PRE – FEASIBILITY REPORT

Page 2: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

2 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

TABLE OF CONTENT

Sr. No. Content

1.0 Executive Summary

2.0 Introduction of Project and Background Information

3.0 Project Description

4.0 Site Analysis

5.0 Planning Brief

6.0 Proposed Infrastructure

7.0 Rehabilitation & Resettlement

8.0 Project Schedule

9.0 Analysis of Proposal

Page 3: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

3 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

1.0 EXECUTIVE SUMMARY

Particulars Details Location Khojon Ki Dhani Limestone Mine

Near Village - Khojon Ki Dhani , Tehsil –Bilara, Distt –Jodhpur, Rajasthan

Latitude 26°22'22.02"N to 26°23'10.02"N Longitude 73°50'11.07"E to 73°50’24.66"E Toposheet No. F Total lease area 9.0ha. Mineable Reserves 2607447.6 tones Capacity Proposed production – 4, 24,935 TPA (RoM) Life of Mine 10 years Ultimate depth of mining 300 mRL Estimated project cost 70/- lacs EMP Cost 2.00 /- Lac

DG Set Not Required

Highest and Lowest Elevation

S. No. Particulars Elevation (mRL)

1. Highest 333 2. Lowest 329

Land use Govt. waste Land

Nearest Habitation/ Town Khojon ki Dhani, about 3.8 km (By road) from lease area in NW direction.

Nearest Airport Jaipur, about 114km from lease area in SW direction. Nearest Highway SH-22 about 9.6 km in SW direction

NH-65A about 16.7 km in SE direction Nearest Railway Station Bilara Railway Station-52 km from mine site in SW

direction Power Supply Khojon ki Dhani Nearest Dispensary and Govt. Hospital

Khojon ki Dhani

Educational Facility Khojon ki Dhani Nearest Telephone Facility Khojon ki Dhani Water Demand and Supply 6.00 KLD, Source: nearby water well Nearest Tourist Places None within the study area Defense Installations None within the study area Archeological Features None within the study area Ecological Sensitive Zones None within the study area Nearest Streams/ Rivers/ Water Bodies (from mine boundary)

Luni river at 9.2 km in SE direction from lease area.

Seismic Zone Seismic zone – II.

Page 4: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

4 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

2.0 INTRODUCTION OF PROJECT /BACKGROUND INFORMATION

Mining project for Limestone with. M.L. No.-138/95. The project is located near village –

Khojon Ki Dhani, Tehsil – Bilara and District – Jodhpur, (Rajasthan). Lease area – 9.0 ha.

Proposed production – 4, 24,935 TPA (RoM).

Identification of the project and project proponent

Name of the Project Khojon Ki Dhani Limestone Mine

Name of the Lessee M/s Patla Minerals Corporation Pvt.Ltd. Dr) 33-34 River View Colony, Morar, Gwalior Madhya Pradesh Rajendra Kumar Daftari (Director of this company)

Location of the project Near village – Khojon Ki Dhani, Tehsil – Bilara and District – Jodhpur, (Rajasthan)

Proposed Production 4, 24,935 TPA (RoM)

Lease Area 9.0ha.

Mob. No. 9928075573

Email [email protected]

Status of the Applicant Pvt. Ltd Company

Brief description of the nature of the project:

The mining lease for an area 9.00 hect. Was granted in favor of Shri B.S Shekhawat S/o

Shri Narayan Singh Shekhawat vide order no. NiDe/P-2(A)48/Jodh/No/85/1500 on

dated 02/08/1985. The lease deed was registered on dated 18/10/1985 for 10 year

(18/10/1985 to 17/10/1995).

The mining lease was transfer in favor of Shri Dilip Kumar Poddar S/o Shri Prithviraj

Poddar R/O Veer Durga Das Nagar, Pali (Raj) Vide order No- 2326 on dated 20/10/1994.

Registered on dated 18/10/1995. The lease deed was excavated on dated 16/10/1996

and was registered on dated 18/10/1995.

The mining lease was first renewed in favor of Shri Dilip Kumar Poddar S/o Shri Prithviraj

Poddar R/O Veer Durga Das Nagar, Pali (Raj) vide order No-2589 on dated 06/12/1995

for 20 years. (18/10/1995 to 17/10/2015).

