RIALI HYDROPOWER COMPANY (PVT) LTD
Prequalification Documents
EPC/Turnkey Contract For
4.8 MW Riali-II Hydropower Project on
Ghoriwala Nullah, Neelam ValleyDistt.Muzafarabad AJ & K
(January 2012)
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 2/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
2
DESIGNMEN ConsultingEngineers (Pvt) Ltd.1st Floor, 9-West, Rizwan Plaza, Jinnah Avenue,F-6, Islamabad.Ph: +92-51-2828577, 2829002Fax.: +92-51-2829891
E-mail:
[email protected] [email protected] Web Site:
www.designmen.com.pk
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 3/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
CONTENTS
Page
PART 1 - Prequalification Procedures
Section I. Instructions to Applicants ..................................................... 4-12
Section II. Prequalification Data Sheet......................................................13-14
Section III. Qualification Criteria and Requirements............................... 15-25
Section IV. Application Forms...................................................................26-42
PART 2 - Works Requirements
Section V. Scope of Works..............................;.....................................................................43-51
3
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 4/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
PART – 1PREQUALIFICATION PROCEDURES
4
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 5/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
SECTION I - INSTRUCTION TO APPLICANTS
Table of Clauses
A. Genera!...........................................................................................51. Scope of Application..............................................................52. Source of Funds.....................................................................53. Corrupt Practices...................................................................54. Eligible Applicants..................................................................65. Eligible Goods and Related Services......................................7
B. Contents of the Prequalification Document....................................76. Sections of Prequalification Document..................................77. Clarification of Prequalification Document............................. 88. Amendment of Prequalification Document.............................8
C. Preparation of Application..............................................................89. Cost of Application................................................................810. Language of Application..........................................................911. Documents Comprising the Application.................................912. Application Submission Form................................................913. Documents Establishing the Eligibility of the Applicant..........914. Documents Establishing the Qualifications of the Applicant. . .915. Signing of the Application and Number of Copies..................9
D. Submission of Application..............................................................1016. Sealing and Identification of Applications.............................1017. Deadline for Submission of Applications....................................... 10.18. Late Applications..................................................................1019. Opening of Applications........................................................10
E. Procedures for Evaluation of Applications20. Confidentiality......................................................................1021. Clarification of Applications ..................................................1122. Responsiveness of Applications............................................1123. Domestic Bidder PricePreference…………………………………………………………………………..1124. SpecialistSubcontractors……………………………………………………………………………………….12
F. Evaluation of Applications and Prequalification of Applicants………………………………………………..1225. Evaluation of Applications……………………………………………………………………………………..1226. Employer’s Right to Accept or RejectApplications…………………………………………………..1327. Prequalification of Applicants……………………………………………………………………………… …1328. Notification of Prequalification……………………………………………………………………………… 1329. Invitation for Bid……………………..
…………………………………………………………………………….1330. Changes in Qualifications of
5
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 6/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
Applicants…………………………………………………………………….13
6
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 7/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
SECTION I. INSTRUCTIONS TO APPLICANTS
A. General
1. Scope of Application 1.1 in connection with the Invitation forPrequalification
indicated in Section II, Prequalification Data Sheet(PDS), the Employer, as defined in the PDS,issues this Prequalification Document (PQD) toapplicants interested in bidding for the worksdescribed in Section V, Scope of Works. Thename and identification of the contract is providedin the PDS.
2. Source of Funds 2.1 The Project is to be financed by local commercialbanks with
debt to equity ratio of 80:20 as per policy
guidelines of Government of Pakistan fordevelopment of private sector power projects.
