pre requisites for project implementation
TRANSCRIPT
-
7/29/2019 Pre Requisites for Project Implementation
1/3
PRE-REQUISITES FOR SUCCESSFUL IMPLEMENTATION OF PROJECT
Successful Project Implementation
Successful implementation of theproject lies on effective project plan.
Based on the anticipated goals and objectives the project planning to be made
Problem formulation and Statement of the problem
The crux of the project lies in the problem formulation process. the project
team should have detailed understanding of the problem, scope intervention areas and
the out come of the project to be hypothesized
Project planning
Project planning: can be defined as
a scientific and systematic process, in which
logical linkages are clearly established, among
various element of projects
Project Budget
The project budgeting phase is in the project formulation phase. Two types of
budgets are to be made. The prior one is the cost category budget (materials,
administration, capital; expenditures etc) and the later is the activity budget. This
project budget is to calculate the cost of each project output.
Feasibility of the project
management appraisal
technical feasibility
financial feasibility
commercial appraisal environmental analysis
economic appraisal
Pre-requisites for successful implementation of
Adequate formulation
Cursory assessment of input requirement
Superficial field investigation
Slip shod method used for estimating cost and benefits
Omission of project linkages
Flawed judgment because of lack of experience and expertise
Deliberate over estimation of benefits and underestimation of benefits.Sound project organization
it is led by a competent leader who is accountable for project performance
the authority of the project leader and his team is commensurate with their
responsibility.
Adequate attention is given to the human side of the project system and
method is clearly defined
Proper implementation planning
develop a comprehensive plan for various activities like land acquisition,
tender evaluation, recruitment of personnel. Construction of building etc.
estimate meticulously the resource requirement (manpower, materials, moneyect) for each period to realize the time plan.
-
7/29/2019 Pre Requisites for Project Implementation
2/3
Define properly the inter linkages between activities of the project.
Specify cost standards.
Advance action
When the project appears prima facie to be viable and desirable, advance
action on the following activities may be initiated:
acquisition of land
securing essential clearances
identifying technical collaborators/consultants,
arranging for infrastructure facilities
preliminary design and engineering and
calling of tenders
Timely availability of funds
Once a project is approved, adequate funds must be made available to meet its
requirements as per the plan of implementation, it would be highly desirable if funds
are provided even before the final approval to initiate advance action. Piecemeal, ad-
hoc and niggardly allocation, with undue rigidities, can impair the maneuverability ofthe project team.
Judicious equipment tendering and procurement
to minimize time over- runs, it may appear that a turnkey contract has obvious
advantages. Since these contracts are likely to be bagged by the foreign
suppliers, when global tenders are floated, a very important question arises.
A judicious balance must be sought which Moderates the outflow of foreign
exchange and provides reasonable fillip to the development of indigenous
technology.
Better contract Management
The Competence and capability of all contractors must be ensured one weak
link can jeopardize timely performance of contract.
Proper discipline must be inculcated among contractors and suppliers by
insisting that they should develop realistic and detailed resource and time
plans which are congruent with the project plan.
Penalties which may be graduated must be imposed for failure to meet
contractual; obligations. Likewise incentives may be offered for good
performance. Help should be extended to contractors and suppliers when they
have genuine problems they should be regarded as partners in common
pursuit.
Project authorities must retain latitude on offload contracts ( Partially of
wholly) to other parties well in time where delays are anticipated.Effective Monitoring:
In order to keep a tab on the progress of the project, a system of monitoring
must be established. This helps in:
Anticipating deviation from implementation plan.
Analyzing immerging problem
Taking corrective action
It should focus sharply on the critical aspect of project implementation
It must lay more emphasis on physical milestones and not on financial targets.
It must be kept relatively simple. If made over complicated, it may lead to
redundant paper work and diversion of resources. Even worse, monitoring
-
7/29/2019 Pre Requisites for Project Implementation
3/3
may be viewed as an end in itself rather than as a means to implement the
project successfully.