pre-proposal for chittagong 2x660mw coal … 2x660mw cfpp project page no : 1 of 94 pre-proposal...
TRANSCRIPT
![Page 1: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/1.jpg)
Chittagong 2x660MW CFPP Project Page No : 1 of 94
Pre-Proposal
PRE-PROPOSAL FOR
Chittagong 2x660MW Coal-Fired
Power Plant Project
October 31, 2014
ORIGINAL
![Page 2: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/2.jpg)
Chittagong 2x660MW CFPP Project Page No : 2 of 94
Pre-Proposal
Pre-Proposal
PROJECT NAME : Chittagong(2x660MW) CFPP Project
Country : Bangladesh
OWNER : POSCO & BMTF Consortium
REV.
NO. DATE DESCRIPTION PREP'N CHECK REVIEW APPROVAL
REV.
NO. PREPARATIONCOMPANY PREPARATION CHECK REVIEW APPROVAL
This Document is the property of PE&C. Therefore, it shall not be released to
any third party without permission of an authorized personnel of the PE&C.
For Pre-Proposal
![Page 3: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/3.jpg)
Chittagong 2x660MW CFPP Project Page No : 3 of 94
Pre-Proposal
TABLE OF CONTENTS
1. INTRODUCTION ........................................................................................................................................ 6
1.1 BACKGROUND ....................................................................................................................................................................... 6
1.2 ECONOMIC OVERVIEW OF BANGLADESH ......................................................................................................................... 6
1.3 POWER SECTOR OF BANGLADESH ......................................................................................................................... 7
1.4 CHRONIC POWER PROBLEMS OF BANGLADESH ............................................................................................................. 8
2. CURRENT STATUS AND ISSUES OF IMPORTED COAL .................................................................... 10
2.1 THE ADVANTAGE OF COAL ............................................................................................................................................... 10
2.2 GLOBAL COAL DEMAND & SUPPLY ............................................................................................................................... 10
2.3 PRICE TRENDS ..................................................................................................................................................................... 12
2.4 THE FORECAST OF GLOBAL COAL PRICE ....................................................................................................................... 14
3. PROJECT OVERVIEW .............................................................................................................................. 15
3.1 PROJECT OVERVIEW ........................................................................................................................................................... 15
4. COST ESTIMATION ................................................................................................................................. 17
4.1 COST OF THE PROJECT ...................................................................................................................................................... 17
4.2 OPERATING AND MAINTENANCE EXPENSES.................................................................................................................. 17
4.3 FUEL COST ........................................................................................................................................................................... 19
4.4 TAXATION ............................................................................................................................................................................ 20
5. REVENUE ESTIMATION .......................................................................................................................... 21
5.1 REVENUE ANALYSIS ........................................................................................................................................................... 21
6. FINANCIAL ANALYSIS ............................................................................................................................ 24
6.1 THE BASIC CONDITIONS ................................................................................................................................................... 24
6.2 INFLATION RATE ................................................................................................................................................................. 24
6.3 FUNDING ............................................................................................................................................................................. 25
6.4 LOAN SCHEDULE AND INTEREST EXPENSES ................................................................................................................... 26
6.5 IRR, ROE ............................................................................................................................................................................ 26
7. SENSITIVITY ............................................................................................................................................. 28
7.1 RESULTS OF SENSITIVITY ................................................................................................................................................... 28
8. OUTLINE OF PLANT CONFIGURATION ............................................................................................... 17
9. SITE INFORMATION AND ENVIRONMENTAL REQUIREMENTS ..................................................... 30
![Page 4: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/4.jpg)
Chittagong 2x660MW CFPP Project Page No : 4 of 94
Pre-Proposal
9.1 PROPOSED SITE LOCATION ............................................................................................................................................... 30
9.2 REQUIRED AREA OF THE TOTAL POWER PLANT ........................................................................................................... 30
9.3 SITE LAYOUT ....................................................................................................................................................................... 30
9.4 ENVIRONMENTAL REQUIREMENTS ................................................................................................................................... 31
10. SCOPE OF SUPPLY .................................................................................................................................. 35
10.1 SCOPE OF WORKS AND SERVICES AS EPC CONTRACTOR’S RESPONSIBILITY .......................................................... 35
10.2 SCOPE OF WORKS AND SERVICES AS IPP DEVELOPER’S RESPONSIBILITY .................................................................. 42
10.3 OUT OF SCOPE OF WORKS TO BE PROVIDED BY OTHERS ........................................................................................... 42
11. DESIGN DESCRIPTION ........................................................................................................................... 43
11.1 TENTATIVE DESIGN CRITERIA ........................................................................................................................................... 43
11.2 EXPECTED PLANT PERFORMANCE .................................................................................................................................... 48
11.3 CODES AND STANDARDS .................................................................................................................................................. 48
11.4 SUBMISSION REQUIREMENTS ........................................................................................................................................... 51
11.5 BOILER AND FLUE GAS TREATMENT FACILITIES ............................................................................................................ 52
11.6 STEAM TURBINE AND AUXILIARIES .................................................................................................................................. 55
11.7 FEED WATER SYSTEM ......................................................................................................................................................... 58
11.8 COAL AND ASH HANDLING SYSTEM .............................................................................................................................. 60
11.9 COOLING WATER SYSTEM ................................................................................................................................................. 62
11.10 STACKS ............................................................................................................................................................................ 63
11.11 CIVIL WORKS ................................................................................................................................................................. 63
11.12 BUILDING LIST ................................................................................................................................................................ 75
11.13 ELECTRICAL EQUIPMENT ............................................................................................................................................... 76
11.14 INSTRUMENT AND CONTROL ...................................................................................................................................... 80
11.15 WATER AND WASTEWATER TREATMENT SYSTEM ................................................................................................... 84
11.16 FIREFIGHTING SYSTEM................................................................................................................................................... 88
11.17 HVAC SYSTEM .............................................................................................................................................................. 91
12. OPERATIONAL REQUIREMENTS ........................................................................................................... 93
12.1 GENERAL .............................................................................................................................................................................. 93
12.2 PLANT DUTY ....................................................................................................................................................................... 93
13. APPENDIX ................................................................................................................................................ 94
13.1 DIAGRAM OF TERMINAL POINTS ..................................................................................................................................... 94
13.2 HEAT BALANCE DIAGRAM ................................................................................................................................................ 94
13.3 WATER BALANCE DIAGRAM .............................................................................................................................................. 94
![Page 5: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/5.jpg)
Chittagong 2x660MW CFPP Project Page No : 5 of 94
Pre-Proposal
13.4 PLOT PLAN .......................................................................................................................................................................... 94
13.5 SINGLE LINE DIAGRAM ....................................................................................................................................................... 94
13.6 CONTROL SYSTEM CONFIGURATION ............................................................................................................................... 94
![Page 6: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/6.jpg)
Chittagong 2x660MW CFPP Project Page No : 6 of 94
Pre-Proposal
1. Introduction
1.1 Background
Bangladesh mainly uses gas-fired power generation utilizing domestic natural gas as its
major sources, and the future development plan for new power generation still focuses
on domestic natural gas as a main energy resource.
However, since the current domestic demand has increased rapidly and the production
or currently available domestic natural gas will face depletion in the near future, it is not
realistic to establish a policy that depends too heavily on domestic natural gas for the
development of a new long-term power generation plan.
Bangladesh has a limited generation capacity of approximately 5.5GW with a daily
availability of 4GW. The capacity is below the ever growing demand of the country,
which leads to frequent load shedding. More over Bangladesh electrification is only 47%,
with most of the supply limited to city needs. Also, it is expected that the on-going
liberalization of the country’s economic policy would accelerate the industrial growth,
which would further increase the demand for power. Although several new power
projects have been identified with a view to bridge the gap between demand and
availability, only a few could be taken up for implementation, due to financial and other
constraints. Lack of availability of sufficient electric power has always been one of the
greatest deterrents to the growth of industry in Bangladesh.
Bangladesh uses indigenous natural gas to generate about 87% of its power. Other
generations are hydro, coal and liquid fuel based. Renewable energy has just started
making a small contribution.
To mitigate such a gap between domestic power demand and supply in Bangladesh
and diversify the power source relied on natural gas, POSCO & BMTF consortium
propose to build the large-sized imported coal-fired high efficiency power plant with this
proposal hereto.
1.2 Economic Overview of Bangladesh
In real terms Bangladesh's economy has grown 5.8% per year since 1996 despite
political instability, poor infrastructure, corruption, insufficient power supplies, and slow
implementation of economic reforms. Bangladesh remains a poor, overpopulated, and
inefficiently-governed nation. Although more than half of GDP is generated through the
service sector, 45% of Bangladeshis are employed in the agriculture sector with rice as
the single-most-important product. Bangladesh's growth was resilient during the 2008-
![Page 7: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/7.jpg)
Chittagong 2x660MW CFPP Project Page No : 7 of 94
Pre-Proposal
09 global financial crisis and recession. Garment exports, totaling $12.3 billion in FY09
and remittances from overseas Bangladeshis, totaling $11 billion in FY10, accounted for
almost 12% of GDP.
<Basic Economic Facts (FY 2012)> Item Content
GDP (purchasing power parity) $305.5 billion (2012 est.)
GDP (official exchange rate) $118.7 billion
GDP - real growth rate 6.1%
GDP - per capita (PPP) $2,000
GDP - composition by sector agriculture: 17.3%, industry: 28.6%, services: 54.1%
Unemployment rate 5%
Exchange rates taka (BDT) per US dollar - 82.17
Public debt 31.7% of GDP (2012 est.)
Stock of direct foreign investment
- at home: $6.64 billion (31 December 2012 est.)
Stock of direct foreign investment
- abroad: $108 million (31 December 2012 est.)
(Source: Central Intelligence Agency)
1.3 POWER SECTOR OF BANGLADESH
Bangladesh has shown tremendous growth in recent years. A booming economic
growth, rapid urbanization and increased industrialization and development have
increased the country's demand for electricity. Presently, 60% of the total population
(including renewable energy) has access to electricity and per capita generation is 292
kWh, which is very low compared to other developing countries. Noncommercial energy
sources, such as wood fuel, animal waste, and crop residues, are estimated to account
for over half of the country's energy consumption. Bangladesh has small reserves of oil
and coal, but very large natural gas resources. Commercial energy consumption is
mostly natural gas around 66%, followed by oil, hydropower and coal.
Electricity is the major source of energy for country's most of the economic activities.
Bangladesh's installed electric generation capacity was 6361 MW in 2011; only three-
fourth of which is considered to be ‘available’. Only 49% of the population has access to
electricity with a per capita availability of 136 kWh per annum. Overall, the country's
generation plants have been unable to meet system demand over the past decade. As
of 2011, 79 natural gas wells are present in the 23 operational gas fields which produce
over 2000 millions of cubic feet of gas per day (MMCFD). It is well short of over 2500
MMCFD that is demanded, a number which is growing by around 7% each year. In fact,
![Page 8: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/8.jpg)
Chittagong 2x660MW CFPP Project Page No : 8 of 94
Pre-Proposal
more than three-quarters of the nation’s commercial energy demand is being met by
natural gas. This influential sector caters for around 40% of the power plant feedstock,
17% of industries, 15% captive power, 11% for domestic and household usage, another
11% for fertilizers, 5% in Compressed Natural Gas (CNG) activities and 1% for
commercial and agricultural uses.
<Bangladesh Power sector at a Glance (FY 2012)>
Item Content
Generation Capacity 8525 MW
Present Demand 7500 MW
Present Generation 5600-6350 MW
Highest Generation 6350 MW ( August 04, 2012)
Per Capita Generation 292 kWh
Transmission line 8949 KM
Distribution Line 2,81,123 KM
Total consumers 13.99 Million
Access to Electricity 60%
Electricity Growth 12 % (Since 2011)
(Source: Power Division, Ministry of Power, Energy & Mineral Resources)
1.4 Chronic Power Problems of Bangladesh
Problems in the Bangladesh's electric power sector include corruption in administration,
high system losses, and delays in completion of new plants, low plant efficiencies,
erratic power supply, electricity theft, blackouts, and shortages of funds for power plant
maintenance. A USAID report on energy conditions of Bangladesh states that Energy in
Bangladesh is indispensable for almost all economic activities, ranging from farm
irrigation to the manufacture of goods by small and micro enterprises. Importantly,
energy is also indispensable for attaining the Millennium Development Goals (MDGs)
for Bangladesh. Although endowed with natural gas resources and some good quality
coal deposits, Bangladesh continues to reel from widespread power shortages due to a
lack of investment in power generation and the inadequate distribution of infrastructure.
While there has been some improvement in generation capacity in the recent past. The
country can currently generate about 4500 megawatts (MW), while peak demand can
be as high as 6000 MW. With only 49% of Bangladeshis having access to electricity,
the per capita energy use is only 180 Kilowatt-hours (kwh), which is one of the lowest in
the region.
![Page 9: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/9.jpg)
Chittagong 2x660MW CFPP Project Page No : 9 of 94
Pre-Proposal
Nevertheless, the country desires to make electricity available to all by 2021. People in
rural areas suffer more than those in urban areas from low access to electricity. Even
those who have electricity experience frequent outages and poor quality power. In
generating and distributing electricity, the failure to adequately manage the load leads to
extensive load shedding which results in severe disruption in the industrial production
and other economic activities. A recent survey reveals that power outages result in a
loss of industrial output worth $1 billion a year which reduces the GDP growth by about
half a percentage point in Bangladesh. A major hurdle in efficiently delivering power is
caused by the inefficient distribution system. It is estimated that the total transmission
and distribution losses in Bangladesh amount to one-third of the total generation, the
value of which is equal to US $247 million per year.
![Page 10: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/10.jpg)
Chittagong 2x660MW CFPP Project Page No : 10 of 94
Pre-Proposal
2. CURRENT STATUS AND ISSUES OF IMPORTED COAL
2.1 The advantage of Coal
The world’s coal reserves are extraordinarily large and widely dispersed, with proved
reserves of 860 billion tones. Coal is safe and easy to transport, and it can be readily
stored. Reflecting these attributes, as well as the reserves base of developing
economies including China and India, the use of coal continues to grow strongly
relative to other fossil fuels.
As per the report of World Coal Association, over the past 30 years, the amount of
electricity produced from coal globally has more than tripled. This is mainly due to the
relatively low cost of building and running coal-fired power plants. The overall cost of
generating electricity is one of the most important factors determining the choice of
technology for new power generation. This is not only true in developing countries
where universal access to energy services is still a challenge, but also in the
established economies where electricity prices are an important variable for the
standard of living of many households. According to studies by the European
Commission, MIT, and the US Congressional Budget Office, coal power plants provide
electricity at a lower cost than nuclear or gas plants. This is also confirmed by levelised
generation cost studies, such as the one carried out regularly by the International
Energy Agency (IEA), which takes account of all the costs over the power plant lifetime.
According to IEA statistics, coal-based electricity is, on average, 7% cheaper than gas
and around 19% cheaper than nuclear.
The advantage of coal is even greater in comparison to renewable energy. IEA and
European Commission studies show that onshore wind costs between US$50 and
US$156 per MWh and solar photovoltaics between US$226 to US$2031. In certain
locations hydro resources can produce electricity at a cost comparable to coal,
however estimates vary greatly according to geographic conditions and the final price
can be as high as US$240 and US$262 per MWh. In comparison, electricity from coal
costs between US$56 to US$82 per MWh.
2.2 Global Coal Demand & Supply
2.2.1 Global Coal Demand
Since 2000, global coal consumption has grown faster than any other fuel.
According to the “World Energy Outlook 2011” by IEA, the 10-year average of
world coal consumption was 4.6% and it grew by 5.4% in 2011, while both China
![Page 11: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/11.jpg)
Chittagong 2x660MW CFPP Project Page No : 11 of 94
Pre-Proposal
and India increased coal consumption by over 9%. Coal accounted for 30.3% of
world energy consumption in 2011 and its share is now over 70% in China and
nearly 53% in India. Coal consumption in China approached half (49.4%) of
global coal consumption in 2011, and India about 8%.
The following graph shows the result of world coal demand through 2010 and the
IEA’s prediction until 2035. Predicted scenario presented in the World Energy
Outlook shows three national approaches towards climate change, which are
Current Policies Scenario, New Policies Scenario, and the 450 Scenario. New
Policies Scenario is a scenario that takes account of broad policy commitments
and plans that have been announced by countries, including national pledges to
reduce greenhouse-gas emissions and plans to phase out fossil-energy subsidies.
450 Scenario is a scenario that sets out an energy pathway consistent with the
goal of limiting the global increase in temperature to 2°C by limiting concentration
of greenhouse gases in the atmosphere to around 450 parts per million of CO2.
In terms of future demand trends, the global coal demand is expected to increase
by 1.9% per annum growth rate from 4.7 billion tones in 2009 to 7.7 billion tones
in 2035 under the current policy scenario. Even under the new policy scenario7,
the demand is expected to remain unchanged since2020, but reach 5.9 billion
tones in 2035.
