presentation slides: collaboration on the thermal modeling ...steering committee chair: hatice...
TRANSCRIPT
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m
Aladar A. CsontosTechnical Executive
September 18, 2019
NRC NMSS REGCON
Collaboration on the Thermal Modeling/Fuel Performance Nexus Path Forward to Improving Safety and Operational Benefits
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m2
ESCP Thermal Modeling Subcommittee: R&D Activities
Stee
ring
Com
mitt
eeCh
air:
Hatic
e Ak
kurt
(EPR
I)St
eerin
g Co
mm
ittee
Chai
r: Ha
tice
Akku
rt (E
PRI)
CISCC SubcommitteeChair: Shannon Chu (EPRI)
CISCC SubcommitteeChair: Shannon Chu (EPRI)
NDE SubcommitteeChair: Jeremy Renshaw (EPRI)
Vice-Chair: Randall Granaas (SCE)
NDE SubcommitteeChair: Jeremy Renshaw (EPRI)
Vice-Chair: Randall Granaas (SCE)
Canister Mitigation/Repair SubcommitteeChair: Gary Cannell (Fluor)/Jon Tatman (EPRI)
Canister Mitigation/Repair SubcommitteeChair: Gary Cannell (Fluor)/Jon Tatman (EPRI)
Fuel Assembly SubcommitteeChair: Mike Billone (ANL) /
Vice-Chair: Sven Bader (Orano)
Fuel Assembly SubcommitteeChair: Mike Billone (ANL) /
Vice-Chair: Sven Bader (Orano)
Thermal Modeling SubcommitteeChair: Al Csontos
Vice-Chair: Sam Durbin
Thermal Modeling SubcommitteeChair: Al Csontos
Vice-Chair: Sam Durbin
International SubcommitteeChair: Jose Conde (Enusa)
Vice-Chair: Brady Hanson (PNNL)
International SubcommitteeChair: Jose Conde (Enusa)
Vice-Chair: Brady Hanson (PNNL)
Phase IBWR DCS
Simulator
NRC/ DOE Lead
Phase IIHBU DemoProject
EPRI Lead
Phase IIIHorizontal Simulator
DOE Lead
Bringing It All TogetherPhenomena Identification
Ranking Table (PIRT)
Gap Analysis
EPRI Lead
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m3
Stakeholder Spent Fuel Integrity: R&D Activities Since 2000, substantial domestic and international R&D to
assess SNF integrity for storage, transportation, and disposal: – High Burnup Demo/Sibling Rod Testing ─ NFIR Testing– ORNL CIRFT Testing ─ SCIP Testing (Studsvik)– ANL Hydrided Cladding Testing ─ SPAR (IAEA)– Other tests (KAERI, CRIEPI, etc.) ─ Thermal Modeling General results:
– Temperatures and pressures lower than originally understood– Cladding more robust and less susceptible to degradation PIRT Gap Analysis (EPRI Lead):
– Use NRC accepted process to put the global R&D results into practice– Thermal Modeling, Decay Heat Modeling, and Fuel Performance
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m4
Benefits of Improved Thermal Methodology Occupational dose benefits:
– Temporary shielding restrictions (blankets)– Time limits to keep mating device door open
Dry storage operational benefits:– More flexible SNF loadouts– Drying time limits and time to boil– Supplemental cooling requirements– Vent surveillance requirements– Fuel and canister degradation mechanisms– Risk informing aging management
Reactor operations/safety benefits:– Reduced SFP temperatures/time-to-boil
Accelerate decommissioning:– Active to passive cooling of SNF
Informs repository loading footprint
Time to Boil Calculations
(SFP)
Fuel Loading into
Storage
Degradation Mechanisms Dry Storage
Repository
Decommissioning
Transportation
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m5
Thermal Measurements – Transient Data from LoadingTransient Peak Cladding Temperature (Cell 14) = 237°C
Video provided by ORNL
40 80 120 160 200 240Celsius
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m6
Phase II: Thermal Modeling Key TakeawaysDLB
Margin
Cell 14 (Hottest Cell) Reasonable surface temperatures Reasonable PCT axial distribution shape Best-estimate PCT biased to higher temps
due to limiting design licensing inputs Best-estimate vs. Licensing Basis Inputs:
– Decay Heat Loadouts: Assume upper bound– Ambient Temps: Assume upper bound– Cask/Canister Design Features (gaps, etc.)