Page 5: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

5 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

The mining lease was transfer in favor of M/s Patla Minerals Corporations Pvt. Ltd

Gwaliyar, Madhya Pradesh vide order No-ME/JDP/CC-II/Minor/ML/138/1995/476 on

dated 03/05/2012.

The Mining plan with PMCP for Limestone mine (M.L No-138/95) Near village – Khojon Ki

Dhani, Tehsil – Bilara and District – Jodhpur, (Rajasthan) has been approved on vide

letter No- SME/JO/CC/Jodhpur/Minor/M.L./138/1995/12352 on dated 12/01/2016 .

(Copy of approval letter of mining plan is attached as annexure-VI)

Shri Rajendra Kumar Daftari is authorized signatory for this company (Copy of

resolution latter is attached as Annexure-V)

As per MoEF’s Notification on 14th March 2017 as the proposal is a case of violation

because production has been achieved without obtain Environment clearance. So we have

applied for Environment Clearance in “A” Category.

Nature of the Project:-

Mining of Limestone is proposed in the lease area 9.0 HECT. Near village – Khojon Ki Dhani,

Tehsil – Bilara and District – Jodhpur, (Rajasthan). Mining will be carried out by Opencast

Mechanized method. Proposed production is 4, 24,935 TPA (RoM) Limestone.

2.3 Need for the project and its importance to the country and or region:

The basic objective of the project is to effective utilization of Material in the country or

region. The material generated from this mine will be used mainly for building

construction work. The Limestone shall be used in future for local construction work

like retaining wall around pits and applied boundary. Limestone will helps in the

economic growth of the country or region.

2.4 Demands-supply gap:

The material generated from this mine will be used as decorative stone in flooring and

in wall tiles.

Page 6: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

6 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

2.5 Imports vs. Indigenous Production

There will be no import for the project. There will be indigenous inputs in the entire

mining activity.

2.6 Export Possibility

The mining activity is not prospecting exports.

2.7 Domestic/Export Markets

Lessee would like to sale out the mineral in domestic market as per requirement. No

export is proposed.

2.8 Employment Generation (Direct or Indirect)

The mining project will generate direct & indirect employment. About 96 people

will get direct employment and 31 people will also be affected indirectly and

employed with allied and related industries, such as transportation,

maintenance, etc.

3.0 PROJECT DESCRIPTION

3.1 Type of project including interlinked and interdependent projects:

The proposed project is mining unit of Limestone in the area of 9.0ha. Situated at Near

village – Khojon Ki Dhani, Tehsil – Bilara and District – Jodhpur, (Rajasthan). Proposed

Production is 4, 24,935 TPA (RoM).

No Interlinked or Interdependent project.

3.2 Location (Location map & Key plan is attached as Plate no. I & II respectively).

State : Rajasthan District : Jodhpur Tehsil : Bilara Village : Khojon KI Dhani

Page 7: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

7 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

TOPOSHEET NO. WITH LATITUDE AND LONGITUDE

The lease area forms a part of Survey of India Topo-sheet no. 45 F/5.

Latitude 26°22'22.02"N to 26°23'10.02"N Longitude 73°50'11.07"E to 73°50’24.66"E

3.3 Details of Alternate Site Considered and the Basis of Selecting the Proposed

Site, Particularly the Environmental Considerations gone into should be

Highlighted:

Mining is site specific project hence no alternate site is considered.

3.4 Size/Magnitude of Operation

It is proposed to produce 4, 24,935 TPA (RoM) of Limestone from the area of 9.0

HECT. by Opencast Mechanized method of mining.

3.5 Project description with process details:

It is a mining project of Limestone from the lease area 9.0 ha, situated at near village –

Near village – Khojon Ki Dhani, Tehsil – Bilara and District – Jodhpur, (Rajasthan). Proposed

production is 4, 24,935 TPA (RoM). The material generated from this mine will be

used mainly as building stone for construction.

Proposed Mining Method

The Khojon Ki Dhani Limestone Mine shall be developed by mechanized open cast

mining. The mineral is lying on the sub surface therefor open cast mining has been the

obvious choose.

