Banyu Urip Project _______________________________
PRESERVATION PROCEDURE FOR SEWAGE TREATMENT UNIT
IDBC-BS-VMPRS-C00001
C 7 Jan 2015 Re-Issued for Approval SB A P AM
B 30 Dec 2014 Issued for Approval SB A P AM
A 22 Dec 2014 Issued for Review SB A P AM
Rev Rev date Description Prepared By Checked
By Reviewed
By
Contract No:
C-3208020
BANYU URIP
PROJECT
EPC5
PRESERVATION PROCEDURE IDBC-BS-VMRPS-C00001
January 7, 2015
Rev C
MPI: Unclassified Page 2 of 8
IDBC-BS-VMPRS-C00001 REV C
Revision Section Description
A All Issued for Review
B All Issued for Approval
C All Re-Issued for Approval
PT BANYU BIRU SEJATI WATER & WASTE WATER TREATMENT CONTRACTOR
PRESERVATION PROCEDURE
1
Preservation Procedure
PRESERVATION PROCEDURE FOR PACKAGE SEWAGE TREATMENT UNIT
PT BANYU BIRU SEJATI
Table of Contents
1. INTRODUCTION ............................................................................................................. 2
2. DEFINITION .................................................................................................................... 3
3. SCOPE OF WORK ............................................................................................................ 4
4. PERSONAL REQUIREMENT ............................................................................................ 4
5. PACKING ......................................................................................................................... 4
6. HANDLING ...................................................................................................................... 5
7. RESPONSIBILITY ............................................................................................................ 5
8. PRIOR INSTALLATION ................................................................................................... 6
9. UNPACKING PROCEDURE .............................................................................................. 6
10. PRESERVATION PRINCIPLE .......................................................................................... 7
11. AFTER INSTALLATION .................................................................................................. 7
PT BANYU BIRU SEJATI WATER & WASTE WATER TREATMENT CONTRACTOR
PRESERVATION PROCEDURE
2
Preservation Procedure
1. INTRODUCTION
This document defines the principles and structure to ensure that main equipment and
material are kept preserved during all phases of the project, before taken into site
installation. There are two groups of main equipment for this application, Laundry Waste
Water Treatment and Sewage Treatment Unit. The Laundry Waste Water Treatment
Package is a system for pre-treatment of raw waste water from laundry section before
entering Sewage Treatment Unit for advance treatment.
Compliance with these requirement will be checked periodically during the goods is kept
in the warehouse. Inspection Schedule and Record are attached in the end of this
document for practical application in the job site.
PT BANYU BIRU SEJATI WATER & WASTE WATER TREATMENT CONTRACTOR
PRESERVATION PROCEDURE
3
Preservation Procedure
2. DEFINITION
The terms used in this procedure have the meaning defined in general form which are
able to be easily understood by persons from all level.
Preservation: The protection and preventive maintenance carried out on main equipment
and material before it is taken into job site for installation.
Preservation Maintenance: The periodic activities to confirm that the preservation applied
is intact and functioning. This also includes repair of deteriorated during preservation.
Preservation Record: The different forms for each discipline, which together with this
standard defines and records the preservation requirements and activities.
Preservation Dossier: Preservation documentation compiled in paper or electronic format
Preservation Check List: The preservation check list, which defines the minimum
requirements to maintain the preservation.
Procedure: Specified way to carry out an activity or a process. Procedures can be
documented or not. When a procedure is documented, the term “documented procedure”
is frequently used.
Sensistive Material: Materials that are susceptible to damage or contamination due to
temperature extremes, improper handling (movement and storage), or incorrect packing.
The materials include those that are perishable, clean, fragile, temperature sensitive,
hazardous chemicals
Clean Material: Any material or component that has been cleaned in a clean environment
and is intended for use in a clean environment.
PT BANYU BIRU SEJATI WATER & WASTE WATER TREATMENT CONTRACTOR
PRESERVATION PROCEDURE
4
Preservation Procedure
3. SCOPE OF WORK
There are some external factors which may cause damage during materials storage in
the warehouse or the place where they are kept prior to installation works started, such
as moisture content, water activity, and temperature.
This standard defines the principles and structure to ensure that equipment and material
are kept preserved during all phases of the project, before taken into the job site for
installation.
4. PERSONAL REQUIREMENT
Lifting and handling operator shall have certificate or license from authorized institution.
