    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    TITRE

    Electricity BalancingFramework Guidelines

    Presentation ofDraft for consultation andInitial Impact Assessment

    29/05/2012Presentation of Draft Framework Guidelines

  • 7/28/2019 Presentation of Draft FGEB

    2/24

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    EBFG process

    . Scoping phase (from April 2011 to December 2011) 7 NRAs drafting team meetings;

    3 expert group meetings;

    1 workshop in Ljubljana.

    . Letter from EC to submit the EBFG (18 January 2012) EBFG is expected to be finalised by 18 July 2012.

    .Consultation phase until 25 June 2012, 12:00

  • 7/28/2019 Presentation of Draft FGEB

    3/24

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    Expected timeline

    Draft FrameworkGuidelines positively

    evaluated by ACER BoR

    April

    May

    July

    August

    September

    June

    End 2012

    Publicconsultation

    Evaluation of

    responses fromstakeholders

    Start of draftingElectricity Balancing

    Network Code(s)by ENTSO-ELast changes

    in texts

    Presentation of

    Draft FG

    29 May

    End of publicconsultation

    25 June

    ACER final approval

  • 7/28/2019 Presentation of Draft FGEB

    4/24

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    . Roles & responsibilities, including support involvement ofconsumption;

    .Harmonised technical specifications to facilitate offering acrossbalancing areas, compatible products & timeframes, harmonisedrules for remuneration of offers;

    . Harmonised and non-discriminatory framework for imbalancesettlement;

    . Rules for the use of cross-border capacities.

    Scope of Framework Guidelines(Invitation letter from EC)

  • 7/28/2019 Presentation of Draft FGEB

    5/24

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Initial Impact Assessment1. Policy objectives

    . Guarantee / enhance operational security How does the proposed option affect short term operational security?

    . Improve competition in balancing markets What is the impact of the proposed option on competition?

    . Increase social welfare What is the impact of the option on the overall social welfare?

    . Facilitate the integration of intermittent generation What is the impact of the option on the integration of IG? Does it hamper the further IG deployment?

  • 7/28/2019 Presentation of Draft FGEB

    6/24

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Integration / harmonization

  • 7/28/2019 Presentation of Draft FGEB

    7/24

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Identified options

    OPTION A: status quo

    . Continuing the current voluntary approach;

    . Projects as BALIT and GCC will continue to developbut without any further harmonization at Europeanlevel

    . Possibly a fully integrated balancing marketimpossible to be achieved

  • 7/28/2019 Presentation of Draft FGEB

    8/24

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Identified options

    OPTION B: European exchange with minimumharmonization requirements

    .Identification of selected cross border products to beexchanged

    . Key concept: exchanges of surpluses both for energyand reserved

    . Implementation models:BSP-TSOTSO-TSO without common merit orderImbalance netting

    .Minimum harmonisation

  • 7/28/2019 Presentation of Draft FGEB

    9/24

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Identified options

    OPTION C: European exchange of balancingservices by means of a defined(medium/high)level of harmonization ofNational arrangements

    . Key elements harmonized (products, PTU, GCT etc)Settlement?

    . Key concept: every available resource (consideringnetwork constraints) is shared in the common merit

    order possible use of margins

    . Implementation models:Imbalance nettingTSO-TSO with common merit order (activation of replacement reservesand frequency restoration reserves)

  • 7/28/2019 Presentation of Draft FGEB

    10/24

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Identified options

    OPTION D: Single European balancingmechanism possible creation ofsupranational TSOs

    .Market design harmonized (BSP, BRP, procurementand settlement) at least at synchronous area level

    . Key concept: fully integrated market

    .Main advantages: guarantee that the most efficientresources are used, optimization of reserves througha centralized sizing and procurement, commonmanagement of the system also in critical situation

  • 7/28/2019 Presentation of Draft FGEB

    11/24

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Initial Impact AssessmentAssessment of policy options

    Criteria Option A Option B Option C Option D

    Effectiveness

    Security of supply - + + ++

    Competition - + ++ +++

    Social welfare - + ++ ++

    Renewables -- + ++ + +

    Time of implementation ++ - -- ---

    Efficiency - + ++ +

    Coherency - + ++ +

  • 7/28/2019 Presentation of Draft FGEB

    12/24

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Initial Impact AssessmentMedium term preferred policy option

    While Option D is considered the most efficient, Option Cseems the only possible to be implemented in the mid term

    Responsibility to balance the system remains at NationalTSOs

    Margins should have limited effects on overallefficiency and should progressively decrease

    Amount of procured balancing reserves shouldprogressively decrease

    Other key harmonization areas: products, pricing method,

    imbalance settlement Exchange of reserves less prescriptive Reservation of interconnection capacity: only upon a

    duly detailed cost benefit analysis

  • 7/28/2019 Presentation of Draft FGEB

    13/24

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Main objectionWHY NOT START FROM OPTION B?

