precast concrete panels (pcp’s)
DESCRIPTION
Texas’ Use of Precast Concrete Stay-in-Place Forms for Bridge DecksTRANSCRIPT
-
1Texas Use of Precast ConcreteStay-in-Place Forms for Bridge
Decks
Brian D. Merrill, P.E.Texas Department of Transportation
Transverse Section
Precast Concrete Panels (PCPs)
4 CIP Concrete 4 PCP
-
2PCP Usage
Developed in 1963 Full scale use started in 1983 when a pay
item change went into effect and standard drawings were offered
Approximately 85% of all deck on stringers are built using this system
PCPs: How they work
Plans give details for full-depth CIP deck If PCP is authorized, PCP standard sheets (3
sheets inserted into plans) give all details for panel fabrication, panel placement, and reinforcing adjustments to CIP portion
-
3Typical Plan Detail for Full-Depth CIP Slab
PCP Standard Detail
-
41 1/21/4 Min
Panel Support Requirements
Advantages of Using PCPs
Speed Cost savings Safety Design
-
5PCP Advantage: Speed
Deck grading and forming can be completed in a few days
Placement of rebar takes half the time compared to full CIP deck
Reduced form removal (overhangs) time Can pour greater deck area in the same time
(PCPs take up half the deck volume)
PCP Advantage: Cost
Time = $$$ Form Setting Placement of Reinforcing Steel Less Time Working over Traffic Reduced Form Removal Time (overhangs) Lower Equipment Costs for Concrete
Placement Insurance
-
6PCP Advantage: Safety
Very stable in high winds (3000 lbs) Cannot fall between girders Only overhang forms need to be removed
PCP Advantage: Design
Prestressed Steel in Slab M+ Areas PCPs use 5000 psi concrete compared to
4000 psi for CIP concrete Excellent quality control on PCP fabrication
-
7Typical Plan Detail for Full-Depth CIP Slab
Design for Full-Depth CIP Slab
4000 psi Concrete, Grade 60 Steel 8 Thick Transverse Reinf: #5s @ 6 T&B Beam in Flexure Design: fs
-
8Design for PCPs
Standard details apply over the same span limits as the full-depth CIP slab (8.7)
M+ resisted by PCP/CIP composite section M- resisted by #5s @ 6 5000 psi concrete 3/8 Gr 270 Strands @ 6, mid-depth of 4
panel; stressed to 16.1 kips
Design for PCPs - Cont.
Panel tensile stress (ft) limited to 6f 'c Ultimate Flexural Capacity of PCP/CIP
Composite Slab (fsu) = (Panel Length)/2D + 2fse/3
#4 bars can be used for panels < 5 long Panels < 3.5 must use #4 bars Standards cover PCP placement on skews,
phased construction, & flared girders
-
9Note #3 bars
Limitations on PCPs
Curved Steel Plate Girders Widenings: not allowed in the bay adjacent
to existing structure Phased Construction: not allowed in the bay
adjacent to previous phase* Steel girders with narrow (
-
10
Standard Detail for Phased Construction
No Panel here
Stage I Stage II
Header
Stage I Stage II
Modified Detail to Allow PCPs for Phased Construction
-
11
PCPs: Keys to Success
Panel Fabrication Grading and Setting of Panels Concrete Placement
PCP Fabrication
3 Plants in Texas* Casting beds are 8 wide, 350 to 500 long Strands extend 3 on each side of panel 5000 psi concrete required but usually get
4000 psi in 14 hours using Type III cement Largest fabricator can produce up 300
panels a day
-
12
-
13
-
14
Grading and Setting PCPs
Critical operation: must ensure adequate depth of CIP and rebar cover
Must ensure that panel support conditions are met mortar
Must account for girder deflection differences between interior/exterior girders
Often requires regrading of deck profile(up to 2 overpour allowed)
-
15
-
16
-
17
1 1/21/4 Min
Panel Support Requirements
Differential Girder Deflections
50% 50%50% 25%25%
-
18
Concrete Placement
Panels must be wetted (SSD) prior to concrete placement
Vibration along girder lines is crucial
-
19
-
20
PCP Research
Test of Precast Prestressed Concrete Bridge Deck Panels 1963 In-house study
Study of In-Service Bridges Constructed with Prestressed Panel Sub-Decks, Project 145-1, 1970, Texas Transportation Institute (Texas A&M)
Development Length of Strands in Prestressed Panel Sub-Decks, Project 145-2, 1970, TTI
PCP Research - Cont.
Evaluation of a Prestressed Panel, Cast-In-Place Concrete Bridge, Project 145-3, 1972, TTI
Cyclic Load Tests of Composite Prestressed-Reinforced Concrete Panels, Project 145-4F, 1972, TTI
The Effect of Transfer Strand Extensions on the Behavior of Precast Panel Bridges, Project 303-1F, 1982, Center for Transportation Research (Univ. of Texas)
-
21
Research Findings
Used to develop current standard details Load transfer of PCP deck compared favorably to
full CIP deck PCP/CIP deck composite action with prestressed
girders was verified Panel support conditions were verified the precast panel deck was stronger, stiffer,
and more crack-resistant than a CIP deck.
Problems
Longitudinal Cracking Transverse Cracking Deck Thickness/Rebar Cover Grading & Yield
Texas has had relatively few problems using PCPs
-
22
Longitudinal Cracking Can reduce deck stiffness Cracks could expose M- steel to corrosive
elements Insufficient panel support (mortar) has
contributed to all major longitudinal cracking
Minor longitudinal cracking has been attributed to drying shrinkage of CIP concrete
-
23
-
24
2 1/2 CIP Slab(3 1/4 per plans)
1 +/-
Major LongitudinalCracking
Original Panel Bedding Material:Preformed Bituminous Fiber Material
-
25
New Panel Bedding Material:
High-Density ExtrudedPolystyrene Foam
ASTM C-578, Type VI40 psi*
Minor Longitudinal Cracking
-
26
Transverse Cracking
Attributed to drying shrinkage of CIP concrete
Not considered to be a significant problem
PCP PCP
CIP Conc.
Transverse Cracks
Roughened Surface
-
27
Grading and Yield
Panels can be difficult to grade if girder cambers vary widely - the high girder controls the grade
Yield (volume of concrete/square foot) can be affected if regrading is necessary
Conclusions
The PCP system is very popular with Texas contractors
Speed is the primary advantage realized by using the PCP system
The benefits of the PCP system far outweigh its limitations and the few negative consequences