The bench Parameter shall be for mineral

1. Height – 1m-6m

2. Width – More than 1m-6m.

The Bench Parameter shall be for O/B Dolomite Limestone

1. Height 1m- 6m.

2. Width – more than 1m – 6

Page 8: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

8 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

The main operation shall be drilling, blasting loading and the transportation by trucks.

Blasting

Small blasting with low charge of holes just to loosen the rocks is proposed in upper

layers to remove the hard overburden. The blasting shall be done by the authorized

contractor on contractual Basis. These contractors have their own safety explosive

container as well as Explosive License. The blast hole parameter proposed are as

follow-

Board blasting Parameters

Length of shot holes : 1.6m

Spacing : 1m

Burden : 0.8m

Stemming : 30%

Charge per hole & Powder factor

Expected powder factor 4 tones/kg of explosive

Quantity of ore broken per hole

=depth x burden x spacing x sp. Gravity

=1.5x0.8x1x2.5

3.24 tones

Explosive required per hole 3.00/4=0.75

Sp. Gel per cartridge 0.15

A.N.F.O. per hole 0.60

Page 9: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

9 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

Type of Explosive

Deferent type of explosive for use in opencast mines like Special Gellain, Ordinary

plain, Detonator, Safety Fuse, ANFO.

Storage of Explosive: The explosive shall be supplied by the authorized contractor at

the blasting site at the time of blasting. The explosive shall be directly used so no

storage of explosive is proposed.

Extent of Mechanization

Type of

Machinery

Nos. Make Capacity H.P

Dumper 8 Tata 20 tonner 119HP

Diesel Pump 1 local -- --

Compressor 4 local 75 CFM --

Jack hammer 6 Local 32mm --

Excavator 3 Local 1.2m3 --

Mobile crane 3 Escort - 10 tonner

Note- Required machinery shall be taken on hire bases.

Source-Approved Mining Plan

3.6 Raw material required along with estimated quantity, likely source, marketing

area of final products, mode of transport of raw material and finished product:

Limestone will be produced by opencast Mechanized method of mining, proposed

production is 4, 24,935 TPA (RoM). It will be transported to users by using Dumper.

Page 10: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

10 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

Year wise Production

Year RoM in

Tonns

Total

Saleable

Limestone

in MT

Waste

generate in

the lime stone

in MT

Dolomitic

limestone

(sub grade) in

tones

Soil generate

from the

lime stone in

MT

Total

waste/

soil/ sub

grade in

MT

I 235198 188538 46660 60700 113798 221158

II 247778 204021 43757 63945 65903 173605

III 299455 241645 57810 85265 128925 272000

IV 398355 338602 59753 -- -- 59753

V 4,24,935 3,61,195 63740 -- -- 63740

Total 1605721 1334001 271720 209910 308626 790256

Detail of achieve production

S.No. Year Proposed

production in MT

Production

achieved in MT

1. 2010-11 Nil Nil

2. 2011-12 3050 3050

3. 2012-13 3900 3701

4. 2013-14 Nil Nil

5. 2014-15 -- --

Source- As per approved mining Plan.

Page 11: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

11 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

3.7 Resource optimization/ recycling and reuse envisaged in the project, if any,

should be briefly outlined.

Not applicable.

3.8 Availability of water its source, energy/power requirement and source :

The total water requirement for the project is estimated 6.00 KLD. Water for mining

operation (dust suppression) and for domestic & drinking purpose will be arranged

from nearby well.

Sr. No. Purpose Total Requirement (KLD)

1 Dust suppression 2.00

2 Drinking 2.00

3 Green belt 2.00

TOTAL 6.00

Diesel for tippers/equipment – about 150 Lt. per day is assumed to be consumed.

Diesel will be brought from outside, from nearby diesel pumps.

Ground Water Table

WATER TABLE

300 mRL (29m bgl)

ULTIMATE DEPTH

SOAPSTONE

329mRL (Lowest Contour) GROUND LEVEL

Proposed working will not intersect Ground

water table.

333mRL (Highest contour) hiesest

269 mRL (60mbgl Post monsoon)

259 mRL (70mbgl Pre monsoon)

Page 12: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

12 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

3.9 Quantity of wastes to be generated (liquid and solid) and scheme for their

management /disposal:

Nature of Waste: - The waste as overburden in the area is top soil. The soil cover in the

area varies from 3m. The rock fragments of small size area also resulted after mining.

