you may want to clear the Schedule Prior To Leveling checkbox so you can forward level, then backward level the same schedule. Report Series: Specify a series code for the reports you want to produce after leveling. Click and select from a list of existing series codes, or choose Tools, Tabular Reports, and Production to define new series codes. Entire Project: P3 applies the leveling algorithm through the end of the project. Until: When leveling early dates (forward leveling), instead of leveling through the entire duration of a project, you can specify a cutoff date. If an activity cannot be scheduled before the specified date because of insufficient resources, P3 schedules the activity on the cutoff date you specify. Level Activities In Filter: To level only certain activities in the project, click and select a filter. P3 allocates resources only to the activities selected by the filter. Excluded activities are treated as if they have no resources and cannot deplete the resource pool. Resource profiles based on the leveled dates may show that resources are over utilized, since P3 assigns more of the resource pool to the selected activities than it would when leveling the entire project. Activities outside the filter can still be delayed by activities which are in the filter and are delayed by leveling. Report: Opens the Report dialog box so you can choose whether to produce a leveling analysis report. When you choose to produce this report, you can also specify the activities to include and a date range. Options: Displays the Schedule/Level Calculation Options dialog box so you can set calculation options for scheduling and leveling projects. Level Now: Levels the project.

Page 22: Primavera 3

22

Prioritization During resource leveling P3 establishes a list of activities in topological sequence. As resources are leveled, if more than one activity can be leveled at the same time, P3 uses the prioritization codes as a tie-breaker. P3 levels the activity with the highest priority (the lowest number) before activities with lower priority. If no data items are specified under prioritization, P3 sorts by activity ID. For backward leveling, the order of activities is reversed; the sort order is automatically descending. Splitting Set options that apply to all activities that you designate for splitting, stretching, or crunching in the individual activities' Constraints form. Maximum Number Of Splits Per Activity: Specify a number from 0 to 99; the default is 1. Maximum Duration Of Each Split: Specify a maximum duration for the suspension between 1 and 999 planning units. Minimum Duration Of Each Work Chunk: Specify the smallest duration allowable for a work chunk; the default is 2, the minimum is 1, and the maximum is 999 planning units. Stretching Units Per Timeperiod May Be As Little As % Of Requirement: Specify the smallest allowable percentage of a resource's required units per timeperiod for any timeperiod while stretching an activity. For example, you could allow the use of 50% of the normal UPT (units per time period). Crunching Units Per Timeperiod May Not Exceed % Of Requirement: Specify the largest allowable percentage of a resource's required units per timeperiod for any timeperiod while crunching an activity. P3 will not exceed the maximum availability limit set in the Resource dictionary. For example, you could allow the use of 200% of the normal UPT. Show Results from Splitting, Stretching, and Crunching in Onscreen Profiles and Loading Reports: Mark this checkbox to see the results of splitting, stretching, and crunching settings on your project in profiles and loading reports. Level your project to resolve the resource conflict. You may also smoothen the resources if necessary. View Resource Profile from View� Resource Profile and Resource Table to study the resource loading. View Tabular Reports from Tools����Tabular Report related to Schedule, Resource, Cost Matrix and Production View Graphical Reports from Tools���� Graphical Reports related to Bar, Time Scale Logic, Pure Logic, Resource and Cost and Production.

Page 23: Primavera 3

23

TARGET PROJECT (Tools����Project Utilities����Target): Please note you must Level your project to resolve the resource conflict before saving any target project. After you establish an acceptable project plan, you can copy it as a target. As the project progresses, use this target as a benchmark to compare dates, resources, and costs to the current schedule. Use this method to measure project status as well as performance. Using target plans enables you to review delayed activities relative to the original plan. You also must maintain target plans to analyze earned value. Project Group/Project Name: Displays the name of the project group or project that is currently open. Target/Number/Version/Data Date: Click the Target column and type a unique four-character project name or right-click to select an existing project. Repeat this step to assign a second target. To remove a target assignment, select the target project name and click , then click OK. Update Target Plans (Tools����Project Utilities����Target ����Update): Globally updates the target project with changes made to the current project. A target plan serves as a record of the original schedule; therefore, it should not be continuously updated. However, if you do need to make changes, use the options in this dialog box to automatically update a target project based on existing data in the current project. For example, replace calendars and dictionaries, add or eliminate activities, and store or replace actual data and budgets. You can also update a target project independently. In a multi user environment, you need exclusive access to both the current and target projects to update a target. Target Project: Displays a list of projects in the current folder. Choose a target project (or any other project) to update it based on data in the current project. Project Data

