Practical Guidance to Strengthen Facility Estimates NSF Large Facilities Workshop Jason Lee, GAO May 1-3, 2017 Kevin Porter, NSF Erik Nylund, CH/KGS 1

Upload: truongdieu

Post on 10-Jul-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

Practical Guidance to Strengthen Facility

EstimatesNSF Large Facilities Workshop Jason Lee, GAO

May 1-3, 2017 Kevin Porter, NSF

Erik Nylund, CH/KGS

1

Page 2: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

Purpose

Strengthen Estimates – Construction, Operations & Maintenance

Highlight Requirements and Best Practices

Emphasize Importance of Cost Estimating Plans, Basis of Estimate

Provide Practical Examples

Answer Questions

2

Page 3: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

Overview

Background – AICA, LFM, Definitions

GAO

12 Steps & 4 Characteristics

Cost Estimating Plans (CEP) Examples

Basis of Estimate (BOE) Examples

Independent Contractor – Kforce Government Solutions & Crowe Horwath

Role doing independent cost assessments for NSF per GAO

NSF CEP & BOE Examples

Misc Items

3

Page 4: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

American Innovation & Competitiveness Act- Oversight of NSF Large Facilities

“shall strengthen oversight and accountability over the full life-cycle… in order to maximize research investment”

“ensure that policies for estimating and managing costs and schedules are consistent with the best practices described in the Government Accountability Office Cost Estimating and Assessment Guide”

“require that any pre-award analysis of a major multi-user research facility project includes the development and consideration of the full life-cyclecost”

4

Page 5: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

AICA - NSF - Construction

“may not approve or execute any agreement to start construction on any proposed major multi-user research facility project unless…

“external analysis of the proposed budget has been conducted”

“independent cost estimate (ICE) of the construction of the project has been conducted using the same detailed technical information as the project”

“considered the analyses… and the independent cost estimate… and resolved any major issues”

5

Page 6: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

AICA - NSF - Operations

“shall require an independent cost analysis (ICA) of the operational proposal for each major multi-user research facility”

6

Page 7: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

Large Facilities Manual – Section 4.2

Strengthen Estimates & Clarify NSF expectations

Implement AICA Requirements

Supplement GAO Cost Guide w/ NSF specific info

Clarify NSF Cost Analysis process

Duration & NSF participants

Conducted at each Design Stage-Gate Review for Construction

Conducted at proposal submission for Operations

ICE and ICA inform NSF Cost Analysis > They DO NOT replace it!

Correct information/detail into estimate at proposal submission

Reduce burden & frustration for Recipient & NSF

Reduce time to award

7

Page 8: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

Cost Estimating Plan (CEP)

AACE International – Recommended Practice No. 36R-08

“establish and communicate how the preparation, development, review and approval of the estimate will be completed”

LFM – includes NSF specific needs

“A plan describing how the cost estimating guidance in this manual will be implemented, how the cost estimate will evolve over time, and how the “Cost Model Data Set” will meet the various needs of the project. The CEP should typically include a narrative and sufficient detail explaining the ground rules and assumptions, roles and responsibilities, practices, systems, and calculations used to develop the cost estimate. “

8

Page 9: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

Basis of Estimate (BOE)

AACE International – Recommended Practice No. 34R-05

“Written documentation that describes how an estimate, schedule, or other plan component was developed and defines the information used in support of development. A basis document commonly includes, but is not limited to, a description of the scope included, methodologies used, references and defining deliverables used, assumptions and exclusions made, clarifications, adjustments, and some indication of the level of uncertainty”

Project Management Institute

“Supporting documentation outlining the details used in establishing project estimates such as assumptions, constraints, level of detail, ranges, and confidence levels.”

