presentation for border transportation partnership

40
1 Presentation for Border Transportation Partnership Detroit River International Crossing May 31, 2005

Upload: louise

Post on 22-Feb-2016

59 views

Category:

Documents


0 download

DESCRIPTION

Presentation for Border Transportation Partnership. Detroit River International Crossing May 31, 2005. Presentation Outline. Background Planning/Need and Feasibility Study Existing and Proposed Crossings DRIC Study Elements DRIC Study Process DRIC Study Schedule. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Presentation for Border Transportation Partnership

1

Presentation for Border Transportation Partnership

Detroit River International Crossing

May 31, 2005

Page 2: Presentation for Border Transportation Partnership

2

Presentation Outline

• Background• Planning/Need and Feasibility Study• Existing and Proposed Crossings• DRIC Study Elements• DRIC Study Process• DRIC Study Schedule

Page 3: Presentation for Border Transportation Partnership

3

The Border Transportation Partnership

Page 4: Presentation for Border Transportation Partnership

4

The Project Team

Lead PartnerCanadian Side

Ontario Ministry of Transportation

Lead PartnerU.S. Side

Michigan Department of Transportation

Consultant TeamCanadian Side

Consultant TeamU.S. Side

Page 5: Presentation for Border Transportation Partnership

5

Why a Border Transportation Partnership?• Individual studies by Michigan and Ontario in the

1990’s• Need for long-term improvements was recognized • Within the mandates of:

– Transport Canada;– U.S. Federal Highways Administration;– Ontario Ministry of Transportation; and– Michigan Department of Transportation

• Each agency agreed to partner in a joint study

Page 6: Presentation for Border Transportation Partnership

6

Planning/Need and Feasibility Study(“The Bi-National Study”)

• Develop a 30-year transportation strategy:– Consistent with environmental assessment

requirements:• Canadian Environmental Assessment Act• Ontario Environmental Assessment Act• U.S. National Environmental Policy Act

– Multi-modal• Completed January 2004

Page 7: Presentation for Border Transportation Partnership

7

P/NF Study: Broad Geographic Area

Page 8: Presentation for Border Transportation Partnership

8

P/NF Study Daily Travel DemandBase Case

5,700

19,300

12,700

14,100Year2000

Year2030

Port Huron / Sarnia

12,800

69,30051,600

27,900

Year2000

Year2030

Detroit / Windsor

Page 9: Presentation for Border Transportation Partnership

9

P/NF Study Projected International Trade

Two-Way Canada-U.S. TradePassing Through Detroit-Windsor

(U.S. Dollars)

2001 2030

$90 Billion +/- $150 Billion+/-(64% Increase)

Page 10: Presentation for Border Transportation Partnership

10

Opportunities Lost If No Improvements By Year 2030

P/NF Study Economic Opportunities

SEMCOG-Essex Economy

Michigan-OntarioEconomy

Cumulative Employment(Full Time Equivalent Jobs)

19,750 – 24,000

70,000 – 84,000

Annual Production(Year 2000 U.S. Dollars)

$3.0 - $3.4Billion

$6.2 – $6.8Billion

Page 11: Presentation for Border Transportation Partnership

11

P/NF Study Network Connections

• Options for maintaining the movement of people and goods should be provided

• The current border crossings are 75 years old and will reach capacity in 10-15 years

• This key trade route requires a new or expanded border crossing

Page 12: Presentation for Border Transportation Partnership

12

P/NF Study Summary Elements of 30-Year Strategy

• Ensure sufficient border processing resources • Optimize the use of existing network in the

short to medium-term (5-10 years)

• Encourage use of other modes and diversion to Bluewater Bridge to reduce travel demand

• Construct a new or expanded crossing from the interstate freeway system in Michigan to the provincial highway system in Ontario

Page 13: Presentation for Border Transportation Partnership

13

P/NF Conclusions

• Clear need for improvements at Windsor-Detroit

• Planning and approval process is unique

• Integrated bi-national public planning process

• Initiate Ontario EA Terms of Reference

Page 14: Presentation for Border Transportation Partnership

14

Private Sector ProposalsAMB ETR

Mich-CanProposal

Detroit-WindsorTruck Ferry

Twin AMB

DRTPProposal

Hennepin Pt.Crossing, Inc.