Update Resource Dictionary With Prices, Availability, And Calendars: Updates prices, minimum and maximum limits, and through dates to match those in the current project. Also adds new resources and their associated resource calendars from the current project. Resources deleted from the Resource Dictionary for the current project remain in the Resource Dictionary for the target project. Do not update the target Resource Dictionary if you plan to analyze the impact of different normal and maximum resource availability limits. Delete From Target Any Activities No Longer In The Current Schedule: Deletes activities in the target that no longer exist in the current schedule.

Page 24: Primavera 3

24

Replace

Custom Data Items: Replaces the Custom Data Items Dictionary to match the current project. When you mark this checkbox, P3 also removes the custom data item values for all activities. To update custom data item values assigned to activities or resources/costs, make sure you mark the Custom Data Item values checkbox. Replace Target Base Calendars: Copies the calendar from the current project to the target project. Calendar changes include the project start date, imposed finish date, data date, number or definition of days in a workweek, non work period definitions, and exceptions. Do not replace the target calendar if you want to perform "what-if" analysis in the current project. Replace Code Structure, Values, and Titles Dictionary: Replaces the Activity Codes and Project Codes Dictionaries to match the current project. Adds, deletes, or replaces code names, titles, and values. Replace WBS Structure, Values and Titles Dictionary: Updates the WBS structure to match the current project. Adds, deletes, or replaces codes, titles, levels, widths, and separators. Activity Data The following items determine which activities P3 updates. First indicate whether all activities should be updated or only those in the current layout. Select: Choose All Activities to update all activities in the target project that exist in the current project. Choose Current Layout to update only those activities selected by the active filter in the current project. Select a subset of activities by marking one or two of the following options; mark all three to update all activities in the project or in the current layout: Underway: Selects activities that have an actual start date or a percent complete less than 100 but greater than zero. Completed: Selects activities that have an actual finish date or are 100 percent complete. Not Started: Selects activities that have no actual start or finish date and are zero percent complete. For Activities Not in the Target Add Activity and All Data Items: Adds activities that exist in the current project but not in the target project, including activity descriptions, relationships, durations, codes, resources, logs, and other data assigned to the new activities. AUTO COST The automatic resource cost calculation rules by which P3 calculates cost and estimates resource use when you update activities. You can define system wide rule or specific rules for any project or project group.

AutoCost Rules (Tools����Options����Autocost Rules): Click on help to read the details of the rules.

