presentation for cmeq committee – june 26, 2017 · 2017-06-27 · presentation for cmeq committee...

36
1 Presentation for CMEQ Committee – June 26, 2017

Upload: others

Post on 01-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

1

Presentation for CMEQ Committee – June 26, 2017

Page 2: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

INTRODUCTION

2

• The Problem• The Express Lane Option• The Project Specifics• The Environmental Process• What’s ahead

Page 3: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

3

BIG PICTURE

• The Caltrain Electrification Project will not fully address projected demand

• SAMTRANS is studying express bus service on the 101 corridor• VTA is in final design to create a 2+ HOV Express Lanes from

south of 85 to the San Mateo County line• SFCTA is studying an extension of the 101 managed lanes into

San Francisco• MTC is planning to improve and increase Park and Ride lots• Municipalities implementing TDM measures

The problem is greater than one project can solve.

Page 4: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

4

THE PROBLEM

• Jobs, housing and population growth continue

• Vehicle trips to grow 4-7% by 2020

• No incentive to share a ride

• Cars avoid the freeway

The congestion on 101 has been bad and will continue to get worse.

Page 5: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

5

THE BACKUPS

Page 6: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

6

101 Southbound AM HOVs

Page 7: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

7

101 Northbound AM HOVs

Page 8: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

8

101 Southbound AM RAMPS

Page 9: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

9

101 Northbound AM RAMPS

Page 10: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

10

CROSS CONNECTOR TRAFFIC

Page 11: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

11

EL CAMINO TRAFFIC

Page 12: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

12

THE CHALLENGE OVERALL

• Find a solution quickly• Secure public and political support of the Project• Secure the required funding• Minimize environmental impacts• Stay within the current Right of Way as much as

possible• Don’t make congestion worse in the other lanes• Reduce commute trips on the local street network• Build the project as soon as possible

Page 13: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

HOW AN EXPRESS LANE OPERATES

13

Page 14: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

TOLLING SIGN

14

Page 15: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

15

HOW A TOLL IS PAID

Page 16: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

16

IMPACT OF EXPRESS LANES

62

40

56

69

49

26

26

59

0 20 40 60

I-95 Miami

I-110 LA

I-10 LA

I-680 Sunol

AM Travel Speed (mph)

General Purpose AM Express AM

57

61

55

70

43

37

32

65

0 20 40 60

I-95 Miami

I-110 LA

I-10 LA

I-680 Sunol

PM Travel Speed (mph)

General Purpose PM Express PM

EXPRESS LANE ADVANTAGE

Page 17: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

17

IMPACT OF EXPRESS LANES

HOV/EXPRESS LANE IMPROVEMENT

19

15.1

11.3

12.4

16

11.8

0 5 10 15 20

I-110 LA

I-10 LA

I-680 Sunol

AM Travel Time (min)

AM Before AM After

11

15

11.1

10.8

18.1

11.3

0 5 10 15 20

I-110 LA

I-10 LA

I-680 Sunol

PM Travel Time (min)

PM Before PM After

20

40 60

0

803 mph

20

40 60

0

803 mph

20

40 60

0

8016 mph

20

40 60

0

801 mph

20

40 60

0

809 mph

2040 60

0

801 mph

AM Speed PM Speed

Page 18: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

18

INTEGRATED PROJECT TEAM

Co-Sponsor Agencies

Integrated Project Delivery Team

Environmental Lead Agency

Page 19: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

19

THE PROJECT LIMITS

Page 20: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

20

PROJECT PURPOSE

• Reduce congestion in the corridor• Encourage carpooling and transit use• Provide managed lanes for travel-time reliability• Minimize operational degradation of the general

purpose lanes• Increase person throughput• Apply technology and/or design features to help

manage traffic

Page 21: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

21

THE ALTERNATIVES

• Alternative 1: No project

• Alternative 2: Modify existing auxiliary lanes to make a new through lane from Whipple Avenue to I-380; convert median lane to an HOV lane for HOV 2+

• Alternative 3: Convert the existing median lane to an HOV 3+ Express Lane

• Alternative 4: Modify existing auxiliary lanes to make a new through lane from Whipple Avenue to l-380; convert median lane to an HOV 3+ Express Lane

THE

ALT

ER

NAT

IVE

S

Page 22: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

22

PRELIMINARY DESIGN CONSIDERATIONS

• Auxiliary lane replacement – Removal of Aux lanes sometimes impacts local street circulation and needs to be replaced to prevent negative impacts.

