September 24, 2015
Presentation to WS Realtors Association
![Page 2: Presentation WS REALTORS 092415 FINAL - wsrar.com...Contact Information Purpose and Need NCDOT – Jamille Robbins Public Involvement Group Leader 919-707-6085 jarobbins@ncdot.gov](https://reader036.vdocuments.us/reader036/viewer/2022070720/5ee12037ad6a402d666c1ef1/html5/thumbnails/2.jpg)
Today We Want to…
• Describe the proposed Business 40 plans,
• Discuss the Design Build process & clarify construction vs. closure,
• Talk to you about your needs prior to construction.
![Page 3: Presentation WS REALTORS 092415 FINAL - wsrar.com...Contact Information Purpose and Need NCDOT – Jamille Robbins Public Involvement Group Leader 919-707-6085 jarobbins@ncdot.gov](https://reader036.vdocuments.us/reader036/viewer/2022070720/5ee12037ad6a402d666c1ef1/html5/thumbnails/3.jpg)
New and Improved Business 40
![Page 4: Presentation WS REALTORS 092415 FINAL - wsrar.com...Contact Information Purpose and Need NCDOT – Jamille Robbins Public Involvement Group Leader 919-707-6085 jarobbins@ncdot.gov](https://reader036.vdocuments.us/reader036/viewer/2022070720/5ee12037ad6a402d666c1ef1/html5/thumbnails/4.jpg)
• Rehabilitate 4th Street bridge
• Replace and widen Peters Creek Parkway Bridge
• Remove EB slip ramp on Peters Creek
• Connect Gregory and Apple streets
• Replace Green Street Bridge with a pedestrian bridge
• Remove Broad Street ramps
• Modify High Street ramp
New and Improved Business 40
![Page 5: Presentation WS REALTORS 092415 FINAL - wsrar.com...Contact Information Purpose and Need NCDOT – Jamille Robbins Public Involvement Group Leader 919-707-6085 jarobbins@ncdot.gov](https://reader036.vdocuments.us/reader036/viewer/2022070720/5ee12037ad6a402d666c1ef1/html5/thumbnails/5.jpg)
• Remove Spruce Street bridge
• Modify interchange ramps at Cherry/Marshall
• Construct Liberty Street bridge over Business 40
• Construct The Strollway over Business 40
• Remove access to Liberty Street
• Modify interchange ramps at Main Street
New and Improved Business 40
![Page 6: Presentation WS REALTORS 092415 FINAL - wsrar.com...Contact Information Purpose and Need NCDOT – Jamille Robbins Public Involvement Group Leader 919-707-6085 jarobbins@ncdot.gov](https://reader036.vdocuments.us/reader036/viewer/2022070720/5ee12037ad6a402d666c1ef1/html5/thumbnails/6.jpg)
Preparing for the Design-Build Process
![Page 7: Presentation WS REALTORS 092415 FINAL - wsrar.com...Contact Information Purpose and Need NCDOT – Jamille Robbins Public Involvement Group Leader 919-707-6085 jarobbins@ncdot.gov](https://reader036.vdocuments.us/reader036/viewer/2022070720/5ee12037ad6a402d666c1ef1/html5/thumbnails/7.jpg)
One “team” is hired to design and construct the entire project. The team includes engineers,
designers and construction contractors.
NCDOT looks for creative methods of design, materials and construction from the D-B Team.
What is Design-Build?
![Page 8: Presentation WS REALTORS 092415 FINAL - wsrar.com...Contact Information Purpose and Need NCDOT – Jamille Robbins Public Involvement Group Leader 919-707-6085 jarobbins@ncdot.gov](https://reader036.vdocuments.us/reader036/viewer/2022070720/5ee12037ad6a402d666c1ef1/html5/thumbnails/8.jpg)
Design-Build Process BUSINESS 40 DESIGN-BUILD SCHEDULE
NOTE: A detailed construction and closure schedule will be available once the Design-Build Team is selected.