3. Corrupt Practices 3.1 The Employer requires that Bidders/Contractorsmust
observe the highest standard of ethics during theprocurement and execution of the contracts. Inpursuit of this policy, the Employer;
(a) Defines, for the purposes of this provision, the
terms set forth below as follows:
(i) "corrupt practice" means the offering,giving, receiving, or soliciting of anything of
value to influence the action of a public
official in the procurement process or in
contract execution; and
(ii) "fraudulent practice" means a
misrepresentation or omission of facts in
order to influence a procurement process
or the execution of a contract; and
(iii) "collusive practice" means a scheme orarrangement between two or more
bidders, with or without the knowledge of
the Employer, designed to establish bid
prices at artificial, non-competitive levels;
and
(iv) "coercive practice" means harming or
threatening to harm, directly or indirectly,
persons or their property to influence their
participation in the procurement process or
affect the execution of a contract; and
7
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 8/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
(b) Will reject a proposal for award if it determines
that the Bidder recommended for award has
directly or through an agent engaged in corrupt,
fraudulent, collusive or coercive practices in
competing for the named contracts; and
(c) will declare a firm ineligible, either indefinitely or
for a stated period of time, to be awarded a
contract, if it at any time determines that the
firm has directly or through an agent engaged
in corrupt, fraudulent, collusive or coercive
practices in competing for, or in executing, a
contract.
4. Eligible Applicants 4.1 An Applicant shall be a private, public orgovernment
owned legal entity, subject to ITA 4.6, or anycombination of them in the form of association(s)including Joint Venture (JV) with the formal intent,as evidenced by a letter of intent to enter into anagreement or under an existing agreement. In thecase of a JV, unless otherwise specified in thePDS, (i) all parties shall be jointly and severallyliable, (ii) there shall be limit on the number of partners as specified in PDS, and (iii) JV shallnominate a representative who shall have theauthority to conduct all business for and on
behalf of any and all the partners of the JV duringthe prequalification process.
4.2 The eligibility criteria listed in this Clause 4 shallapply to the Applicant, including the partiesconstituting the Applicant, i.e., its proposedpartners, subcontractors or suppliers for anypart of the Contract including related services.
4.3 An Applicant and all parties constituting theApplicant shall have the nationality of anycountry except those with which the Islamic
Republic of Pakistan has no commercial relationas a result of official regulation. An Applicant shallbe deemed to have the nationality of a country if the Applicant is a citizen, or-is constituted,incorporated or registered and operates inconformity with the provisions of the laws of thatcountry.
This criterion shall also apply to thedetermination of the nationality of proposedsubcontractors or suppliers for any part of theContract including related services.
4.4 Applicants and all parties constituting the
8
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 9/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
Applicant shall not have a conflict of interest.Applicants shall be considered to have a conflictof interest, if they participated as a consultant inthe preparation of the design or technicalspecifications of the works that are the subject
of this prequalification. Where a firm, or a firmfrom the same economic or financial group, inaddition to consulting, also has the capability tomanufacture or supply goods or to constructworks, that firm, or a firm from the sameeconomic or financial group, cannot normally bea supplier of goods or works, if it providedconsulting services for the contractcorresponding to this prequalification, unless itcan be demonstrated that there is not asignificant degree of common ownership,influence or control.
4.5 An Applicant shall submit only one application inthe sameprequalification process, either individually as anApplicant or as a partner of a joint venture. NoApplicant can be a subcontractor whilesubmitting an application individually or as apartner of a joint venture in the sameprequalification process. A Subcontractor in anyapplication may participate in more than oneapplication, but only in that capacity. AnApplicant who-submits, or participates in, morethan one application, will cause all theapplications in which the Applicant hasparticipated to be disqualified.
4.6 An Applicant that is under a declaration of ineligibility by theEmployer in accordance with ITA 3, at the date of submission of the application or thereafter, shallbe disqualified.
4.7 Pakistan, Azad Jammu & Kashmir and GilgitBallistan Government-owned entities shall be
eligible only if they can establish that they arelegally and financially autonomous, and operate'under commercial law, and that they are notdependent agencies of the Employer.
4.8 Applicants shall not be under execution of a Bid-SecuringDeclaration in the Employer's country.
4.9 Applicants shall provide such evidence of theircontinued eligibility satisfactory to the Employer,as the Employer shall reasonably request.
5. Eligible Goods and 5.1 All goods and related services to be supplied
9
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 10/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
under theRelated Services Contract shall not have as their country of origin,
any country with which the Islamic Republic of Pakistan has no commercial relation as a result of official regulation.