5. PACKING
a. Flexible joint shall be packed in covered wooden box as shown with the minimum
thickness of the lumber is 10 mm. Interior of crate is covered with plastic to protect
the flexible joint from any water damage.
Flexible joint shall be packed vertically to prevent damage to flange shall be in fully
close position for shipment.
b. The flexible joint must be packed in sea packing, water proof and must meet the
condition all of stages of transport (rail, road, air and sea). Packing shall be
properly and solidly made to afford the goods protection from any mechanical
and/or water damage that may be reasonably expected during transport.
PT BANYU BIRU SEJATI WATER & WASTE WATER TREATMENT CONTRACTOR
PRESERVATION PROCEDURE
5
Preservation Procedure
6. HANDLING
a. Lifting and handling of the crates shall be carried out by a fork lift truck, by means
of the appropriate fork hitches. The lifting shall be carried out in the lifting points
which have been marked on the crates.
b. The lifting and handling for each flexible joint shall be done using lifting equipment.
The sling and the hooking of the load must be carried out using the appropriate
tools (brackets, hook, fasteners, rope) and care to be taken to the balancing in
order to prevent the flexible joint from falling or moving during the lifting and
handling.
c. The lifting and handling of some flexible joint have to be carried out by using
appropriate means and at respecting the carrying limits. The handling must be
carried out on pallets, protecting the machined surface to avoid any damage.
d. Caution must be taken during the handling to avoid that this equipment passes
over the worker or any other place where a possible fall could cause personel
injury.
7. RESPONSIBILITY
Principally, the main equipment and material must be stored protected from direct
sunlight, heat, dust, dirt and humidity. If they cannot be stored in a building until they can
be installed, we recommend storing them under a shed or in the shadow and covered with
a tarpaulin to protect them from dust, sunlight, and rainwater based on the properly
Preservation Procedure.
The site manager and his or her designated representative are responsible to follow this
procedure. This is to make sure that preservation of the main equipment and material has
been implemented.
Application of this procedure in the job site is mandatory for PT Banyu Biru Sejati to
maintain the warranty.
PT BANYU BIRU SEJATI WATER & WASTE WATER TREATMENT CONTRACTOR
PRESERVATION PROCEDURE
6
Preservation Procedure
8. PRIOR INSTALLATION
All materials are packing correctly for standard land transportation before shipping. Plastic
wrapping is applied for some of electrical materials to prevent rust and dust which have
damage potential when in use.
The packing of all material must be checked 2-3 days before the date of installation. This
is to ensure they are still in good condition and ready to be installed in the job site. Any
damage or improper on the packing should be reported for action required.
When they are ready for site installation, unpacking steps are used to take out the
materials from their packing.
9. UNPACKING PROCEDURE
The materials are delivered to the job site in the standard packing for land transportation.
They must be unpacking to take out from their packing. The following steps may be used
for unpacking the materials for installation.
a. Provide the standard tools required, such as hammer, pincer, plier, crowbar, chain
hoist, etc.
b. Take the material from warehouse or the place where they have been stored
before to the job site according the requirement or order
c. Open the packing with suitable tools
d. Place the materials to the possible nearest installation place
e. Repacking the remaining materials when not all of them is used for installation
PT BANYU BIRU SEJATI WATER & WASTE WATER TREATMENT CONTRACTOR
PRESERVATION PROCEDURE
7
Preservation Procedure
10. PRESERVATION PRINCIPLE
The materials construction generally composed from metal and plastic/composite. As a
first fill requirement, there will sometimes oil, grease and liquid chemicals which is packed
separately from main components.
Flow of fresh air in the room or area where the materials are storage should be adequate.
This can be controlled by installing intake and exhaust ventilation fans. The temperature
is also should be maintain in the range of 20 – 35 °C.
When there is water activity near the materials storage location, attention must be taken.
The spilled or excessive water must be able to drain easily to the public sewage line. Any
spilled water on the floor for a long period of time can cause rust on the iron or other
metal. This must be avoided due to the electrical failure or malfunction may arise if
improper action applied. Periodically check carried out in weekly and monthly with the
repair and cleaning.
11. AFTER INSTALLATION
After the flexibel joint installation and before the line testing, it is recomended to perform
an accurate cleaning of the lines to eliminate dirt and any foreign objects that could
seriously jeopardize the tightness between joint and the correct operation of the flexible
joint.
***