preparing and using protective coating specifications

Upload: johnybull

Post on 02-Jun-2018

231 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    1/38

    !"#$%"&'( %'* +,&'(

    !"-.#/.&0# 1-%.&'(2$#/&3&/%.&-',

    SSPC: The Society for Protective Coatings40 24th Street, 6th Floor Pittsburgh, PA 15222-4656

    Copyright 2011

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    2/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    1

    SSPC: The Society for Protective Coatings

    Preparing and Using Protective Coating

    Specifications

    Introduction

    For many decades, some owners and engineers have considered protective coatings asincidental work not requiring any specialized expertise. With the changes that have

    occurred in protective coatings in the past 60+ years, we know that treating coatings asincidental work can produce costly errors. Up until the designation of hazardous

    materials in paint, such as lead, chromium, cadmium, arsenic, it was common for ownersto allow contractors to scrape and paint with primers containing one or more of these

    materials, and expect years of good service. Those paints were frequently used forprotection of steel structures because they worked, and they were generally one-part

    materials that did not require careful mixing of multiple components, Parts A and B forinstance. Those days are gone, and the replacement coatings are much more complicatedin formulation, in surface preparation requirements, in mixing, and in application and

    curing. There is less room for error in using high performance industrial coatings today.

    The purpose of this report is to describe some best practices for preparing andadministering a quality specification for application of high performance protective

    coatings and linings to industrial structures. This report focuses on developing anappropriate set of requirements for applying coatings and linings to obtain maximum

    coating system performance, service life, and protection of substrates in the prevailingservice environment. A well-prepared and administered specification will help ensure

    that the selected contractor performs the work according to the specification requirementsin the allotted time.

    This report focuses on the preparation and administration of specifications for

    competitively bid contracts, frequently called low bid contracts. This is the mostcommon type of contract, at least in the public sector, and is widely seen throughout the

    coating community. Competitively bid contracts are generally the most difficult forwhich to develop specifications (more detail required), and arguably, are the most

    difficult to administer, although when designed and administered appropriately, they canproduce consistent, predictable, and cost-effective results. This report is also applicable to

    direct selection, best value, and other negotiated contracts, but some tailoring of the

    requirements discussed herein may be prudent.

    The primary audience for this report includes facility owners, both public and private,

    coating program managers and engineers, and architecture-engineering firms responsiblefor preparing coatings specifications for clients. However, all parties involved in coating

    contracts can benefit from the information presented in this report.

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    3/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    2

    This report does not cover the formatting of the specification document. It instead,permits specification preparers to use their own formats as long as the requirements are

    presented logically and systematically so that its users can readily find them. Also, thisreport does not cover contract language intended to manage risk. However, all the

    recommendations included in this report should be considered by the designer

    (specification writer) based upon knowledge of the project (competent design) andrisk/reward factors dictated by cost and other restrictions imposed by the specific project.

    This document does not provide legal advice. It is instead intended to serve as a guide forthe creation of a coating specification. This document and any associated educational

    information are only offered as a general discussion of the subject matter and do notpurport to offer legal advice. It is strongly recommended that the designer seek the

    assistance of competent local legal counsel prior to final dissemination or use..

    This report is composed of two parts and four appendices:

    Part I. The Contracting Environment

    Part II. Items Commonly Required in Coating Specifications

    Appendix A. Itemized Checklist of Important Items to go into a Specification

    for Coating Steel/Concrete

    Appendix B. Glossary of Words or Terms as Used in This Report (that may

    not be familiar with all readers and may be used differently by different

    people)

    Appendix C. Description of CSI/CSC Division and Section Formats

    Appendix D. Guidance for Developing a Coating Condition Survey (CCS)

    Appendix E. Other Resources.

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    4/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    3

    Part I. The Contracting Environment

    Types of Coating and Lining Contracts

    To be effective, a well-designed coating specification must take into account the field

    conditions in which the specification will function. Thus it is important to consider boththe types of contracts and the roles of contracting parties in the construction contracting

    environment.

    A construction contract is a written legal agreement between two or more competentparties, usually an owner and a contractor, in which an offer for conducting coating work

    is made and accepted. It provides benefits for all parties.

    A coating specification is that part of a coating contract that details the qualitative andquantitative requirements of the process and finished product. The contractor is required

    to provide the specified product and no more without receiving additional compensation.

    There are many types and variations of contracts used in the construction industry,including the coating industry. For purposes of this report, contracts will be divided into

    two groups:

    Competitive-bid Negotiated

    Competitive Bid.A competitive -bid contract, also known as Design-Bid-Build (DBB),

    is a type of contract in which the contractor who quotes the lowest acceptable price isawarded the contract. With such a contract, there is little or no chance for reward with

    negotiated follow-on work, so the contractor has little to no incentive for providing morethan minimal completion of contract requirements. Nor should the prudent owner expect

    more.This is the most common type of contract used for coating work, as it can result inthe lowest cost for the desired work.

    Negotiated.A negotiated contract can have any of a large number of types and options,

    generally ranging from direct selection (no competition) through many forms ofcompetitive negotiation. A negotiated contract permits more of a partnering relationship

    between the owner and the contractor. This type of contract is likely to be easier toadminister, and the results are more likely to be closer to full contract conformance. But

    this does not diminish the need for proactive contract administration. Actual contract

    performance will be a function of the contractors quality management system and intentto satisfy the customer. Such a relationship may be more beneficial to both parties than acompetitive-bid contract, which sometimes becomes adversarial in nature.

    Creating a Level Playing Field

    There are many types of contracts to address many different purposes and ownerprocesses. The competitive bidding process is generally thought by public agencies to be

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    5/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    4

    the most equitable way to distribute public contracting funds. That assumption, however,is only valid when the entire process is fair to all potential bidders. This fair process

    creates the level playing field. that nearly every owner desires to find, and mostcontractors wish for when bidding on jobs., Such fairness is difficult to develop,

    implement, and maintain in the real world; however, designing a good specification can

    help work toward achieving a more equitable contracting environment.

    A level playing field will exist in any owners contracting environment when its contract

    requirements are equitably, equally, and totally enforced. All bidders must know andbelieve they will be held responsible to meet all contract requirements. Then, contractors

    who are fully qualified will be encouraged to bid, and those not fully qualified will bediscouraged from bidding. A level playing field encourages contractors to be more

    efficient in all aspects of planning and executing work. It can even result in an improvedowner-contractor relationship by establishing a good working environment.

    Writing a specification that cannot or will not be enforced defeats the purpose of striving

    for an equitable contracting environment. Working with competitive-bid contracts can bechallenging but it is possible to overcome the drawbacks by developing a better

    awareness of the issues . Identifying and addressing the root causes of competitivebidding problems and writing your specification to close gaps and potential loopholes

    will most likely enhance project success.

    Roles of the Contracting Parties

    The agreement between the facility owner and the contractor is typically one in which the

    contractor will perform the specified requirements and the owner will pay the contractprice.

    The Owners Role

    The owner should:

    Develop a complete and unambiguous description of the work detailing thedesired product

    Provide pro-active administration and enforcement of the project requirements,including timely Quality Assurance (QA) action

    Coordinate actions Professionally manage the project while ensuring coordination and cooperation so

    that others perform their responsibilities in an appropriate and timely fashion and

    in a friendly manner

    Key Elements for Success.Key elements of the specification that give the owner the

    best chance of hiring the lowest responsible bidder who will likely fulfill all contractrequirements are:

    Hiring a contractor with an established quality management system (QMS) (e.g.,

    SSPC QP Contractor Certification, ISO 9001, etc.)