DETAIL OF PROPOSED WASTE TO BE GENERATED S.

No Year I II III IV V Total

1. mineral waste (MT) 46660 43757 57810 59753 63740 27172

2. Over Burden(MT) -- -- -- -- -- --

3. Total Waste (1+2) MT

46660 43757 57810 59753 63740 271720

4. In Cum 18664 17503 23124 23901 25496 108688

5. Swell volume (m3) 22397 21003 27749 28681 30595 13042

Generation of top Soil- Top soil will be used for plantation.

Generation & stacking of sub grade mineral- It is also proposed to stack the sub

grade material between pillar C & D. The Sub grade mineral shall be used in mixing with

high grade to make avg. grade makeable.

Page 13: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

13 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

3.10 Schematic representations of the feasibility drawing which give information of

EC purpose:

Page 14: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

14 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

4.0 SITE ANALYSIS

4.1 Connectivity

Connectivity Details from Project Site:

4.2 Land form, land use and land ownership

The lease area is almost flat & mid hilly. The highest elevation of the area is 333 mRL

and lowest elevation is 3329 mRL.

Sr. No. Particulars Details

1. Road

Connectivity

The village Khojon Ki Dhani, nearest population center is 3.8 km away ( By

Road) from the lease area & it is connected with other important towns and

cities through a good network of roads with regular public transport

services. The Tehsil Headquarters of Bilara is at a distance of 54.00 km by

road in SW & District Headquarter Jodhpur is 107 km connected by road.

2. Nearest

Highway

NH-65 A 16.7 km from lease area in SE direction

SH-21 (9.6 km in SW direction)

3.

Nearest

Railway

Station

The Nearest Railhead is at Bilara at a distance of 52 km from lease area SW

direction

4. Nearest

Airport

The nearest civilian airport for regular commercial flights is at Jaipur

the road distance from the lease area is around 114 km in SW

direction

Type of Land Area in Hectares

Govt. waste Land 9.0

Total: 9.0

Page 15: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

15 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

4.3 Topography

Topographically the Mining Area comprises flat & mid hilly. There is no nalla or

stream observed within lease area. The highest elevation is 333mRL and lowest is 329

mRL. Irrigation of agricultural land in the surrounding of the lease area is done by

water source from tube/dug well.

4.4 Existing Land use Pattern

The lease area is Govt. waste Land (9.0ha.). There is no village or hutments within the

lease area. Existing land use pattern is given as below:-

Sr. No. Particulars Existing

A) Mining Activity

1 Pits 1.9293

2 Top soil Dumps -

3 Dump 0.3915

4 Plantation -

5 Infrastructure (workshop & building

0.0048

6 Road 0.4159

7 Backfilled & plantation -

8 Water storage -

9 Mineral stack yard

10 Sub grade stack yard

10 Non utilized 6.2585

Total area

9.00

4.5 Existing Infrastructure:

There is no existing infrastructure is available in the lease area. All necessary

infrastructures will be developed before mining operation commenced. Site services

as per Mines Rules 1956 will be developed. First-Aid station with all necessary

medical facilities, Toilets as per the provisions of Mines Rules will be developed.

Page 16: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

16 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

Regular medical checkup of the mine employees will be carried out as per the

provisions of Mines Rules 1956.

4.6 Soil classification:

The soil is varying in thickness from 2.0m located at places over the dolomitic

limestone deposit. The dolomitic limestone with is varying in thickness from 2.0 m

below the hard limestone layer.

Regional geology & local geology:

a) Regional geology:-

The area cover part of Jodhpur and area is covered by alluvium and wind blow sand NE-

SW direction of longitudinal

Dunes trading in the western part of the area. low-lying hills and flat topped plateaus.

The maximum and minimum elevation of lease area are 310mrl (pundlu ka magra) and

306 respectively from the mean sea level.

The drainage is represented by jori river and a few nalas emerging from the hills.

The area is accessible by road and railway. The rock exposed in the area belong to the

Bilara and the Bilara group of the marwar super group. The palana formation is

observed in a few well in zone running from nort to south in the eastern paart of the

area all the three formation of the Bilara group i.e the dhanapa,gotan and the pondlo

formation are exposed in the area. the dhanapa formation comprises of chert, cherty

dolomite and dolomitic limestone and is exposed in the western and southern part of

the area.

