prequalification - qsouq.qa · pdf fileappendix c - resume of company experience ... nabeel...
TRANSCRIPT
1
Prequalification Document-2015 Rev 28 16.09.2015
Geotechnical Services, Materials and
Environmental Testing Laboratory
Gulf Laboratories Co. W.L.L
Prequalification
Gulf Laboratories Co. W.L.L
Junction of Street No. 2 and
Al-Kassarat Street, Salwa Industrial Area,
Doha, P.O Box 4024
Phone: +974 44607034
+974 44607036
Fax: +974 44607628
E-mail address: [email protected]
Website: www.gulflaboratories.com
2
Prequalification Document-2015 Rev 28 16.09.2015
Contents
Page No.
Company Details………………………………………………………………………..………………….. 3
Key Personnel……………………………………………………………………………………………….. 4
Equipment and Resources………………………………………….…………………………………… 6
Services Offered………………………………………………………………………………………….... 11
Organizational Structure……………………………………………………………………………..…. 13
Appendices
Appendix A - Certificates of Registration, MoE Certificate of Conformity,
Municipality License and Qatar Chamber of Commerce and Industry Certificate
Appendix B - ISO 17025 Accreditation / OHSAS, QMS, EMS Certification
Appendix C - Resume of Company Experience
Appendix D - Field and Laboratory Testing ISO 17025 Accredited Test Parameters
3
Prequalification Document-2015 Rev 28 16.09.2015
Company Details Name of Company : Gulf Laboratories Co. W.L.L
Head Office Address : P.O. Box 4024, Doha, Qatar
Commercial Registration No. : 14419
Nature of Business : Ground Investigations and Materials / Environmental Testing
Established : Mid-1970’s
Owners : Mannai Corporation – Doha
Employees : 200 ++
Office/Laboratory Location : Junction of Street # 2 and Al Kassarat Street
Salwa Industrial Area
Telephone Nos. : +974 446 07034
+974 446 07036
Fax No. : +974 446 07628
E-mail Address : [email protected]
Geotechnical and Drilling Site
Street No. 24, Gate 21, Al Kassarath Street
Investigation Department : Salwa Industrial Area
Telephone Nos. : +974 446 06585
+974 445 02371
Fax No. : +974 446 06562
E-mail Address : [email protected]
Workshop Location : Street 46, Salwa Industrial Area
Petroleum Testing Lab : Ground Floor, Building B2, Manweir Facility Phase1,
Location
Site No.: CB-50, Support Services Area
Ras Laffan Industrial City, Qatar
Telephone Nos.
+974 4433 5313
+974 4433 5327
+974 4433 5328
MOE Approval Certificate Nos. Geotechnical / Soil Investigation : No. SI 75
Validity 11-01-2016
Material Testing Laboratory : No. ML 286
Validity 30-05-2015
We are certified to ISO 9001:2008, ISO 14001:2004, OHSAS 18001:2007 and are
accredited to ISO 17025:2005.
4
Prequalification Document-2015 Rev 28 16.09.2015
Key Personnel
General Manager : Andrew Slate, B. Sc, C. Geol, Eur. Geol
Deputy General Manager : Dr. Richard Ellis, B. Eng Ph.D. C. Eng FCIHT FIAT MIQ Drilling & Geotechnical Service Manager : K.P. Abdul Majeed, B. Sc, M. Sc
Laboratory Operations Manager : Thomas Varghese, B. Sc
Senior Geotechnical Staff : M.N. Sananth, M.Tech Chief Chemist& Head of Chemical Laboratory : K.M. Arunan, B. Sc, C. Chem, C. Sci, FRSC
Project Leaders : Abdul Rahman, B. Sc, M. Sc
Durga Bashyal, B. Sc, M. Sc
Elizabeth Stanmore, B.Sc. C. Env
Senior Geologists : Bal Dhoj Karki, B. Sc, M. Sc
Dr. Sujin Jayadevan, B. Sc, M. Sc, Ph.D.
Abdul Jawad, B. Sc, M. Sc
Vineeth Nair, B. Sc, M. Sc
Gulzar Ansari, B. Sc, M. Sc
M.D Abdul Faisal, B.Sc. M. Tech (Applied Geology)
Geologists / Engineers : Nabeel Chakkattayil, B.Sc., M Sc
Suhail Mohammed, B. Sc., M. Sc
Safuvan Chakkana Prambil, B. Sc., M. Sc.
Jasim Sainulabdeen, B. Sc. Eng
Nishad Pulikkal, B. Sc., M. Sc
Shabeer Ahamed B Sc, M. Sc.
Uzair Ummer B. Sc, M.Sc.
Ragesh Parappurah, B. Sc., M. Sc
Sibin Das P, B. Sc, M. Sc.
Muhammed Shakeer, B. Sc, M. Sc.
Sabareesh K, BSc, M. Sc.
Moahmmed Ansar B. Sc, M. Sc.
Ragesh P, B. Sc, M. Sc.
Geophysicist : Rupesh Kumar, B. Sc, M. Sc.
Antoreep Dey, B. Sc, M.Sc.
Physical Lab Senior Supervisor : Nestor Maniti, B. C.E
5
Prequalification Document-2015 Rev 28 16.09.2015
Chemical Lab Senior Supervisor : Sajeev Yohannan, B. Sc, M. Sc
Senior Chemists/Chemists/ : 14 nos.
Microbiologists : 2 nos.
Laboratory Staff : 147 nos.
Petroleum Chemists : Frederick Andal, B Sc Chemistry
xxxxx
HSE Head : Kevin Thomas, B. Sc
HSE Sr. Officer : xxxxx
QA/QC Head : Allan Nabong, B Sc CE
QA/QC Senior Supervisor : Jeffrey B. Laviña. B. Sc Chemistry
HSE Senior Safety Officers : Robert Castillo, B Sc Ch. Eng
: Mohammad Faisal, BA
Drilling Supervisor/Engineer : K. Kalimuthu
John Mathias
Drillers : & Drilling Assistants
Other Support Staff : 65 nos.
: 40 nos
6
Prequalification Document-2015 Rev 28 16.09.2015
Equipment and Resources
Drilling Rigs – 6 no. Dual Purpose Truck Mounted
Hands England HE-35, Hands England HE-36
Boyles BBS 25, Dando Geotech
2 no. Pilcon Traveller T30 Rigs
Drilling Rigs – 27 no. Dual Purpose Crawler Mounted
2 no. Beretta T44 Rigs, 9 Hanjin P4000SD Rigs. 9 no. DESCO SP5500S, 6no. BEC 800,
1no. Getech DTHR 300
Drilling Rigs – Water Well / Geothermal Drilling Rig
1 no. DESCO SP7500S
Drilling Rigs – Reverse Circulation Drilling Rig
1 no. DESCO SP7500RC, with automatic sampler and rod carrier
Drilling Rigs – Cable Percussion
Pilcon Wayfarer Light Cable Percussion Rig
Other Plant & Test Equipment
Pagani 200T Cone Penetration Rig with Piezo-cone
Jack-up Drilling Barge “Nautilus” (12m x 6m)
Air Compressors – 250 to 750cfm, Water Bowsers and Water Tanker
Pressure meter test equipment,
Drilling parameter measurement systems
Ground Penetrating Radar with DGPS
Pile Integrity Testing Equipment
7
Prequalification Document-2015 Rev 28 16.09.2015
Soil Resistivity Testing Equipment
Thermal Resistivity Testing Equipment
Submersible Pumps, V-Notch Weir Tanks, Pressure Transducer and Data loggers
Soil and Aggregate Testing Laboratory
Automatic soil compactor
CBR machine
Slake Durability test machine
Sieve set
Electronic balances
Drying Ovens
Micro-Deval
Concrete Testing Laboratory
Concrete Trial Mix Design
Water permeability testing unit
Slump set testing apparatus
Air Meter
8
Prequalification Document-2015 Rev 28 16.09.2015
Concrete Penetrometer
Concrete Density Test
Making and Curing of Concrete Specimen
Compressive Strength Test
Flow table Test
Bleeding test
Concrete Temperature measurement
Durability Test
Water Absorption
Water Penetration
Chloride Migration Test
Rapid Chloride Permeability Test
ISAT
Asphalt Testing Laboratory
Marshall Mix Design Test
Ignition Oven for Binder content
Automatic Marshall Compactor
Marshall Testing machine
Cement Testing Laboratory
Blaine Air permeability apparatus
Mortar Mixer
Jolting apparatus
Curing Cabinet
Steel Bar Testing Laboratory
Universal Testing Machine
Chemical laboratory
BOD Incubators
Muffle Furnaces
Microwave Digester
HACH spectrometers
Ultra Pure water system
9
Prequalification Document-2015 Rev 28 16.09.2015
Distillation Apparatuses for Ammonia, TKN and Cyanide
Rotary Evaporator for Oil & Grease test
Microwave Extraction & Digester
Optical Emission Spectrometer for Chemical Composition of Steel
& Alloys
Environmental Testing Laboratory
Gas Chromatograph Mass Spectrometer (GC-MS)
Gas Chromatograph FID
ICP OES
TOC Analyser
Noise monitoring unit
Microbiological and Drinking Water Testing Laboratory
Bacteria culture Incubator
Microscope
Colony counter
Geotechnical Testing Laboratory
Automatic Consolidated Oedometer with data processing system
Digital Shear Testing – Fully Automatic with data processing
system
Tri-axial system with electric load cell and electronic axial strain
Transducers
Uni-axial Compressive strength and Young’s modulus testing
Rock Shear testing
On-site Materials Testing Laboratories
Nuclear gauges for In-situ density testing
10
Prequalification Document-2015 Rev 28 16.09.2015
Concrete & Asphalt core drilling
Plate bearing test equipments
In-situ CBR testing equipments
Petroleum Testing Laboratory (Ras Laffan Annex)
Insulating Liquids (Transformer oils) and Lube Oils condition
monitoring
Fuels Testing, Tests for other Petroleum Products
Equipments/Software:
GC Headspace
UHPLC
Viscometer
Tensiometer
Karl Fischer Titrator
Color Comparator, Flash Point Apparatus, Potentiometric Titrator,
Laser Particle Counter
Breakdown Voltage Tester (BDV)
Power Dissipation Factor/Power Factor Testing Instrument
Delta-X Research Transformer Oil Analyst™ software
11
Prequalification Document-2015 Rev 28 16.09.2015
Services Offered GROUND INVESTIGATION
Onshore Soil Investigations, Near shore Soil Investigations
Contaminated Land and Environmental Investigations
Exploratory Borehole Drilling and Sampling
Trial Pitting
In-Situ Testing
Static “Dutch” Cone Penetration Testing
Dynamic Cone Penetration Testing
Probe hole Surveys
Geophysical Investigations
Soil Resistivity Testing
WATER RESOURCES AND WATER MANAGEMENT
Water Well Drilling
Soak-away Borehole Drilling
Well Casing Installation
Pumping Tests and Permeability Testing
Earthing and Cathodic Protection Boreholes
LABORATORY / MATERIALS TESTING
Soil and rock mechanics laboratory testing
Groundwater, seawater & wastewater analysis
Concrete testing
Aggregate testing
Asphalt testing
Chemical testing
Steel Bar Testing
Environmental testing
Petroleum Products testing
12
Prequalification Document-2015 Rev 28 16.09.2015
GEOLOGICAL INVESTIGATIONS / MINERAL RESOURCES
Geological mapping
Walk-over surveys
Exploratory core drilling
GROUND ENGINEERING AND GROUND IMPROVEMENT
Pressure grouting
Gravity filling of cavities and voids
Anchor drilling
Micro-piling
OTHER SERVICES
Pile Integrity Testing
Underground Service Detection
Ground Penetrating Radar
Electromagnetic Surveys
Electrical Resistivity Survey
Thermal Resistivity Testing
13
Prequalification Document-2015 Rev 28 16.09.2015
Gulf Laboratories Organizational Structure
Executive Committee Mannai Corporation
Andrew SlateGeneral Manager
Dr. Richard Ellis, Ph.D.Dy General ManagerLaboratory Manager
QHSE Manager Quality Leader /Management
Representative
Dileep KVSection Head - Admin
KP Abdul MajeedDrilling & Geotechnical
Manager
Thomas VargheseLab. Operations Manager
Technical Leader
Jerin Sam KurianRadiation Protection
Officer
Abdul RehmanDurga Bashyal
Elizabeth StanmoreSenior Project Leaders
John MatiasKrishnan Kalimuthu
Amalandu Bikash DattaDrilling Supervisor
Amalandu Bikash DattaDrilling Foreman
Mohd BasheerWorkshop Supervisor
Sanaath M. N.Senior Specialist -
Geotechnical
Drilling and Workshop Facility Crews
Chemical, Environmental, Microbiology and Petroleum Laboratory
Physical Testing Laboratory
Jasim SainulabdeenSuhail MohammedSafuvan Parambil
Nishad PulikkalRagesh Parappurath
Shabeer AhamedUzair Ummer
Sibin Das PMuhammed Shakeer
Sebareesh K.Moahmmed Ansar
Geologists/ Engineers
Mannai Corporation Accounts, Credit Management, Legal Dept.,
Procurement, HR & Admin
QHSE Department
Man BahadurRishad BasheerBiju TulachanMaria Ruth
Mohammed FawzilAdministration
Prajin Microbiologist
Sajeev YohannanSenior Lab Supervisor
- Chemical
Bal Dhoj KarkiDr. Sujin Jayadevan
Abdul JawadVineeth NairGulzar Ansari
Md Abdul FaisalSenior Geologists
Approved by: Andrew Slate
General Manager
Rev. 9 15.07.15
Jahufar KhanPrince George
Cassandro JuayangVarghese George
John PhilipJino
Jobin ThomasEaster Gagasa
Jessica HernaezKim Lee Chua
Admin Staff
Hamid GalalSenior Officer- Public
Relations
Rupesh KumarAntoreep DeyGeophysicist
Chemists/ Asst. Chemists
Sirajul Islam Mohammed Nisam
Drilling Coordinators
GULF LABORATORIES CO., W.L.L.ORGANIZATION CHART
xxxxChemist - Petroleum
K.M. ArunanChief Chemist & Head of
Chemical Lab
Chemical Laboratory Assistants
QSHE Dept. (See separate
org.chart)
N. ManitiSenior Lab Supervisor
- Physical
Senior Laboratory Technicians
Laboratory Technicians
Assistant Laboratory Technicians
Frederick Andal Senior Chemist -
Petroleum
---Senior Welfare
Officer
Nikhil MaxAdolf Xavier Jordan Rotea
Senior Chemists
14
Prequalification Document-2015 Rev 28 16.09.2015
15
Prequalification Document-2015 Rev 28 16.09.2015
APPENDIX A
CERTIFICATE OF REGISTRATION, MOE CERTIFICATE OF CONFORMITY,
MUNICIPALITY LICENSE, AND QATAR CHAMBER OF COMMERCE AND INDUSTRY
MEMBERSHIP CERTIFICATE
16
Prequalification Document-2015 Rev 28 16.09.2015
GULF LABORATORIES CO. W.L.L
MUNICIPALITY LICENSE
17
Prequalification Document-2015 Rev 28 16.09.2015
GULF LABORATORIES CO. W.L.L
CERTIFICATE OF REGISTRATION
18
Prequalification Document-2015 Rev 28 16.09.2015
19
Prequalification Document-2015 Rev 28 16.09.2015
20
Prequalification Document-2015 Rev 28 16.09.2015
GULF LABORATORIES CO. W.L.L
QATAR CHAMBER OF COMMERCE AND INDUSTRY MEMBERSHIP
CERTIFICATE
21
Prequalification Document-2015 Rev 28 16.09.2015
GULF LABORATORIES CO. W.L.L
QATAR CHAMBER OF COMMERCE AND INDUSTRY MEMBERSHIP
CERTIFICATE
22
Prequalification Document-2015 Rev 28 16.09.2015
GULF LABORATORIES CO. W.L.L Ministry of Environment Certificate of
Conformity – Material Testing Laboratory
23
Prequalification Document-2015 Rev 28 16.09.2015
GULF LABORATORIES CO. W.L.L Ministry of Environment Certificate of Conformity – Geotechnical Services
24
Prequalification Document-2015 Rev 28 16.09.2015
APPENDIX B
ISO 17025 ACCREDITATION / OHSAS, QMS, EMS CERTIFICATION
25
Prequalification Document-2015 Rev 28 16.09.2015
GULF LABORATORIES CO. W.L.L
ISO 17025:2005 ACCREDITATION
26
Prequalification Document-2015 Rev 28 16.09.2015
GULF LABORATORIES CO. W.L.L ISO 17025:2005 ACCREDITATION
(Petroleum Testing Laboratory – Ras Laffan Annex)
27
Prequalification Document-2015 Rev 28 16.09.2015
28
Prequalification Document-2015 Rev 28 16.09.2015
29
Prequalification Document-2015 Rev 28 16.09.2015
GULF LABORATORIES CO. W.L.L
ISO 9001:2008 CERTIFICATION
30
Prequalification Document-2015 Rev 28 16.09.2015
GULF LABORATORIES CO. W.L.L ISO 14001:2004 CERTIFICATION
31
Prequalification Document-2015 Rev 28 16.09.2015
32
Prequalification Document-2015 Rev 28 16.09.2015
GULF LABORATORIES CO. W.L.L
OHSAS 18001:2007 CERTIFICATION
33
Prequalification Document-2015 Rev 28 16.09.2015
34
Prequalification Document-2015 Rev 28 16.09.2015
APPENDIX C
RESUME OF COMPANY
EXPERIENCE
35
Prequalification Document-2015 Rev 28 16.09.2015
Major Completed Projects
Geotechnical Investigations & Drilling Projects
2014
2 Location Client Project Value (US$)
Qatar SOLETANCHE BACHY QATAR
W.L.L.
RED LINE NORTH UNDERGROUND. 80,900
Qatar HYDER CONSULTING INDUSTRIAL INTERCHANGE 59,025
Qatar SINOHYDRO ADDITIONAL GROUND INVESTIGATION, UTILITY TUNNEL, AT LUSAIL 177,076
Qatar GULF CONTRACTING CO. ERT- DOHA FESTIVAL CITY 4,118
Qatar TR ENGINEERING CO. FEED FOR EXPANSION OF FUEL & GAS HEADER, RLIC, QATAR. 91,709
Qatar ACTION INTERNATIONAL
SERVICES LLC
GEOTECHINCAL INVESTIGATION at DOHA AIRPORT, QATAR. 112,260
Qatar AL HABTOOR LEIGHTON STFA SOIL
GROUP - HSSG
QATARA HOSPITALITY, QATAR. 7,950
Qatar ENERGOPROJEKT-ENTEL FEED FOR REPLACEMENT OF DIESEL ENGINE DRIVEN IAC PACKAGEDUKHAN. 38,469
Qatar SAMSUNG C&T/MITSUBISHI QATAR FACILITY D/WPP-OFFSHORE PROJECT-MESAIEED. 66,731
Qatar GHD GLOBAL PTY LTD FEED for SITE DEVELOPMENT AT MESAIEED (MIC)-GEOPHYSICAL SURVEY 34,756
Qatar RASGAS CO. LTD GROUND WATER MONITORING WELLS, TIW LOCATION 35,964
Qatar HYUNDAI HEAVY INDUSTRIES QATAR FACILITY D/WPP-OFFSHORE PROJECT-MESAIEED.
66,649
Qatar GS ENGINEERING & CONSTR.
CORP
QATAR FACILITY D/WPP-OFFSHORE PROJECT-MESAIEED. 75,418
Qatar GHD GLOBAL PTY LTD FEED for SITE DEVELOPMENT AT RLIC-GEOPHYSICAL SURVEY 29,365
Qatar TALAL TRADING & CONT. CO. EARTHING BOREHOLES AT LUSAIL. 1,784
Qatar LEVEL NINE CONSTRUCTION EARTHING BOREHOLES AT AL RAYYAN 1,922
Qatar SHELL GLOBAL ENVIRONMENTAL WALKOVER SURVEY, AL KARAANA PERTROCHEM.
COMPLEX
19,561
Qatar URBACON INTERNATIONAL LUSAIL RECLAIMED ISLANDS- MARINE PROJECT 150,110
Qatar KHALIFA HMA AL-KHUWAIRI WATER WELL 1,922
Qatar ALYSJ JV QATAR INTEGRATED RAIL PROJECT –GOLD LINE UNDER GROUND 945,855
Qatar IMPREGILO CONSTRUCTION OF ABU HAMOUR(MUSAIMEER) DRAINAGE TUNNEL - Phase
1
43,606
Qatar PUBLIC WORKS AUTHORITY
(ASHGHAL) FRAME WORK CONTRACT 8,236,101
Qatar GHD GLOBAL PTY LTD FEED FOR UPGRADING AND CONSTRUCTION – SOILD RESISTIVITY 2,059
Qatar AL-ANDALUS PETROL STATION GROUND WATER MONITORING WELLS 24,019
Qatar EXXON MOBIL RESEARCH QATAR SABKHA CORE DRILLING- AL ZAREQ AREA 14,649
Qatar SWISSBORING QATAR EPIC OF WELLHEAD SCADA AND CATHODIC PROTECTION IN DUKHAN 4,667,124
Qatar FIVES FCB
Qatar Cement Plant - Ext.5 61,688
Qatar HYDER CONSULTING DOHA EXPRESSWAY GROUP 5 - Al Khor Bypass 700,819
Qatar SHELL GLOBAL SOLUTIONS
INTERNATIONAL BV
Al Karaana Petrochemical Complex-Ras Laffan. - Call Off No.3 39,287
Qatar HYUNDAI ENGG & CONST. CO.
LTD.