B. Contents of the Prequalification Document
6. Sections of 6.1 The document for the prequalification of ApplicantsPrequalification (hereinafter "prequalification document") consistsof parts 1Documents and 2 which comprise all the sections indicated
below, and should be read in conjunction withany Addenda issued in accordance with ITA 8
PART 1 Prequalification Procedures
• Section I Instructions toApplicants (ITA)
• Section II. Prequalification Data
Sheet (PDS)
• Section III. Qualification Criteria and
Requirements
• Section IV. Application Forms
•
Part-2 Works Requirements
• Section V. Scope of Work
6.2 The "Invitation for Prequalification Applications"issued by the Employer is not part of theprequalification document.
6.3 The Employer accepts no responsibility for thecompleteness of the prequalification documentand its addenda unless they were obtaineddirectly from the Employer.
6.4 The Applicant is expected to examine ail
instructions, forms, and terms in thePrequalification Document and to furnish all
information or documentation required by the
Prequalification Document.
7. Clarification of Pre- 7.1 A prospective Applicant requiring any clarificationof the
qualification Document prequalification Document shall contact the
Employer in writing at the Employer's address
indicated in the PDS. The Employer will respond
in writing to any request for clarification
provided that such request is received no laterthan fourteen (14) days prior to the deadline for
10
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 11/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
submission of applications. The Employer shall
forward copies of its response to all applicants
who have acquired the prequalification document
directly from the Employer including a
description of the inquiry but without identifying
its source. Should the Employer deem itnecessary to amend the prequalification
document as a result of a clarification, it shall do
so following the procedure under ITA 8 and in
accordance with the provisions of ITA 17.2.
8. Amendment of Pre- 8.1 At any time prior to deadline for submission of applicationsqualification Documents the Employer may amend the Pre-qualification
Document by issuing addenda.
8.2 Any addendum issued shall be part of thePrequalificationDocument and shall be communicated in writingto all whohave obtained the Prequalification Documentfrom theEmployer.
8.3 To give prospective Applicants reasonable timeto take an addendum into account in preparingtheir applications, the Employer may, at its
discretion, extend the deadline for thesubmission of applications.
C. Preparation of Applications
9. Cost of Application 9.1 The Applicant shall bear all costs associated withthe
preparation and submission of its application. TheEmployer will in no case be responsible or liablefor those "costs, regardless of the conduct oroutcome of the prequalification process.
10. Language of 10.1 The application as well as all correspondence andApplication documents relating to the prequalification
exchanged by the Applicant and the Employer,shall be written in the language specified in thePDS. Supporting documents and printed literaturethat are part of the application may be in anotherlanguage, provided they are accompanied by anaccurate translation of the relevant passages inthe language specified in the PDS, in which case,for purposes of interpretation of the application,the translation shall govern.
11. Documents 11.1 The application shall comprise the following.Comprising
11
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 12/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
The Application (a) Application Submission Form in accordance withITA 12.
(b) Documentary evidence establishing theapplicant’s
Eligibility to prequalify, in accordance with ITA 13.(c) Documentary evidence establishing the
Applicant's
qualifications, in accordance with ITA 14;
(d) written confirmation authorizing the
signatory of the
application to commit the Applicant in
accordance with
ITA Sub-Clause 15.3; and
(e) any other document required as specified in the
PDS.
12. Application 12.1 The Applicant shall prepare an ApplicationSubmission
Submission Form Form using the form furnished in Section IV,Application Forms. This Form must be completedwithout any alteration to its format.
13. Documents 13.1 To establish its eligibility in accordance with ITA 4,the
Establishing the Applicant shall complete the eligibilitydeclarations in the
Eligibility of the Application Submission Form and Forms ELI(eligibility) 1.1
Applicant and 1.2 included in Section IV, Application Forms.
14. Documents 14.1 To establish its qualifications to perform thecontract(s) in
Establishing the accordance with Section III, QualificationCriteria and
Qualifications Requirements, the Applicant shall providethe information
of the Applicant information and Information Forms included inSection IV, Application Forms.