The Gotan formation is exposed adjacent to the dhanaps formation and comprises an

inter bedded sequens of limestone ,dolomitic limestone and dolomite and is exposed in

the occupies a large area in central and southern part of the leasearea . it consists of

chert, cherty dolomite and dolomitic limestone with some interblend of the bilara group

is exposed near the pundlu village in the northern part of area. it consists of gritty and

pebby sandstone with siltstone and clay and is exposed only in nort eastern corner of

the area. the palana formation has been observed in a few dug well in the eastern part

of lease area. it consists of white to violet colored kaolinite with angular quartz grains,

Page 17: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

17 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

loose sand with lenses of calcareous grit and porous fine to medium grained, current

bedded sandstone. This is overlain by pockets of pebbles, gravels, kankar and the

undifferentiated. Aeolian and fluvial sediments overlying a major part of area included

sand, soil, calcrete grit and ferruginous sandstone.

Good quality of limestone and sand stone are being quarried at several places for

industrial and building material purposes in the area.

b) Local Geology

The local geological succession for the area may be summarized as below

Neo

Proterozoic

Marewar

super group

Bilara group Pondlo

formation

Chert, cherty dolomite

and dolomitic limestone

with interbeds of

siltstone and claystone

Litho logy the soil is varying in thickness from 1.0meter located at place over the

dolomitic limestone deposit. Dolomatic limestone varying in thickness from 2.0 meter

located below the hard limestone layer the hard and weathered limestone layer over

the deposit varies from 10meter in thickness.

4.7 Climatic details

The district experiences arid to semi-arid type of climate. Mean annual rainfall (1971-

2012) of the district is 374 mm whereas normal rainfall (1901-1970) is lower than

average rainfall and is placed at 314 mm. Rainy days are limited to maximum 15 in a year.

Almost 80% of the total annual rainfall is received during the southwest monsoon, which

enters the district in the first week of July and withdraws in the mid of September.

Probability of annual rainfall exceeding 650 mm is only 10%. However, there is 90%

probability that the annual rainfall will be more than 190 mm. The probability of

occurrence of mean annual rainfall is 45%. Drought analysis based on agriculture criteria

indicates that the district is prone to mild and normal type of droughts. Occurrence of

Page 18: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

18 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

severe and very severe type of drought is very rare. As the district lies in the desert area,

extremes of heat in summer and cold in winter are the characteristic of the desert. Both

day and night temperatures increase gradually and reach their maximum in May and June

respectively. The temperature varies from 49oC in summer to 1oC in winter. Atmosphere

is generally dry except during the monsoon period. Humidity is the highest in August with

mean daily relative humidity at 81%. The annual maximum potential

4.8 Social Infrastructure

The infrastructure like, toilets, first aid stations etc. will be provided inside the applied

area.

The nearest village is Khojon Ki Dhani, health & educational facilities (in the form of

primary schools) are available there.

Medical facilities, Primary Health Centre are there in the area, imparting services, for

advance medical facilities. In each village one health worker has been appointed by the

Govt. to provide primary health facilities.

The water required will be available by the local water well department in the lease

area and through water tanker.

Communication services like post office and telephones are available in the nearby

village. Some of the villagers are having mobile phones.

An occupational health unit will be organized and the proposed measures will be

adopted:

Pre & Periodical Medical Checkup program for all the workers.

Compulsory medical checkup program and first-aid box with necessary

equipment will be provided.

Training for workers.

Safety equipment i.e. dusts mask, safety shoes, gloves etc.

Page 19: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

19 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

5. PLANNING BRIEF

5.1 Planning concept

It is proposed to produce 4, 24,935 TPA (RoM) of Limestone from the lease area. It is

situated in Jodhpur District of Rajasthan.

5.2 Population projection

Man power requirement for mining is estimated to be 31 Nos. Most of the employees

will be recruited from neighboring village depending upon the availability of skilled &

unskilled people. Migration of highly educated and skilled person will take place but it

will be on temporary basis. So there will no permanent migration of people, hence

there will be no population projection.

5.3 Land use Planning:

Land use pattern (Hects.)

Sr.

No.

