5/07/2010 AEP - 01 1 CHENNAI METRO RAIL PROJECT TRACTION / SUBSTATIONS AEP - 01 PRE – BID MEETING 09 th AUGUST 2010

Upload: kesavmurthy1972

Post on 19-Nov-2014

154 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 011

CHENNAI METRO RAIL PROJECT

TRACTION / SUBSTATIONS AEP - 01

PRE – BID MEETING09th AUGUST 2010

Page 2: Pre - Bid Meeting PPT - AEP 01

CONTENTS

5/07/2010 AEP - 012

• PROJECT KEY DATA

• SCOPE OF THE CONTRACT

• RECEIVING SUB STATION (RSS)

• 33 kV AUXILIARY SUPPLY &

• AUXILIARY SUB STATION (ASS)

• SCADA

• TRACTION NETWORK

• OHE ARRANGEMENT

• INTERFACE MANAGEMENT

• BIDDING PROCESS

• LIST OF DOCUMENT TO BE SUBMITTED

• BIDDER QUERIES

Page 3: Pre - Bid Meeting PPT - AEP 01

PROJECT KEY DATA

5/07/2010 AEP - 013

THE PROJECT IS SPLIT INTO THREE (3) STAGES:

1. Stage 1 (37.2 tkm) consists of the elevated part (Koyambedu to St.

Thomas Mount) of the Corridor 2 and Koyambedu depot.

2. Stage 1a consists of Chennai Airport to Little Mount (Elevated part

of Corridor 1, 17 tkm) and transition works from Stage 1

3. Final stage consists remaining part in both corridors (Underground

parts, 49 tkm) and transition works from Stage 1 a

Page 4: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 014

SECTIONTRACK LENGTH IN KM

CORRIDOR – I CORRIDOR –II TOTAL

UNDERGROUND 29 20 49

ELEVATED 17 23.5 40.5

DEPOT - 13.7 13.7

PROJECT KEY DATA

Page 5: Pre - Bid Meeting PPT - AEP 01

55/07/2010 AEP - 01

C&CUG sections:

Elevated:

Page 6: Pre - Bid Meeting PPT - AEP 01

SCOPE OF THE CONTRACT

5/07/2010 AEP - 016

The Works to be executed under this Contract includes

• the design, manufacture and supply,

• the installation, testing and commissioning

• the technical maintenance support including training of personnel

for a complete, integrated Power Supply and Overhead

Equipment system for Corridor 1, Corridor 2 and Koyambedu Depot.

Page 7: Pre - Bid Meeting PPT - AEP 01

• 110 kV AC GIS Receiving Substations (3), related Auxiliary Main

Substations (3) & Traction Substations (3)

• 33 KV cable ring main network , 33 kV switchgear, DC supply for

the controls, 33kV/415V transformers (dry type), DG sets

• SCADA , control and monitoring of the complete 110kV, 33 kV and

25 kV power supply system, including the interfacing with other

project SCADA systems and its integration at the Depot Operations Control Center

• all civil works for the RSS buildings and for the 25 kV AC traction

supply

• other equipments in the RSS such as Low Voltage distribution

system, UPS and DC system

5/07/2010 AEP - 017

SCOPE OF THE CONTRACT

Page 8: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 018

• the quality and safety management

• the training to operation and maintenance of personnel for the

project

• the supply of spares, maintenance tools and operation &

maintenance manuals

• the interface management

• all the transitions works necessary for a staged operation

SCOPE OF THE CONTRACT

Page 9: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 019

Page 10: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 0110

RSS LOCATION – CHENNAI CENTRAL

Page 11: Pre - Bid Meeting PPT - AEP 01

RSS LOCATION – KOYAMBEDU DEPOT

5/07/2010 AEP - 0111

Page 12: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 0112

RSS LOCATION – ALANDUR

Page 13: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 0113

• Land Preparation

• Civil / Structural / Services / Finishes

• Access roads

• All building services : lighting and small power, fire detection, fire

fighting, water supply, sanitary & sewage, plumbing and drainage

works, etc …

RSS CIVIL WORKS

Page 14: Pre - Bid Meeting PPT - AEP 01

RSS BUILDING – SECTION PLAN

5/07/2010 AEP - 0114

Page 15: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 0115

RSS BUILDING – FLOOR PLAN

Page 16: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 0116

33 kV AUXILIARY SUPPLY: OPTION 1

Page 17: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 0117

33 kV AUXILIARY SUPPLY: OPTION 2

Page 18: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 0118

AUXILIARY SUB-STATION

• Auxiliary transformers of 33 kV/ 415 Volts Dry type transformers

• Chennai Central will have 3 nos of Auxiliary transformers.

• All other stations will have 2 nos of Auxiliary transformers at

each stations.