Page 15: Presentation for Border Transportation Partnership

15

The DRIC EA/EIS Study Will:• Coordinate the U.S. and Canadian work programs

• Assess impacts for route, plaza, and crossing alternatives– Engineering

– Social

– Economic

– Cultural

– Natural environment

• Incorporate public and agency input

Page 16: Presentation for Border Transportation Partnership

16

Preliminary Statement of Project Purpose

The purpose of the Detroit River International Crossing Project is to, for the foreseeable future (i.e., at least 30 years):

• Provide safe, efficient and secure movement of people and goods across the Canadian-U.S. border in the Detroit river area to support the economies of Michigan, Ontario, Canada and the U.S.

• Support the mobility needs of national and civil defense.

Page 17: Presentation for Border Transportation Partnership

17

Preliminary Statement of Project NeedTo address future mobility requirements across the Canada-U.S. border, there is a need to:

• Provide new border crossing capacity to meet increased long-term demand;

• Improve system connectivity to enhance the seamless flow of people and goods;

• Improve operations and processing capability; • Provide reasonable and secure crossing options in

the event of incidents, maintenance, congestion, or other disruptions.

Page 18: Presentation for Border Transportation Partnership

18

Ontario EA Terms of Reference

Purpose of the Undertaking

The purpose of the undertaking is to provide for the safe, efficient, and secure movement of people and goods across the Canadian-U.S. border in the Detroit River area to support the economies of Ontario, Michigan, Canada, and the U.S.

Page 19: Presentation for Border Transportation Partnership

19

Our Goal:

• Approved location for a river crossing

• Approved connections to freeways in Canada and U.S.

• Approved locations for plazas in Canada and the U.S.

• Comprehensive engineering to support approvals, property acquisition, design and construction

• Submission for approval by December 2007

Page 20: Presentation for Border Transportation Partnership

20

Detroit River CrossingsForecasted Traffic Volumes

Page 21: Presentation for Border Transportation Partnership

21

Sensitivity Analysis

Scenario Year Capacity Reached

Base Forecast 10 to 15 yearsSensitivity Tests

High Trade Growth Advance 3 years

Low Trade Growth Defer 3 years

Diversion to Intermodal Rail Defer 2 years High Diversion to St. Clair River Crossing Defer 6 years

High Passenger Car Demand Advance 4 years Low Passenger Car Demand Defer 5 years

Extreme Low Scenario Defer 11 years Extreme High Scenario Advance 7 years

Page 22: Presentation for Border Transportation Partnership

22

Detroit River Crossing Capacity

CrossingFacility

Year Capacity Reached

US Road Access

US Border Processing

Bridge / Tunnel

CAN Border

Processing

CAN Road Access

Ambassador Bridge > 30 years 5 to 10 years

10 to 15 years

5 to 10 years

5 to 10 years

Detroit-Windsor Tunnel

0 to 5 years

5 to 10 years > 30 years 5 to 10

years5 to 10 years

Page 23: Presentation for Border Transportation Partnership

23

Bridge Types

• Cable Stay Bridges– Main spans up to 1,500 ft

• Greenville Mississippi River Bridge – 1,300 ft

Page 24: Presentation for Border Transportation Partnership

24

Bridge Types

• Suspension Bridges– Main spans over 1,500 ft

• Tacoma Narrows Bridge – 2,800 ft

Page 25: Presentation for Border Transportation Partnership

25

Tunnel Types• Soft Ground Bored Tunnels• Rock Bored Tunnels• Cut/Cover – Submerged• Mined (Drill and Blast)• Construction

– Bored tunnels in soft ground up to 80 ft/day– Bored tunnels in hard rock up to 30 ft/day