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    6/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    5

    Requiring performance and payment bonds for the full cost of the projectprovided by a rated insurance company

    Establishing comprehensive quality control (QC) requirements (i.e., require theuse of qualified QC personnel, as well as a qualified work force of blasters and

    painters or other craft workers) and the means to assure compliance

    Requiring a detailed Work Plan such as that described by Brandon and Damianoin the Journal of Protective Coatings and Linings (Work Plan: Use It or Lose It,JPCL, June 2011, pp. 14-19)

    * Implementing Corrective Action throughout the job, including timely response toprogram weaknesses and elimination of the causes of nonconformities

    Competent Design.The design must be accurate and complete so that contractors can

    properly estimate the cost of full contract conformance. Even so, depending on marketvariables, competitive bidding can encourage some level of betting on what estimate will

    win the job rather than bidding the cost of full performance. The specification and itsadministration must be very strict for competitive bid contracts, because hungry

    contractors may bid low to obtain the contract and plan to make up differences with add-ons, or, even worse, by cutting corners to be sure to make a profit. Owners should be

    wary of estimates that are significantly below their estimated cost of full performance. Anextremely low bid, say 20-25% lower than the second low bidder, will likely indicate that

    the contractor failed to take all requirements into account, or that the specification wasvague or incomplete. Another reason for developing a good specification is that it reduces

    the chance of getting wildly low bids.

    The designer, generally an architect or engineer, is charged with creating a competentdesign for the project that will result in the desired product, and includes all of the

    information needed for each potential bidder to estimate costs and prepare a competitivebid. The designer may be an employee of a large organization or an independent

    contractor hired by the owner. The designer may, in turn, hire coating or other specialiststo assist in unfamiliar phases of the specification. The designers chief responsibility is to

    establish and convey project requirements in the specification. The designer should alsobe responsible for continuous review of all requests for information involving all

    technical issues, as well as all submittals, to ensure that the specification is being properlyexecuted.

    With a well-written and executed specification, the owner is much more likely to receive

    the desired product within the established time and price. However, if the specification isweak, vague, ambiguous or incomplete, the owner may encounter one or more of these

    problems:

    Withdrawal of bid invitation to correct project specification deficiencies Unrealistically high or low bids

    Bids from unqualified contactors Costly change orders for additional work

    Change orders because of different interpretations of specification requirements Costly delays resulting from disputes

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    7/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    6

    Very costly litigation Defaulted contracts

    Pre-Bid Conference.For large contracts, it is a good practice for owners to hold pre-bid

    conferences for potential bidders. Here, the owner presents the specification and

    describes the scope of work. The participants may ask for additional information aboutthe project and specification requirements, and owners should answer questions asappropriate, and provide those answers to all potential bidders. Participants are frequently

    given the opportunity to tour the work site (if available) with the owner to becomefamiliar with it. Potential bidders are allowed to take measurements and photographs and

    ask questions concerning the work. Holding an informative pre-bid conference may resultin more realistic bids with a narrower bidding range. Owners may also require the

    contractor who is awarded the contract to inspect the work site and all conditionsaffecting the work, review all contract documents, and then submit any errors, omissions,

    or other discrepancies within a certain period of time, such as 30 days after award.

    Pre-Construction Meeting.The owner should hold a pre-construction conference withthe selected contractor, QC and QA personnel, and other interested personnel as soon as

    possible after the award of the contract. This ensures that all participants have the sameunderstanding of requirements and administrative procedures to be followed. Scheduling

    and safety requirements can be discussed also. Ideally, the approved Work Plan will bediscussed at the conference, but it can just as effectively be discussed at a separate pre-

    work meeting if timing is an issue.

    Qualifications of Personnel for Planning and Specifying Coating Work. Facilityowners must exercise due diligence when choosing personnel, both in-house and

    consultants, for all coatings-related work. SSPC supports owners hiring qualified coatingspecialists or having persons become qualified through SSPC and other industry

    programs. More information about the SSPC Protective Coatings Specialist (PCS)Program can be found here: http://www.sspc.org/Protective-Coatings-Specialist-PCS-

    Program/In addition, JPCL/PaintSquare maintains a list of coating industry consultants.

    Role of the Contractor in Producing Quality Products

    Payment for Work Completed. The contractor is responsible for planning, scheduling,and producing work that conforms to all contract requirements. The contractor is also

    required to provide objective evidence of conformity (documentation) of completed workto project requirements when tendering for work to date. The fact that invoices are

    allowed to contain projected work rather than actual work to date seems to confoundmany administrators in their attempts to ensure payment for work based on objective

    evidence of conformity, but there are ways to handle this. Some owners may choose toeither audit invoices for evidence of conformity a month or two in arrears, or to require

    contractors to provide this traceability through logs or other methods. Other owners maychoose to make a one-time extra payment at the beginning of the project to compensate

    for the extra delays associated with payment for evidence of conformity. There may be

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    8/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    7

    other ways as well, but the intent is to keep all parties focused on paying only fordocumented conformity.

    Subcontractors.Even on large construction contracts, the coating portion may comprise

    only a small part of the work. When a subcontractor is used for specialized work such as

    coating, the prime contractor must provide documentation that the qualifications of thecoating subcontractor are equal to those of the prime contractor, or as specified. Someprime contractors may shop around for the cheapest subcontractors available for different

    parts of project work without considering their capabilities for providing quality work.This is a bad practice, because the prime contractor is responsible for all requirements of

    the project contract. This practice will likely become less of an issue where bidding isdone in a known environment with a level playing field, as subcontractor bids to prime

    contractors will be both responsive to all contract requirements and competitive in pricebased on efficiencies.

    The prime contractor should also have a separate contract containing appropriate

    submittals with the subcontractor that will ensure that all project requirements will bemet. In the event that there is a conflict between the requirements of the owners contract

    and the subcontractors contract, a dispute is likely to arise. Thus, both the contractor andsubcontractor should be familiar with the terms of the contract between the owner and the

    prime contractor and that between the prime contractor and subcontractor.

    Prime contractors must provide subcontractors with scheduling and sequencinginformation to avoid interference among different trades. They must also provide

    subcontractors with notice of any changes made to scheduling and sequencing that mayoccur during project production. The Prime must inform subcontractors of any

    communications between the prime and the owner that may affect the subcontractorswork.

    Vague Specification Requirements.Coating contractors like to bid on well-prepared

    project specifications because it is easier for them to determine the amount and quality ofwork required, and thus, easier to prepare a realistic and accurate bid. A few contractors

    may look for errors or vague requirements in a coating specification that will requirechange orders. Then, they may decide to bid low to get the contract and hope to make up

    for the money they left on the table through change orders and extras. This is an unwisepractice that can be prevented by a clear, complete specification and good contract

    administration.

    Requests for Information (RFI).There are often contract clauses that requirecontractors to review plans and specifications and request clarification where necessary,

    and advise the owner of errors, omissions, or other contract deficiencies whereappropriate, before work begins. A request for information (RFI) may be used to ask for

    clarification of vagueness in requirements or apparent work conflicts or discrepancies.Contractors should include procedures for the RFI process in their QC plans. RFIs should

    never be used for requesting contract deviations.

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    9/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    8

    Role of the Inspector in Producing Quality Products

    Requirements for inspection come in many variations, and inspectors may be hired by theowner, the contractor, the engineer, or some combination of these. The owner may or

    may not specify qualifications for the contractors inspectors (referred to as QC

    inspectors hereafter), and may or may not hire Quality Assurance (QA) inspectors tomonitor the contractors Quality Control (QC)/QA inspection and documentation.Regardless of the QC and QA inspection functions, the owner should specify

    requirements for inspection and documentation. If the contractor is to documentconformity to all requirements, this should be clear in the specification. It is

    recommended that the owner base payment obligations on objective quality evidence(OQE) of conformity to all requirements. This must be coordinated with procedures for

    payment.

    Inspector Responsibilities.The coating QC inspector is responsible for:(1)observing production work as it is being done;

    (2)

    assessing the conformity of the work to project requirements as described in theWork Plan; and

    (3)documenting and timely reporting of results of the inspection to others in eitherthe QC program or the QA program if the QA process includes hold point

    inspections.

    Inspectors should not be responsible for final acceptance or rejection of work unlessspecifically assigned this responsibility and qualified for this task. Quite often, the final

    accept/reject function requires knowledge and experience beyond that required ofinspector certification programs. Making accept/reject decisions are more suited to

    Protective Coating Specialists (PCS) certifications, or other qualifications.