LFM

PMI definition

Additional guidance on our expectations, level of detail, acceptable justifications

9

Page 10: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

Known as the investigative arm of Congress, GAO exists to support Congress in meeting its constitutional responsibilities. To that end, GAO works to

• Help improve the performance of federal government

• Ensure government agencies and programs are accountable to the American people

• Examine the use of public funds, and

• Evaluate federal programs by providing analyses and recommendations to help Congress make informed oversight and funding decisions

Page 10

The Role of GAO in Government

Page 11: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

• Drafted 2005-2007, published in 2009

• Outlines GAO’s criteria for assessing cost estimates during audits

• Contains 20 chapters with supporting appendixes

• Chapters 1-17: developing credible cost estimates and the 12-step cost estimating process for developing high quality cost estimates

• Chapters 18-20 address managing program costs once a contract has been awarded and discuss Earned Value and risk management

• Also provides case studies of prior GAO audits to show typical findings related to the cost estimating process

Page 11

Cost Estimating and Assessment Guide

Page 12: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

12

A Reliable Process for Credible Cost Estimates

Page 13: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

Page 13

Characteristics of Reliable Estimates

13

Comprehensive

• Develop the estimating plan

• Determine the estimating approach

Accurate

• Develop the point estimate

• Compare the point estimate to an independent estimate

• Update the estimate with actual costs

Credible

• Create an independent cost estimate

• Conduct sensitivity analysis

• Conduct risk and uncertainty analysis

Well Documented

• Define the program

• Identify ground rules and assumptions

• Obtain data• Document the

estimate• Present estimate

to management

Are all costs included?

Is the estimate unbiased?

What is the uncertainty?

Can the estimate be recreated?

Page 14: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

A comprehensive estimate• Includes both government and contractor costs of

the program

• Covers the full life cycle of the program, from inception of the program through retirement (not just the Construction Stage)

• Applies to both FAR-based contracts and Cooperative Agreements

Comprehensive Cost Estimates

Page 15: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

California High-Speed Passenger Rail: Project Estimates Could Be Improved to Better Inform Future Decisions – GAO-13-304

“While the O&M estimate includes common elements for administration and support costs, the O&M WBS is greatly simplified. As a consequence, up to two-thirds of O&M costs are collected in a single cost element.”

DHS and GSA Need to Strengthen the Management of DHS Headquarters Consolidation – GAO-14-648

“GAO found that the 2013 cost estimate…does not include a life-cycle cost analysis of the project, including the cost of operations and maintenance.”

VA Construction: Improved Processes Needed to Monitor Contract Modifications, Develop Schedules, and Estimate Costs – GAO-17-70

“All applicable costs for the construction contract appear to be included in the cost estimate…. However, VA’s $341-million cost estimate for activating the Denver facility is not well supported.”

Comprehensive Cost Estimates - Examples

Page 16: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

16

A Focus on Step 2 and Step 10

Page 17: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

1. A written study plan• Determines the estimating team’s composition

• Identifies subject matter experts

• Includes a schedule for the cost estimating effort

2. Team includes experienced and trained cost estimators

3. Estimating team is from a centralized office

Not meeting Step 2 criteria is typically a cause for why other best practices are not met

Step 2: Develop the Estimating Plan

Page 18: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

2020 Census: Census Bureau Needs to Improve Its Life-Cycle Cost Estimating Process – GAO-16-628

“We found the Bureau had little planning information among its documents supporting its cost estimate. Early fundamental planning and guidance documents such as general policies and procedures for cost estimation…can contribute to consistent control over the process used to develop a cost estimate and help ensure that desired standards and practices are implemented.”

“Eight years later, the absence of guidance to control the cost estimation process persists. Investment in the planning documents to help control and support cost estimation early in the estimation cycle, such as…guidance on key steps and process flows [and] assignment of responsibilities…can help institutionalize practices and ensure that otherwise disparate parties in the process operate consistently.”

Step 2: Census Bureau Estimate Plans

Page 19: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

Step 10: Document the Estimate

Cover Page and Introductio

n

Executive Summary

Introduction

System Description

Program Inputs

Methodology by Cost Element

Data by Cost

ElementNarrative

text

Cost tables Sensitivity analysis

Uncertainty analysis

Management approval

Tracked updates

Contingency

derivation

Good documentation should describe the cost estimating process, data sources, and methodologies.

Page 20: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

Checked Baggage Screening: TSA Has Deployed Optimal Systems at the Majority of TSA-Regulated Airports, but Could Strengthen Cost Estimates – GAO-12-266

“TSA did not adequately document many assumptions or methodologies underlying its cost model to the extent that would allow someone unfamiliar with the cost estimate, using only the available documentation, to easily re-create the estimate.”