Page 25: Primavera 3

25

UPDATE PROGRESS Once the Auto Cost Rules are set you may update the progress automatically using Tools�Update Progress option. New Data Date: Click to select a new data date if the one shown is not correct. Estimate Progress within Update Period for: Choose to update all (visible) activities scheduled to work during the current update period or only selected (spotlighted) activities. Update: Click to update each applicable activity. For each activity in the update, P3 estimates percent complete amounts as of the data date, sets dates to actual if they fall before the new data date, and estimates remaining durations for activities that are not finished as of the data date. P3 also updates resource assignments based on the revised percent completes and remaining durations while adhering to Auto cost rules. SUMMARIZATION Use the Summary Calculations dialog box to select the calendar P3 uses for summary calculations and specify the weighting factor P3 uses to compute percent-complete values. If All Activities In The Summary Are Not On The Same Calendar, Use Calendar: Specifies the calendar P3 uses for summary calculations when multiple calendars are assigned to the activities being summarized. Click to select a different calendar. P3 calculates the duration for summary activities based on work periods determined by the calendar you specify. Use the Following As The Weighting Factor When Computing Percent Complete: You can base the percent complete for each summarized group on duration, resource units, or cost. Duration: The duration method (the default) calculates the percent complete as = [(Sum of Orig Dur - Sum of Rem Dur) ÷ Sum of Orig Dur] x 100. Resource Units or Cost: The resource units and cost methods compute the summary percent complete for each group as = [Sum of (Budget x Percent Complete) ÷ Sum of Budget] x 100. If no resource percent complete is specified, P3 uses the schedule percent complete for the activity. CREATING FRAGNETS Fragnets are sections of a network that you can use to build new projects quickly. Create fragnets using data from your own projects or retrieve sample fragnets provided with P3. P3 stores the activities related data in a fragnet such as Activity ID and description, Durations, Percent complete, Float, Relationships for activities within the fragnet. It also stores other Logs such as Resources and costs (and associated Dictionary information), Constraints, WBS values, Custom data items, Activity code values, Activity type Assignment: Level Resources, Create Target Projects, Set AutoCost Rules suitable to your project, update progress, Create and store the fragnets, create related layouts and reports.

Page 26: Primavera 3

26

Exercise No: 6 (Please continue from the Exercise No: 5) UPDATING PROGRESS P3 offers several ways of updating your schedule. You can update progress for all activities and resources as a whole; update activities and resources individually; or use a combination of the two methods. If your project is progressing exactly as planned or if you only need to estimate progress, simply specify the data date or "as-of" date, then have P3 determine which activities have progressed and how much and calculate the remaining durations of activities that have started. P3 also notes which activities have completed and sets their remaining durations to zero. If your project is not progressing as planned—many activities are out-of-sequence, activities are taking more or less time to complete than originally planned, or actual resource use is exceeding planned use—update activities and resources individually. This will help you forecast the effects of this unforeseen progress or lack of progress, so that you can take appropriate corrective action wherever necessary. Most projects progress somewhere between these two situations: some activities are progressing as planned and some are not. If this is the case, you'll want to combine the two updating methods. Let P3 calculate your project as if it is progressing exactly as planned, and then individually update those activities and resources that have deviated from the plan. You can record progress at any time. P3 records progress up to the current data date. For example, suppose you update the schedule every Friday and the current data date is Friday, November, 5. Suppose another week passes and now it is November 12. Update progress through the end of the day November 11, then advance the data date to November 12; P3 revises the schedule based on the actual dates, delays, and other changes you just recorded. METHODS OF UPDATING PROGRESS 1. Update progress (Tools ����Update Progress): If activities are progressing on schedule, you may want P3 to estimate progress for all

activities as of the new data date you specify. P3 can quickly estimate activity dates, percent complete amounts, and remaining durations when you use the Update Progress dialog box to update a project.

Estimating activity progress is a quick and convenient way to update your project. P3 estimates progress only for those activities that were supposed to take place. Since progress can occur on activities out of sequence, you may need to update additional activities—especially if you selected activities by dragging the data-date line or by using the Progress Spotlight feature. You should also review all incomplete activities to make sure their remaining durations, actual dates, and percent complete amounts are realistic. Once you spotlight activities, you can quickly update the project as "on time."

In P3, you can either update projects automatically or update each activity manually. You will probably combine these methods for most updates. First, update the entire project: P3 updates each activity as though it progressed according to its early dates. P3 calculates resource use according to progress. Next, adjust the actual dates, duration, and resource use of the activities that did not occur exactly as scheduled.

Page 27: Primavera 3

27

2. Estimate progress for spotlighted activities (View���� Progress Spotlight or click the Progress Spotlight icon on the desktop)

• Spotlight the activities for which you want to estimate progress by dragging the data date line or by using the Progress Spotlight feature.

• Choose Tools, Update Progress. Enter the new data date if the one shown is not accurate. The data date is not necessarily the date you are working on the project. For example, if on Tuesday you are updating a project to show progress as of the end of the day last Thursday, the data date is last Friday.

