preliminaryestimate
TRANSCRIPT
-
8/12/2019 preliminaryestimate
1/22
TOPIC 1:
PRELIMINARY
ESTIMATES
-
8/12/2019 preliminaryestimate
2/22
DEFINATION AND IMPORTANCE
OF PRELIMINARY ESTIMATESDEFINATION
Defined as an activity in particular work to makepossible offer to execute task base on a stipulated sum
Technique to forecast the possible cost incurred for acertain building or construction project via a systematiccalculation employing certain method, prepare at earlystage of the project
Is a part of the cost planning process that is controllingof the project cost at the design stage before anydrawings are embarked upon.
-
8/12/2019 preliminaryestimate
3/22
USE OF THE PRELIMINARY
ESTIMATE METHOD
To ascertain the actual cost forecast of aproject.
Assist the client in knowing to what extent heneed to be financially committed to aparticular project
Estimated is also function as a design guidewhether the project to the allocation madeeither
-
8/12/2019 preliminaryestimate
4/22
Contd
If the estimate is higher that the client budgetfor that particular project, the following could
be carried out :-
The design could be altered to reduce thecost
Extra provisions are sought after orrequested from the client
The project is postponed or cancelled
-
8/12/2019 preliminaryestimate
5/22
Contd
If the estimate is low than the allocated sum,the following could be done
Accept the estimate
To modify the design and/or thespecifications to increase the estimateappropriate to the provision set aside.
-
8/12/2019 preliminaryestimate
6/22
-
8/12/2019 preliminaryestimate
7/22
METHOD WHEN IT IS USED NOTE
UNIT OF
MESUREMENT
UNIT Inception feasibility
Appropriate for projectthat have standard unitof accommodation, itscommonly used to
establish the cost limitfor public sectorproject
Cost/studentCost/classroomCost/bedCost/ chair
CUBIC Outline proposal
Used to calculate the
volume of air-conditioned space orspace which is givenmechanical ventilation
Cost/m3
FLOOR
AREA
Outline proposalUsed extensively, canbe used for almost all
types of building
Cost/m2
-
8/12/2019 preliminaryestimate
8/22
THE SELECTION OF THEMETHOD WILL DEPEND ON
The information and time to prepare theestimate
The experience of Quantity Surveyor
The total and type of cost data available
-
8/12/2019 preliminaryestimate
9/22
UNIT METHOD
This method is also referred to as cost according tobuilding function
Estimate the building cost base on the size depends
on the population unit
Example: the total number of student in a school,total number of bed in a hostel or hospital and etc.
Easier method but the most unrefined.
Total population can be obtained from the client orthe design team
-
8/12/2019 preliminaryestimate
10/22
USAGE
The cost estimate is obtained by multiplying thenumber of accommodation for a new building withthe cost per unit of accommodation based on a
suitable building
The current unit of accommodation can be obtainedby calculating from the sketch design or by
obtaining information from the client.
-
8/12/2019 preliminaryestimate
11/22
Example:
Estimate the total cost to build a mosque to house acongregation of 500 individuals.
From a suitable cost data, get the cost/ congregation of asimilar mosque that has been updated. Lets us say that the
cost is RM 1400.00/ congregation.
Total cost = Number of accommodation x cost/congregation
500 individuals x 1,400
= RM 7000,000.00
-
8/12/2019 preliminaryestimate
12/22
CUBIC METHOD
In Malaysia this method is seldom or almostnever used
Only in certain case, it is utilized
To calculate the space which is need to be air-conditioned
To calculate the space that needs mechanical
ventilation
-
8/12/2019 preliminaryestimate
13/22
USAGE
Measure the volume of the new building andits volume is then multiplied with the suitable
price rate per m3Unrelated works is to be volume must be
calculated separately
The volume of the building is calculated as
follows:Volume = length x width x height
-
8/12/2019 preliminaryestimate
14/22
i. Height of pitch rooffrom the top surface of the foundation tohalf apex / height of roof
ii. Height of flat roofFrom the top surface of foundation to 600mmabove the flat roof or parapet wall
(which is higher)
-
8/12/2019 preliminaryestimate
15/22
L
W
Flat roofPitch roof
-
8/12/2019 preliminaryestimate
16/22
Example
Estimate the total cost to build a 2-storey bungalow if theconstruction cost/m3 of a similar construction is RM550.00. estimate the construction cost base on
a) Pitch roof
b) Flat roof
-
8/12/2019 preliminaryestimate
17/22
20.00
10.00
1.00
3.50
3.50
1.50
-
8/12/2019 preliminaryestimate
18/22
a) Pitch roof
Building volume = 20.00 x 10.00 x [1.00 +2(3.50) + (1.50)]
=20.00 x 10.00 x 8.75
=1750m3
Total building cost = volume x cost/m3
=1750m3 x RM550.00
=RM962,500.00
-
8/12/2019 preliminaryestimate
19/22
b) Flat roof
Building volume = 20.00 x 10.00 x [1.00 +2(3.50) + 0.60]
=20.00 x 10.00 x 8.60
=1720m3
Total building cost = volume x cost/m3
=1720m3 x RM550.00=RM946,000.00
-
8/12/2019 preliminaryestimate
20/22
Floor area method
Make a preliminary estimate as most of the cost dataare kept or are available in this form
The measurement for GFA must be similar betweenthe new building and the analyzed building
Need to consider criteria in measurement of area
In the calculation the floor area of a building there areseveral criteria need to be taken
1. The actual area of the building
2. If the project offers a standard or different type ofaccommodation it is better for each to be priced separately
3. Unrelated work to the area, for example, external workmust be priced separately
-
8/12/2019 preliminaryestimate
21/22
Contd
The rate per m2 chosen must be current rate asbuilding cost often differ
The site, external works, condition of contract, thequantity and the quality of equipment and others thatrelated to the floor area must be calculated separately
It is clear and difficulty of this method lies inchoosing the appropriate rate, which requiresexperience, observation and familiarity toward varied
building types
-
8/12/2019 preliminaryestimate
22/22
USAGE
The floor area of a building to be erected. Only thebuilding used this floor area method. Other worksmay use other method like approximate quantity.
Total cost = area x cost/m2 gross floor area (GFA)
Area calculate the area of the building. Themeasurement method differs according to
practices
Cost/m2 GFA from similar building type andfunction