Particulars Existing At the end of

5th year

At the end of

mine

A) Mining Activity

1 Pits 1.9293 5.2095 -

2 Top soil Dumps - 0.1934 -

3 Dump 0.3915 0.5794 -

4 Plantation - 0.1125 0.8675

5 Infrastructure (workshop & building

0.0048 0.0241 0.0100

6 Road 0.4159 0.1009 -

7 Backfilled & plantation

- - 3.2631

8 Water storage - - 4.8594

9 Mineral stack yard 0.0109 -

10 Sub grade stack yard 0.4980

10 Non utilized 6.2585 2.2713 -

Total area

9.00

9.00 9.00

Page 20: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

20 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

Note- At the end of mine period about 4.1306 ha area will be planted in which includes 3.26 Ha

area will be planted on backfill mine out area & 0.8675 ha. area will be planted on statuary

barrier. About 4.8594 mine out area will be converted into rain water storage.

5.4 Assessment of infrastructure demand (physical and social).

Temporary office and stores will be provided in the mine lease area. Specified first-aid

box with all necessary facilities will be maintained at the site office and the rest shelter

as per Mines Act-1952. Medical facilities, Primary Health Centre are there in the area,

imparting services, for advance medical facilities. Communication services like post

office and telephones are available in the nearby village. Some of the villagers are having

mobile phones.

5.5 Facilities provided:

5.5.1 Infrastructure

Additional facilities will be made as per the requirement. Arrangements for safe and

healthy working conditions. Provision of Drinking water from nearby well. Most

workers will be from nearby villages so no accommodation at mine site will be

required.

5.5.2 Landscaping and green belt development

It is proposed that applicant will plant 200 saplings per year. One workman will be

deputed for maintenance of the plantation throughout the year.

1. Babool

2. Gulmohar

3. Amaltas

4. Perkin Sonia

5. Neem

Page 21: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

21 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

Programme of plantation

S.No. year Proposed plantation Area ha.

1 I 170 0.173

2 II 170 0.173

3 II 170 0.173

4. IV 170 0.173

5. V 170 0.173

5.5.3 Health and safety System

During the opencast working, and allied activities, all the precautionary measures

shall be taken into account as per MMR 1961 and MCDR 1988 for safety and security.

Following Safety & security measures will be enforced;

Moving front of the quarry shall have temporary fencing.

Permanent fencing will be provided where quarry has reached the ultimate pit

limit.

Mine entrance will have a permanent check post and record shall be

maintained of all persons / vehicles entering the mine area.

Round the clock security arrangement shall be provided to prevent inadvertent

entry of persons.

5.5.4 Disaster Management and Risk Assessment

Inspite of following all the precautionary measures and following all safety rules,

regulations and procedures, in mining accidents cannot be ruled out completely. The

Project Proponent will formulate a Disaster Management Plan with the approval of

DGMS. Following are the accidents which can take place in mechanised opencast

mining and measures proposed to be taken.

Fall of human beings or fall of machines from benches/ dumps/haul roads.

Due to drilling / blasting and handling of explosives.

Fire & Explosion in machinery

Page 22: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

22 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

Emergency situation due to social reason such as public unrest, terrorism etc.

Preventive Measures:

All provisions of MMR 1961, conditions imposed in permission for Deep hole

drilling and blasting and use of HEMM, and conditions of explosive license will be

followed.

Fire fighting equipment in the machinery/ workshop/ office will be maintained.

Persons will be trained in the use of fire fighting equipment and mock rehearsal

will be conducted.

Training of security personnel.

Procedures as laid down in Disaster Management Plan to be followed.

Training;

Persons will be trained in the following:

Knowledge of Chemicals and use of protective equipment

Procedures for reporting emergencies.

Location and use of fire fighting equipment

Knowledge of alarm system and siren

Evacuation procedures.

Training in first aid as per Mines Rules 1955

Emergency Equipment & Facilities:

Mobiles.

Fire fighting equipment’s

Emergency medical supplies

Other protective equipment’s i.e. goggles, helmet, face shield, hand gloves,

Safety belts, barricade tape. First Aid station as per the provisions of Mines

Rules 1955.