(Source: IEA World Energy Outlook 2011)
Coal demand has been increasing rapidly since 2002 and coal price has been
rising as a result. The period of stable demand was of stable coal prices also but
in situations where rapidly increasing coal demand in non-OECD countries in
![Page 12: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/12.jpg)
Chittagong 2x660MW CFPP Project Page No : 12 of 94
Pre-Proposal
recent years, tight supply has caused coal prices to increase and uncompetitive
coal resources will allow the mining of coal and an increase in coal supply as the
result. Therefore, the future price of coal is expected to rise until stabilizing the
balance between supply and demand.
2.2.2 Global Coal Production
Countries with a higher export volume of coal are Indonesia, Australia, and then
Russia. In high-volume production countries such as China, the United States
and India, coal is essentially devoted to domestic consumption and exports are
minimal. China has recently become a net importer.
<Countries with a Higher Export Volume of Coal>
(Unit: Million ton per year)
Country Export (Million t per year)
Indonesia 383
Australia 301
Russia 134
USA 114
Colombia 828
South Africa 74
Canada 35
(Sources: BP, IEA, World Steel Association, WEC 2012)
2.3 Price Trends
Australian thermal coal price index, until around 2003, had remained at about $20 ~ $30
per ton, but began to rise from around 2004 with similar trends in other energy prices, and
reached around $180 per ton before the financial crisis in 2008. After that, the coal price
index fell to about $60 per ton due to weak demand, and then recovered due to the
expansion of China’s coal imports. Coal prices in 2010 due to a slowdown in production
caused by heavy rain in Australia in January have risen to $120 per ton.
![Page 13: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/13.jpg)
Chittagong 2x660MW CFPP Project Page No : 13 of 94
Pre-Proposal
-40.00%
-30.00%
-20.00%
-10.00%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
0
50
100
150
200
250
Sep-03
Mar-04
Sep-04
Mar-05
Sep-05
Mar-06
Sep-06
Mar-07
Sep-07
Mar-08
Sep-08
Mar-09
Sep-09
Mar-10
Sep-10
Mar-11
Sep-11
Mar-12
Sep-12
Mar-13
Price Change
0
50
100
150
Jan-…
Apr-…
Jul-09
Oct-…
Jan-…
Apr-…
Jul-10
Oct-…
Jan-…
Apr-…
Jul-11
Oct-…
Jan-…
Apr-…
Jul-12
Oct-…
Jan-…
Apr-…
Jul-13
Indonesian Coal Price Reference Australian Coal Price
The average Australian coal price of recent 10 years is about $86 per ton and the 5 years
average increased to about $103 per ton mostly due to the expansion of China’s coal
imports.
(Source: World Bank, 2013)
This price is considered to be one indicator in the contracts between other Asian
consumers such as South Korea, Taiwan and China and suppliers, because Indonesian
coal price trends have a similar trend with the Australian coal price. The reference price is
also considered to be an indicator in the negotiation of contracts of Indonesian coal exports.
The Indonesian coal price seems to have remained at a constant difference to the
Australian coal price due to a quality gap. But it should be noted that China and India has
increased the import of less middle or low-grade coal and so the Indonesian coal price
advantage may be affected by trends in such importers. The following graph indicates the
Indonesian coal price (HBA) that shows similar trends to Australian coal price. It is the price
that the government of Indonesia has been publishing a monthly since January 2009 to be
used by coal producers for all spot and term contracts. It is on a rising trend since
November 2012, but lost its way to reach US$ 100 per ton since April.
(Source: Ministry of Energy & Mineral Resources of Indonesia, 2013)
![Page 14: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/14.jpg)
Chittagong 2x660MW CFPP Project Page No : 14 of 94
Pre-Proposal
2.4 The Forecast of Global Coal Price
Long-term coal price scenario of IEA in World Energy Outlook 2011 said that the
current policy scenario assumes $110 per ton of coal import price of the OECD.
Moreover, in the long-term coal price forecast financial institutions are assumed to be
approximately from $ 80 to $100 per ton units in general.
< Long-term Coal Price Scenario for OECD Countries>
(Unit: USD per ton)
Current Policies Scenario New Policies Scenario
2015 2020 2025 2030 2035 2015 2020 2025 2030 2035
104.6 109.0 112.8 115.9 118.4 103.7 106.3 108.1 109.3 110.0
(Source: IEA World Energy Outlook 2011, Real terms, 2010 prices)
However, the following graph indicates World Bank’s expectation of the Australian Coal
price, and it shows a little gap with IEA’s.
(Unit: per ton)
Coal 2013 2014 2015 2016 2017 2018 2019 2020 2025
Australian 90 91 90 91 91.9 92.9 93.9 94.9 100
(Source: World Bank Commodity Forecast Price data, July 2013)
![Page 15: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/15.jpg)
Chittagong 2x660MW CFPP Project Page No : 15 of 94
Pre-Proposal
3. PROJECT OVERVIEW
3.1 Project Overview
3.1.1 Background of the project
This project is promoted as part of BPDA’s (Bangladesh Power Development
Board, 2011) a future power plant construction plans, Bangladesh Plan are as
follows:
No Description Capacity(MW) Probable Location(s)
1 Domestic Coal 11,250 North West Region at Mine Mouth
2 Imported Coal 8,400 Chittagong and Khulna
3 Domestic gas/LNG 8,850 Near Load Centers
4 Nuclear 4,000 Ruppur
5 Regional Grid 3,500 Bahrampur - Bheramara, Agartola -
Comilla, Silchar - Fenchuganj, Purnia-Bogra, Myanmar - Chittagong
6 Others 2,700 Near Load Centers
Total 35 38,700
(Source: BPDA(An Overview of Power Sector of Bangladesh, 2011)
![Page 16: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/16.jpg)
Chittagong 2x660MW CFPP Project Page No : 16 of 94
Pre-Proposal
The prime objective of this project is to avail 1,320 MW electricity to the people of
Bangladesh within the shortest possible time probably 5 years or less and of
under the budget using world's best EPC. The average Bengali only uses 252
KWH per capita, while this ratio is 561 KWH in India and 12,900 KWH in USA.
We would like to improve the life of people in Bangladesh and get them double
the amount they have now through this project. The other objectives of this
project are to look at the best way to go for the workers and the country and to
make it number 1 employer in Bangladesh by giving employees the following:
All advancement to the employees
Plant completely running by only Bengals in 5 years
Giving all the employees a free hot lunch program
Free medical clinic for all the employees and their families
ISO Training for all employees (ISO9001 is an internationally recognized
Quality Management System)
High School and College courses given free to all employees
Better than average pay and retirement program
Plus much more
3.1.2 Site
This project will be built on the Bay of Bengal at Chittagong location, Bangladesh.
The port of Chittagong is the principle port of the People’s Republic of
Bangladesh. It is situated on the southern area at Matarbari island.
3.1.3 Project structure
The investment structure of the project is as follows:
POSCO is scheduled to participate as a major shareholder and also will perform
EPC work. In addition, foreign investors are reviewing investment.
![Page 17: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/17.jpg)
Chittagong 2x660MW CFPP Project Page No : 17 of 94
Pre-Proposal
4. COST ESTIMATION
4.1 Cost of the Project
4.1.1 Estimated Total- Project-cost
The estimated total investment for project is as follows:
(Unit: Million USD)
Item Amount Remark
EPC EPC 1,740
Other EPC 233
Incidental Financing Fees 69
Total Project Cost 2,042
Interest during construction 306
Total Investment 2,349
In addition, the level of the reflected financial fees for project financing as follows:
Item Content
Financing Fees
Management Fee 2% of total loan
Agent Fee(Unit: USD 1,000) 50
Commitment Fee 0.15% of undrawdown balance
4.1.2 Estimates of annual total investment
Annual construction schedule provided by POSCO and cumulative EPC schedule are
12.6% for 1st year, 32.4% for 2nd year, 55.8% for 3rd year, 76.8% for 4th year 92.8%
for 5th year and 5.5th should be 100.0%.
Item 2015 2016 2017 2018 2019 2020
Total Project Cost 297 464 514 407 263 98
Interest during construction - - 35 88 115 69
Total Investment 297 464 549 494 377 167
4.2 Operating and Maintenance Expenses
4.2.1 Basic assumption
![Page 18: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/18.jpg)
Chittagong 2x660MW CFPP Project Page No : 18 of 94
Pre-Proposal
O&M costs would be divided into fixed costs and variable costs. Fixed costs
would compose of O&M advisory cost, maintenance cost, land lease fees etc.
and variable costs would compose of maintenance cost, other costs.
Since O&M costs are not generally exceed 1 cent per kWh, we assume 0.55
cents per kWh. This cost is same level when converting to kWh from the
Reference Escalable Capacity Price (RECP), Reference Variable O & M Price in
the Reference.
In addition, the following figure shows the mapping of reference price and O&M
costs in this analysis.
Item Calculated Amount Total Amount (USD 1,000)
Escalable Capacity Price USD 0.00125 per kWh 284
Reference Variable O&M Price USD 0.00425 per kWh 963
Sub total USD 0.0055 per kWh 1,247
Fixed O&M cost USD 0.7745 per kW(Month) 284
Variable O&M cost USD 0.00425 per kWh 963
Sub total 1,247
![Page 19: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/19.jpg)
Chittagong 2x660MW CFPP Project Page No : 19 of 94
Pre-Proposal
4.3 Fuel Cost
4.3.1 Basic assumption
1) Fuel Option
We compared the two types of coal specification and selected one for this
project.
Item GAD5400 GAD5600(GAR5000)
Gross Calorific Value (ADB) 5,400 5,600
Gross Calorific Value (ARB) 4,100 5,000
Total Moisture (ARB) 38% 26%
Inherent Moisture (ADB) 17approx 14approx
Ash (ADB) 7% 10%
Volatile Matter (ADB) 43approx 43approx
Fixed Carbon (ADB) By Difference 33%
Total Sulphur (ADB) 0.8% 1.0%
HGI 60 50
Size 0-50mm 90% 90%
Selection Ⅹ O
The result of comparison is GAD5400 cheaper than GAD5600, however
considering ARB Calorific Value after removing moisture GAD5600 has more
economical value the GAD5400.
Therefore, for analyzing the feasibility, assumed GAD5600 (≒ GAR 5000)
conducted as the fuel.
2) Main assumption
The coal price is assumed USD 100 per ton and this includes the coal price
Daewoo international supply and transportation cost.
Especially, the fuel cost is estimated considering the port for coal imports is
yet constructed so the coal transportation cost expected to be high.
Item Content Amount Remark
Coal
Quantity 327,317 ton per every month Plant capacity factor of 84.6% is considered.
Loading port Samarinda anchorage, East Kalimantan
Price USD 100 per ton Include Carry cost
![Page 20: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/20.jpg)
Chittagong 2x660MW CFPP Project Page No : 20 of 94
Pre-Proposal
4.4 Taxation
4.4.1 Taxation and duties in Bangladesh
Taxations and duties related to power business are VAT and custom duty for
imported goods, insurance on product import, VAT for consumption, and
corporate tax. Tax rates are as follows.
Items Custom Duty General VAT VAT on electric
power consumption Corporate Tax
(Under Govt. List)
Tax rates 0%, 3%, 5%, 12%,
or 25%. 15% 5% 27.5%
Applied Exemption Exemption Exemption 27.5%
(Source: NBR, the central authority for tax administration in Bangladesh)
As per PPA, The Company shall be exempt from any imposition of Taxes on the
sale of Dependable Capacity or Net Energy Output to BPDB under this
Agreement. And, corporate tax rate assumed 27.5%.
4.4.2 Tax holiday
As per PPA, where the Company maintains its existence as a company
organized under the Laws of Bangladesh operating exclusively as a power
generation company, the Company shall, commencing on the Commercial
Operations Date and continuing until the fifteenth (15th) anniversary of the
Commercial Operations Date, be exempt from taxation or withholding tax in
Bangladesh on its income from the sale of Dependable Capacity and Net Energy
Output.(or on any payments received by the Company in lieu thereof).
However, according to the current income tax law (2012-2013, national board of
revenue), there is no tax holiday regulation related to power generation.
Since the tax incentive to power generation is uncertain, we assume that our
company will not be exempted from tax and 27.5% tax will be charged.
<Compare of Tax holiday regulation>
Regulation Details
PPA Exempt from any imposition of Taxes on the sale of Dependable Capacity or Net Energy Output
2011~2012 - Before June 30, 2013 : exempt from tax for 15 years
- From July, 2013: will exempt from tax for 10 years subject to certain limits and conditions.
2012~2013 Not Mentioned
![Page 21: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/21.jpg)
Chittagong 2x660MW CFPP Project Page No : 21 of 94
Pre-Proposal
5. REVENUE ESTIMATION
5.1 Revenue Analysis
5.1.1 Result of Tariff calculation
Item Detail Remark
Levelized Tariff 9.75 US cents /kWh
Reference Capacity Price
RNECP 36.5691 USD per kW-Month
At COD
RECP 0.7745 USD per kW-Month
Reference Energy Price
RVOMP 0.00425 USD per kWh
At COD
Fuel Price 0.04334 USD per kWh
1) Levelized Tariff
Levelized Tariff Charge in US cents/kWh can be calculated in two steps:
a. First, calculate the net present value (NPV) in US cents/kWh of the
Reference Tariffs for all the Contract Years by discounting each of the annual
Reference Tariffs to the beginning of the first Contract Year by using the
discount rate of 12%; and
b. Then, calculate the Levelized Tariff Charge in US cents/kWh that can result
in the same NPV as calculated above for the same discount rate (12%).
2) Reference Capacity Price
The Reference Capacity Price component of the Reference Tariff will be
subdivided in three parts, each payable for one (1) kW of available
Dependable Capacity (DC) in the relevant month:
i) the Reference Non-Escalable Capacity Price or RNECP, expressed in
Dollar per Kw per month, to cover costs of debt servicing, return of equity and
return on equity;
ii) the Reference Foreign Escalable Capacity Price or RECP (US), expressed
in Dollar per kW per month, to cover the fixed costs of operation and
maintenance of the Facility denominated in foreign currencies; and
iii) the Reference Local Escalable Capacity Price or RECP (Tk), expressed in
Taka per kW per month, to cover the fixed costs of operation and
maintenance of the Facility denominated in local currency.
![Page 22: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/22.jpg)
Chittagong 2x660MW CFPP Project Page No : 22 of 94
Pre-Proposal
3) Reference Energy Price
The Reference Energy Price component of the Reference Tariff will be
subdivided in three parts, each payable for one (1) kWh of Net Energy Output
(NEO) in the relevant month:
i) The Reference Foreign Variable Operation and Maintenance Price or
RVOMP(US), expressed in Dollar per kWh, to cover variable costs of
operation and maintenance of the Facility denominated in foreign currencies;
ii) The Reference Local Variable Operation and Maintenance Price or
RVOMP(Tk), expressed in Taka per kWh, to cover variable costs of operation
and maintenance of the Facility denominated in local currency ; and
iii) The Reference Fuel Price, payable by BPDB for the Fuel consumed during
operation of the Facility based on the Reference Heat Rates.
4) Constraints on Tariff Charges
Tariff Charges (i.e. Reference Tariff) and components thereof (except as may
result from indexation allowed in the PPA) shall be subject to following
limitations and constraints:
a. Total Reference Tariff and each of its components should be greater than
zero for each Contract Year.
b. Each of the components RECP(US), RECP(Tk), RVOMP(US) and
RVOMP(Tk) must be constant or same across all the Contract Years.
c. Reference Heat Rates quoted for various plant load factors at the
Reference Site Conditions should remain same for the respective load factors
for each Contract Year.
Bidder should account for the heat rate degradation over the Term when
establishing the Reference Heat Rates.
d. Total Reference Tariff in US cents /kWh for the first Contract Year shall not
exceed 111% of the Levelized Tariff Charge.
e. Total Reference Tariff in US cents/kWh for any Contract Year other than
the first Contract Year shall not exceed 110% of the Levelized Tariff Charge.
f. Total Reference Tariff in Taka/kWh levelized over the first ten Agreement
Years (calculated in the similar manner as the Levelized Tariff Charge, except
that the calculation shall be limited to first ten Agreement Years) shall not
exceed 108% of the Levelized Tariff Charge.
g. Escalable Component of the Capacity Price shall not exceed 20% of the
total Capacity Price for any Contract Year and in aggregate. (For the purpose
![Page 23: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/23.jpg)
Chittagong 2x660MW CFPP Project Page No : 23 of 94
Pre-Proposal
of expressing total Reference Tariff in US cents/kWh for any Contract Year,
Reference Capacity Price shall be expressed in US cents/kWh by assuming
generation of Net Energy Output during 8760 x 0.846 hours at Contracted
Facility Capacity for the Contract Year.)