    To assume that a certified coating inspector has the capability to properly represent theowners interests may be unfair to both the inspector and the owner. A final accept/reject

    decision by unqualified personnel can do more harm than good in terms of incentivizingappropriate contractor behavior, or in providing the desired work product.

    Regardless of employment arrangements and assigned duties, inspectors are expected to

    provide honest, unbiased data in reporting of tests and observations that are specified fordetermining conformance of the work. The required inspections, tests and observations

    from the project specification and referenced documents should be incorporated into theInspection & Test Plan as a part of the Work Plan.

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    10/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    9

    Legal Concerns in Coating Contracts

    Because coating contracts are legal documents, it is important to consider various legal

    concerns when writing the specification and drawing up the contract. A contracts attorney

    should review the final contract with special attention to:

    (1)Full performance - conformity to all contract requirements.

    (2)Breach of contract - nonconformity to some or all portions of a contractrequirement.

    (3)Substantial completion - project condition in which nonconformance is not

    material to the performance, breach is unintentional, and should be subject toa price credit for all value not received.

    (4)Claims - Assertions for a right, such as money or property, as part of a legal

    obligation.

    (5)Mechanics liens - Security interests in the title to property for the benefit ofthose who have supplied labor or materials that improve the property.

    (6)Alternative Dispute Resolution Identifying processes or systems designed to

    resolve disputes between parties without going into litigation, or detailing thedrafting parties preferences including venue and jurisdiction if litigation is

    necessary.

    (7)Indemnification - Agreement to compensate or reimburse someone fordamages incurred as a result of the act of another.

    (8)Affirmative action - Policy designed to redress past discrimination against

    women and minority groups through measures to improve their economic andeducational opportunities.

    A well-written specification should eliminate or minimize the issues discussed below.

    Contract Deviations. Deviations (often called variances) are changes to contract

    requirements. Contractor requests for deviations should be submitted during thesolicitation process when they can best be addressed by addenda to the specification.

    Otherwise, requests for deviation should be submitted early in the planning process.

    Requests for deviation (DFS) should be made by the contractor in the production phaseonly when unforeseen conditions are discovered that could not have been identified prior

    to production.

    Differing Site Conditions (Site Variation). Owners should inform potential contractorsof all site conditions that may affect the project cost or production before bidding begins

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    11/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    10

    or provide for a full and unfettered site investigation. Thus, it can be critical to provide allbidders the opportunity to inspect the work site, where feasible, before submitting their

    bids.

    After production begins, the contractor may discover work site conditions that differ

    materially from those indicated in the specification and could not have been identifiedduring the planning process. The contractor should be required to inform the owner ofthis within a reasonable time frame, so that these conditions may be promptly addressed.

    Differing site conditions are often a cause of contract disputes and litigation.

    Specification Nonconformance. A nonconformity is some element of interim or finalwork that fails to completely meet all contract requirements. A nonconformity usually

    requires rework or repair. In some cases, a nonconformity may be disposed of in amanner that may preclude rework or repair, based on the recommendation of the PCS. A

    properly prepared specification will reduce the potential for nonconformance and thusminimize costs for rework and delays.

    Corrective and Preventive Action

    A set of tools to be used during contract performance has proven to be particularly

    effective in minimizing the occurrence and recurrence of nonconformities with thespecification. When properly used, this set of tools, Corrective Action (CA) and

    Preventive Action (PA), can keep the contractor focused on producing conforming work.It is wise to consider these tools as a good mechanism for obtaining quality work rather

    than a means of contract enforcement.

    CA identifies the root cause of a nonconformity, takes steps to eliminate it, and thenfollows up to ensure that the nonconformity does not recur. Corrective Action is initiated

    through a Corrective Action Request (CAR) which may be prepared by the inspector orother individual involved in the project QC or QA process. It is tracked on a

    Nonconforming Work Log, or similar document, and on a Corrective Action Log, toensure that the problem is satisfactorily resolved and that appropriate action is taken. The

    correction and repair procedures taken by the contractor should be those prescribed in thespecification or as recommended by the coating manufacturer and/or an established

    industry practice, and documented.

    While CA is reactive in nature (responding to identified nonconforming work), PA isproactive in nature. It makes use of knowledge and past experience to prevent

    nonconformities from occurring in the first place. PA is initiated, managed, and trackedthrough preventive action requests (PARs) in much the same manner that is done for

    Corrective Action. A PAR may be initiated by anyone who sees an opportunity to preventa potential action that would require CA. Health and safety programs and safety

    incentives are good examples of PAs that have had good payoff.

    CA/PA clauses can be specified in the project specification or in the QMS standard. Forinstance, SSPC QP series contractor certifications require project-specific Work Plans,

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    12/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    11

    Corrective Action, and other requirements that are pertinent to the contract administrator.If an owner has specific requirements that tend to overlap QP series requirements, it is the

    contractors responsibility to harmonize the requirements to avoid any conflictingrequirements. The ideal place to do this is in the Work Plan.

    Basic Expectations from a Contractors Quality Management System (QMS)

    A quality management system addresses the principles and processes surrounding the

    design, development, and delivery of a general product or service. Specifying a QMSstandard as a preliminary requirement of the contractor sets up a process of organized

    activities to meet established goals.

    The owner should have expectations from the contractor concerning the work to beaccomplished. The most important expectation is that only work conforming to the

    specification will be tendered. More specific expectations of contractors obligated to aQMS include but are not be limited to:

    (1)Reviewing the specification for discrepancies, omissions, and conflicting

    statements.

    (2)Performing complete project planning and submitting a Work Plan or series ofprocess control procedures (PCPs) to the owner.

    (3)Verifying conforming work through inspection, process control, or a

    combination thereof.

    (4)Producing documentation of conforming work (objective evidence ofconformance)

    (5)Identifying and addressing all nonconformities through Corrective Action.

    (6) Submitting certifications of contractor and craft-worker personnel.

    (7) Submitting qualifications of personnel doing planning and preparation.

    (8) Complying with laws and regulations governing the project.

    (9) Submitting written requests for deviations from project requirements, as

    necessary. (No oral agreements to changes should ever be made.)

    The QMS concept is based on proven relationships between planning processes andsatisfactory results and promotes continual improvement to build on the planning process.

    The intent of the QMS is to ensure that the contractors initial planning and preparationand its verification efforts are designed to achieve conforming work.

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    13/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    12

    Coordination of Contract Participants to Obtain Quality Work

    As discussed in this section, obtaining a work product conforming to all contractrequirements in a timely manner is best achieved by setting up a process that establishes a

    level playing field and holds all parties to a contract accountable:

    (1)The designer must prepare a specification that describes all requirements in areadily understandable manner that is realistic and achievable.

    (2)The owner must provide complete information for potential bidders to

    estimate costs, ensure fairness in the bidding and the contract administrationprocesses.

    (3)

    The contractor must collect all contract requirements from the contract

    documents, referenced documents, secondary references in referenceddocuments, and any other pertinent documents, such as best practices. From

    this information the contractor must develop a Work Plan that describes allprocesses that will be used to create conforming product, and all inspection

    and documentation requirements.

    (4)The contractor must use the Work Plan as a continuous working document, allwork must be inspected to the Work Plan requirements.

    (5)Supervisors and production workers must understand all requirements and

    have the ability, equipment, and incentive to meet all requirements forprocesses in each phase of the work.

    (6) Inspectors must verify that the work meets all specification requirements. All

    nonconformities must be documented, tracked, and either corrected orresolved through contract change order. A Nonconformity Log can facilitate

    tracking.

    (7)Owner quality assurance (QA) personnel should audit the documentationprepared by the inspectors and periodically conduct observations, as deemed

    necessary, to ensure that documentation of all work is complete. If the latter isnot the case, use the Corrective Action system to address the documentation

    deficiencies and any other identified issues. A Corrective Action Request(CAR) Log can facilitate tracking.