• MV Switchgear

• Diesel Generator set (415 Volts)

Page 19: Pre - Bid Meeting PPT - AEP 01

SCADA

The SCADA system shall comprise of the following:

• Dedicated Human Machine Interface (HMI) maintenance terminals

• Head-end servers and database

• Remote Terminal Units (RTU) / Programmable Logic Controllers

(PLC)

• Marshalling Cabinets

5/07/2010 AEP - 0119

Page 20: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 0120

TRACTION NETWORK: SECTIONING SCHEME

Page 21: Pre - Bid Meeting PPT - AEP 01

Traction network includes:

• Traction substation (TSS)

• Feeding post (FP)

• Sub sectioning post (SS)

• Sub sectioning and paralleling post (SSP)

• Overhead contact system (Flexible & Rigid)

5/07/2010 AEP - 0121

TRACTION NETWORK

Page 22: Pre - Bid Meeting PPT - AEP 01

OHE ARRANGEMENT

• Underground stations, cut & cover, tunnels: Rigid overhead contact

system (ROCS)

• Viaduct - Portals with drop arms & masts with base plate welded

• Depot - Portals with drop arms & masts with foundation

5/07/2010 AEP - 0122

Page 23: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 0123

OHE ARRANGEMENT ON VIADUCT

Page 24: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 0124

OHE FOUNDATION IN DEPOT

Page 25: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 0125

Contractor will have to focus on:

• Minimizing power losses

• High quality OHE design to achieve good Panto-OHE contact

performance

Page 26: Pre - Bid Meeting PPT - AEP 01

INTERFACE MANAGEMENT

5/07/2010 AEP - 0126

Page 27: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 0127

INTERFACE SHEET – EXAMPLE

Page 28: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 0128

Page 29: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 0129

Page 30: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 0130

Page 31: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 0131

Contractor have to focus on

• Interface management scope as per interface sheets and

interface drawings.

• Being part of the interface management process with the other

contractors.

• Following the various interface requirements required in all

stages of work such as

• Design stage

• Supply & Installation stage

• Testing & Commissioning stage

• Maintenance stage

INTERFACE MANAGEMENT

Page 32: Pre - Bid Meeting PPT - AEP 01

BIDDING PROCESSBID DATES:

LAST DATE FOR CLARIFICATIONS – 10th SEPTEMBER 2010

BID SUBMISSION DATE : 8th OCTOBER 2010 (up to 14:00 hrs)

BID OPENING DATE: 8th OCTOBER 2010 (at 14:30 hrs)

BID VALIDITY PERIOD: 150 DAYS

COMPLETION OF THE FACILITIES: 1490 days (49 months)

CONTRACT PERIOD: 2220 days ( 73 months) from the Effective Date (24 months from the date of completion with respect to end of Defect Liability Period)

5/07/2010 AEP - 0132

Page 33: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 0133

S.NO. LIST OF DOCUMENTS / FORMS TO BE SUBMITTED

1 Form of Bid (Annexure-1 of ITB)

2 Bank Guarantee for Bid security (Attachment-1 of ITB / Annexure 2 of ITB)

3 Bid Documents ( Vol 1 to 8) : Original, plus one copy duly signed

4 Power of Attorney (Attachment-2)

5 Bidder's Eligibility and Qualifications (Attachment–3 of ITB)

6 Eligibility and Conformity of the Facilities (Attachment-4 of ITB):

6.a Technical & Performance characteristics of the Facilities - As per 9.3(d)(i) of ITB

6.b List of full particulars of the facilities including available sources, spare part & special tools, etc. - As per 9.3(d)(ii) of ITB

6.c Technical Specification of the facilities - As per 9.3(d)(iii) of ITB

6.d Bidders Technical Submissions - As per 9.3(d)(iv) of ITB

6.e Other relevant technical requirements - As per 24.1(d) of BDS

LIST OF DOCUMENTS TO BE SUBMITTED

Page 34: Pre - Bid Meeting PPT - AEP 01

5/07/2010 AEP - 0134

S.NO. LIST OF DOCUMENTS / FORMS TO BE SUBMITTED

7 Form of Contract Agreement (Annexure-3 of ITB):

7.a Price Adjustment (Appendix - 2 of Annexure-3 of ITB)

7.b Insurance Requirements (Appendix - 3 of Annexure-3 of ITB)

7.c Time Schedule (Appendix - 4 of Annexure-3 of ITB)

7.d List of Subcontractors proposed by the bidder (Attachment 5)

8 The bidder should submit as proof, a letter issued by the manufacturer or producer confirming that the manufacturer or producer is supplying and/or installing plant and equipment - As per 9.3 – (c) of BDS

9 The Bidders shall submit a list of items of supply or services that they propose to purchase as per 9.3(e) of BDS

10 Statement of Minor Deviations (Annexure-10 of ITB)

11 Pricing Documents (As per Vol 7, and priced for Financial Evaluation Only)

12 Prequalification Criteria Undertaking (annexure 17 of ITB)

LIST OF DOCUMENTS TO BE SUBMITTED

Page 35: Pre - Bid Meeting PPT - AEP 01

TECHNICAL EVALUATION

Bidders have to fill all Technical Data Sheets of Appendix B of Volume 4.

When expected values are provided in Technical Data Sheets, the value shall be confirmed by the bidder otherwise it will be treated as a deviation.

Bidders have to provide a pre RAM plan in accordance with Clauses 4.2.1.1 and 4.2.1.2 of Section 4 ,Volume 4. The pre RAM plan shall demonstrate the proposed facilities have ability to meet the RAM requirements specified .

Bidders have to provide details of rigid overhead catenary system as per clause ITB 24.1 (d) of BDS.

The above information is to be included in Attachment 4 of ITB Clause 9.3

Minor deviations shall be listed in Attachment 6 to the Bid as per the form contained in Annexure 10 of ITB.