QEZ 3 Canal Excavation, Quay Walls and Channel Dredging 433,087
Qatar LANE - SOLID TADMUR A JOINT
VENTURE
MMUP PH.2, PKG 14 (PACKAGE 1) 346,258
Qatar SHELL GLOBAL SOLUTIONS
INTERNATIONAL BV
Al Karaana Petrochemical Complex, Ras Laffan-CALL OFF No.4 10,322
2012
Location Client Project Value (US$)
Qatar GEMS -NDPP ADDITIONAL NEW DOHA PORT PROJECT - ADDITIONAL GEOTECHNICAL SITE
INVESTIGATION
1,069,585
Qatar ITCC DRILLING EARTH BOREHOLES 4,324
36
Prequalification Document-2015 Rev 28 16.09.2015
Qatar SINOHYDRO CORPORATION CP1
PROJECT
LUSAIL WATER FRONT- PERGOLA FOUNDATIONS 63,660
Qatar FAHAD ABDEL HAD SOFAN WATER WELL CLEANING 961
Qatar SCHLUMBERGER PUMPING TEST WORKS IN DOHA, AL WAKRA & ALKHOR 54,427
Qatar QPMC GABBRO TERMINAL PROJECT MESAIEED 76,063
Qatar AL HUDA ENGINEERING WORKS CONSTRUCTION AT SUPREME EDUCATIONAL COUNCIL HEAD 237,479
Qatar FUGRO PENINSULAR RENTAL OF PRESSURE METER 3,294
Qatar TECHNICAL ENGINEERING CONSULTANCY FOR BEACH DEVELOPMENT 16,102
Qatar STFA MARINE CONSTRUCTION MESAIEED GABBRO BERTH #3ECT 21,854
Qatar TECHNITAL CONCEPT DESING OF ROADS PACKAGE-2 44,557
Qatar SINOHYDRO CORPORATION CP1
PROJECT
LUSAIL CP1 PROJECT 16,625
Qatar PUNJ LLOYD LTD CONTAMINATION STUDY NDIA 40,767
Qatar CHINA HARBOUR ENGINEERING
COMPANY
NDPP-GEOTECHNICAL INVESTIGATION WORK 110,611
Qatar TAG ENGINEERING DRILLING EARTHING BOREHOLES 6,873
Qatar CDC-TAKENAKA JV CONTAMINATION STUDY NDIA 103,259
Qatar SEEF LUSAIL REAL ESTATE
DEVELOPMENT COMPANY
W.L.L
LUSAIL COMMERCIAL WATERFRONT DEVELOPMENET 27,869
Qatar QATALUM RELINING FACILITY SITE GEOTECHNICAL AND TOPOGRAPHICAL
SURVEY
43,761
Qatar BLACK CAT ENGINEERING &
CONSTRUCTION
EPIC OF AMMONIA RECOVERY & AMMONIA FLARE SYSTEMS 20,544
Qatar URBACON INTERNATIONAL DUKHAN BEACH HOUSE 17,793
Qatar GHD RELOCATION OF FACILITIES FOR BUCK HALL-G 35,024
Qatar LEADERS INTERNATIONAL
SCHOOL
PROPOSED SCHOOL AT AIN KHALID, DOHA 5,491
Qatar SHABEEB NASAR AL NUAIMI CLEANING WATER WELLS AT UMBERKKA, QATAR 4,118
Qatar SINOHYDRO CORPORATION CP1
PROJECT
LATERAL UTILITY TUNNEL LUSAIL 16,183
Qatar URBACON INTERNATIONAL ISLAND PROJECT BRIDGE 64,167
Qatar CHINA HARBOUR ENGINEERING
COMPANY
NPP SPT BOREHOLES 23,931
Qatar SINOHYDRO CORPORATION CP1
PROJECT
LUSAIL PROJECT 16,859
Qatar MARAFEQ QATAR LUSAIL PROJECT 38,859
Qatar PREMIER INN HOTELS EDUCATIONAL CITY, QATAR 14,058
Qatar CHINA HARBOUR ENGINEERING
COMPANY
NEW PORT PROJECT (SAMPLING SPT BOREHOLES) 5,005
Qatar CHINA HARBOUR ENGINEERING
COMPANY
NEW PORT PROJECT- SPT BOREHOLES 192,012
Qatar SINOHYDRO CORPORATION CP1
PROJECT
GEOPHYSICAL SURVEY-MASW 23,871
Qatar MARAFEQ QATAR PWC PLANT – LUSAIL 15,045
Qatar MIDDLE EAST DREDGING
COMPANY
NDPP-ACCESS CHANNEL DREDGING & OUTER BREAKWATERS
CONSTRUCTION
35,824
Qatar ACTION NDPP WATER WELL 24,530
Qatar QATAR KENTZ RLIC QATAR 8,758
Qatar KLING COSULT LUSAIL KATARA HOTEL- MARINA DISTRICT 34,645
Qatar AL HUDA ENGINEERING WORKS CONSTRUCTION AT SUPREME EDUCATIONAL COUNCIL HEAD 11,765
Qatar QDVC 2CIA UNDERGROUND STATIONS & AL KHOR VADUCT WORKS 3,624
37
Prequalification Document-2015 Rev 28 16.09.2015
Qatar CHINA HARBOUR ENGINEERING
COMPANY
NEW PORT PROJECT 153,920
Qatar TAG ENGINEERING EARTHING BOREHOLE- QATAR RADIO & TELEVISION CORPORTATION 9,289
Qatar ASWAN TRADING &
CONTRACTING COMPANY
QUARRY FEASIBILITY STUDY 17,447
Qatar SINOHYDRO CORPORATION CP1
PROJECT
LUSAIL PROJECT 7,975
Qatar CHINA HARBOUR ENGINEERING
COMPANY
NEW PORT PROJECT-SPT BORE HOLES (COAST GUARD) 170,487
Qatar KEO INTERNATIONAL ADDITIONAL FIELD TESTING AND INTERPRETATIVE REPORTING 4,393
Qatar GREAT LAKES DREDGE & DOCK
CO
MARINE / NEARSHORE SITE INVESTIGATION - SUMAISIMAH, QATAR 109,720
Qatar BUILTECH ENGINEERING &
CONTRACTING CO.
DRILLING OF EARTHING BOREHOLE AT NEW DOHA PORT 2,059
Qatar MOHAMMED KHARAN SIYAN
AL-MANSSORI
DRIILLING OF WATER WELL AT AFJAN, DUKHAN 8,236
Qatar JABIR NASSER AL-HUMAIDI CLEANING OF WATER WELL AT TINBAK 9,609
Qatar RASGAS COMPANY LIMITED GEO-ENVIRONMENTAL INVSESTIGATION, DRILLING GROUNDWATER
MONITORING WELLS
16,911
Qatar ELETTRO OROBICA S.R.L. - CASH
CUSTOMER
RADAR SITE LOCATION - NDIA 14,825
Qatar MATHAR AL DOSRI WATER WELL CLEANING 5,491
Qatar AECOM EXISTING LAND TREATMENT UNIT (LTU) 46,500
Qatar QATAR GAS OPERATING CONSULTANCY SERVICES FOR SITE SURVEY & SOIL INVESTIGATION 112,945
Qatar GULF CONTRACTING BEARING CAPACITY OF PIPE SUPPORT FOUNDATIONS- PEARL GTL
PROJECT
8,219
Qatar MILAHA MILAHA LOGISTIC CITY 24,810
Qatar AL JABEER & PARTNERS QATAR FOUNDATION – EARTHING BOREHOLES 8,460
Qatar ARAB ENGINEERING BUREAU GEO ENVIRONMENTAL INVESTIGATION 19,781
Qatar PUNJ LLOYD LTD DRILLING OF BOREHOLES FOR DEEP WELL GROUND BEDS 24,740
Qatar SCHLUMBERGER DEWATERING WELLS AT INDUSTRIAL AREA. 17,832
Qatar DECORELLE DRILLING EARTHING BOREHOLES 5,452
Qatar AL BADIYA TRDNG & CONTG 5,101
Qatar SINOHYDRO CORPORATION CP1
PROJECT
SINOHYDRO CORPORATION CP1 PROJECT 15,795
Qatar TRADING AND AGENCY SERVICES
LTD.
DRILLING EARTHING BOREHOLES 7,007
Qatar QATAR GAS OPERATING GROUND WATER MONITORING WELLS INSTALLATION 42,889
Qatar IMPERIAL TRADING &
CONTRACTING CO. WLL
DRILLING EARTHING BOREHOLES 1,479
Qatar DANWAY QATAR DRILLING EARTHING BOREHOLE in ARAB D, DUKHAN 5,753
Qatar KEO INTERNATIONAL AL QAJBAH DEVELOPMENT 10,689
Qatar QDVC ENERGY CITY STATION, LUSAIL 19,726
Qatar QATAR KENTZ QATAR KENTZ- SIDRA MEDICAL CITY, QATAR FOUNDATION, DOHA . 5,890
Qatar NASSER MUBARAK NA
ALMADEED- AL ALI CONSULT
NASSER MUBARAK NA ALMADEED- AL ALI CONSULT 4,340
Qatar SAMSUNG ENGINEERING SAMSUNG ENGINEERING- LAFFAN REFINERY DHT PROJECT , RAS
LAFFAN, QATAR.
96,200
Qatar WORLEY PRSONS DEVELOPMENT OF ORYX GTL PRODUCT STORAGE TANKS AREA. 113,710
38
Prequalification Document-2015 Rev 28 16.09.2015
Qatar MUSTAFAWI RENTAL OF JACK UP, BARGE. 78,082
Qatar TEBODIN FEED FOR INSTALLATION OF 20" WET GAS PIPELINE 25,692
Qatar GHD DRIILLING GROUND WATER MONITORING WELLS, AT HALUL ISLAND 13,171
Qatar AECOM EXISTING LAND TREATMENT UNIT (LTU) 25,562
Qatar AECOM NEW LAND TREATMENT UNIT-RASLAFAN 11,719
Qatar HYDER CONSULTING ME AL HUWAILAH ROAD 29,325
Qatar METALEX TRADING &
CONTRACTING DOHA INDUSTRIAL AREA, STRT#38 1,834
Qatar DECORELLE ABA PALACE RAYYAN 1,834
Qatar QATAR MULTITECH TRAD QTEL RLU DOHA 1,377
Qatar URBACON INTERNATIONAL THE ISLAND PROJECT 189,064
Qatar MOTT MACDONALD ASHGAL LAGOONS PROJECT 129,145
Qatar ASWAN TRADING WATER WELL DRILLING AT OWAINA, DUKHAN 6,151
Qatar NASSER AL HAJIRI CO. LTD PEARL GTL PROJECT 14,274
Qatar QDVC SHERTON 4,795
Qatar SINOHYDRO CORPORATION CP1
PROJECT LUSAIL PROJECT 23,699
Qatar METALEX TRADING &
CONTRACTING
SUPPLY AND INSTALLATION OF 80M SELF SUPPORT TOWER AT ABU
SAMRA 1,233
Qatar QVC NEW CHLORIDE-ALKALI AND EDC PLANT IN MESAIEED. 25,048
Qatar SHEIKH ABDUL RAHMAN BIN
JASSIM CLEANING WATER WELL IN ALKHOR 13,356
Qatar DAR AL HANDASAH NDPP 5,137
Qatar TOURIST TRAVEL BUREAU CLEANING WATER WELL AT UMMBERKA, QATAR 1,644
Qatar QDVC ENERGY CITY STATION 2,740
Qatar ASWAN TRADING WATER WELL IN AL OWAINA, DUKHAN 11,493
Qatar AMAR CONSTRUCTION DRILLING EARTHING BOREHOLE AT RAYYAN 8,507
Qatar MR. ABDULLA MUBARAK HAMAD DRILLING WATER WELL IN AFFAN, DUKHAN 4,932
Qatar EMBASSY OF JAPAN PROPOSED BUILDING FOR EMBASSY OF JAPAN 9,534
Qatar KEO INTERNATIONAL QATAR SHELL - AL KHOR HOUSING 41,079
Qatar QATAR NAVIGATION QATAR NAVIGATION LOGISTIC CITY 25,263
Qatar SHEIKH ABDUL RAHMAN BIN
JASSIM
CLEANING WATER WELL AT SULAIMI, QATAR 8,904
Qatar AEB DOHA FESTIVAL CITY AT SHAMAL ROAD 8,279
Qatar QATAR VINYL COMPANY NEW CHLORIDE-ALKALI AND EDC PLANT IN MESAIEED. 45,408
Qatar ENERGY TECHNICAL SERVICES EPIC FOR FIRE TRAINING GROUND 4,807
39
Prequalification Document-2015 Rev 28 16.09.2015
Qatar ENERGY TECHNICAL SERVICES EPIC OF MOSQUE &EID MUSALLA 6,008
Qatar FAHAD SAQR AL MEREKHI CLEANING WATER WELL 3,562
Qatar QATAR ENGINEERING
LABORATORIES
NDPP- CONE PENETRATION TEST 7,014
Qatar MARBU DRILLING SOAKAWAY BOREHOLES AT AQUA PARK 1,863
Qatar POLY PRODUCTS PROPOSED FACTORY AT QATAR INDUSTRIAL 5,055
Qatar CHINA HARBOUR ENGINEERING
COMPANY NDPP 132,550
Qatar NASS GROUP DRILLING SHORING BOREHOLES AT AL WAAB 7,123
Qatar SCHLUMBERGER DOHA METRO RED LINE 830,089
Qatar AL NASHAT CONTRACTING EPIC OF RAW SEWAGE EFFLUENT NETWORK AT RAS LAFFAN CITY 7,123
Qatar AMAR CONSTRUCTION DRILLING EARTHING BOREHOLE 4,562
Qatar ALPHA GULF DRILLING EARTHING BOREHOLES AT WAKRA 1,096
Qatar FAWZY FAWY TAHA ABOUZEID
C/O KHALID INTERNATIONAL 1,781
Qatar MSHEIREB PROPERTIES GOLF COURSE COMMUNITY EDUCATION CITY- DOHA 22,432
Qatar DOHA MOTORS TRADING PROPOSED G+M+ OFFICE BLOCK & WORKSHOP AT RLIC 3,562
Qatar AEB BEACH VILLA AT THE PEARL QATAR FOR Mr. ALL AL FARDAN 7,164
Qatar SINOHYDRO CORPORATION CP1
PROJECT
LUSAIL PROJECT 7,466
Qatar A.A. ENGINEERING AL WAAB CITY SALWA ROAD 1,096
Qatar TAG QATAR RADIO TV CORPORATION COMPLEX DOHA 75,810
Qatar SHK KHALIFA BIN HAMAD AL
THANI
CLEANING WATER WELL 3,342
Qatar FBA MIX CONSTRUCTION & DESIGN OF BLOCK & HOLLOW COREFACTORY,
MESAIEED 4,110
Qatar QATAR GAS OPERATING SOIL SAMPLING & TESTING 5,548
Qatar UNITED COSNTRUCTION PROPOSED AL MANA TOWER (3B+G+M+20 FLOORS) DOHA 4,808
Qatar HALCROW MMUP PACKAGE 25 AL HADARMA EAST 37,198
Qatar HALCROW MMUP PACKAGE 22 AL SAADI RASHEEDA STREET 72,513
Qatar AL AHMADANI GROUP PROPOSED 2B+G+M+6 STOREY BUILDING AT OLD GHANIM DT DOHA 9,041
Qatar ACTION RENTAL OF RIG & CREW - LUSAIL DEWATERING PUMP 7,671
Qatar I T C C ASHGAL SCHOOLS NO 9,14,15 & 16 123,288
Qatar QAFCO DRILLING & INSTALLATION OF 2NOS. GROUND WATER QUALITY
MONITORING BOREWELLS 6,096
Qatar AEB CENTRO HOTEL AT BIN MAHMOUD DOHA 5,616
Qatar MEECC Q-CHEM MESAIED 8,767
Qatar METALEX TRADING &
CONTRACTING INSTALLATION OF 80M SELF SUPPORT TOWER AT ABU SAMARA 5,199
Qatar HYDER CONSULTING ME AL JAMILIYA PTP & NORTH CAMP 8,219
Qatar AEB RESIDENTIAL TOWER (3B+G+50) AT WEST BAY 26,507
40
Prequalification Document-2015 Rev 28 16.09.2015
Qatar GULF CONTRACTING BEARING CAPACITY OF PIPE SUPPORT FOUNDATIONS- PEARL GTL
PROJECT 28,901
Qatar SINOHYDRO CORPORATION CP1
PROJECT LUSAIL PROJECT – CP1 - Cantilever 15,848
Qatar AMAR CONSTRUCTION CBQ BRANCH - AL KARTHEYATH 4,986
Qatar COWI A/S PACKAGE NO.21 DESIGN OF MAJOR ROADS IN THE CENTRE OF DOHA 158,548
Qatar CONSOLIDATED GULF CO. WLL GDS STATION W1 & W2 AT RAS ABU FONTAS 10,609
Qatar REDCO INTERNATIONAL SEWAGE TANKERS RECEIVING STATION RIGID PAVEMENT 4,006
Qatar RAMADA PLAZA UNDERGROUND SOIL INVESTIGATION 760
Qatar PUNJI LLOYD NDIA- DOHA 4,636
Qatar AEB ADDITIONAL VISITOR CAR PARKING AT THE PEARL QATAR 23,129
Qatar QPMS NEW ACCESS ROAD TO QPMS SAND WASHING PLANT 9,903
Qatar GREAT LAKES DREDGE & DOCK
CO
NDPP CP 06 . Qatar 103,575
Qatar MARBU ROAD WORKS, PARKING, LANDSCAPING , SHADES AND DEVELOPMENT
OF AL-JABEL AREA, DUKHAN 14,752
Qatar EMBASSY OF INDIA PROPOSED INDIAN EMBASSY BUILDING DOHA 16,332
Qatar AL MAKKI REAL ESTATE 2B+G+7 STOREY BUILDING, AL SADD , DOHA 4,384
Qatar CHINA HARBOUR ENGINEERING
COMPANY RENTAL OF STEEL BOAT 3,918
Qatar ROYAL ENGINEERING CONTAINER 5,479
Qatar QATAR GAS OPERATING LAFFAN PROJECT 3,644
Qatar TRAGS DRILLING EARTHING BOREHOLES AT QAPCO , MESAIEED 7,808
Qatar SHK HASSAN BIN FAHAD BIN
JASSIM AL THANI WATER WELL DRILLING IN AL KHEESA 1,616
Qatar A A ENGINEERING SERVICES AL WAAB CITY SALWA ROAD 1,534
Qatar MUBARAK HASSSAN ISAAL NASR CLEANING WATER WELL 1,096
Qatar DANWAY QATAR EPIC STATICS WITHIN DUKHAN FIELD 3,973
Qatar ASWAN TRADING &
CONTRACTING COMPANY WATER WELL DRILLING AT OWAINA, DUKHAN 16,753
Qatar BIN NASER TRADING DRILLING SOAKAWAY BOREHOLES FOR RESIDENTIAL BUILDINIG IN
GARAFA 1,918
Qatar MOHAMED AL I MALADIH WATER WELL AT NASRIYA 1,370
Qatar HASSAD FOOD ADDITONAL DRILLING WORKS & WELL CASING INSTALLATION FOR
FLOWER GREEN HOUSING 26,370
Qatar KHALID CEMENT INDUSTRIES
COMPLEX PRE STORAGE CONCRETE PRODUCTION PLANT- SALWA IND AREA. 7,481
41
Prequalification Document-2015 Rev 28 16.09.2015
2010
Location Client Project Value (US$)
Oman Private client Residential Commercial Building and at plot 206 Al Maweleh south-Al
Seeb 1,450
UAE Salva Resources / Readyrock
Quarries
Limestone Exploration Site at Fujairah , United Arab of Emirates-Core
Drilling 46,800
Oman Horizon Engg. Consultancy Commercial and Residential Building at plot No 294 AlMabela South 1,430
Oman Horizon Engg. Consultancy Commercial Residential Building at plot No 568, block 2 AL Mabela 1,430
Oman Gharafi International Cargo Facilities at Muscat and Salalah International Airports 24,929
Oman Technibuild Micropile drilling 25,402
Oman National Contracting Co. Thermal Resistivity testing, Sohar 5,148
Oman Gulf Mining Core drilling services in ibri and Waqba 24,700
Oman Al Musdaq Modern Trade Maine Geotechnical Investigation at Ras Al Hadd 15,600
Oman Cowi& Partners Salalah Airport Interchange 31,462
Oman Al Fairouz / APM Mining Diamond core drilling services – South Batinah 388,700
Oman Saraya Bandar Jissah Ritz Carlton Hotel at SBJ 46,272
Qatar SINOHYDRO CORPORATION LUSAIL DEVELOPMEMNT – CANTILEVER 12,978
Qatar CHINA HARBOUR ENGINEERING
CO. DREDGING & RECLAMATION WORKS AT AL RUWAIS PORT 175,342
Qatar KEO INTERNATIONAL
CONSULTANTS SHOOTING RANGE & TRAINING COMPLEX AT LEHSANIYAH 14,540
Qatar AL JABER & PARTNERS QATAR FOUNDATION – EARTHING BOREHOLES 17,872
Qatar AMERICAN INTERNATIONAL
CONTRACTORS AL UDEID AIR BASE – SOF09 – GROUND INVESTIGATION 16,100
Qatar ARAB ENGINEERING BUREAU NORTH GATE MALL DEVELOPMENT AT SHAMAL ROAD 40,367
Qatar TECHNIP FRANCE PLATEAU MAINTANANCE PROJECT 2,046
Qatar AL JABER TRASNPORT PEARL GTL PROJECT 19,569
Qatar SCHLUMBERGER PROPOSED WORK AT DEVELOPMENT AT ABU HAMOUR 6,027
Qatar ARAB ENGINEERING BUREAU OFFICERS & RETAIL BUILDING 17,093
Qatar ARAB ENGINEERING BUREAU MIXED USE DEVELOPMENT AL KHALEEJ STREET, BIN MAHMOOD 15,784
Qatar MARBU CONSTRUCTION & UPGRADE OF EMERGENCY APPROACH ROADS TO
ARABD. FNGLCS & JDS IN DHUKAN FIELD 16,862
Qatar HASSAD FOOD WATER WELL & PUMPING TETST WORKS IN SHAHANIYA FARM 19,726
Qatar JAN DE NUL NDPP- CP06 10,348
Qatar LARSEN & TOUBRO DOHA SOUTH SEWARAGE TREATMENT WORKS PH-II EXPANSION 25,359
42
Prequalification Document-2015 Rev 28 16.09.2015
Qatar TECHNICAL RESOURCES ARAB MUSEUM OF MODERN ARTS 6,986
Qatar HYDER CONSULTING ME ASPIRE ZONE 37,288
Qatar PRIVATE ENGINEERING OFFICE DOHA CENTRAL GRAND PARK 36,319
Qatar SINOHYDRO CORPORATION CP1
PROJECT DRILLING DIAMETER BOREHOLES 27,381
Qatar KEPPLER SEGHERS DOHA NORTH SEWERAGE TREATEMENT PLANT - BAGGING PLANT 7,077
Qatar PRIVATE ENGINEERING OFFICE LAND AT SOUK WAKEF, DOHA 14,151
Qatar A I C I UDEID AIR BASE 7,816
Qatar HYDER ENVIRONMENT ASSESMENT AT WAKRA PETROL STATION 13,028
Qatar QATAR GAS OPERATING QATAR GAS FACILITY RLIC 23,260
Qatar QATAR KENTZ FAHAHIL STRIPPIN PLANT DOKHAN 3,836
Qatar BURHAN INTERNATIONAL DEVELOPMENT OF ROADS IN BANIHAJER ZONE 213,680
Qatar CDC-TAKENAKA JV NDIA - CP35 4,881
Qatar QATAR KENTZ PEARL GTL SITE- RLIC 4,795
Qatar SCHLUMBERGER SHALLOW GROUND WATER MONITORING IN DOHA 868,651
Qatar C T J V 6,425
Qatar ENERGY TECHNICAL SERVICES WORKSHOP AT QRSFA - DHUKAN 3,051
Qatar C T J V QCS PROJECT RASLAFFAN 9,356
Qatar EXXONMOBIL RESEARCH SABKHA CORE DRILLING 43,986
Qatar REDCO CONSTRUCTION -
ALMANA DOHA SHOWCASE STADIUM 2022 AT ABU HAMOUR 15,726
Qatar HX STEEL INTERNATIONAL DRILLING BOREHOLES GDI- DUKHAN FIELD 3,425
Qatar HE SHEIKH FAHAD BIN
ABDULLAH ABDUL AZIZ AL THANI DRILLING WATER WELL 2,466
Qatar SINOHYDRO CORPORATION CP1
PROJECT GROUND WATER MONITORING WELLS AT SWI LUSAIL 9,634
Qatar
CONSOLIDATED CONTRACTORS
INTLS CO / TEYSEER
CONTRACTING COMPANY
QGX II PROJECT RASLAFFAN 9,836
Qatar ELECTRO THAWRAT DRILLING EARTHING BOREHOLES , DIE SUBSTATION 8,548
Qatar AL QAHTANI ENGINEERING DRILLING SOAKWAY BOREHOLE 4,110
43
Prequalification Document-2015 Rev 28 16.09.2015
Qatar QATAR KENTZ PEARL GTL SITE- RLIC 5,342
Qatar ARCHIRODON CONSTRUCTION
OEVRSEAS CO.SA DRILLING BOREHOLES EARTHING- RLIC 5,342
Qatar G H D DRILLING & INSTALLATION GROUND WATER MONITORING WELLS 60,685
Qatar
CONSOLIDATED CONTRACTORS
INTLS CO / TEYSEER
CONTRACTING COMPANY
QGX II PROJECT RASLAFFAN 7,260
Qatar SHEIKH NASAR BIN JASSIM AL
THANI CLEANING WATER WELL AT WADI WASIAH 4,658
Qatar HE SHEIKH FAHAD BIN
ABDULLAH ABDUL AZIZ AL THANI DRILLING WATER WELL 24,658
Qatar DOPET HALUL PROJECT 15,110
Qatar METALEX TRADING &
CONTRACTING DRILLING EARTHING BOREHOLE AT DOHA IND AREA 2,466
Qatar GULF CONTRACTING DOHA WEST SEWAGE TREATMENT WORKS EXTENTION :3 8,219
Qatar H.E SHEIKH ABDULLA BIN JASIM
AL THANI AL THANI WATER WELL 2,301
Qatar QATAR KENTZ PEARL GTL SITE- RLIC 6,986
Qatar SAOUD ABDULLA HAMAD AL
HAZAB CLEANING WATER WELL AT MUAITHER 1,370
Qatar ARAB ENGINEERING BUREAU MIC Housing Project Phase#2 20,400