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    14/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    13

    Part II. Items Commonly Required in

    Coating Specifications

    Part I described the contract environment and outlined tools that the specification

    developer (designer) can use to develop specifications that provide the owner with thebest chance of success for competitive bid coating contracts. Part II lists key elements ofthe specification and describes their functions.

    Coordination Requirements

    To be fully effective, the technical specifications must be coordinated with the owners

    front-end documents, as well as the general requirements for each project. The front-end documents, such as General Conditions, Additional General Conditions, Special

    Conditions, etc., establish the legal contracting environment, and the generalrequirements, designated as Division I requirements by the Construction Specification

    Institute (CSI), apply to all technical specifications. Division I specification Sectionsinclude such requirements as Submittals, Payment Procedures, Site Conditions, Quality

    Control, Environmental Protection Requirements, and many more.

    Foundation of the Specification

    Coating specifications, as with most technical specifications for construction work, canbe very complex documents, even without considering the thousands of seemingly

    mundane issues that are encountered on every project. Many specifications do not try tocover all of the routine issues, but most industries have developed standards for these

    routine issues. The coating industry, for instance, has covered many of these issues forcoating of industrial steel structures in SSPC PA 1 Shop, Field, and Maintenance Printing

    of Steel. Each coating specification for steel structures should start with SSPC PA 1 asthe foundation, and modify as needed or add to it as necessary to create a complete

    specification that gives both the contract administrator and the contractor a completedescription of requirements. SSPC PA 7 should be similarly used for concrete structures.

    Key Elements

    Scope of Project. Specifications should have introductions that describe the general

    scope of the project to prospective bidders. It should cover requirements for furnishing allof the required materials, labor, equipment, and tools for the surface preparation,

    application, and inspection work for the project. It should also provide a description ofthe project location and may include a map or plan of the work area. No project

    requirements should be included in the scope. Each project requirement should be locatedin its appropriate area of the specification and nowhere else. This minimizes confusion to

    persons using the specification. Enough information should be presented in the scopesection to permit potential bidders to determine whether they are interested in

    investigating the proposed project further.

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    15/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    14

    Areas to be Coated and Not to be Coated. The specification must define all of the areasthat are to be coated and all of the areas that are not to be coated in order for the

    contractor to understand the full scope of the project. Areas not to be coated may have tobe masked, and, if other areas are added after start of the production, the owner may be

    required to provide additional funding.

    Site Access and Storage Area. The owner must provide contractor personnel withaccess to the work site. Work areas often have limited access because of security or

    safety concerns or the presence of other conditions such as vehicular traffic, closeproximity to the public, or the presence of other trades. Also, sufficient area must be

    provided for the contractor to store required equipment and materials.

    Site Investigation Clause. When the contract documents fully describe the projectsexisting conditions, the importance of site investigation prior to submitting bids can be

    diminished, because bids are more likely to be representative of costs of performing thework and it is less likely that differing site condition claims will arise. It is reasonable to

    require qualified bidders to identify errors, omissions, and other contract discrepanciesthey find prior to submitting bids, but this is difficult to administer. A reasonable

    alternative is to require the contractor to advise the contract administrator of any errors,omissions, and other contract discrepancies, other than those that cannot be anticipated or

    identified without special access, within a reasonable time after submission of bids, suchas 30 days.

    References/Applicable Documents. A reference section of the specification should

    provide a listing of all documents (e.g., test procedures) cited in the specification and noothers. References to other reading materials of interest will only create confusion as they

    might be considered as a specification requirement. The listed documents form a part ofthe specification, to the extent described in the specification. Because the requirements in

    the referenced standards or documents are incorporated into the contract and becomeenforceable contract requirements, designers must read and know what they say. They

    should not be used as a catch-all just in case the designer might have left somethingout. Designers should also be aware that some of the information in the standards may be

    contradictory or in conflict with other standards and thereby create ambiguities that maybe interpreted against the drafter.

    Technical organizations that provide standards and other guidance relevant to coating

    projects include but are not limited to:

    ASTM (American Society for Testing and Materials) for test procedures

    API (American Petroleum Institute) for fuel tanks and appurtenances

    AWWA (American Water Works Association) for water tanks and appurtenances FHWA (Federal Highway Administration) for bridge and highway structures

    NACE International for metal corrosion NSF (National Sanitation Foundation) for potable water tank interiors

    SSPC (The Society for Protective Coatings) for guidance in coating operations

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    16/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    15

    Precedence of Documents. If required, this section of the specification sets an order ofprecedence in the event there is a conflict or an ambiguity between contract documents.

    Some owners use General Conditions or Special Conditions in the front-end documentsto describe precedence.

    Approved submittals usually supersede specifications, unless stated otherwise; however,many owners require that all deviations embedded in submittals be separately identifiedin special submittals called Requests for Deviation, or similar. It is also good practice to

    require that any work encumbered by a pending Request for Deviation in submittals beidentified as such in each applicable submittal.

    Definitions. A definition section of the specification should include definitions of all

    words and terms used in the specification that are not universally understood. Localworkers often use terms that are not understood by workers in other geographical areas.

    Industry standard definitions such as those in SSPCsProtective Coatings Glossary arenormally preferred to those of governmental organizations, because they are more widely

    used in the coatings industry.

    Submittals. Submittals are the required documents, information or products (samples)for owner or designer review to assure conformity with the specification. Paint submittals

    are typically required to ensure the contractor is intending to use the specified products inaccord with the manufacturers recommendations and the specifications so that if there

    are any conflicts between the specifications and the manufacturers recommendations,they can be reconciled before the work proceeds.

    A submittal section of the specification requires the contractor to regulate the timely flow

    of materials and documents used on the project and ensure their compliance withspecification requirements. Some of the submittals require submission in time for owner

    review in time for procurement, delivery, and contractor QC of materials and equipmentbefore initiating the production. Other submittals document the progress and quality of

    the production work to date.

    Typical coating project submittals required prior to initiation of production include butare not limited to:

    Manufacturers product data sheets for materials to be used

    Manufacturers material safety data sheets for materials to be used Samples of specified liquid coatings

    Coating draw-down films (cured films of uniform thickness applied to cardboardor other substrates)

    Any required permits, access rights, etc. Procedures for procuring samples of coating for laboratory testing

    Procedures for procuring samples of abrasives for laboratory testing Laboratory test results

    Certificates of product conformity to specification

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    17/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    16

    Project-specific Work Plan (or series of process control procedures [PCPs] to beutilized by the contractor for the specific project)

    Project-specific safety, health, and environmental protection plan Containment drawings (SSPC Guide 6)

    Warranty

    Typical coating project submittals required after initiation of production include but arenot limited to:

    Requests for information (RFI) log

    Contract change order log Submittal log

    Daily production reports (including safety reports)

    Daily inspection and test reports

    Corrective Action Requests (CARs) Nonconformity log

    CA log PA log

    Other reports that would provide meaningful data

    Safety and Health Plans. SSPC PA Guide 10 Guide to Safety and Health Requirementsfor Industrial Painting Projects provides guidance, including sample contract language,

    for specifying safety and health requirements for contractors. SSPC Guide 17 Guide toDeveloping a Corporate Safety Program for Industrial Painting and Coating Contractors

    is also usable by owners to evaluate contractors safety programs. Again, thesedocuments should be reviewed by the owner or designer to ensure they are appropriate

    for inclusion in the contract documents.

    Work Plan and Process Control Procedures (PCPs). A Work Plan is a writtendocument containing a list of all actions and procedures, assembled in logical sequence

    that describes all steps necessary for the contractor to produce a finished productconforming to all specification requirements. It translates the requirements of the

    specification into a series of steps for field implementation. It provides to the contractorsstaff the ability to plan and prepare to accomplish cost effective production within the

    schedule and in accordance with project requirements. It also provides the owners staffwith the ability to review submittals and understand the contractors intended processes.