<Table of Schedule(Reference Price)>
Year
Reference Capacity Price
Reference Capacity
Price
Reference Energy Price Fuel Cost
(Included Inland Trans. Cost)
Energy Price
Total Reference
Tariff
Non-Escalable Capacity
Price
Escalable Capacity
Price
Escalable Capacity
Price
Variable O&M Price
Variable O&M Price
USD/kW -Month
USD/kW -Month
Tk./kW -Month
USD/ kWh
USD/ kWh
Tk/ kWh
USD/ kWh
USD/ kWh
USD/ kWh
RNECPn
RECP(US)n
RECP(TK)n
RCPn RVOMP
n RVOMP
n 0 REPn RTn
1 2 3 4 5 6 7 9 10
1 36.5691 0.2003 45.9388 0.0605 0.002 0.18 0.0433 0.0476 10.8054
2 35.4355 0.2003 45.9388 0.0586 0.002 0.18 0.0433 0.0476 10.6218
3 34.3370 0.2003 45.9388 0.0569 0.002 0.18 0.0433 0.0476 10.4439
4 33.2725 0.2003 45.9388 0.0551 0.002 0.18 0.0433 0.0476 10.2716
5 32.2411 0.2003 45.9388 0.0535 0.002 0.18 0.0433 0.0476 10.1046
6 31.2416 0.2003 45.9388 0.0518 0.002 0.18 0.0433 0.0476 9.9427
7 30.2731 0.2003 45.9388 0.0503 0.002 0.18 0.0433 0.0476 9.7859
8 29.3347 0.2003 45.9388 0.0488 0.002 0.18 0.0433 0.0476 9.6339
9 28.4253 0.2003 45.9388 0.0473 0.002 0.18 0.0433 0.0476 9.4867
10 27.5441 0.2003 45.9388 0.0459 0.002 0.18 0.0433 0.0476 9.3440
11 26.6902 0.2003 45.9388 0.0445 0.002 0.18 0.0433 0.0476 9.2058
12 25.8628 0.2003 45.9388 0.0431 0.002 0.18 0.0433 0.0476 9.0718
13 25.0611 0.2003 45.9388 0.0418 0.002 0.18 0.0433 0.0476 8.9420
14 24.2842 0.2003 45.9388 0.0406 0.002 0.18 0.0433 0.0476 8.8162
15 23.5314 0.2003 45.9388 0.0394 0.002 0.18 0.0433 0.0476 8.6943
16 22.8019 0.2003 45.9388 0.0382 0.002 0.18 0.0433 0.0476 8.5761
17 22.0950 0.2003 45.9388 0.0370 0.002 0.18 0.0433 0.0476 8.4617
18 21.4101 0.2003 45.9388 0.0359 0.002 0.18 0.0433 0.0476 8.3508
19 20.7464 0.2003 45.9388 0.0348 0.002 0.18 0.0433 0.0476 8.2433
20 20.1032 0.2003 45.9388 0.0338 0.002 0.18 0.0433 0.0476 8.1392
21 19.4800 0.2003 45.9388 0.0328 0.002 0.18 0.0433 0.0476 8.0383
22 18.8762 0.2003 45.9388 0.0318 0.002 0.18 0.0433 0.0476 7.9405
23 18.2910 0.2003 45.9388 0.0309 0.002 0.18 0.0433 0.0476 7.8457
24 17.7240 0.2003 45.9388 0.0300 0.002 0.18 0.0433 0.0476 7.7539
25 17.1745 0.2003 45.9388 0.0291 0.002 0.18 0.0433 0.0476 7.6650
Levelized 30.0513 0.2003 45.9388 0.0499 0.002 0.18 0.0433 0.0476 9.7500
![Page 24: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/24.jpg)
Chittagong 2x660MW CFPP Project Page No : 24 of 94
Pre-Proposal
6. FINANCIAL ANALYSIS
6.1 The Basic Conditions
6.1.1 Key factors
Applied key factors, when performed analyzing, are as follows:
ITEM Content Remark
Capacity
Gross Capacity(1,320MW)
Net Capacity(1,223MW)
Annual Generation 9,063.6 MW Plant capacity factor of 84.6% is considered.
Construction Cost EPC Cost : USD1,739,810
Construction Period #1 2016.01.01 ~ 2020.12.31 60Months
Construction Period #2 2016.01.01 ~ 2021.06.30 66Months
Operation Period 2021.01.01 ~ 2046.06.30 25Years
Exchange rate USD 1= 80 TAKA
Equity : Debt 30%: 70%
Interest rate 7.64%
Inflation rate 0%
Levelized Reference Price 9.75 cents per kWh
Coal Price USD 100 per ton Data from Daewoo
International
O&M Costs 0.0055 USD per kWh
Corporation tax rate 27.5%
Tax Holiday 15 years After COD
6.2 Inflation Rate
Past 10 years inflation rate in USA is approximately 2.27%, 6.42% in Bangladesh.
Period USA Bangladesh USA Bangladesh
10 year average 2.27% 6.42%
2.27% 6.42% 5 year average 1.67% 7.23%
3 year average 1.75% 7.36%
(Source: IMF, World Economic Outlook Databases)
![Page 25: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/25.jpg)
Chittagong 2x660MW CFPP Project Page No : 25 of 94
Pre-Proposal
Despite the inflation rate, while performing analysis, constant price (assuming 0%
inflation) applied.
Reasons are according to RFP I) Tariff is to be presented in constant price, II)the
financial impact rarely occurs when Tariff levels and O & M costs are match to each
other.
Details
TARIFF
CHARGES
PROPOSAL
a. As per the private Sector Power Generation Policy of Bangladesh and the commercial
terms of the draft PPA, the Bidders are to propose a power tariff for coal operation, as per
format and instructions provided in Section D, Exhibit II, and within the limitations
prescribed below, based on capacity and energy payments.
b. The calculation on which the capacity and energy payment are to be made and their
derivation from the capital structure, financing plan and plant performance shall be shown
explicitly.
c. The proposed Tariff Charges and its components in the Bidder’s Proposal shall be
quoted in Dollar or Taka (as the case may be) to four decimal places, and in real or
constant terms, that is without any indexation allowed in this RFP after the Bid Date
for Exchange Rate, Foreign Index and Local Index.
6.3 Funding
Total investment cost of the project is approximately USD 2,349 million, equity and
debt rate should be 30% of equity and 70% of debt. In addition, analysis assumed
equity capital injection occurs before debt commitment.
![Page 26: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/26.jpg)
Chittagong 2x660MW CFPP Project Page No : 26 of 94
Pre-Proposal
(Unit: USD million)
Item Amount Item Amount
EPC 1,740 Equity 705
Other EPC(Include IDC) 609 Debt 1,644
Total EPC 2,349 Total Investment 2,349
6.4 Loan Schedule and Interest Expenses
6.4.1 Terms
Funding plans are as follows:
The interest rate for debt which is borrow form MDB or via agencies in Korea
ECA financing was assumed that, and some of debt raise from the foreign
investors.
Item Content
Repayment period for principal 15 years after COD
Repayment method Even repayment of principal only
Interest rate 7.64%
In addition to the basic financial conditions above, the SPC shall comply with
dividend payment condition until complete repayment of debt. For dividend
payment condition applied normal level condition for project financing, defined as
follows:
Item Content Remark
Debt Ratio Below 300%
Simple DSCR More than 1.2
Cumulative DSCR More than 1.5
6.5 IRR, ROE
6.5.1 Result
Calculated on the basis of the above-mentioned procedure, the Project IRR and
ROE is as follows based on all of assumption mentioned above.
![Page 27: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/27.jpg)
Chittagong 2x660MW CFPP Project Page No : 27 of 94
Pre-Proposal
Item Result
Project IRR 15.67%
Equity IRR 19.66%
ROE 15.00%
![Page 28: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/28.jpg)
Chittagong 2x660MW CFPP Project Page No : 28 of 94
Pre-Proposal
7. SENSITIVITY
7.1 Results of Sensitivity
7.1.1 Coal price Sensitivity
Results of changes in Coal price are as follows:
Item 80%
of Base Case 90%
of Base Case Base Case
110% of Base Case
120% of Base Case
Coal Price (USD/Ton)
80.00 90.00 100.00 110.00 120.00
Tariff (Cents/kWh)
8.90 9.32 9.75 10.18 10.61
7.1.2 Interest rate Sensitivity
Results of changes in Interest rate are as follows:
Item Base Case -
1.00% Base Case -
0.50% Base Case
Base Case +0.50%
Base Case +1.00%
Interest Rate 6.64% 7.14% 7.64% 8.14% 8.64%
Tariff (Cents/kWh)
9.62 9.68 9.75 9.82 9.89
7.1.3 Coal-Price Sensitivity
Results of changes in Coal price are as follows:
Item Base Case 105%
of Base Case 110%
of Base Case 115%
of Base Case 120%
of Base Case
O&M price (USD/kWh)
0.0055 0.0058 0.0061 0.0063 0.0066
Tariff (Cents/kWh)
9.75 9.78 9.81 9.84 9.86
![Page 29: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/29.jpg)
Chittagong 2x660MW CFPP Project Page No : 29 of 94
Pre-Proposal
8. Outline of Plant Configuration
This project is for the development of Bangladesh Chittagong Coal-Fired Power Plant (2
x660MW) (hereinafter referred to as “Chittagong CFPP”) located in the South East of
Bangladesh. The plant will be designed to generate total gross power output of 1,320 MW of
electricity at the generator terminal side and utilize “Ultra Super Critical Technology”
(hereinafter referred as to “USC”).
The power block will consist of two (2) steam turbines to be connected to two (2) steam
generators. Also included are mechanical and electrical auxiliaries and associated
instrumentation and control systems.
In recent years, requests for sustainable use of existing resources and concerns about the
effect of CO2 emissions on global warming have strengthen the focus of plant engineers and
the power industry on more efficient energy conversion process and system.
Coal-based power generation is still a fundamental part of energy supply in account of
reliability, security of supply, low fuel costs, and competitive cost of electricity. But CO2
emissions problem have attracted more and more attention due to its political awareness.
Relatively large CO2 emissions of coal increase the need for more efficient coal-based power
generation.
The efficiency of the power plant affects both the fuel costs and the amount of CO2 emitted to
the environment. Therefore, applying proven state-of-the art technology for optimal
efficiencies are key requirements in new power plant project. Increasing the steam
parameters is a kind of the well-known lever for raising the overall pant efficiency.
Ultra supercritical (USC) steam power plants meet notably the requirements for high
efficiencies to reduce both fuel costs and emissions as well as for a reliable supply of electric
energy at low cost. Recent developments in high-temperature materials also allowed for
significant efficiency gains.
![Page 30: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/30.jpg)
Chittagong 2x660MW CFPP Project Page No : 30 of 94
Pre-Proposal
9. Site Information and Environmental requirements
9.1 Proposed Site location
This proposal is based on the following site location which availability shall be
confirmed by the Owner in due course.
1) Location: Matarbari island of Maheskhali Upazila of Cox’s Bazar district
2) Coordinates : To be confirmed later
The proposed site above is surrounded by the Bay of Bengal in the West, Kohelia river
on the East, the designated site of JICA power plant on the north.
9.2 Required Area of the Total Power Plant
The total estimated area for the power plant is about 314 ha that includes Power Block,
Switch yard, Coal Stock yard and Ash Disposal Pond.
However, the exact amount of area can be confirmed at the firm proposal stage when
the systems or specifications of all the facilities are designed in detail.
9.3 Site Layout
The layout planning of the whole area was arranged as follows based on the
circumstantial conditions, and is provided in Figure 9.1.
Proposed Site Layout drawing refers to the Appendix 13.4, Plot Plan.
The north side
The boundary of the north-western limit is fixed under the constraint that it does
not go over the designated site of JICA power plant
- The east side
The boundary of the eastern limit is fixed under the constraint of the existing river
![Page 31: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/31.jpg)
Chittagong 2x660MW CFPP Project Page No : 31 of 94
Pre-Proposal
Figure 3.1 Overall Power Plant
9.4 Environmental Requirements
The environmental requirements of the Plant will be in accordance with the applicable
Bangladesh standards, regulations or laws as well as the relevant codes about the
Environmental, Health and Safety Guidelines.
9.4.1 Airborne Emissions
The plant exhaust emissions will not exceed the emission limit of pollutants
shown on Table 9.1. EP and FGD will be installed to meet such limitation.
Table 9.1Emission Limits of Pollutants (1)
Pollutant Unit IFC
Guidelines Bangladesh Standards
Proposed Requirement
NOx mg/m3N 510 600 460
SO2 mg/m3N 850 (2) 820
Particulate Matter mg/m3N 50 150 50
(Source) Environmental, Health, and Safety Guidelines for Thermal Power Plants, IFC 2008 / Schedule 11 and 12, Rule 13, Environment Conservation Rules, 1997
![Page 32: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/32.jpg)
Chittagong 2x660MW CFPP Project Page No : 32 of 94
Pre-Proposal
(Note)
(1) The above are based on 6% O2 dry conditions.
(2) At least a 275m height stack is required for dispersion of sulfuric acid.
Regarding the SO2 emission limit, IFC Guidelines state that selection of the
emission level in the range is to be determined by EIA considering the project’s
sustainability, development impact, and cost-benefit of the pollution control
performance.
9.4.2 Noise Emissions
The noise levels will not exceed the standard noise levels mentioned in Table 9.2.
At this stage, the noise limit at the plant boundary cannot be established. It
should be established considering that the noise level of the nearest village shall
be kept within 50 dBA during day time and 40 dBA during night time
Table 9.2 Noise Standards for Industrial Areas
Item Unit IFC Guidelines Bangladesh Standards
Residential Area Industrial Area
Day time dBA 70 (7:00 – 22:00) 50 (6:00 – 21:00) 75 (6:00 – 21:00)
Night time dBA 70 (7:00 – 22:00) 40 (21:00 – 6:00) 70 (21:00 – 6:00)
(Source)Environmental, Health, and Safety Guidelines for Thermal Power Plants, IFC 2008 / Schedule 11 and 12, Rule 13, Environment Conservation Rules, 1997
All measurement of noise and testing will be done in accordance with relevant
code. To comply with the above stated noise criteria, any modifications
necessary, including the installation of additional and/or improved sound
attenuation equipment, will be implemented.
Maximum near field noise will not exceed 85 dB(A) at 1.0m distance and 1.5m
high from the end of each piece of equipment enclosure.
9.4.3 Effluent Limit
The Effluents generated from various sources will be treated and discharged to
sea after meet the standards of IFC(World Bank) Guidelines. A measuring point
of wastewater would be located on the outfall near the battery limit.
![Page 33: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/33.jpg)
Chittagong 2x660MW CFPP Project Page No : 33 of 94
Pre-Proposal
Table 9.3 Effluent Guidelines
No. Parameter Unit IFC(W.Bank) Guidelines (Base on)
1 Arsenic (As) mg/l 0.5
2 Cadmium (Cd) mg/l 0.1
3 Chromium (total Cr) mg/l 0.5
4 Chromium (hexavalent Cr) mg/l 0.5
5 Copper (Cu) mg/l 0.5
6 Iron (Fe) mg/l 1.0
7 Lead (Pb) mg/l 0.5
8 Mercury (Hg) mg/l 0.005
9 Oil & grease mg/l 10
10 pH - 6-9
11 Zn (Zn) mg/l 1.0
12 Total Suspended Solid (TSS) mg/l 50
13 Total Residual Chlorine mg/l 0.2
14 Temperature Increase ℃ (*)
(Source) Environmental, Health, and Safety Guidelines for Thermal Power Plants, IFC 2008
(Note) (*) Site specific requirement to be established by the EA. Elevated temperature areas due to
the discharge of once-through cooling water (e.g., 1 Celsius above, 2 Celsius above, 3 Celsius
above ambient water temperature) should be minimized by adjusting intake and outfall design
through the project specific EA depending on the sensitive aquatic ecosystems around the
discharge point.
9.4.4 Sanitary Wastewater
The treated sanitary wastewater quality will meet IFC Guidelines shown in Table
9.4. Septic tanks will be installed to meet such limitations.
Table 9.4 Sanitary Effluent Standards
No. Parameter Unit IFC
Guidelines
1 pH - 6-9
2 BOD mg/l 30
3 COD mg/l 125
4 Total nitrogen mg/l 10
![Page 34: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/34.jpg)
Chittagong 2x660MW CFPP Project Page No : 34 of 94
Pre-Proposal
5 Total phosphorus mg/l 2
6 Oil and grease mg/l 10
7 Total suspended solids mg/l 50
8 Total coliform bacteria MPN/100ml 400
(Source) Environmental, Health, and Safety Guidelines for Thermal Power Plants, IFC 2008
(Notes) MPN = Most Probable Number
9.4.5 Environmental Monitoring Facilities
The Continuous Emission Monitoring System (hereinafter called “CEMS”) will be
installed to monitor flue gas from the Plant. CEMS shall be required to monitor
the amount of the flue gas and its concentrations of NOx, SO2, and Particulate
Matter.
The continuous monitoring system for the amount of the effluent from the
wastewater treatment system and its pH value and turbidity shall be monitored.
The monitoring shall be conducted at the treated water pit of the wastewater
treatment system in the Plant.