5/07/2010 AEP - 0135

Page 36: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 1

5/07/2010 AEP - 0136

Queries

ABB Limited is a large company of a repute and also Capable of carrying out large projects with it's own resources and credit limits with Indian banks. Also, as you are well aware, ABB Limited is a Market leader for Metro Rail Project business in India having executed majority of Delhi Metro Rail Projects and are also carrying out Metro Rail Projects in Bangalore and in Mumbai. In view of these reasons, the requirement of parent company guarantee & parent company undertaking may please be waived for ABB Limited. Pease confirm.

As per RBI Guidelines, banks are issuing Bank Guarantees with the following additional clauses1) Notwithstanding anything contained hereinabove Our liability under this guarantee is restricted to Rs. ________(Rupees _________Only) 2) This Bank Guarantee shall be valid up to _______. 3) We are liable to pay the Guarantee amount or any part of thereof under this Bank Guarantee only upon the Employer serves upon us a written claim or demand on or beforethe date of expiry of the guarantee i.e. on or before _________.We request you to consider the above and amend the formats accordingly.

Page 37: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 1

5/07/2010 AEP - 0137

Queries

Please increase the amount of advance payment to 20% as 5% will result in a severely negative cash flow for the Contractor..

Please confirm that 5% retention money withheld from each interim payment can be replaced by an equivalent bond.Alternatively, please consider to release 50% of retention money upon Operational Acceptance of Stage 1 and the remaining 50% upon Operational Acceptance of Stage 2 (as the Performance Security shall be valid until the end of the Defects Liability Period anyway).

Please confirm that the provisions of Clause 7 do not apply as the payments shall be released to the Contractor by the Employer (see inter alia Clause 2.1).

Please specify the Employer's scope of works and supply in more detail.

Please confirm that the bank guarantee can be reduced gradually in proportion to the amount of advance payment deducted from interim payments made by the Employer to the Contractor.

Please replace the term "Works" with "Facilities" throughout the document. Same applies for the other parts of Bidding Documents.

Please confirm that the information to be provided by the Contractor will be solely used for the purposes of the project, i.e. for operating and maintaining the Facilities.

Please delete the requirement for such warranty as the Contractor will not find suitable sub-contractors who agree to such agrrements.

Please confirm that Annexure 14 does not apply in case the parent company takes part in the bidding consortium.

Please confirm that Annexure 15 does not apply in case the parent company takes part in the bidding consortium.

Please confirm that Annexure 16 is not applicable as the ITB do not specify any requirements for such guarantee.

Page 38: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 2

5/07/2010 AEP - 0138

Queries

Patent indemnity obligations cannot be extended to claims on account of the sale of the products produced by the Facilities in any country, as the Contractor cannot be liable for patent infringement of products produced in the Facility. Hence the same is to be deleted. Indemnity for patent infringement will not be provided to the Employer in the following cases: a) Modifications to the product/ equipment made in accordance with specifications/ modifications required by the Employer b) Designs/ documentation provided by the Employer c) Use of the product/equipment supplied by us, in contravention of our instructions for use.

The exclusion of the obligation of the Contractor to repair or replace defective Equipment from the overall liability cap to be removed.

Since tender provides for High Sea Sale transactions, Please confirm that the project registration with customs would be done by CMRCL for all imports for the projects and the contractor obligations will be restricted only to facilitate the clearnce of the customs.

We request you to specify the notice period in cases of termination for convenience.

The sales tax authority of Tamil Nadu is in the process of assesment for the year 2005-06 recently and hence we will not be in a postion to produce the clearance certificate due to non completion of assesment by the authorities. However, we can submit copy of VAT Registration certificate and latest monthly returns to ensure that we are registered and making regular VAT payment in state of Tamil Nadu. Please arrange to modify the clause suitably.

As per the provsiion of Tamil Nadu VAT Act , interstate Own manufactured items & imported supplies are outside the purview of the works contract in Tamil Nadu. Hence, no TN VAT will be payable for these trasanctions. Please confirm that no Works Contract TDS will be deducted on the above transactions.

For local supplies ,if contractor submits non deduction certificate from their assessing authorities , WCT should not be deducted. please confirm .

Page 39: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 2

5/07/2010 AEP - 0139

Queries

Since the project is Metro rail project and under the provision of service tax 69 , services / labour portion of Railway project is outside the ambit of service tax. Please confirm whether service tax is applicable for this project .

We request you to consider the following as Defects Laibility period.For Stage 1 : the Defect Liability Period shall be twenty four (24) months from the date of Completion of the Facilities or Thirty (30) months from the date of despatch of last consignment for the Stage 1, whichever occurs earlier.For Stage 2 : the Defect Liability Period shall be twenty four (24) months from the date of Completion of the Facilities or Thirty (30) months from the date of despatch of last consignment for the Stage 1,whichever occurs earlier.

Events mentioned in sub clauses ii, iii, iv, vi, vii, viii and ix are events beyond control of contractors and hence right of extension of time is needed. We request you to delete the above sub clauses.

Suspension of work for reasons not solely attributable to the Contractor should entitle the Contractor to costs incurred. We request you to delet this clause.

While payment of exgratia is acceptable,Providing employment to the dependent of the deceased is not acceptable. We request you to delete this requirement.

We are not responsible for registration or payment of cess under BOCW Act'1996 and Welfare Cess Rules'1998. You are requested to confirm that you shall not deduct any amount during the execution towards BOCW & Welfare cess.