    The Work Plan also permits but is not limited to scheduling such project procedures as:

    Health, safety, and environmental compliance plans

    Confined space entry plans Procurement of necessary materials

    Procurement of necessary job site and support equipment Assigning the management team to the project

    Obtaining craft workers with the necessary skills Mobilization of all of the above

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    18/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    17

    Worker training and personal protective equipment (PPE) Inspection and test plan (including forms with criteria for conformance and

    nonconformance) and log to match requirement and schedules of other workprocedures

    A process control procedure (PCP) is a written procedure presenting details of theindividual process being conducted as part of the total project work. It documents a singleprocess such as mobilization and setup, abrasive blasting, coating application and curing,

    and clean up.

    Coating work typically involves multiple processes, each of which will have to bedocumented. Sometimes the owner prefers to use PCPs instead of a Work Plan to

    facilitate routine coordination of work between the contractors forces and the ownersforces. PCPs are commonly used in refineries and shipyards. In such locations, work is

    usually done piecemeal and must be coordinated with that of other trades. All of thePCPs, when combined, should contain the same basic information as in a Work Plan.

    When PCPs are used individually, a separate schedule is required to show the order inwhich each process is to be used. When using a Work Plan or a series of PCPs, hold or

    check points may be placed in the specification to permit inspection for conformance ofwork to date before proceeding further.

    Work Plans are more commonly used where the entire site is turned over to the contractor

    to complete work on the contractors schedule. The format, i.e. Work Plan vs. a series ofPCPs, is the contractors choice, unless specified otherwise in the contract documents.

    Good planning will result in more efficient work production, and thus a savings to thecontractor. It will also help to avoid disputes by identifying conflicts, discrepancies, etc.

    at an early time in the process.

    Quality Assurance. A quality assurance section of the specification includesprerequisites, standards, limitations, and criteria that define the quality for products and

    work. They may include but are not limited to:

    Qualifications of the coating contractor Qualifications of certified protective coating specialist (PCS)

    Qualifications of a coating inspection company Qualifications of a quality control (QC) coating inspector

    Qualifications of individuals performing abrasive blasting, water jetting, coatingapplication and in some cases operation of specialized equipment such as plural

    component spray systems

    Qualifications of a certified industrial hygienist (CIH)

    Qualifications of a testing laboratory for coatings Qualifications of a testing laboratory for abrasives

    Certifications of materials Regulatory requirements

    Field sampling requirements Pre-construction conference and coordination meeting

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    19/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    18

    Qualifications and certification statements may be requested to establish the capabilitiesof the contractor and those employed or utilized by the contractor. SSPC-QP 1, Standard

    Procedure for Evaluating Painting Contractors (Field Application to Complex IndustrialStructures)can help assess a contractors ability to complete the project work in a

    satisfactory and timely manner. Additional certifications (e.g., SSPC-QP 2) may be

    required for special projects, e.g., if removal or disturbance of existing lead-based, orother hazardous paint complicates the work.

    SSPC offers additional industry-specific contractor Quality Management Certificationsfor specialty applications such as: Shop Coating (QP 3), Metallizing (QP 6), Coating of

    Concrete (QP 8).

    The coating industry is fortunate to have multiple certification programs for coatinginspection personnel and coating inspection companies. It is recommended that these

    certifications be used to the maximum extent on coating projects (e.g. NACE CIP orSSPC equivalent for inspectors or SSPC QP 5 for coating inspection companies).

    While qualifications for contract planners, administrators, and workers are often

    undefined, it may be desirable to identify more specific qualifications, such as thoselisted above, to help reduce the number of discrepancies between the owner and the

    contractor and permit easier resolution.

    Delivery and Storage of Materials and Equipment. A delivery and storage section ofthe specification should contain special requirements for packing and shipping products,

    equipment and their components. Conditions for acceptance of these items at the projectsite should also be included, along with special storage, handling, and disposal

    requirements necessary to prevent contamination or damage.

    It may be desirable to have a clause permitting the owners representative to obtain fromthe contractor at any time a sample of the coating being applied. Local air pollution

    personnel usually have this authority.

    Handling of Hazardous Materials and Production Waste. All hazardous materialsbrought onsite should be stored and handled in the safe manner as described in their

    material data safety sheets (MSDSs), which must always accompany the products. Anemergency action plan should be in place to respond to accidents involving hazardous

    materials. An OSHA-approved procedure must be in place for collecting, storing, anddisposal of hazardous waste generated during project work. Spill kits for clean up of

    spills are frequently required.

    Description of Project Site Conditions. It is important that the project site condition befully described. Information on any environmental limitations or other conditions at the

    project site that might affect project work should be presented. These may includeprevailing temperature, humidity, or ventilation. This section may also describe where the

    contractor can locate work equipment, trailers, lunchrooms, or shower facilities.

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    20/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    19

    Specified Type and Size Range of Abrasives. The specified abrasives should be testedfor particle size distribution, oil content, crystalline silica, and soluble contaminants by

    the referenced test methods, e.g., SSPC-AB 1, for conformance to specification beforeuse. This presumes the specification contains specific requirements for the abrasive. If

    there are no abrasive requirements specified then the choice of abrasive is left to the

    contractor.

    Kits and Equipment for Testing for Surface Cleanliness and Profile and Film

    Thickness. QC kits and other equipment necessary for testing for surface cleanliness andprofile and for coating thickness must be available at the work site. Production workers

    must be able to monitor the quality of their own work, and QC personnel must be able toverify that the specification requirements are being met. Wet film gages are commonly

    used by applicators to verify that the wet coating thickness at application time will meetthe final dry film thickness specification requirements once the coating dries. The

    specific parameters and test requirements must be included in the specification if theowner/designer expects those tests to be performed.

    Specified Types of Coating Materials Delivered and Their Verification. A materials

    section of the specification lists the coating materials to be used on the project. It mayprovide the names and code identifications of approved products, a qualified products list

    (QPL), Qualified Products Database, a description of the generic material, or adescription of the required performance. Typically public works projects require the

    allowance of an or equal clause if a particular product or manufacturer is referenced.There are specific legal requirements to be met if public owners want to try to sole

    source or limit the paint products. The legal requirements vary based on the status of thepublic owner (e.g., federal, state, or local governments, defense agencies, etc.) In some

    cases these limitations are unenforceable. The designer should be familiar with the legalrequirements if the intent is to limit bidders to the use of products to only a single paint

    manufacturer.

    The VOC (volatile organic compound) content of coating materials is required in mostU.S. geographical locations. If commercial products are specified, their colors should be

    selected from the manufacturers list of available colors. It is always best to procure allproducts of a multiple coat system from the same supplier and make sure that they are

    suitable for the intended use. Where multiple suppliers of a single system must be used,rules for determining all requirements of the coating system must be specified to avoid

    conflict among suppliers.

    Upon delivery, the coating materials must be identified as those specified and as havingsufficient shelf life to complete the project. It is a good practice to check both the

    condition of the containers, including the seals, and the condition of the coating bylaboratory testing of one or more samples and record the batch numbers. The volume of

    coating materials required can be calculated from their spreading rates and the surfaceareas to be covered. This will ensure that there is sufficient coating at the job site to

    complete the work.

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    21/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    20

    Acceptable Ambient Conditions. A section of the specification should list acceptableambient conditions for surface preparation and coating application and curing or at least

    require the products to be applied in accordance with the manufacturersrecommendations. These include but are not limited to:

    Air temperature Surface temperature Dew point/relative humidity

    Wind speed Lighting for all work areas (as prescribed in SSPC-Guide 12)

    Pre-cleaning of Surfaces for Painting Prior to Surface Preparation. This section of

    the specification describes the required pre-cleaning actions (e.g., grinding of welds andsharp edges) before the actual surface preparation for coating. It also describes the

    required levels of pre-cleaning.