![Page 35: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/35.jpg)
Chittagong 2x660MW CFPP Project Page No : 35 of 94
Pre-Proposal
10. Scope of Supply
This Project basically consists of 2 x 660MW Coal-fired Thermal Power Generation
Facilities, and includes designing, furnishing, constructing, installing, checking, starting-up
and testing of complete operable systems and facilities.
This proposal includes works and services as both EPC contractor and IPP developer’s
responsibility (Chapter 10.1 & 10.2).
However, the items in Out of Scope of Works(Chapter 10.3) below are excluded in this
proposal and shall be supplied by others.
10.1 Scope of Works and Services as EPC Contractor’s responsibility
The EPC Contract requires all of the works for engineering and management,
whenever in these specifications the terms "provide", "furnish", "supply", "furnish
and/or install", etc., are used, its intended that the Contractor shall supply and install
all systems and facilities unless specific notation is made that the equipment, device,
or system is to be installed by others.
The Contract shall also include all works in place from the initial site construction to
start-upend testing as required for complete operable systems and facilities with
Contractor's and Contractor’s Vendors services of technical direction as required for
placing the systems and facilities into successful operation, and for training the
Employer's plant personnel in the operation and maintenance of the systems and
facilities.
The Contractor shall execute checkout, start-up and perform initial operation of
systems and facilities in coordination with the Employer's plant operation staff. The
terminal point of EPC Contractor’s Scope of works refers to Appendix 13.1, Diagram
of Terminal points.
10.1.1 General
1) Project management
2) Engineering services including the following:
A. Project scheduling
B. Conceptual layout and project detailed design
C. Preparation of specifications for equipment and materials
D. Procurement and expediting of all equipment and materials
E. Delivery of equipment and materials to Site
![Page 36: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/36.jpg)
Chittagong 2x660MW CFPP Project Page No : 36 of 94
Pre-Proposal
3) Geotechnical Investigations and other surveys of the Site
4) Detailed design of the following
A. Civil and structural systems
B. Architectural systems
C. Mechanical systems
D. Chemical systems
E. Electrical systems
F. Control systems
5) Procurement service of the following
A. Expediting procurement
B. Testing and inspection of equipment
6) Construction services including the following
A. Construction management
B. Construction, equipment erection and installation, labor, labor supervision,
and tools required to implement the engineering designs
C. Construction Equipment
D. Performance testing
E. Startup
F. Construction closeout
10.1.2 Boiler and Auxiliaries
The Works include, but are not limited to, the following equipment / materials:
1) Boiler
2) Coal Bunker
3) Coal Pulverizer
4) Coal Feeder
5) Coal Burner
6) Ignition lighter
7) Start-up Oil Burner
8) Forced Draft Fan
9) Primary Air Fan
10) Soot Blower System
11) Air Heater
12) Induced Draft Fan
13) Electrostatic Precipitator
14) Flue Gas Desulfurizer
![Page 37: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/37.jpg)
Chittagong 2x660MW CFPP Project Page No : 37 of 94
Pre-Proposal
15) Stack
16) Fuel Oil Service Tank
17) Fuel Oil Pump
18) Essential Spare Parts as a minimum
19) Tools and Test Equipment
20) Consumable Parts and Material for Commissioning and Initial Operation
10.1.3 Steam Turbine and Auxiliaries
The Works include, but are not limited to, the following equipment / materials:
1) Steam Turbine
2) Condenser
3) Steam Turbine Bypass System (High Pressure Bypass)
4) Steam Turbine Bypass System (Low Pressure Bypass)
5) Condenser Cathodic Protection Equipment
6) Condenser Tube Cleaning Equipment
7) Motor-driven Condenser Vacuum Pump
8) Condensate Pump
9) Grand Steam Condenser
10) Condensate Polishing Plant
11) Low Pressure Feed Water Heaters
12) Deaerator
13) Motor-driven Boiler Feed Pump for start-up
14) Turbine-driven Boiler Feed Pump
15) High Pressure Feed Water Heaters
16) Closed Cycle Cooling Water Pump
17) Closed Cycle Cooling Water Heat Exchanger
18) Auxiliary Oil Pump
19) Emergency Bearing Oil Pump
20) Oil Cooler
21) Turning Gears
22) Turning Gear Oil Pump
23) Steam Turbine Supervisory Instrument
24) Essential Spare Parts as the minimum
25) Tools and Test Equipment
26) Consumable Parts and Material for Commissioning and Initial Operation
![Page 38: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/38.jpg)
Chittagong 2x660MW CFPP Project Page No : 38 of 94
Pre-Proposal
10.1.4 Coal and Ash Handling Equipment
The Works include, but are not limited to, the following equipment / materials:
1) Coal handling equipment (from Coal yard to boilers)
2) Coal Conveyor (from Coal yard to boilers)
3) Stacker / Reclaimer
4) Coal Yard
5) Coal Discharging Conveyer
6) Coal Shifting Conveyor
7) Essential Spare Parts as a minimum
8) Tools and Test Equipment
9) Consumable Parts and Material for Commissioning and Initial Operation
10) Ash Handling Equipment
11) Furnace Bottom Clinker Handling Equipment
12) Fly Ash Collection Equipment
13) Fly Ash Storage Silo
14) Ash Discharging Conveyor
15) Essential Spare Parts as a minimum
16) Tools and Test Equipment
17) Consumable Parts and Material for Commissioning and Initial Operation
10.1.5 BOP (Balance of Plant)
The Works include, but are not limited to, the following equipment / materials:
1) Auxiliary Boiler
2) Circulating Water Supply System including Screen, Pump and Piping
3) Desalination Plant including Service Water Supply Facilities and Service Water
Tank
4) Demineralization Plant
5) Make-up Water Tank
6) Chemical Injection / Sampling Facilities
7) Service Gas Supply System
8) Compressed Air Supply System
9) Waste Water Treatment Facilities
10) Fire Protection System
10.1.6 Electrical Equipment / Materials
![Page 39: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/39.jpg)
Chittagong 2x660MW CFPP Project Page No : 39 of 94
Pre-Proposal
The Works include, but are not limited to, the following equipment / materials:
1) Generator and Auxiliaries including Excitation System
2) Generator Circuit System including IPB, VT/ SA and NGR
3) Generator Circuit Switching Devices (GCB and DS with Earthing switch)
4) Generator Step-up Transformer with Auxiliaries
5) Unit Auxiliary Transformer with Auxiliaries
6) 6.6kV Medium Voltage Switchgears with Meters and Protection Relays
7) 415V Unit and Common Switchgears
8) 415V Essential Switchgear
9) Motor Control Center (MCC)
10) Uninterruptable Power Supply Facilities (UPS)
11) Emergency Power Supply Facilities
12) DC Power System
13) Generator and Transformer Protection Relays
14) Cathodic Protection System
15) Power Cables and Wiring Materials
16) Control Cables and Wiring Materials
17) Cable Trays and Fitting Materials
18) Grounding Materials
19) Plant Lighting System
20) Communication System
10.1.7 Instrument and Control Equipment
1) Distributed Control System (DCS)
2) Field Instrumentation
3) Control Valve, MOV and On-off valve
4) Vibration Monitoring System (VMS)
5) Continuous Emission Monitoring System (CEMS)
6) Water & Steam Sampling Analysis System
7) Programmable Logic Control System (PLC)
10.1.8 400kV Switch yard equipment
1) Circuit Breakers (3-phase)
2) Disconnecting Switches (3-phase)
![Page 40: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/40.jpg)
Chittagong 2x660MW CFPP Project Page No : 40 of 94
Pre-Proposal
3) Earthing Switches (3-phase)
4) Current Transformers (3-phase)
5) Voltage Transformers (3-phase)
6) Lightning Arresters (3-phase)
7) Control Building
8) Bay Control Unit (BCU)
9) Station Control System (SCS)
10) SCADA (RTU)
11) Protection Relay
12) AC and DC Auxiliary Power System including Battery
10.1.9 Civil, Structure and buildings
The civil works shall include, but not be limited, the following:
1) Site survey(The topography and sea)
2) Soil investigation
3) Site preparation works
4) Site strip and grading
5) Soil banking with slope protection works
6) Soil excavation and backfill
7) Piling and foundation works for all equipment & facilities in the Power Plant
8) Temporary site services (Temporary road, drainage, office etc.)
9) Laydown and contractor’s areas
10) Underground utilities (Electrical duct bank, culvert, trench, piping work etc.)
11) Wastewater treatment system structure
12) Power Plant drainage
13) Road & paving within the site boundary
14) Fence & gate for site security
15) Intake & discharge construction work (If necessary)
16) Coal storage pond & ash storage pond construction work (If necessary)
The structure and buildings Works include, but are not limited to, the following
civil, structures and buildings:
1) Temporary buildings
2) Preliminary works
3) Foundations for pipe racks and pipe support
4) Boiler structures, cladding and stack foundations
![Page 41: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/41.jpg)
Chittagong 2x660MW CFPP Project Page No : 41 of 94
Pre-Proposal
5) Turbine building and foundations
6) Electrical building
7) Control room/ office building
8) Workshop and warehouse building, standard equipment and tools for daily
maintenance
9) 400 kV Switchyard control building
10) Water treatment plant building and associated tank foundations
11) Civil works for cooling water system, cooling water intake structures, cooling
water pump house, underground inlet cooling water culvert, underground
cooling water discharge culvert and discharge structures
12) HVAC systems
13) Fire detection system for the Plant
14) Electrical installations of the buildings, small power systems, indoor normal,
emergency and exit lighting for the Plant's buildings
15) Service platforms and structures, lifting beams and lifting devices for Plant
equipment in order to facilitate daily operation and maintenance
16) Offices and Facilities for the Employer’s Engineer at Site as specified by the
Employer
10.1.10 Spare part, special tool
1) Spare part for startup / commissioning
2) Special tool for construction / maintenance
10.1.11 Site training for Owner’s Employee
1) Steam turbine and Generator
2) ESP
3) DCS Control & Instrumentation
4) Demineralization Plant
5) Coal and Ash Handling
6) Electro-chlorination Plant
7) Seawater Cooling System
8) Fire Fighting System
9) Emergency Diesel Generator System
10) Compressed air / instrument air
![Page 42: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/42.jpg)
Chittagong 2x660MW CFPP Project Page No : 42 of 94
Pre-Proposal
10.2 Scope of works and services as IPP developer’s responsibility
1) Land for Power Plant, Coal yard and Ash pond Site office, Lay-down and
warehouse areas for the Contractor including Sub-contractors
2) Getting all necessary permissions(including environmental permits) for
construction, erection and operation of the plant from Authorities of Republic
of Bangladesh Government
3) Labor Cost and Site Expenditure for the Owner’s staff during construction
and Commissioning before COD
4) Costs of travel or stay of the Owner’s engineers for factory inspection and
test at the Contractor’s shop or those of his sub-contractor
5) Shop (Overseas) training for Owner's Employee, if necessary
6) Material for Pre-commissioning, Commissioning and tests Consumer
A. Coal
B. Ignition Diesel Oil
C. Water
D. Electric
7) Insurance
A. Project Cargo (Including Marine Cargo)
B. EAR (Erection All Risk)
C. Worker's Compensation / Employer's Liability
D. Others for Owner side
8) Customs Duty (regarded to be exempted in this proposal)
9) 2 Years Spare Parts
10) Power Sale during Reliability Test
10.3 Out of Scope of works to be provided by Others
1) 400KV Transmission line from New Switchyard to National Grids
2) Jetty Facilities, Port & Harbor
3) Access Way (Road & Bridge) to the site
4) Land acquisition and Permissions and construction cost for Access Road
5) Coal Handling system and coal transfer (from coal supplier to coal yard)
![Page 43: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/43.jpg)
Chittagong 2x660MW CFPP Project Page No : 43 of 94
Pre-Proposal
11. Design Description
11.1 Tentative Design Criteria
In accordance with data from several metrological data sources, the Plant shall be
designed according to Table 11.1 Design Criteria. The Minimum Ambient Dry Bulb
Temperature was obtained by statistical treatment of daily minimum temperatures of
January from 1992 to 2011 at the Kutubdia observation station. The Maximum
Ambient Dry Bulb Temperature was obtained by statistical treatment of daily minimum
temperatures of April and May from 1992 to2011 at the Kutubdia observation station.
The Design Ambient Dry Bulb Temperature was obtained using the above 20 years
data as typical conditions. The Annual Rainfall was obtained from the above 10 years
data (from 2002 to 2011) at the Kutubdia observation station. Design Ambient Dry
Bulb Temperature, Relative Humidity and Design Sea Water Temperature at Turbine
Maximum Continuous Rating (TMCR) conditions are 30℃, 80% and 30℃,
respectively. The design conditions were determined tentatively according to the
limited metrological data in order that these could be revised during the design stage.
Table 11.1 Tentative Design Criteria
Design Ambient Dry Bulb for Performance Guarantee
30℃
Relative Humidity for Performance Guarantee
80%
Design Sea Water Temperature (TMCR/TBN Capability)
30℃ / 32℃
Minimum/Maximum Relative Humidity 20% / 100%
Minimum/Maximum Ambient Dry Bulb Temperature
15℃ / 35℃
Barometric Pressure 0.1013 Mpa
Elevation 10m+ M.S.L. for Power Block Area
Sea Water Level High Water Level = +2.2m M.S.L Low Water Level = -2.2m M.S.L
Seismic Criteria* 0.28 (Zone 3)
Wind Design* 72.2 m/s (Chittagong)
Annual Rainfall 4877 mm
Maximum Rainfall Rate (1 hour)* 85 mm/hr
Snow Load 0 kg/m2
(Source) *:Bangladesh Notional Building Code 2010, Others: Assumption
![Page 44: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/44.jpg)
Chittagong 2x660MW CFPP Project Page No : 44 of 94
Pre-Proposal
Table 11.2 summarizes tentative specification of Design Coal. The caloric value (HHV)
of imported coal is 5,000kcal/kg and it is used for this proposal.
Table 11.2 Tentative Specification of Design Coal
Gross Calorific Value (ADB, kcal/kg) 5,600
Gross Calorific Value (ARB, kcal/kg) 5,000
Total Moisture (ARB, %) 26 %
Inherent Moisture (ADB, %) 14 %
Ash (ADB, %) 10 %
Volatile Matter (ADB, %) 43 %
Fixed Carbon (ADB, %) 33 %
Total Sulphur (ADB, %) 1.0 %
HGI 50
Size 0-50 mm 90%
Table 11.3 Seawater Analysis
No. Contaminants Units Seawater
1 pH - 7.7
2 Temperature ℃ 32
3 Turbidity NTU 12
4 Conductivity ㎛ hos/cm 84103
5 Total suspended solids mg/l 18
6 Total dissolved solids mg/l 33000
7 Total alkalinity as CaCO3 mg/l 216
8 Total hardness as CaCO3 mg/l 9376
9 Ca hardness as CaCO3 mg/l 571
10 Mg hardness as CaCO3 mg/l 1921
11 Chloride mg/l 37135
12 Sulphate mg/l 4145
13 Sodium mg/l 21270
14 Potassium mg/l 872
15 Fluoride mg/l 0.7
16 Nitrate as N mg/l 2.8
![Page 45: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/45.jpg)
Chittagong 2x660MW CFPP Project Page No : 45 of 94
Pre-Proposal
No. Contaminants Units Seawater
17 Total Phosphates mg/l 0.18
18 Chemical oxygen demand mg/l Appx.50
Table 11.4 Redundancy apply for main equipment
No. Item Redundancy
1 Condenser 1x100% / Unit
2 Condensate pump 3x50% / Unit
3 Condensate polishing plant 1x100% / Unit
4 Gland steam condenser 1x100% / Unit
6 High Pressure Heater#1 1x100% / Unit
7 High Pressure Heater#2 1x100% / Unit
8 High Pressure Heater#3 1x100% / Unit
9 Deaerator 1x100% / Unit
10 Boiler feed water pump(Turbine Driven) 2x50% / Unit
11 Boiler feed water pump(Motor Driven, Start-up) 1x25% / Unit
12 Low Pressure Heater#1 1x100% / Unit
13 Low Pressure Heater#2 1x100% / Unit
14 Low Pressure Heater#3 1x100% / Unit
15 Low Pressure Heater#4 1x100% / Unit
16 CCW Pump 2x100% / Unit
17 CCW Head Tank 1x100% / Unit
18 CCW Heat Exchanger 2x100% / Unit
19 Main cooling water Pump 2x50% / Unit
20 Auxiliary cooling water pump 1x100% / Plant
![Page 46: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/46.jpg)
Chittagong 2x660MW CFPP Project Page No : 46 of 94
Pre-Proposal
Fig. 11.1 Basic wind speed map of Bangladesh
(Source: BANGLADESH NATIONAL BUILDING COD 2010)
![Page 47: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/47.jpg)
Chittagong 2x660MW CFPP Project Page No : 47 of 94
Pre-Proposal
Fig. 11.2 Seismic Zoning Map of Bangladesh
(Source : BANGLADESH NATIONAL BUILDING COD 2010)
![Page 48: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/48.jpg)
Chittagong 2x660MW CFPP Project Page No : 48 of 94
Pre-Proposal
Table 11.5 Seismic Zone Coefficient Z for Some Important Towns of Bangladesh
Town Z Town Z Town Z Town Z
Bagerhat 0.12 Dinajpur 0.20 Kushtia 0.20 Panchagarh 0.20
Bandarban 0.28 Faridpur 0.20 Lalmanirhat 0.28 Patuakhali 0.12
Barguna 0.12 Feni 0.20 Madaripur 0.20 Rajbari 0.20
Barisal 0.12 Gaibandha 0.28 Manikganj 0.20 Rajshahi 0.12
Bhola 0.12 Gazipur 0.20 Mongla 0.12 Rangamati 0.28
Bogra 0.28 Habiganj 0.36 Munshiganj 0.20 Rangpur 0.28
Brahmanbaria 0.28 Jaipurhat 0.20 Mymensingh 0.36 Satkhira 0.12
Chandpur 0.20 Jamalpur 0.36 Narsingdi 0.28 Sirajganj 0.28
Chittagong 0.28 Jessore 0.12 Natore 0.20 Srimangal 0.36
Chuadanga 0.12 Khagrachari 0.28 Naogaon 0.20 Sunamganj 0.36
Comilla 0.20 Khulna 0.12 Netrakona 0.36 Sylhet 0.36
Cox's Bazar 0.28 Kishoreganj 0.36 Noakhali 0.20 Tangail 0.28
Dhaka 0.20 Kurigram 0.36 Pabna 0.20 Thakurgaon 0.20
(Source : BANGLADESH NATIONAL BUILDING COD 2010)
11.2 Expected Plant Performance
The expected plant performance at TMCR conditions are summarized in Table 11.6.