Employer‘s failure to provide possession of or access to the Site or other areas failure to obtain any governmental permit necessary for the execution and/or completion of the Facilities is excluded from the grounds for which contractor has a right of suspension.Contractor should have a right to suspend the work on these grounds as well and hence we request you to amend the clause suitably.

An express disclaimer is to be provided regarding equipment supplied, disclaiming all implied warranties including warranties of merchantability and fitness for purpose.We request you to incorporate the following additional clause as part of Special Conditions of contract"Except as expresly provided under the contract, the Contractor disclaims all implied warranties including warranties for merchantability and fitness for purpose".

Page 40: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 2

5/07/2010 AEP - 0140

Queries

Please confirm that the Contractor is responsible for obtaining permits, approvals and/or licenses required for the Contractor's scope of works only.

Please confirm that the Employer is obliged to provide access to the site as specified in Clause 10.2 irrespective of the provisions of Appendix 6 of the Form of Contract.

Please confirm that all permits, approvals and/or licenses to be applied for in the name of the Employer will be applied for by the Employer regardless of the provisions of Appendix 6 to the Form of Contract.

Please add: "The Contractor's performance obligations are subject to the proviso that the fulfillment is not prevented by any impediments arising out of national and international foreign trade and customs requirements or any embargos or other sanctions."

Please confirm that dispute resolution as per GCC Clause 6 can be a recourse in case of disagreement between the Employer's Representative and the Contractor.

Please confirm that the Employer will provide operating and maintenance personnel for pre-commissioning as specified in GCC Clause 24.1 irrespective of the provisions of Appendix 6 of the Form of Contract.

It is understood that the Employer's Representative may only withhold the Completion Certificate for reason of major defects that adversely affect the functionality of the Facilities. Minor defects not adversely affecting the functionality of the Facilities may not serve as grounds for the refusal to issue the said certificate. Please confirm.

Please confirm that the information to be provided by the Contractor will be solely used for the purposes of the project, i.e. for operating and maintaining the Facilities.

Please confirm that the information to be provided by the Contractor will be solely used for the purposes of the project, i.e. for operating and maintaining the Facilities.

Please changei) Arbitration rules according to the rules of the International Chamber of Commerce (ICC)

Please confirm that price for spare parts for a period of 8 years upon expiry of DLP shall not be included in the Lump Sum Price.

Page 41: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 2

5/07/2010 AEP - 0141

Queries

"Those parts of the Works subject to Key Dates shall be completed to a state whereby any Interfacing Contractor can immediately commence his works without the need to make any change, addition or modification to the Contractor‘s Works."Pease confirm that this provision applies subject to the Contractor having implemented the Facilities in accordance with the Contract as the Contractor cannot reasonably be expected to implement interface requirements beyond his contractual obligations.

Please clarify that all taxes and duties shall be paid by the Contractor and shall be included in the Lump Sum Price.

Please confirm that dispute resolution as per GCC Clause 6 can be a recourse in case of disagreement between the Employer's Representative and the Contractor.

Please define the term "Operational Commissioning" or replace it with "Commissioning".

Please confirm that Liquidated Damages paid on individual Key Dates will be returned if the Contractor meets the final Key Date.

Please delete "if such suspension is necessary for the proper execution of the Works". Otherwise, please clearly specify the events referred to by this phrase.

Please confirm that this requirement applies in case of death or total incapacitation of Contractor's staff only.

Please confirm that any and all road works are the scope of other contractors.

Please confirm that 5% retention money withheld from each interim payment can be replaced by an equivalent bond.Alternatively, please consider to release 50% of retention money upon Operational Acceptance of Stage 1 and the remaining 50% upon Operational Acceptance of Stage 2 (as the Performance Security shall be valid until the end of the Defects Liability Period anyway).

Page 42: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 3

5/07/2010 AEP - 0142

Queries

As almost all electronic equipment is prepared for ambient 35°C and max. 40°C with max. 90% humidity, We request you to modify this clause accordingly. Air conditioning should be specified for these values.

As not all suppliers use AUTOCAD for drawings at allwe propose to produce all drawings with appropriate CAD-Systems and transfer them finally into dwg- or dxf-files that can be transmitted into the AUTOCAD-System. Kindly confirm that same is acceptable.

Page 43: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 4

5/07/2010 AEP - 0143

Queries Performance of the overhead line system shall be demonstrated according to OHLE/pantograph dynamic behaviour for the maximum design speed (80km/h + 10%).

Normally, a Simulation is done to determine the performance of the overhead line system when the dynamic behavior of the OHLE with pantograph interaction is studied. The tension in the OHE Conductors, pre-sag, dropper spacing etc and the pantograph characteristics such as upward pressure, primary and secondary suspension properties etc are taken into account for Simulation. The dynamic behavior is studied for various speeds and the maximum recommended speed is arrived at. This Simulation is done only for new OHLE Designs. Since we are going to use only proven designs, already certified for speeds 80 kmph and above (upto nearly 120 kmph), this Simulation may not be required. CMRL may please review & confirm.As per cl.2.2.9 ( c), it is envisaged to provide One ASS at every passenger station and Two ASS at Koyembedu depot, whereas as per cl. 3.2.4.4, it is envisaged to proVIDE One ASS at every passenger station and Three ASS at Koyembedu depot. Please clarify and confirm the requirement. “It is envisaged to provide one ASS at every passenger station and 2 ASS in Koyambedu Depot”.In Underground Stations also, will there be only 1 ASS with 2 transformers?.Incoming bays, Power Transformer bays & coupling bays (at RSS):The description of these clause refers / suits for Air-Insulated Substation, whereas the requirements are gas Insulated Substations. Please clarify and may amend the specification.As per clause 3.2.1.4.3 e, gas flooding system is required for all equipments in the switchgear room, wheras as per clause 6.6.2.4.5.9.8, 4 Nos of 5kG CO2 portable fire extinguishers shall be supplied for the power equipment room. Please clarify and confirm the requirement of fire protection system for switchgear / power equipment room.We presume that acquistion of land, right of way & other permissions for laying 110kV cabling works shall be in the scope of CMRL. Please confirm.