Project AdvertisedJanuary 2016 Shortlist
Design-Build Teams1st Qtr. 2016
Design-Build Team SelectedJuly 2016
Construction begins on Peters Creek Parkway and other local improvements.Late 2016/2017
“New and Improved” Business 40 Reopens
Project Completed
14
25
3
6 7
Business 40 closes*after Peters Creek Parkway is completed*Business 40 will be closed for NO MORE THAN 2 YEARS
![Page 9: Presentation WS REALTORS 092415 FINAL - wsrar.com...Contact Information Purpose and Need NCDOT – Jamille Robbins Public Involvement Group Leader 919-707-6085 jarobbins@ncdot.gov](https://reader036.vdocuments.us/reader036/viewer/2022070720/5ee12037ad6a402d666c1ef1/html5/thumbnails/9.jpg)
Why Design-Build? • Expedites project completion. • Typically results in costs savings*. • Encourages innovative designs. • Minimizes impacts to drivers. • Simplified Transportation Management Plan (TMP).
* Example: The D-B team may begin construction on one portion of the project while they finish the design and right of way acquisition on another.
![Page 10: Presentation WS REALTORS 092415 FINAL - wsrar.com...Contact Information Purpose and Need NCDOT – Jamille Robbins Public Involvement Group Leader 919-707-6085 jarobbins@ncdot.gov](https://reader036.vdocuments.us/reader036/viewer/2022070720/5ee12037ad6a402d666c1ef1/html5/thumbnails/10.jpg)
Design-Build Proposal Includes • Preliminary Transportation Management Plan –
maintenance of traffic. • Phasing Schedule – specifies “when” and “how”.
• Ex: Identifies which bridges will be constructed first, second, etc., and re-opened to traffic.
• Mobilization Plan – identifies how/where equipment will be set up.
• Date/length of closure. • Preliminary Roadway plans. • Aesthetics. • Bridge layouts.
![Page 11: Presentation WS REALTORS 092415 FINAL - wsrar.com...Contact Information Purpose and Need NCDOT – Jamille Robbins Public Involvement Group Leader 919-707-6085 jarobbins@ncdot.gov](https://reader036.vdocuments.us/reader036/viewer/2022070720/5ee12037ad6a402d666c1ef1/html5/thumbnails/11.jpg)
Two Phases of the Business 40 Project
![Page 12: Presentation WS REALTORS 092415 FINAL - wsrar.com...Contact Information Purpose and Need NCDOT – Jamille Robbins Public Involvement Group Leader 919-707-6085 jarobbins@ncdot.gov](https://reader036.vdocuments.us/reader036/viewer/2022070720/5ee12037ad6a402d666c1ef1/html5/thumbnails/12.jpg)
Phase 1- PCP and Local Improvements
1. Widen MLK, Jr. Boulevard between Marshall & Trade. 2. Construct temporary improvements at select intersections. 3. Reconstruct Peters Creek Parkway bridge over Business 40. 4. Improve intersection of Peters Creek Parkway & Academy.
US 52 Improvements Completion: 2016
W-S Traffic Signal Improvements Completion: 2016
Research Parkway Completed
Salem Creek Connector Completion: 2016
1
2
3
4
![Page 13: Presentation WS REALTORS 092415 FINAL - wsrar.com...Contact Information Purpose and Need NCDOT – Jamille Robbins Public Involvement Group Leader 919-707-6085 jarobbins@ncdot.gov](https://reader036.vdocuments.us/reader036/viewer/2022070720/5ee12037ad6a402d666c1ef1/html5/thumbnails/13.jpg)
• Repave entire 1.2 miles of Business 40 • Replace bridges, one and/or two at a time, depending on
phasing schedule
• Close Business 40 for up to two years
Phase 2 - Closure
![Page 14: Presentation WS REALTORS 092415 FINAL - wsrar.com...Contact Information Purpose and Need NCDOT – Jamille Robbins Public Involvement Group Leader 919-707-6085 jarobbins@ncdot.gov](https://reader036.vdocuments.us/reader036/viewer/2022070720/5ee12037ad6a402d666c1ef1/html5/thumbnails/14.jpg)
Reminders:
• Construction DOES NOT mean closure. • Peters Creek Parkway interchange and local
road work will be completed BEFORE Business 40 is closed!