    . Indeed Option B may represent a first interestingstep, but

    . Not enough guarantees of improving system efficiency;

    . Not a real integration, lack of control on actually activatedbids;

    . Only most expensive resources to be made available

    . Suboptimal use of balancing resources and transmissioncapacity

    . Insufficient expected increase in social welfare

    . Long implementation process (to create compatible cross-border products) with limited gains

  • 7/28/2019 Presentation of Draft FGEB

    14/24

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Study commissioned by the EC

    .Intended to assist ACER in drafting the ImpactAssessment

    .Analysis on the feasibility and on technical,economic and social impacts of the identifiedoptions

    .Quantitative assessment to support strategicdecisions

    .Main inputs expected at the end of theconsultation phase

  • 7/28/2019 Presentation of Draft FGEB

    15/24

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Framework GuidelinesTHE SCOPE

    . General provisions Scope, links and interdependencies, existing arrangements

    . General principles NRAs, TSOs, BSPs, BRPs, transparency, reporting

    . Procurement of balancing services Activation and cross-border exchanges of balancing energy Procurement and cross-border exchanges ofreserves

    .Reservation and use of interconnection capacity for balancing Underlying grid model, use and reservation

    . Balance responsibility and imbalance settlement

  • 7/28/2019 Presentation of Draft FGEB

    16/24

  • 7/28/2019 Presentation of Draft FGEB

    17/24

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Framework GuidelinesMAIN ELEMENTS: BALANCING ENERGY

    Harmonisation of products (with possible local specificities)

    Common principles for the pricing method (marginal pricing) and selection process (MeritOrder)

    Harmonisation of intraday gate closure times, as close to real time as possible

    Activation of balancing energy

    Cross-border exchanges of balancing energy

    No guideline on Frequency Containment Reserves FCR (Primary Control)

    Step 1 : imbalance netting between adjacent control areas;

    Step 2 : coordination to optimise the activation of Replacement Reserves RR;

    Step 3 : coordination to optimise the activation of Frequency Restoration Reserves FRR.

    BASE : TSO to TSO model with a common merit order

  • 7/28/2019 Presentation of Draft FGEB

    18/24

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    3 YEARSBalancing energy from RR

    - Possible margins for TSOs

    - Possible regional approach

    Coordination between TSOs

    to activate FRR and reduce costs

    SECURITY:

    Unless a CBAdemonstratesthat it is notpositive

    5 YEARS at the latestBalancing energy from FRR

    Optimisation

    in using

    automatic

    reserves

    Framework GuidelinesTHE PROPOSED ROADMAP

    - No margin for TSOs

    - European-wide

    7 YEARS at the latestBalancing energy from FRR & RR

  • 7/28/2019 Presentation of Draft FGEB

    19/24

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    Consultation questions

    PRICING METHODOLOGY

    Do you consider that harmonisation of the pricingmethod is a prerequisite to establish a TSO-TSOmodel with common merit order list for balancing

    energy? Do you support PAC principle?

    MARGINS

    Do you think that margins should not exceedthe reserve requirements needed to meet the

    security criteria which will be defined in networkcodes related to System Operation?

  • 7/28/2019 Presentation of Draft FGEB

    20/24

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    Consultation questions (2)

    IMPLEMENTATION MODELS

    Do you support to aim at similar target models forFRR and RR? Do you think appropriate to

    distinguish manually and automatically activatedFRR reserves in terms of target model or timing ofimplementation ?

    Do you support the proposed timing for

    implementation?REGIONAL APPROACH

    Do you consider regional implementation asrelevant milestones which are to be aimed at?

  • 7/28/2019 Presentation of Draft FGEB

    21/24

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    Framework GuidelinesMAIN ELEMENTS: BALANCING RESERVES

    Harmonisation of products (with possible local specificities)

    Common principles for the procurement process (relation to BSPs)

    Coordination between TSOs for the sizing of reserves according to LF code provisions

    Procurement of contracted reserves

    Cross-border exchanges of contracted reserves

    If reservation of cross border capacity isneeded, it will allowed only where it can be

    demonstrated it would result in increasedoverall social welfare

    Subject to CBA performed by TSOsand submitted to NRAs for approval

    No charge for the use of XB capacity for theexchange of balancing energy after IGC

    Capacity for day ahead trade Capacity for AS

    Marginal value of

    capacity for day

    aheadtrade

    Optimalallocation

    Marginal value of

    capacity for trade

    withAS

  • 7/28/2019 Presentation of Draft FGEB

    22/24

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Framework GuidelinesINCENTIVES and BALANCE RESPONSIBILITY

    Marginal pricing = stronger incentives to participate and to be balanced

    NC to oblige Balance responsible parties (BRPs) to be balanced in day-ahead timeframe

    BRPs to be incentivised to be balanced in real time No special treatment for RES

    ENTSO-E to assess (CBA) the need to harmonise imbalance settlement period at European-level

    Balance responsibility and imbalance settlement

    Transparency

    Consistent with ERGEGs proposal to EC with respect to balancing data

    Derogations

    Possible derogations can be granted by national regulators

    Maximum period of 2 years

  • 7/28/2019 Presentation of Draft FGEB

    23/24

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    Consultation questions (3)

    PRICING

    Do you support pay-as-cleared / marginal pricingprinciple?

    SETTLEMENT

    Do you consider important to harmonizeimbalance settlement? Do you think the EBFGshould be more specific on how to do it?

  • 7/28/2019 Presentation of Draft FGEB

    24/24

    ELECTRICITY BALANCING FRAMEWORK GUIDELINES

    Presentation of Draft FG on Electricity Balancing, 29.5.2012

    Thank you for

    yourattention

    Thank you for your attention!