practice of design for maintenance -...

39
Practice Of Design For Maintenance Dr. Kang Kok Hin [email protected]

Upload: vuongdieu

Post on 21-Apr-2019

215 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

Practice Of Design For Maintenance

Dr. Kang Kok Hin

[email protected]

Page 2: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in
Page 3: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in
Page 4: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

Practices of Design for

Maintainability

• Design - transformation of idea into process that meets designer’s

requirements & end user’s needs

• Maintainability - degree to which design maintained economically &

efficiently - characteristic of final design; maintenance - result of design

• Design for Maintainability - design plant to find optimum balance

between capital cost & maintenance cost

• For designer, end users both O&M teams of plant

• Survey conducted with 5 concentrator engineers within Lonmin

Platinum

• What would be requirements in terms of plant maintainability when

designing new concentrator?

Page 5: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

Practices of Design & Maintainability

• Top 4 requirements:

Ease of access,

Standardization of eqpt internally & between concentrators,

Skill levels to maintain eqpt &

Redundancy of running eqpt, all have time to repair

component

• Easier to access eqpt, shorter time to maintain

• Eqpt standardized, specialized skills not required, reducing time

to repair

• Focus on time to repair (or MDT), plot of ‘MDT’ vs ‘MTBM’ for

various operational availability levels

• At 90% availability, plant engineers 80 hours to complete all

corrective/preventative actions on plant; down time includes all

delays, not only pure repair time of eqpt

Page 6: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

Practices of Design & Maintainability

• Design team reduce MDT when eqpt fails, Some practical

examples include:

Provide lifting eqpt access to all high maintenance eqpt, e.g.

pumps & pulleys

Install permanent trolleys on all crawl beams to increase time

to repair

Install standby pumps & dedicated pipelines (with auto

changeover), not affecting available maintenance hours per

month

Make pumps accessible under flooded plant conditions,

through walkways & access platforms

Provide dedicated pipe routes with access

Install split guards & split bearings on main conveyor pulleys

Provide easy & clean access to all instrumentation

Take cognizance of environmental implications of oil spills +

time to clean up

Page 7: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

Practices of Design & Maintainability

• Maintainability: design parameter; not expensive if considered early in

design

• Failure to consider maintenance team very expensive in form of safety

risks to personnel, eqpt retrofits, operation disruptions & cutting torch

maintenance

• Design engineer review project goals & strategies with operational team

prior to design sign-off; invest time to compile design & installation

specifications & sign-off from operational teams & contractor for design

& construction

• During design, utilize 3D design packages, specifically review

maintenance access with key maintenance team

• Design improvements apparent during construction; flexible during

construction & get maintenance team on site early

• Cheaper to improve design during construction, than disrupting value

chain of running item

Page 8: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

Practices of Design & Maintainability

• Survey conducted of largest 211 building design firms in USA -

investigate relationship between design practices & maintenance

• Findings shed light on extent to which maintenance issues considered

when designers specify building materials & service eqpt; level of

designers' knowledge in maintenance-related issues; degree to which

design personnel exposed to training in maintenance-related matters;

extent to which designers consult property managers/maintenance

consultants; relative importance of maintenance issues to other design

factors; level of difficulty in cleaning, inspecting, repairing, replacing

various components; magnitude & frequency of complaints that

designers receive from clients/tenants

• Building Performance enhanced if designers cognizant of maintenance-

matters

• Whether planning to construct new facility or remodel existing one,

process begins with understanding of needs, space, shop eqpt & layout,

bays, maintenance, parts rooms, utility requirements, etc.

Page 9: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in
Page 10: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in
Page 11: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in
Page 12: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in
Page 13: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in
Page 14: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in
Page 15: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in
Page 16: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in
Page 17: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in
Page 18: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in
Page 19: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in
Page 20: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

Early Planning

• Eqpt selection, layout, utility requirements & finishes considered

early in process, earlier in design process needs identified,

more likely approved & less cost

• After construction, additions require expensive change order

• During construction, same line cost $1,000 to add as change

order

• Planning & attention to smallest detail prevent mistakes that

hinder efficiency of maintenance facility

• Lighting – Choose light fixtures offer full spectrum of light

• Lighting ramifications on efficiency, functionality & safety of

facility + on atmosphere of workplace

• High-pressure sodium lights work well outdoors; not suited for

maintenance shop

Page 21: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

Early Planning

• Inside building, lights’ orange-yellow cast creates poor color

rendition, different colored wires look same & blood

indistinguishable from grease

• Overhead Clearance – Ductwork, plumbing, cranes installed too

low encroach on overhead space & interfere with unobstructed

vertical clearance in repair bay, rendering cranes & lifts useless

• Door Size: Measure each vehicle‘s width & height – mirrors &

vertical extensions; 10’ wide garage doors accommodate truck 8’

wide

• Most trucks mirrors protrude up to 1’ on each side, which shrinks

clearance from 2‘to only few inches

• Building Finishes/Aesthetics: bottom 4’to 6’ of shop walls durable

(concrete or masonry) to withstand abuse in shop environment.