Page 44: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 4

5/07/2010 AEP - 0144

Queries Supply and erection of a) HV (110 KV) Cables from the TNEB metering station to RSS. Contractor will provide these cables and terminate them in the Cable end boxes / cable termination structure at the TNEB metering station at one end & CMRL RSS at the other end.

CMRL may clarify• Who will provide the Cable termination Structures in the TNEB Metering Station• Who will provide the Instrument Transformers (CT, PT), for protection and measurement, in the TNEB Metering Station• Incidentally, there is no “Interface Sheet” (between AEP-01 & TNEB), in the Bid document. CMRL may consider providing a suitable interface sheet.This item talks about ‘foundations’ for OHE. It is understandable if it is only for ‘at-grade’ sections. However in the ‘Interface Sheet’ (PageA7), it says AEP-01 Contractor shall furnish loading particulars to Viaduct Contractor AC-01 and shall design the type of mast “including base plate of bolted mast foundation ….” And AC-01 shall provide the details of foundations …..”. Normally, the Viaduct and the parapet are designed taking into account the loads due to OHE and the Holding Down Bolts are provided by the Viaduct Contractor where the OHE Contractor ‘fastens’ the OHE mast via Base Plate and Nuts. The drawing also shows a “Typical OHE Mast foundation on Viaduct”. The arrangement needs to be clarified.“Automatically switched neutral section at all neutral sections and feeding posts”, is included. The “Traction feeding and Sectioning Diagrams” show “Short Neutral Sections”. CMRL may please clarify as to what system is intended to be used.

In the list of items included in the Scope of Work, “Supply and erection of Booster Transformers and Spider return Conductors, if required (items) is also included. It is not clear who will decide, and how, whether the BT’s and RC is required of not. This will have a substantial implication on the Contract price CMRL may please clarify. In the same list (item 4), it is stated, “Mast Foundations and Geotechnical investigations shall be done as per foundations design and calculation”. It is not clear. CMRL may please clarify.

The Auxiliary Transformer capacities have been specified in this para. Since we do not have any control on the downstream loads and the same (downstream loads) are not in our scope of works, we shall consider specified capacities for auxiliary transformers, for estimating the lumpsum price. Please confirm.

Page 45: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 4

5/07/2010 AEP - 0145

Queries

Comments as above apply to capacities of DG Sets also. Please confirm.It is stated that the traction system shall be able to allow the normal operation of the train in 2026, considering 32 six-car trains per corridor and a 2.5 minutes headway for the specified degraded model. In para 4.4.4.2 it is also stated that when one out of the three TSS is out of order, it shall be possible to run 6-car trains at 5 minutes headway. We request clarifications from CMRL.• Is a Traction Simulation Study required to be carried out as a part of Design & Build Contract. In this connection, the following may be noted- The locations of Traction Substations (3 in number) are fixed as per Bid Documents- Capacities of traction transformers (ONAN) are fixed 21.5/30 MVA.- Headways for normal operation (2.5 minutes) and degraded operation (5 minutes) are fixed.

In view of the above, it may please be clarified whether a Traction Simulation Study is required to be done and if so, what would be the scenarios for which Simulations are to be done. If the Power Supply System Design has to be altered based on the Simulation Study, will the variations be paid for by the CMRL. • The Bid Documents specify (see para 3.5 of General Overview) that initially 4-car trains (DTC+MC+MC+DTC) will be used. Subsequently 6-car rakes with (DTC+MC+MC+MC+MC+DTC- 67% Traction Power) OR (DTC+MC+TC+MC+MC+DTC-50% Traction Power) configuration will be used. To maintain the System performance (2.5 minutes headway or 5 minutes headway) with the above 2 configurations, the Power Supply Design will be different. The Bid specification should clarify as to what would be the design criteria. CMRL may please clarify.

Line differential requires supply of identical two differential relays one at TNEB Metering station and the other at proposed receiving station. We presume that there is a feeder protection panel is already existing at TNEB metering station and we need to supply loose relay, which shall be mounted at existing feeder protection panel. Please clarify and confirm.

Our recommendation is to use master-master communication system. However, master-slave configuration is possible through setting which is not automatic. Please confirm.

Page 46: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 4

5/07/2010 AEP - 0146

Queries

We presume that the "110/25kV Auxiliary Power Transformer" contains typographical error and the same may please changed as "110/25kV Traction Power Transformer".

We provide protection bay wise, which will detect the fault in a particular bay and isolates the fault. Total current monitoring of current and disconnection of number of bays will isolate few healthy bays also, hence it is not recommended. Please clarify and confirm.

Data Retention periods for Historical Storage is not mentioned. This is required to size the servers.