Qatar QDVC LUSAIL CAR PARK PROJECT 1,644
Qatar NEW LINE GROUP DRILLING EARTHING BOREHOLE AT DOHA 1,507
Qatar STFA MARINE CONSTRUCTION EPIC OF CONTAINER TERMINAL AT MESAIEED BERTH #7 27,507
Qatar ENERGY TECHNICAL SERVICES EPIC OF MOSQUES 14,556
Qatar STFA MARINE CONSTRUCTION EPIC OF CONTAINER TERMINAL AT MESAIEED BERTH #7 35,637
Qatar GEMS INTERNATIONAL NDPP - HIRE OF GEOLOGIST / ENGINEER 10,959
Qatar SINOHYDRO CORPORATION CP1
PROJECT CP5- GOLF 1 SUBSTATION LUSAIL, DOHA 10,993
Qatar HYDER CONSULTING ME ASPIRE ZONE HYDRO GEOLOGICAL INVESTIGATION -PHASE II 100,388
Qatar HX STEEL INTERNATIONAL PROPOSED DEVELOPMENT AT RAS LAFFAN – GEOTECHNICAL
INVESTIGATION 4,581
Qatar ARUP QATAR NATIONAL MUSEUM – GEOPHYSICAL INV 12,678
Qatar CONSOLIDATED GULF CO. WLL HV CONTROL CENTRE BUILDING , DUKHAN 15,651
Qatar PREMIUM CONSTRUCTION CONSTRUCTION & REPAIR OF STREET LIGHT SYSTEM 15,753
Qatar ARUP MV2 SITE LUSAIL SIMSIMA ROUTE 10,116
Qatar ALPHA GULF PROPOSED 2B+G+2 BUILDING IN NUAIJAH DOHA 3,562
Qatar INDUSTRIAL SERVICES GROUP PROPOSED G+5 BUILDING AT MUMTAZA DOHA 3,562
Qatar A R U P MEEZA MV3 GROUND INVESTIGATION 5,718
44
Prequalification Document-2015 Rev 28 16.09.2015
Qatar QATAR INDUSTRIAL
LABOROTORIES DRILLING GEOTECHNICAL BOREHOLES – AL KHOR HIGWAY 71,233
Qatar SINOHYDRO CORPORATION CP1
PROJECT CP-5 UTILITY TUNNELS & INTERCHANGE 115,104
Qatar BURHAN INTERNATIONAL DEVELOPMENT OF ROADS IN BANIHAJER ZONE – GEOTECHNICAL
INVESTIGATION 31,697
Qatar T C J V PLATEAU MAINTANANCE PROJECT – GEOTECHNICAL INVESTIGATION 151,339
Qatar GEMS INTERNATIONAL NDPP - ADDITIONAL GEOTECHNICAL INVESTIGATION –Variation Order
-7
1,161,961
Qatar REDCO INTERNATIONAL G+2 STORING BUILDING AT WUKAIR 6,437
Qatar GEMS INTERNATIONAL RENTAL OF JACK UP, BARGE & DRILLING OF MARINE BOREHOLES 963,878
Qatar HALCROW QEC TRUCK MARSHALLING AREA & PEOPLE MOVER 82,572
Qatar KEPPLER SEGHERS DOHA NORTH SEWERAGE TREATEMENT PLANT 13,026
Qatar
CONSOLIDATED CONTRACTORS
INTLS CO / TEYSEER
CONTRACTING COMPANY
QGX PROJECT RASLAFFAN 3,288
Qatar BLACK CAT ENGINEERING &
CONSTRUCTION EPIC FOR PRODUCED WATER TREATMENT & INJECTION PHASE-2 62,672
Qatar AMERICAN INTERNATIONAL
CONTRACTORS SITE INVESTIGATION ATALUDEID AIR BASE 15,477
Qatar KLG ORGANIC QATAR W.L.L CHLORINATED PARAFFIN WAXES (CPW) PROJECT 8,487
Qatar RENCO QATAR NDIA - CP35 103,151
Qatar MANSOOR ISSA AL HAKI 2B+G+6 GUILDING AT BINMAHMOOD 4,397
2009
Location Client Project Value (US$)
Qatar CDC-Takenaka JV NDIA - Passenger Rail System – Geotechnical investigation
works
1,019,393
Qatar STFA Marine Construction EPIC for Container Terminal Berth 7 at Mesaieed Port – CPT
soundings
240,959
Qatar AdilJaidah& Associates B+G+2 Office Building at C-ring Road 5,145
Qatar Coastal Consulting Engineering Submarine Cable at Corniche, Doha 15,019
Qatar Hyatt Plaza Drilling Soakaway boreholes 5,616
Qatar GHD Global Doha Park Project - Soil Testing & Drilling Boreholes to
Groundwater level. 9,641
Qatar CDC-Takenaka JV NDIA –Geotechnical investigation works 12,042
Qatar JGC / KBR –Qatar Shell Pearl GTL PROJECT PI-008 – Proposed Location of Operational
Waste Storage Cell – Geotechnical Investigation – Trial Pits
22,873
Qatar CCIC&Teyseer JV Qatargas 3 & 4 Onshore projects – Drilling Boreholes for vertical
anodes 10,885
Qatar Pillar Microwave Transmission Site – Muaither – Earthing Borehole 1,370
Qatar Dohaland Heart of Doha, Geotechnical Investigation Works 681,018
45
Prequalification Document-2015 Rev 28 16.09.2015
Qatar Rent-a-Port Lusail Development – Marine Geotechnical Investigation 66,608
Qatar CCIC&Teyseer JV NDIA, CP-27 Geotechnical Investigation for utility tunnel 20,548
Qatar KBAS Contracting Barwa Industrial Area & Development of Mohd. Bin Jassim St. 7,808
Qatar Sinohydro Corporation LusailStormwater Pumping Station SW1 – geotechnical
investigation 47,102
Qatar Mannai Trading Co. Proposed Development at RLIC for MCL – Geotechnical
Investigation 19,963
Qatar Hyder Consulting Lusail Pumping Station – Geotechnical Investigation 9,197
Qatar HalcrowYolles NDIA –Airport Operations Facilities Package No. 2 –
geotechnical investigation 33,075
Qatar Qatar Kentz Pearl GTL, RLIC – Earthing borehole drilling 5,342
Qatar Consolidated Gulf Co. WLL Mesaieed Tank Farm Area – geotechnical investigation 6,997
Qatar Tracer Qatar Improvement to Roads and Cark park at HGH – Earthing
boreholes
23,518
Qatar Danway Qatar Drilling Earthing Boreholes in Dukhan 16,767
Qatar Gulf Contracting Co. WLL Earthing Boreholes 5,764
Qatar Danway Qatar Drilling Earthing Boreholes in Umm Bab 2,541
Qatar Atkins / Mumtalkat Plot ECQ-D-11 Energy City, Lusail 21,085
Qatar Arab Engineering Bureau Ras Al Nassa Development (Marine Works), Doha 53,301
Qatar Zenon Trading & Contracting Co. Soakaway borehole drilling 6,329
Qatar KEO International NDIA – Subsurface Exploration and Geotechnical Exploration 47,278
Qatar DOPET Design Inputs for Raft Foundation 1,233
Qatar Al Jaber Energy Services Common Sulphur Plant Qatargas II – Cathodic Protection
boreholes
10,247
Qatar Redco Construction Almana Construction of B+G+3 office Building at Al Wakrah 2,027
Qatar Qatar Primary Material Co Geotechnical Investigation 16,362
Qatar Hyder Consulting Qatar Foundation, Education City, Additional Geotechnical
Investigation – infiltration tests 14,438
Qatar Gulf Contracting CO. WLL DOHA WEST SEWAGE TREATMENT WORKS - DRILLING
EARTHING BOREHOLES 43,836
Qatar WSP Environmental Aerospace City, Al Khor- Geotechnical Investigation 162,995
Qatar GEMS New Doha Port project – Supplementary site investigation 2,169,160
Qatar Aswan Trading Drilling Water Wells in Al Khor Farm 24,616
Qatar CCIC&Teyseer JV Qatargas 3 & 4 Onshore projects – Drilling Boreholes for vertical
anodes 7,123
Qatar Middle East Engineering
&Corrosion Control WLL MEEC - QP Tank Farms 21,945
Qatar STFA Marine-Construction
Company Gabbro Berth - Piezocone testing 35,644
Qatar Qatar National Museum QNM - Additional SI - Pumping tests 53,682
Qatar Cedgec Central Control Room for QAPCO 8,811
46
Prequalification Document-2015 Rev 28 16.09.2015
Qatar Nasser- Al Hajiri Pearl GTL Project - Earthing boreholes 33,288
Qatar Mohamed Mohanna Ali Dosari Cleaning & Deepening Water Well At Al-Khuraib 1,370
Qatar Shannon Engineering HKT & MKT Office Building Najma 0
Qatar CCIC &Teyseer Contracting Borehole at RLIC 10,890
Qatar Al Jaber& Partners Education City - North Side Utility Tunnels 35,616
Qatar JGC KBR Pearl GTL Project off Plot Waste Cell 22,885
Qatar Dornier Consulting Drilling of Additional GW Monitoring Wells 100,000
Qatar Diplomatic Contracting Company New Industrial Area - Soakaways 4,049
Qatar KEO International NDIA -CP63 - Additional SI works 29,147
2008
Location Client Project Value (US$)
Qatar MR. ABDULLA ABDULARAHMAN
HYDER
APARTMENT (B+G+2) - GEOTECHNICAL INVESTIGATION WORKS 1,507
Qatar QATAR DEVELOPMENT CO. KINDER GARTEN SCHOOLS AT ISHGAWA - GEOTECHNICAL
INVESTIGATION 4,205
Qatar SOGREAH PUMPING TEST & WATER ANALYSIS 66,740
Qatar FIVES SOLIOS QATALUM PROJECT - FUME TREATMENT PLANT - SOIL
INVESTIGATION 33,808
Qatar QATAR PRIMARY MATERIALS GEOLOGICAL PROSPECTING FOR SAND DEPOSITS - SITE
INVESTIGATION 21,034
Qatar GEMS NDPP PROJECT 401,562
Qatar CRC MARKIYAH MALL - DRILLING EARTHING BOREHOLE 8,440
Qatar CH2MHILL DRILLING & INSTALLATION GROUND WATER WELL AT MESAIEED 13,432
Qatar FLUOR GROUND WATER MONITORING WELL IN CONDENSATE 1 & 2
AREA 64,029
Qatar MINISTRY OF MUNICIAPL
AFFAIRS & AGRICULTURE
DRILLING 3 NOS. WATER WELL AT SABKHAT DUKHAN 7,397
Qatar HYUNDAI ENG'G & CONST. CO.
LTD
RAS LAFFAN "C" IWPP PROJECT (RAPO) - THERMAL RESISTIVITY
TEST
2,534
Qatar CCIC& TEYSEER RASGAS ONSHORE/ONPLOT EXPANSION - DRILLING OF GROUND
WATER MONITORING WELLS
20,274
Qatar HYUNDAI ENGINEERING &
CONSTRUCTION CO. LTD
RAS LAFFAN "C" IWPP PROJECT- SOIL INVESTIGATION WORKS 285,686
Qatar FOSTER WHEELER QATAR PETROCHEMICAL COMPLEX PROJECT - ENVIRONMENTAL
BASE LINE SURVEY
153,374
Qatar NIPPON KOEI QUOTATION FOR PROVISION AND TRANPORTATION OF CORE
BOXES
3,562
Qatar JGC-KBR / QATAR SHELL PEARL GTL PORJECT - SHELL CONTRACT PI-012 TPME, PROJECT
NO. 9216T - GEOTECHNICAL INVESTIGATION WORKS 45,400
Qatar FLUOR MIDEAST LTD WEST SIDE FLUOR CAMP - DRILLING OF GROUND WATER
MONITORING WELLS 26,837
Qatar QATAR DEVELOPMENT CO. RIVERA GARDENS - DUHAIL - GEOTECHNICAL INVESTIGATION
WORKS 4,205
47
Prequalification Document-2015 Rev 28 16.09.2015
Qatar MAFCO B+G+10 BUILDINGS AT FAREEQUE ABDUL AZEEZ -
GEOTECHNICAL INVESTIGATION
20,466
Qatar RAKO CONTRACTING GEOTECHNICAL INVESTIGATION AT WAKRA 4,103
Qatar FERNAS CONSTRUCTION CO. EPIC FOR FUEL GAS SUPPLY TO QNCC - IV AND GCC -I PLANTS
AT UMM -BAB AREA 3,699
Qatar BEHZAD TRANSPORT DRILLING EARTHING BOREHOLES AT ADARMA 1,575
Qatar DOPET DOHA PETROLEUM CONSTRUCTION CO. (DOPET) - QP SITE 15,870
Qatar AL HUDA ENGINEERING WORKS EARTHING BOREHOLES FOR PLAZA II & III 1,912
Qatar KEPPLER SEGHERS DOHA NORTH SEWERAGE TREATMENT PALNT SITE 1 & 2 27,005
Qatar SALAM PETROLEUM SERVICES GEOTECHNICAL INVESTIGATION KHATIYAH MAIN IN DUKHAN
FIELDS 7,047
Qatar MADAR BUILDING MATERIAL GEOTECHINCAL INVESITGATION WORKS 7,064
Qatar AL WAZEERI TRADING
TRANSPORT & CONTG AL WAZEERI TRADING TRANSPORT 2,071
Qatar MAFCO CONTRACTING G + 3 BUILDING AT AL SAAD AREA - GEO TECHNICAL
INVESTIGATION WORKS 15,110
Qatar FERNAS CONSTRUCTION CO. PLANTS AT UMMBAB AREA - GEOTECHNICAL INVESTIGATION
WORKS 21,381
Qatar BEZHAD TRANSPRT DRILLING ONE BORE HOLE 1,575
Qatar AL SRAIYA STRABAG NEW IZGHAWA LINK ROAD - GEOTECHNICAL INVESTIGATION
WORKS
13,329
Qatar AMMICO CONTRACTING CO.
WLL
DRILLING & INSTALLATION OF GROUNDWATER OBSERVATION
WELL
4,384
Qatar KEO INTERNATIONAL GEOTECHNICAL INVESTIGATION 133,479
Qatar DAEWOO ENGINEERING CONSTRUCTION CO. RAS LAFFAN YARD RLIC - GEOTECHNICAL
INVESTICATION 171,486
Qatar STFA MARINE CONSTRUCTION GABRO BERTH EXPANSION AT MESAIEED 94,863
Qatar QATAR KENTZ DRILLING EARTHING BOREHOLES 4,110
Qatar MEDCO QATAR BAHRIAN CAUSEWAY - SOIL INVESTIGATION 121,014
Qatar MSK CONTRACTING GEOTECHNICAL 5,479
Qatar MSK CONTRACTING DRIILING GROUND WATER WELL 3,562
Qatar DOPET DRILLING EARTHING BOREHOLES 9,189
Qatar ABYAAR REAL ESTATE
DEVELOPMENT GEOTECHNICAL INVESTIGATION WORKS 84,614
Qatar AL JABER & PARTNERS DRILLING EARTHING BOREHOLES 43,315
Qatar ENERGY TECHNICAL SERVICES GEOTECHNICAL INVESTIGATION WORKS 8,000
Qatar QATAR PRIMARY MATERIALS SITE IVESTIGATION 63,233
Qatar REDCO GROUP PRECAST CONCRETE FACTORY - GEOTECHNICAL INVESTIGATION 5,425
Qatar QATAR KENTZ PEARL GTL SITE - RLIC - DRILLING EARTHING BORE HOLE 18,493
Qatar CCIC& TEYSEER PACKAGE CP 27 - NDIA - GEOTECHNICAL INVESTIGATION 25,478
Qatar HYDER CONSULTING ME THE SPORTS CITY PROJECTS - BOREHOLE DRILLING, PUMPING
TEST 76,660
48
Prequalification Document-2015 Rev 28 16.09.2015
Qatar QATAR PRIMARY MATERIALS CEMENT SILOS, GABBRO BERTH, MESAIEED - GEOTECHNICAL
INVESTIGATION 40,849
Qatar HILL INTERNATIONAL GRAND HYATT RESORT PORJECT - PHASE II - GEOTECHNICAL
INVESTIGATION 43,281
Qatar AL JABER GROUP ABUDHABI TOWER - GROUND INVESTIGATION 695,348
Qatar BEITY PROPOSED G + 8 BUILDING AT OLD GHANEM - SITE
INVESTIGATION WORKS
5,452
Qatar COWI A/S BARWA AL KHOR DEVELOPMENT - GEOTECHNICAL
INVESTIGATIONS
194,926
Qatar CONSTRUCTION ENTERPRISES
COMPANY
CONSTRUCTION OF AL KHOR PORT CHANNEL - GEOTECHNICAL
INVESTIGATION
5,660
Qatar EL SEIF ENGINEERING CONTG DRILLING BOREHOLE 3,642
Qatar AL RIYADH TRADING & CONT.
CO.
EARTHING BOREHOLES AT AL WAAB 1,904
Qatar QATAR KENTZ SOIL RESISTIVITY TEST 1,301
Qatar STS LUSAILPROJECT 43,712
Qatar DORNIER CONSULTING DRILLING INSTALLATION OF GROUNDWATER MONITOR WELLS
AT DUKHAN
107,945
Qatar TADMUR CONTRACTING &
TRADING EST
GEOTECHNICAL INVESTIGATION WORKS - FAHAHIL STRIPPING
PLANT IN DUKHAN
7,136
Qatar QDVC WEST BAY PARK SITE - SOIL INVESTIGATION 149,588
Qatar HYDER CONSULTING ME PACKAGE 1 - WAKRAH MAIN ROAD - GEOTECHNICAL
INVESTIGATION
101,582
Qatar HYDER CONSULTING ME PACKAGE 2 - MAJOR ROADS IN AL KHOR & AL HUWAILAH -
GEOTECHNICAL INVESTIGATION
113,318
Qatar HYDER CONSULTING ME PACKAGE 3 : ROADS & INFRASTRUCTURE - AIN KHALID 120,273
Qatar HYDER CONSULTING ME PACKAGE 4 - ROADS & INFRASTRUCTURE IN AL KHEESA NORTH -
GEOTECHNICAL INVESTIGATION
176,021
Qatar HYDER CONSULTING ME PACKAGE 5 : ROADS & INFRASTRUCTURE IN AL KHOR
INDUSTRIAL AREA
96,189
Qatar HYDER CONSULTING ME PACKAGE 6 : MKEINES UMMBAB LINK ROAD 155,687
Qatar AL FOWRIYA TRADING &
CONTRACTING G+1 SAFARI HYPER MARKET AT AIN KHALID DOHA 3,433
Qatar PUNJ LLOYD LTD SOIL RESISTIVITY SURVEY - WORK ORDER 1,370
Qatar CHIYODA CORPORATION BARZAN ONSHORE PLANNING PROJECT- GEOTECHNICAL
INVESTIGATION
120,890
Qatar AL UMMA TRADING &
CONTRACTING
DRILLING GROUNDWATER WELLS AT BIN MAHMOUD AREA 4,110
Qatar SINOHYDRO CORPORATION CP1
PROJECT
LUSAIL DEVELOPMENT PRELIMINARY INFRASTRUCTURE WORKS
P GEOTECHNICAL INVESTIGATION
67,605
Qatar INTERNATIONAL CONTRACTING
& TRADING CO.
QATAR FOUNDATION - DRILLING WATER WELL 4,438
Qatar HYDER CONSULTING ME PACKAGE 4 A - ROADS & INFRASTRUCTURE IN UMM QARN -
GEOTECHNICAL INVESTIGATION
36,177
Qatar ARUP IQ TOWER - THE CRYSTAL - GEOTECHNICAL INVESTIGATION 512,378
Qatar FERNAS CONSTRUCTION CO. DRILLING EARTHING BOREHOLES 24,690
Qatar SLAG AGGREGATE PRODUCER QUARRY FEASIBILITY STUDY 12,096
Qatar MEDCO QATAR BAHRIAN CAUSEWAY - SOIL INVESTIGATION 100,226
Qatar ATLAS INTERNATIONAL QSTRG STAGE -3 - DRILLING EARTHING BOREHOLE 24,164
49
Prequalification Document-2015 Rev 28 16.09.2015
Qatar EL SEIF ENGINEERING CONTG P94-NDIA, DRILLING BOREHOLES FOR EARTHING 102,753
Qatar DOPHA PETROLEUM CONT CO
LTD
GRC 05/115 DRILLING EARTHING BOREHOLES 9,189
Qatar HYDER CONSULTING ME LUSAIL PUMPING STATION , GEOTECHNICAL INVESTIGATION
WORKS
43,984
Qatar ATELIERS JEAN NOUVEL NEW QATAR NATIONAL MUSEUM GEOTECHNICAL
INVESTIGATION
275,970
Qatar NEW VISION DRILLING EARTHING BOREHOLES AT SALWA ROADQ 1,644
2007
Location Client Project Value (US$)
Qatar CDE IRELAND LTD GEOTECHNICAL INVESTIGATION FOR SAND WASHING PLANT AT
AL KARANA
22,563
Qatar HYDRO ALUMINIUM AS QATALUM PROJECT – GEOTECHNICAL INVESTIGATION FOR
BRIDGES ACROSS COOLING WATER CHANNEL
10,931
Qatar JGC - KBR C/O QATAR SHELL GEOTECHNICAL WORKS FOR THE FIREWATER TANK / WEST
LAYDOWN AREA LOT W7A
9,445
Qatar JGC KBR - QATAR SHELL POTABLE WATER & FIRE WATER SYSTEM, CAMPAREA,
RASLAFFAN - GEOTECHNICAL INVESTIGATION
14,400
Qatar NIPPON KOEI CO. LTD / ASCO
CONSULTING ENGINEER
ABU HAMOUR SOUTHERN OUT FALL - GEOTECHNICAL AND
GEOPHYSICAL INVESTIGATION
224,459
Qatar STRABAG QATAR WLL PLANT OFFICE AREA BUILDINGS - GEOTECHNICAL
INVESTIGATION
14,015
Qatar PRIVATE ENGINEERING OFFICE /
GHD
PRIVATE BEACH VILLA AL THAKHIRA - GEO TECHNICAL
INVESTIGATION
11,740
Qatar CONSOLIDATED CONTRACTORS
INT'L CO. (CCIC)
QATARGAS II LNG FACILITIES PROJECT, RASLAFFAN - DRILLING
EARTHING BORE HOLE (CONTRACT GTC-QG-11-ONS-15)
149,658
Qatar GEA BARWABUSINESSCENTER - GEOTECHNICAL & HYDROLOGICAL
INVESTIGATION
305,462
Qatar AL JABER ENERGY SERVICES COMMON SULPHURPLANT, QATAR GAS II - RLIC, GEOTECHNICAL
INVESTIGATION
22,551
Qatar ENCANA INTERNATIONAL
(QATAR) LIMITED
DRILLING WATER WELL & PUMPING TEST 61,200
Qatar RAS LAFFAN OLFINS COMPANY
LTD (RLOC)
ETHYLENE PIPELINE - MESAIEED TOPOGRAPHICAL SURVEY 30,155
Qatar GEA GERMAN ENGINEERS AND
ARCHITECTS
BARWABUSINESSCENTER - GEOTECHNICAL & HYDROLOGICAL
INVESTIGATION - 2ND PHASE 386,473
Qatar ATKINS QATARFOUNDATIONEDUCATIONCITY - ADDITIONAL
GEOTECHNICAL INVESTIGATION
65,642
Qatar CBI SHELL PEARL GTL TANKAGE- CBI CONTRACT NO. 153130 -
GEOTECHNICAL SITE INVESTIGATION
803,320
Qatar STFA MARINE CONSTRUCTION CONSTRUCTION OF NEW TEMPORARY BERTH NO. 7 AT
MESAIEED - STAND PIPE INSTALLATION & ASS. WORKS
61,136
Qatar JGC MIDDLE EAST FZE GROUND WATER MONITORING WELLS CONSTRUCTION AT
DOLPHIN PROJECT
54,301
Qatar RAFAEL VINOLY ARCHITECTS ARABMUSEUM OF MODERN ART - GEOTECHNICAL
INVETIGATION
117,722
Qatar JGC KBR - QATAR SHELL STORAGE OF CORE BOXES 23,836
Qatar FCB QNC-3 ANCHORS IN ROCK UMMBAB - DRILLING BOREHOLES
FOR ANCHORS
62,740
Qatar QATAR PRIMARY MATERIALS GEOLOGICAL PROSPECTING FOR SAND DEPOSITS, SOUTH
QATAR. SITE INVESTIGATION
79,301
50
Prequalification Document-2015 Rev 28 16.09.2015
Qatar QATAR PRIMARY MATERIALS QPMC SAND WASHING PLANT-SOUTH OF AL-KARANA, GROUND
INVESTIGATION
19,759
2006
Location Client Project Value (US$)
Qatar HALCROW
DEVELOPMENT OF RUWAIS PORT PHASE 2, DRILLING EARTHING BOREHOLES
89,067
Qatar HALCROW
NEW DOHA INT’L AIRPORT, AIRLINE OPERATIONS FACILITIES GEOTECHNICAL INVESTIGATION
112,182
Qatar GULF ENGINEERING
MULTI PURPOSE ADMIN. COMPLEX – RASLAFFAN, GEOTECHNICAL INVS.