• Cost– Comparable to very long span bridges– $160 to $240 US million/mile

Page 26: Presentation for Border Transportation Partnership

26

Tunnel FeasibilityCategory Southern Central Eastern

Soft Ground Bored Tunnel

Not feasible • Insufficient soil

depth

Possibly Feasible • Soil depth varies

from marginal to insufficient

Feasible • Marginal soil

depth

Rock Tunnel Not Feasible• Poor rock• Deep tunnel/ long

approaches• Poor history

Not Feasible• Poor rock• Even deeper tunnel/

long approaches• Poor history

Not Feasible• Poor rock• Very deep tunnel/

long approaches

Submerged Tunnel Not Feasible• Rock excavation

required• Environmental

Issues

Technically Feasible – Engineering

Not Feasible & Prudent – Environmental Issues

Technically Feasible – Engineering

Not Feasible & Prudent – Environmental Issues

Page 27: Presentation for Border Transportation Partnership

27

Crossing Feasibility Summary

Location

Type

South

Central EastGrosse Ile Fighting

Island

Soft Ground Bored Tunnel No No Yes Yes

Rock Bored Tunnel No No No No

Submerged Tunnel No No No No

Bridge Yes Yes Yes Yes

Page 28: Presentation for Border Transportation Partnership

28

Plaza Functions

Page 29: Presentation for Border Transportation Partnership

29

South Crossing Corridor• Further Distances to Freeways• Intensely Developed in US• Detroit River is approximately 3 miles wide• Piers Likely in Detroit River• Detroit River International Wildlife Refuge• Numerous Natural Environmental Impacts• Poor Connections to West• Airport Flight paths• Rural in Canada• Direct Route Southerly

Page 30: Presentation for Border Transportation Partnership

30

Central Crossing Corridor• Short Connections to I-75 and EC Row

Expressway• Major Infrastructure Improvements Required

for Connection to Freeway in Canada• Difficult Connection to I-75• Industrial Development• Many Brine Wells• Environmental Justice Concerns• Detroit River is Narrowest • Natural Environmental Impacts

Page 31: Presentation for Border Transportation Partnership

31

Eastern Crossing Corridor

• Densely Developed in Both Nations• Less Desirable from a Travel Demand

Perspective• Impacts to Belle Isle• Detroit River is Over one mile wide • Natural Environmental Impacts• Mid Length Connections to Freeways

Page 32: Presentation for Border Transportation Partnership

32

Evaluation Process

Select Technicallyand Environmentally Preferred Alternative;

Refine & CompletePreliminary Design

Refine andAssess

PracticalAlternatives

Assess IllustrativeAlternatives &

Identify PracticalAlternatives

Purpose of theUndertaking

Assess PlanningAlternativesand Develop

Illustrative Alternatives

Steps in Evaluation Process

TIMEAug ‘05

Jan ‘06Jan ‘07

Dec ‘07NUMBER OFALTERNATIVES

AMOUNT OFANALYSIS

Page 33: Presentation for Border Transportation Partnership

33

Balance of Social, Environmental andEngineering FactorsPROPOSED EVALUATION CRITERIA

Socio-Economic Environment

• Property and Access• Community Effects (Noise, Disruption, etc.)

•Land Use Strategies• Disposal Sites & Contaminated Areas

Cultural Environment

• Archaeology• Heritage and Recreation

Natural Environment

• Air Quality • Agricultural Areas• Fisheries and Aquatic Habitat • Groundwater and Surface Water• Noise

• Other Resources• Special Wildlife and Habitat Areas • Wetlands• Woodlands

Technical Considerations

• Traffic and Network Operations • Engineering/Constructability• Cost

Page 34: Presentation for Border Transportation Partnership

34

Consultation

THE PARTNERSHIP

PRIVATESECTOR

ADVISORYGROUP

COMMUNITY CONSULTATION

GROUP

CDNPROJECT

TEAMEXPERTISE

MUNICIPALCOUNCILS

MUNICIPALADVISORY

GROUP

CDNGENERAL

PUBLIC

CDNBORDER

AGENCIES CROSSING OWNERS,

OPERATORSPROPONENTS

CDNREGULATORY

AGENCIES

LOCALADVISORYCOUNCIL

U.S. PROJECTTEAM

EXPERIENCE

CITY/TOWNSHIPCOUNCILS

PUBLICAGENCYGROUP

U.S.GENERAL

PUBLIC

U.S.BORDER

AGENCIESFIRST

NATIONS

U.S.REGULATORY

AGENCIES

Page 35: Presentation for Border Transportation Partnership

35

Study Process Schedule

PUBLICMEETINGS

NEPA

OEAA

CEAA

Initial Public Outreach PIOH 2 PIOH 3 PIOH 5

PublicHearing(NEPA)

Consultation/PIOH

(OEAA)

Decisionby MOE

Undertake Assessment of Socio-economic, Cultural &

Natural Environment &Technical Considerations &

Identify Practical Alternatives

Complete PreliminaryDesign of Technically

& EnvironmentallyPreferred Alternative

Compile and Circulate Report(s)