    Blast Cleaning of Surfaces for Coating Application. Abrasive blast cleaning is themost commonly specified surface preparation method for cleaning industrial steel

    surfaces for coating. Waterjetting is sometimes used to prepare previously blasted andcoated steel surfaces. Any required special equipment or procedures should be specified

    along with the required level of cleaning and profiling. Some recommended methods forsurface preparation of concrete and concrete masonry unit (CMU) for coating are

    described in ASTM D4258, Practice for Surface Cleaning Concrete for Coating, andASTM D4261, Practice for Surface Cleaning of Concrete Unit Masonry for Coating.

    Other requirements that may be included are field checking for cleanliness of abrasives

    and air supply used in abrasive blasting and blow down and the quality of the water usedin waterjetting (usually potable water can be specified).

    Coating Application. An application section of the specification specifies acceptable

    methods (e.g., brush, roller, or spray) that may be used to apply the specified materials.Manufacturers product or technical data sheets (usually specification submittals) are

    commonly required to provide recommended procedures for application for specificcoatings. Application concerns are listed below, with those specifically applicable to

    chemically-curing multiple component coatings identified with a *.

    Condition in container The ratio by volume of the components to combine *

    Instruction for mixing components

    Amounts of thinner, if any, permitted

    Ambient conditions for application Induction time at different temperatures *

    Pot life at different temperatures * Recoat window *

    Contrasting colors for multiple coat systems Stripe coating requirements

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    22/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    21

    Acceptable dry film thickness range Acceptable wet film thickness range (if coating must be tacky when topcoat is

    applied)

    The dry film thickness range should have minimum and maximum limits necessary for

    optimum coating performance. If appearance is important the appearance of cured filmscan be required to be in accordance with SSPC-PA 1 for steel surfaces and in accordancewith SSPC-PA 7 for concrete surfaces.

    QC Inspection and Documentation Requirements. Project documentation, including

    inspection and testing records, must be used to determine the contractors compliancewith specification requirements and approved procedures. Project-specific forms that

    include pass and fail criteria found in the specifications should be used for thedocumentation. The coatings inspector should sign these forms and copies of the

    documentation should be forwarded to the contract administrator as soon as they havebeen completed or as specified in the contract documents.

    Accepting Project Work and Clean-Up of all Equipment, Materials, and Waste

    Products. A punch list of action items needing completion is prepared prior to a finalinspection to ensure that all work is complete and ready for the final acceptance by the

    owner.

    At all times, the contractor must keep the premises and surrounding area free fromaccumulation of waste materials and rubbish created by project work. Following

    completion and acceptance of the work, the contractor must remove all debris,equipment, and materials from the site. Materials and equipment may have to be

    decontaminated if exposed to hazardous materials such as lead-based paint before beingremoved from the work site. The existing facilities must be restored to their original

    condition.

    Some owners find that it is cost-effective to take possession of specific hazardousmaterials. The specifics of any such transfer should be detailed in the specifications,

    including requirements for submittal of procedures, etc.

    Warranty. The warranty section of the specification requires:

    That all materials and equipment be of good quality and new That the work be free from defects

    That the work conforms to all contract documents

    It is important that a warranty section of the specification clearly states any special orextended warranty or bonding for conformance to specification.

    Warranties for coating work are typically for one year after acceptance of the work.

    Arrangements should be made to have completed projects re-inspected for deficienciesprior to the termination of the warranty period, so that a written legal claim can be made

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    23/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    22

    within this time frame. Some owners withhold 5 to 10% of the total payment until the endof the warranty period to ensure that deficiencies found within this period are addressed.

    A prudent owner or designer should consider defining the conditions that wouldconstitute a breach of warranty at the end of the warranty period. If desired, a scheduled

    warranty inspection and list of attending parties can be included in the specification.

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    24/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    23

    Appendix A. Checklist of Items Commonly Found in

    Specifications for Coating Steel and Concrete

    NOTE: This list is intended to be used with the text above, even though it is more

    detailed than the text. Use applicable portions of this document for each project, and addrequirements not listed here as appropriate to produce a competent design.

    General contract considerations

    Coordinate with owners front-end documents (General Conditions, Additional

    General Conditions, Special Conditions, etc.) Define scope of project fully (Get detailed field conditions if maintenance work)

    Contract specifications (using CSI three-part Section format see Appendix C))

    GENERAL

    Scope of ProjectAreas to be coated and not to be coated

    Site Access and Storage Area

    Site Investigation Clause

    References (sometimes called Applicable Documents)

    SSPC PA 1 Shop, Field, and Maintenance Painting of Steel

    For coating concrete surfaces:

    SSPC-PA 7, Applying Thin Film Coatings to Concrete

    SSPC-TU 10, Procedures for Applying Thick Film Coatings and

    Surfacings Over Concrete Floors

    Surface preparation

    Others

    Precedence of Documents

    Definitions

    Submittals (pre-work)(Many of these continue during work)

    Contract errors, omissions, and other discrepancies, including conflicting

    requirements, ambiguous requirements

    Procedures for Corrective Action

    Project-specific Work Plan or Process Control Procedures (PCPs)

    Project-specific Health, safety, and environmental compliance plans

    Site access/security requirements

    Project-specific Confined space entry plans (permit required and non-

    permit required)

    Procurement of necessary materials

    Procurement of necessary job site and support equipment

    Assigning the management team to the project

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    25/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    24

    Obtaining craft workers with the necessary skills

    Mobilization of all of the above

    Worker training and personal protective equipment (PPE)

    Inspection and test plan (ITP) (including forms with criteria for

    conformance and nonconformance)

    ITP Log to match requirement and schedules of other work procedures

    Qualifications

    Qualifications of the coating contractor

    Qualifications of certified protective coating specialist (PCS)

    Qualifications of a coating inspection company

    Qualifications of a quality control (QC) coating inspector

    Qualifications of individuals performing abrasive blasting, water

    jetting, coating application

    Qualifications of a certified industrial hygienist (CIH)

    Qualifications of a testing laboratory for coatings Qualifications of a testing laboratory for abrasives

    Certifications for materials used

    Regulatory requirements

    Field sampling requirements

    Pre-construction conference, coordination and progress meetings

    Manufacturers product data sheets for materials to be used

    Shelf-life of applicable materials

    Rules for shelf-life extension

    Manufacturers material safety data sheets for materials to be used

    Samples of specified liquid coatings Coating draw-down films (cured films of uniform thickness applied to

    cardboard or other substrates)

    Laboratory test results

    Certificates of product conformity to specification

    Requests for Information (RFI) Log

    Contract Change Order Log

    Submittal Log

    Daily production reports (including safety reports)

    Daily inspection and test reports (DIRs)

    Corrective Action Requests (CARs)

    Nonconforming Work Log

    Corrective Action Log

    Preventive Action Log

    Other reports that would provide meaningful data

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    26/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    25

    Submittals Required during Production

    All Logs

    Production, inspection, and other reports

    CARs

    Other reports or information affecting production or conformity to

    requirements

    PRODUCTS

    Coating materials and thinners (other than as specified by mfg.)

    Contrasting colors for multi-coat systems

    Abrasives

    Test Kits

    Amine blush testing

    Salt testing

    EXECUTION

    Deliver, Store, Mix, Apply, and Cure Coatings According to SSPC-PA 1 (for steel

    surfaces) or SSPC PA 7 or TU 10 for concrete surfaces)

    Equipment for Surface Preparation and Coating Application

    Kits and Equipment for Testing for Surface Cleanliness and Profile and Film

    Thickness

    Specified Types of Coating Materials Delivered and Their Verification

    Field mock-up (as part of verifying procedures during start-up particularly for

    coating of concrete)

    Acceptable Ambient Conditions Periods of control

    During surface preparation

    During coating application and initial curing (specify initial cure time)

    During other operation

    Parameters of control

    Air temperature

    Surface temperature

    Dew point/relative humidity

    Wind speed

    Surface contaminants

    Lighting for all work areas (as prescribed in SSPC-Guide 12)

    Blast Cleaning of Surfaces for Coating Application

    Desired results

    Allowable methods

    Ambient conditions for surface preparation

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    27/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    26

    Pre-cleaning of Surfaces for Painting Prior to Surface Preparation

    Profile shape/height/peak density

    Protection of areas not to be prepared

    Other Methods of Surface Preparation (e.g. Water jetting; Hand and Power Tool

    cleaning; Scarifying, etc.)