68,000
Qatar PUNJ LLOYD
NDIA FUEL SYSTEM-GEOTECHNICAL & GEOPHYSICAL SIOL INVESTIGATION
153,829
Qatar CTJV
AL KHALEEJ PROJECT PHASE 2, GEOTECHNICAL & TOPOGRAPHICAL SURVEY
52,250
Qatar IMCO
DRILLING EARTHING BOREHOLES & INSTALLATION OF EARTH RODS
40,288
Qatar CHIYODA TECHNIP AL KHALEEJ GAS PROJECT 28,125
Qatar QATAR SHELL GTL
PEARL GTL PROJECT PI-017, HARBOUR TANK FARM INTERIM SITE INESTIGATION
90,297
Qatar HALCROW
OLD DOHA PORT REDEVELOPMENT GEOTECHNICAL INVESTIGATION
28,127
Qatar HYDER CONSULTING LUSAIL DEVELOPMENT GROUND WATER INVESTIGATION
377,632
Qatar STS CONSULTANTS
QATAR CONVENTION CENTER & TOWER GEOTECHNICAL SITE INVESTIGATION
255,556
Qatar ELLERBE BECKET
SPECIALITY TEACHING HOSPITAL IN EDUCATION CITY, GEOTECHNICAL INVS.
48,564
Qatar CHIYODA TECHNIP
QATAR LIQUIFIED GAS CO PMP/AGX PROJECT GEOTECHNICAL & TOPOGRAPHICAL SURVEY
96,497
Qatar FCB CEMENT
THIRD EXTENSION OF UMMBAB CEMENT PLANT-GEOTECHNICAL INVESTIGATION
52,844
Qatar CHIYODA TECHNIP
QATAR GAS 3 & 4 ONSHORE PROJECT TRAINS 6 & 7 SUB CONTRACTORS CAMP
31,280
Qatar HYDRO ALUMINIUM AS QATALUM PROJECT-GEOTECHNICAL INVESTIGATION 12,986
Qatar BAUER INTERNATIONAL OLD GHANIM SITE DRILLING GROUND WATER MONITORING WELL
22,132
Qatar QATAR KENTZ RL3 COMMON OFFLOT PROJECT-RASLAFFAN 37,836
Qatar QATAR KENTZ PEARL GTL PLANT TANK AREA BOREHOLE WORK 75,973
Qatar QATAR SHELL PEARL GTL PROJECT CONSTRUCTION CAMP TRIAL PIT WORK
30,462
Qatar QAPCO
SIOL & WATER CONTAMINATION SURVEY IN AREA A & B OF QATOFIN PROJECT
85,622
Qatar CBI
CBI CONTRACT # 146682, RASLAFFAN GEOTECHNICAL INVESTIGATION
88,638
Qatar GALFAR ALMISNAD
EPIC UMMBAB TO SALWA ROAD DUAL CARRIAGE, EARTHING BOREHOLES
112,534
Qatar LINDE AG
AIR SEPERATION UNITS, RASLAFFAN – PEARL QATAR, GEOTECHNICAL INVS.
109,671
Qatar JGC-KBR C/O QATAR SHELL
PEARL GTL PROJECT ADDITIONAL CAMP SOIL INVESTIGATION WORK
95,463
Qatar AL-JABER & PARTNERS
PEARL PROJECT-EFFLUENT TREATMENT PLANT, GEOTECHNICAL INVESTIGATION
432,359
51
Prequalification Document-2015 Rev 28 16.09.2015
Qatar GALFAR ALMISNAD
CONSTRUCTION OF ROADS, UTILITY CROSSINGS & STREET LIGHTING IN INDUSTRIAL AREA, MESAIEED
25,077
Qatar HYDRO ALUMINIUM AS
QATALUM PROJECT – ADDITIONAL TOPOGRAPHICAL, BATHYMETRICAL & GEOTECHNICAL INVESTIGATION
107,103
2005
Location Client Project Value (US$)
Qatar MANNAI CORPORATION WAREHOUSE AT STREET 23/24 SALWA INDUSTRIAL AREA 3,658
Qatar QATAR DREDGING CO. PEARL OF THE GULF PROJECT – DOHA 47,136
Qatar HYDRO ALUMINIUM AS QATAR ALUMINIUM PROJECT 266,858
Qatar J & P QATAR W.L.L ERC 0492/C1 AL GHARRAFFA INTERCHANGE 2,411
Qatar KBAS CONTRACTIN & TRADING QUARRY FEASIBILITY AT KARAMA 17,205
Qatar INDUSTRIAL SERVICE GROUP OFFICE BLDG (2B +G + 9) AT NEW KHOLAIFAT 6,027
Qatar CHIYODA CORPORATION RASGAS NEWCAMPAREA FOR TRAIN 6 & FEED PROJECT
78,840
Qatar KBAS CONTG & TRADING KHALIFA STADIUM 1,842
Qatar MANNAI CORPORATION
WARE HOUSE AT ST 23/24 SALWA INDUSTRIAL AREA – ENVIRONMENTA SAMPLING & TESTING
3,658
Qatar C CC
RAS LAFFAN EXPANSION PROJECT GROUND WATR MONITORING WELLS
7,397
Qatar KBAS CONTRACTING SALAM STREET / DRILLING OF SOAKWAY BOREHOLES 5,589
Qatar JGC MIDDLE EAST FZE DOLPHIN – UPSTREAM AND COMPRESSION FACILITIES 18,315
Qatar MTC SURVEY QAFAC II & GEOTECHNICAL SURVEY 39,082
Qatar MTC SURVEY
NEW BRITISH EMBASSY OFFICES RESIDENCE & AMENITIES TOPOGRAPHICAL & GEO TECHNICAL SURVEY
12,671
Qatar CHIYODA CORP
SOIL INVESTIGATION & TOPOGRAPHICAL SURVEY – QATAR GASIII – PROJECT QATAR GAS 3 FEED PROJECT RASLAFFAN
304,372
Qatar J & P DRILLING BORE HOLES OUR QUOTE ER/6553 4,171
Qatar QATAR KENTZ WLL
QATARGAS II DEVELOPMENT PROJECT RLIC CAMPAREA, RASLAFFAN, (7-BOREHOLES, SOIL &ROCK SAMPLING LAB TEST)
9,849
Qatar FBJ ENTERPRISES VILLA COMPLEX LUQTA – GEOTECHNICAL INVESTIGATION 5,971
Qatar GULF ENGINEERING & INDUSTRIAL CONSULTANCY
BMC 2004023 CONSULTANCY QTY SURVEY FOR AQUATIC & FISHERIES REASEARCH CENTRE AT WAKRAH
33,879
Qatar SMEC INTERNATIONAL HALUL ISLAND REMEDIATION 103,667
Qatar COWI A/S NORTH BEACH DEVELOPMENT ADDITIONAL BOREWELL 3,397
Qatar QATAR KENTZ 524-QG-II LABOUR CAMP FACILITIES PHASE II – RASLAFFAN 6,685
Qatar DODSAL PTE LTD
DOLPHIN UPSTREAM & COMPRESSION FACILITIES PROJECT RLIC – DRILLING EARHING BOREHOLES
3,767
Qatar PENINSULAR PETROTECH ENG.
HALUL TANK CP SYSTEM, DRILLING BOREHOLES FOR CATHODIC PROTECTION
61,349
Qatar ARAB CONSULTING ENGINEERS 15 NEW SCHOOLS AROUND DOHA AND VILLAGES 50,137
Qatar CPC/LATTANZI DOHA AIRPORT – GEOTECHNICAL INVESTIGATION 5,765
Qatar QATAR PETROLEUM GEOTECHNICAL INV. FOR GABBRO PROJECT 346,927
Qatar DESCON ENGINEERING RLIC AREA EARTHING BOREHOLE 5,308
Qatar KELLOG BROWN ROOT
FEED FOR RATIONALIZATION OF CONTROL SYSTEM AT KHATIYAH AND FAHAHIL DEGASSING STATION
15,795
Qatar TRAGS AL KHOR CLUB CONVERSION – EARTHING BOREHOLES 5,088
Qatar C.D.C
BARJEEL RESIDENTIAL TOWERS AT WEST BAY – PILING AND EXCAVATION WORKS
123,844
52
Prequalification Document-2015 Rev 28 16.09.2015
Qatar J & P DRILLIJNG BORE HOLE FOR STREET LIGHTING 1,956
Qatar ALHUDA ENG WORKS DEVELOPMENT OF KHALIFA TENNIS & SQUASH 4,877
Qatar Q-CON EPIC OF 11KV DUKHAN TOWNSHIP NETWORK UPGRADE 18,808
Qatar ATKINS
PRIMARY INFRASTRUCTURE DESIGN SERVICES FOR EDUCATION CITY
110,818
Qatar QATAR PETROCHEMICAL
HIGH COD TANK IN ETHYLENE PLANT GEOTECHNICAL INVESTIGATION
7,767
Qatar ATKINS
FEED FOR LPG PIPELINE FROM QP REFINARY TO NEW LPG BOTTLING PLANT
42,941
Qatar PRIVATE ENGINEERING OFFICE VILLA AT AL THAKIRA – GEOTECHNICAL INVESTIGATION 5,589
Qatar GULF DESIGN PROPOSED BUILDING AT A-RING ROAD FOR AHMED DARWISH 5,247
Qatar ATKINS QATAR PRIMARY ROUTES DHUKAN HIGHWAY 74,014
Qatar CHIYODA TECHNIP JOINT VENTURE
ADDITIONAL TOPOGRAPHICAL SURVEY OF DESALINATED WATER PIPES ROUTE AND GEOTECHNICAL INVESTIGATION AT LEAN LNG TANK AREA
28,962
Qatar SLAG AGGREGATE PRODUCER QUARRY FEASIBILITY STUDY AT KARAMA 7,808
Qatar AL-SAAD CONSULTING ENG
2B+G+M+14+SERVICE FLOOR FOR DR. SUMAIKH AT OLD SALATA
9,781
Qatar CTJV
RASGAS ONSHORE/ONPLOT EXPANSION PROJECT – GEOTECH INVESTIGATION
78,840
Qatar SILVER ARACH PROPOSED G+5 BUILDING AT UMM GHUWALINA 4,384
Qatar CCC/TEYSEER JV
QATAR GAS II DEVELOPMENT PROJECT RASLAFFAN – DRILLING GROUND WATER
18,630
Qatar QATAR PETROLEUM
GEOTECHNICAL INVESTIGATION FOR THE GABBRO SUPPORT SERVICES
346,927
Qatar CDC
BARJEEL RESIDENTIAL TOWER AT WEST BAY – PILING AND EXCAVATION WORKS
123,844
Qatar TEFFEN
EPIC OF RASLAFFAN, MESAIEED ETHANE TRANSMISSION PIPELINE PROJECT
37,151
Qatar WS ATKINS
NEW DOHA INTERNATIONAL AIRPORT – INFRASTRUCTURE ROAD PRELIMINARY DESIGN
106,135
Qatar HALCROW LTD MUSEUM OF ISLAMIC ARTS – GEOTECHNICAL INVESTIGATION
27,555
53
Prequalification Document-2015 Rev 28 16.09.2015
2004
Location Client Project Value (US$)
Qatar CHIYODA CORPORATION QATARGAS II LNG PLANT FEED PROJECT – RAS LAFFAN 161,995
Qatar KETTANESH CONSTRUCTION RAS LAFFAN LNG TANK-5 40,860
Qatar AL HUDA ENGINEERING WORKS KHALIFA SPORTS HALL – DOHA 12,329
Qatar DOHA PETROLEUM CONST. CO. HELIUM RECOVERY UNIT – RAS LAFFAN 18,767
Qatar AMERICAN INT’L. CONTRACTORS INC. (AICI)
MILLENNIUM VILLAGE FACILITIES – AL UDEID AIRBASE 11,849
Qatar CHIYODA CORPORATION AL KHALEEJ GAS PROJECT – LPG TANKS – RAS LAFFAN 50,431
Qatar QATAR PETROLEUM GEOTECHNICAL INVESTIGATION FOR PHOTOGRAPHY MUSEUM 41,856
Qatar ENELPOWER RAS LAFFAN POWER & DESALINATION STATION 14,932
Qatar LG ENGG. & CONST. CORP. – KOREA
QP LAB PROJECT – MESAIEED 20,966
Qatar OVERSEAS BECHTEL, INCORPORATED – UK
NEW DOHA INTERNATIONAL AIRPORT PROJECT 1,730,653
Qatar CHIYODA CORPORATION QATARGAS II LNG PLANT FEED PROJECT – RAS LAFFAN (ON-PLOT)
121,185
Qatar W.S ATKINS & PARTNERS DUKHAN ROAD – DETAILED DESIGN 40,592
Qatar AL ATTIYAH CONTG. & TRADG. CO.
ERC 0588 C1 RIW IN NORTH OF DUHAIL – STAGE 2 16,767
Qatar CHIYODA CORPORATION RLIC – CAMPAREA 106,443
Qatar DORNIER CONSULTING GROUNDWATER ASSESSMENT PROJECT – MONITORING WELLS IN DUKHAN
45,842
Qatar MECON QAPCO EXPANSION PROJECT – MESAIEED 26,458
Qatar DORNIER CONSULTING GROUNDWATER ASSESSMENT – HALUL ISLAND 24,932
Qatar JAMES CUBITT & PARTNERS ENGINEERING CONSULTANCY
LAFFAN TOWER (3 B+G+M+32+2 P+15) ADMINISTRATIVE TOWER AT WEST BAY
11,767
Qatar JOANNOU & PARASKEVAIDES QATAR W.L.L.
ERC 0492/C1 – AL GHARRAFFA INTERCHANGE 34,603
Qatar QATAR PETROLEUM LTC 172/03 – BASELINE SURVEY AND MONITORING OF THE
GROUNDWATER MONITORING WELLS IN MESAIEED INDUSTRIAL CITY
281,418
Qatar FCB CEMENT QATAR CEMENT PLANT UMM BAB 27,123
Qatar CHIYODA CORPORATION QATARGAS II LNG PLANT PROJECT – SULPHUR HANDLING AREA& PIPELINE ROUTE
61,014
Qatar BUZWAIR E&C. ERC 0390 C5 – DESIGN & CONST. OF ACCESS ROADS TO MOTORCYCLE RACETRACK
15,452
Qatar MARUBENI GTC 1/2002 – POWER SUPPLY TO QATAR FOUNDATION AND 132kV OHL REPLACEMENT BY CABLE IN GHARRAFA – DOHA
52,041
Qatar COWI – QATAR NORTH BEACH DEVELOPMENT – DOHA 727,617
Qatar QATAR PETROLEUM SO # 30443 – FIREWALL TANK AT FAHAHIL STRIPPING PLANT 6,493
Qatar MMAA – DRAINAGE DEPT. 7A+7B+7E – ABU HAMOUR SOUTHERN OUTFALL 20,990
Qatar ATKINS NEW QASCO DIRECT REDUCTION IRON FACILITY 7,397
Qatar INDUSTRIAL SERVICES GROUP TOWER BUILDING AT WEST BAY 7,808
Qatar NASSER S. AL HAJRI CO. LTD. DOLPHIN ONSHORE FACILITIES PROJECT – RAS LAFFAN 136,986
Qatar QATAR DREDGING CO. NDIA – CORE DRILLING IN ROCK OUTCROP 11,616
54
Prequalification Document-2015 Rev 28 16.09.2015
Qatar QATAR LIQUEFIED GAS CO. AMINE REGENERATION UNITAREA 7,808
Qatar MEDGULF CONST. CO. GTC 04/175/ED – EPIC OF NEW PRODUCTION & INJECTION WELLS AT ARAB D PLANT IN DUKHAN
25,327
Qatar ATKINS DUKHAN HIGHWAY – ADDITIONAL BOREHOLES 16,896
Qatar RMJM – DUBAI DUBAI TOWER – DOHA 583,578
Qatar CHIYODA CORPORATION QATARGAS II LNG PLANT FEED PROJECT – RAS LAFFAN 8,135
Qatar MOHAMED BIN MUBARAK SALEH AL KULAIFI
DEVELOPMENT AT WEST BAY LAGOON – DOHA 6,671
Qatar TRADING & AGENCY SERVICES DUKHAN FITNESS CENTRE, DUKHAN TOWNSHIP 11,027
*Pre-2004 project references are available on request.
55
Prequalification Document-2015 Rev 28 16.09.2015
Major Completed Projects and On-going Projects
Laboratory (Qatar)
Client Project Details Period
ISG-IMPREGILO, SK-E&C-
GALFAR AL MISNAND JV
DOHA METRO – REDLINE NORTH
UNDERGROUND – GROUND WATER
ANALYSSIS
GROUND WATER ANALYSIS 25-05-2014
KEO INTERNATIONAL TREATED SEWAGE EFFLUENT
SAMPLING LABORATORY TESTING WORKS 22-05-2014
ORYX GTL
CALL OFF SERVICE FOR
ENVIRONMENTAL ANALYSTICAL
SERVICES FOR LABORATORY
SECTION
LABORATORY TESTING WORKS 11-05-2014
RASGAS LTD GROUND WATER ANALYSIS AND
TCLP ANALYSIS LABORATORY TESTING WORKS 24-04-2014
AL JABER ENGINEERING RASGAS PROJECT LABORATORY TESTING WORKS 01-03-2014
CARILLION QATAR LLC ANALYSIS OF DRINKING WATER WATER SAMPLE TESTING 23-02-2014
IMPREGILO SAMPLING AND ANALYSIS OF
WATER SAMPLES – 6400010469 WATER SAMPLE ANALYSIS 13-02-2014
QATAR SHELL U137254 – PROVISION OF GROUND
WATER SAMPLING & ANALYSIS LABORATORY TESTING WORKS 04-02-2014
CH2M HILL
INTERNATIONAL
DC-QOP-684C, WITH DOLPHIN
ENERGY WATER ANALYSIS AND SERVICE 26-01-2014
BOSKALIS
WESTMINISTER EAST LTD
ENVIRONMENTAL MONTHLY
MONITORING OF SEDIMENT & SEA
WATER
LABORATORY TESTING WORKS 21-01-2014
MIDDLE EAST DREDGING
CO. – MEDCO
NPP PROJECT – SITE LABORATORY
FOR TESTING WORKS LABORATORY TESTING WORKS
07-01-2014 -
Ongoing
GULF DRILLING PROVISION OF WATER ANALYSIS
SERVICE – CALL ON BASIS WATER ANALYSIS
31-12-2013 – On
going
J & P CONSTRUCTION OF WEST CORRIDOR
P010 (PACKAGE 1) LABORATORY TESTING WORKS
06-10-2013 – On
going
DOLPHIN ENERGY CALL OFF EXTERNAL LABORATORY
ANALYTICAL SERVICE LABORATORY TESTING WORKS
23-08-2013 – On
going
IMPREGILLO
CONSTRUCTION OF ABU HAMOUR
SURFACE & GROUND WATER
TUNNEL – PHASE 1
LABORATORY TESTING WORKS 01/07/2013 – On
going
56
Prequalification Document-2015 Rev 28 16.09.2015
ANAS
QUALITY ASSURANCE / QUALITY
CONTROL PAVEMENT
CONSULTANCY FROM PUBLIC
WORKS AUTHORITY
LABORATORY TESTING WORKS 26-06-2013 – On
going
CHINA HARBOUR
PORT BASIN AND BREAKWATER
CONSTRUCTION – WATER QUALITY
SAMPLING, TESTING AND
REPORTING
SEA WATER ANALYSIS 23-06-2013 – On
going
LARSEN & TOUBRO DOHA SOUTH STW PROJECT PHASE
11 – LABORATORY TESTING WORKS LABORATORY TESTING WORKS
26-06-2013 – On
going
SINOHYDRO GROUP LTD
SIDRA VILLAGE PROJECT – STAFF
HOUSING FOR SIDRA, MEDICAL AND
RESEARCH CENTRE – PACKAGE 2 –
COMPACTION TESTING WORKS
COMPACTION TESTING WORKS 11-06-2013 – On
going
RAS GIRTAS POTABLE WATER ANALYSIS POTABLE WATER ANALYSIS 11-06-2013 – On
going
CONSOLIDATED
CONTRACTORS GROUP
NEW PORT PROJECT – CONTAINER
TERMINALS INFRASTRUCTURE AND
UTILITY BUILDING – LABORATORY
TESTING WORKS
LABORATORY TESTING WORKS – SITE LAB 04-06-2013 – On
going
DORNIER CONSULTING WELL WATER SAMPLING LABORATORY TESTING WORKS 01/06/2013 – On
going
QATAR GAS OPERATING CALL OFF CONTRACT FOR
LABORATORY SERVICE LABORATORY TESTING WORKS
22-05-2013 – On
going
SEA SHORE ENGINEERING
MAINTENANCE OF WASTE
MANAGEMENT FACILITIES,
RASLAFAN – ENVIRONMENTAL
ANALYSIS, SOIL & GROUND WATER
ENVIRONMENTAL ANALYSIS 16-05-2013 – On
going
GHD GROUND WATER ANALYSIS GROUND WATER ANALYSIS 15-05-2013 – On
going
DOHA PETROLEUM
(DOPET) POTABLE WATER ANALYSIS POTABLE WATER ANALYSIS
13-05-2013 – On
going
DEGREMONT WASTE WATER TREATMENT PLANT –
LUSAIL WASTE WATER ANALYSIS
13-05-2013 – On
going
URBACON GENERAL
CONTRACTING
COAST GUARD PROJECTS,
SUMAISMAH – WATER AND
SEDIMENT QUALITY MONITORING
WATER AND SEDIMENT QUALITY MONITORING 17-04-2013 -
Completed
TARGET ENGINEERING
CONSTRUCTION CO.
RAF A2 DESALINATION PLANT – SEA
WATER INTAKE PUMP HOUSE &
OFFICE PIPE LINE WORKS –
LABORATORY TESTING WORKS 28-03-2013 – On
going
57
Prequalification Document-2015 Rev 28 16.09.2015
LABORATORY TESTING WORKS
CONSOLIDATED
CONTRACTORS GROUP
DUKHAN – HIGHWAY PROJECT
(CENTRAL CONTRACT ) LABORATORY TESTING WORKS
27-03-2013 – On
going
MIDMAC YUKSEL
LUSAIL DEVELOPMENT FOR
PRIMARY INFRASTRUCTURE –
PACKAGE 4
LABORATORY TESTING WORKS 18-03-2013 -
Completed
SCHLUMBERGER WATER ANALYSIS WATER ANALYSIS 28-02-2013 – On
going
GULF CONTRACTING CO.
