Pre-Disaster Mitigation Grants 2012. Presented to Palm Coast City Council December 20, 2011. FIVE YEAR GOALS Maintain a Safe Community MAJOR PROJECTS Water Control Structure (one replacement per year). CITY COUNCIL GOALS AND OBJECTIVES 2011 & 2012. Canal Control Structures 5-Year Plan. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Pre-Disaster Mitigation Grants 2012

Pre-Disaster Mitigation Pre-Disaster Mitigation Grants 2012Grants 2012

Presented to Presented to

Palm Coast City Council Palm Coast City Council

December 20, 2011December 20, 2011

Page 2: Pre-Disaster Mitigation Grants 2012

FIVE YEAR GOALSFIVE YEAR GOALS• Maintain a Safe CommunityMaintain a Safe Community

MAJOR PROJECTSMAJOR PROJECTS• Water Control Structure (one replacement per year)Water Control Structure (one replacement per year)

CITYCITY COUNCIL GOALS AND COUNCIL GOALS AND OBJECTIVES 2011 & 2012OBJECTIVES 2011 & 2012

Page 3: Pre-Disaster Mitigation Grants 2012

Canal Control Structures 5-Year Plan

COPC Eligible for Structure Waterway Rating FEMA Funding Year

R-1 Royal Palms 11 Yes 2012

BT-2 Bellaire 11 No 2013

L-1 Sesame 9 Yes 2014

M-2 Mulberry 9 No 2014

I-1 Iroquois 9 Yes 2015

I-4 Ulysses (N) 9 Yes 2015

I-6 Ulysses (S) 9 Yes 2015

L-4 Royal Palms 9 No 2016

Page 4: Pre-Disaster Mitigation Grants 2012

Three Sisters General Location

Page 5: Pre-Disaster Mitigation Grants 2012

119 cfs @ NWL 21.0’

186 cfs @ NWL 20.0’

420 cfs @ NWL 20.5’ 725 cfs @ NWL 15.2’

Page 6: Pre-Disaster Mitigation Grants 2012

Three Sisters Design Three Sisters Design ConsiderationsConsiderationsOver the last 2 years, many designs were considered, and eliminated:

•A bridge would be required to maintain and construct a single weir.

•Each waterway has a different elevation and flow rate.

•The stilling basin before the culverts under I-95 attenuates and reduces water velocities.

•The proposed design has been permitted by the SJRWMD.

•A new design would require withdrawal of the PDM Grant application.

•With new design elevations, the new permit would require stormwater and groundwater modeling.

Page 7: Pre-Disaster Mitigation Grants 2012

Three Orphans General Location

Page 8: Pre-Disaster Mitigation Grants 2012

QUESTIONS ?