What is the purpose of web enabled operator consoles as the web browser interface can be provided for remote monitoring, even if the operator consoles are not web enabled.

Description of lightning protection refers for Lightning protection of Air Insulated substation. Please clarify and the specification may please be amended suitably for GIS.

Please confirm whether the foundations mentioned herein is in the scope of other contractors.

DG sets proposed for all passenger stations and the DG sets will be supplied with acoustic enclosures and does not require any room and fencing. Please confirm whether the construction of DG room is in the scope of contractor in all passenger stations. Please clarify and confirm.

Please confirm the scope of supply of UPS and construction of room for UPS. Please clarify and confirm.

Please inform us what type of fire detection system to be offered against this requirement.

Please furnish us the specification of main building and also please inform which is main building.

We presume that the lightning arresters for incomers and transformers feeders are outdoor Air Insulated Type. Please confirm.

RDSO approval will not be applicable for 110kV GIS. Please confirm.

Page 47: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 4

5/07/2010 AEP - 0147

Queries

These specifications are similar to the specification of outdoor AIS equipments. Please confirm whether the outdoor AIS bays are included in our scope.

As per the normal practice, most of the GIS supplied with free standing LCC and the same may please be accepted.

Requirements furnished earlier in this specification will be applicable for AIS equipments and it will not be applicable for GIS e.g requirement of cl.7.1.1.41 Page 7-4. Please confirm.

As per normal practice, TNEB will insist for Dyn11 vector group for 110/33kV power transformers. Please clarify and confirm.

Ratings of 110/33kV power transformers mentioned in these clauses are differing i.e 25/31.5MVA Vs 31.5/40MVA. Please clarify and confirm the losses, if the ratings required is 25/31.5MVA.

As per the specification, the neutral of secondary winding is earthed through a resistor and hence the 33kV system will become unearthed system and correspondingly the highest system voltage at 33kV will become 52kV and not 36kV. Please clarify and confirm.

No Servo mechanism is required for parallel operation of the transformer and hence same will not be provided. Please confirm.

As per the practice, the radiators are epoxy / enamel painted. The requirement may please be modfied as "Hot dip galvanisation or epoxy /enamel painted for radiators.

For solid earthing of high voltage neutral, no isolators shall be introduced in the connection between neutral and earth electrode. Please explain the purpose of this isolator.

Aluminium / Aluminium can also be considered for the windings, since the same are having advantages over copper windings and the same have been accepted in other metro projects. Aluminium / Copper windings (primary / secondary) are not manufactured and the same may please chnaged as Aluminium / Aluminium or Copper / Copper.

Page 48: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 4

5/07/2010 AEP - 0148

Queries

Specification calls for both Vaccum / SF6 Breaker. This requirement shall be restricted to Vacuum only in line with other metro projects.

Specifcation is silent about the Internal Arc Classification requirement. However, as per the latest IEC (IEC 62271- 100/200), a switchgear should be Internal Arc Tested and an Internal Arc Classified switchgear should be tested for 1s at the design fault level at the most stringent condition. Kindly amend the specification.

Specification calls for complete painting in the metal surfaces of the switchgear. However we will offer panels made up of special environment friendly material called "Alu Zinc" which is used globally by leading switchgear manufacturers. Alu Zinc is light in weight, has more strength, and extremely corrosion resistant compared to normal CRCA sheets and this does not require any surface treatment like powder coating. Panels shall be made up of Alu Zinc material except front doors & end covers which shall be painted sheet steel. We shall provide powder coated paint only for front doors and end covers,which shall be made of CRCA sheet.

The purpose of the standby rectifier set is not clear. Please elaborate and explain.

The rating of circuit breaker shall be designed for the transformer secondary connected to it. The current rating 630A mentioned for 100 to 200kVA auxiliary transformer secondaries are very high. Please clarify.

Please explain the purpose of a "on/off voltage relay" and what exactly means "permanent power supply".

"LVSB1 and LVSB2 shall be connected to the respective transformers, by the station contractor". Please clarify which connection this clause refers to and we presume that the "station contractor" refers to passenger station building contractor.

Due to cast resin dry type transformers, Protection against the gas & Protection against low oil level are not applicable. Please confirm.

The requirement of Fault detection relay with torroidal transformers at 33kV switchgear for 33kV cables faults is not clear. Please clarify.

Page 49: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 4

5/07/2010 AEP - 0149

Queries We presume that terminalogy "Lightning bridge circuit breaker, Lighting bridge coupling circuit breaker & Lighting cable circuit breaker" refers to protection relays. Please clarify and confirm.

Low voltage protections are not applicable for 33kV switchgear. Please clarify and confirm.

Please confirm the 33kV switchgear busbar shall be protected with bus differential as per these clauses. Please let us know the busbar differential is really required for 33kV switchgear. clarify and confirm.

Please confirm the 33kV switchgear shall be provided with synchronisation facility as per this clause. Please clarify and confirm.

As per the normal practice, the overall impedance of the earthing mat shall be restricted to 1 ohm. Please confirm.

Single phase impedance relay shall be with open protocol.

Please inform us the location of these DG set installations in Elevated and underground stations.

Capacity of Day tank (name itself) shall be with capacity of fuel sufficient for one full day of operation of DG set and not for 7 days operation. Please clarify.

Please confirm whether the Gas flooding system / Fire tracing shall be provided for AMF panels of DG sets.

