1/26/2010 1 Presentation to the McCall City Council January 28, 2010 McCall City Hall McCall Municipal Airport - Environmental Assessment January 28, 2010 McCall Municipal Airport - Environmental Assessment January 28, 2010 Welcome and Introductions John Anderson, Airport Manager, McCall Municipal Airport Project Overview Rainse Anderson, Project Manager, WHPacific Project Update Sarah Lucas, Project Planner, WHPacific Alternatives Comparison Rainse Anderson and Sarah Lucas Project Timeline Rainse Anderson and Sarah Lucas Question & Answer Session City Council and WHPacific

Upload: others

Post on 29-Jun-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Presentation to the McCall City Council › 141 › media › 113208.pdf · 1/26/2010 1 Presentation to the McCall City Council January 28, 2010 McCall City Hall McCall Municipal

1/26/2010

1

Presentation to the McCall City Council

January 28, 2010

McCall City Hall

McCall Municipal Airport - Environmental AssessmentJanuary 28, 2010

McCall Municipal Airport - Environmental AssessmentJanuary 28, 2010

� Welcome and Introductions� John Anderson, Airport Manager, McCall Municipal Airport

� Project Overview� Rainse Anderson, Project Manager, WHPacific

� Project Update� Sarah Lucas, Project Planner, WHPacific

� Alternatives Comparison� Rainse Anderson and Sarah Lucas

� Project Timeline� Rainse Anderson and Sarah Lucas

� Question & Answer Session� City Council and WHPacific

Page 2: Presentation to the McCall City Council › 141 › media › 113208.pdf · 1/26/2010 1 Presentation to the McCall City Council January 28, 2010 McCall City Hall McCall Municipal

1/26/2010

2

Purpose� Bring the runway/taxiway centerline separation at the Airport into compliance with FAA design standards.

Need� Improve airport safety, as the current runway/taxiway centerline separation is substandard.

Alternatives will:� Evaluate a runway/taxiway centerline separation of 240’, 300’ and 400’, including the no action alternative, for environmental impact.

McCall Municipal Airport - Environmental AssessmentJanuary 28, 2010

Since last City Council briefing (June 5, 2009) the following has occurred:

◦ WHPacific sent the City Council a memo with information requested at the June 5 meeting

◦ FAA sent letter to City Council regarding their position

◦ WHPacific sent the Airport a “next steps” memo

McCall Municipal Airport - Environmental AssessmentJanuary 28, 2010

Page 3: Presentation to the McCall City Council › 141 › media › 113208.pdf · 1/26/2010 1 Presentation to the McCall City Council January 28, 2010 McCall City Hall McCall Municipal

1/26/2010

3

� FAA will not support the 240-foot option� Doing so is a short term vision of the Airport

� 300-foot runway / taxiway separation is justified� FAA will consider USFS operations

� Constructing to C-II or C-III standard is a wise use of federal funds

� Support property acquisition needed for 400-foot separation

� Building the taxiway to C-II or C-III standard does not help justify a runway extension

� Current runway length is adequate to serve the critical aircraft through the planning period

� Support constructing taxiway to 50-foot width� Only at the 300- or 400-foot separation

McCall Municipal Airport - Environmental AssessmentJanuary 28, 2010

Aircraft Operations Data*

•IFR operations Feb 2007 to Feb 2008. Does not include USFS operations

McCall Municipal Airport - Environmental AssessmentJanuary 28, 2010

Page 4: Presentation to the McCall City Council › 141 › media › 113208.pdf · 1/26/2010 1 Presentation to the McCall City Council January 28, 2010 McCall City Hall McCall Municipal

1/26/2010

4

McCall Municipal Airport - Environmental AssessmentJanuary 28, 2010

Alternative 1Alternative 1Alternative 1Alternative 1 Alternative 2Alternative 2Alternative 2Alternative 2 Alternative 3Alternative 3Alternative 3Alternative 3 Alternative 4Alternative 4Alternative 4Alternative 4

(No Action) (No Action) (No Action) (No Action) (240’ x 50’) (240’ x 50’) (240’ x 50’) (240’ x 50’) (300’ x 50’) (300’ x 50’) (300’ x 50’) (300’ x 50’) (400’ x 50’) (400’ x 50’) (400’ x 50’) (400’ x 50’)

Meets FAA Runway/Taxiway No Yes Yes Yes

Separation Standards

Future Development Limitations

High Moderate Low Low

Wetland Impacts & Mitigation None $0 0.97 ac $160,000 1.39 ac $230,000 0.30 ac $49,500

Property Acquisition None $0 0.61 ac $85,000 8.16 ac + 7.91 ac

$1,122,000 +

16.07 ac $2,212,000 $1,090,000 =

$2,212,000

Taxiway Construction $0 $4,793,625 $4,812,825 $5,269,500

20-Year Maintenance Cost $1,072,750 $570,714 $579,286 $590,714

Overall Cost $1,072,750 $5,609,339 $7,834,111 $8,121,714

Financial Responsibility *State Grant Only if Available

City (100%) City (100%) City (2.5%) City (2.5%)

$1,072,750 $5,609,339 $195,853 $203,043

State Grant (0%) State Grant (0%) State Grant (2.5%) State Grant (2.5%)

$0 $0 $195,853 $203,043

FAA (0%) FAA (0%) FAA (95%) FAA (95%)

$0 $0 $7,442,405 $7,715,629

TaskTaskTaskTask TimelineTimelineTimelineTimeline

Finalize alternatives chapter 2 weeks after preferred alternative (PA)

Complete the environmental consequences chapter

3 weeks after PA

Prepare a wetlands functional assessment 2 weeks after PA

Identify possible wetland mitigation sites 12 weeks after PA

Prepare administrative draft EA 3 weeks after completion of the above tasks

FAA & City review of administrative draft EA 4-5 weeks for FAA / City review; 2 weeks for WHPacific to make revisions

Public reviews of Draft EA 45 day comment period

Final EA submittal & FONSI issuance* 4 weeks after public comment ends

* FONSI expected mid-August

McCall Municipal Airport - Environmental AssessmentJanuary 28, 2010

Page 5: Presentation to the McCall City Council › 141 › media › 113208.pdf · 1/26/2010 1 Presentation to the McCall City Council January 28, 2010 McCall City Hall McCall Municipal

1/26/2010

5

TaskTaskTaskTask TimelineTimelineTimelineTimeline

Final EA submittal & FONSI issuance Mid-August

Begin engineering for taxiway relocation & mitigation siteSeptember 20117 month duration

Phase I Bidding: Mitigation & north ½ of taxiway relocation April 2012

2 month duration

Phase I ConstructionJune 2012

5 month duration

Phase II Bidding: South ½ of taxiway relocationApril 2013

2 month duration

Phase II ConstructionJune 2013

5 month duration

Project CloseoutNovember 2013

2 month duration

McCall Municipal Airport - Environmental AssessmentJanuary 28, 2010

McCall Municipal Airport - Environmental AssessmentJanuary 28, 2010

Page 6: Presentation to the McCall City Council › 141 › media › 113208.pdf · 1/26/2010 1 Presentation to the McCall City Council January 28, 2010 McCall City Hall McCall Municipal

1/26/2010

6

McCall Municipal Airport - Environmental AssessmentJanuary 28, 2010

McCall Municipal Airport - Environmental AssessmentJanuary 28, 2010

Page 7: Presentation to the McCall City Council › 141 › media › 113208.pdf · 1/26/2010 1 Presentation to the McCall City Council January 28, 2010 McCall City Hall McCall Municipal

1/26/2010

7

McCall Municipal Airport - Environmental AssessmentJanuary 28, 2010