presentation to federal review team – application of ... · presentation to federal review team...
TRANSCRIPT
![Page 1: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/1.jpg)
Page 1 of 2
Canadian Nuclear Commission canadienne Safety Commission de sûreté nucléaire
P.O. Box 1046 Station B 280 Slater Street Ottawa, Ontario Canada K1P 5S9
C.P. 1046 Succursale B 280, rue Slater Ottawa (Ontario) Canada K1P 5S9
Meeting MinutesE-Docs #:3507296 File/Dossier:2.01
CEAR #: 07-05-29525Date: February 25, 2010
SUBJECT OBJET
Presentation to Federal Review Team – Application of Ontario Power Generations Plant Parameter Envelope to the Environmental Impact
Assessment
ATTENDEES
PARTICIPANTS
OPG Leslie Mitchell John Peters Donna Pawlowski MPMO Stephan Skocylas EC Sandro Leonardelli Duck Kim Dave Broadhurst Adelaide Wan
DFO Stephen Haayen Lisa Fowler Laurie Wood HC Melanie Lalani (phone) Kitty Ma (phone)
CNSC Andrew McAllister Sarah Watt Doug Miller (phone) CEA Agency Jill Adams Robyn-Lynne Virtue
LOCATION OF MEETING
ENDROIT DE LA RÉUNION
OPG Head Office 700 University Avenue
Toronto, Ontario Canada, M5G 1X6
Conference Room #4 (Mezzanine Level)
DATE February 25, 2010
TIME/HEURE 12:30 pm – 3:00pm
REMARKS
REMARQUES
1. Introductions, purpose of the meeting
The attendees introduced themselves and OPG went over the purpose of the meeting.
2. OPG Presentation to Government Department/Agencies Leslie Mitchell and John Peters (OPG) went through the presentation entitled “Purpose of the Plant Parameter Envelope within the New Nuclear at Darlington Environmental Assessment”. See attached.
3. Discussion
The discussion focused on the purpose of the Plant Parameter Envelope (PPE) and the information expected in the Environmental Impact Statement (EIS) and Licence to Prepare Site (LTPS).
The attendees discussed the development of the PPE approach. The discussions covered the following topics: sources of information for the PPE; environmental performance, space for site layout and level of detail
![Page 2: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/2.jpg)
Page 2 of 2
needed for the EIS.
The use of the bounding PPE for components of the project that are independent of the reactor technology, such as cooling technologies, were discussed. The attendees discussed how these were dealt with in the EIS with respect to the bounding PPE / assessment of alternative means.
Leslie Mitchell (OPG) explained the Infrastructure Ontario procurement process, including items such as length of process and timing of design details.
Doug Miller (CNSC) provided an overview of the mandate of the CNSC, how CNSC is reviewing the EIS and the LTPS and the mechanisms that link the two reviews. Andrew McAllister (CNSC) to provide a copy of CNSC Regulatory Policy P-223 to participants.
The attendees discussed their involvement in the EIS review and its implications for their approval and permitting of the project. This led to a discussion of the JRP process and how their reviews and recommendations could fit into the overall process.
MINUTES WRITTEN BY
Name(s)/Nom(s) : Sarah Watt
![Page 3: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/3.jpg)
Purpose of the Plant Parameter Envelope within the New Nuclear at Darlington
Environmental Assessment
February, 2010
![Page 4: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/4.jpg)
1
CNSC Licensing requirements for NND
NND Project for EA purposes
Plant Parameter Envelope description
Bounding framework and model plant layouts
Review Licensing steps & timelines for NND
Summary
Outline of the Presentation
![Page 5: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/5.jpg)
2 Technology Selection
In 2007 Infrastructure Ontario commenced the competitive bid process to select the preferred vendor who will deploy their standard design and construct NND.
Selection of the preferred vendor is being determined in a timeframe in parallel but independent of the EA schedule, on the understanding that the EA is the earliest step in the licensing process.
OPG has developed an approach that meets the EIS Guidelines without a technology specified
Once the preferred design is selected OPG will:
Receive, review and accept the detailed design;
Use results of the EA to confirm and inform the safety analysis and design as necessary;
Confirm the EA is bounding of the final design as part of the subsequent licensing processes.