• Entire inside of building walls/structure painted to allow building

maintenance to extend useful life of facility

• Design facility's exterior to complement surrounding environment

& adding native landscaping help gain public approval of project

Page 22: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

Early Planning

• Expandability – building not only handles current work load,

adaptable & accommodate demands 20 years from now

• Additional bays not built during initial construction, room left on

site to accommodate expansion

• Load bearing walls avoided to maximize flexibility for future

odifications

• Public Involvement – Everyone with interest in project informed

• Appearance – Form follows function, make functional building

good-looking; isn't possible to make good-looking building

functional

• Peer Review: During initial design, encourages shop, fleet & fleet

maintenance managers to hold peer review session, invite other

managers to critique design. Peers contribute great ideas &

validate design

• Design maintenance facility: Ask right questions & planning in

advance means maintenance managers experience smooth

design & construction process that results in safe, efficient,

positive work environment lasting whole life of facility

Page 23: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

Impact of Technology on FM

• FMs asked to install, implement, work with variety of technologies

without any prior experience in information technology

• Technologies covered include:

Building information modeling (BIM)

Building automation systems (BAS)

FM automation (CAFM/IWMS)

Condition assessment/life cycle analysis

Radio frequency identification (RFID)

Geographic information systems (GIS)

Social networking

Sustainability and energy analysis

Information and communications technology (ICT)

Workflow technology that supports standards - Business Process

Modeling Notation (BPMN) & those developed by Workflow

Management Coalition (WfMC)

Page 24: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

Support/Logistics

Products

Development

Design Influence

System Reliability Analysis, Modeling, and Allocation

Fault Tree Analysis (FTA)

Maintainability Analysis

Level of Repair

Maintainability Prediction

Design Reviews and Evaluation

Failure Mode, Effects, and Criticality Analysis (FMECA)

System Redesign/ Improvement

Reliability Centered Maintenance (RCM)

Maintenance Task Analysis (MTA)

Have Requirements Been Met? Support Test/ Evaluation

Reliability Prediction

System Test & Evaluation (Hot Bed Testing)

Sustaining

SYSTEM

Support

Functional Analysis

Functional Flow/ Data Flow Diagrams

Allocation of System Requirements

System Architecture/ Selection of System Elements

Concept of Operations

TLR & Maintenance Concept

Yes

No

Detailed Support Product List

Cost as an Independent Variable (CAIV): Design to Affordability Analysis (Strategic Decision Making)

Technology/Standards Evolution & COTS Products Market Surveillance

Technology Refreshment

• Supply Support (Spare/Repair Parts)

• Maintenance Planning

• Test/Support Equipment

• Technical Documentation/IETM

• Manpower/Personnel

• Training/CBT

• Facilities; PHS&T

• Design Interface; Computing

Support

Elements of Logistics Support:

Requirements For The:

Evaluation Tech. Refreshment Fleet Feedback

Lifetime Support

Systems & Supportability Engineering

Packaging, Handling, Storage, and Transportation (PHS&T) is the combination of resources, processes, procedures, design, considerations, and methods to

ensure that all system equipment, and support items are preserved, packaged, handled, and transported properly, including environmental considerations, &

..

Page 25: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in
Page 26: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

Characteristics Of Maintainability

• Users left out from design stage

• Builder not notified of original concept or design intent

• Designers chose special fitting/eqpt difficult to maintain • Operational availability issues • Excellent operational maintainability:

Page 27: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

Why Buildings Fail

• As facilities completed, owner's maintenance responsibilities increase. (need for

maintenance services increases with addition of new buildings, for many

government agencies, manpower & budgets frozen or reduced) It is not the

responsibility of architect/designer to maintain facility, this aspect not fully

considered during design process

• When decisions made regarding design without maintenance, ==> facility more

costly to maintain, or components cannot be maintained:

Ceiling lights installed only accessed & changed out with scaffolding,

requiring closure of entrance to facility for a week

Air-conditioning unit installed above drop ceiling in restroom or office area

with no room for ladder set up. Unit accessed by technician if stands on

restroom or office partition; unit will not be properly maintained & relocated

Lights installed in new buildings not accessible; abandoned when lamps fail

Lights requiring access panel to be cut into existing walls to access ballasts

High-cost, custom lighting fixtures/lamps installed in parking garages. As

they fail, replaced with lower-cost fixtures

Page 28: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

Why Buildings Fail

• Rooftop air-conditioning units with no elevator access to bring

chemicals to units; A technician must carry chemicals up to equipment

• Trees planted very close to new buildings; results in clogged

downspouts during rainy season & lead to premature roofing failure

• Lack of enough telephone outlets, electrical outlets, computer

outlets/cables. It is far less expensive to install extra eqpt when building

being built than to add t after building is in service. This leads to

exposed wiring, holes in finishes, other degradations of building's

aesthetics

• Installing inferior-quality components to save up-front money. Carpet-

small initial cost increase, long-term cost reduced dramatically. Carpets

installed with 20- to 25-year non-prorated warranties

• Installing large glass architectural structure in front of new building,

requires purchase of $1 million piece of eqpt to facilitate cleaning glass

• Installing exterior "uplights", inherently fail due to moisture getting into

fixtures

Page 29: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

Why Buildings Fail

•Eqpt installed easily during construction inaccessible after final walls &

other appurtenances completed

•Installation of high-maintenance security systems

•High-maintenance eqpt installed with no local vendor support

•What can be done to make facilities more maintainable, less

costly to operate during building life?