Step 10: Documentation for a “Never-Ending” Program

Page 21: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

NSF – High Quality CEP & BOE Example –Construction

Antarctic Infrastructure Modernization for Science (AIMS) Successfully completed Preliminary Design Review (PDR)

21

Page 22: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

AIMS – CEP

22

Page 23: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

AIMS - CEP

23

Page 24: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

AIMS – BOE* - WBS 5.4.1

*BOE organized per AACE International Recommended Practice No. 34R-05. (2010)

Page 25: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

AIMS – BOE – WBS 5.4.1

Page 26: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

AIMS – BOE – WBS 5.4.1

Page 27: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

NSF – High Quality CEP & BOE Example –O&M

National Ecological Observatory Network (NEON) Some elements under construction

Some elements in operation

27

Page 28: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

NEON CEP & BOE Example – O&M

NEON

28

Page 29: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

NEON CEP & BOE Example – O&M (continued)

29

Page 30: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

NEON CEP & BOE Example – O&M (continued)

30

Page 31: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

NSF - CEP & BOE Examples – Summary Leading Practices/Observation

Complete BOE document with good project and scope description

Clear linkages from BOE to Cost Book (via WBS)

Thorough and well-documented assumptions for cost drivers, cost estimating methods, and data sources

Integrated cost model which includes build up from lowest to highest levels of the WBS

Use of a “quality standard” as though cost estimate will be subject to third party review and such that third party can replicate

Supportable cost escalations; and indirect/fringe/overhead rates

Sufficient documentation of risk and sensitivity analyses; discussion of cost estimate limitations

31

Page 32: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

NSF - CEP & BOE Example – O&M

NSF is not prescriptive – Tailor to your facility!!

Academic Research Fleet

Ship Operations format established by OCE is both the CEP and the BOE

“WBS” elements are the various Level of Effort cost categories defined by OCE

Suitable for NSF to conduct a cost analysis (mainly Program)

32

Page 33: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

Can Contingency be used during Operations Stage?

Yes (per LFM 4.2.6)

Must comply with paragraph 200.433 of the Uniform Guidance (Held separately to manage project risk)

Must comply with LFM - formal risk assessment, Risk Management Plan, Risk Register, contingency calculation

Approved by NSF

Generally for major up-grade sub-elements of Ops proposal

Example?

33

Page 34: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

§ 200.433 Contingency provisions

(a) Contingency is that part of a budget estimate of future costs (typically of large construction projects, IT systems, or other items as approved by the Federal awarding agency) which is associated with possible events or conditions arising from causes the precise outcome of which is indeterminable at the time of estimate, and that experience shows will likely result, in aggregate, in additionalcosts for the approved activity or project. Amounts for major project scope changes, unforeseen risks, or extraordinary events may not be included.

(c) Payments made by the Federal awarding agency to the non-Federal entity's “contingency reserve” or any similar payment made for events the occurrence of which cannot be foretold with certainty as to the time or intensity, or with an assurance of their happening, are unallowable, except as noted in § 200.431 Compensation—fringe benefits regarding self-insurance, pensions, severance and post-retirement health costs and § 200.447 Insurance and indemnification.

34

Page 35: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

Do you really mean Allowance not Contingency? Allowance*: Resources included in the basis of estimate for baseline cost estimates to

cover the cost of known but as-of-yet undefined details or requirements for an individual WBS element. May be used when the level of project definition may not enable certain costs to be estimated definitively or times when it is simply not cost effective to quantify and cost every small item included with the WBS element, but reliable correlations are available.

Past project experiences, demonstrated statistical correlation Most likely costs

Examples:

Preliminary Design – design or material take-off allowance

Small Items - Bolts, structural steel connections

Hand excavation/backfill (vs. machine excavation/backfill)

35

*Adapted from AACE International

Page 36: Practical Guidance to Strengthen Facility Estimates - NSF · Practical Guidance to Strengthen Facility Estimates ... Basis of Estimate ... Basis of Estimate (BOE) Examples

Questions?