preliminaryestimate

Upload: rajan-ranjan

Post on 03-Jun-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 preliminaryestimate

    1/22

    TOPIC 1:

    PRELIMINARY

    ESTIMATES

  • 8/12/2019 preliminaryestimate

    2/22

    DEFINATION AND IMPORTANCE

    OF PRELIMINARY ESTIMATESDEFINATION

    Defined as an activity in particular work to makepossible offer to execute task base on a stipulated sum

    Technique to forecast the possible cost incurred for acertain building or construction project via a systematiccalculation employing certain method, prepare at earlystage of the project

    Is a part of the cost planning process that is controllingof the project cost at the design stage before anydrawings are embarked upon.

  • 8/12/2019 preliminaryestimate

    3/22

    USE OF THE PRELIMINARY

    ESTIMATE METHOD

    To ascertain the actual cost forecast of aproject.

    Assist the client in knowing to what extent heneed to be financially committed to aparticular project

    Estimated is also function as a design guidewhether the project to the allocation madeeither

  • 8/12/2019 preliminaryestimate

    4/22

    Contd

    If the estimate is higher that the client budgetfor that particular project, the following could

    be carried out :-

    The design could be altered to reduce thecost

    Extra provisions are sought after orrequested from the client

    The project is postponed or cancelled

  • 8/12/2019 preliminaryestimate

    5/22

    Contd

    If the estimate is low than the allocated sum,the following could be done

    Accept the estimate

    To modify the design and/or thespecifications to increase the estimateappropriate to the provision set aside.

  • 8/12/2019 preliminaryestimate

    6/22

  • 8/12/2019 preliminaryestimate

    7/22

    METHOD WHEN IT IS USED NOTE

    UNIT OF

    MESUREMENT

    UNIT Inception feasibility

    Appropriate for projectthat have standard unitof accommodation, itscommonly used to

    establish the cost limitfor public sectorproject

    Cost/studentCost/classroomCost/bedCost/ chair

    CUBIC Outline proposal

    Used to calculate the

    volume of air-conditioned space orspace which is givenmechanical ventilation

    Cost/m3

    FLOOR

    AREA

    Outline proposalUsed extensively, canbe used for almost all

    types of building

    Cost/m2

  • 8/12/2019 preliminaryestimate

    8/22

    THE SELECTION OF THEMETHOD WILL DEPEND ON

    The information and time to prepare theestimate

    The experience of Quantity Surveyor

    The total and type of cost data available

  • 8/12/2019 preliminaryestimate

    9/22

    UNIT METHOD

    This method is also referred to as cost according tobuilding function

    Estimate the building cost base on the size depends

    on the population unit

    Example: the total number of student in a school,total number of bed in a hostel or hospital and etc.

    Easier method but the most unrefined.

    Total population can be obtained from the client orthe design team

  • 8/12/2019 preliminaryestimate

    10/22

    USAGE

    The cost estimate is obtained by multiplying thenumber of accommodation for a new building withthe cost per unit of accommodation based on a

    suitable building

    The current unit of accommodation can be obtainedby calculating from the sketch design or by

    obtaining information from the client.

  • 8/12/2019 preliminaryestimate

    11/22

    Example:

    Estimate the total cost to build a mosque to house acongregation of 500 individuals.

    From a suitable cost data, get the cost/ congregation of asimilar mosque that has been updated. Lets us say that the

    cost is RM 1400.00/ congregation.

    Total cost = Number of accommodation x cost/congregation

    500 individuals x 1,400

    = RM 7000,000.00

  • 8/12/2019 preliminaryestimate

    12/22

    CUBIC METHOD

    In Malaysia this method is seldom or almostnever used

    Only in certain case, it is utilized

    To calculate the space which is need to be air-conditioned

    To calculate the space that needs mechanical

    ventilation

  • 8/12/2019 preliminaryestimate

    13/22

    USAGE

    Measure the volume of the new building andits volume is then multiplied with the suitable

    price rate per m3Unrelated works is to be volume must be

    calculated separately

    The volume of the building is calculated as

    follows:Volume = length x width x height

  • 8/12/2019 preliminaryestimate

    14/22

    i. Height of pitch rooffrom the top surface of the foundation tohalf apex / height of roof

    ii. Height of flat roofFrom the top surface of foundation to 600mmabove the flat roof or parapet wall

    (which is higher)

  • 8/12/2019 preliminaryestimate

    15/22

    L

    W

    Flat roofPitch roof

  • 8/12/2019 preliminaryestimate

    16/22

    Example

    Estimate the total cost to build a 2-storey bungalow if theconstruction cost/m3 of a similar construction is RM550.00. estimate the construction cost base on

    a) Pitch roof

    b) Flat roof

  • 8/12/2019 preliminaryestimate

    17/22

    20.00

    10.00

    1.00

    3.50

    3.50

    1.50

  • 8/12/2019 preliminaryestimate

    18/22

    a) Pitch roof

    Building volume = 20.00 x 10.00 x [1.00 +2(3.50) + (1.50)]

    =20.00 x 10.00 x 8.75

    =1750m3

    Total building cost = volume x cost/m3

    =1750m3 x RM550.00

    =RM962,500.00

  • 8/12/2019 preliminaryestimate

    19/22

    b) Flat roof

    Building volume = 20.00 x 10.00 x [1.00 +2(3.50) + 0.60]

    =20.00 x 10.00 x 8.60

    =1720m3

    Total building cost = volume x cost/m3

    =1720m3 x RM550.00=RM946,000.00

  • 8/12/2019 preliminaryestimate

    20/22

    Floor area method

    Make a preliminary estimate as most of the cost dataare kept or are available in this form

    The measurement for GFA must be similar betweenthe new building and the analyzed building

    Need to consider criteria in measurement of area

    In the calculation the floor area of a building there areseveral criteria need to be taken

    1. The actual area of the building

    2. If the project offers a standard or different type ofaccommodation it is better for each to be priced separately

    3. Unrelated work to the area, for example, external workmust be priced separately

  • 8/12/2019 preliminaryestimate

    21/22

    Contd

    The rate per m2 chosen must be current rate asbuilding cost often differ

    The site, external works, condition of contract, thequantity and the quality of equipment and others thatrelated to the floor area must be calculated separately

    It is clear and difficulty of this method lies inchoosing the appropriate rate, which requiresexperience, observation and familiarity toward varied

    building types

  • 8/12/2019 preliminaryestimate

    22/22

    USAGE

    The floor area of a building to be erected. Only thebuilding used this floor area method. Other worksmay use other method like approximate quantity.

    Total cost = area x cost/m2 gross floor area (GFA)

    Area calculate the area of the building. Themeasurement method differs according to

    practices

    Cost/m2 GFA from similar building type andfunction