pre-feasibility study cost estimation resources ©2002 dr. bradley c. paul
TRANSCRIPT
![Page 1: Pre-Feasibility Study Cost Estimation Resources ©2002 Dr. Bradley C. Paul](https://reader035.vdocuments.us/reader035/viewer/2022072010/56649db95503460f94aa958e/html5/thumbnails/1.jpg)
Pre-Feasibility Study Cost Estimation Resources
©2002 Dr. Bradley C. Paul
![Page 2: Pre-Feasibility Study Cost Estimation Resources ©2002 Dr. Bradley C. Paul](https://reader035.vdocuments.us/reader035/viewer/2022072010/56649db95503460f94aa958e/html5/thumbnails/2.jpg)
Pre-Feasibility Study
Order of Magnitude Estimates Determined which things would be considered
Pre-Feasibility Study Determines whether there is enough promise to justify the effort required to move forward
Feasibility Study (generally 10-30% +/-) Next Moves to Project Approval (5-10%)
![Page 3: Pre-Feasibility Study Cost Estimation Resources ©2002 Dr. Bradley C. Paul](https://reader035.vdocuments.us/reader035/viewer/2022072010/56649db95503460f94aa958e/html5/thumbnails/3.jpg)
Pre-Feasibility Study
Pre-Feasibility Study– Requires that you have a concept for what going to
build– Break project down into areas and tasks
Outby Haulage Ventilation Mine Workings
Costs of Components Done Separately– Need to include everything
![Page 4: Pre-Feasibility Study Cost Estimation Resources ©2002 Dr. Bradley C. Paul](https://reader035.vdocuments.us/reader035/viewer/2022072010/56649db95503460f94aa958e/html5/thumbnails/4.jpg)
Methods of Getting Pre-Feasibility Cost Data Clear List of What is Included to make sure
all components are included Begin to Find Manuals Available
– EPRI Coal Mine Cost Model (about 1981)– Bureau of Mines Cost Estimating System
(1984)– SERPA Cost Program (current)– Western Mine Cost Service
![Page 5: Pre-Feasibility Study Cost Estimation Resources ©2002 Dr. Bradley C. Paul](https://reader035.vdocuments.us/reader035/viewer/2022072010/56649db95503460f94aa958e/html5/thumbnails/5.jpg)
Typical Cost Manual Approaches
Factored Cost Estimates– Use Curves that are a function of some over-all
characteristic Example US Bureau of Mines Cost Estimating System
Itemized Cost Estimates– Specify cubic yards of concrete– Apply a cost per cubic yard– Used by EPRI and Serpa
![Page 6: Pre-Feasibility Study Cost Estimation Resources ©2002 Dr. Bradley C. Paul](https://reader035.vdocuments.us/reader035/viewer/2022072010/56649db95503460f94aa958e/html5/thumbnails/6.jpg)
Strengths and Weaknesses
Factored Cost Estimation Approach– Requires a lesser degree of engineering detail be
worked out to run all costs linked to a specific generally known parameter
– Lets get closer to answer with less work Itemized Cost Estimates
– Structure is same as Feasibility Estimate allows more transparent transition to Feasibility study
estimates
![Page 7: Pre-Feasibility Study Cost Estimation Resources ©2002 Dr. Bradley C. Paul](https://reader035.vdocuments.us/reader035/viewer/2022072010/56649db95503460f94aa958e/html5/thumbnails/7.jpg)
General Comments on Major Cost Estimation Resources EPRI - Coal Mine Cost Model
– Most cost model resources are for hard rock and industrial minerals - this one is coal
– Model covers coal mining costs but is weak in ancillary facilities and some capital costs
Example - No capital cost capability for shaft or slope
– Model linked to a computer program that has not been updated
1981 software in the 21rst century looses a lot
![Page 8: Pre-Feasibility Study Cost Estimation Resources ©2002 Dr. Bradley C. Paul](https://reader035.vdocuments.us/reader035/viewer/2022072010/56649db95503460f94aa958e/html5/thumbnails/8.jpg)
More EPRI Comments
1980 and 1981 cost base– needs significant inflation indexing
will see later that knowing how much to index with what is important
doesn’t show which indices to use on what
Productivity Sensitive– crews and advances done with simulations current in 1980– coal mine productivity has increased about 250%
are some productivity indices from BLS but not a common updating procedure