WLL
PEARL GTL PROJECT RAS LAFFAN –
PROJECT LABORATORY TESTING
WORKS
LABORATORY TESTING WORKS 24-01-2013 – On
going
MARUBENI WATER SAMPLING AND ANALYSIS WATER SAMPLING AND ANALYSIS 05-02-2013 – On
going
SINOHYDRO-DOMOPAN
JV
INDEPENDENT LABORATORY
TESTING WORKS LABORATORY TESTING WORKS
05-02-2013 – On
going
DESCON ENGINEERING PMP AND OTHER VARIOUS PROJECT LABORATORY TESTING WORKS 10/01/2012 On
going
JGC CORPORATION POTABLE WATER, SOIL AND
ENVIRONMENTAL ANALYSIS LABORATORY TESTING WORKS
10/01/2013– On
going
QDVC LUSAIL CAR PARK LABORATORY TESTING WORKS 05/01/2013 – On
going
XYLEM WATER SOLUTION DOHA SOUTH WWTP WATER ANALYSIS 2013 – On going
PUNJ LLOYD PLOYSILICON PLANT RASLAFFAN LABORTORY TESTING WORKS 10/01/2012 On
going
MEDGULF
CONSTRUCTION TEST FOR EARTH WORKS SOIL TESTING 22/01/2012-Ongoing
BOOM GENERAL
CONSTRUCTION
PWA/GTC/011/08-09 –
CONSTRUCTION AND
MAINTTENANCE OF AL KHOR PARK
LABORATORY TESTING WORKS 29/01/2012 -
Completed
CONSTRUCTION
DEVELOPMENT
COMPANY
P347/QATAR FOUNDATION OFFSITE
WARE HOUSE AT INDUSTRIAL AREA CONCRETE TESTING WORKS
15/02/2012 -
Completed
MIDMAC CONTRACTING CONSTRUCTION OF QF H.Q AND
STRATEGIC STUDIES CENTRE ANALYSIS OF POTABLE WATER
28/02/2012 -
Ongoing
QATAR GAS QGII-CWO-CSP-1174-11 – SOIL
SAMPLING WITHIN JETTY OFFICES SOIL SAMPLING
08/03/2012 On
going
BUZWAIR ENGINEERING PWA/GTC/073/2010/2011 ROAD
IMPROVEMENT IN RAYYAN AREA – SOIL SAMPLING
03/04/2012 -
58
Prequalification Document-2015 Rev 28 16.09.2015
& CONTRACTING PHASE 2 Completed
COWI SAMPLING AND ANALYSIS FOR SOIL
AND GROUND WATER SOIL AND GROUND WATER SAMPLING
06/05/2012 -
Completed
Q-CON 02-N2, PIPELINE BACKBONE IN
RASLAFFAN LABORATORY TESTING SERVICES
07/06/2012 On
going
QATAR KENTZ JETTY BOIL OFF-GAS PROJECT LABORATORY TESTING WORKS PHYSICAL,
CHEMICAL & CEMENT 17/06/201 On going
SINOHYDRO GROUP KAHRAMA AWARENESS PARK
PROJECT LABORATORY TESTING WORKS
01/07/2012 On
going
RAS GIRTAS RGPC-LAB-002-2012 – LABORATORY
TESTING WORKS LABORATORY TESTING WORKS
18/07/2012 On
going
TECHNIP
FEASIBILITY STUDY & CONCEPT
OPTIMIZATION – EFFLUENT
TREATMENT PLANT
SPENT CAUSTIC SAMPLING AND ANALYSIS 19/07/201 -
Completed
KEPPEL SEGHERS DOHA NORTHSEWAGE TREATMENT
WORKS CP-682/10
COMPACTION TESTING USING NUCLEAR DENSITY
GAUGE
07/08/2012 On
going
SAMSUNG ENGINEERING LAFFAN REFINERY DIESEL –
HYDROTREATER PROJECT
PROVISIONOF CONCRETE QUALITY CONTROL
ENGINEER
12/09/2012 -
Completed
KEPPEL SEGHERS DOHA NORTH SEVAGE TREATMENT THIRD PARTY LAB ANALYS Jan 2011 On going
PARSONS WASTEWATER ANALYSIS REQUIRED
BY PUBLIC WATER AUTHORITY WASTE WATER ANALYSIS
Jan 2011 – Feb 2011-
Completed
HYDER CONSULTING
EXPANSION OF INDUSTRIAL AREA
SEWERAGE TREATMENT FACILITY –
SECOND PHASE
SLUDGE SAMPLING AND ANALYSIS Jan 2011- March
2011-Completed
QATAR PETROCHEMICAL
COMPANY
GROUND WATER SAMPLING AND
ANALYSIS LABORATORY TESTING WORKS
Feb 2011 – Nov
2011-Completed
REDCO INT’L Burj marina LABORATORY TESTING WORKS Mar 2011 On going
HYDER CONSULTING PACKAGE 24 – AL KHOR – AL
THAKIRA SOIL AND GROUND WATER SAMPLING Apr 2011 - Oct 2011
DEGREMONT MARUBANI DOHA WEST SEWAGE TREATMENT
WORKS WASTE WATER ANALYSIS Apr – 2011 On going
QATAR GAS SOIL SAMPLING AND ANALYSIS SOIL SAMPLING AND ANALYSIS Apr 2011 – On going
QATAR ALUMINIUM
(QATALUM)
SEA WATER SAMPLING AND
ANALYSIS
SEA WATER SAMPLING AND ANALYSIS May -2011 -
Completed
QATAR SHELL GTL LTD PEARL GTL TEMPORARY LAB TESTING – CALL OFF SERVICE May 2011 On going
59
Prequalification Document-2015 Rev 28 16.09.2015
QATAR SHELLGTL
RESEARCH AND
TECHNOLOGY CENTRE
TECHNOLOGY & SCIENCE PARK –
QATAR FOUNDATION
ANALYSIS OF DESULPHIRIZATION SOLUTION FOR
HEAVY METALS June 2011 On going
QATAR ENGINEERING
AND CONSTRUCTION CO.
JETTY BOIL OF GAS RECOVERY LABORATORY TESTING WORKS June 2011 Ongoing
DOLPHIN ENERGY DOLPHIN PLANT RAS LAFFAN GROUND WATER SAMPLING AND TESTING
SERVICES
June 2011 On going
AL HUDA ENGINEERING
CONSTRUCTION OF SUPREME
EDUCATION COUNCIL HEAD
QUARTERS BUILDING
LABORATORY TESTING WORKS Jul 2011 – On going
REDCO INT’L QATAR AIRWAYS CREW
ACCOMMODATION
SOIL SAMPLING AND LABORATORY TESTING
WORKS
Jul 2011 -2012 -
Completed
REDCO INT’L DOHA LAND LABORATORY TESTING WORKS Jul 2011 On going
QATAR FERTILIZERS
(QAFCO) QAFCO – 5 PROJECT
RECLAIMED/DREDGED MATERIAL SAMPLING
ANALYSIS Jul 2011 -Completed
MIDMAC TARMAC NDIA LABORATORY TESTING WORKS Aug 2011 On going
REDCO INT’L 5 SCHOOLS AROUND DOHA &
VILLAGE
SOIL SAMPLING AND LABORATORY TESTING
WORKS
Aug 2011 -
Completed
TECHNITAL BEACH DEVELOPMENT AT RAS
USHAYRIQ PENINSULA ENVIRONMENTAL TETING
Aug 2011
Oct 2011 -Completed
NASSER AL HAJRI BARZAN ONSHORE FACILITIES LABORATORY TESTING WORKS Sep 2011 On going
WORELY PARSON
ENVIRONMENTAL IMPACT
ASSESSMENT AT AL KARANA AND
BIRKA
ENVIRONMENTAL TESTING Oct 2011
Nov 2011-Completed
YUKSEL MIDMAC DOHA EXPRESS – PACKAGE 7 NUCLEAR DENSITY Nov 2011 -
Completed
GALFAR AL MISNAD CONCRETE CORING AT QATAR GAS
BUILDING AT WEST BAY CONCRETE CORING
Nov 2011
Dec 2011 -
Completed
JGC CORPORATION BARZAN ONSHORE PROJECT SAMPLING AND ANALYSIS OF WATER Nov 2011
Q-CON PLATEAU MAINTENANCE PROJECT LABORATORY TESTING WORKS Dec 2011 On going
TECHNITAL DEVELOPMENT OF AL WAKRA JETTY ENVIRONMENTAL TESTING Dec 2011
On going
PUBLIC WORK
AUTHORITY (ASHGHAL) TENDER#AA/DOM/10-11M/1398
DRAINAGE NETWORKS ANALYSTICAL
PROGRAMME Jan 2011 Ongoing
60
Prequalification Document-2015 Rev 28 16.09.2015
HYDER CONSULTING`
DA/07-08/D/025/1 – SECOND PHASE
EXPANSION OF INDUSTRIAL AREA
SEWERAGE TREATMENT FACILITY
EXPANSION OF INDUSTRIAL AREA SEWAGE
TREATMENT FACILITY
Jan 2011 Feb 2011--
Completed
SINOHYDRO
CORPORATION NDIA – CP- 1 PROJECT – LUSAIL
ONSITE LABORATORY FOR SOIL, AGGREGATE ,
CONCRETE , STEEL AND ASPHALT TESTING
Year 2008 and
Ongoing
HYUNDAI ENGINEERING QAFCO 5 & QAFCO 6 ONSITE LABORATORY FOR SOIL, AGGREGATE ,
CONCRETE , AND ASPHALT TESTING July 2008 -Completed
J&P PARASKEVAIDES MALE & FEMALE STUDENTS
HOUSING AT QATAR FOUNDATION
ONSITE LABORATORY FOR SOIL, AGGREGATE ,
CONCRETE TESTING Nov 2010 -Completed
KETTANEH
CONSTRUCTIONS
PLATEAU MAINTENANCE PROJECT
ON SHORE FACILITIES RAS LAFFAN
ONSITE LABORATORY FOR SOIL, AGGREGATE ,
CONCRETE TESTING Nov 2011 On going
QATAR ENGINEERING
CONSTRUCTION
Q3 99 – WASTE WATER DISPOSAL
SURFACE FACILITIES
SOIL, AGGREGATE AND CONCRETE TESTING -
CALL ON BASIS Feb 2011 On going
QATAR CONSTRUCTION
ENGINEERING
CONSTRUCTION OF OPERATATOR
SHELTER LIFTING STATION AND
SEWER NETWORK – DOLPHIN
SOIL, AGGREGATE AND CONCRETE TESTING -
CALL ON BASIS Dec 2012 On going
QATAR ENGINEERING
CONSTRUCTION Q 356 – HALUL ISLAND
ONSITE LABORATORY FOR SOIL, AGGREGATE ,
CONCRETE , AND TESTING Feb 2011 -Completed
QATAR ENGINEERING &
CONSTRUCTION CO QAFCO MELAMINE SOIL, CONCRETE AND IN-SITU TESTING
Feb 2008
May 2011- -
Completed
QATAR ENGINEERING &
CONSTRUCTION CO DOLPHIN SOIL, CONCRETE AND IN-SITU TESTING
Apr 2008 May 2011--
Completed
QATAR ENGINEERING &
CONSTRUCTION CO INTERIM MODIFICATION SOIL, CONCRETE AND IN-SITU TESTING
Aug 2010 – Feb 2011-
-Completed
QATAR ENGINEERING &
CONSTRUCTION CO ORYX GTL SOIL, CONCRETE AND IN-SITU TESTING
Sep 2010 – Mar 2011-
-Completed
SUB SEA PROTECTION
SYSTEM LLC ARAMCO CONCRETE TESTING
Mar 2011 –
Oct 2011--Completed
MIDMAC CONTRACTING NDIA CP 14- AIRSIDE & LAND SIDE
ROAD WORKS
ONSITE LABORATORY FOR SOIL, AGGREGATE ,
CONCRETE , AND ASPHALT TESTING Feb 2006 -Completed
MIDMAC CONTRACTING NDIA CP 28- PASSENGER TERMINAL -
FOUNDATIONS
ONSITE LABORATORY FOR SOIL, AGGREGATE ,
CONCRETE , AND ASPHALT TESTING
Aug 2007 – Sept
2009-Completed
CCIC NDIA CP 17 – AIR TRAFFINC
CONTROL SUPPORT & FACILITIES
ONSITE LABORATORY FOR SOIL, AGGREGATE ,
CONCRETE , AND ASPHALT TESTING
Apr 2007 – Sep 2011-
Completed
CCIC NDIA CP 27 – MIDFIELD AREAS ONSITE LABORATORY FOR SOIL, AGGREGATE , October 2007 -
61
Prequalification Document-2015 Rev 28 16.09.2015
ACCES SYSTEM CONCRETE , AND ASPHALT TESTING Ongoing
CCIC NDIA – CP 96 ONSITE LABORATORY FOR SOIL, AGGREGATE ,
CONCRETE , AND ASPHALT TESTING Mar 2011 On going
CCIC NDIA – CP 19 ONSITE LABORATORY FOR SOIL, AGGREGATE ,
CONCRETE , AND ASPHALT TESTING Mar 2011 On going
CCIC NDIA- CP 95 ONSITE LABORATORY FOR SOIL, AGGREGATE ,
CONCRETE , AND ASPHALT TESTING Mar 2011 On going
CCIC NDIA CP - 93 ONSITE LABORATORY FOR SOIL, AGGREGATE ,
CONCRETE , AND ASPHALT TESTING Mar 2011 On going
CCIC NDIA CP - 76 ONSITE LABORATORY FOR SOIL, AGGREGATE ,
CONCRETE , AND ASPHALT TESTING Mar 2011 On going
BILFINGER BERGER BARWA CITY PHASE 1 ONSITE LABORATORY FOR SOIL, AGGREGATE ,
CONCRETE , AND ASPHALT TESTING Sep 2007 -Completed
REDCO INTERNATIONAL BARWA CITY PROJECT CONCRETE AND MATERIAL TESTING Jan 2010 – Ongoing
REDCO INTERNATIONAL LUSAIL READYMIX ONSITE LABORATORY FOR SOIL, AGGREGATE ,
AND CONCRETE TESTING
March 2010 Mar
2011--Completed
REDCO INTERNATIONAL 12 NEW DEPARTURE GATE AT DIA CONCRETE AND MATERIAL TESTING – CALL ON
BASIS
March 2011
-Completed
REDCO INTERNATIONAL SIMULATOR CENTRE (QATAR
AIRWAYS)
CONCRETE AND MATERIAL TESTING – CALL ON
BASIS Jan 2011 -Completed
GALFAR AL MISNAD CONSTRUCTION OF THE CULTURAL
VILLAGE CONCRETE, MATERIALS AND IN-SITU TESTING
Jan 2009 – April
2010-Completed
GALFAR AL MISNAD CONSTRUCTION OF THE
INFRUSTRUCTURE FOR KATARA CONCRETE, MATERIALS AND IN-SITU TESTING July 2010 -Completed
GALFAR AL MISNAD EPIC FOR PRODUCED WATER CONCRETE, MATERIALS AND IN-SITU TESTING Feb 2010 -
Completed
RENCO QATAR
CP-35 AIR TRAFFIC &
METEOROLOGICAL SPECIFIC
EQUIPMENT
CONCRETE AND MATERIAL TESTING Oct 2010 – Dec 2011
--Completed
GCC / SELEX CP-35 CONCRETE AND MATERIAL TESTING March 2011 Dec 2011
--Completed
DEGREMONT DOHA WEST STP SEWAGE WATER ANALYSIS Jan 2009 On going
DEGREMONT BARWA HOUSING PROJECT SEWAGE WATER ANALYSIS Mar 2010
Aug 2011--Completed
FIVE OCEANS – OMAN ODC ENVIRONMENTAL
ENVIRONMNETAL ANALYSIS Dec 2010 --
62
Prequalification Document-2015 Rev 28 16.09.2015
MONITORING Completed
GHD 75/10530/02 – CONSTRUCTION SITE SOIL & WATER ANALYSIS 2011-Completed
QDVC SHERATON CAR PARK GROUND WATER ANALYSIS Feb 2011
Jul 2011 --Completed
TCJV PMP DRINKING WATER ANLYSIS Feb 2011 On going
ZOOM STEEL MINING & EXPLORATORY WORKS -
OMAN CHEMICAL ANALYSIS OF ROCK
Jan 2010 – April
2010--Completed
TECHNITAL UPD/TAC/T/04/08-09 NOISE MONITORING & ECOLOGICAL SURVEY Nov 2010 – May
2011--Completed
ULTRA CONSTRUCTION DOHA NORTH SEWAGE &
ASSCOCIATED WORKS ENVIRONMNETAL ANALYSIS
Sept 2009 – Oct
2011--Completed
IBER DROLA MESAIEED POWER PLANT ENVIRONMENTAL SAMPLING & ANALYSIS June 2008 – JUL
2010-Completed
NEW DOHA PORT
PROJECT COMMITTEE NEW DOHA PORT ENVIRONMENTAL SAMPLING & ANALYSIS
March 2010- Mar
2011-Completed
HYDER CONSULTANTS MMUP- CONCEPT DESIGN OF
ROAD/INFRASTRUCTURE. NOISE MONITORING
Dec2009
May 2010--
Completed
HYDER CONSULTANTS MMUP- CONCEPT DESIGN OF
ROAD/INFRASTRUCTURE. NOISE MONITORING
Sept 2008
Apr 2010-Completed
MIDMAC - TARMAC DOHA INTERNATIONAL AIRPORT ADDITIONAL 14 BAY APRONS AT DOHA
INTERNATIONAL AIRPORT
Jan 2009 – Sept 2009
--Completed
DANWAY QATAR GTC/07/122/ED- SUB STATIONS AT
DUKHAN OIL FIELDS SOIL & IN-SITU TESTING OWRKS
June 2008 – Dec
2009--Completed
ASCO NAKHILAT SHIP REPAIR YARD, RAS
LAFFAN SOIL & IN-SITU TESTING OWRKS
Aug 2009 – Dec 2010-
Completed
ASCO EMERGENCY & SAFETY COLLEGE,
RAS LAFFAN SOIL & IN-SITU TESTING OWRKS
June 2009 -
Completed
CCIC CBCS – QATAR FOUNDATION CONCRETE TESTING Aug 2007 – Mar
2008-Completed
CHIYODA TECHNIP JOINT
VENTURE – CTJV QATAR GAS 3 & 4 POTABLE WATER SAMPLING AND ANALYSIS June 2008 – Ongoing
COMPASS CATERING QATALUM SEWAGE WATER ANALYSIS April 2008 – May
2010--Completed
63
Prequalification Document-2015 Rev 28 16.09.2015
COMPASS CATERING QATALUM PROJECT POTABLE WATER ANALYSIS April 2008 – May
2010--Completed
COMPASS CATERING QATAR SHELL GTL POTABLE WATER ANALYSIS March 2009 -
Ongoing
COWI QATALUM GROUND WATER ANALYSIS Aug 2008 – Mar
2011-Completed
CONSPEL QATAR CHILLED WATER NETWORK AT
PEARL QATAR CHILLED WATER ANALYSIS July 2010 - Ongoing
DESCON ENGINEERING QATAR SHELL GTL ALL TESTING WORKS INCLUDING ON-SITE
LABORATORY
Sep 2008 – Feb 2011-
-Completed
DOLPHIN ENERGY GROUND WATER MONITORING
WELLS ENVIRONMENTAL ANALYSIS Aug 2009 - Ongoing
GULF DRILLING RIG – GULF4, AL ZUBARAH, ADL
DOHA, GULF 3
POTABLE WATER AND SEWAGE WATER
ANALYSIS Aug 2008 – Ongoing
J&P PARASKEVAIDES PEARL QATAR SOIL AND AGGREGATE TESTING Feb 2009 – Ongoing
J&P PARASKEVAIDES
CONSTRUCTION OF ADVANCE
WORKS FOR THE CONVENTION
CENTRE - QATAR FOUNDATION
ONSITE LABORATORY FOR SOIL, AGGREGATE ,
CONCRETE TESTING
Aug 2009 – Aug 2010-
Completed
J&P PARASKEVAIDES AL WAKRAH HOSPITAL ASPHALT TESTING Jun 2010 – May 2011
ITT WATER & WASTE
WATER - UK DOHA SOUTH STW SAMPLING & ANALYSIS OF SEWAGE WATER
AUG 2010 – OCT
2010-Completed
JANDENUL DREDGING GABBRO BERTH EXPENSION ENVIRONMENTAL ANALYSIS Aug 2009 – Feb 2010-
Completed
JANDENUL DREDGING GABBRO BERTH EXPENSION SOIL AND AGGREGATE TESTING Aug 2009 – Feb 2010-
Completed
VEOLIA QATAR DOHA SOUTH STW & INDUSTRIAL
AREA STP SAMPLING & ANALYSIS OF SEWAGE WATER
AUG 2009 – OCT
2010-Completed
KEPPEL SHEGERS AL DHAKEERA SEWAGE TREATMENT
PLANT SEWAGE WATER ANALYSIS
Oct 2008 –
Completed
KEPPEL SHEGERS DOHA NORTH SEWAGE TREATMENT
WORKS SEWAGE WATER ANALYSIS
Oct 2008 – -
Completed
METITO AL KHOR STP SEWAGE WATER ANALYSIS Jun 2009 – Ongoing
METITO DOHA WEST SEWAGE WATER ANALYSIS March 2010 Jun
2011-Completed
METITO QATALUM WWTP SEWAGE WATER ANALYSIS Aug 2010 – Jun 2011-
Completed
64
Prequalification Document-2015 Rev 28 16.09.2015
METITO PEARL QATAR SEWAGE WATER ANALYSIS Dec 2009 – Jun 2011-
Completed
QATAR ALUMINUM QATALUM SEA WATER AND WASTE WATER ANALYSIS Jan 2010 --Completed
QATAR AIRWAYS WATER ANALYSIS POTABLE WATER ANALYSIS Apr 2010 – Ongoing
QATAR SHELL GTL PEARL GTL WASTE WATER ANALYSIS Dec 2009 – Oct 2011-
Completed
QATAR KENTZ RASLAFFAN POTABLE WATER ANALYSIS Jan 2009 – Ongoing
QATAR COOL PEARL QATAR CHILLED WATER ANALYSIS Apr 2010 – Ongoing
QATAR COOL WEST BAY DISTRICT COOLING CHILLED WATER ANALYSIS Apr 2010 – Ongoing
QATAR PETROLEUM BASLINE SURVEY OF GROUND
WATER MONITORING WELLS ENVIRONMENTAL ANALYSIS
Jan 2010 – -
Completed
QATAR VINYL COMPANY MESAIEED ENVIRONMENTAL ANALYSIS Jul 2009 - Ongoing
REDCO GROUP RAYYAN PALACE SOIL AND IN-SITU TESTING Apr 2010 – May
2011-Completed
SCHLUMBERGER ASGHAL, VINCI ENVIRONMENTAL ANALYSIS Nov 2009 – Ongoing
STRABAG QATAR QATAR SHELL PEARL GTL CONCRETE AND MATERIAL TESTING Jan 2008 – May 2010-
Completed
SIX CONSTRUCT SEWAGE TREATMENT PLANT SEWAGE WATER SAMPLING AND ANALYSIS Aug 2010 – Ongoing
SIX CONSTRUCT RO PLANT POTABLE WATER ANALYSIS Aug 2010 – Ongoing
TRANSFIELD MANNAI AL WOSAIL TOWER, QATAR
FOUNDATION POTABLE WATER ANALYSIS Aug 2009 – Aug 2011-
Completed
WAAGNERBIRO QATAR ASGHAL SEWAGE WATER SAMPLING AND ANALYSIS Oct 2009 - Ongoing
TEKFEN QATAR NORTH ROAD CONCRETE TESTING Jan 2008 – Jun 2009-
Completed
GULF CEMENT CO NEW CEMENT FACTORY, UMMBAB-
FEASIBLITY STUDY. CHEMICAL ANALYSIS ON LIMESTONE
Oct – Dec 2006-
Completed
CCIC RLX, RAS LAFFAN GROUND WATER MONITORING April 2006 –Feb 2011-
Completed
JGC MIDDLE EAST DOLPHIN, RAS LAFFAN GROUND WATER MONITORING Oct 2005 –Mar 2010-
Completed
SYNOHYDRO GAMUDA NEW DOHA INT’NATIONAL AIRPORT ENVIRONMENTAL TESTING & POTABLE WATER
ANALYSIS
April 2006 - -
Completed
METITO PROJECT; C705 ENVIRONMENTAL TESTING Dec 2006 – -
Completed
65
Prequalification Document-2015 Rev 28 16.09.2015
URS CORPORATION ORYX GTL, RAS LAFFAN ENVIRONMENTAL TESTING Mar-06
Feb 2009-Completed
A.A. ENGINEERING INDUSTRIAL AREA STW SEWAGE WATER TESTING Mar 2006 – Jun 2009-
Completed
RUMAILLAH SERVICES PUMPING STATIONS-DOHA SEWAGE WATER TESTING Sep 2005 – Sep 2006-
Completed
QATAR DREDGING CO NEW DOHA INTERNATIONAL
AIRPORT
ENVIRONMENTAL TESTING Jan 2005 - 2007--
Completed
CompletedCompleted SATCO International RAS LAFFAN ENVIRONMENTAL TESTING ON SOIL & WATER Aug 06 -Completed
BOSKALIS WESTMINSTER RAS LAFFAN ENVIRONMENTAL TESTING ON SOIL & WATER Feb 2006 Jul 2009
MUSHRIF CONT.CO DOHA WEST STW MATERIALS AND IN-SITU TESTING Sep 2006- Mar 2009-
Completed DESCON ENG.CO OLEFIN PROJECT, RAS LAFFAN MATERIALS AND IN-SITU TESTING Jul 2006- Jul 2009
ALJABER ENERGY COMMON SULPHUR, QATARGAS II,
RAS LAFFAN
MATERIALS AND IN-SITU TESTING Jun 2006- Feb 2009-
Completed FLUOR MIDDLE EAST RAS GAS, RAS LAFFAN MATERIALS AND IN-SITU TESTING Sep2006-
Apr 2009-Completed NASSER AL HAJRI RAS GAS, RAS LAFFAN MATERIALS AND IN-SITU TESTING Sep 2006- Mar 2009-
Completed NASSER AL HAJRI QATARGAS SRU, RAS LAFFAN MATERIALS AND IN-SITU TESTING Sep 2006- Jan 2011-
Completed CDC/TAKENAKA NEW INTERNATIONAL AIRPORT SOIL, & CONCRETE TESTING Sep 2006- Ongoing
MIDMAC NEW INTERNATIONAL AIRPORT SOIL, ASPHALT, CONCRETE AGGREGATE TESTING Sep 2005 –Aug 2009-
Completed SIX CONSTRUCTION CO. NEW INTERNATIONAL AIR PORT CONCRETE TESTING Aug 2005 - Nov
2006--Completed
Completed ITT INDUSTRIES DOHA SOUTH SEWAGE WATER
ANALYSIS
SEWAGE WATER TESTING Jun - Jul 2005-
Completed ASHGHAL AL DHAKIRA SEWAGE TREATMENT
WORK
SEWAGE WATER TESTING May - Jun 2005-
Completed NASSER AL HAJRI DOLPHIN PROJECT, RAS LAFFAN MATERIALS AND IN-SITU TESTING Oct 2004 – Mar 2009-
Completed QATAR PETROLEUM BASE LINE SURVEY OF GROUND
WATER MONITORING WELLS AT MIC
GROUNDWATER SAMPLING AND LABORATORY
TESTING.
