premature storm drainage system repairs and replacement
TRANSCRIPT
![Page 1: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/1.jpg)
Date
Premature Storm Drainage System Repairs and Replacement
April 8, 2015
Stewart EdwardsProgram Manager
Design Management TeamCharlotte-Mecklenburg Storm Water Services
![Page 2: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/2.jpg)
Agenda
• Storm Water Infrastructure• Identifying Problems (Before and After)
Infrastructure is Installation• Common Premature Problems and Failures• What is Storm Water Doing on Our Projects?
2
![Page 3: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/3.jpg)
Stormwater Infrastructure
• Stormwater infrastructure consists of pipe, inlets, junctions, creeks, and ditches
• Systems in public rights-of-way• Systems on private property in
public drainage easements • Connected as a system• Access and easements
(private/public versus City)
Steele Creek Landing Subdivision
3
![Page 4: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/4.jpg)
Stormwater Infrastructure
Service Life Expectations (examples)• Reinforced Concrete Pipe (RCP) – 100+ years• High Density Polyethylene Pipe (HDPE) – 50 years + TBD• Corrugated Metal Pipe (CMP-no longer allowed) – 25-30
years• Aluminized (other new coatings) Corrugated Pipe – 75 years
– Life Expectancy comes from different sources ACPA, FHWA, FLH, NASPD, local experience, etc. and assumes appropriate installation. The actual life can be influenced by local conditions, environmental characteristics, installation, use, etc.
RCP HDPE CMP4
![Page 5: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/5.jpg)
Identifying Problems During and After Infrastructure is Installed
• Construction inspection• Testing (compaction and materials)• Closed Circuit Television (CCTV - video) inspection• Confined space entry (Manual Entry)
5
![Page 6: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/6.jpg)
Bad JointsCracked Pipe
Broken Pipe
Utility Intrusion
Images from Astonboro Drive (Built 2002) 6
Identifying Problems During and After Infrastructure is Installed
![Page 7: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/7.jpg)
• HDPE (plastic pipe egged shaped) loss of structural integrity
Images from Mallard Landing RoadBuilt 2006
• Sanitary sewer punched through the storm drain
7
Identifying Problems During and After Infrastructure is Installed
![Page 8: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/8.jpg)
• Reinforcing steel used to support frame and grate
Images from Mallard Landing RoadBuilt 2006
• Slab cut to move inlet position
8
Identifying Problems During and After Infrastructure is Installed
![Page 9: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/9.jpg)
Common Premature Problems
• Premature failures impact public roads and private property
• Problems usually are not detected until several years have past.
• Streets settle• Sinkholes form• House foundations impacted• Need structural shoring
during repair construction.
Sahalee Lane 9
![Page 10: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/10.jpg)
Common Premature Problems
Haines Mill RoadThe Villas at Laurel ValleyBuilt 2006
• Precast catch basin leaking around joints
• Sinkholes formed• System is in backyards and
access is limited • Shoring will be needed to
protect the foundations of nearby homes
10
![Page 11: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/11.jpg)
Provincetowne DriveReavencrestBuilt 2001
• Separated pipe joints• Sinkholes formed• Shoring will be needed to protect
the foundations of nearby homes
Common Premature Problems
11
![Page 12: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/12.jpg)
Cozen WayDrawley FarmsBuilt 2004
• Sinkholes formed• Non-standard structures• Poor pipe installation• Public safety and liability
concerns for the City
Common Premature Problems
12
![Page 13: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/13.jpg)
Clementine CourtProvidence PointeBuilt 2002
• Missing brick in catch basin• Sinkholes formed• Precast structures leaking• Presents a public safety
concern to the property owner
• Limited access to enter and repair system
• Shoring will be needed to protect the foundations of nearby homes
Common Premature Problems
13
![Page 14: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/14.jpg)
Common Premature Problems
Sahalee LaneClaiborne Woods SubdivisionBuilt 2000
• Sinkhole formed due to pipe being damaged (egged shaped and joints failed) during installation
• Pipe damage allowed backfill material to migrate away and created a sinkhole
• Shoring will be needed to protect the foundations of nearby homes
14
![Page 15: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/15.jpg)
Common Premature Problems
Astonboro DriveChastain ParcBuilt 2002
• Broken and cracked pipe• Road is settling and rutting• Potential cavities under the
road • Estimated $100,000 repair
15
![Page 16: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/16.jpg)
Common Premature Problems
Steele Creek LandingMallard LandingBuilt 2006• Broken pipes and separated
joints • Sinkholes formed• Pipe holding water• Estimated $500,000 repair
Note: Steele Creek Landing was presented to the City for a voluntary annexation consideration.
16
![Page 17: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/17.jpg)
Common Premature Problems
Oasis LaneBelmeade Green SubdivisionBuilt 2006
• Separated joints, broken pipe, poor compaction
• Sinkholes formed• Shoring will be needed to protect
the foundations of nearby homes• Estimated $250,000 repair costs
17
![Page 18: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/18.jpg)
Challenges (Correcting Problems on Existing Infrastructure)
• Inconveniencies to traffic and property owners
• Shoring houses, reconstruction of road infrastructure, restoring landscaping, additional costs
• Working around utility infrastructure (gas, communication, electric, poles, sewer, etc.)
• Estimated approximately $2M of the $10M annual Storm Water Budget is needed to repair premature failures
• Takes away from intent of program
Foundation Protection
18
Shoring is not installed during the development phase, but is required during repairs.
![Page 19: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/19.jpg)
What is Storm Water Doing on Our Projects
• Increased level of inspection • Increased training of inspection staff and
contractors• CCTV (pipe video) inspection after work is
complete and at end of warranty period• Longer warranty periods from contractor on
questionable infrastructure
19
![Page 20: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/20.jpg)
![Page 21: Premature Storm Drainage System Repairs and Replacement](https://reader030.vdocuments.us/reader030/viewer/2022012522/6195f2d2a822184c3576f889/html5/thumbnails/21.jpg)
The End