• Choose to update all (visible) activities scheduled to work during the current update period or only selected (spotlighted) activities.

• Click Update.

For each activity in the update, P3 estimates percent complete amounts as of the data date, sets dates to actual if they fall before the new data date, and estimates remaining durations for activities that are not finished as of the data date. P3 also updates resource assignments based on the revised percent completes and remaining durations while adhering to Autocost rules. In addition, P3 takes into account only the first price per unit in the Resource Dictionary, if more than one price per unit for varying through dates exists, when updating resource assignments. Note: If you estimate progress for selected activities that do not fall within the update period, those activities will show no progress. When spotlighting activities, you can only estimate progress—percent complete, remaining duration, and so on—for activities that are within the update period. If you manually update a spotlighted activity and then run Update Progress, P3 bypasses the activity and your changes are retained.

3. Record progress using the Activity form or columns (View����Activity Form): You can record progress at any time. P3 records

progress up to the current data date. For example, suppose you update the schedule every Friday and the current data date is Friday, November, 5. Suppose another week passes and now it is November 12. Update progress through the end of the day November 11, then advance the data date to November 12; P3 revises the schedule based on the actual dates, delays, and other changes you just recorded. You may record RD, AS, AF, % completion for an selected activity.

ANALYZING PROGRESS

1. Tracing progress using the progress line: Show a progress line in the Bar chart to graphically trace progress on activities and quickly see how a project is performing. Click the Progress Line tab in the Sight Lines dialog box (Format, Sight Lines) to select line type and color and whether you want to base progress on target variance or on actual progress. Using the variance option, you can immediately gauge whether your project is staying on track based on your original estimates. An activity is behind schedule if the progress line is drawn to the left of the data date line on the activity bar and ahead of schedule if the line is drawn to the right of the data date line on the activity bar.

Note: P3 draws the variance progress line based on a continuous, seven-day calendar.

Page 28: Primavera 3

28

Choose the Progress Points option to see the progress line zig zag among activities that have started or that should have started, relative to the target start and finish dates. When using this option, you should choose to display target bars with progress based on the current project. (Choose Format, Bars). If an activity was scheduled to start before the data date, but has no progress, P3 draws the progress line to the target start point (indicating a delay.)

To display the progress line in the Bars area: Choose View, Progress Line.

P3 draws the progress line to the data date line when:

• the activity is completed,

• the activity has no progress and is scheduled to start after the data date,

• the activity is a milestone or a flag,

• the activity does not exist in the target project, and/or

• the resource dates do not exist in the target project.

Note: The key bar determines the bar to which the progress line is drawn. For example, if you are displaying the current and the target bar with the target bar designated as the key bar, the progress line connects points on the target bar.

2. Interrupt activity progress: During a project, you may need to stop work on an activity temporarily. Specify suspend and resume dates

to indicate a work stoppage.

Note: The activity must have an actual start date before you can record a suspend date. To interrupt activity progress

• Select the activity, then right-click and choose Activity Detail, Dates.

• In the Suspend field, click and select the last day on which work occurred for the activity.

• When work begins again, click and select a date in the Resume field.

P3 calculates an actual duration for all activities with progress based on the amount of time actually worked. P3 considers non work time and specific calendar definitions.

3. Compare actual progress to the target: Comparing progress to the original plan is the best way to determine whether your project is

staying on track. P3 provides several onscreen displays, as well as printed reports and graphics, to help you compare the current schedule to the target plan. A Bar chart layout enables you to determine whether you are ahead of or behind schedule.

Page 29: Primavera 3

29

You can also analyze schedule and cost performance by displaying the scheduled budget and earned value in the Activity columns or by opening the Budget Summary form (from Activity Form). For detailed reporting, create schedule, activity matrix, or resource and cost graphics. Produce the earned-value report to analyze cost and schedule variance.

4. Identify problem areas: If you are unconcerned with small variances at the activity-detail level, you can analyze cost and schedule

variance at the summary level. To analyze cost and schedule variance at a summary level

• Define columns to include Scheduled budget (BCWS), Earned value (BCWP), Actual cost, Cost variance, and Schedule variance.