Jul 2004 – Apr 2008-
Completed SIX CONSTRUCT MUSEUM OF ISLAMIC ARTS MATERIALS AND IN-SITU TESTING Jan 2004 - Feb 2005-
Completed SIX CONSTRUCT /
MIDMAC
KHALIFA STADIUM REDEVELOPMENT
– PACKAGE 3 – WEST STAND
MATERIALS AND IN-SITU TESTING Oct 2003 to Mar
2005-Completed
OVERSEAS BECHTEL INC. NEW DOHA INTERNATIONAL
AIRPORT PROJECT
SOIL AND WATER SAMPLING AND TESTING FOR
VARIOUS CONTAMINANT SPECIES
Feb - Aug 2004-
Completed
HYDER CONSULTING DOHA WEST SEWAGE TREATMENT
WORKS - FLOW SAMPLING AND
LABORATORY TESTING
SEWAGE SAMPLING AND LABORATORY TESTING Sep - Oct 2003-
Completed
QAPCO QATOFIN PROJECT, MESAIEED SOIL AND WATER SAMPLING AND TESTING FOR
VARIOUS CONTAMINANT SPECIES Nov-03-Completed
AL BAIDA TECHNICAL
SERVICES
DEEP WELL DRILLING PROJECTS, SW
QATAR
HEAVY METAL ANALYSIS OF GROUND WATER
SAMPLES
Jul-03-Completed
QP / MIC NODCO REFINERY AREA, MESAIEED ENVIRONMENTAL ANALYSIS – HEAVY METALS
AND TPH Apr-03-Completed
66
Prequalification Document-2015 Rev 28 16.09.2015
MMAA – DRAINAGE
DEPARTMENT
GROUND WATER SAMPLING AND
ANALYTICAL LABORATORY TESTING
– PUMP STATIONS ENVIRONMENTAL
IMPACT STUDY
GROUND WATER SAMPLING AND LABORATORY
TESTING FOR VARIOUS CONTAMINANT SPECIES May-03-Completed
MMAA – DRAINAGE
DEPARTMENT
CP-505 INDUSTRIAL AREA
SEWERAGE
LABORATORY ANALYSIS OF SEWAGE SAMPLES Feb-03-Completed
QATAR PETROLEUM WOQOD BITUMEN STORAGE AND
LOADING FACILITIES – MESAIEED
SOIL AND WATER SAMPLING AND TESTING FOR
VARIOUS CONTAMINANT SPECIES Jan-03-Completed
NITCO AL KHOR SEWAGE TREATMENT
WORKS
LABORATORY ANALYSIS OF SEWAGE SAMPLES May - Sep 2002-
Completed
MMAA – DRAINAGE
DEPARTMENT ABU HAMOUR SOUTHERN OUT FALL.
MARINE WATER, LAKE SURFACE WATER &
SEDIMENT AND DISCHARGE WATER SAMPLING
AND ANALYSIS FOR CONTAMINATION STUDY.
OFFSHORE CURRENT AND TIDAL MONITORING.
Jun 2002 - Apr 2003-
Completed
GULF HOUSING & CONST. QATARGAS – DEBOTTLENECKING
PROJECT, RAS LAFFAN
MATERIALS AND IN-SITU TESTING Jul 2002 – Jul 2005-
Completed
GRANDI LAVORI FINCOSIT LAND RECLAMATION IN LPG
STORAGE AREA AT RAS LAFFAN
MATERIALS AND IN-SITU TESTING Mar 2002 – May
2003-Completed
GRANDI LAVORI FINCOSIT MULTI-PRODUCTS BERTH, MESAIEED MATERIALS AND IN-SITU TESTING Oct 2001 – Sep 2004-
Completed
GRANDI LAVORI FINCOSIT CRUSHED STONE FACILITY AT
MESAIEED MATERIALS AND IN-SITU TESTING Oct 2001 - Aug 2004-
Completed
GRANDI LAVORI FINCOSIT RAS LAFFAN COMMON COOLING
WATER PROJECT MATERIALS AND IN-SITU TESTING Jun 2002 - Nov 2003
CCIC RAS LAFFAN COMMON COOLING
WATER PROJECT MATERIALS AND IN-SITU TESTING Jun 2002 - Sep 2004-
Completed
CCIC RAS LAFFAN EXPANSION PROJECT MATERIALS AND IN-SITU TESTING Oct 2001 – 2004-
Completed
J&P IMMIGRATION & SALWA
INTERCHANGES MATERIALS AND IN-SITU TESTING Apr 2003 – Sep 2004-
Completed
CCIC KHALIFA SPORTS HALL MATERIALS AND IN-SITU TESTING Sep 2003 – Aug 2005.
-Completed
READINESS
MANAGEMENT U.S. AIRBASE, AL UDEID ASPHALT AND CONCRETE TESTING WORKS Apr - Jun 2002-
Completed
INTERBETON QAFCO – IV EXPANSION, MESAIEED ALL TESTING WORKS INCLUDING ONSITE
LABORATORY
May 2002 – May
2003-Completed
CCIC QAFCO – IV EXPANSION, MESAIEED ALL TESTING WORKS INCLUDING ONSITE
LABORATORY
2002 – 2004-
Completed
WSP INTERNATIONAL RAS ABU ABOUD - EIA SAMPLING AND ANALYSIS OF SOIL AND WATER
FOR CONTAMINATION STUDY Dec-02-Completed
QAPCO GROUND WATER MONITORING
WELLS
SAMPLING AND ANALYSIS OF SOIL AND WATER
FOR CONTAMINATION STUDY Feb-02-Completed
MECON / KHARAFI SULPHUR RECOVERY EXPANSION LAB AND FIELD TESTING OF SOIL, CONCRETE &
AGGREGATE
2001 – 2002-
Completed
ERM / LAHMYER RAS ABU FONTAS, SAILIYAH,
WAJBAH AND DOHA SOUTH – EIA
SAMPLING AND ANALYSIS OF SOIL AND WATER
FOR CONTAMINATION STUDY Sep-01-Completed
67
Prequalification Document-2015 Rev 28 16.09.2015
HYDER CONSULTING DOHA SOUTH SEWAGE TREATMENT
WORKS – FLOW SAMPLING &
LABORATORY TESTING
SEWAGE SAMPLING & LABORATORY TESTING Jul-01-Completed
TECHNIP ALBA, BAHRAIN ALL TESTING WORKS INCLUDING ONSITE
LABORATORY
1999 – 2001-
Completed
LG ENGINEERING NODCO REFINERY EXPANSION,
MESAIEED
ALL TESTING WORKS INCLUDING ONSITE
LABORATORY
1999 – 2001-
Completed
QAFCO QAFCO – IV CONTAMINATED LAND
INVESTIGATION
SAMPLING AND ANALYSIS OF SOIL AND WATER
FOR CONTAMINATION STUDY May-00-Completed
DAMES & MOORE NGL-4 BASE CASE, NGL-3 AND NGL
TANK FARM – ENVIRONMENTAL
IMPACT ASSESSMENT
SAMPLING AND ANALYSIS OF SOIL AND WATER
FOR CONTAMINATION STUDY Aug-99-Completed
MIDMAC CONTRACTING
CO QAFCO – III EXPANSION, MESAIEED LAB AND FIELD TESTING OF SOIL, CONCRETE &
AGGREGATE
1996 – 1998-
Completed
TOYO ENGINEERING QATAR GAS UPSTREAM PROJECT,
RAS LAFFAN
ALL TESTING WORKS INCLUDING ONSITE
LABORATORY
1995 – 1998-
Completed
TAYLOR WOODROW QATAR FLOUR MILL, DOHA LAB AND FIELD TESTING OF SOIL, CONCRETE &
AGGREGATE
1995 - 1997-
Completed
CHIYODA CORPORATION QATAR GAS LNG PROJECT, RAS LAS
LAFFAN CONCRETE TESTING
1994 - 1996-
Completed
68
Prequalification Document-2015 Rev 28 16.09.2015
APPENDIX D
FIELD AND LABORATORY TESTING
(ISO 17025 ACCREDITED TEST PARAMETERS)
69
Prequalification Document-2015 Rev 28 16.09.2015
No. Field of Testing Standard Title of Standard
1 Concrete BS EN-12390-1-2009 Testing of hardened Concrete Shape, Dimension, and
other requirement for Specimens and molds
2 Concrete BS EN-12390-3-2009 Testing of hardened Concrete Compressive Strength
test of Concrete Specimen
3 Concrete BS EN-12390-7-2009 Testing of hardened Concrete Density test of Concrete
Specimen
4 Concrete BS EN -12390-8-
2009
Testing hardened concrete Depth of Penetration of
Water under Pressure
5 Concrete ASTM C- 1202:2012 Standards Test Method for Electrical Indication of
concrete to Resist Chloride Ion Penetration
6 Concrete BS 1881-Part
122:2011
Testing Hardened Concrete Method for Determination of
water Absorption
7 Aggregates ASTM C 117-13
Materials Finer than 75 microns Sieve in Mineral
Aggregates by Washing. Procedure A—Washing with
Plain Water
70
Prequalification Document-2015 Rev 28 16.09.2015
8 Aggregates ASTM C127 - 15
Standards Test Method for Density, Relative
density,(Specific Gravity) and Absorption of Coarse
Aggregates.
9 Aggregates ASTM C-131-/131M-
14
Standards Test Method for Resistance to Degradation of
small Size Coarse Aggregate by Abrasion and Impact in
the Los Angeles machine
10 Aggregates ASTM C -136-2014 Standards Test Method for Sieve Analysis of Fine and
Coarse Aggregates.
11 Aggregates BS 812-Part 112-90 Aggregates Testing. Method for Determination of
Aggregates Impact Value, Dry Procedure
12 Aggregates ASTM C-142-C142M-
10
Standards Test Method for Clay Lumps and Friable
Particles in Aggregates
71
Prequalification Document-2015 Rev 28 16.09.2015
13 Aggregates BS EN 933 Part
1:2012
Test for Geometrical Properties of Aggregates
,Determination of Particles size distribution.
14 Aggregates BS-EN -933-Part 3-
2012
Test for Geometrical Properties of Aggregates
,Determination of Flakiness Index of Aggregates
15 Aggregates BS-EN -1097-6-2013
Test for Mechanical and Physical Properties of
Aggregates ,Determination of Particle Density and Water
Absorption
16 Soil ASTM D 2419-14 Standards Test Method for Sand Equivalent value of Soil
and Fine Aggregates.
17 Soil BS 1377 Part 2:1990
Soils for civil engineering purposes: Classification Tests
- Determination of Moisture Content - Test 3.2: Oven
Drying method
72
Prequalification Document-2015 Rev 28 16.09.2015
18 Soil BS 1377 Part 2:1990
Soils for civil engineering purposes: Classification Tests.
Test 4.3 - Determination of Liquid Limit of soil by Cone
Penetrometer (Definitive method)
19 Soil BS 1377 Part 2:1990
Soils for civil engineering purposes: Classification Tests.
Test 5 - Determination of Plastic Limit and Plasticity
index
20 Soil BS 1377 Part 2:1990 Soils for civil engineering purposes: Classification Tests.
Test 9.2 Sieve Analysis of soil By Wet sieving Method
21 Soil BS 1377 Part 4:1990
Soils for civil engineering purposes: Compaction related
tests. Test 3.6 - Compaction related Test Method Using
4.5kg rammer
22 Soil BS 1377 Part 4:1990 Soils for civil engineering purposes: Compaction related
73
Prequalification Document-2015 Rev 28 16.09.2015
tests. Test 7 - Determination of California Bearing ratio.
23 Asphalt ASTM D -
2041/D2041M-11
Standards test Method for Theoretical Maximum Specific
Gravity and Density of Bituminous Paving Mixture
Procedure 9.5.1 (Weighing in water)
24 Asphalt ASTM D
2726/D2726M-14
Standards test Method for Bulk Specific Gravity and
Density of Non Absorptive Compacted Bituminous
Mixtures
25 Asphalt BS EN 12697-Part
1:2012
Bituminous mixtures. Test methods for hot mix asphalt .
Soluble binder content. Centrifuge extraction method
26 Asphalt BS EN 12697-Part
2:2002
Bituminous Mixtures Test Method for Hot mix Asphalt,
Determination of Particle size Distribution
74
Prequalification Document-2015 Rev 28 16.09.2015
27 Asphalt BS EN 12697-Part
30:2012
Bituminous Mixtures Test Method for Hot mix Asphalt ,
Specimen preparation by Impact Compactor
28 Asphalt BS EN 12697-Part
34:2012
Bituminous Mixtures Test Method for Hot mix Asphalt,
Marshall Test
29 Asphalt BS EN 12697-Part
36:2003
Bituminous Mixtures Test Method for Hot mix Asphalt ,
Determination Of thickness of a bituminous Pavement
30 Geotechnical ASTM D-5873-14 Determination of Rock Hardness by Rebound Hammer
Method
31 Geotechnical ASTM D 5731-08 Determination of the point load strength index of rock
and application to rock strength classifications
75
Prequalification Document-2015 Rev 28 16.09.2015
32 Geotechnical ASTM D-4644-08 Slake Durability of Shales and Similar Weak Rocks
33 Soil BS 1377 Part 7:1990
Soils for civil engineering purposes: Shear Strength test
(Total Stress) . Test 4 - Determination of shear strength
by direct shear (small shear box apparatus) Procedure
4.5.4 - Shearing: single stage tests
34
Environmental
Chemistry -
Water and
Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Standard Methods for the Examination of Water and
Wastewater. Test 2540-D: Total Suspended Solids
(TSS) Dried @ 103°C - 105°C
35
Environmental
Chemistry -
Water and
Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Standard Methods for the Examination of Water and
Wastewater. Test 2710-C Test on sludge - settled
sludge volume
36
Environmental
Chemistry -
Water and
Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Standard Methods for the Examination of Water and
Wastewater. Test 2710-D Sludge - Sludge volume Index
(SVI)
37 Environmental
Chemistry -
Water and
Standard Methods for
the Examination of
Water and
Standard Methods for the Examination of Water and
Wastewater. Test 4500 SO4-C Sulfate - Gravimetric
76
Prequalification Document-2015 Rev 28 16.09.2015
Wastewater Wastewater 22nd
Edition: 2012
method
38
Environmental
Chemistry -
Water and
Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Standard Methods for the Examination of Water and
Wastewater. Test 4500 SO4-E Sulfate - Turbidimetric
method
39
Environmental
Chemistry -
Water and
Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Standard Methods for the Examination of Water and
Wastewater. Test 5220-D Chemical Oxygen Demand
(COD)
40
Environmental
Chemistry -
Water and
Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Standard Methods for the Examination of Water and
Wastewater. Test 2130-B Turbidity, Nephelometric
method
41
Environmental
Chemistry -
Water and
Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Standard Methods for the Examination of Water and
Wastewater. Test 2340-C Total Hardness, EDTA
Titrimetric Method
42
Environmental
Chemistry -
Water and
Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Standard Methods for the Examination of Water and
Wastewater. Test 2320-B Total Alkalinity, Titration
method
43
Environmental
Chemistry -
Water and
Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Standard Methods for the Examination of Water and
Wastewater. Test 2510-B Conductivity, Laboratory
method
77
Prequalification Document-2015 Rev 28 16.09.2015
44
Environmental
Chemistry -
Water and
Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Standard Methods for the Examination of Water and
Wastewater. Test 4500H+ B pH value, Electrometric
method
45
Environmental
Chemistry -
Water and
Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Standard Methods for the Examination of Water and
Wastewater. Test 4500 F - D Fluoride, SPADNS
method
46
Environmental
Chemistry -
Water and
Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Standard Methods for the Examination of Water and
Wastewater. Test 3500-Ca -B Calcium, EDTA
Titrimetric method
47
Environmental
Chemistry -
Water and
Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Standard Methods for the Examination of Water and
Wastewater. Test 3500-Mg-B Magnesium, Calculation
method
48
Environmental
Chemistry -
Water and
Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Standard Methods for the Examination of Water and
Wastewater. Test 4110 - B Anions by Ion
Chromatography
49
Environmental
Chemistry -
Water and
Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Standard Methods for the Examination of Water and
Wastewater. Test 4110 - D Bromide and Oxyhalides
by Ion Chromatography
50
Environmental
Chemistry -
Water and
Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Standard Methods for the Examination of Water and
Wastewater. Test 4500 Cl- B Chloride, Argentometric
method
78
Prequalification Document-2015 Rev 28 16.09.2015
51
Environmental
Chemistry -
Water and
Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Standard Methods for the Examination of Water and
Wastewater. Test 5310 - BTotal Organic Carbon
(TOC), High Temperature Combustion Method
52 Water/Soil
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
USEPA 6010 C Metals
53
Environmental
Chemistry -
Water and
Wastewater
Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
USEPA 5030 Method 5030 - Purge and Trap for
Aqueous Sample/ 8260 C BTEX in water - METHOD
8260C VOLATILE ORGANIC COMPOUNDS BY GAS
CHROMATOGRAPHY/ MASS SPECTROMETRY
(GC/MS)
54 Soil
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
USEPA 5035 CLOSED-SYSTEM PURGE-AND-TRAP
AND EXTRACTION FOR VOLATILE ORGANICS IN
SOIL AND WASTE SAMPLES/ 8260 C VOLATILE
ORGANIC COMPOUNDS BY GAS
CHROMATOGRAPHY/ MASS SPECTROMETRY
(GC/MS)
55
Environmental
Chemistry -
Water and
Wastewater
Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
USEPA 3510/ 8270 D Pesticides in water (GC-MS) US
EPA METHOD 8270D SEMI- VOLATILE ORGANIC
COMPOUNDS BY GAS CHROMATOGRAPHY/MASS
SPECTROMETRY (GC/MS)
56
Environmental
Chemistry -
Water and
Wastewater
Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
USEPA 3510/ 8270 D PCB in water (GC-MS) - US EPA
METHOD 8270D SEMI- VOLATILE ORGANIC
COMPOUNDS BY GAS CHROMATOGRAPHY/MASS
SPECTROMETRY (GC/MS)
57
Environmental
Chemistry -
Water and
Wastewater
Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
USEPA 5030 Method 5030 - Purge and Trap for
Aqueous Sample / Method 5035 - Closed System Purge
and Trap and Extraction for Volatile Organics in Soil and
Waste Sample/ 8260 C Trihalomethane in water
58
Sediment, Soil,
and Solid Wastes
- Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
US EPA 5035 CLOSED-SYSTEM PURGE-AND-TRAP
AND EXTRACTION FOR
VOLATILE ORGANICS IN SOIL AND WASTE
SAMPLES/ 8260 C (Trihalomethane in soil ) - US EPA
8260 C VOLATILE ORGANIC COMPOUNDS BY GAS
79
Prequalification Document-2015 Rev 28 16.09.2015
CHROMATOGRAPHY/
59 Concrete BS 1881 Part 124
:1988
Testing Concrete: Method for the analysis of hardened
concrete. Clause 10.3 - Determination of Sulphate
content
60 Concrete BS 1881 Part 124
:1988
Testing Concrete: Method for the analysis of hardened
concrete. Clause 10.2 - Determination of chloride
content.
61 Aggregates BS 812 Part
118:1988
Testing Aggregates: Methods for the determination of
sulphate content. Clause 6 Determination of the total
sulphate content by acid extraction
62 Aggregates BS 812 Part 117:
1988
Testing Aggregates: Methods for the determination of
water soluble chloride, Appendix C - Test method for
determination of chloride content of aggregates using a
nitric acid extract, for aggregate containing chloride not
extracted by water
80
Prequalification Document-2015 Rev 28 16.09.2015
63 Aggregates BS 812 Part
117:1988
Methods for the determination of water soluble chloride
salts
64 Aggregates BS 812 Part
118:1988
Testing Aggregates: Methods for the determination of
sulphate content. Clause 5.2 Determination of water
soluble sulphates
65 Aggregates BS 812 Part
118:1988
Testing Aggregates: Methods for the determination of
sulphate content. Clause 6 Determination of Acid
soluble sulphates
66 Soil BS 1377 Part 3:1990
Soils for civil engineering purposes: Chemical and
Electro-chemical tests. Clause 3 - Determination of
Organic Matter content
81
Prequalification Document-2015 Rev 28 16.09.2015
67 Soil BS 1377 Part 3:1990
Soils for civil engineering purposes: Chemical and
Electro-chemical tests. Clause 4 Determination of the
mass loss of ignition
68 Soil BS 1377 Part 3:1990
Soils for civil engineering purposes: Chemical and
Electro-chemical tests. Clause 5 - Determination of the
sulphate content of soil and ground water Sub Clause
5.2 Preparation of soil and its acid extract
69 Soil BS 1377 Part 3:1990
Soils for civil engineering purposes: Chemical and
Electro-chemical tests. Clause 9 - Determination of the
pH value
70 Chemistry-
Cement BS EN 196-2:2013
Method of testing cement. Chemical analysis of cement.
Clause 4.5.16 Chloride in cement ( BS EN 196-2:2005
Test No. 14)
71 Chemistry-
Cement BS EN 196-2:2013
Method of testing cement. Chemical analysis of cement.
Clause 4.4.1 Determination of Loss on ignition ( BS EN
196-2:2005 Test No. 7)
72 Chemistry-
Cement BS EN 196-2-2013
Method of testing cement. Chemical analysis of cement.
Clause 4.4.2 Determination of Sulphate ( BS EN 196-
2:2005 Test No. 8)
82
Prequalification Document-2015 Rev 28 16.09.2015
73 Chemistry-
Cement BS EN 196-2-2013
Method of testing cement. Chemical analysis of cement.
Clause 4.4.3 Determination of residue in insoluble in
hydrochloric acid and sodium carbonate ( BS EN 196-
2:2005 Test No. 9)
75 Chemistry-
Cement BS EN 196-2-2013
Method of testing cement. Chemical analysis of cement.
Clause 4.4.5 -Decomposition ( BS EN 196-2:2005 Test
No. 13.5)
75 Chemistry-
Cement BS EN 196-2-2013
Method of testing cement. Chemical analysis of cement.
Clause 4.5.6 Determination of Pure silica( BS EN 196-
2:2005 Test No. 13.6)
76 Chemistry-
Cement BS EN 196-2-2013
Method of testing cement. Chemical analysis of cement.
Clause 4.5.10 Determination of Iron oxide ( BS EN 196-
2:2005 Test No. 13.10)
77 Chemistry-
Cement BS EN 196-2-2013
Method of testing cement. Chemical analysis of cement.
Clause 4.5.11 Determination of Aluminum Oxide Al2O3 (
BS EN 196-2:2005 Test No.13.11)
78 Chemistry-
Cement BS EN 196-2-2013
Method of testing cement. Chemical analysis of cement.
Clause 4.5.14 Determination of Calcium by EDTA ( BS
EN 196-2:2005 Test No. 13.14)
79 Chemistry-
Cement BS EN 196-2-2013
Method of testing cement. Chemical analysis of cement.