15. Signing of the 15.1 The Applicant shall prepare one original of the documents
Application and No. of comprising the application as described inITA 11 and clearly
Copies mark it “ORIGINAL”. The original of theapplication shall be typed or written in indelibleink and shall be signed by a person dulyauthorized to sign on behalf of the Applicant.
12
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 13/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
15.2 The Applicant shall submit copies of the signed
original
application, in the number specified in the PDS,
and clearly
mark them "COPY". In the event of any
discrepancybetween the original and the copies, the original
shall
prevail.
15.3 The requirement regarding the legal instrument
evidencing
the authorization to represent and sign on behalf
of the
Applicant shall be as specified in PDS.
Application
submitted by a JV shall include an undertaking
signed by all
Partners:
a) Stating that all Partners shall be jointly and
severally liable, and
b) nominating a representative who shall have
the authority to conduct all business for and
on behalf of any and all the partners of the JV
during the pre-qualification process and in the
event the JV is prequalified, during the bidding
process and in the event the JV is awarded the
Contract during Contract execution.
D. Submission of Applications
16. Sealing and 16.1 The Applicant shall enclose the original and thecopies of the
Identification of application in a sealed envelope that shall;Applications a) bear the name and address of the
Applicant;
b) be addressed to the Employer, inaccordance with ITA 17.1 and
c) bear the specific identification of thisprequalification process indicated in thePDS 1.1
16.2 The Employer will accept no responsibility for notprocessing any envelope that was deliveredunsealed or not identified as required.
17. Deadline for 17.1 Applicants may always submit their applicationsby mail (not
Submission of e mail) or by hand. Applications shall bereceived by the
13
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 14/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
Applications Employer at the address and no later than thedeadline indicated in the PDS.
17.2 The Employer may, at its discretion, extend thedeadline for the submission of applications by
amending the Prequalification Document inaccordance with ITA 8, in which case all rights andobligations of the Employer and the Applicantssubject to the previous deadline shall thereafterbe subject to the deadline as extended.
18. Late 18.1 Any application received by the Employer afterthe deadline
Applications for submission of applications prescribed in ITA 17for any
reason will be returned unopened to theApplicant.
19. Opening of 19.1 The Employer shall prepare a record of theopening of
Applications applications that shall include as a minimum thename and address of the Applicants.
E. Procedures for Evaluation of Applications
20. Confidentiality 20.1 Information relating to the evaluation of applications, and
Recommendation for prequalification shall not bedisclosed to Applicants or any other persons notofficially concerned with such process until thenotification of prequalification is made to allApplicants.
20.2 From the deadline for submission of applicationsto the time of notification of the results of theprequalification in accordance with ITA 28, anyApplicant that wishes to contact the Employer onany matter related to the prequalification process,may do so but only in writing.
21. Clarification of 21.1 To assist in the evaluation of applications,the Employer mayApplications at its discretion ask any Applicant for a
clarification of its application which shall besubmitted within a stated reasonable period of time. Any request for clarification and allclarifications shall be in writing.
21.2 If an Applicant does not provide clarifications of the information requested by the date and timeset in the Employer’s request for clarification, its
application maybe rejected.
14
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 15/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
22. Responsiveness 22.1 The Employer may reject any applicationwhich is not
of Applications responsive to the requirements of thePrequalification Documents.
23. Domestic 23.1 if so indicated in the PDS a 7 ½ percent margin of priceBidder Price Preference preference for qualifying domestic bidders shall
apply in bid evaluation. On the basis of information submitted by Applicants and availableat the time of notification, the Employer willinform pre-qualified Applicants of their apparenteligibility to qualify for the domestic bidder pricepreference (subject to subsequent confirmation atbid evaluation, in accordance with Sub-Clause23.2)
23.2 A domestic bidder is one that meets the followingcriteria;
a) for an individual firm;i) is registered with Pakistan
Engineering Council.ii) has more than 51 percent ownership
by Pakistani nationals.iii) does not subcontract more than 10
percent of the contract price,excluding provisional sums, toforeign contractors.
b) for a joint venture (JV) of domestic firmsi) individual member firms shall satisfy
(a) (i) and (a)(ii) above.ii) the JV shall not subcontract more
than 10 percent of the contractprice, excluding provisional sums, toforeign firms.
c) for a joint Venture (JV) of domestic andforeign firms
i) Individual domestic member firmssatisfy the criteria stated in (a)(i)and (a)(ii) above.
ii) Individual foreign firms areregistered with Pakistan EngineeringCouncil.
iii) Total proportional participation of domestic firms in the JV is 51percent or greater.
iv) The JV shall not subcontract morethan 10 percent of the contractprice, excluding provision sums, to
foreign firms.