• Choose Format, Organize. Group by Responsibility.

Note: You must group activities by resource or cost account to modify resource and cost data in the Activity columns. Choose Format, Summarize All. Select Responsibility in the Summarize To field.

5. Sight Lines command (Format menu)

Use this command to specify the placement of horizontal and vertical sight lines, the thickness and color of the data date and progress lines, and whether you want to base Progress on target variance or on actual progress for the progress line. Horizontal sight lines help you trace an activity bar to its corresponding data in Activity columns. Vertical sight lines help trace an activity bar to its exact position on the timescale. Sight lines can be solid, dashed, or dotted, in varying shades of gray to black, depending on how you define them. The data date line indicates the "as of" date P3 uses to calculate the schedule. The progress line graphically traces progress on activities so you can quickly see how a project is performing. You can choose to base the progress line on finish date variance or on actual progress.

6. Progress Lines

Based on the Difference between Current and Target Finish Dates: Choose this option to see the progress line drawn to the left or right of the data date line using the variance value for all activities. For example, if the target finish date is two days before the current finish date (negative variance), the progress line is drawn two days to the left of the data date line. Conversely, if the target finish date is two days after the current finish date (positive variance), the progress line is drawn two days to the right of the data date line. If an activity is on schedule (zero variance) the progress line is drawn to the data date. By Connecting Progress Points: Choose this option to see the progress line zig zag among activities that have started or that should have started, relative to the target start and finish dates. When using this option, you should choose to display target bars with progress based on the current project (choose Format, Bars).

GLOBAL CHANGE The Global change feature enables you to make changes to all activities, or a selected group of activities, at one time. You can use Global change to edit existing values, assign new values, or delete a group of activities from your project. To change data globally, add a Global change specification, then define the changes. To select data to change, either define If: statements or click the Selection tab to create selection statements.

Page 30: Primavera 3

30

Click Trial Run to preview the proposed changes without affecting the stored project data. If you are satisfied with the changes shown in the trial-run report, click Run to apply the changes.

Note: Always back up your project before running a Global change; you can undo a change only by restoring a backup of the project. In a multi user environment, P3 does not change data exclusively locked by another user at the time you run. STORE PERIOD PERFORMANCE Normally P3 spreads actual data evenly from the recorded actual start date to the data date. However, you can have P3 store actual cost, use, and earned value for each update period. You can analyze historical data using the Resource Table or Resource Loading report. Tips for storing period performance 1. Since you cannot change period performance data once you store them, you may want to create a backup copy of the project before

closing out the update period. 2. Be sure to define prices for resources in the Resource Dictionary before storing period performance. Changing prices after closing out

an update period may result in cost variances. 3. The project controls coordinator should establish a regular time period, such as monthly or quarterly, for performing updates. Using a

consistent time period to store performance data makes it easier to analyze historical data later. To store period performance 1. Add activities, assign resources to them, and schedule your project. 2. Record progress by assigning an actual start to each activity and updating the resource's quantity this period or quantity to date. 3. Change the data date to a date that is later than all of the actual dates you recorded and schedule the project again. 4. Choose Tools, Store Period Performance, and click Store Now. P3 resets the Actual Quantity and Cost This Period of all resources to zero. If P3 cannot close out all resource assignments, it creates a log file (CLOSEOUT.OUT) in your Userloc folder listing the assignments it could not process. P3 also creates an audit file in the Projects folder named <project name>HST.OUT that contains a history of closeout dates for the project. RECORD AND REVIEW PERIOD PERFORMANCE When you store period performance (choose Tools, Store Period Performance), P3 stores the actual cost and quantity values for resource assignments and resets each resource assignment's actual this period value to zero so you can begin tracking progress for the current period. You can review historical actual data for resources in the resource profile or table, the resource loading report, and resource/cost graphics. Actual cost and quantity values are shown from the start of the resource assignment to the data date. P3 spreads the actual values using the currently assigned calendar.