Margins exist between best-estimate vs. limiting design licensing basis models:– Quantifying input sensitivities is the key to
technical/regulatory strategy to gain margins
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m7
Phase II: Key Takeaways Steady state PCTs from all models and measurements
significantly lower than the design licensing basis:
Parameter FSAR LAR Best-Estimate
HBU Cask Measurements
PCT (model vs data) 348°C 318°C 254-288°C 229°C
Heat Loadouts 36.96kW 32.934kW 30.456kW 30.456kW
Ambient Temperature 100°F 93.5°F 75°F 75°F
Design Specifics Gaps Gaps Gaps No Gaps?
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m8
Thermal Modeling Technical/Regulatory Strategy Goals PIRT Product Objectives:
– Provide an independent, objective, and technically defensible reference from a committee of recognized subject matter experts
– Provide technical insights for developing margin assessments– Assist in defining and prioritizing R&D testing and modeling needs PIRT Scope:
– Focused and Technically Driven with Recognized Subject Matter Experts– Thermal & Decay Heat Modeling / Fuel Performance Nexus (PCT Limit) Project Goals:
– Streamlined regulatory path – Reduced model DLB input penalties– Improved operational flexibilities – Improved Thermal Models
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m9
Steering Committee
NRC/DOE/EPRI/ Stakeholders
Project Manager(s)Al Csontos (EPRI)
Thermal Model Inputs & Uncertainty
Quantification TeamDavid Richmond (PNNL)
Decay Heat Modeling & Uncertainty
Quantification TeamHatice Akkurt (EPRI)
Fuels/Cladding Performance &
Uncertainty Quantification TeamKeith Waldrop (EPRI)
Esta
blish
Com
mitt
ee S
cope
, Lea
ders
hip,
and
SM
Es
SME
Deve
lop
PIRT
s, An
alys
es, &
Rep
ort
Roles & ResponsibilitiesDefine the problem (e.g., licensing, operational, or programmatic)Define the specific objectives Define the hardware and scenarioDefine the evaluation criterion Ensure resources are available - experts and expert reviewers to participate on panel(s)
Roles & ResponsibilitiesProject management of the Committee members to achieve the PIRT objectives
Roles & ResponsibilitiesIdentify plausible phenomena Identify & review available tech dataRank importance and rationalesAssess phenomenon uncertainty Develop Independent PIRT report
Proj
ect
Man
agem
ent
PIRT StructureMichael Layton (NRC)Ned Larson (DOE)Sylvia Saltzstein (SNL)Randy Stark (EPRI)Jeremy Renshaw (EPRI)Suzanne Leblang (Entergy Services)Zita Martin (TVA - Holtec)Neil Fales (3 Yankees - NAC)Steven Edwards (Duke Energy - Orano)
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m10
PIRT Activities and Path Forward Steering Committee Meetings:
– March and July 2019 Resolved steering committee feedback:
– Multiple charter revisions and meetings to address comments Joint Agreement of the Charter and Team Leadership/Members:
– Team leadership meetings to coordinate PIRT next steps– Provide PIRT Questionnaire to send to the team SME members Schedule:
– PIRT Expert Panel Meetings: October 2019– Draft Final PIRT Report: March 2020– Final PIRT Report: June 2020
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m11
Thermal Modeling Technical/Regulatory Nexus
Near Term (1 Year): Vendor Amendments
PIRT/Gap Analysis:• ▪ Thermal Model Gaps Q2:• - Thermal Model Inputs• - Decay Heat Models• ▪ Examine approaches for
immediate utility impacts▪ Provide technical basis for
• regulatory decision-making• ▪ PIRT Report Q2 2020 • ▪ Implement through vendor
amendments and/or 72.48
Mid Term (1-2 Years): ISG-11 R3 PCT Limits
PIRT/Gap Analysis:▪ Fuel Performance:
- NUREG-2224 HBU Report- DOE CIRFT/Sister Rod Tests- HBU Demo Gas Sampling
Regulatory Vehicle:▪ NRC Reg Guide or Topical
Report for NRC Review▪ Vendor amendments
Long Term: Topical Report
Topical Report for NRC Review: ▪ Establish generic approach for
use of actual data vs. designlicensing basis approach forthermal and other modeling
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m12
Summary
400350300250Temperature, °C
Axia
l Ele
vatio
n Design Basis vs.
Actual Margin PCTMargin
Overall Thermal Margins
High Burnup Demo: An Opportunity• Cask Loaded in 2017• Data used for blind benchmarking of models• Data supports license renewals
Biases Identified in Thermal Models• 25-90°C bias in best-estimate models• Licensing models biases of 80°C to >100°C• PIRT as a vehicle for regulatory considerations
Next Steps• Hold PIRT meetings (Q4 2019)• PIRT Report (2020)• Possible Topical Report (2022)
© 2019 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m13
Together…Shaping the Future of Electricity