J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N2005

Draft OEAReport

D

Final OEA Report

PIOH 4

RefinePractical

Alternatives

Compile &DocumentResults of theseInvesti-gations

On-going Meetings and Workshops on Project Issues

DRIC

PRO

DUCT

SPR

OCES

S PR

ODUC

TSCO

NSUL

TATI

ONPR

OCES

S ST

EP

2006 2007

Assess Planning Alternatives(Alternatives To) and

Define Study Area

Finalize Purposeof the Undertaking

Develop Illustrative Alternatives

SelectTechnically

andEnvironmentally

PreferredAlternative

PIOH 1

DraftCEAA Project

Description

DraftCEAA Scoping

Document

NEPAPurpose & Need

Statement

NEPAScoping

Document

DraftEnvironmentalImpact Study

FinalEnvironmentalImpact Study

Record ofDecision

from FHWA

FinalCEAA Project

Description

FinalCEAA Scoping

Document

Draft CEAAScreening

Report

Final CEAAScreening

ReportDecisionby RA’s

TransportationPlanning/Need

Report

Study AreaExisting

ConditionsReport

Illustrative RouteAlternatives Generation &

Assessment Report

CanadianPlaza Alternatives

Generation &Assessment

Report

PracticalRoute Alternatives

Generation &Assessment

Report

Selection ofTechnically Preferred

Alternative Report(Ont.)

ConceptDesign Alternatives

Generation &Assessment Report

(Ont.)

EngineeringReport(Mich.)

AccessJustification Report

(Mich.)

Consultation to include Concurrence Meetings as prescribed under NEPA(coordinated with U.S. Consultant), and additional meetings in U.S. and Canada on an on-going basis

Undertake Investigations of:

• Technical Considerations

• Social Environment

• Economic Environment

• Cultural Environment

• Natural Environment

to Assess Practical Alternatives

Page 36: Presentation for Border Transportation Partnership

36

Key MilestonesStudy Area Features, Opportunities & Constraints April ‘05

Initial Set of Crossing Alternatives & Connecting Routes in Canada and the U.S. June ‘05

Final Set of Alternatives December ‘05

Results of Social, Economic, Environmental and Engineering Assessments Winter ‘06

Preferred Crossing Location & Connecting Routes in Canada and the U.S. Spring ‘07

Finalize Engineering and Mitigation Measures Summer ‘07

Document Study and Submit for Approvals End of ‘07

Page 37: Presentation for Border Transportation Partnership

37

Who Decides?

DRIC Study

Partnership Recommendation

OEAAMinister of Environment

CEAAFederal Agencies

NEPAU.S. Agencies

APPROVALS

Page 38: Presentation for Border Transportation Partnership

38

DRIC Project Time Line

2005 2006 2007 2008 2009 2010 2011 2012 2013

EA Review &Approval

• Coordinated Canada – U.S. process• Streamlined within existing legislation• Public meetings have begun

NEWCROSSING

2013

LandAcquisition

Technically andEnvironmentally Preferred

Alternative SelectedMid-2007

Detroit RiverInternational Crossing

Route Planning andEnvironmental Assessment

ENGINEERING / CONSTRUCTION

Page 39: Presentation for Border Transportation Partnership

39

Project Contacts – Canadian StudyMr. Dave Wake

Windsor Projects Coordinator

Ministry of Transportation Tel. (519) 873-4559

[email protected]

Mr. Roger Ward Senior Project Manager

Ministry of Transportation Tel. (519) 873-4586

[email protected]

DRIC Project Office

2465 McDougall Street, Suite 100Windsor, Ontario N8X 3N9

Tel. (519) 969-9696; Fax (519) [email protected]

Mr. Len Kozachuk, P.Eng. Deputy Project Manager

URS Canada Inc. Tel. (905) 882-4401

[email protected]

Project Web Site: www.partnershipborderstudy.com

Toll Free : 1-800-900-2649

Page 40: Presentation for Border Transportation Partnership

40

Project Contacts – U.S. StudyMr. Mohammed Alghurabi

Senior Project Manager

Michigan Department of TransportationTel. (517) 373-7674

[email protected]

Mr. Joe CorradinoDRIC Project Manager

The Corradino GroupTel. (313) 964-1926

[email protected]

Project Web Site: www.partnershipborderstudy.com

Toll Free : 1-800-900-2649

Detroit Project OfficeThe Corradino Group, Inc.

535 Griswold StreetBuhl Building, Suite 918Detroit, Michigan, 48226

Tel. (800) 880-8241

Southfield Project OfficeThe Corradino Group, Inc.

20300 Civic Center Drive, Suite 410Southfield, Michigan, 48076

Tel. (248) 799-0140Fax (248) 799-0146