• Liberty/Main and Cherry/Marshall one-way pairs CANNOT be closed at the same time.
![Page 15: Presentation WS REALTORS 092415 FINAL - wsrar.com...Contact Information Purpose and Need NCDOT – Jamille Robbins Public Involvement Group Leader 919-707-6085 jarobbins@ncdot.gov](https://reader036.vdocuments.us/reader036/viewer/2022070720/5ee12037ad6a402d666c1ef1/html5/thumbnails/15.jpg)
During the closure, there will be access into
downtown!
![Page 16: Presentation WS REALTORS 092415 FINAL - wsrar.com...Contact Information Purpose and Need NCDOT – Jamille Robbins Public Involvement Group Leader 919-707-6085 jarobbins@ncdot.gov](https://reader036.vdocuments.us/reader036/viewer/2022070720/5ee12037ad6a402d666c1ef1/html5/thumbnails/16.jpg)
US 52 Improvements Completion: 2016
Research Parkway Completed • 1st & 2nd Streets
• 5th Street • MLK Jr., Drive • Northwest Blvd. • Peters Creek Parkway • Academy Street • Research Pkwy/Salem Creek Connector • U.S. 52
Salem Creek Connector Completion: 2016
Downtown Roads to use during Closure
![Page 17: Presentation WS REALTORS 092415 FINAL - wsrar.com...Contact Information Purpose and Need NCDOT – Jamille Robbins Public Involvement Group Leader 919-707-6085 jarobbins@ncdot.gov](https://reader036.vdocuments.us/reader036/viewer/2022070720/5ee12037ad6a402d666c1ef1/html5/thumbnails/17.jpg)
Area Roads Available During Closure
![Page 18: Presentation WS REALTORS 092415 FINAL - wsrar.com...Contact Information Purpose and Need NCDOT – Jamille Robbins Public Involvement Group Leader 919-707-6085 jarobbins@ncdot.gov](https://reader036.vdocuments.us/reader036/viewer/2022070720/5ee12037ad6a402d666c1ef1/html5/thumbnails/18.jpg)
What do YOU need from us?
![Page 19: Presentation WS REALTORS 092415 FINAL - wsrar.com...Contact Information Purpose and Need NCDOT – Jamille Robbins Public Involvement Group Leader 919-707-6085 jarobbins@ncdot.gov](https://reader036.vdocuments.us/reader036/viewer/2022070720/5ee12037ad6a402d666c1ef1/html5/thumbnails/19.jpg)
Next Steps in 2015
• Continue meeting with stakeholders.
• Prepare quarterly newsletters.
• Coordinate with DWSP and Chamber on communication and marketing strategies.
• Refine social media strategies: • Web site: www.business40nc.com • Twitter: @NCDOT_Triad #Biz40NC
• Finalize aesthetics for bridges.
• Complete design specifications for D-B proposal.
![Page 20: Presentation WS REALTORS 092415 FINAL - wsrar.com...Contact Information Purpose and Need NCDOT – Jamille Robbins Public Involvement Group Leader 919-707-6085 jarobbins@ncdot.gov](https://reader036.vdocuments.us/reader036/viewer/2022070720/5ee12037ad6a402d666c1ef1/html5/thumbnails/20.jpg)
Purpose and Need Contact Information ! NCDOT
– Jamille Robbins Public Involvement Group
Leader 919-707-6085 [email protected]
– Pat Ivey, P.E. Division 9 Engineer
336-747-7800 [email protected]
– Cassandra Herndon Business Liaison 336-747-7833 [email protected]
! Consultant Team – Karen Simon Stakeholder Presentations
336-749-1411 [email protected]
! Web site: – www.business40nc.com
! Twitter: – @NCDOT_Triad #Biz40NC
! Email: – [email protected]