preliminary estimate
TRANSCRIPT
TOPIC 1: PRELIMINARY ESTIMATES
DEFINATION AND IMPORTANCE OF PRELIMINARY ESTIMATES
DEFINATION Defined as an activity in particular work to make
possible offer to execute task base on a stipulated sum
Technique to forecast the possible cost incurred for a certain building or construction project via a systematic calculation employing certain method, prepare at early stage of the project
Is a part of the cost planning process that is controlling of the project cost at the design stage before any drawings are embarked upon.
USE OF THE PRELIMINARY ESTIMATE METHOD
To ascertain the actual cost forecast of a project.
Assist the client in knowing to what extent he need to be financially committed to a particular project
Estimated is also function as a design guide whether the project to the allocation made either
Cont’d If the estimate is higher that the client
budget for that particular project, the following could be carried out :-
The design could be altered to reduce the cost
Extra provisions are sought after or requested from the client
The project is postponed or cancelled
Cont’d If the estimate is low than the allocated
sum, the following could be done
Accept the estimate
To modify the design and/or the specifications to increase the estimate appropriate to the provision set aside.
METHOD FOR PRELIMINARY ESTIMATE
UNIT
CUBIC
FLOOR AREA
METHOD WHEN IT IS USED
NOTEUNIT OF
MESUREMENT
UNIT Inception feasibility
Appropriate for project that have standard unit of accommodation, its commonly used to establish the cost limit for public sector project
Cost/studentCost/classroomCost/bedCost/ chair
CUBIC Outline proposal
Used to calculate the volume of air-conditioned space or space which is given mechanical ventilation
Cost/m3
FLOOR AREA
Outline proposalUsed extensively, can be used for almost all types of building
Cost/m2
THE SELECTION OF THE METHOD WILL DEPEND ON The information and time to prepare
the estimate
The experience of Quantity Surveyor
The total and type of cost data available
UNIT METHOD This method is also referred to as ‘cost according
to building function’
Estimate the building cost base on the size depends on the population unit
Example: the total number of student in a school, total number of bed in a hostel or hospital and etc.
Easier method but the most unrefined.
Total population can be obtained from the client or the design team
USAGE The cost estimate is obtained by multiplying
the number of accommodation for a new building with the cost per unit of accommodation based on a suitable building
The current unit of accommodation can be obtained by calculating from the sketch design or by obtaining information from the client.
Example:Estimate the total cost to build a mosque to house a congregation of 500 individuals.From a suitable cost data, get the cost/ congregation of a similar mosque that has been updated. Lets us say that the cost is RM 1400.00/ congregation.
Total cost = Number of accommodation x cost/congregation
500 individuals x 1,400 = RM 7000,000.00
CUBIC METHOD
In Malaysia this method is seldom or almost never used
Only in certain case, it is utilized To calculate the space which is need to
be air-conditioned To calculate the space that needs
mechanical ventilation
USAGE
Measure the volume of the new building and its volume is then multiplied with the suitable price rate per m3
Unrelated works is to be volume must be calculated separately
The volume of the building is calculated as follows:
Volume = length x width x height
i. Height of pitch rooffrom the top surface of the foundation to half apex / height of roof
ii. Height of flat roofFrom the top surface of foundation to
600mm above the flat roof or parapet wall (which is higher)
L
W
Flat roofPitch roof
ExampleEstimate the total cost to build a 2-storey bungalow if the construction cost/m3 of a similar construction is RM 550.00. estimate the construction cost base on
a) Pitch roofb) Flat roof
20.00
10.00
1.00
3.50
3.50
1.50
a) Pitch roofBuilding volume = 20.00 x 10.00 x [1.00 +2(3.50) + ½ (1.50)]
=20.00 x 10.00 x 8.75 =1750m3
Total building cost = volume x cost/m3=1750m3 x RM550.00=RM962,500.00
b) Flat roof
Building volume = 20.00 x 10.00 x [1.00 +2(3.50) + 0.60]
=20.00 x 10.00 x 8.60 =1720m3
Total building cost = volume x cost/m3=1720m3 x RM550.00=RM946,000.00
Floor area method Make a preliminary estimate as most of the cost
data are kept or are available in this form The measurement for GFA must be similar between
the new building and the analyzed building Need to consider criteria in measurement of area
In the calculation the floor area of a building there are several criteria need to be taken 1. The actual area of the building2. If the project offers a standard or different type of
accommodation it is better for each to be priced separately
3. Unrelated work to the area, for example, external work must be priced separately
Cont’d The rate per m2 chosen must be current rate as
building cost often differ
The site, external works, condition of contract, the quantity and the quality of equipment and others that related to the floor area must be calculated separately
It is clear and difficulty of this method lies in choosing the appropriate rate, which requires experience, observation and familiarity toward varied building types
USAGE The floor area of a building to be erected. Only
the building used this floor area method. Other works may use other method like approximate quantity.
Total cost = area x cost/m2 gross floor area (GFA)
Area – calculate the area of the building. The measurement method differs according to practices
Cost/m2 GFA – from similar building type and function
EXAMPLEEstimate the cost of the building by referring to the plans given if the construction cost is RM 1,500/m2 25.00
8.00
10.00 3.00
15.00
5.00
25.00
10.00
10.00
7.00
5.00
Ground floor plan First floor plan
CONT’DFloor areaGround floor25.00 x 5.00 = 125.0010.00 x 3.00 = 30.00 5.00 x 7.00 = 35.00
190.00
First floor25.00 x 5.00 = 125.0010.00 x 3.00 = 30.00 155.00
345.00
Total cost = area x cost/m2 Gross Floor Area
= 1500.00 x 345.00 = RM 517,500.00
UNIT CUBIC FLOOR AREA
Fast and easy Easiest method to
obtain cost limit to prepare the monetary allocations for several years to come
No necessity for drawings
The estimate can be prepared quickly
The client and architect easily understand the concept of floor area. most work items are appropriately associated with the concept of floor area rather than the volume method
Cost data easily available as most of the data from previous project most utilize this method
ADVANTAGES
DISADVANTAGESUNIT CUBIC FLOOR AREA
An unrefined method and in accurate. Only suitable to provide and overall approximate estimate
Does not take into account changes to plan, number of storeys and other factors related to design
Unrelated work concerning unit of accommodation has to be calculated separately.
Does not take into account changes to plan, height, of storey and the overall height of the building
Unrelated work to the volume has to be calculated separately
Does not help architect in design work as it is difficult to predict or to know the effects of the changes to specifications, design, etc. to the cost per m3
Difficult to obtain similar cost data
Does not take into account changes to plan, height, of storey and the overall height of the building as these factors effect the building cost
Other work which are not related to the floor area must be calculate separately
Difficult to calculate and allocate the cost for different site conditions, quality of materials, condition of contract and etc.