![Page 6: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/6.jpg)
Regulatory Guidance – Licensing
Guidance provided indicates specific design need not be
selected at this licensing stage – high level design
information only:
CNSC INFO-0756 Licensing Process for Nuclear Power
Plants in Canada, section 4.2.1:
“An application for a Licence to Prepare Site does not require detailed
information or determination of a reactor design; however, high level design
information is required for the environmental assessment that precedes the
licensing decision for a Licence to Prepare Site. An application for a Licence to
Construct must contain more detailed information about the reactor design and
a supporting safety case”
OPG developed our Plant Parameter Envelope (PPE)
approach consistent with this direction.
3
![Page 7: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/7.jpg)
Regulatory Guidance – Licensing – cont’d
CNSC RD-346 Site Evaluation for New Nuclear
Power Plants
Section 4.0: “as the first step in establishing a new NPP, site evaluation
takes into account all phases of the NPP life cycle, from site preparation
to abandonment.”
Figure 4.1 indicates high level design information required at this stage.
4
Section 5.1: “Proposed NPP designs
are evaluated against applicable
safety goals, taking into account the
characteristics of the site, the risks
associated with external hazards,
and the potential impact of the NPP
on the environment.”
![Page 8: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/8.jpg)
Regulatory Guidance – Licensing – cont’d
EIS Guidelines Appendix 2 (guidance on LTPS
Application requirements) notes the possibility of
more than one type of plant/design being under
consideration
For General Nuclear Safety and Control Regulation
3(1)(d), guidance indicates that “the plant description
should include:
List of plant types/designs under consideration3”
(footnote indicates this is not mandatory information for the LTPS)
OPG developed our Plant Parameter Envelope (PPE)
approach consistent with this direction.
5
![Page 9: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/9.jpg)
Regulatory Guidance – EA
CEAA provides the following
Purpose of the Act:
4.(1)(a) “to ensure that projects are considered in a careful and precautionary
manner before federal authorities take action in connection with them, in
order to ensure that such projects do not cause significant adverse
environmental effects”
Timing of Assessment:
11. (1) Where an environmental assessment of a project is required, the
federal authority referred to in section 5 in relation to the project shall ensure
that the environmental assessment is conducted as early as is practicable in
the planning stages of the project and before irrevocable decisions are made,
and shall be referred to in this Act as the responsible authority in relation to
the project.
OPG commenced EA as directed by the Province of Ontario, as early as
practical in the planning stages of the project consistent with the CEAA
direction.
6
![Page 10: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/10.jpg)
Regulatory Guidance – EA Guidelines
2.1 Environmental Assessment as a Planning Tool:
“Environmental assessment is a planning tool used to ensure that projects are
considered in a careful and precautionary manner in order to avoid or mitigate the
possible adverse effects of development on the environment and to encourage
decision-makers to take actions that promote sustainable development and thereby
achieve or maintain a healthy environment and a healthy economy.”
7.2 Alternatives to the Project:
“An analysis of alternatives to the project must describe functionally different ways to
meet the project’s need and achieve the project’s purpose from the perspective of the
proponent. This section must therefore identify and discuss other technically and
economically feasible methods of producing electricity other than the construction and
operation of the OPG Darlington NNPP that are within the control and/or interests of
OPG.”
7.3 Alternative Means of Carrying out the Project:
“The EIS must identify and describe alternative means to carry out the project that are,
from the perspective of the proponent, technically and economically feasible.”
7
![Page 11: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/11.jpg)
8 Scope of the Project for EA Purposes
• Preparation of the Darlington Nuclear Site for up to four nuclear power reactors and associated facilities;
• Construction of the nuclear reactors and associated facilities;
• Construction of the appropriate nuclear waste management facilities;
• Operation and maintenance of the new nuclear reactors for approximately 60 years of full power electricity production
• Operation and maintenance of the appropriate nuclear waste management facilities; and
• Prepare preliminary plan for decommissioning and eventual abandonment of the nuclear reactors and associated facilities.
Note: The Project Scope for EA Purposes is defined for this stage of the planning process.
![Page 12: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/12.jpg)
9 Organization of the PPE
The PPE groups over 200 prorated values:
Site parameters;
Reactor Class Specific parameters;
Vendor Design Specific parameters.