Page 31: Primavera 3

31

Additional Considerations: When storing period performance, consider the following:

• If you change the activity's base calendar or the resource calendar after you have stored performance data, P3 spreads the data based on the new calendar.

• When you close out at the project group level, P3 closes out each member project as well, using each project's respective data date. The data date at the project group level should be set to the same or a later date than the data date in each of its member projects.

• To avoid cost variances, do not change prices after storing period performance data.

• When you cut, copy or paste activities between projects, the period performance data are retained with the activity, provided the same planning unit is used in the project to which you are copying. However, period performance data may be spread differently if the project you are copying to uses different calendars.

• You need to have exclusive access to the project when closing out an update period. If you do not have exclusive access to the project and attempt to store period performance while other users are in the project, P3 displays a warning message and does not allow you to continue. To obtain exclusive access to the project when closing out an update period, choose File, Open and mark the Exclusive checkbox in the Open a Project dialog box.

Project Check-in/Check-out Project participants may want to use a version-control utility called Project Check-in/Check-out that is provided in P3. This utility enables a project participant to check out a project to work with at another location; it also notifies any other participants that the project they are attempting to access has been checked out; the project can still be accessed from its usual location, however. Project managers should recommend this method to all participants who are planning to make changes to a project when it is located anywhere other than the network where it normally resides. Establish relationships between projects from different project groups You can also assign relationships between activities from different project groups. In this case use the Inter Project Relationship Manager to create a project group file that manages the linked activities. Netset The Primavera Network Administration program (Netset) is provided with P3 for managing the user database in a multi user network environment. Note: You cannot run Netset and P3 concurrently on your workstation; close P3 before running the Netset program. To start Netset: Start Netset from the Primavera programs group. Type Netset as the password and click OK. Netset is password-protected to prevent unauthorized users from changing the network setup and other information. "Netset" is the default password; you should change this password after using Netset the first time. You can change the Netset password by using Options, Change Administrator Password