15
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 16/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
24. Specialist 24.1 Applicants planning to subcontract any of the keyactivities
Sub-Contractors indicated in Section III. Qualification Criteria andRequirements shall specify the activity (ies) orparts of the works to be subcontracted in the
Application Submission Form. Applicants shallclearly identify the proposed specialistsubcontractors in Forms ELI-1.2 and EXP(experience) – 4.2(b) in Section IV. Such proposedspecialist subcontractor(s) shall meet thecorresponding qualification requirementsspecified in Section III, Qualification Criteria andRequirements.
24.2 At this time, the Employer does not intend toexecute certain specific parts of the works bysubcontractors selected in advance by the
Employer (Nominated Subcontractors) unlessotherwise stated in the PDS.
F. Evaluation of Applications and Pre-qualification of Applicants
25. Evaluation of 25.1 The Employer shall use all the factors,methods, criteria andApplications requirements defined in Section III, Qualification
Criteria and Requirements to evaluate thequalifications of the Applicants. The Employerreserves the right to waive minor deviations in thequalification criteria if they do not materiallyaffect the capability of an Applicant to performthe contract.
25.2 Only the qualifications of subcontractors thathave beenidentified in the application may be considered intheevaluation of an Application. However, thegeneralexperience and financial resources of
subcontractors maynot be added to those of the Applicant forpurposes of Prequalification of the Applicant.
25.3 In case of multiple contracts, the Employer shall
prequalify
each Applicant for the maximum number and
types of
contracts for which the Applicant meets the
appropriate
aggregate requirements of such contracts, asspecified in
16
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 17/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
Section ill, Qualification Criteria and
Requirements.
26. Employer’s 26.1 The Employer reserves the right to accept or
reject anyRight to Accept Or applications and to annul the prequalification
process andReject Applications reject all applications at any time, without thereby
incurring any liability to Applicants.
27. Prequalification 27.1 All applicants whose applications have metor exceeded
Of Applicants (“passed”) the specified threshold requirementswill to the exclusion of all others, be pre-qualifiedby the Employer.
28. Notification of 28.1 Once the Employer has completed theevaluation of the
Prequalification applications it shall notify all applicants in writingof the names of those applicants who have beenprequalified.
29. Invitation to Bid 29.1 After the notification of the results of theprequalification
the Employer shall invite bids from all theApplicants that have been prequalified. Thecontractors prequalified through this process
shall be eligible to participate in internationalcompetitive bidding for EPC/Turnkey Contract of 4.8 MW Riali-II Hydropower Project on GhoriwalaNullah, Neelam Valley Distt. Muzafarabad AJ&K.
The employer has the discretion to exclude anyprequalified contractor from bidding process.
30. Changes in 30.1 Any change in the structure or formation of anApplicant
Qualifications after being prequalified in accordance with ITA 27and
of Applicants invited for bidding shall be subject to written
approval of the Employer prior to the deadline forsubmission of bids, Such approval shall be denied if as a consequence of the change the Applicant nolonger substantially meets the qualification criteriaset forth in Section III, Qualification Criteria andRequirements, or if in the opinion of the Employer,a substantial reduction in competition may result,or if a new Partner that had not been pre-qualifiedas an Applicant is added to a pre-qualifiedApplicant. Any such changes shall be submitted tothe Employer not later than 14 days before thedeadline for submission of bids.