    Desired results

    Allowable methods

    Ambient conditions for surface preparation

    Pre-cleaning of Surfaces for Painting Prior to Surface Preparation

    Profile shape/height/peak density

    Protection of areas not to be prepared

    Coating Application

    Condition in container

    The ratio by volume of the components to combine

    Instruction for mixing components Amounts of thinner, if any, permitted

    Ambient conditions for application and curing (length of cure)

    Induction time at different temperatures

    Pot life at different temperatures

    Allowable application methods

    Stripe coating

    Protection of areas not to be coated

    Protection of painted surface during curing

    Initial cure period

    Recoat window Acceptable wet/dry film thickness range

    Repairs (how much allowable and special requirements)

    QC Inspection and Documentation Requirements

    Final inspection

    Punch List

    Clearing of Punch List

    Clearing of Nonconforming Work Log

    Clearing of Corrective Action Log

    Review of docs for completion/certification of documentation

    Warranty & correction period requirements/criteria

    Clean-up and proper disposal of wastes

    Clean up of site to condition at start of project

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    28/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    27

    Appendix B. Glossary of Words and Terms as

    Used in Report

    Addendum - Modification of original specification before contract signing and

    start of work Affirmative action - Policy designed to redress past discrimination against

    women and minority groups through measures to improve their economic and

    educational opportunities Audit - Systematic review of evidence to verify acceptable completion of work

    CA - See Corrective Action CAR - See Corrective Action Request Change order - Modification to the original specification after production has

    begun to address errors or unforeseen conditions that may occur

    Claim(legal) - Legal demand or assertion by a claimant for compensation,payment, or reimbursement for a loss under a contract or an injury due to

    negligence Coating contractor- An individual or firm whose primary business is providing

    surface preparation and coating application services for home, commercial, orindustrial markets

    Competent design- Cost effective design that encompasses all of the pertinentscope and technical requirements of a specification and for which the owner is

    willing to pay Compliant Fulfillment of a legal or regulatory requirement

    Confined space - As defined in U.S. regulations, a space that is large enough andso configured that an employee can bodily enter and perform assigned work; has

    limited or restricted means for entry or exit; and is not designed for continuousoccupancy

    Conforming- Fulfilling a contract requirement Contract - A written legal agreement between two or more competent parties,

    usually an owner and a contractor, in which an offer for conducting work is madeand accepted; it provides benefits for all parties.

    Contract administrator- The representative of the facility owner (the second

    party to the contract) is generally responsible for administering the contract

    requirements, coordinating actions, and keeping the project moving forward whileensuring that others perform their respective responsibilities appropriately

    Contractor - The first of two parties to a contract who is responsible for planningand preparing production work that conforms to contract requirements and for

    tendering that conforming work for acceptance and payment with appropriateobjective evidence (documentation) of conformance to specification

    Contractor quality control - That part of an owner-contractor relationship inwhich the project contractor is responsible for conformance with specification

    requirements and correcting any deviations Correction- Action taken to address and/or correct a nonconformity (i.e., fix a

    problem)

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    29/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    28

    Corrective Action - Correcting a nonconformity and eliminating its root cause sothat it does not recur

    Corrective action request (CAR) - Written request to identify the root cause of anonconformity, correct it, and prevent its recurrence

    Designer/Engineer - Owners representative responsible for preparation of

    contract specifications, as well as technical aspects of their implementation Deviation - A change to the project specification, generally submitted during the

    planning process

    Differed site conditions - A physical condition, other than the weather or a act ofGod, discovered on a coating project that differs in a material respect from what

    was indicated in the specification or what might be reasonably expected Dispute resolutions - Process or system designed to resolve disputes between

    parties without having to enter into litigation Hazardous substances - In the U.S., 400 substances defined as posing hazards to

    humans and the environment, based upon ignitability, corrosivity, reactivity, andtoxicity

    Indemnification - Act of compensating for incurred injury, loss, or damage Inspection - Confirmation by observation, testing, and documentation to provide

    evidence whether specified requirements have been met Lien - A legal claim against an asset which is used to secure a loan and which

    must be paid when the debt is paid off Litigation - Legal action Lockout/Tagout System - In the U.S., an OSHA rule that provides a means of

    protecting workers from injury or death caused by the accidental start-up or

    release of stored energy from equipment. It involves (1) blocking the flow(lockout) of energy from a power source to a piece of equipment by using a

    device such as a padlock or chain, or by removing a fuse or circuit breaker(lockout) and (2) placing a tag (tagout) on the source identifying the party who

    has locked it out. Maintenance Coating or Coating Maintenance- refers to repair and/or

    overcoating of existing coating as opposed to complete removal of coatings andrecoating.

    Material Safety Data Sheet - Information sheet that informs workers about

    health and safety hazards of a materials components and provides safety

    procedures for handling and proper actions to be taken in the event of anemergency

    Mechanics lien - A security interest in the title to property for the benefit of thosewho have supplied labor or materials that improve the property

    MSDS - See Material Safety Data Sheet

    Nonconformity- Interim or final work that fails to fulfill contract requirements

    and requires rework or repair Objective evidence of nonconforming work- Documented evidence (i.e.,

    written records or photographic documentation) indicating required rework orrepairs

    Objective Quality Evidence - Unbiased documentation of a existing condition

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    30/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    29

    Occupational Safety and Health Administration - Federal government agencyin the Department of Labor with the responsibility of maintaining a safe and

    healthy work environment OQE - See Objective quality evidence

    OSHA - See Occupational Health and Safety Administration

    Owner - Individual, group of individuals, or organization that actually owns afacility or is responsible for its operation and maintenance PA - See Preventive action

    PAR - See Preventive action report PCP - See Process control procedure

    Pre-construction conference- Meeting of owner, contractor, and other pertinentpersonnel to review specification requirements before production work begins

    Preventive action - Action taken to prevent nonconformity or any condition that

    reduces efficiency before it has the opportunity to occur

    Preventive action report - Action taken to prevent a problem from occurring,based on an understanding of the product or process

    Prime contractor - Individual or firm that holds a construction contract with afacility owner

    Proactive - assuming an active rather than a passive role in doing oraccomplishing a task, i.e., taking the initiative

    Process control procedure - Written procedure presenting details of theindividual process being conducted as of a total work project.

    QA - See Quality assurance QC - See Quality control

    QPL - See Quality products list Qualified products list - List of products approved by the owner for protection of

    specified surfaces, i.e., materials that have passed tests as the qualifying agencybelieves to demonstrate satisfactory performance

    Quality - Degree of excellence or essential characteristics Quality assurance - All of the actions required by the owner to ensure contractor

    conformity to all contract requirements Quality control - That part of quality assurance in which the contractor ensures

    that all project work meets the standards developed by coating and relatedtechnical organizations, specifically those required in the project specification

    QMS - See Quality management system Quality Management System - System of general or specific policies and

    procedures intended to improve and control work processes Request for information - Procedure for contractor to procure information from

    an owner to clarify contract requirements

    RFI - See Request for information

    Safety plan - Contractor-developed plan for a project that addresses specificproject hazards and provides workers with both general safety training and

    additional safety training related to specific project hazards Site variation - See Differing site conditions

    Specification- That part of a contract that details the qualitative and quantitativerequirements for the finished product

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    31/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    30

    Subcontractor- Individual or firm contracted by the Prime contractor to performpart or all of a contract

    Submittal - Project documentation that the contractor is required to provide to theowner to assure completeconformanceto the specification; some submittals are

    required before production is initiated, and others are submitted during actual

    work production. Technical standard- Consensus document of engineering, trade or other

    professional associations that define a test method or procedure of the

    organization Tender- Offer for acceptance and payment

    Variance- See Deviation Volatile organic compound - Organic chemical product, such as a coating and

    liquid cleaner, that contains compounds that pollute the air upon evaporation VOC - See Volatile organic Compound

    Verification - Confirmation by examination and provision of evidence thatspecification requirements have been met

    Warranty- Written guarantee of integrity of a product and the producersresponsibility for repair or replacement of deficient parts

    Work - Materials, workmanship, manufacture, and fabrication of components Work Plan- Document containing a list of all actions and procedures, in logical

    sequence, necessary to produce a product meeting all specification requirements

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    32/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    31

    Appendix C. Description of CSI/CSC Division and

    Section Formats

    There are numerous formats for organizing project specifications, one of which is the

    MasterFormat, published by the Construction Specification Institute (CSI).MasterFormat is a master list of numbers and titles classified by work results orconstruction practices, used throughout the North American construction industry to

    organize project manuals, detailed cost information, and relate drawing notations tospecifications.