• Right of Way – In replacing Aux lanes, the team is minimizing right of way impacts by utilizing design exceptions, shifting alignments, and working with cities.

• Environmentally sensitive areas – The team identifies sensitive areas early and is working to reduce impacts.

• Relocation of existing sound walls – Design team is working with impacted Cities to minimize issues associated with sound walls.

Page 23: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

23

LANE CONFIGURATION A

Existing Conditions / No Build

Page 24: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

24

LANE CONFIGURATION B

Merged Lane in Converted No. 1 Lane

Page 25: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

25

LANE CONFIGURATION C

Managed Lane with Converted Auxiliary Lanes

Page 26: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

26

LANE CONFIGURATION D

Managed Lane with Converted Auxiliary Lanes and Auxiliary Lane Replaced

Page 27: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

27

AERIAL VIEW OF LANE SHIFT

Page 28: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

28

CHALLENGES WITH THE ALTERNATIVES

• Alternative 2: There is currently a high volume of 2-person carpools (HOVs) along with Clean Air Vehicles and HOV violators

• Alternative 3: There is no additional capacity to accommodate growth, so it is estimated to only work if a significant amount of people change their travel behavior.

• Alternative 4: Transitions into and out of the Santa Clara and San Francisco facilities must be carefully coordinated with VTA and SFCTA.

CHAL

LEN

GES

WIT

H TH

E AL

TERN

ATIV

ES

Page 29: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

29

TECHNICAL STUDIES

ENVIRONMENTAL STATION

Page 30: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

30

KEY SELECTION CRITERIAKE

Y SE

LECT

ION

CRI

TERI

A • Vehicle hours of delay: How many hours each car sits in traffic

• Change in travel times: How long it takes to get from point A to point B

• Person throughput: How many people can we move through point A on the way to point B

• Vehicle miles travelled: How many miles a vehicle travels in a specific time period (could mean reduced vehicle travel or could also mean gridlock)

Page 31: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

31

FUNDING & COORDINATION

• $11.5m for Environmental Clearance – This funding is secured (SMCTA, SAMCEDA)

• $9.5m for Preliminary Design– Partially funded to start the early stage of the design phase (Federal Earmark).

• Funding to complete Design and go to Construction is not secured.

• Continued coordination with SAMTRANS, Caltrainand cities

Page 32: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

32

FUTURE POLICY CONSIDERATIONS

• Which agency will operate these lanes?• Should this lane open as a 2+ HOV or 3+ HOV Express

Lane?• If it opens as a 3+ HOV Express should 2-person HOVs

get a discount?• What should be the hours of tolling? • Tolling generally changes based on congestion. What

should be the frequency and increment of change?• How should excess (revenue beyond operations and

maintenance cost) revenue be directed?

The following policy questions have to be answered in the future.

Page 33: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

33

PUBLIC ENGAGEMENT SCHEDULE

Scoping Meeting

Two Community Meetings

Public Comment Period

Environmental Clearance

October 2016 Late Spring 2017 January 2018 Fall 2018OUTREACH SCHEDULE

Page 34: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

34

www.dot.ca.gov/d4/101managedlanes

Page 35: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

35

IMPACT OF EXPRESS LANES

11

19

15.1

11.3

19

30.4

33.9

13.3

0 10 20 30

SR 167 Seattle

I-110 LA

I-10 LA

I-680 Sunol

AM Travel Time (min)

General Purpose AM Express AM

8

11

15

11.1

13

18.9

26.2

12.1

0 10 20 30

SR 167 Seattle

I-110 LA

I-10 LA

I-680 Sunol

PM Travel Time (min)

General Purpose PM Express PM

EXPRESS LANE ADVANTAGE

Page 36: Presentation for CMEQ Committee – June 26, 2017 · 2017-06-27 · Presentation for CMEQ Committee – June 26, 2017. INTRODUCTION 2 ... • VTA is in final design to create a 2+

36

IMPACT OF EXPRESS LANES

GENERAL PURPOSE LANE IMPROVEMENT

30.4

33.9

13.3

27.1

29

15.3

0 10 20 30

I-110 LA

I-10 LA

I-680 Sunol

AM Travel Time (min)

AM Before AM After

18.9

26.2

12.1

20.1

34.6

12.3

0 10 20 30

I-110 LA

I-10 LA

I-680 Sunol

PM Travel Time (min)

PM Before PM After

20

40 60

0

806 mph

20

40 60

0

806 mph

20

40 60

0

804 mph

20

40 60

0

802 mph

20

40 60

0

804 mph

2040 60

0

800 mph

AM Speed PM Speed