Beisel Road - Overview0.8 mile dirt and gravel road off a major state
road (Mt. Bethel Garmany Rd.)Dead-end at USFS property31 different parcels on this road or accessed
from it
Beisel Road - History In 1981, non-exclusive easement acquired by USA for a
portion of what is now Beisel Rd In 1990, through a land exchange USA conveyed property
to William C. Sullivan, but retained ingress-egress rights along what was designated Forest Service System Road FSSR-1011
Subsequently, a cooperative agreement was made between USFS and Newberry County for maintenance along FSSR-1011 (Beisel Rd)
In 2009, residents requested paving of Beisel Rd through USFS and Newberry County, however, the road was not a County road
USFS supported the County assuming full maintenance of the road
By Ordinance, Newberry County no longer accepts new roads into its system that are not paved
Beisel Road – History (continued)Newberry County Council amended its Road
Paving Ordinance to allow the acceptance of unpaved roads that have been maintained continuously for at least 3 years by a government authority
In August 2010, 100% of property owners on Beisel Rd granted right-of-way required for Newberry County to accept the road and make it eligible for paving
October 20, 2010 Newberry County Council unanimously accepted Beisel Rd into its road system
Paving of Beisel RdWiden and Pave with Triple Treatment
20 ft driving surface6 ft shoulders6 in stone basePavement markings: lines and reflectors
Proposed Project CostsEngineering $39,000Construction $232,900TOTAL $271,900
Paving of Beisel RdProposed Source of Funds
USFS Title II Grant $135,950.00CTC C-Funds $135,950.00TOTAL $271,900.00
CTC has already committed $39,000 to initiate the engineering portion of this
project
Beisel Road – Program Oversight & Schedule
Newberry County will manage procurement & oversee construction in conjunction with a CTC Consultant
All payments, reimbursements, & recordkeeping will be processed by the Newberry County Finance Director
Proposed Schedule:Schedule Item Start Finish Duration
Engineering Phase 3/1/2011 5/1/2011 2 monthsAdvertise Construction Solicitation 5/1/2011 6/1/2011 1 month
Construction Bid Opening 6/1/2011 6/1/2011 0 days
Bid Award By County Council 6/1/2011 6/1/2011 0 days
Construction 7/1/2011 9/1/2011 2 months
Project Completion 9/1/2011 9/1/2011 0 days