![Page 13: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/13.jpg)
Derivation of the PPE for NND EA
PPE is a composite representation constructed to describe a range of
different nuclear plant designs by using the most limiting values provided
by the vendors of the different designs under consideration for each
parameter in the PPE;
Limiting values range from specific values, to ranges, or may be generic,
e.g., “meets regulatory requirements”;
Result is a “Model Plant” that provides a composite description based on
the bounding limit of reactor design impact for the range of plants designs
and the associated facilities included in the PPE;
Composite PPE Model Plant will have greatest effects based on the limiting
PPE design parameters, while the effects of an actual plant once designed
for the site will be less that the impact predicted based on PPE.
EA assessment of the effects of Model Plant will be bounding for any
specific plant that falls within the range of the composite PPE values.
10
![Page 14: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/14.jpg)
11 Summary of PPE Parameters used by NND
Site Parameters – parameters related to the impact of
the site on the plant, as assumed in the plant designs
Examples: snow load, earthquakes, design basis tornado
Reactor Class Specific (RCS) – parameters that are
similar within each reactor class (PWR, PHR)
Examples: fuel enrichment, total mass of zirconium alloy in core,
heaviest construction shipment
Vendor Design Specific – parameters which address
radiological effects due to nuclear fuel
Examples: Airborne effluent, liquid radwaste, solid radwaste
![Page 15: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/15.jpg)
12 Sample Site Parameters
Parameter Limiting ValueLimiting Reactor
Maximum rain fall rate 400 mm/d
100 mm/h
30 mm/15 min
ACR-1000
Snow and ice load 3000 Pa ACR-1000
Peak ground acceleration
0.3 g EPR, AP1000, ACR-1000
Maximum ground water -1 m EPR
Basic wind speed 232 km/h EPR, AP1000
Design Basis Tornado (DBT) max wind speed
368 km/h EPR
DBT radius of maximum rotational speed
46 m ACR-1000
DBT max pressure drop 8274 Pa EPR
![Page 16: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/16.jpg)
13
Sample Reactor Class Specific Parameters:
Plant Characteristics
Parameter PWR
Limiting Value
PWR Limiting Reactor
PHR
(ACR-1000)
Electrical Output
1708 MW EPR 1165 MW gross
1085 MW net
Thermal Power
4590 MW EPR 3200 MW
Capacity Factor
94% EPR >95% annual
>90% lifetime
Design Life 60 years All 60 years
Building Height
71.3 m AP1000 65.8 m
Foundation Embedment
12.7 m EPR 13.5 m
![Page 17: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/17.jpg)
14
Sample Reactor Class Specific Parameters:
Construction
ParameterPWR
Limiting value
PWR Limiting Reactor
PHR
(ACR-1000)
Module dimensions
Length 28.35 m
Width 25 m
Height 27.43 m
Diam. 39.62 m
AP-1000 Length 17.37 m
Width 10.1 m
Height 10.45 m
Longest item Length 40 m
Heaviest construction shipment
861.8 metric tons
AP-1000 422 metric tons
(on land)
1600 metric tons
(by water)
800 metric tons
(calandria)
Laydown area
12.6 acres EPR 32.9 acres
Construction population
4200 EPR 2000 to 2500
![Page 18: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/18.jpg)
15
Sample Vendor Design Specific Parameters:
Normal Operating Source Term
Parameter EPR AP-1000 ACR-1000
Normal gaseous emission source term
1.77 1015 Bq/y 4.08 1014 Bq/y 5.9 1013 Bq/y
Gaseous H-3 emission
6.67 1012 Bq/y 1.295 1013 Bq/y 5.0 1013 Bq/y
Liquid source term
7.15 109 Bq/y 9.46 109 Bq/y 2.1 1010 Bq/y
Liquid H-3 source term
6.14 1013 Bq/y 3.74 1013 Bq/y 1.2 1014 Bq/y
![Page 19: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/19.jpg)
16 Sample PPE Values and Usage
Parameter Value Where Used
1.1.1 Building Height
71.3 m
(AP1000)
LTPS / EIS: Site Evaluation of the OPG New Nuclear at Darlington – Part 2: Dispersion of Radioactive Materials In Air and Water
EIS: Section 3.1, Table 3.1-2 – Airborne Release Parameters (for estimation of public dose due to normal operation)
(Table 2) Number of Reactor Units On Site
3 EPR
4 AP1000
4 ACR-1000
LTPS / EIS :Exclusion Zone Determination for Darlington New Nuclear Project
LTPS: Section 4.0 Conclusions
2.6.2 Cooling Water Flow Rate (once-through cooling)
228,400 L/s
(4 ACR-1000)
EIS: Aquatic Environment Assessment of Environmental Effects TSD NND EA, Section 2.2.1, Project Basis for Assessment, page 2-2
![Page 20: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/20.jpg)
17
The PPE is a tabular set of data that:
Creates a Model Plant derived from publicly available
vendor information for multiple reactor designs being
considered;
Model Plant as defined includes range of design elements to
identify the most limiting values for assessment purposes;
Provides a bounding envelope of plant design and site
parameter values for use in the Licence To Prepare Site
(LTPS) Application and Environmental Assessment (EA);
Plant Parameter Envelope Summary
![Page 21: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/21.jpg)
18 PPE & Alternative Means
Plant Parameter Envelope approach allows EA to examine any of the potential designs within the bounding envelope of the Model Plant;
Practicable ways of completing the project are bounded by the model plant – in some cases, additional options are considered;
Bounding envelope was found to not result in significant adverse effects on the environment;
Advantages and disadvantages of alternative means described in EIS were assessed in the following manner:
Radiological emissions, accidents and malfunctions were considered for each of the proposed designs. Reactor designs and number of units are incorporated in the Model Plant and not considered as options.
Used Fuel Interim Storage is part of the specific design and not considered as options.
Low and Intermediate Radioactive Waste Interim storage locations options considered. Volume determined from the PPE Model Plant
Excavated material management options considered and volumes derived from bounding site layouts.
Condenser Cooling options compared and preference selected.
![Page 22: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/22.jpg)
19 PPE & Model Plant Layouts
PPE values used to derive Model Plant were also used
to derive bounding site development layouts;
Model Plant Layouts described are reasonable maximum
extent of key layout parameters:
Maximum footprint of four reactors;
Maximum extent of land required for atmospheric cooling;
Maximum soil excavation required.
Maximum values were derived for various works and activities and
used for assessment of effects (e.g., maximum soil excavated) for
the individual environmental components;
EA bounds the conditions defined collectively by the three model
plant layout scenarios (a composite Model Plant Layout).
![Page 23: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/23.jpg)
20 PPE Conclusions
The PPE provides bounding values for “Model Plant” based on
multiple vendor inputs:
defines the bounding conditions to capture the worst case
environmental effects for consideration in the EA;
Model Plant facilitates robust evaluations before a reactor design has
been selected, and ensures actual design will have less effects;
Approach is consistent with CNSC licensing requirements.
PPE used by OPG to support the EA and the LTPS Application for the
OPG NND Project:
PPE is a living document which OPG will maintain;
PPE represents licensing limits within a modern regulatory framework
that features built-in margins;
PPE will be used to confirm selected technology is bounded by
present/updated evaluations.
![Page 24: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/24.jpg)
21 CNSC Licensing Steps going forward
Once EA approval granted, there are several
subsequent licensing steps
Each licence may contain conditions OPG must
adhere to, or hold points where approval must be
obtained to proceed
New Nuclear Power Plant:
• Licence to Prepare Site
• Construction Licence
• Operating Licence
New Nuclear Waste Facility
• Construction Licence
• Operating Licence
![Page 25: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/25.jpg)
The Licensing Review Process22
![Page 26: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/26.jpg)
EA & Licensing Process Overview
(CNSC INFO-0756)23
![Page 27: Presentation to Federal Review Team – Application of ... · Presentation to Federal Review Team – Application of Ontario Power ... with respect to the bounding PPE / assessment](https://reader036.vdocuments.us/reader036/viewer/2022070923/5fbb5a5487e3f2010470f723/html5/thumbnails/27.jpg)
Conclusion
In initial planning phases, EA and Licence to Prepare
Site can be approved without a specific technology
being selected;
PPE approach ensures the EA adequately considers
alternatives, assessing the “worst case” Model
Plant;
Subsequent licensing steps provide adequate
opportunity to ensure the actual design fits within
the bounding scenarios,
Effects are minimized through appropriate licence /
permits / authorization process
24