Table 11.6 Expected Plant Performance
Gross Power Output (kW) at TMCR 2 x 660,190 kW
Net Power Output (kW) 2 x 611,807 kW
Gross Efficiency, HHV (%) 42.02 %
Gross Heat Rate, HHV (kJ/kWh) 8567 kJ/kWh
Note 1. TMCR : Turbine Maximum Continuous Rating
2. The above performance results are expected based on the design criteria in chapter 5.1
11.3 Codes and standards
All Project equipment and systems shall be designed, constructed, inspected, installed
and tested as appropriate at the manufacturer’s works, after installation and during
![Page 49: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/49.jpg)
Chittagong 2x660MW CFPP Project Page No : 49 of 94
Pre-Proposal
commissioning in accordance with the latest relevant International codes, standards
and accident prevention regulations. Full name of the code and standard are as below.
Code Name Full Name
AASHTO American Association of State Highway and transportation Officials
ABMA American Boiler Manufacturers Association
ACI American Concrete Institute
ACRI Air-Conditioning and Refrigeration Institute
AISC American Institute of Steel Construction
AISE Association of Iron and Steel Engineers
AISI American Iron and Steel Institute
ANSI American National Standards Institute
API American Petroleum Institute
ASCE American Society of Civil Engineers
ASHRAE American Society of Heating, Refrigeration & Air Conditioning Engineers
ASME American Society of Mechanical Engineers
ASTM American Society of Testing and Materials
AWS American Welding Society
AWWA American Water Works Association
BNBC Bangladesh National Building Code
BS British Standards Institute
CEMA Conveyor Equipment Manufacturers Association
CEN European Committee for Standardization
CENELEC European Committee for Electro technical Standardization
CL Chlorine Institute
CMAA Crane Manufacturers Association of America
CSRI Concrete Reinforcing Steel Institute
DEMA Diesel Engine Manufacturers Association
DIN Deutsches Institute fur Normung
EHS IFC Environmental Health and Safety Guidelines
EN Euro Norm
GB GuoBiao, Chinese national standards
HEI Heat Exchange Institute
HIS Hydraulic Institute Standard
IAPH International Association of Ports and Harbours
![Page 50: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/50.jpg)
Chittagong 2x660MW CFPP Project Page No : 50 of 94
Pre-Proposal
Code Name Full Name
IBC International Building Codes
IEC International Electrotechnical Commission
IEEE Institute of Electrical and Electronics Engineers
IP Institute of Petroleum
ISO International Organization for Standardization
JIS Japanese Industrial Standards
KS Korean Standards
MS Malaysia Standard, Manufacturer’s Standard, Industrial Ventilation
MSS Manufacturer’s Standardization Society
NACE National Association of Corrosion Engineers
NEMA National Electrical Manufacturers Association
NFPA National Fire Protection Association
OSHA Occupational Safety and Health Administration
SSPC Society of Protective Coatings (formerly known as Steel Structures Painting Council)
TEMA Tubular Exchanger Manufacturers Association
TRD Technical Rules for Steam Generators
UBC Uniform Building Code (USA)
UFC Uniform Fire Code
UPC Uniform Plumbing Code
VDI Verein Deutscher Ingenieure
VGB Society of Large Utility Owners
WFCF Water Pollution Control Federation
• Loads and Stresses
All civil and structural design will be in accordance with ASCE 7, “Minimum
Design Load for buildings and other structures”.
• Structural Steel
Steelwork for structures will be designed according to the American Institute of
Steel Construction (AISC, Specification for the design, fabrication and erection of
structural steel for buildings).
• Reinforced Concrete
Structural concrete works will be designed in accordance with the following
codes/standards:
![Page 51: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/51.jpg)
Chittagong 2x660MW CFPP Project Page No : 51 of 94
Pre-Proposal
- ACI 318 Building code requirements for reinforced concrete
- ACI 301 Specification for structural concrete for buildings
- ACI 315 Building code requirements for detailing reinforced concrete
structures
Materials for Civil & Architecture
a) Concrete
Minimum concrete compressive strength fck at 28 days of cube specimen will be
as follow:
fck, MPa Area of Use
16 Lean concrete
27 Structures and equipment foundations
40 Marine facilities
b) Reinforcing Steel
The reinforcing steel will conform to the requirements of ASTM Designation A615
Grade40, Grade60.
11.4 Submission Requirements
This proposal shall be in the English language. The International Systems International
d ’Units (“SI”) system of units (metric) in accordance with the provisions of ISO 31 and
ISO 1000 shall be used in the proposal.
Quantity Name of Unit Symbol
Length Meter m
Mass Kilogram Kg
Time Second S
Temperature Degree Celsius C
Electric current Ampere A
Area Square meter m2
Volume Cubic meter m3
Force Newton N
Pressure Bar bar
![Page 52: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/52.jpg)
Chittagong 2x660MW CFPP Project Page No : 52 of 94
Pre-Proposal
Pressure below 1 bar Millibar mbar
Stress Newton per square millimeter N/mm2
Velocity Meter per second m/s
Rotational Speed Revolutions per minute Rpm
Flow
Cubic meter per day Cubic meter per hour Kilogram per hour Liter per second metric ton per hour For gaseous substance: standard cubic meter per hour (referred to 0 °C and 1013 mbar)
m3/d m3/h kg/h l/s t/h Nm3/h
Density Kilogram per cubic meter Kilogram per standard cubic meter
Kg/m3 Kg/Nm3
Torque, moment of force Newton meter Nm
Work, energy or heat Joule J
Power, radiant flux Watt W
Heat release rate Watt per square meter W/m2
Surface Tension Newton per meter N/m
Concentration Parts per million Ppm
Frequency Hertz Hz
Electric Potential Volt V
Conductance Siemens S
Luminous Flux Lumen Lm
Energy Kilowatt hour kWh
Fuel (Energy) Kilocalorie gram per Kilogram Kcal/kg
11.5 Boiler and Flue Gas Treatment Facilities
Boilers and flue gas treatment facilities for this project shall be composed of two
boilers, two electrostatic precipitators, and a flue gas desulfurization system, and their
auxiliary equipment, each of which is associated with each of the two condensing type
steam turbines of 660 MW generation capacities.
(1) Boilers
The two boilers shall both be pulverized coal firing, radiant reheat, and variable
![Page 53: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/53.jpg)
Chittagong 2x660MW CFPP Project Page No : 53 of 94
Pre-Proposal
pressure once-through boilers for outdoor installation. Each boiler will be designed
as a balanced draft furnace with low NOx burners. About 1,835.0 ton/hr ultra
supercritical main steam (258 bara, 603.8 ℃ at boiler outlet) are generated. The
design criteria of the boilers are shown in Table 11.7.
Table 11.7 Boiler Design Criteria
Type Pulverized coal fired, single reheat, once-through, Ultra Supercritical, (Outdoor Installation)
Steam Flow Rate at TMCR - Main Steam - Reheat Steam
1920.0 ton/hr 1550.8 ton/hr
Steam Pressure at TMCR - Superheater Outlet - Reheater Outlet
258.0 bara 52.0 bara
Steam Temperature - Superheater Outlet - Reheater Outlet
603.8 ℃
602.4℃
Fuel Pulverized coal, light oil or high speed diesel oil for unit start up, and ignition and stabilization of coal burners
Drafting System Balanced draft with forced draft fans and induced draft fans
The boiler will be designed for pulverized coal firing and fuel oil will be used for
igniters and initial warm up for unit starting up. The boiler shall have corner or
opposite fired, radiant- and convection- heat transfer superheaters and reheaters,
attemperators, economizers, regenerative air heaters, and a HP/LP turbine bypass
system.
(2) Primary Air Fan, Forced Air Fans
Each boiler primary air fans (PAF) and capacity forced draft fans (FDF) for
supplying the required primary/secondary air for the boiler. These fans would be of
axial flow type with variable pitch moving blades.
(3) Induced Draft Fans
Each boiler will be equipped with induced draft fans for keeping the draft of the
furnace at slightly reduced pressure to prevent flue gas leakage. These fans would
be of axial flow type with variable pitch moving blades.
![Page 54: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/54.jpg)
Chittagong 2x660MW CFPP Project Page No : 54 of 94
Pre-Proposal
(4) Boiler Circulation Pumps
There will be a boiler circulation pump. The purpose of this pump is to return water
drained from the water separator to the inlet of the economizer and recover the
heat during the operation at low load.
(5) Soot Blowing System
The boiler shall be provided with soot blowers and wall blowers. The entire soot
blower operations shall be carried out from the DCS of the plant control system. An
intelligent automatically controlled operation system will be applied for the soot
blower system.
(6) Burner Management & Automatic Plant Control Systems
The boiler will be equipped with a complete burner management system including
mill automation and secondary air control with all required accessories as detailed
in the DC System (Control and Instrumentation).
(7) Mills & Milling System
Each boiler will be installed with mills. It would include one standby for the
pulverized coal firing system for enhanced reliability. Each mill has a gravimetric
raw coal feeder. The pulverized coal from each mill is transported through several
pulverized coal pipes to the burners. The burners are arranged for tangential firing
or opposite firing.
(8) Electrostatic Precipitators
The flue gas dust collection system for each boiler will consist of a two pass
electrostatic precipitator (ESP). The electrostatic precipitator ash collection
hoppers will have a capacity sufficient for required hours operations at the
maximum collection rate in any section of the electrostatic precipitator. The ESPs
will be provided complete with motorized or magnetic rapping mechanisms,
rectifier transformers, hoppers and their heaters and all associated auxiliaries. The
hopper outlet will be provided with a diversion gate for Dry Fly Ash collection
System. The ESP will be capable to limit dust emission, with the worst coal having
the maximum ash content.
(9) Flue Gas Desulfurization System (FGD)
![Page 55: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/55.jpg)
Chittagong 2x660MW CFPP Project Page No : 55 of 94
Pre-Proposal
FGD will reduce SO2 in flue gas to satisfy Bangladesh regulations and the
international standards, including the WHO. SO2 concentration in flue gas entering
FGD will be estimated for the worst coal condition (sulphur content of 1.0 Air
dry %). Seawater Temperature rise through FGD will be 2 ~ 3 deg C. If alkalinity of
Seawater is found insufficient than expected after detail seawater analysis, NaOH
dosing for FGD is might be required to control (guarantee) the pH of SWFGD
effluent.
For this project, Seawater FGD is recommended with the following reasons:
- Since Seawater FGD uses seawater as an absorbent of SO2, a handling system
and pulverizing system of limestone are not required.
- Since no byproducts such as gypsum is produced, a dewatering, storage and
delivery system and disposal area are not required.
- Because of the above reasons, project costs and land area will be extremely
reduced.
Seawater FGD for each boiler of this project shall consist of the following
equipment/facilities:
-Sulfur dioxide absorbers
-Regenerative gas-gas heaters (GGH)
-Seawater boost up pumps
-Seawater pipes and valves
-Flue gas bypass system (bypass duct and bypass damper)
-Inlet and outlet flue gas ducts
-Air blowers for aeration
-Aeration pond
-Instrumentation and control system
11.6 Steam Turbine and Auxiliaries
The steam turbine plant will be comprised of a steam turbine, condenser, condensate
equipment, feed water heaters, boiler feed pumps and condenser circulating cooling
water system as the fundamental configuration.
11.6.1 Steam Turbine
![Page 56: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/56.jpg)
Chittagong 2x660MW CFPP Project Page No : 56 of 94
Pre-Proposal
The steam cycle system will be a single reheat, ultra supercritical, condensing
type required for high efficiency and a large-size power plant. The steam cycle is
of ultra-supercritical pressure considering that the unit size is 660 MW class.
Tandem compound shaft configuration would be applied in this project. High
pressure (HP), intermediate pressure (IP) and low pressure(LP) steam turbines
are connected in the same shaft.
The latest design for the last stage blades (LBS) of the LP turbine also would be
applied to contribute to high efficiency and decreasing investment costs.
11.6.2 Condenser
In thermal power plants, the purpose of a surface condenser is to condense the
exhaust steam from a steam turbine into cycle water (steam condensate) so that
it is reused in the boiler as boiler feed water.
There are many fabrication design variations depending on the manufacturer, the
size of the steam turbine, and other site-specific conditions.
A single pass-one division of tube and shell circuit schematics is preferable, even
for condenser types for large-sized turbines, being based on the HEI (Heat
Exchange Institute) standard.
The required amount of cooling water for the condenser is calculated by the
following formula.
Gw = Q/(δtd x cpxρ)
Where,
- Gw :The required amount of cooling water for the condenser [m3/h]
- Q: Incoming heat to condenser [kcal/h]
- δtd: temperature difference of cooling water between inlet and outlet of
condenser [°С]
- cp: specific heat of cooling water [kcal/kg °С]
- ρ: specific gravity of cooling water [kg/m3]
Based on the data of an Appendix 13.4, heat balance diagram, the total required
amount of cooling water was estimated at 93,562ton/h for one unit.
Titanium would be applied to condenser tubes and tube sheet cladding material
concerning corrosion by sea water.
11.6.3 Condensate pump
A condensate pump is a specific type of pump used to extract the condensate
![Page 57: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/57.jpg)
Chittagong 2x660MW CFPP Project Page No : 57 of 94
Pre-Proposal
(water) in the hot-well of a condenser. Condensate pumps, as used in hydraulic
systems, are usually motor-driven centrifugal pumps.
In a thermal power plant, the condensate pump is normally located adjacent to
the main condenser hot-well, often directly below it.
These pumps are used in succession to provide sufficient Net Positive Suction
Head (NPSH) to prevent cavitation and the subsequent damage associated with
it.
11.6.4 Condenser Polishing Plant
A USC plant does not have function of boiler water blow and however it requires
high quality of boiler feed water so that a condensate demineralizer shall be
installed after the condensate extraction pumps. Contaminants in the condensate
water are colloidal matters of iron and coppered, sodium ion and chloride ion. In
some case the condensate demineralizer is to equip filters to remove colloidal
matters. After the filters the condensate demineralizer has ion exchangers for
dissolved matters.
11.6.5 Condenser Vacuum
The estimate for a condenser vacuum such as 0.087bara (saturated temperature
43°С) is done on the basis of the method provided in the HEI standard.
On the one hand, the condenser vacuum depends on the actual measurement
data of seawater temperature, and the vacuum has been studied on the basis of
a design seawater temperature of 30.0°С at the condenser inlet in accordance
with Table 11.1, tentative design criteria.
The cooling water facilities will be designed so that discharged water temperature
will be 37°C, which is not considered problematic since the temperature is not
higher than 40°C.
11.6.6 Vacuum system
For water-cooled surface condensers, the shell’s internal vacuum is most
commonly supplied and maintained by two types of vacuum systems, such as
steam jet type air ejectors and motor driven vacuum pumps.
The motor driven vacuum pumps are preferable on the basis that they are more
serviceable.
![Page 58: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/58.jpg)
Chittagong 2x660MW CFPP Project Page No : 58 of 94
Pre-Proposal
11.7 Feed water system
11.7.1 Deaerator
A deaerator is a device that is widely used for the removal of air and other
dissolved gases from the feed water to steam-generating boilers. In particular,
dissolved oxygen in boiler feed waters will cause serious corrosion damage in
steam systems by the oxidizing of surfaces of metal piping and other metallic
equipment. Water also combines with any dissolved carbon dioxide to form
carbonic acid that causes further corrosion. Most deaerators are designed to
remove oxygen down to levels of 7 ppb by weight (0.0005 cm³/L) or less.
