Project Management PlanDescribes how the project will be executed, monitored, and controlled.

Should be appropriately detailed for the project.

May be summary level or very detailed.

May include one or many subsidiary plans.

Subsidiary plans are detailed to the necessary extent. They may be informal.

May include a description of selected life cycle.

Page 3: Practical Guide to Useful Project Management Plan

Scope Management PlanDescribes how scope will be defined, developed, monitored and controlled.

Strongly depends on project life cycle.

Describes how to: Define scope;

Validate deliverables;

Prepare Project Scope Statement;

Create and maintain a Work Breakdown Structure (templates, tools, techniques and practices);

Obtain formal approval of deliverables;

Monitor and control scope.

Project

21 3

1.1

1.2

1.3

2.1 3.1

3.2

3.3

3.4

Page 4: Practical Guide to Useful Project Management Plan

Requirements Management PlanDescribes processes to analyze, document, and manage requirements.

Strongly depends on project life cycle.

Describes:

How to plan, track and report requirements activities.

How to priorities requirements.

Timing, document formats and approvals needed.

Page 5: Practical Guide to Useful Project Management Plan

Scope Baseline

Formally fixed and documented amount of work that is planned for the project.

Consists of:

Project Scope Statement;

Work Breakdown Structure (WBS);

WBS Dictionary.

Page 6: Practical Guide to Useful Project Management Plan

Schedule Management PlanDescribes criteria and activities for creating, monitoring and

controlling schedule.

May include:

Schedule methodology (Critical Path, Critical Chain, Sprints);

Schedule tools (Network Diagram, Gantt Chart, etc.);

Level of accuracy, units of measurement;

Integration of WBS, activities and estimates;

How to measure performance, Control Thresholds;

Reporting formats.

2.2

Start

1.1

1.2

2.1

Finish

Page 7: Practical Guide to Useful Project Management Plan

Schedule Baseline

Formally approved and documented final version of the project schedule.

May include:

Project Schedule;

Start and Finish dates for each activity.Mar

29

Page 8: Practical Guide to Useful Project Management Plan

Cost Management PlanDescribes how the project costs will be planned, structured and controlled.

May include:

Level of accuracy for estimates;

Level of precision;

Units of measurement;

Integration with WBS, activities and estimates;

Control thresholds;

How to measure performance;

Reporting formats.$$

$

Page 9: Practical Guide to Useful Project Management Plan

Cost Baseline

Formally approved and documented version of the project budget.

May include:

Calendar based cost budget;

Deadlines for funding.

Page 10: Practical Guide to Useful Project Management Plan

Change Management PlanDocuments how changes will be processed, monitored, and

controlled.

May include:

Plan to prevent changes proactively;

Process of creating, reviewing, approving and monitoring of change requests;

Change Log;

Description of Change Control Board activities.

Page 11: Practical Guide to Useful Project Management Plan

Configuration Management PlanDescribes the ways to log changes made in project documentation and deliverables.

Ensures that composition of a project item configuration is correct.

Defines the latest version of project management plan, processes and deliverables.

Logs changes made to project documentation, processes and deliverables.

##

Page 12: Practical Guide to Useful Project Management Plan

Risk Management PlanDescribes how risk management activities are structured and performed.

May include:

Methodology (approaches, tools, sources of data);

Ways to prevent risks;

Budgeting and timing;

Roles and responsibilities;

Risk Categories;

Descriptions of risk probability and impact, probability and impact matrix;

Tracking and reporting.

!

Page 13: Practical Guide to Useful Project Management Plan

Quality Management PlanIs closely related to organization’s quality policies.

It should be created early during project planning as it is beneficial to build it into project scope.

May include:

Identified quality requirements.

How to implement processes that comply with quality policies.

How to demonstrate compliance with the quality policies.

Page 14: Practical Guide to Useful Project Management Plan

Process Improvement Plan

Defines ways to analyze processes on the project to identify opportunities to enhance their value.

Describes how to:

Improve project management processes.

Improve product development processes.Plan

Do

CheckAct

Page 15: Practical Guide to Useful Project Management Plan

Procurement Management PlanDescribes how a project team will acquire goods and services

from external sources.

May include:

Description of procurement processes.

Procurement documentation to be used.

Best practices.

Types of contracts to be used.

Page 16: Practical Guide to Useful Project Management Plan

Human Resources Management PlanDescribes how project human resources should be defined, staffed, managed and released

from the project.

May include:

Roles and responsibilities;

Project organization charts;

Staffing management plan:

Staff acquisition and Resource calendar;

Training needs and Staff release plan;

Recognition and rewards system;

Safety.

Page 17: Practical Guide to Useful Project Management Plan

Communication Management PlanDescribes how project communication will be planned, structured and controlled.

May include:

Stakeholder communication requirements;

Information to be communicated and why;

Methods and technology to be used;

Escalation process;

Communication constraints;

Glossary of common terminology.

bla-bla? bla-bla-bla

Page 18: Practical Guide to Useful Project Management Plan

Summary

Create a Project Management Plan for each project.

Collaborate with the project team.

Reuse subsidiary plans.

Keep Project Management Plan usable.

Keep it detailed on appropriate level.