17
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 18/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
SECTION II. PREQUALIFICATION DATA SHEET
A. General
ITA 1.1 The name of the Employer is:Riali Hydropower Company (Pvt) Ltd. (RHPCO)Represented by:Chief executive, Abdul Karim KhadimRiali Hydropower Company (Pvt) Ltd. (RHPCO)59E, St: 7, I-10/3, Islamabad-Pakistan
Tel No. +92-51-4446873-74Fax No. +92-51-4444536E-mail: [email protected] any person nominated by the Employer from time to time andnotified to the Contractor and the Engineer.
ITA 1.1 The name, identification and number of the tentative contract isContract No. RHPP-II/ICB-01.
ITA 2.1 The name of the Project is;EPC/Turnkey Contract for 4.8 MW Riali-II HydropowerProject on Ghoriwala Nullah, Neelam Valley Distt.Muzafarabad AJ & K
ITA 4.1 i) Copy of Joint Venture agreement should be provided with theApplication.
ii) Composition of the Joint Venture should be such that the leadpartner has a minimum of 51% share. In case of a JV lead by aforeign firm, the share of the local firm(s) shall not be less than30 percent.
iii) Maximum number of partners in the JV shall be four (04)B. Contents Prequalification Document
ITA 7.1 For Clarification Purpose, the Employer’s address is;Riali Hydropower Company (Pvt) Ltd. (RHPCO)59E, St: 7, I-10/3, Islamabad-Pakistan
Tel No. +92-51-4446873-74Fax No. +92-51-4444536
E-mail: [email protected] C. Preparation of ApplicationsITA 10.1 The language of the application as well as of all correspondence is
EnglishITA 11.1 (d) The Applicant shall submit with its application, the following additional
documents - None-ITA 15.1 In addition to the original, the number of copies to be submitted with
the application is FourITA 15.3 The requirement regarding the legal instrument evidencing their
authorization to represent and sign on behalf of the Applicant shall bePower of Attorney on a legal paper.
D. Submission of Application
ITA 17.1 The applications shall be addressed to;Project Coordinator/Manager
18
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 19/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
DESIGNMEN Consulting Engineers (Pvt) Ltd.1st Floor, 9-West, Rizwan Plaza, Jinnah Avenue,F-6, Islamabad.Ph: +92-51-2828577, 2829002Fax.: +92-51-2307615
The deadline for application submission is;
Date February 27, 2012 Time 1600 hours
E. Evaluation of ApplicationsITA 23.1 A margin of preference shall apply for eligible domestic bidders. The
procedure for evaluation will be specified in bidding documents.ITA 24.2 At this time the Employer does not intend to execute certain specific
parts of the works by subcontractors selected in advance (NominatedSubcontractor).
19
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 20/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
SECTION III QUALIFICATION CRITERIAAND REQUIREMENTS
This Section contains all the methods, criteria and requirements that the Employershall use to evaluate applications. The information to be provided in relation to each
requirement and the definitions of the corresponding terms are included in therespective Application Forms.
CONTENTS
1. Eligibility……………………………………………………………………………………………………………………………..16
2. Historical Contract Non-Performance………………………………………………………………………………….17
3. Financial
Status……………………………………………………………………………………………………………………18
4. Experience including staff andequipment…………………………………………………………………………..19
20
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 21/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
21
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 22/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
SECTION III – QUALIFICATION CRITERIA AND REQUIREMENT
ELIGIBILITY AND QUALIFICATION CRITERIA COMPLIANCE REQUIREMENTSDOCUMENTATI
ON
No. Subject Requirement Single Entity Joint Venture
SubmissionRequirements
All PartiesCombined
EachPartner
One Partner
1. ELIGIBILITY 1.1 Nationality Nationality in
accordance with ITASubClause4.2
Must meetrequirement
Existing orintended JVmust meet
requirement
Must meetrequirement
N/A ApplicationSubmission Form
Forms ELI-1.1 and1.2 withattachments.