Please note for 1500KVA Dgset the total noise insertion loss shall be 25Dba and the requirement of 75db at 1Mtr distance is not applicable for DGsets of capacity more than 1000kVA as per CPCB guidelines.Alternator shall be suitable for 150% overload for 30 sec. Please clarify and confirm.

Please note that the AVR may be integrated with the DG set controller as per manufacturer’s standard design, hence separate AVR may not be provided.Starting battery shall be provided as per DG manufacturer’s recommendation and standard practice. Please clarify and confirm.

Page 50: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 4

5/07/2010 AEP - 0150

Queries As per the clause 7.1.3.1.5, Page 7-10, the earth faul current is limited and the same will be flowing thorugh the mettalic screen of the cables. Hence, metallic screen shall be designed to carry the earth fault current and not short ciruit current. Please confirm.Linear resistance shall be different for copper and aluminium conductor. Please clarify whether linear resistance given herein is for copper or aluminium. We presume that this is for copper, if so, please provide for aluminium conductor, which is in the range of 0.0469 Ohm/kM.The voltage grade of the cable 18/36kV refers to earthed grade, whereas it is mentioned as unearthed type. Please clarify and confirm.Service Life of 15 years is not possible for Core SCADA equipment's like Servers and software. Due to their very nature, these equipment's keep updating very frequently. Hence any single installation can not have a service life of 15 years. CMRL shall have a policy to have a continuous AMC's so that equipment's and software are upgraded as and when required.There is no mention of any OS for the servers and workstations.

Data Retention periods for Historical Storage is not mentioned. This will be required to size the server accordingly

There are some observations/questions on the ‘Traction Feeding & Sectioning Diagrams’ and ‘Single Line Diagrams for RSS/TSS’ etc. These can at best be discussed.We shall offer type tested equipments for this project and we shall submit the type test certificates conducted earlier on similar or higher rated equipments for the approval during the execution stage. We presume that the same are acceptable to CMRL and hence need not to repeat the type tests / special for this project. Please confirm.In line with our policy, we shall ensure compliance with our OHS standards as a minimum on site, that is complying with well known international standards being ILO Safety and Health in construction ISBN92-2-107104-9,Operation of electrical installations EN 50110-1 Commission (IEC) 61482. Please confirm whether CMRL follows any other OHS standards to be followed at site? If yes, please arrange to forward for our reference.

Page 51: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 4

5/07/2010 AEP - 0151

Queries You are requested to bring to our notice any site specific hazard(s) that may affect ABB’s employees or its contractors during the execution of the work on site. As per our assessment of following listed specific hazards, we do not find any hazards in the proposed green field project. - Presence of asbestos materials within the proposed working area;- details of other legacy issues such as presence of polychlorinated biphenyls (PCB’s) in old electrical equipment such as transformers, lead and other heavy metals etc.- other ground contamination where excavation work may be carried out;- location of any live electrical conductors that will remain energized throughout the execution of the work on site;- location of any areas where there is a significant concentration of flammable liquids or vapors likely to be present.- details of any areas where there are hazardous substances present that may present a risk to ABB employees or its contractors;- details of any radiation hazards likely to be encountered;- location of any pressurized systems, pipelines that may be located within the proposed working area;- location of any underground services that may be encountered during the work.We reserves the right for the purpose of health and safety requirements to create a “site” physically demarcated within which we can exercise control, and in particular prevent access by unauthorized persons, including the client’s personnel particularly during high risk activities such as erecting steel works, testing and commissioning. Please confirm.We request you to appoint a representative to liaise with our Responsible/site manager on matters relating to OHS and general progress during project execution. Please confirm.This can be guaranteed only doing train simulation and the performance values can slightly differ from those specified. Will it be acceptable ?

We understand that the overall system functionality is Chennai Metro responsibility.

For RAMS the standards EN50126, 50128 and 50129 are specified. EN50128 and 50129 are not relevant for power supply systems but are contructed to attend the “signalling”system.Therefore ,we ask to reduce the requirement to RAMS to EN50126 only.

Page 52: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 4

5/07/2010 AEP - 0152

Queries

Please confirm that rails are in direct contact with earth and delete that item of specification clause 5.5.6.

We understand that the indications to air-insulated switchgears are residues from duplication of older or similar specifications related to air insulated switchgear. Kindly confirm that the requirement of Chennai metro is of SF6-gas insulated switchgear. Kindly modify the specifications accordingly in the next ammendment.

We request to confirm that 27.5 kV switchgear shall be SF6 gas insulated. If yes, please amend the clauses accordingly.

Therefore, we recommend that the specification should be

changed to Impulse withstand voltage of 200kV. Kindly confirm and amend accordingly.

Please confirm that rails are in direct contact with earth and delete that item of specification clause 5.5.6.