Consider following:

• Dialogue between engineers, architects, designers, customers,

maintenance personnel, contractors. Dialogue must start at first

meeting & carry throughout project

• Architectural or engineering firm uses staff for quality control or

contractor for constructability review, in-house maintenance group

considered resource for design review

• Troughout design process - maintenance standards for organization

Page 30: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

Why Buildings Fail

• Close interaction throughout design & construction phases,

e,g, input to & review of design by maintenance personnel.

Assign knowledgeable maintenance professional part of design

& build team, reduce routine burden

• Adequate time allowed for document review. Maintenance

need to assert importance of their input to organization &

schedule adequate time

• Being involved from 1st meeting on, maintenance staff avoid

last- minute reviews vs in-depth reviews

• Consider maintenance requirements to keep it that way

Page 31: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

Maintainability Strategy

• High system availability & reliability

• Align w/service partners; LCCM

• Sustainability of built environ (Green Mark or equivalent)

• DfM & operation

• Corrective, preventive, predictive maintenance

• CAFM & related ICT

• Take over audit/hand-back

EXAMPLE

• FP system poorly maintained higher average failure rate than same system maintained w/dedicated program, periodically

• Checklist & forms – Maintainity

based

• Predictable, specifiable,

measurable parameters

Specification design; Fault

detection

Isolation, built-in test, auto test

eqpt, Comms for periodic

exercise/monitoring of FP eqpt

• FMEA Criticality Analysis

• M&E Reliability Stress Analysis

• Quality Assurance & Reliability,

inclusion in specs/contract for

procurement of critical FPS

Page 32: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

DfM Checklist

Checklist categories:

• General Maintenance Reduction

• Safety & Environmental System Design Features

• Design Standardization Features

• Design Features for Routine Maintenance

• Design Features for Troubleshooting

• Design Features for Repair/Replacement

• Visual Inspections & Accessibility

• Design for Physical Accessibility

• M&E System maintenance Design

• Personal Protective Equipment

• Storage Battery etc.

• DfM: product serviceable (easily repaired) & supportable (cost-effectively kept in or restored to usable condition)

• Durability (absence of failures)

• Reliability- how long eqpt down/available

Page 33: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

Design Out For Maintenance

• DoM conflicting: design-out maintenance problems, no maintenance • DoM root cause elimination category where solution to DfR & intentionally create

high reliability eqpt through engineering design change to components • Design engineer considers plant improvement as proactive activity for cost

reduction. Particularly DoM for failure elimination

• Many organizations adopted unattainable goal of ‘All accidents preventable. Goal helps people focus on ways to prevent accidents, i.e. reducing unsafe conditions/unsafe acts

• Eqpt failures in plant. Focusing on goal e.g. ‘all failures preventable’, or ‘all downtime preventable’, leads plant personnel to identify causes of failures & discover ways to reduce them

• DoM - Maintenance tactic whereby changes or modifications done to eqpt to remove failure cause, allow other maintenance strategies applicable in managing consequence

• To manage consequences of failure & allow failure in better-managed, less-costly fashion- change in maintenance &/or operating strategy to those actions that deliver lower maintenance costs

• Change maintenance practizes to reduce stress in eqpt components, increase time to a component’s failure - not DoM causes of failure

• DOM: elimination of maintenance through creation of reliability by design

Page 34: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

Design Out For Maintenance

• In Reliability Centered Maintenance (RCM), final solution when maintenance &/or operating strategy ineffective in reducing risk

Design-out & Design for Reliability (DfR)

• Proactive reliability-creating, include: Failure Mode Effects Analysis FMEA, Physics of Failure Analysis PoFA, Highly Accelerated Life Testing HALT, Highly Accelerated Stress Screening HASS, etc.

• Remove failure through component design changes

• In design prototype & make it fail, looking for failure modes to DoM

• Finite Element Analysis FEA to ‘virtually prototype’ component designs

• Before making part, model digitally & apply computer-generated stresses to simulate what might happen & component’s weaknesses

• Make real component & put it in real machine, stress it through failure testing trials to identify failure modes

Design-out & Risk Reduction

• Economic value from better design. Make changes to design because less costly

• Operating risk drives need for design change

• With DfR improvement, better engineered designs; high reliability components

• DfR powerful methodology for defect removal & failure cause elimination so maintenance not required

Page 35: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in
Page 36: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

FIRE PUMP/TANK ROOM +

CONSUMER ELECT S/R – STORES

Page 37: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in
Page 38: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

HT S/R – HT CABLE

• High tension cables

in HT Switch room

laid on ground and

exposed, pose as

safety hazard

Page 39: Practice Of Design For Maintenance - jpak.jkr.gov.myjpak.jkr.gov.my/document/files/Dokumen/Slaid/L#2_Practice of Design... · Air-conditioning unit installed above drop ceiling in

Thank You !!