From technical (efficiency and operation, etc.) aspects and cost aspects, tray-
type and spray-type deaerators are considered the main options for selection.
11.7.2 Boiler feed pump
A boiler feed pump is a specific type of pump used to pump feed water into a
steam boiler. Theater may be freshly supplied or returning condensate produced
as a result of the condensation of the steam produced by the boiler.
These pumps are normally high pressure units that use suction from a
condensate return system and can be of the centrifugal pump type. Turbine
driven type will be applied for Boiler feed pump in account of reliability at plant
start-up.
11.7.3 Feed water heater
Feed water heaters are applied to improve thermal efficiency. The source of
heating is the extracted steam from the turbine. The number of heaters is
determined considering economic benefits such as improved efficiency and
additional investment costs, etc. In general, six to eight heaters are installed for
large scale power plants over 200MW.
11.7.4 Heat exchanger
A heat exchanger is a device built for efficient heat transfer from one fluid to
another. The fluid may be separated by a solid wall, so that they are never mixed,
or they may be in direct contact. Heat exchangers may be classified according to
their flow arrangement. In parallel-flow heat exchangers, two fluids enter the
exchanger at the same end, and travel in parallel to the other side. In counter-
![Page 59: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/59.jpg)
Chittagong 2x660MW CFPP Project Page No : 59 of 94
Pre-Proposal
flow heat exchangers the fluids enter the exchanger from opposite ends. The
counter-flow design is more efficient, in that it can transfer the most heat from the
heat (transfer) fluid.
- Types of heat exchangers
The shell and tube heat exchanger is the most common type of heat exchanger
in large coal fired power plants, and is suitable for higher-pressure applications.
This type of heat exchanger consists of a shell (a large pressure vessel) with a
bundle of tubes inside of the shell. One fluid runs through the tubes, and another
fluid flows over the tubes (through the shell) to transfer heat between the two
fluids.
- Shell and tube heat exchanger
Feed water is at a high pressure so that a shell and tube heat exchanger is
applied. In this case, feed water flows inside of the tube and extracted steam and
its condensate flows outside of the tube. There can be many variations on the
shell and tube design. Typically, the tubes are bent in the shape of a U (called U-
tubes) and the ends of each tube are connected to water boxes divided by a
partition sheet.
U-tube heat exchangers are the most common type of heat exchanger in coal
fired power plants and will be applied in this project.
- Selection of tube material
To be able to transfer heat well, the tube material should have good thermal
conductivity. Because heat is transferred from the hot to cold side through the
tubes walls, there is a temperature difference through the width of the tubes.
Because of the tendency of the tube material to thermally expand differently at
various temperatures, thermal stress occurs during operation. This is in addition
to any stress from high pressures from the fluids themselves. The tube material
should also be compatible with both the shell and tube side fluids for long periods
under the operating conditions(temperatures, pressures, pH, etc.) to minimize
deterioration of the tubes, such as corrosion.
All of these requirements call for a careful selection of strong, thermally-
conductive, corrosion-resistant, high quality tube materials, typically metals,
including copper alloy, stainless steel, carbon steel, non-ferrous copper alloy,
Inconel, nickel, has tally and titanium. Materials would be chosen in consideration
![Page 60: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/60.jpg)
Chittagong 2x660MW CFPP Project Page No : 60 of 94
Pre-Proposal
of fluid handled. An inadequate selection of tube material might result in a leak in
the tube between the shell and tube sides causing fluid cross-contamination and
possibly loss of pressure.
11.8 Coal and Ash Handling System
11.8.1 Coal Handling System
The coal is transferred to the coal yard via trucks or any other methods by others.
Coal in the coal yard is handled by stackers/reclaimers. Portable device could be
used in case of unserviceability of stackers/ reclaimers.
(1) Consumption of the Coal (Design Conditions)
The coal yard is assumed to be an open type. The storage nominal capacity of the
coal yard is specified to meet coal consumption for required days (incl. margin)
with continuous operation with a capacity factor of 100% of two units at the rated
output. The number of days for storing the quantity of the coal takes a margin of 20%
into consideration, assuming that receiving coal by others may be prevented for
about 80% of required days a year due to the interference of cyclones every year.
(2) Nominal Capacity of the Coal Yard
The coal yard is of open type. The storage nominal capacity of the coal yard is
specified to meet the coal consumption for approximately 60 days of continuous
operation with a capacity factor of 100% of two units at the rated output. The
number of 60 days for storing the quantity of the coal takes a margin of ten days
into consideration, assuming that receiving coal by others may be prevented for
about 24 days a year due to the interference of cyclones every year.
(3) Nominal Capacity of the Stackers/Reclaimers
a) Nominal Capacity of the Stackers
Stackers will be provided with proper capacity to pile coals for storage.
b) Nominal Capacity of the Reclaimers
The coal handling system is planned to be operated continuously for 24 hours.
The nominal capacity of the reclaimer is estimated so that the required amount
per day of coal can be supplied in required hours.
c) The number of the Stackers/Reclaimers
The number of stackers/reclaimers shall be several sets in consideration with
![Page 61: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/61.jpg)
Chittagong 2x660MW CFPP Project Page No : 61 of 94
Pre-Proposal
operability, and they will be installed between respective piles.
(4) Nominal Capacity of the Discharge Conveyor
The capacity of the discharge conveyor has to be designed so as to meet the
capacity of their reclaimer with a margin. It is a definite requirement that the unit
has to be continuously operated even if one discharge conveyor is out of order.
For this purpose, the number of discharge conveyors must be two, including one
spare.
Moreover, the type of the conveyer will be a ground type that can be easily
inspected.
(5) Conveyor Type Selection
The flat type conveyor will be applied to this project. After the plot plan is
determined in the detailed design stage, the conveyor specification will be given
further consideration.
11.8.2 Ash Handling System
In general, ash in coal is captured in various parts in the flue gas flow in the course of
the combustion of coal in the boiler until the flue gas is discharged from the stack.
- The ash which is melted by the coal combustion falls to the bottom hopper of the
boiler furnace and is captured. This is called clinker. About 10 - 20% of the amount
of all ash is captured in this way.
- A part of the combustion ash which floats in the flue gas falls to the bottom hopper
of the economizer and the air heater in the downstream of flue gas and is captured.
This combustion ash is called cinder ash. 5% or less of the amount of all ash is
captured here.
- The combustion ash which is captured by the electrostatic precipitator is caught in
the bottom hopper of the electrostatic precipitator. It is called fly ash. In general, 80
- 90% of the amount of all ash is captured here.
The collected coal ash is generally transported and processed through ash handling
systems that may be roughly categorized into two systems as follows.
- The first system handles clinker that falls to the bottom hopper of the boiler and the
pyrite exhausted from the coal pulverize.
- The second system handles the cinder ash and fly ash that falls to the bottom
![Page 62: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/62.jpg)
Chittagong 2x660MW CFPP Project Page No : 62 of 94
Pre-Proposal
hopper of the economizer, air heater and electrostatics precipitator.
(1) Bottom Ash Handling System
The water sealed drag chain system handles clinker ash that falls to the bottom
hopper of the boiler and the pyrite exhausted from the coal pulverizer. The clinker
that falls to the bottom hopper of the boiler is collected using the water sealed
conveyor and is dehydrated for transport to a bottom ash bunker for temporary
storage. The pyrite flows into the bottom of the ash bunker. The clinker ash and
pyrite are transported to the ash disposal pond by belt conveyer or trucks in order
to keep the power station roads clean.
(2) Fly Ash Handling System
The vacuum – pneumatic system handles the cinder ash and fly ash that falls to
the bottom hoppers of the economizer, air heater and electrostatic precipitator. The
cinder ash and fly ash are transported to intermediate ash silos using a vacuum
and transported from intermediate ash silos to the fly ash silos for temporary
storage using compressed air. Finally, the fly ash is transported to the ash disposal
pond by belt conveyer or trucks in order to keep the power station roads clean.
(3) Nominal Capacity of the Ash Pond
The nominal capacity of the ash disposal pond is calculated based on the total
volume of the ash to be accumulated for the total operating duration with 80%
capacity factor of two units.
Various studies have been conducted regarding effective utilization of coal ash
produced in large quantities in the boiler, and the following uses have proven
practical.
- Clinker: road bed material
- Fly ash: material for cement, concrete aggregate, road pavement, fertilizer
11.9 Cooling water system
Circulating water system supplies cooling water from sea to condenser, and also
transfers from condenser to sea using circulation water pump (CWP). CWP is
installed near the sea intake system, and the pump supplies necessary circulating
water flow for heat transferred by condenser, CCCW cooler and condenser vacuum
pump cooler.
4 x 25% CWP per plant which is vertical type driven by motor shall be installed. The
![Page 63: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/63.jpg)
Chittagong 2x660MW CFPP Project Page No : 63 of 94
Pre-Proposal
equipment will be located outdoor and subject to the environmental conditions.
Each pump intake structure is prepared per the recommendation of the design
standard of the Hydraulic Institute Standards. The facilities will be designed to meet
the specified intake structures design conditions.
The intake structure for purification of intake seawater consists of four (4) x 25%
chambers of screening channel. It will be provided with traveling band screens, bar
screens, and a stop log. Each channel will be interconnected by an opening of
division wall of intake structure at CW inlet chamber of intake structure.
11.10 Stacks
Stacks are a common facility for Units 1 & 2.
(1) Foundation
The foundation is of a mat foundation (shape octagonal) type
(2) Concrete windshield
The windshield is made of reinforced concrete. It protects the inner flues form
wind-force, seismic-force and other forces.
(3) Inner flues
The cast able lining type is selected for this project from the viewpoint of the
availability and cost of the material.
- Cylinder: Two cylinders (an extension of the cylinder of Unit 2 is expected in the
future)
- Material: SS400
(4) Platform and ladder
Ten platforms are set up inside the windshield for maintenance of the stack.
A ladder is also set up inside the windshield for access to the platforms.
(5) Ventilation system
Natural ventilation is provided for maintaining the inside temperature during
maintenance in good conditions.
(6) Aeronautical light
An aeronautical light system and aircraft warning light will be provided based on
the regulation.
(7) Lightning
Lightning protection will be set up on the top of the stack.
11.11 Civil Works
![Page 64: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/64.jpg)
Chittagong 2x660MW CFPP Project Page No : 64 of 94
Pre-Proposal
11.11.1 Site Preparation work
11.11.1.1 Survey and Geotechnical Soil Investigation
1) Site Surveying
Topographical survey will be conducted to verify the existing site condition
Survey works will include the following.
- Triangulation & Traverse Survey
- Leveling Survey
2) Hydro-Oceanographic survey
Most thermal power plants are usually located along the coastlines to provide an
adequate source of cooling water for the plant. As a result, potential damage from
oceanographic events must be reviewed. Protection against these events must be
incorporated into the design to ensure plant safety and uninterrupted plant
operation.
The major hydro-oceanographic event which must be considered during plant
design consists of astronomical tide, wind wave, current and so on.
The purpose of these surveys is to check the safety by over the oceanographic
events.
- Tidal level observation
- Tidal current observation
- Buoy tracking
- Measurement of temperature, collection of soil under/on the sea bed
- Measurement of salinity, sea/soil resistivity for cathodic protection
- Simulation for wind wave prediction (Design wave)
- Simulation for Thermal diffusion prediction
- Simulation for bottom sediments transport prediction
- Bathymetric survey
![Page 65: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/65.jpg)
Chittagong 2x660MW CFPP Project Page No : 65 of 94
Pre-Proposal
3) Geotechnical Soil Investigation
The Main purpose of geotechnical soil investigation is to explore the subsurface
stratigraphy and to obtain foundation design criteria and construction
recommendations.
- Field Investigation
- Boring
- Sampling
- In-situ test
- Laboratory
- Index property test
- Structural property test
- Chemical property test
11.11.1.2 Determination of Site Elevation
The existing site ground level is supposed to be +1.0m M.S.L. And according to
the record of storm surge in Bangladesh, the actual surge height observed in
period of near 50 years is 7.6m (April 1991, Chittagong Patenga).Based on that,
the Site Elevation is determined as below H.W.L + 50 year return period of
previous highest record = 2.2m M.S.L + 7.6m M.S.L = 9.8m M.S.L => +10.0m
M.S.L
Figure 11.3-1 Plant Embankment level
![Page 66: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/66.jpg)
Chittagong 2x660MW CFPP Project Page No : 66 of 94
Pre-Proposal
Embankment will be executed from the existing ground level to the determined
level.
The amount of embankment shall be determined after receiving site layout and
topographic survey data.
11.11.1.3 Soil improvement
The existing ground strata is supposed to be very soft as the typical soil condition
of other neighboring seaside in Bangladesh.
The purpose of soil improvement is to increase the shear strength of the soil, to
reduce the soil compressibility and the permeability of the soil prior to construction
and completed plant load, and prevent potential damage to the structures by
Differential settlements.
If the embankment is completed, the probability of consolidation settlement and
circular slip are very high. The vertical drain method is generally used as an
improvement method. But the method of soil improvement shall be determined
after geotechnical investigation. The features of potential vertical drains methods
are as below.
Table 11.8-1 Features of vertical drains
Item PBD
(Plastic Board Drain)
PSD
(Pack Sand Drain)
Illustration
Advantage
. Deep Penetration (>50m)
. Rapid installation
. Low Cost
. Low well resistance
. Rapid installation
(4or 6 drains simultaneously)
Disadvantage
. Decrease of discharge capacity
(3yr)
. Deterioration by hot
competition
. shallow penetration (<30m)
. High cost relatively
. Poor penetration in sharp
transition
![Page 67: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/67.jpg)
Chittagong 2x660MW CFPP Project Page No : 67 of 94
Pre-Proposal
Table 11.8-2 Features of vertical drains
Item SD
(Sand Drain) FD
(Fiber Drain)
Illustration
Advantage
. Good penetration into stiff layer
. High discharge capacity in long
term
. Hard to sever by lateral force
. Environment- friendly
Disadvantage
. Difficulty in sand supply
. High cost
. Slow installation
. Rare practices
. High cost relatively
. Uncertain hydraulic properties
11.11.2 Intake and Discharge
11.11.2.1 General
The Once-through cooling system will be adopted where cooling water is taken
from the sea and moved to condenser for heat exchange and then discharge back
again to the sea.
The civil part of primary components in cooling water system consists of the
following;
Sea water Intake conduit velocity cap
Sea water Intake conduit
Sea water Intake structure
Seal pit
Discharge system
Outfall
11.11.2.2 Sea water Intake Conduit Velocity Cap
The sea water intake conduit velocity cap can be installed at a near point of
offshore.
The safety screen bar will be installed in the entrance of intake basin to exclude
various life stages or fish or other aquatic organisms.
![Page 68: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/68.jpg)
Chittagong 2x660MW CFPP Project Page No : 68 of 94
Pre-Proposal
The Intake Head is precast concrete structure build on the ground and placed in
target position with caution. It should be connected to intake pipeline and protected
by Armor stone surrounded.
11.11.2.3 Sea water Intake conduit
The sea water intake conduit can be used pipe or concrete box. As an aspect of
processing period, pipe is suitable to use.
Figure 11.3-2 Figure of Conceptual Intake with a velocity cap headworks
11.11.2.4 Sea water Intake structure
The intake structure is concrete structure and constructed so that it can maintain
the minimum water level and supply the sufficient amount of water to the pump
under L.W.L sea water level condition.
![Page 69: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/69.jpg)
Chittagong 2x660MW CFPP Project Page No : 69 of 94
Pre-Proposal
Figure 11.3-3 recommended intake structure layout [ANSI/HI 9.8-1998]
Figure 11.3-4 Filter wall details for proper bay width [ANSI/HI 9.8-1998]
![Page 70: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/70.jpg)
Chittagong 2x660MW CFPP Project Page No : 70 of 94
Pre-Proposal
11.11.2.5 Seal pit
Primary function is to prevent the influx of air at the discharge conduit and to
maintain the siphon head at the condenser.
Upstream head height above weir crest to maintain siphon head should be
considered backwater and overflow water depth for the minimum flow rate. Seal pit
structure will be a reinforced concrete structure.
11.11.2.6 Discharge system
The open channel type of surface discharge system along the shoreline might be
suitable. And the dispersion study of the discharge water shall be conducted to
confirm the sea water temperature conditions.
11.11.2.7 outfall
The outfall will be a reinforced concrete structure.
At the outfall natural spreading occurs due to diffusion of turbulence with an angel
of about 10˚ related to the axis of the discharged jet. The mean velocity is reduced
accordingly. When the outlet structure opening is steeper than this diffusion anger,
no reduction of the flow will take place (see Fig. 11.3-5). In this case calming
elements are required (sea Fig 11.3-6).