![Page 9: Pre-Feasibility Study Cost Estimation Resources ©2002 Dr. Bradley C. Paul](https://reader035.vdocuments.us/reader035/viewer/2022072010/56649db95503460f94aa958e/html5/thumbnails/9.jpg)
SERPA
A Hardrock Package A comprehensive mine cost package that has
been maintained to fairly current status with costs
– is private so seeing exactly what is in the package is not really possible
– fairly current still means the driving routines run in DOS cryptic key sequences and IO problems suspect that costs are updated but engineering assumptions in code
may not be
![Page 10: Pre-Feasibility Study Cost Estimation Resources ©2002 Dr. Bradley C. Paul](https://reader035.vdocuments.us/reader035/viewer/2022072010/56649db95503460f94aa958e/html5/thumbnails/10.jpg)
SERPA
Has a lot of defaults built in Has relatively simple categories of mine needs May almost be able to run at at the fairly precise
order of magnitude estimate stage– most manuals really can’t help you till get to
prefeasibility– Ability to add details and replace defaults gives system
power that extends up into pre-feasibility weaknesses in showing details of output probably make use in
feasibility stage really questionable
![Page 11: Pre-Feasibility Study Cost Estimation Resources ©2002 Dr. Bradley C. Paul](https://reader035.vdocuments.us/reader035/viewer/2022072010/56649db95503460f94aa958e/html5/thumbnails/11.jpg)
Western Mine Cost Service
Collection of cost models and typical item prices– comes as articles over time
makes comprehensive approach at any one time questionable may have to inflation index different parts of mine cost
separately very vulnerable to holes in needed costing
Hardrock manual that has some coal mining equipment items in it– can use on coal but comprehensive approach problem
![Page 12: Pre-Feasibility Study Cost Estimation Resources ©2002 Dr. Bradley C. Paul](https://reader035.vdocuments.us/reader035/viewer/2022072010/56649db95503460f94aa958e/html5/thumbnails/12.jpg)
Western Mine Cost Service
Place where manual shines– identify a critical cost area and you want to get down to
itemizing equipment or features and need costs great alternative to fishing for vendors that will give you prices
before your really shopping for equipment
– event is likely to occur as Pre-feasibility study moves into true feasibility study
– Manual caters all the way from Order of Magnitude to Feasibility but is comprehensive nowhere
![Page 13: Pre-Feasibility Study Cost Estimation Resources ©2002 Dr. Bradley C. Paul](https://reader035.vdocuments.us/reader035/viewer/2022072010/56649db95503460f94aa958e/html5/thumbnails/13.jpg)
US Bureau of Mines Cost Estimating System Prob the most comprehensive high precision pre-
feasibility manual ever written– No holes - covers everything– Too much detail and work to function in Order of
Magnitude Estimation– Factored cost estimate approach is not compatible with
itemized detail needed in critical areas of Feasibility Study
– Manual is clearly hardrock not good for quarry’s either
![Page 14: Pre-Feasibility Study Cost Estimation Resources ©2002 Dr. Bradley C. Paul](https://reader035.vdocuments.us/reader035/viewer/2022072010/56649db95503460f94aa958e/html5/thumbnails/14.jpg)
Status of BM CES
Mid 90s Congress killed Bureau of Mines– manual has been without caretaker– lots spin off people went to Western Mine Cost
and Serpa came from BofM Had beautiful spreadsheet program that ran
manuals rapidly was designed for Lotus 123 not updated to latest spreadsheets and some macros
don’t work
![Page 15: Pre-Feasibility Study Cost Estimation Resources ©2002 Dr. Bradley C. Paul](https://reader035.vdocuments.us/reader035/viewer/2022072010/56649db95503460f94aa958e/html5/thumbnails/15.jpg)
Status of BM CES cont
Had automatic cost indexing but that’s not been maintained
fortunately same index structure was picked up by Western Mine Cost which has been maintained
getting recent indexing into spreadsheet model is an on your own
– can do it manually as you will see