Please explain in detail the requirement in "necessary works during transition from Stage-I to Phase-I"

Customer shall provide maximum supporting steel fixtures intervals permitted

Please confirm whether Fabricated B-Series Structures shall be used depending upon the requirement along with H type mast Please confirm whether RDSO type N, O, P, R, BFB portals shall be used depending upon the requirement in place of H type portalsPlease confirm whether 107Sq.mm. hard drawn grooved copper conductor can be used as contact wire for stabling lines and workshop lines

Customer shall elobrate the requirement under Corrosion protection measure including the menace of bimetallic effect

Please confirm the rolling stock contractor shall supply complete pantograph assembly including collector strips

Customer shall elobrate in detail the requirment of "Installation of bird protection devices"

Page 53: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 4

5/07/2010 AEP - 0153

Queries Customer shall confirm for Main lines the mechanical tension of the messenger wire and of the contact wire are kept constant by means of Gas / Spring tensioning device in place pulleys-block tensioning device. Customer shall confirm for Main lines the mechanical tension of the messenger wire and of the contact wire are kept constant by means of Gas / Spring tensioning device in place pulleys-block tensioning device. Please confirm Zinc coated galvanised steel cantilever fittings required or stainless steel cantilever fittings required in Main lines. Please confirm Cold Rolled Seamless or galvanised steel tubes to be deployed for cantilever assemblies and also request you to mention the sizes of the cantilever tubesPlease clarify and confirm whether the following studies shall be performed by Power supply & Traction contractors as part their scope of works.- Traction load flow simulation study- EMC/EMI study- Earth potential rise study- System / line resonant frequency study- Harmonic analysis studyWhere the OCC is proposed ?

What are the railway controlled facilities to interfaced with SCADA System. Pl provide details

Are "Universal Workstations" dedicated SCADA workstation to be provided at OCC and each SCR. Pls confirm. Why are these called 'Universal' ? Are these SCADA Workstations other than the 'Universal Workstation" mentioend in clause 3.2.2.2.3

We assume that 1 SCADA workstation is needed at each RSS and SCR. Please confirm.

Please provided the hardware/server/workstation details and quantities required for OCC and SCR

Is any Video Wall for the control . If yes pl provide the details

This clasue is contradictory with clause no. 2.2.9 c---"It is envisaged to provide One ASS at every passenger station and Two ASS at Koyambedu depot"

Page 54: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 4

5/07/2010 AEP - 0154

Queries

BCC mentioend hetre !! Is BCC needed , If yes - Please provide details

The system can be provided with percentage expansion capability. However, the quantum of extension required should be specified for initial system to be offered. For new stations addition of more RTUs, instrumentation, OCC equipments may be required, which can not be estimated. Please provide details

Please provide the numbers of sectioning and sub-sectioning posts and Local Auxiliary power distribution for Main Line and Depot

Please provide the I/O detials for sectioning and sub-sectioning posts and Local Auxiliary power distribution

Is the 'central recording system' is apart from the main SCADA data base servers to be provided? Please clarify and provide details of same.

Please indicate the type of format/interface required for making the SCADA data available to employer or other systems. Provision will be made available in SCADA, but exact requirement ( other system details) need to be specified for appropriate interface.

BCC mentioend hetre !! Is BCC needed , If yes - Please provide details

Will the Web clients be read/view type only. Presume no control/configuration changes are envisaged from those.

It is mentioned that only Web clients are required. Does it mean that no dedicated client machines are required in the architecture? Only Webserver license with appropriate concurrent clients would be sufficient?

Please indicate the type of format/interface required ( by other third party systems) for seamless interchange

Page 55: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 4

5/07/2010 AEP - 0155

Queries

Is SCADA workstattion is needed also at RSS. Please confirm . Is it only Work station or SCADA software is also also expected to be installed in RSS workstation.

If Yes-- Is the Local wiorkstation is meant to monitor the respective RSS or the entire network

Kindly clarify/elaborate. Normally the SCADA s/w is provided for one Operating System, while HW platform can be of other make but OS be same.

For full set of SCADA functionality, as required by employer, IEC-104 communication protocol between RTU & OCC could be preferred than Modbus TCP. Please advise.

Duration (or size) for data storage is required at RTU to be supplied ? Though RTUs will have enough storage but there's practical limitations ( in any RTU ..) depending on scan rate, no of I/Os, duration for which data to be stored.

Systems are capable for expansion. For catering to exact requirement of expansion with adequate capacity, Please provde details.

Page 56: Pre - Bid Meeting PPT - AEP 01

BIDDER QUERIES: Volume 7

5/07/2010 AEP - 0156

Queries

We understand that Govt. of India has issued customs notification no 07/2007 dt 22/1/2007 read with notification no 42/96 dt 23/7/1996 serial no 36 as per Customs Tariff Act 1975 for all Metro projects. As per this notification, all imports are eligible for a basic customs duty of 5%. Kindly confirm that these notification and concessional customs duty rate of 5% is applicable to Chennai Metro Rail Project also.

As per tender conditions, this project is eligible for "Deemed Export" benefits and also this tender is being called under ICB and funded by JICA, please confirm whether Project Authority Certificates will be issued to enable us to get the claim of deemed exports benefits under Foreign Trade Policy.

Please confirm whether all taxes and duties such as CST, VAT, ED, Import duties (CVD+Customs Cess+SAD ) will be considered for evaluation purpose.

We request to allow contractors to submit their price breakups for each cost centres as per the actual calculations and we request you no to limit with apportionments.

Since the price break up in the tender is on milestone basis and the milestone includes supply, installation and testing at site, the invoicing for milestones can be done only after completion of testing at site. The time lag between supply and successful tetsing at site would be too long for getting the payments and this could adversley affect the project cash flow in turn the projectprogress. Hence, we request you to accept a break up of cost centres based on supply separately and installation & testing separately. We shall submit these price breakups for each cost centre along with our lumpsum price at the tendering stage itself. Please confirm.