Figure 11.3-5 Velocities at outfall structure with surface discharge
![Page 71: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/71.jpg)
Chittagong 2x660MW CFPP Project Page No : 71 of 94
Pre-Proposal
Figure 11.3-6 Hydraulic concept of forced spreading at outlet structure
Figure 11.3-7 Flow Diagram of Cooling Water System
![Page 72: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/72.jpg)
Chittagong 2x660MW CFPP Project Page No : 72 of 94
Pre-Proposal
11.11.2.8 Building and Equipment Foundation
The foundation type will be applied on the shallow foundation or deep foundation
according to result of soil investigation. And the foundation will be designed per the
requirements of the American Concrete Institute ACI318 “Building Code
Requirements for Reinforced Concrete”.
The shallow foundation is unit that provides support for a structure by transferring
loads to soil or rock at shallow depths (Such as strip, pad grillage, mat foundation
etc.). The load transfer is primarily through shear resistance of the bearing strata.
Table 11.8.3 Type of shallow foundation
Strip foundation(Wall footing) Pad foundation
Grillage(Beam) foundation Mat foundation
The deep foundation is unit that provides support for a structure transferring loads
by end bearing and/or by shaft resistance at considerable depth below the ground
(Such as pile foundation, slurry wall etc.).
![Page 73: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/73.jpg)
Chittagong 2x660MW CFPP Project Page No : 73 of 94
Pre-Proposal
The foundation will be designed to keep the maximum soil or rock pressures within
safe bearing values. To prevent unequal settlement footing will be designed to
keep the bearing pressure as nearly uniform as practical.
Final design of all site development and foundation type will be based on the
results of a comprehensive subsurface investigation program.
Table 11.8.4 Type of deep foundation
Pile foundation Slurry wall
For purposes of design, every structure and foundation will be designed to resist
the overturning, hydrostatic uplift, and sliding effects caused by applied forces.
Stability analyses will be performed by superimposing all appropriate loads for
each of the conditions being investigated in accordance with standard engineering
practice as governed by applicable codes and standards.
a) Sallow foundation stability: Use only service loads to resist the applied forces. Use
minimum factors of safety as follows:
- Minimum factor of safety against compression failure : 3.0
- Uplift (wind, seismic or hydrostatic) : 2.0
- Overturning (wind, seismic, or other) : 1.5
- Sliding (wind, seismic, or other) : 1.5
b) Bearing Capacity: Maximum bearing pressure will not be greater than the
allowable bearing pressure. Equipment foundation deflection (settlement) will be
limited to a maximum of 25 mm (1.0-inch) of total deflection. More stringent
deflection (settlement) criteria shall be used as required for a proper installation
and /or to comply with equipment manufacturer’s criteria.
![Page 74: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/74.jpg)
Chittagong 2x660MW CFPP Project Page No : 74 of 94
Pre-Proposal
c) Deep Foundations stability
- Compression – Minimum factor of safety : 3.0
- Uplift – Minimum factor of safety : 2.0
- Reduce pile or drilled shaft capacities to account for spacing and group effects.
- Foundations resisting lateral loads shall be designed to maintain lateral deflections
below limits which will not create detrimental lateral deflection of the structure or
equipment supported thereon.
- Verification of the allowable capacity of piles will be determined by full-scale
field load tests performed prior to installing production piles.
11.11.3 Road & Paving
The road will be located throughout the plant and central to load. Some lighting
may be installed.
Roads are classified in two classes. Road widths, radius of corners, curves and
pavement will be designed to be entirely suitable for the sizes of vehicles.
We propose two road types as shown in the table below.
Table 11.8.5 Type of deep foundation
Road type No. of Lanes(m) Minimum radius(m)
TYPE-A 8.0 10.0
TYPE-B 6.0 10.0
Type-A roads will consist of two 3.00 meter asphalt pavement lanes. The main
plant roads will be type-A roads.
Type-B roads will consist of one 4.00 meter asphalt pavement lane. Access
roads to equipments and buildings will be type-B roads.
The cross slope of the road will be 2.0% and maximum grade of road will be 5%.
The road pavement structure of the particular road sections will be designed
based on the expected maximal weight and size of the components / material to
be delivered or transport from the plant. And will be designed for AASHTO.
11.11.4 Site Drainage
a) General Description of Storm water Drainage System
The plant will be provided with the following runoff drainage systems:
- Clean storm water runoff
![Page 75: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/75.jpg)
Chittagong 2x660MW CFPP Project Page No : 75 of 94
Pre-Proposal
- Oil-contaminated runoff and discharges
- Chemical contaminated runoff and discharges (plant process waste)
b) Clean storm water runoff
Open surface drains will be used to convey clean storm water from the ditch
and underground storm water piping. Typical clean storm water flows
include runoff from road, grassed areas, building roof drains.
c) Oil-contaminated runoff
An Oil/Water Separator System will be provided to collect discharges from
the following sources:
- Outdoor oil pumping areas
- Maintenance shop
- Transformers
d) Chemical contaminated runoff
Contaminated storm water runoff is storm water collected from areas that
contain hydrocarbons or chemicals and is directed to the wastewater
treatment system. Typical areas requiring collection of contaminated storm
water runoff include the following:
- Hydrocarbon and chemical storage areas
- Fuel storage areas
- Sewage treatment
e) The sanitary wastes are collected by gravity whenever possible.
Wastewater is treated to the required criteria for the final disposal.
11.12 Building List
No. Building List
1 Turbine Building (including T/G FND.)
2 Main Control Building
3 Warehouse
4 Water & Waste Water Treatment Building
5 Administration Building
6 FGD Control Building
7 Switchyard Control Building
8 Electro-chlorination Building
9 Coal Handling Control & Switchgear House
10 Guard House
11 Service Gas Storage Shelter
![Page 76: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/76.jpg)
Chittagong 2x660MW CFPP Project Page No : 76 of 94
Pre-Proposal
11.13 Electrical Equipment
11.13.1 Conceptual Design of the Unit Electrical System
The configuration of the power plant consists of two boilers, two steam turbines
and two generators. Each generator shall be connected to the Generator Step-
Up Transformer (GSUT) by an Isolated Phase Bus duct (IPB) respectively. The
voltage of the power output from the generator shall be stepped up to 400kV by
GSUT. The output from the GSUT shall be transmitted to the Bangladesh
network via the 400kV switchyard located next to the power plant area.
A generator main circuit breaker located at the GSUT low voltage side shall be
introduced. Therefore, each generator shall be synchronized with the
Bangladesh network by a generator circuit breaker located at the GSUT low
voltage side respectively.
The design criteria for configuration, size and rating of components of the unit
auxiliary power distribution system are as follows:
1) A single event (either a planned or forced outage of a piece of equipment) shall
not cause the loss of the generating unit, but may lead to reduced output of the
unit.
2) For voltage levels 400V and above, except for the case of single-ended
switchgear, it shall be possible for any switchgear power supply to transfer
safety either automatically or manually as applicable from one source to the
alternate source under normal operating conditions, without having to black-out
the switchgear.
3) Loss of the transformer (other than the generator step-up transformer and
excitation transformer) shall not lead to an output of the generating unit. The
failure of a unit transformer may cause the loss of the generating unit until such
time as the faulty unit transformer is isolated and the unit can be restarted from
a healthy transformer.
4) Loss of the switchgear bus bar, normally fed from the unit transformers shall
lead to a power output reduction of generation less than 50% and shall not
cause a loss of the generating unit.
Each unit shall be provided one three-winding Unit Auxiliary Transformers (UAT)
and branched from the generator main circuit by IPB connection.
The UAT shall be connected to the two unit 6.6kV switchgears and the two
![Page 77: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/77.jpg)
Chittagong 2x660MW CFPP Project Page No : 77 of 94
Pre-Proposal
common 6.6kV switchgear via a circuit breaker respectively via a circuit breaker
respectively.
Both of the unit 6.6kV switchgear and the common 6.6kV switchgear shall be
interconnected via a circuit breaker respectively.
During the unit operation, the power source to the unit auxiliary loads shall be
fed from the generator output via a unit auxiliary transformer. During the unit
shut down and the unit start up, the power source to the unit auxiliary loads
shall be fed from the 400kV switchyard via the startup transformer.
Before de-synchronizing the generator, the power source to the unit auxiliary
loads shall be transferred from the unit 6.6kV switchgear to the common 6.6kV
switchgear, and after synchronizing the generator, the power source to the unit
auxiliary loads shall be transferred from the common 6.6kV switchgear to the
unit 6.6kV switchgear.
11.13.2 Generator
The overview requirements of the generator are shown below
Item Specification
Number of generators 2 (unit 1 and unit 2)
Type Three phase field rotating synchronous
Number of poles 2
Number of phases 3
Rated output 660MW
Rated frequency 50Hz
Rated speed 3,000rpm
Rated terminal voltage Manufacture’s standard (18 – 25kV)
Power factor 0.80 (lagging), 0.95 (leading)
Short circuit ratio Not less than 0.5
Cooling method Water or H₂gas direct cooling for stator coil
H₂gas direct cooling for rotor coil
Type of excitation system Static or brushless excitation system
![Page 78: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/78.jpg)
Chittagong 2x660MW CFPP Project Page No : 78 of 94
Pre-Proposal
11.13.3 Transformer
1) Generator step-up transformer (GSUT)
The GSUT shall be oil immersed type and shall be fitted with On Load Tap
Changer (OLTC) on the high voltage winding, having a range sufficient to
allow for the voltage variation at transmission voltage (400kV) and the
transformer regulation.
The GSUT shall be provided with Oil Natural Air Forced (ONAF) cooling.
The GSUT shall be rated to match the generator output.
2) Unit Auxiliary Transformer (UAT)
The UAT shall step down the voltage from the generator terminal voltage to
6.6kV, to provide power supply to the unit auxiliaries.
The UAT shall be oil immersed and shall be fitted with On Load Tap Changer
(OLTC) on the high voltage winding with automatic voltage regulator, having a
range sufficient to allow for the voltage variation at generator terminal voltage
and the transformer regulation.
The UAT shall be provided with Oil Natural Air Forced/ Oil Natural Air Natural
(ONAF/ONAN) cooling.
Sizing of the UAT shall be based on the total unit load.
11.13.4 Generator Circuit Switching Devices
The generator circuit breaker and the disconnecting switches with earthing
switches shall be provided at the low voltage side of the GSUT for the generator
synchronization with the Bangladesh network.
11.13.5 Unit Electric Supply
The unit electric supply shall be configured from unit auxiliary transformer. The
unit load for plant operation shall be powered from the unit transformer and the
common load for plant operation, such as water handling, waste water handling;
coal handling, etc.
Moreover, as an electric power source for emergencies, one set of diesel
engine driven generators shall be provided for the purpose of safety shut down
of the unit.
11.13.6 6.6kV Unit and Common Metal Clad Switchgears
![Page 79: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/79.jpg)
Chittagong 2x660MW CFPP Project Page No : 79 of 94
Pre-Proposal
Two sets of 6.6kV unit metal clad switchgears and two sets of common 6.6kV
metal clad switchgears shall be provided for power supply to the unit auxiliary
loads and the common auxiliary loads.
Each unit switchgear and each common switchgear shall be powered from the
unit auxiliary transformer secondary winding respectively.
The unit switchgear and the common switchgear shall be interconnected via
bus-tie circuit breaker respectively for the purpose of a back-up power supply
vice versa.
11.13.7 415V Unit and Common Switchgears
Several 415V unit and common switchgears shall be provided for power supply
to the unit auxiliary loads and the common auxiliary loads.
Each switch gear shall be powered from 6.6kV switchgear via 6.6kV/415V low
voltage transformer respectively. The unit switchgear and the common
switchgear shall also be interconnected via bus-tie circuit breaker respectively
for the purpose of a back-up power supply vice versa.
11.13.8 400kV Switchyard
400kV switchyard shall be provided next to the power plant area for delivery of
the generating power to the Bangladesh network. This switchyard will be
interconnected with the Bangladesh network by two circuits of new 400kV
transmission lines.
a) Design Concept
In order to maintain the reliability of the switchyard, the 400kV bus bar system
shall preferably be double bus with 1+1/2 circuit breaker configuration of outdoor
type.
The switchyard shall be designed to be able to connect six circuits, consisting of
two circuits for transmission lines, two circuits for unit 1 and Unit 2. The circuit
breaker shall be the type of gas insulation breaker (GCB) and the disconnecting
switch shall be the type of air insulation switch (AIS).
This switchyard is owned by PGCB and the control and monitoring of this
switchyard equipment shall be done from NLDC by remote control.
Quantity of main equipment
![Page 80: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/80.jpg)
Chittagong 2x660MW CFPP Project Page No : 80 of 94
Pre-Proposal
The quantity of the main equipment is as follows:
Circuit Breakers (3-phase) 6 sets
Disconnecting switches (3-phase) 16 sets
Earthing Switches (3-phase) 16 sets
Current Transformers (3-phase) 12 sets
Voltage Transformers (3-phase) 4 sets
Lightning Arresters (3-phase) 2 sets
In addition to the above, other equipment including the control equipment is
required. The switchyard equipment shall be controlled and monitored from NLDC
by remote control through the Substation Control System (SCS) located in the
switchyard.
Equipment and its location
Control building at the switchyard
Bay Control Unit (BCU) In the control building at the
switchyard or switchyard
Station Control System (SCS) In the control building at the switchyard
SCADA (RTU) In the control building at the switchyard
Protection relay in the control building at the switchyard
AC and DC auxiliary power in the control building at the switchyard
System including battery (power source will be fed from the
power plant)
11.14 Instrument and Control
The intent of the control and instrumentation specifications is that integrated system will
be installed allowing highly automated, centralized control and monitoring of the whole
Plant from the control systems Hyman-Machine Interfaces (HMI) located in a Central
Control Room (CCR). For reference purpose in this specification, this system will be
referred to as the DCS.
11.14.1 System Configuration of the instrumentation and control system
The DCS will be a distributed, microprocessor-based system for boiler
![Page 81: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/81.jpg)
Chittagong 2x660MW CFPP Project Page No : 81 of 94
Pre-Proposal
combustion and miscellaneous modulating control systems (CCS); burner
management system (BMS); & boiler protection system (BPS); motor control
system (MCS); LCD-based operator interface; configured and complete with all
system equipment and programs, hardware and software, and all related
equipment and appurtenances to meet the functional and operational
requirements, as hereinafter specified.
The scope of supply will include design, manufacture, hardware selection,
assembly, control optimization, configuration, programming, documentation,
testing, training, information transfer, delivery, spare parts/special tools, and
field services as required.
The DCS will include communication links for interfaces to the following:
• PLC-based Systems and Micro processor-based Systems (e.g.coal handling,
water treatments, ESP, etc.)
• Load Dispatching–Power
• Plant Master Clock with GPS
• Turbine control system
• Continuous emission monitoring system
• Vibration Monitoring and Analyzing System
• Etc.,
1) Technical Requirement
a) System Configuration
The DCS will be distributed functionally to the greatest possible extent. The
segregation for each of the two (2) units DCS will be as follows:
• Motor control/sequential logic (MCS)
• Boiler combustion controls (CCS)
• Burner control furnace safety system (BMS) & boiler protection system (BPS)
• Interface with other systems
b) System Communication
A dual redundant data highway (network) will be used to transmit data among
stations. Both data highways will be in continuous operation. Fiber optics will be
utilized to the greatest extent possible.
Fault-tolerant redundant data highway communication system including data
![Page 82: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/82.jpg)
Chittagong 2x660MW CFPP Project Page No : 82 of 94
Pre-Proposal
communication interfaces with other control and monitoring system.
All hardware, software and responsibility for the establishment of digital data
communication link of DCS and other control systems such as STG and BOP
auxiliary systems, etc. The data communication networks are designed so that
the communication speed is sufficient to support control and monitoring function
for the interface system.
c) Operator Interface, Graphics, and LCD-Based
All DCS control, monitoring, and diagnostic functions will be available
through the DCS operator interface.
The operator workstation will allow use of multi-tasking, multi-user operating
systems that provide the real-time deterministic response required for process
control applications. The workstations will support standard LAN protocols such
as Ethernet TCP/IP or similar.
Operator's workstation will be composed of color LCD monitors and keyboards.
During performing functional operations by the operator, the procedure will be
as simple as possible and concise information of the procedure will be
incorporated with the LCD display. Through the operator's workstation the
operator will be able to command all printers and other peripheries.
d) Historical Data Collection, Storage and Presentation
A Historical Data Collection, Storage and Presentation (Historian) System will
fully automate the collection, storage and presentation of plant data. The
Historian will provide a centralized collection of information, a real-time
database and a historical data archive. The Historian will interface with all of the
plant real-time systems simultaneously and will be capable of reading and
writing to these systems. The system will store to an adequately sized storage
medium with a printer and necessary software.