Page 32: Primavera 3

32

P1N1235 REMOVE TEMP. CONSTR. BARRIER OPERATOR 0.00 8.00 015300 E

CRANE 0.00 1.00 015300 E

LABOR-G 0.00 8.00 015300 L

FOREMAN 0.00 2.00 015300 L

P1N1240 PLACE TEMP. STRIPING & DIVERT TRAFFIC LABOR-G 0.00 16.00 015500 L

P1N2100 PLACE CONST. BARRIER LABOR-G 8.00 96.00 015300 L

CRANE 1.00 12.00 015300 E

OPERATOR 0.00 0.00 015300 L

FOREMAN 2.00 24.00 015300 L

P1N2105B INSTALL EROSION CONTROL DEVICES FOREMAN 0.13 2.00 022270 L

LABOR-G 16.00 240.00 022270 L

NETTING 2500.00 37500.00 022270 M

P1N2115A GRUB & STRIP TOPSOIL FOREMAN 4.00 32.00 021100 L

TRUCKD 1.00 8.00 021100 E

DRIVER 24.00 192.00 021100 L

DOZER 1.00 8.00 021100 E

LOADER 0.00 0.00 021100 E

P1N2190 INSTALL SIGN SUPPORT STRUCTURE LABOR-G 8.00 64.00 015800 L

DRIVER 8.00 64.00 015800 L

FOREMAN 2.00 16.00 015800 L

TRUCK 1.00 8.00 015800 E

OPERL 8.00 64.00 015800 L

POSTDRVR 1.00 8.00 015800 E

P1N2195 ERECT SIGNS CRANE 1.00 3.00 015800 E

FOREMAN 2.00 6.00 015800 L

OPERATOR 8.00 24.00 015800 L

LABOR-G 16.00 48.00 015800 L

P1N2200 INSTALL TEMP. SHEETING FOREMAN 2.00 24.00 021600 L

SHEETING 1.00 12.00 021600 E

CARP 16.00 192.00 021600 L

LABOR-G 24.00 288.00 021600 L

COMPR 1.00 12.00 021600 E

P1N2210 EXCAVATE RETAINING WALL FOREMAN 2.00 24.00 022250 L

LOADER 1.00 12.00 022250 E

OPERATOR 8.00 96.00 022250 L

LABOR-G 8.00 96.00 022250 L

P1N2220 CONSTRUCT FOOTING FOREMAN 2.00 42.00 033100 L

Page 33: Primavera 3

33

VIBRATOR 2.00 54.00 033100 E

LABOR-G 24.00 648.00 033100 L

FINISHER 24.00 648.00 033100 L

CONCRETE 35.00 945.00 033100 M

P1N2230 CONSTRUCT RETAINING WALL FOREMAN 2.00 54.00 033100 L

VIBRATOR 2.00 54.00 033100 L

LABOR-G 16.00 432.00 033100 L

FINISHER 24.00 648.00 033100 L

CONCRETE 19.00 513.00 033100 M

P1N2240 PLACE POROUS FILL BEHIND WALL FOREMAN 2.00 18.00 022250 L

DOZER 1.00 9.00 022250 E LABOR-G 16.00 144.00 022250 L

OPERATOR 8.00 72.00 022250 L P1N2250 BACKFILL RETAINING WALL FOREMAN 2.00 14.00 022250 L

DOZER 1.00 7.00 022250 E

OPERATOR 8.00 56.00 022250 L LABOR-G 8.00 56.00 022250 L

P1N2260 CONSTRUCT CONCRETE BARRIER AGAINST WALL

FOREMAN 2.00 40.00 033100 L

VIBRATOR 2.00 40.00 033100 E

LABOR-G 24.00 480.00 033100 L

FINISHER 24.00 480.00 033100 L CONCRETE 11.00 220.00 033100 M

P1N2270 CONSTRUCT CONCRETE BARRIER AGAINST WALL

FOREMAN 0.33 8.00 033100 L

VIBRATOR 2.00 48.00 033100 E

LABOR-G 24.00 576.00 033100 L

FINISHER 4.00 96.00 033100 L CONCRETE 11.00 44.00 033100 M

P1N2300 CONSTRUCT CONCRETE BARRIER AGAINST WALL

FOREMAN 2.00 50.00 033100 L

VIBRATOR 2.00 50.00 033100 E

LABOR-G 24.00 600.00 033100 L

FINISHER 24.00 600.00 033100 L CONCRETE 11.00 275.00 033100 M

P1N2320 CONSTRUCT CONCRETE BARRIER AGAINST WALL

FOREMAN 2.00 48.00 033100 L

VIBRATOR 2.00 48.00 033100 E

LABOR-G 24.00 576.00 033100 L

FINISHER 4.00 96.00 033100 L CONCRETE 11.00 44.00 033100 M

P1N3200 CONSTRUCT CONCRETE BARRIER AGAINST WALL

FOREMAN 2.00 40.00 033100 L

Page 34: Primavera 3

34

VIBRATOR 2.00 40.00 033100 E

LABOR-G 24.00 480.00 033100 L FINISHER 24.00 480.00 033100 L