Page 23: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

23 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

6.0 PROPOSED INFRASTRUCTURE

S. No. Details

1 Lease Area 9.0 hectares.

2 Residential Area Not Applicable

3 Connectivity The village Khojon Ki Dhani nearest population center is 3.8 km

away from the lease area & it is connected with other

important towns and cities through a good network of

roads with regular public transport services. The Tehsil

Headquarters of Bilara is at a distance of 54 km by road &

District Headquarter Jodhpur is 107 km connected by road.

The nearest railhead is at Bilara at a distance of 52 km from

lease area in SW direction

4 Green Belt 170 plants will be planted per year.

5 Social Infrastructure Social Infrastructure and other necessary other facilities will be

provided by mine’s proponent.

6 Water Management 6.00 KLD, Source: nearby well .

7 Sewerage System Domestic Effluent treated in soak pits and overflow used for

gardening

8 Industrial Waste Management N.A.

9 Solid Waste Management Top soil will be generating during mining operation & it will be

used for plantation.

10 Power requirement N.A.

7.0 REHABILITATION & RESETTLEMENT PLAN

There is no human settlement within the mine lease area. No human settlement will be

disturbed due to the mining activity. So, no Rehabilitation and Resettlement is proposed.

Page 24: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

24 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

8.0 PROJECT SCHEDULE

8.1 Proposed schedule and approval for implementation

The Proposed project shall be established after getting the Environmental Clearance

from MoEF.

8.2 Project cost estimation

Estimated Project Cost for the proposed project is Rs. 70.00/- Lacs.

(A) Capital investment/-

Site facility and PPE for Labors = Rs. 1.89 lac /-

Machineries & Tools = Rs 55.00 lac/-

Financial assurance = Rs. 2.50 lac/-

PMCP = Rs. 2.50/- lacs

Social fund & activities = Rs. 2.00 lac/-

EMP = Rs. 4 lac/-

Miscellaneous = Rs. 1.80 lac/-

Total cost Rs. 69.69 lac/- (say 70 lac/-)

(B) Operational cost-

The mineral will be mined from the applied area and the cost of per ton of mining will

be approx. Rs. 180/- per ton.

8.3 ECONOMIC VIABILITY

The anticipated cost of mining is Rs. 180/- per ton cost. Average sale value is assumed

at Rs. 350-400/- ton of stone. Hence the project will be viable.

Page 25: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

25 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

9.0 ANALYSIS OF PROPOSAL

Project will create direct & indirect employment opportunities within the

surrounding region. Unit will use good faith efforts to employ local people from the

nearby villages depending upon the availability of skilled & un-skilled man-power

surrounding the project site.

In the proposed project would require significant workforce of non-technical and

technical persons. Migration of highly education and skilled experience will result in

increase of literacy in the surrounding villages.

In addition, the proposed expansion of project shall enhance the prospects of

employment.

Assessment of the potential socioeconomic benefits during mining

focused primarily on work force requirements, acquisition of supplies, and the

temporary increased demand for services related to the mining project like food,

housing, communications, law enforcement, medical care, local transportation etc.

Due to these, additional revenue to local suppliers for required products and

services related to the construction and operation phases of the project will generate.

Thus, mining activities will provide numerous new, although temporary, work

opportunities for both skilled and unskilled labor, as well as contribute

significantly to the local economy.

Additional government revenue expected from royalty, taxes, duties and other fees.

An added benefit to the proposed project will result in considerable growth of

stimulating the industrial and commercial activities in the state. Small and medium

scale industries may be further developed as a consequence.

Page 26: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

26 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

ANNEXURES

Page 27: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

27 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

Annexure-I Copy Of applied Map

Page 28: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

28 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

Page 29: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

29 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

Annexure- II Copy of Demarcation report & Pre Demarcation Report

Page 30: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

30 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

Page 31: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

31 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

Annexure-III Copy of Khasra Map & Jamabandi

Page 32: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

32 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

Page 33: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

33 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

Annexure-IV Copy of order letter of ME

Page 34: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

34 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

Page 35: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

35 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

Annexure-v Copy of Board Resolution

Page 36: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017. 9. 11. · II 247778 204021 43757 63945 65903 173605 III 299455 241645 57810 85265 128925

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

36 M/s Patla Minerals Corporation Pvt. Ltd. Khojon Ki Dhani Limestone Mine

Annexure-VI Approval Letter of Mining Plan