    Division Structure

    Division 00 - Procurement and Contracting Requirements

    Miscellaneous examples of sections:00 10 00 Solicitation

    00 20 00 Instructions for Procurement00 30 00 Available Information00 40 00 Procurement Forms and Supplements

    00 50 00 Contracting Forms and Supplements00 61 00 Bond Forms

    00 70 00 Conditions of the Contract

    Division 01 - General Requirements Requirements that apply to the entire

    contract

    Miscellaneous examples of sections:01 10 00 Summary

    01 20 00 Price and Payment Procedures01 30 00 Administrative Requirements

    01 31 00 Project Management and Coordination01 32 00 Construction Progress Documentation

    01 33 00 Submittal Procedures01 35 00 Special Procedures

    01 40 00 Quality Requirements01 50 00 Temporary Facilities and Controls

    01 60 00 Product Requirements01 70 00 Execution and Closeout Requirements

    01 80 00 Performance Requirements

    01 90 00 Life Cycle Activities01 91 00 Commissioning01 92 00 Facility Operation

    01 93 00 Facility Maintenance01 94 00 Facility Decommissioning

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    33/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    32

    Divisions 02 thru 48 Technical Requirements - Requirements that apply

    Miscellaneous examples of sections:

    03 00 00 Concrete04 00 00 Masonry

    05 00 00 Metals

    06 00 00 Wood, Plastics, and Composites07 00 00 Thermal and Moisture Protection08 00 00 Openings

    09 00 00 Finishes (including coatings)09 90 00 Painting and Coating

    09 91 00 Painting09 96 00 High-Performance Coatings

    09 96 13 Abrasion-Resistant Coatings09 96 23 Graffiti-Resistant Coatings

    09 96 26 Marine Coatings09 96 33 High-Temperature-Resistant Coatings

    09 96 35 Chemical-Resistant Coatings09 96 43 Fire-Retardant Coatings

    09 96 46 Intumescent Painting09 96 53 Elastomeric Coatings

    09 96 56 Epoxy Coatings09 96 59 High-Build Glazed Coatings

    09 96 63 Textured Plastic Coatings09 96 66 Aggregate Wall Coatings

    09 97 00 Special Coatings09 97 13 Steel Coatings

    09 97 13.13 Interior Steel Coatings09 97 13.23 Exterior Steel Coatings

    09 97 23 Concrete and Masonry Coatings09 97 26 Cementitious Coatings

    09 97 26.13 Interior Cementitious Coatings09 97 26.23 Exterior Cementitious Coatings

    10 00 00 Specialties23 00 00 Heating, Ventilating, and Air Conditioning

    (HVAC)23 10 00 Facility Fuel Systems

    23 11 00 Facility Fuel Piping23 11 13 Facility Fuel-Oil Piping

    23 11 16 Facility Gasoline Piping23 11 23 Facility Natural-Gas Piping

    23 11 26 Facility Liquefied-Petroleum Gas Piping23 12 00 Facility Fuel Pumps

    23 12 13 Facility Fuel-Oil Pumps23 12 16 Facility Gasoline Dispensing Pumps

    23 13 00 Facility Fuel-Storage Tanks33 00 00 Utilities

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    34/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    33

    33 10 00 Water Utilities33 50 00 Fuel Distribution Utilities

    33 51 00 Natural-Gas Distribution33 52 00 Liquid Fuel Distribution

    33 56 00 Fuel-Storage Tanks

    45 00 00 Industry-Specific Manufacturing Equipment46 00 00 Water and Wastewater Equipment48 00 00 Electrical Power Generation

    *The miscellaneous examples of sections are intended to show the layout of the

    CSI/CSC Masterformat. The entire system is available through the CSI web site:http://www.csinet.org/. CSC Construction Specifications Canada:

    http://www.csc-dcc.ca/

    The U.S. Department of Defense facilities guide specifications use a modifiedversion of the above numbering system, available at the following web site:

    http://www.wbdg.org/ccb/browse_org.php?o=70.

    Section Format

    Each Section concerns a particular portion of the work, and has a three-part structure that

    interfaces with the Division 01 general sections. The format is as follows:

    Section xx xx xx xxPart 1 General

    Part 2 ProductsPart 3 Execution

    Sections in Division 01 contain requirements only under Part 1 General while Sections

    in Divisions 02 48 generally have requirements in all three Parts. The Part 1requirements in Divisions 02 48 supplement the general requirements of Division 01

    Sections. For instance, it is common for there to be requirements in many Divisions 02 48 Sections specific submittals, and these submittals would be subject to the general

    submittal requirements in Section 01 33 00 Submittal Procedures.

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    35/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    34

    Appendix D. Guidance for Developing a Coating

    Condition Survey (CCS)

    SSPC PA Guide 5, Guide to Maintenance Coating of Steel Structures in Atmospheric

    Service, covers procedures for developing a maintenance coating program for steelstructures. The guide may be used for one-time recoat or long-range recoat programs.Every owner should consult this guide to manage the coatings on their facilities. When a

    specific facility or group of facilities is considered for maintenance coating work, a CCSshould be performed in accordance with SSPC Technology Update 3 ( SSPC TU 3)

    Maintenance Overcoatingto determine if maintenance overcoating is appropriate, and toestablish the detailed requirements for the maintenance coating design.

    The CCS should be accomplished by personnel from a business that routinely performs

    coating evaluations, and the individual investigator should be Certified by SSPC orNACE as a Protective Coatings Specialist (PCS). The CCS should be sufficiently detailed

    to provide all technical information about the coatings, and structures to be coated,inorder to properly design the project. At a minimum, the CCS should provide a detailed

    report of:

    1. Existing coating conditions, including condition of coating film, and the existenceof potentially hazardous substances that may impact coating management (i.e.

    lead, cadmium, chromium, etc.);

    2. Analysis of remaining coating life, suitability of overcoating, and technicalrequirements for overcoating;

    3. Technical recommendations for the most cost effective management of existing

    coating systems, including any hazardous materials present in paint film; and

    4. Any other information of interest to the coating system management that shouldbe identifiable by an individual trained and experienced in the field of coating

    analysis, coating failure analysis, and coating design.

    The scope of the CCS should be tailored to the specific project, and it should berecognized that while multiple coating failures or deficiencies may look similar to the

    untrained eye, the risks of generalizing to save evaluation costs are potentially very high.The cost of large-scale failure of the overcoating, and complete replacement of the

    coating system, is far more than the cost of a CCS for all but the smallest projects.

    The risks of overcoating can usually be avoided by designing the project to remove allexisting coatings to bare metal, then providing appropriate surface preparation and

    coating application. However, the extra costs of the coating removal, especially ifcontaining hazardous material, may be exorbitant compared to the costs of maintenance

    overcoating where the existing coating system is in fair-to-good condition.

  • 8/10/2019 Preparing and Using Protective Coating Specifications

    36/38

    SSPC Preparing and Using Protective Coating Specifications Aug. 2011

    35

    The fact that lead was highly used as a primer is indicative of its value to the corrosioncontrol industry. Premature removal of sound lead primer is not considered to be a good

    coating