Clause 4.5.15 Determination of magnesium by EDTA
method ( BS EN 196-2:2005 Test No. 13.15)
83
Prequalification Document-2015 Rev 28 16.09.2015
80 Chemistry-
Cement BS EN 196-2-2013
Method of testing cement. Chemical analysis of cement.
Clause 4.15.19 Determination of alkali (reference
method)( BS EN 196-2:2005 Test No. 17)
81
Fly
Ash/Microsilica/G
GBS/Admixture
BS EN 15167-1: 2006
Ground granulated blast furnace slag for use in
concrete, mortar and grout. Definitions, specifications
and conformity criteria Annex A: Method for determining
the moisture content of granulated blast furnace slag
82
Fly
Ash/Microsilica/G
GBS/Admixture
ASTM C 311/C311M-
13
Standard Test Methods for Sampling and Testing Fly
Ash or Natural Pozzolans for Use in Portland-Cement
Concrete Moisture content clauses 10,11,& 13
83
Fly
Ash/Microsilica/G
GBS/Admixture
BS EN 480-8:2012
Admixture for concrete, mortar and grout - Test methods
Part 8; Determination of the conventional dry material
content (Previously BS 5075 Part 1)
84
Fly
Ash/Microsilica/G
GBS/Admixture
BS EN 480-10-2009
Method I
Admixture for concrete, mortar and grout - Test
methods. Part 10: Determination of water soluble
chloride content (Previously BS 5075 Part 1)
85 Gypsum ASTM C471M-14 Admixtures for concrete, mortar and grout — Test
methods Gypsum
84
Prequalification Document-2015 Rev 28 16.09.2015
86 Soil BS 1377 Part 3:1990 Soils for civil engineering purposes: Chemical and
Electro-chemical tests. Acid soluble suphate
87 Microbiology
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Standard Methods for the Examination of Water and
Wastewater. Test 9223 B Total coliform
88 Microbiology
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Standard Methods for the Examination of Water and
Wastewater. Test 9222 D Fecal Coliform
89 Microbiology
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Standard Methods for the Examination of Water and
Wastewater. Test 9215 B Heterotrophic plate count
(pour plate method)
85
Prequalification Document-2015 Rev 28 16.09.2015
Edition: 2012
90 Microbiology BSEN ISO
11731.2:2008
Water quality. Detection and enumeration of Legionella.
Direct membrane filtration method for waters with low
bacterial counts
91 Microbiology
WHO-Laboratory
Manual of
Parasitological and
Bacteriological
Techniques
Nematode Egg/ Helminth Ova
92 Gypsum ASTM C471M-14 Standard Test Method for Chemical Analysis of Gypsum
and Gypsum Products (Metric) - Clause 7 Free Water
93 Gypsum ASTM C471M-14
Standard Test Method for Chemical Analysis of Gypsum
and Gypsum Products (Metric) - Clause 8 Combined
water
94 Gypsum ASTM C471M-14
Standard Test Method for Chemical Analysis of Gypsum
and Gypsum Products (Metric) - Clause 10 Silicon
Dioxide and insoluble Matter
86
Prequalification Document-2015 Rev 28 16.09.2015
95 Gypsum ASTM C471M-14
Standard Test Method for Chemical Analysis of Gypsum
and Gypsum Products (Metric) - Clause 11 Iron and
Aluminum Oxide
96 Gypsum ASTM C471M-14
Standard Test Method for Chemical Analysis of Gypsum
and Gypsum Products (Metric) - Clause 12 Calcium
Oxide
97 Gypsum ASTM C471M-14
Standard Test Method for Chemical Analysis of Gypsum
and Gypsum Products (Metric) - Clause 14 Sulfur
trioxide
98 Gypsum ASTM C471M-14 Standard Test Method for Chemical Analysis of Gypsum
and Gypsum Products (Metric) - clause 15 Chloride
87
Prequalification Document-2015 Rev 28 16.09.2015
99 Aggregates AASHTO T27-2014 Sieve Analysis of Fines and Coarse Aggregates
100 Aggregates AASHTO T11-05-
2013
Material Finer than 0.075mm(No.200) Sieve in Mineral
Aggregates - Procedure A: Washing with plain paper
101 Aggregates AASHTO T- 96-2010 Resistance to Degradation of small size aggregates. By
Abrasion and Impact in the Los Angeles machine
102 Aggregates AASHTO T- 104-
2011
Soundness of Aggregate by Use of Sodium Sulphate or
Magnesium sulphate
103 Soil AASHTO T 267-86
(2013)
Determination of Organic content in soils by loss of
ignition
88
Prequalification Document-2015 Rev 28 16.09.2015
104 Aggregates
AASHTO T- 304-
2011 (NOT
DEMONSTRATED-
DELETED FROM
SCOPE UNDER
LABS REQUEST)
Uncompacted Void Content of Fine Aggregates
105 Soil AASHTO T 290-95
(2012) Water-soluble sulfate content in soil
106 Soil AASHTO T 291-94
(2013) Water-soluble chloride ion content in soil
107 Soil AASHTO T-89-2013 Standard Method of Test for Determining the Liquid Limit
of Soils
108 Soil AASHTO T-90-2014 Standard Method of Test for Determining the Plastic
Limit and Plasticity Index of Soils
109 Soil AASHTO T- 180-
2010
Moisture Density Relation of Soil using 4.5kg Rammer
and 457mm Drop.
89
Prequalification Document-2015 Rev 28 16.09.2015
110 Asphalt ASTM D6926-2010 Preparation of Bituminous Specimens using Marshall
apparatus
111 Asphalt ASTM D1188-07
Edition 1
Bulk Specific Gravity and density of Compacted
Bituminous Mixtures using Coated samples.
112 Steel
BS
4449:2005+A2:09/BS
EN ISO 6892-
1:09/BSEN 15630-1-
10
Tensile, Yield & Elongation of Reinforcement steel
Bar/Bend @90° Rebend @20°
113 Steel ASTM E 415-14 Standard Test Method fo Analysis of Carbon and Low -
Alloy Steel by spark Atomic Emission Spectrometry
114
Environmental
Chemistry -
Water and
Wastewater
DIN-38405-07 Cyanides in lightly polluted water (Ion Chromatography
method)
115 Environmental
Chemistry -
Water and
ASTM D5176:2008 Total Chemically Bound Nitrogen in water by Pyrolisis
and Chemiluminescence Detection
90
Prequalification Document-2015 Rev 28 16.09.2015
Wastewater
116 Asphalt ASTM D6927:2006 Standards Test For Marshall Stability and Flow of
Bituminous Materials.
117 Concrete BS 1881-122:2011 Testing Concrete: Method for the determination of water
absorption
118 Concrete BS 1881-208:1996 Testing Concrete: Recommendations for the detn of the
initial surface absorption of concrete
119 Concrete BS EN 12350-1:2009 Testing fresh concrete. Sampling
120 Concrete BS EN 12350-2:2009 Testing fresh concrete. Slump-test
91
Prequalification Document-2015 Rev 28 16.09.2015
121 Concrete BS EN 12504-1:2009 Testing concrete in structures. Cored specimens.
Taking, examining and testing in compression
122 Concrete BS EN 12390-2:2009 Testing hardened concrete. Making and curing
specimens for strength tests
123 Concrete ASTM
C31/C31M:2012 Making and Curing Test Specimens in the Field
124 Concrete ASTM C39/C39M-
12A
Compressive Strength of Cylindrical Concrete
Specimens
125 Concrete ASTM C42/C42M-
13
Obtaining and Testing Drilled Cores and Sawed Beams
of Concrete
126 Concrete ASTM C143/C143M-
12 Slump of Hydraulic Cement Concrete
127 Concrete ASTM C231/C231M-
14
Air Content of Freshly Mixed Concrete by the Pressure
Method
92
Prequalification Document-2015 Rev 28 16.09.2015
128 Concrete ASTM C617/C
617M-12 Capping Cylindrical Concrete Specimens
129 Concrete ASTM
C1064/C1064M-12
Temperature of Freshly Mixed Hydraulic Cement
Concrete
130 Aggregates ASTM C88-13 Soundness of Aggregates by the use Sodium Sulfate or
Magnesium Sulfate
131 Aggregates ASTM C128-12 Density, Relative Density, and Absorption of Fine
Aggregate
132 Aggregates ASTM C535-12
Resistance to Degradation of Large Sized Coarse
Aggregate by Abrasion and Impact in Los Angeles
Machine
93
Prequalification Document-2015 Rev 28 16.09.2015
133 Aggregates ASTM D4791-10 Flat Particles, elongated particles, or flat and elongated
particles in coarse aggregate
134 Aggregates BS 812-103.1:1985 Testing aggregates. Method for determination of particle
size distribution. Sieve tests Clause 7.3
135 Aggregates BS 812-103.1:1985 Testing aggregates. Method for determination of particle
size distribution. Sieve tests Test 9.2
136 Aggregates BS EN 933-1:2012
Tests for geometrical properties of aggregates.
Determination of particle size distribution. Sieving
method
137 Aggregates BS 812-105.1:1989 Testing Aggregates: Methods for the determination of
Particle Shape-Flakiness Index
138 Aggregates BS 812-105.2:1990 Testing Aggregates: Methods for the determination of
Particle Shape-Elongation Index of coarse aggregate
94
Prequalification Document-2015 Rev 28 16.09.2015
139 Aggregates BS 812-2:1995 Testing Aggregates: Methods of determination of density
Test 5.3 - Method for aggregates all larger than 10 mm
140 Aggregates BS 812-2:1995
Testing Aggregates: Methods of determination of density
Test 5.4 - Method for aggregates between 40 mm and 5
mm
141 Aggregates BS 812-2:1995
Testing Aggregates: Methods of determination of density
Test 5.5 -Method for aggregates 10 mm nominal size
and smaller
142 Aggregates BS 812-102:1989 Testing Aggregates: Methods for sampling
143 Aggregates BS 812-109:1990 Testing Aggregates: Methods for the determination of
moisture content Clause 6- Definitive, oven-drying
95
Prequalification Document-2015 Rev 28 16.09.2015
method
144 Aggregates BS 812-110:1990 Testing Aggregates: Methods for the determination of
aggregate crushing value
145 Aggregates BS 812-111:1990 Testing Aggregates: Methods for the determination of
ten percent fines value (TFV)
146 Aggregates BS EN 933-7_1998
Tests for geometrical properties of aggregates.
Determination of shell content. Percentage of shells in
coarse aggregates
147 Cement BS EN 196-1_2005 Methods of testing cement. Determination of strength
148 Cement AASHTO TP64 – 03
Standard Method of Test for Predicting Chloride
Penetration of Hydraulic Cement Concrete by the Rapid
Migration Procedure
96
Prequalification Document-2015 Rev 28 16.09.2015
149 Cement NT Build 492
CONCRETE, MORTAR AND CEMENT-BASED REPAIR
MATERIALS:CHLORIDE MIGRATION COEFFICIENT
FROM NON-STEADY-STATE MIGRATION
EXPERIMENTS
150 Cement BS EN 196-
3:2005+A1:2008
Methods of testing cement. Determination of setting
times and soundness
151 Cement BS EN 196-6_2010 Methods of testing cement. Determination of fineness
152 Cement BS EN 196-7_2007 Methods of testing cement. Methods of taking and
preparing samples of cement
153 Cement BS 6073-1:1981 Precast concrete masonry units. Specification for
precast concrete masonry units
154 Cement BS EN 771-3:2011 Specification for masonry units. Aggregate concrete
masonry units (dense and lightweight aggregates)
97
Prequalification Document-2015 Rev 28 16.09.2015
155 Cement BS EN 1338:2003
Concrete paving blocks. Requirements and test
methods. Annex E - Determination of total water
absorption
156 Cement BS 6717:2001
Precast, unreinforced concrete paving blocks.
Requirements and test methods Annex B -
Measurement of the dimensions of a single paving block
157 Cement ASTM C187:2011
Edited 1
Amount of Water Required for Normal Consistency of
Hydraulic Cement Paste
158 Cement ASTM C191:2013 Time Setting of Hydraulic Cement by Vicat Needle
159 Cement ASTM
C172/C172M:2014 Sampling Freshly Mixed Concrete
160 Cement ASTM Density, Yield, and Air Content (Gravimetric) of Concrete
98
Prequalification Document-2015 Rev 28 16.09.2015
C138/C138M:2014
161 Cement ASTM C183:2013 Sampling and the amount of Testing of Hydraulic
Cement
162 Cement ASTM C349:2008 Compressive Strength of Hydraulic Cement Mortars
(Using Portions of Prisms Broken in Flexure)
163 Cement ASTM
C989/C989M:2014 Slag Cement for use in Concrete and Mortars
164 Cement ASTM C1240:2014 Silica Fume Used in Cementitious Mixtures
165 Asphalt ASTM C136:2014 Sieve Analysis of Fine and Coarse Aggregates
99
Prequalification Document-2015 Rev 28 16.09.2015
166 Asphalt ASTM
D2172/D2172M-11
Quantitative Extraction of Bitumen from Bituminous
Paving Mixtures Clause 11.6.1 Ashing Method
167 Asphalt ASTM
D3549/D3549M-11
Thickness or Height of Compacted Bituminous Paving
Mixture Specimens
168 Asphalt BS 598-104:2005
Sampling and examination of bituminous mixtures for
road and other areas: Methods of test for determination
of density and compaction Test 4 - Measurement of
Density of Cores
169 Asphalt BS 812-103.1:1985 Testing aggregates. Method for determination of particle
size distribution. Sieve tests
170 Asphalt BS EN 12697-
39:2012
Bituminous mixtures. Test methods for hot mix asphalt.
Binder content by ignition
171 Asphalt BS EN 12697-5:2009 Bituminous mixtures. Test methods for hot mix asphalt.
Determination of the maximum density
100
Prequalification Document-2015 Rev 28 16.09.2015
172 Asphalt BS EN 12697-6:2012 Bituminous mixtures. Test methods for hot mix asphalt.
Determination of bulk density of bituminous specimens
173 Asphalt BS EN 12697-8:2003
Bituminous mixtures. Test methods for hot mix asphalt.
Determination of void characteristics of bituminous
specimens
174 Asphalt BS EN 12697-9:2002 Bituminous mixtures. Test methods for hot mix asphalt.
Determination of the reference density
175 Asphalt BS EN 12697-
13_2000
Bituminous mixtures. Test methods for hot mix asphalt.
Temperature measurement
176 Asphalt BS EN 12697-
26:2012
Bituminous mixtures. Test methods for hot mix asphalt.
Stiffness
177 Asphalt BS EN 12697-
27:2001
Bituminous mixtures. Test methods for hot mix asphalt.
Sampling
101
Prequalification Document-2015 Rev 28 16.09.2015
178 Asphalt BS EN 12697-
28:2001
Bituminous mixtures. Test methods for hot mix asphalt.
Preparation of samples for determining binder content,
water content and grading
179 Asphalt BS EN 12697-
29:2002
Bituminous mixtures. Test methods for hot mix asphalt.
Determination of the dimensions of a bituminous
specimen
180 Asphalt BS EN 12697-
35_2004
Bituminous mixtures. Test methods for hot mix asphalt.
Laboratory mixing
181 Soil ASTM D1557-12 Laboratory Compaction Characteristics of Soil Using
Modified Effort
182 Soil ASTM D4318-2010
Ed 1 Liquid Limit, Plastic limit, and Plasticity Index of Soils
183 Soil BS 1377 Part 2:1990 Soils for civil engineering purposes: Classification Test
102
Prequalification Document-2015 Rev 28 16.09.2015
Test 9.3 - Dry sieving method
184 Soil BS 1377 Part 2:1990 Soils for civil engineering purposes: Classification Test
Test 9.5 - Sedimentation by the hydrometer method
185 Soil BS 1377 Part 4:1990
Soils for civil engineering purposes: Compaction related
tests Test 3.5 - Method using 4.5 kg rammer for soils
with particles up to medium-gravel size
186 Soil BS 1377-9:1990
Soils for civil engineering purposes: In Situ Tests Test
2.1 -Sand replacement method suitable for fine- and
medium-grained soils (small pouring cylinder method
187 Soil BS 1377-9:1990
Soils for civil engineering purposes: In Situ Tests Test
2.5 - Nuclear methods suitable for fine-, medium- and
coarse-grained soils
188 Soil CML Test 10-97 Standard Method of Test for Determination of California
Bearing Ratio
103
Prequalification Document-2015 Rev 28 16.09.2015
189 Soil BS EN 933-8:2012 Tests for geometrical properties of aggregates.
Assessment of fines. Sand equivalent test
190 Chemistry-
Aggregates ASTM C40/C40M-11 Organic Impurities in Fine Aggregates for Concrete
191 Chemistry-
Aggregates
ASTM
C123/C123M-12 Lightweight Particles in Aggregate
192 Chemistry-
Aggregates ASTM C289-07
Potential Alkali Silica reactivity of Aggregates (Chemical
Method)
193 Chemistry-
Aggregates ASTM C430-08 Fineness of Hydraulic Cement by the 45 micron Sieve
194 Chemistry- BS812-118:1988 Testing Aggregates: Methods for the determination of
104
Prequalification Document-2015 Rev 28 16.09.2015
Aggregates sulphate content Test 6-Determination of the total
sulphate content by acid extraction
195 Chemistry-
Aggregates BS812-117:1988
Testing Aggregates:Methods for the determination of
water soluble chloride Appendix C - Test method for
determination of chloride content of aggregates using a
nitric acid extract, for aggregate containing chloride not
extracted by water
196 Chemistry-
Aggregates
BS EN 1744-
1_2001_A1:2012
Tests for chemical properties of aggregates. Chemical
analysis. Test 12 - Determination of acid soluble sulfates
197 Chemistry-
Aggregates BS EN 1744-5:2006
Tests for chemical properties of aggregates.
Determination of acid soluble chloride salts
198 Chemistry-
Aggregates
BS EN ISO 11127-
7:2011
Preparation of steel substrates before application of
paints and related products. Test methods for non-
metallic blast-cleaning abrasives. Determination of
water-soluble chlorides
199 Chemistry-
Concrete ASTM
C1152/C1152M-04 Acid Soluble Chloride in Mortar and Concrete
105
Prequalification Document-2015 Rev 28 16.09.2015
Reapproved 2012
200 Chemistry-
Concrete
ASTM
C1218/C1218M-99
Reapproved 2008
Water Soluble Chloride in Mortar and Concrete
201 Chemistry-
Concrete AASHTO T260-97
Sampling and Testing for Chloride Ion in Concrete and
Concrete Raw Materials Test 5.4.1 - Method 1:
Potentiometric Titration
202 Chemistry-
Cement BS EN 196-21:1992
Methods of testing cement. Determination of the
chloride, carbon dioxide and alkali content of cement
Test 4 - Determination of the chloride content
203 Chemistry-
Cement BS EN 196-21:1992
Methods of testing cement. Determination of the
chloride, carbon dioxide and alkali content of cement
Test 8 - Determination of the alkali content (Alternative
Method)
204 Chemistry-
Cement ASTM C114-13
Chemical Analysis of Hydraulic Cements Test 8 - Silicon
Dioxide (Reference Test Method)
106
Prequalification Document-2015 Rev 28 16.09.2015
205 Chemistry-
Limestone ASTM C25-11 E1
Chemical Analysis of Limestone, Quicklime, and
Hydrated Lime Test 9 - Insoluble Matter Including Silicon
Dioxide (Optional Perchloric Acid Method)
206 Chemistry-
Limestone ASTM C25-11 E1
Chemical Analysis of Limestone, Quicklime, and
Hydrated Lime Test 10 - Silicon Dioxide
207 Chemistry-
Limestone ASTM C25-11 E1
Chemical Analysis of Limestone, Quicklime, and
Hydrated Lime Test 19 - Loss on Ignition
208 Chemistry-
Limestone ASTM C25-11 E1
Chemical Analysis of Limestone, Quicklime, and
Hydrated Lime Test 24 - Total Sulfur by Sodium
Carbonate Fusion
209 Chemistry-
Limestone ASTM C25-11 E1
Chemical Analysis of Limestone, Quicklime, and
Hydrated Lime Test 31 - Calcium and Magnesium Oxide
(Alternative EDTA Titration Method)
210 Chemistry-
Limestone
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
6010C - 1 Revision 3 February 2007 METHOD 6010C
INDUCTIVELY COUPLED PLASMA-ATOMIC
EMISSION SPECTROMETRY (Aluminum Oxide, Ferric
Oxide, Titanium Dioxide, Potassium Oxide, Sodium
107
Prequalification Document-2015 Rev 28 16.09.2015
Oxide, and Phosphorus Only
211 Geotechnical ASTM D1557-12 Laboratory Compaction Characteristics of Soil Using
Modified Effort (56,000 ft-lbf/ft3 (2,700 kN-m/m3))
212 Geotechnical ASTM D4318-10 Ed
1 Liquid Limit, Plastic limit, and Plasticity Index of Soils
213 Geotechnical ASTM D4543-08
Preparing rock core as cylindrical test specimens and
verifying conformance to dimensional and shape
tolerances
214 Geotechnical ASTM D7012-14 Compressive Strength and elastic moduli of intact rock
core specimens under varying stress and temp.
215 Geotechnical ASTM D7625-10 Laboratory determination of abrasiveness of rock using
the cerchar method
216 Geotechnical ASTM Abrasive Resistance of Dimension Stone Subjected to
108
Prequalification Document-2015 Rev 28 16.09.2015
C1353/C1353M-09
Ed 1
Foot Traffic using a Rotary Platform, Double Head
Abraser
217 Geotechnical ASTM D3967-08 Splitting Tensile Strength of Intact Rock Core Specimens
218 Geotechnical ASTM D7012-14
Compressive Strength and elastic moduli of intact rock
core specimens under varying stress and temp. Test A -
Triaxial Compressive Strength of Undrained Rock Core
Specimens Without Pore Pressure Measurements
219 Geotechnical ASTM D7012-14
Compressive Strength and elastic moduli of intact rock
core specimens under varying stress and temp. Test D -
Method D: Elastic Moduli of Intact Rock Core Specimens
in Uniaxial Compression.