2) Integrated Engineering Work Station
EWS(Engineering Workstation) function is the following:
• For fault finding, programming facilities such as boiler, steam turbine and BOP
• Test, configure process interface modules/cards
• Generate control software through logic diagram
• Diagnostic programs
• Fault detection through diagnostics
![Page 83: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/83.jpg)
Chittagong 2x660MW CFPP Project Page No : 83 of 94
Pre-Proposal
3) DCS function of the Power Plant
• The DCS shall have the following functions:
• Plant interlock system
• Boiler control system
• Burner management system
• Turbine control system
• Plant auxiliaries interlock and sequence control system
• Data acquisition historical storage and retrieval system
11.14.2 Control and Operation Philosophy
During normal operation the main operator functions will be selection and
supervision of the appropriate Plant configuration to meet the electrical load targets.
Start-up and normal shutdown of the Plant will remain directly under the operator’s
control by management and coordination of the start-up and shutdown sequences of
the various plant areas. Automation of the Plant start-up sequences for individual
Plant areas will be provided. The Plant controls must also automatically manage
between different load cases without excessive deviation from the various set
points for load demand signaled from the load dispatcher to the Plant DCS.
1) Plant Automation
The degree of automation is to be such that the total time required for
starting/stopping, the quality of key control parameters, and the protection of the unit
shall be made by the automation equipment, not by the operator intervention.
All the operations required from the preparation of plant start up such as operation
of circulating water system, auxiliary steam system, clean up condensate system,
etc., to the rated load and vice versa without interruption, for loading, unloading and
governing transient conditions shall be fully automated.
The startup/shutdown procedures including draining and venting of the plant shall be
selectable and controlled automatically according to the plant status such as restart,
hot start, warm start and cold start respectively.
Also, to minimize the operation procedures in starting and stopping, efforts shall be
made by the Supplier to simplify the design consistent with the need for any special
components to facilitate boiler/turbine temperature matching.
The starting and stopping procedures of the plant are to be divided into some break
points at which operator intervention is required to make procedures to the next
![Page 84: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/84.jpg)
Chittagong 2x660MW CFPP Project Page No : 84 of 94
Pre-Proposal
operation stage. When the plant automation system is failed, normal operation of the
plant shall be still available by operator from central control room.
The Plant's instrument and control systems shall be designed to provide for the
reliable safe and efficient start-up, operation. shutdown and emergency shutdown of
the Plant and its auxiliaries. The Plant DCS shall be the primary operational,
monitoring and controlling point for all installed equipment including STG and other
equipment furnished with PLC or other proprietary control systems.
2) Design Conditions
The instrumentation and control equipment will fulfill the general technical
requirements. The type and make of equipment will be internationally proven in
steam power plants. The plant instrumentation and control equipment will be
selected and designed in such a way that the following functions will be performed
for each power unit.
a) Automatic start-up of the unit, automatic boiler ignition and loading, turbine
rolling-up, generator synchronizing and turbine generator loading up to the
preselected load.
b) The automatic start-up procedure will also include all unit auxiliary equipment.
c) Unit automatic start-up will be accomplished by hierarchical function group
control system in coordination with automatic analogue control system.
11.15 Water and Wastewater Treatment System
11.15.1 Desalination plant and Water treatment plant
Service water is utilized as the source of demineralized water for boilers,
cooling water for equipment, ash disposal and firefighting, etc.
There is no source of fresh surface water in the vicinity of the site, and
underground water is no suitable to draw a sufficient amount of water given
possible adverse effects, such as the drying up of wells in the vicinity of the site
and subsidence of the ground.
Therefore, a desalination plant is required to produce service water
The desalination plant and demineralization plant will treat sea water by
reaction and coagulation, pretreatment (DAF or equiv.), Multimedia Filter (MMF),
SWRO system, Ion Exchanger and Mixed Bed Polisher(MBP) system.
![Page 85: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/85.jpg)
Chittagong 2x660MW CFPP Project Page No : 85 of 94
Pre-Proposal
The sea water is supplied to pretreatment system by sea water feed pump. The
sea water is passes through coagulation and pretreatment system for the
removal of particulate organic and colloidal material. And then treated sea water
by pretreatment system is transferred to MMF filter for removal of suspended
solids.
The filtered water is supplied to cartridge filter by the demi system feed pumps,
and then to the SWRO unit by SWRO high pressure pump for desalination.
Permeate from SWRO will be used as service water, potable and firefighting
water.
Desalinated water will be used to produce potable water. To sterilize the water,
hypochlorite will be applied. And rest of desalinated water from SWRO unit is
transferred to Ion Exchanger and MBP system for demineralization. The brine
water from the SWRO unit is discharged directly to the discharge pond to the
sea. The regeneration waste water from demineralization plant is discharged to
the abnormal waste water storage pit.
Desalination system and Water treatment plant will have controls and
monitoring functions for each stream during operation and chemical cleaning
process. System will have provisions of control locally.
System compositions
• Desalination Plant
- Pretreatment (DAF or equiv.) system
- Pre-treated water pond
- Multimedia Filter system (MMF)
- 1’st filtered water tank
- SWRO unit
- CIP (Cleaning) system
- Chemical injection system for SWRO
- Desalination water storage tank
The desalinated water will be further demineralized in Ion exchanger (2B3T)
and MBP system as the make-up water supply to demineralized water
![Page 86: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/86.jpg)
Chittagong 2x660MW CFPP Project Page No : 86 of 94
Pre-Proposal
consumers.
The finally treated water by demi water system is managed by silica,
conductivity value and flow transmitter where treated water is transferred to
demineralized water tank.
The demineralization system will be complete with a chemical injection and
storage system consisting of sodium hypochlorite, sodium hydroxide,
hydrochloric acid, assorted chemical dosing pumps and mixing agitators, etc.
The water designated to feed the power plant will be supplied from sea. The
characteristics related to the seawater are presented in following table. This
seawater analysis is only reference. Any change in the sea water analysis will
affect the design.
Note) This proposal is based on the above seawater analysis data.
Under the above operating conditions the final quality of the demineralized
water will meet the following (this value have been assumed. If necessary, it will
be changed later) ;
• Silica, mg/l as SiO2 : less than 0.02
• Conductivity, μS /cm : less than 0.2
• pH : 5.5 – 7.5
The demineralization plant will be housed indoors and have controls and
monitoring functions for each stream during operation and regeneration process.
System compositions
• Demineralization System
- Ion exchanger (2B3T)
- Mixed bed exchanger
- Regeneration system
- Chemical injection system for demineralization plant
![Page 87: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/87.jpg)
Chittagong 2x660MW CFPP Project Page No : 87 of 94
Pre-Proposal
11.15.2 WASTE WATER TREATMENT PLANT
The waste water originating from the power plant can be classified into three
categories such as normal waste water, abnormal waste water and oily waste
water.
The waste water generated from each source of the power plant will be
collected to the wastewater storage pit and then will be treated by the pH
control method with chemical and sedimentation method.
The capacity of the wastewater system will be in accordance with Contractor’s
water balances and will be designed system capacity
The normal wastewater is generated from desalination system and water
treatment system, sump pits of power plant, etc. Normal wastewater will be
collected in the Normal waste water storage pit. Wastewater is equalized and
mixed by aeration in the pit, then it will be transferred to clarifier for wastewater
via pH reaction tank, coagulation tank. The wastewater will be neutralized in the
pH reaction tank by means of acid and caustic dosing which is controlled pH
analyzer located on pH reaction tank. After pH adjustment, chemical of
coagulant and coagulant aid will be injected in coagulation tank in order to
flocculate particulates, organics and etc. The floc is settled in a clarifier and
clarified water is stored in clarified water pit via monitoring pit and it will be
discharged to WWT effluent pond.
The abnormal wastewater from water and wastewater treatment area by
regeneration/cleaning process and power block during overhaul period will be
collected in the abnormal wastewater storage pit near the water treatment
building. The wastewater is neutralized in this pit by acid or caustic. And then
the wastewater is equalized and mixed by aeration then transferred to a normal
wastewater storage pit. The wastewater is equalized and mixed by aeration in
the wastewater storage pit.
The oily wastewater is generated from the G.T Area sump pit, TR Area sump pit,
etc.
The oily waste is transferred into the API oil separator. Oil is removed in the API
oil separator and CPI(Corrugated Plate Separator) oil separator and treated
water flows into the normal wastewater storage pit.
![Page 88: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/88.jpg)
Chittagong 2x660MW CFPP Project Page No : 88 of 94
Pre-Proposal
Treated water from wastewater treatment plant is transferred into the WWT
effluent pond. And then it will be reused for Coal handling spray water and Ash
handling spray water in site or discharged to the discharge pond.
The sewage treatment system consisting of septic tank type, compact
purification facility complete with pumps, drives, storage tank including all
auxiliaries and all accessories shall be supplied.
The sludge transferred from the clarifier by means of a sludge transfer pump for
clarifier will be thickened in the thickener, and then thickened sludge will be
delivered to dehydrator in order to make the sludge cake. The sludge cake is
collected in a cake box. Wastewater from the dehydrator is returned to the
normal wastewater storage pit.
C-Polymer pumped by a C-polymer dosing pump and sludge pumped by the
sludge transfer pump are mixed in control compartment on the sludge-mixing
tank for sludge conditioning. After conditioning, the readily drainable water is
separated from the sludge by a dehydrator.
System compositions
• Waste water treatment system
- Normal waste water storage pit
- Abnormal waste water storage pit
- API & CPI Oil Separator
- Oily storage pond
- pH adjustment, Coagulation, Flocculation Tank with agitator
- Clarifier with reducer & scraper
- Sludge Thickener
- Sand filter & A/C filter (if necessary)
- Dehydrator facilities
- Chemical feed system (for WWT)
- PLC based control system
11.16 Firefighting system
11.16.1 General
![Page 89: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/89.jpg)
Chittagong 2x660MW CFPP Project Page No : 89 of 94
Pre-Proposal
A water spray system is recommended as it is quickly effective for the local
cooling extinguishment of fires. And it is generally used for firefighting systems
of thermal power plants in which there is the possibility of the spread of fire due
to heat from the continuous fire of the plant. The Fire Fighting System will be
equipped with the following specialized fire alarm and hydrocarbon firefighting
systems as a minimum requirement for one unit.
11.16.2 Application of Fire Fighting System
1) Fire Water Tank
2) Fire Water Pumps
3) Fire Water Network
4) Fire Hydrants and Hose Boxes
5) Sprinkler Systems
6) Water Spray Systems
7) Foam Systems
8) FM-200 (HFC-227ea) Systems
9) Carbon Dioxide (CO2) Extinguishing Systems
10) Portable Fire Extinguishers
11) Fire Alarm Systems
11.16.3 Standard
Firefighting activities for the main building are to be undertaken in accordance
with the acting security norms, standards and regulations for power plants of
Bangladesh, and facilities shall be designed on the basis of NFPA standards.
NFPA10 Standard for Portable Fire Extinguishers
NFPA11 Low, Medium, and High Expansion Foam
NFPA12 Carbon Dioxide Extinguishing System
NFPA14 Standard for the Installation of Standpipe and Hose Systems
NFPA15 Standard for Water Spray Fixed Systems for Fire Protection
NFPA20 Standard for the Installation of Stationary Pumps for Fire Protection
NFPA30 Flammable and Combustible Liquid Code
NFPA850 Electric Generating Plants and High Voltage Direct Current Converter
Station
NFPA2001 Clean Agent Fire Extinguishing Systems
![Page 90: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/90.jpg)
Chittagong 2x660MW CFPP Project Page No : 90 of 94
Pre-Proposal
11.16.4 System Description
1) Fire Water Tank
The fire water for firefighting is stored in the fire water tank. The total
capacity of the firefighting water is determined based on the requirements
and recommendations of NFPA 850 and capable of supplying for two (2)
hours at a maximum fire water demand, which covers the largest fire water
demand plus operating of two (2) hydrants.
2) Fire Water Pumps
The fire water is taking suction from the storage tank by the fire pumping
system installed within the fire pump house to be located adjacent to the
storage tank. The fire pumping system consists of one (1) 100 % duty
electric motor pumps and one (1) 100 % stand-by diesel engine driven pump.
The rated flow of fire pumps shall be determined in compliance with NFPA
20. The diesel engine driven fire pump is provided with a 12 hours fuel
supply tank, starter batteries, controls, exhaust and silencer. The fuel supply
tank is installed external to the pump house.
In order to prevent the activation of the main fire pump due to minor leaks
causing fluctuations in pressure, two(2) electric motor driven jockey pumps
are provided, and connected to the system. The duty of the units shall be as
small as to allow that, in the event of pressure drop in the fire ring main, the
main fire pump is immediately brought into operation.
3) Fire Water Network
The firewater piping network is sized to provide the design firewater demand
to each area of the facility.
4) Fire Hydrants and Hose Boxes
Above ground, fire hydrants will be provided throughout the plant. All
buildings, structures and equipment will be within reach of hose streams from
two hydrants while hydrant spacing generally will be not be greater than 90m
or as required by NFPA Code, whichever is the more stringent.
Each hydrant will be provided with a post-indicator valve in its connection to
the fire water ring main.
5) Sprinkler Systems
![Page 91: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/91.jpg)
Chittagong 2x660MW CFPP Project Page No : 91 of 94
Pre-Proposal
Sprinkler systems will be provided in accordance with NFPA 13. Design
parameters will be in accordance with the recommendations of NFPA 850.
6) Water Spray System
Water spray systems will be provided in accordance with NFPA 15. Design
parameters will be in accordance with the recommendations of NFPA 850.
7) Foam Systems (Foam Chamber and Foam Monitor)
Foam systems will be provided in accordance with NFPA 11.
8) FM-200 (HFC-227ea) Systems
FM-200 systems will be provided in accordance with NFPA 2001.
9) Carbon Dioxide (CO2) Extinguishing Systems
CO2 systems will be provided in accordance with NFPA 12.
10) Portable Fire Extinguishers
Portable fire extinguisher, based on dry chemical/powder or CO2 depending
on the fire risk, shall be provided in all the buildings.
11.16.5 Fire Alarm Systems
A fire detection system is provided whose main functions are the actuation of
the extinguishing systems and the annunciation, both centralized and local, of
alarms and systems status. The system includes fire detectors in all the
protected areas and monitored by the installation of the following types of fire
detectors:
1) Temperature rate of rise detectors, for the areas with higher fire risk
2) Optical type smoke detectors, where slow combustion fires are possible with
consequent smoke release
11.17 HVAC system
11.17.1 General
The Scope of Work includes all necessary Heating, Ventilation and Air
![Page 92: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/92.jpg)
Chittagong 2x660MW CFPP Project Page No : 92 of 94
Pre-Proposal
conditioning (HVAC) equipment including Plant, controls, instrumentation,
interlocking and cabling systems necessary to maintain appropriate ambient
conditions for equipment and personnel.
11.17.2 Ambient Temperature
Summer design conditions 33. 3℃ DB / 27. 8 ℃ WB
Winter design conditions 11.1℃ DB / 6.4 ℃ WB
11.17.3 Indoor Design Conditions per Each Building
The indoor room conditions are to be set for heating, ventilation and air-
conditions system design as per ASHRAE or process needs.
11.17.4 System Description
1) Air Conditioned Areas
The air-conditioned areas shall be provided with Air Handling Units or
Packaged Air Cooled DX-Units.
2) Ventilated Areas
Ventilated areas will be provided with mechanical ventilation. Roof mounted
exhaust fan, ventilated wall mounted supply and exhaust fan, duct in-line fan,
air intake louver shall be applied.
11.17.5 HVAC Control
The HVAC control system shall be supplied with DDC or microprocessor based
temperature /humidity control system to control and monitor the operation of
HVAC equipment.
In addition, the controller should perform remote (on/off) operation, fault alarm
record temperature, humidity and pressure readings, and control time-schedule.
![Page 93: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/93.jpg)
Chittagong 2x660MW CFPP Project Page No : 93 of 94
Pre-Proposal
12. Operational Requirements
12.1 General
The main components and their auxiliaries shall be designed to ensure that trouble
free starts and operations are achieved throughout the design life of the plant.
Adequate redundancies for auxiliary facilities and equipment shall be made available
to achieve high availability. The main components and their auxiliaries shall be
designed to be able to start and rise up to full load byte initiation of a single push
button. The entire plant shall be suitable for continuous power load operation.
12.2 Plant Duty
1) Cold start
2) Warm start
3) Hot start
4) Black start (Not applicable)
![Page 94: PRE-PROPOSAL FOR Chittagong 2x660MW Coal … 2x660MW CFPP Project Page No : 1 of 94 Pre-Proposal PRE-PROPOSAL FOR Chittagong 2x660MW Coal-Fired Power Plant Project October 31, 2014](https://reader031.vdocuments.us/reader031/viewer/2022013117/5af6c3fd7f8b9a8d1c8f4dfe/html5/thumbnails/94.jpg)
Chittagong 2x660MW CFPP Project Page No : 94 of 94
Pre-Proposal
13. Appendix
13.1 Diagram of Terminal points
13.2 Heat Balance Diagram
13.3 Water balance diagram
13.4 Plot Plan
13.5 Single line diagram
13.6 Control system configuration