CONCRETE 11.00 220.00 033100 M

P1N3220 CONSTRUCT CONCRETE BARRIER AGAINST WALL

FOREMAN 2.00 12.00 033100 L

VIBRATOR 2.00 12.00 033100 E

LABOR-G 24.00 144.00 033100 L FINISHER 24.00 144.00 033100

CONCRETE 11.00 66.00 033100 M

P1N3225B CONSTRUCT CONCRETE BARRIER AGAINST WALL

FOREMAN 2.00 12.00 033100 L

VIBRATOR 2.00 12.00 033100 E LABOR-G 24.00 144.00 033100 L

FINISHER 24.00 144.00 033100 L

CONCRETE 11.00 66.00 033100 M

P1NP100A PROCUREMENT OF NOISE BARRIER POST & PANELS

0.00 0.00 028400 M

P1NP200C PROCUREMENT OF SIGN STRUCTURES 0.00 0.00 028400 M P2G600 PROJECT COMPLETE

P2N2115B REMOVE GUIDE RAIL FOREMAN 2.00 8.00 021200 L

LABOR-H 16.00 64.00 021200 L

LOADER 1.00 4.00 021200 E OPERATOR 8.00 32.00 021200 L

P2N2125A EXCAVATE FOR ELECTRICAL FOREMAN 2.00 20.00 022250 L LABOR-G 8.00 80.00 022250 L

LOADER 1.00 10.00 022250 E OPERL 8.00 80.00 022250 L P2N2125B INSTALL TEMP. ELECTRICS ELEC 24.00 360.00 160100 L

FOREMAN 2.00 30.00 160100 L P2N2130 INSTALL ELECTRIC CONDUITS & STRUCTURES ELEC 24.00 456.00 160700 L

FOREMAN 2.00 38.00 160700 L LABOR-S 16.00 304.00 160700 L

CRANE 1.00 19.00 160700 E P2N2140 INSTALL POWER & LIGHTING ELEC 24.00 360.00 160100 L

LABOR-S 16.00 240.00 160100 L

FOREMAN 2.00 30.00 160100 L WIRING 10.00 150.00 160100 M

P2N2150 SUBGRADE PREPARATION FOREMAN 2.00 28.00 025100 L ROLLER2 1.00 14.00 025100 E

OPERATOR 8.00 112.00 025100 L

LABOR-H 8.00 112.00 025100 L

P2N2170 PLACE AGGREGATE & ASPHALT BASE COURSE FOREMAN 2.00 20.00 025100 L OPERATOR 24.00 240.00 025100 L

SPREADER 1.00 10.00 025100 E

Page 35: Primavera 3

35

ROLLER1 1.00 10.00 025100 E

DOZER 1.00 10.00 025100 E LABOR-H 16.00 160.00 025100 L

BASE 7725.00 77250.00 025100 M

P2N2180 PLACE ASPHALT STABILIZED COURSE FOREMAN 2.00 24.00 025100 L PAVER 1.00 12.00 025100 E

ROLLER2 1.00 12.00 025100 E OPERATOR 8.00 96.00 025100 L

LABOR-H 18.00 216.00 025100 L STABL 6437.50 77250.00 025100 M

P2N2185 PLACE 2" SURFACE COURSE FOREMAN 2.00 20.00 025400 L PAVER 1.00 10.00 025400 E

OPERATOR 8.00 80.00 025400 L

ROLLER2 1.00 10.00 025400 E LABOR-H 8.00 80.00 025400 L

ASPHALT 7725.00 77250.00 025400 M P2N2196 STRIPE ROADWAY FOREMAN 2.00 18.00 025400 L

STRIPPER 1.00 9.00 025400 E

TRUCK 1.00 9.00 025400 E

DRIVER 8.00 72.00 025400 L OPERATOR 8.00 72.00 025400 L

LABOR-H 32.00 288.00 025400 L P2N2198 REMOVE TEMP. BARRIER CRANE 1.00 4.00 015300 E

OPERATOR 8.00 32.00 015300 L

FOREMAN 2.00 8.00 015300 L LABOR-G 8.00 32.00 015300 L

P2N3100 PLACE TEMP. CONST. BARRIER FOREMAN 2.00 12.00 015300 L LABOR-G 8.00 48.00 015300 L

CRANE 1.00 6.00 015300 E OPERATOR 8.00 48.00 015300 L

P2N3110 REMOVE TEMP. PAVEMENT FOREMAN 2.00 18.00 021200 L LABOR-G 16.00 144.00 021200 L LOADER 1.00 9.00 021200 E

OPERATOR 8.00 72.00 021200 L P2N3120 REGRADE AREA FOREMAN 2.00 14.00 022250 L

DOZER 1.00 7.00 022250 E OPERATOR 8.00 56.00 022250 L

P2N3225A REMOVE TEMP. CONST. BARRIER LABOR-G 8.00 40.00 015300 L

FOREMAN 2.00 10.00 015300 L

OPERATOR 8.00 40.00 015300 L CRANE 1.00 5.00 015300 E