220 Geotechnical ASTM G57-06
Reapproved 2012
Field measurement of Soil Resistivity Using the Wenner
Four Electrode Method
221 Geotechnical BS 1377 Part 2:1990
Soils for civil engineering purposes: Classification Test
Clause 4.3 - Cone penetrometer method (definitive
method)
109
Prequalification Document-2015 Rev 28 16.09.2015
222 Geotechnical BS 1377 Part 2:1990
Soils for civil engineering purposes: Classification Test
Clause 5 -Determination of the plastic limit and plasticity
index
223 Geotechnical BS 1377 Part 2:1990 Soils for civil engineering purposes: Classification Test
Clause 9.2 -Wet sieving method
224 Geotechnical BS 1377 Part 4:1990
Soils for civil engineering purposes: Compaction related
tests Test 3.5 - Method using 4.5 kg rammer for soils
with particles up to medium-gravel size
225 Geotechnical BS 1377 Part 4:1990
Soils for civil engineering purposes: Compaction related
tests Test 3.6 - Method using 4.5 kg rammer for soils
with some coarse gravel-size particles
226 Geotechnical BS 1377 Part 4:1990
Soils for civil engineering purposes: Compaction related
tests Test 7 - Determination of the California Bearing
Ratio (CBR)
110
Prequalification Document-2015 Rev 28 16.09.2015
227 Geotechnical BS 1377-5:1990
Soils for civil engineering purposes: Compressibility,
permeability, and durability tests Test 3 - Determination
of the one-dimensional consolidation properties
228 Geotechnical BS 1377 Part 7:1990
Soils for civil engineering purposes: Shear Strength test
(Total Stress) Test 8 - Determination of the undrained
shear strength in triaxial compression without
measurement of pore pressure (definitive method)
229 Geotechnical BS 1377-9:1990
Soils for civil engineering purposes: In Situ Tests Clause
3.3 -Determination of the penetration resistance using
the split-barrel sampler (the standard penetration test
SPT)
230 Geotechnical BS 1377-9:1990
Soils for civil engineering purposes: In Situ Tests Clause
4.1 - Determination of the vertical deformation and
strength characteristics of soil by the plate loading test
231 Geotechnical BS 1377-9:1990
Soils for civil engineering purposes: In Situ Tests Clause
4.3 - Determination of the in-situ California Bearing Ratio
(CBR)
111
Prequalification Document-2015 Rev 28 16.09.2015
232 Geotechnical BS 5930-A2:2010 Code of Practice for Site Investigations Clause 6
Procedure
233 Geotechnical BS 5930-A2:2010 Code of Practice for Site Investigations Clause 22 -
Sampling the ground
234 Geotechnical BS 5930-A2:2010 Code of Practice for Site Investigations Clause 23 -
Groundwater
235 Geotechnical BS 5930-A2:2010 Code of Practice for Site Investigations Clause 25 -
Tests in boreholes
236 Geotechnical BS 5930-A2:2010 Code of Practice for Site Investigations Clause 27 -
Pumping Test
237 Geotechnical BS 5930-A2:2010 Code of Practice for Site Investigations Clause 47 -
Reports
112
Prequalification Document-2015 Rev 28 16.09.2015
238 Geotechnical ISRM 1978 (2007
Edition)
Determination of Hardness and Abrasiveness of Rock
ISRM 2007 Edition Page 91,
239 Geotechnical ISRM 1978 (2007
Edition)
Laboratory testing of Rock Swelling ISRM Clause 3 Part
2 (1999-2006) p 295
240 Geotechnical -
Chemistry BS 1377-3:1990
Soils for civil engineering purposes: Chemical and
Electro-chemical tests Clause 6.3 - Determination of the
carbonate content ( 6.3 Rapid titration method)
241 Geotechnical -
Chemistry BS 1377-3:1990
Soils for civil engineering purposes: Chemical and
Electro-chemical tests Determination of the chloride
content Clause 7.2 (7.2 Determination of water-soluble
chloride content)
242 Geotechnical -
Chemistry BS 1377-3:1990
Soils for civil engineering purposes: Chemical and
Electro-chemical tests Determination of the chloride
content Clause 7.3 (7.3 Determination of acid-soluble
chloride content)
113
Prequalification Document-2015 Rev 28 16.09.2015
243 Geotechnical -
Chemistry BS 1377-3:1990
Soils for civil engineering purposes: Chemical and
Electro-chemical tests Determination of the pH value
Clause 9.5 (9.5 Electrometric method of pH
determination)
244 Chemistry-
Asphalt
ASTM
D2172/D2172M-11
Quantitative Extraction of Bitumen from Bituminous
Paving Mixtures Clause 11.6.1 - 11.6.1 Ashing Method
245 Chemistry-Soil ASTM C1580-09 Ed 1 Water Soluble Sulfate in Soil
246 Chemistry-Soil ASTM G200-
09(2014)
Measurement of Oxidation reduction potential (ORP) of
Soil
247 Chemistry-Soil BS 1377-3:1990
Soils for civil engineering purposes: Chemical and
Electro-chemical tests Clause 5.3 - 5.3 Preparation of
soil and its water extract
248 Chemistry-Soil APHA/AWWA 22nd
Edition
Standard Method s for the examination of water and
Wastewater 4500 Norg B - Nitrogen (Organic) Macro-
Kjeldahl Method
249 Chemistry-Soil APHA/AWWA 22nd
Edition Standard Method s for the examination of water and
Wasterwater 4500 N Org 4500 NH3 B- Preliminary
114
Prequalification Document-2015 Rev 28 16.09.2015
Digestion Step
250 Chemistry-Soil APHA/AWWA 22nd
Edition
Standard Method s for the examination of water and
Wastewater 4500 NH3 B&C - Nitrogen (Ammonia)
Preliminary Digestion Step and Titrimetric Method
251 Chemistry-Soil
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 9030B ACID-SOLUBLE AND ACID-
INSOLUBLE SULFIDES: DISTILLATION
252 Chemistry-Soil
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 9034 TITRIMETRIC PROCEDURE FOR
ACID-SOLUBLE AND ACID INSOLUBLE SULFIDES
253 Chemistry-Soil
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 9045D SOIL AND WASTE pH
254
Chemistry-Fly
Ash/Microsilica/G
GBS/Admixture
ASTM C114-13 Chemical Analysis of Hydraulic Cements Test 8 - Silicon
Dioxide (Reference Test Method)
255
Chemistry-Fly
Ash/Microsilica/G
GBS/Admixture
ASTM C114-13 Chemical Analysis of Hydraulic Cements Test 9 -
Ammonium Hydroxide Group (Reference Test Method)
256
Chemistry-Fly
Ash/Microsilica/G
GBS/Admixture
ASTM C114-13 Chemical Analysis of Hydraulic Cements Test 13 - Zinc
Oxide (Reference Test Method)7
115
Prequalification Document-2015 Rev 28 16.09.2015
257
Chemistry-Fly
Ash/Microsilica/G
GBS/Admixture
ASTM C114-13 Chemical Analysis of Hydraulic Cements Test 15 -
Calcium Oxide (Reference Test Method)
258
Chemistry-Fly
Ash/Microsilica/G
GBS/Admixture
ASTM C114-13 Chemical Analysis of Hydraulic Cements Test 16 -
Magnesium Oxide (Reference Test Method)
259
Chemistry-Fly
Ash/Microsilica/G
GBS/Admixture
ASTM C114-13 Chemical Analysis of Hydraulic Cements Test 17 - Sulfur
260
Chemistry-Fly
Ash/Microsilica/G
GBS/Admixture
ASTM C114-13
Chemical Analysis of Hydraulic Cements Test 22 -
Chloroform-Soluble Organic Substances (Reference
Test Method)
261
Chemistry-Fly
Ash/Microsilica/G
GBS/Admixture
ASTM C618-12A Standard Specification for Coal Fly Ash and Raw or
Calcined Natural Pozzolan for Use in Concrete1
262
Chemistry-Fly
Ash/Microsilica/G
GBS/Admixture
BS EN 450-1:2012 Fly ash for concrete. Definition, specifications and
conformity criteria
263 Chemistry-Fly
Ash/Microsilica/GASTM C1240-14 Silica Fume Used in Cementitious Mixtures
116
Prequalification Document-2015 Rev 28 16.09.2015
GBS/Admixture
264
Chemistry-Fly
Ash/Microsilica/G
GBS/Admixture
ASTM C311/C311M-
13
Sampling and Testing Fly Ash or Natural Pozzolans for
use in Portland Cement Concrete
265 Concrete ASTM C232/C232M-
14 Standard test method for Bleeding of Concrete
266
Chemistry-Fly
Ash/Microsilica/G
GBS/Admixture
ASTM E70-07 pH of Aqueous solutions with the glass electrodes
267
Chemistry-Fly
Ash/Microsilica/G
GBS/Admixture
ASTM C494/C494M-
13 Chemical Admixtures for Concrete
268
Environmental
Chemistry -Water
and Wastewater
ASTM D512-12 Chloride Ion in Water
269
Environmental
Chemistry -Water
and Wastewater
ASTM D516-11 Sulfate Ion in Water
270 Environmental
Chemistry -Water BS 1377-3:1990 Soils for civil engineering purposes: Chemical and
Electro-chemical tests Test 5 Determination of the
117
Prequalification Document-2015 Rev 28 16.09.2015
and Wastewater sulphate content of soil and ground water
271
Environmental
Chemistry -Water
and Wastewater
BS 1377-3:1990
Soils for civil engineering purposes: Chemical and
Electro-chemical tests Test 8 Determination of total
dissolved solids
272
Environmental
Chemistry -Water
and Wastewater
BS 6068-2.5:1995 Water Quality: Physical, chemical, and Biochemical
methods - Determination of pH
273
Environmental
Chemistry -Water
and Wastewater
BS EN ISO 9963-
1:1996, BS 6068-
2.51:1996
Water quality. Determination of alkalinity. Determination
of total and composite alkalinity
274
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
2540B - Total Solids Dried at 103 - 105°C
275
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
2540C - Total Dissolved Solids Dried at 180°C
118
Prequalification Document-2015 Rev 28 16.09.2015
276
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
2540F - Settleable Solids
277
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
2540G - Total, Fixed, and Volatile Solids in Solid and
Semi-solid samples.
278
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
4500-Br - Bromide B - Phenol Red Colorimetric Method
279
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
4500-CN - Cyanide C - Total Cyanide After Distillation
280 Environmental Standard Methods for 4500-O Oxygen (Dissolved) C - Azide Modification
119
Prequalification Document-2015 Rev 28 16.09.2015
Chemistry -Water
and Wastewater
the Examination of
Water and
Wastewater 22nd
Edition: 2012
281
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
4500-NH3 (Nitrogen - Ammonia) B&C - Preliminary
Distillation Step and Titrimetric Method
282
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
4500-NO3 - (Nitrogen - Nitrate) D - Nitrate Electrode
Method
283
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
4500-NO2 - (Nitrogen - Nitrite) B - Colorimetric Method
284
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
4500-N Org - (N/N Org)/ NH3 C - Semi-Micro Kjeldahl
Method/Titrimetric Method
285
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
4500-Cl (Chlorine - Residual) G - DPD Colorimetric
Method
120
Prequalification Document-2015 Rev 28 16.09.2015
286
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
4500-CN - Cyanide E - Colorimetric Method
287
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
4500-CN - Cyanide F - Cyanide Selective Electrode
Method
288
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
4500- P Phosphorus C - Vanadomolybdophosphoric
Acid Colorimetric Method
289
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
4500-P Phosphorus D - Stannous Chloride Method
290
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
4500-S2- Sulfide- F - Iodometric Method
291 Environmental
Chemistry -Water
Standard Methods for
the Examination of
Water and
4500-SiO2 Silica C - Molybdosilicate Method
121
Prequalification Document-2015 Rev 28 16.09.2015
and Wastewater Wastewater 22nd
Edition: 2012
292
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
4500-NO3 - (Nitrogen - Nitrate) E - Cadmium Reduction
Method
293
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
4500-NH3 (Nitrogen - Ammonia) F - Phenate Method
294
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
5210 Biochemical Oxygen Deman (BOD) B - 5-Day BOD
Test
295
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
5520 Oil and Grease B - Liquid-liquid Partition
Gravimetric Method
296
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
5520 Oil and Grease D - Soxhlet Extraction Method
122
Prequalification Document-2015 Rev 28 16.09.2015
297
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
5530 Phenol B & C - Clean up/Chloroform Extraction
Method
298
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Method 1664, Revision A: N-Hexane Extractable
Material (HEM; Oil and Grease) and Silica Gel Treated
N-Hexane Extractable Material (SGTHEM; Non-polar
Material) by Extraction and Gravimetry
299
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
2310 Alkalinity B - Titration Method
300
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
4500-Cl (Chlorine - Residual) B - Iodometric Method I
301 Environmental Standard Methods for 2580 Oxidation Reduction Potential (ORP) - Oxidation-
123
Prequalification Document-2015 Rev 28 16.09.2015
Chemistry -Water
and Wastewater
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Reduction Potential Measurement in Clean Water
302
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
2550 Temperature B - Laboratory and Field Methods
303
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
4500-Norg B + NH3 F (LR) - Macro Kjeldahl Method +
Phenate Method
304
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
4500-CO2 (Carbon Dioxide) C - Titrimetric Method for
Free Carbon Dioxide
305
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
2120 Color C - Spectrophotometric-Single Wavelength
Method (Proposed)
306
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
5540 Surfactants C - Anionic Surfactants as MBAS
124
Prequalification Document-2015 Rev 28 16.09.2015
307
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
4500-Cl- (Chloride) D - Potentiometric Method
308
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
4500-S2- Sulfide- D - Methylene Blue Method
309
Environmental
Chemistry -Water
and Wastewater
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
10200 Plankton H - Phytoplankton Counting Techniques
310
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Acidity Method 305.1 - Titrimetric
311
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Chlorine,Method 330.5 Total Residual -
Spectrophotometric DPD
312 Environmental
Chemistry -Water
US EPA - Methods
For Chemical
Analysis of Water and
Residue, Method 160.2Non Filterable - Gravimetric 103-
105 C
125
Prequalification Document-2015 Rev 28 16.09.2015
and Wastewater Wastes
313
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Residue, Method 160.4 Volatile Gravimetric Ignition at
150 C
314
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Phenolic, Total Recoverable Method 420.1 -
Spectrophotometric Manual 4-AAP with distillation
315
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Temperature , Method 170.1 - Thermometric
316
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Nitrogen Ammonia Method 350.2 - Titrimetric Distillation
Procedure
317
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Nitrogen Total, Kjeldahl Method 351.3 -
Colorimetric,Titrimetric, or Potentionmetric
126
Prequalification Document-2015 Rev 28 16.09.2015
318
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Calcium Method 215.2 - EDTA Titrimetric method
319
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Fluoride Method 340.1 - SPADNS method
320
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Oxygen -Dissolved Method 360.2 - Modified Winkler (Full
Bottle Technique)
321
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Alkalinity Method 310.1 - Titrimetric (pH - 4.5)
322
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Turbidity Method 180.1 - Nephelometric
323 Environmental
Chemistry -Water
US EPA - Methods
For Chemical
Analysis of Water and
Sulfate Method 375.4 - Turbidimetric
127
Prequalification Document-2015 Rev 28 16.09.2015
and Wastewater Wastes
324
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Residue Method 160.1 - Filterable Gravimetric Dried at
180C
325
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Color Method 110.2 - Colorimetric Platinum Cobalt
326
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Color Method 110.3 - Spectrophotometric
327
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Nitrite Method 354.1 - Spectrophotometric
328
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Methylene Blue Active Substances (MBAS) Method
425.1 - Colorimetric
128
Prequalification Document-2015 Rev 28 16.09.2015
329
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Method 300.1 - Colorimetric (Anions, Bromate, Chlorate,
Chlorite)
330
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Conductance Method 120.1 - Specific Conductance
331
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
pH Method 150.1 - Electrometric
332
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Residue, Total Method 160.3 - Gravimetric, Dried at 103-
105C
333
Environmental
Chemistry -Water
and Wastewater
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 9060A TOTAL ORGANIC CARBON
334 Environmental
Chemistry -
Marine Water
Manual of
oceanographic
observations and
Manual of oceanographic observations and pollutant
analyses methods (MOOPAM) - 1999 (IV-38) - Total
129
Prequalification Document-2015 Rev 28 16.09.2015
and Sediment pollutant analyses
methods (MOOPAM)
Organic Carbon
335
Environmental
Chemistry -Water
and Wastewater
ASTM D1498-14 Oxidation Reduction Potential of Water
336
Environmental
Chemistry -Water
and Wastewater
ASTM D1252-06
Reapproved 2012 Ed
1
COD of Water
337
Environmental
Chemistry -Water
and Wastewater
ASTM D4458-09 Chloride Ion in Brackish water, Seawater, and Brines
338 Aggregates AASHTO T2 Sampling of Aggregates
339
Environmental
Chemistry -
Water,Wastewate
r, Sediment, Soil,
and Sludge -
Metals
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
3120B ICP-AES Al, Ba, Be, B, Cd, Cr, Cu, Co, Ca, Fe,
Pb, Li, Mg, Mo, Ni, Zn, Sb, As, Hg, K, Se, Si, Ag, Na,Sr,
Tl, Sn, Ti, V, W
340 Environmental US EPA - Methods 6010C - 1 Revision 3 February 2007 METHOD 6010C
130
Prequalification Document-2015 Rev 28 16.09.2015
Chemistry -
Water,
Wastewater,
Sediment, Soil,
and Sludge -
Metals
For Chemical
Analysis of Water and
Wastes
INDUCTIVELY COUPLED PLASMA-ATOMIC EMISSION
SPECTROMETRY Al, Ba, Be, B, Cd, Cr, Cu, Co, Ca, Fe,
Pb, Li, Mg, Mo, Ni, Zn, Sb, As, Hg, K, Se, Si, Ag, Na,Sr,
Tl, Sn, Ti, V, W
341
Environmental
Chemistry -
Water,
Wastewater -
Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
US EPA METHOD 8260C VOLATILE ORGANIC
COMPOUNDS BY GAS CHROMATOGRAPHY/ MASS
SPECTROMETRY (GC/MS)
342
Environmental
Chemistry -
Water,
Wastewater -
Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 8015C NONHALOGENATED ORGANICS BY
GAS CHROMATOGRAPHY (GC-FID)
343
Environmental
Chemistry -
Water,
Wastewater -
Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 8270D SEMIVOLATILE ORGANIC
COMPOUNDS BY GAS CHROMATOGRAPHY/MASS
SPECTROMETRY (GC/MS) and GC-FID
344
Environmental
Chemistry -
Water,
Wastewater -
Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 8081B ORGANOCHLORINE PESTICIDES BY
GAS CHROMATOGRAPHY
345
Environmental
Chemistry -
Water,
Wastewater -
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 9065 PHENOLICS
(SPECTROPHOTOMETRIC, MANUAL 4-AAP WITH
DISTILLATION)
131
Prequalification Document-2015 Rev 28 16.09.2015
Organics
346
Environmental
Chemistry -
Water,
Wastewater -
Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
8082A - 1 Revision 1 February 2007
METHOD 8082A POLYCHLORINATED BIPHENYLS
(PCBs) BY GAS CHROMATOGRAPHY
347
Environmental
Chemistry -
Water,
Wastewater -
Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 8041A PHENOLS BY GAS
CHROMATOGRAPHY
348
Environmental
Chemistry -
Sediment, Soil,
and Solid Waste
Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 8015C NONHALOGENATED ORGANICS BY
GAS CHROMATOGRAPHY (GC-MS)
349
Environmental
Chemistry -
Sediment, Soil,
and Solid Waste
Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 8270D SEMIVOLATILE ORGANIC
COMPOUNDS BY GAS CHROMATOGRAPHY/MASS
SPECTROMETRY (GC/MS)
350
Environmental
Chemistry -
Sediment, Soil,
and Solid Waste
Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
8082A - 1 Revision 1 February 2007 METHOD 8082A
POLYCHLORINATED BIPHENYLS (PCBs) BY GAS
CHROMATOGRAPHY (GC-MS)
132
Prequalification Document-2015 Rev 28 16.09.2015
351
Environmental
Chemistry -
Sediment, Soil,
and Solid Waste
Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Volatile Organics METHOD 3540C SOXHLET
EXTRACTION
352
Environmental
Chemistry -
Sediment, Soil,
and Solid Waste
Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 8121 CHLORINATED HYDROCARBONS BY
GAS CHROMATOGRAPHY: CAPILLARY COLUMN
TECHNIQUE
353
Environmental
Chemistry -
Sediment, Soil,
and Solid Waste
Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 8041A PHENOLS BY GAS
CHROMATOGRAPHY
354
Environmental
Chemistry -
Sediment, Soil,
and Solid Waste
Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 3540C SOXHLET EXTRACTION
133
Prequalification Document-2015 Rev 28 16.09.2015
355
Environmental
Chemistry -
Sediment, Soil,
and Solid Waste
Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
US EPA METHOD 8270D SEMI- VOLATILE ORGANIC
COMPOUNDS BY GAS CHROMATOGRAPHY/MASS
SPECTROMETRY (GC/MS)
356
Environmental
Chemistry -
Sediment, Soil,
and Solid Waste
Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 9071B n-HEXANE EXTRACTABLE MATERIAL
(HEM) FOR SLUDGE, SEDIMENT, AND SOLID
SAMPLES
357 Microbiology
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Heterotrophic Plate Count 9215D - Membrane Filter
Method
358 Microbiology
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Membrane Filter Techniques for members of the coliform
group 9222B - Standard Total Coliform Membrane Filter
Procedure
359 Microbiology
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Faecal Enterococcus/Streptococcus Group 9230C -
Membrane Filter Techniques
360 Microbiology
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Faecal Enterococcus/Streptococcus Group 9230D-
Fluorogenic Substrate Enterococcus Test
361 Microbiology Standard Methods for
the Examination of
Water and
Nematological Examination 10750
134
Prequalification Document-2015 Rev 28 16.09.2015
Wastewater 22nd
Edition: 2012
362 Microbiology
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Iron and Sulfur Bacteria 9240D - Enumerating, Enriching,
and Isolating Iron and Sulfur Bacteria
363 Microbiology
Standard Methods for
the Examination of
Water and
Wastewater 22nd
Edition: 2012
Iron and Sulfur Bacteria 9240B - Iron Bacteria
364 Microbiology BS EN ISO
16266:2008
Water quality. Detection and enumeration of
Pseudomonas Aeruginosa. Method by membrane
filtration
365 Microbiology
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 9132 TOTAL COLIFORM: MEMBRANE-
FILTER TECHNIQUE
366 Microbiology
Analysis of
Wastewater for use in
Agriculture
Laboratory Manual of
Parasitological and
Bacteriological
Techniques
Laboratory Manual of Parasitological/Microscopic
Examination (Helminth and Nematode) / Microscopic
Examination
367 Microbiology
Manual of
Microbiological
Methods for the food
and drinks Industry
5th Edition Guideline
N0.43
CCFRA 1.1.4: 2003- Total Bacterial Count (Pour Plate
Method)
368 Microbiology Manual of
Microbiological
Methods for the food
CCFRA 1.1.1:2007 - Total Bacterial Count (TBC) for
Swab (Aerobic/ Anaerobic)
135
Prequalification Document-2015 Rev 28 16.09.2015
and drinks Industry
5th Edition Guideline
N0.43
369 Transformer Oil ASTM D4059 -
00(2010)
Standard Test Method for Analysis of Polychlorinated
Biphenyls in Insulating Liquids by Gas Chromatography
370 Transformer Oil
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 8082A POLYCHLORINATED BIPHENYLS
(PCBs) BY GAS CHROMATOGRAPH
371 Microbiology
Laboratory Manual of Parasitological/Microscopic
Examination (Helminth and Nematode) / Microscopic
Examination
372 Chemistry-
Cement BS EN 196-2:2013
Method of testing cement. Chemical analysis of cement.
Clause 4.5.2 Decomposition with sodium peroxide ( BS
EN 196-2:2005 Test No. 13.2)
373 Chemistry-
Cement BS EN 196-2:2013
Method of testing cement. Chemical analysis of cement.
Clause 4.5.13 Determination of magnesium oxide by
DCTA (reference method) ( BS EN 196-2:2005 Test No.
13.13)
374 Chemistry-
Cement BS EN 196-2:2013
Method of testing cement. Chemical analysis of cement.
Clause 4.5.8 Determination of soluble silica ( BS EN 196-
2:2005 Test No. 13.8)
375 Chemistry-
Cement BS EN 196-2:2013
Method of testing cement. Chemical analysis of cement.
Clause 4.5.9 Determination of total silica( BS EN 196-
2:2005 Test No. 13.9)
136
Prequalification Document-2015 Rev 28 16.09.2015
376 Chemistry-
Cement BS EN 196-2:2013
Method of testing cement. Chemical analysis of cement.
Clause 4.1.5 Preparation of Test Sample of Cement ( BS
EN 196-2:2005 Test No. 6)
377 Aggregates BS EN 933-4:2008 Tests for geometrical properties of aggregates.
Determination of particle shape. Shape index
378 Chemistry-
Cement BS 5075 Part 1:1982
Concrete Admixtures: Specifications for accelerating
admixtures, regarding admixtures and water reducing
admixtures
379 Soil BS 1377 Part 2:1990 Soils for civil engineering purposes: Classification Tests.
4.5 Casagrande apparatus method
380
Sediment, Soil,
and Solid Wastes
- Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 8015 - Total Petroleum Hydrocarbons (TPH)
/8270 Analysis of Semi-volatile organic compounds by
GC-MS
381
Sediment, Soil,
and Solid Wastes
- Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
Method 5030 - Purge and Trap for Aqueous Sample /
Method 5035 - Closed System Purge and Trap and
Extraction for Volatile Organics in Soil and Waste
Sample/ Method 8260 - Volatile Organic Compounds by
GC-MS
137
Prequalification Document-2015 Rev 28 16.09.2015
382
Sediment, Soil,
and Solid Wastes
- Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 3540C Soxhlet Extraction / Method 8121-
Chlorinated Hydrocarbons by Gas Chromatography:
Capillary Column Technique
383
Sediment, Soil,
and Solid Wastes
- Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 3540C Soxhlet Extraction / Method 8270D-
Semi-volatile Organic Compounds by GC-MS (GAS
CHROMATOGRAPHY/MASS SPECTROMETRY)
384
Sediment, Soil,
and Solid Wastes
- Organics
US EPA - Methods
For Chemical
Analysis of Water and
Wastes
METHOD 3540C Soxhlet Extraction / Method 8270D-
Semi-volatile Organic Compounds by GC-MS (GAS
CHROMATOGRAPHY/MASS SPECTROMETRY) -
Pesticides