1.2 Conflict of interest
No conflicts of interestin pronounce of ITASub Clause 4.4
Must meetrequirement
Existing orintended JVmust meet
requirement
Must meetrequirement
N/A ApplicationSubmission Form
1.3 Eligibility Not having beendeclared ineligible bythe Employer, asdescribed in ITA Sub-Clause 4.6
Must meetrequirement
Existing orintended JVmust meet
requirement
Must meetrequirement
N/A ApplicationSubmission Form
1.4 GovernmentOwnedEntity
Applicant required tomeet conditions of ITASub-Clause 4.7
Must meetrequirement
Existing orintended JVmust meet
requirement
Must meetrequirement
N/A Forms ELI 1.1 and1.2 withattachments
1.5 Ineligibilitybased on aUnitedNationsresolution orapplicablelaw
Not having beenexcluded as a result of the PakistanEngineering Council(PEC) or any otherapplicable laws of official regulations, Orby an act of
Must meetrequirement Existing orintended JVmust meet
requirement
Must meetrequirement NotApplicable ApplicationSubmission Form
22
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 23/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
compliance with UNSecurity Councilresolution, inaccordance with ITB4.8 & 4.9
SECTION III – QUALIFICATION CRITERIA AND REQUIREMENT
ELIGIBILITY AND QUALIFICATION CRITERIA COMPLIANCE REQUIREMENTSDOCUMENTATI
ON
No. Subject Requirement Single Entity
Joint VentureSubmission
RequirementsAll PartiesCombined
Each Partner One Partner
2. HISTORICAL CONTRACT NON-PERFORMANCE2.1 History of
Non-PerformingContracts
Non-Performance of acontract did not occurwithin the last ten (10)years prior to thedeadline for applicationsubmission based on allinformation on fullysettled disputes orlitigation. A fully settleddisputes or litigation isone that has beenresolved in accordancewith the DisputeResolution Mechanismunder the respectivecontract, and where allappeal instancesavailable to the applicanthave been exhausted.
Must meetrequirementby itself or as
partner topast or
existing JV
N/A Must meetrequirementby itself or as
partner topast or
existing JV
N/A Form CON-2
2.2 Failure toSignContract
Not being underexecution of a BidSecuring Declaration,pursuant to Sub-Clause
Must meetrequirement
Must meetrequirement
Must meetrequirement
N/A ApplicationSubmissionForm
23
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 24/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
4.8 for the last ten (10)years.
2.3 PendingLitigation
All pending litigationshall in total notrepresent more thanfifty percent (50%) of the Applicant’s networth and shall betreated as resolvedagainst the Applicant.
Must meetrequirementby itself or as
partner topast or
existing JV
N/A Must meetrequirementby itself or as
partner topast or
existing JV
N/A Form CON-2
SECTION III – QUALIFICATION CRITERIA AND REQUIREMENT
ELIGIBILITY AND QUALIFICATION CRITERIA COMPLIANCE REQUIREMENTSDOCUMENTATI
ON
No. Subject Requirement Single Entity Joint Venture
SubmissionRequirements
All PartiesCombined
Each Partner One Partner
3. FINANCIAL STATUS3.1 Financial
Performance
Submission of audited balancesheets or if not required by thelaw of the applicants country,other financial statementsacceptable to the Employer, forthe last five (5) years todemonstrate;
a) the current soundness of the applicants financialposition and its prospectivelong term profitability. As aminimum a Bidder’s net worthcalculated as the differencebetween total assets and totalliabilities should be positiveand
Must meetrequirement
N/A Must meetrequirement
N/A Form FIN-3.1withattachments
24
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 25/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
b) access to, or availability of,financial resources such asliquid assets, unencumberedreal assets, lines of credit, andother financial means, otherthan any contractual advancepayments to meet thefollowing cash-flowrequirement;1. US$ seven (7) million per
year and
2. the overall cash flowrequirements for thiscontract and its currentworks commitment.
SECTION III – QUALIFICATION CRITERIA AND REQUIREMENT
ELIGIBILITY AND QUALIFICATION CRITERIA COMPLIANCE REQUIREMENTSDOCUMENTAT
ION
No.
Subject RequirementSingleEntity
Joint VentureSubmission
RequirementsAll PartiesCombined
EachPartner
One Partner
3.2 AverageAnnualConstruction
Turnover
Minimum average annualconstruction turnover of US$ TEN(10) million (calculated as totalcertified payments received for
contracts in progress or completed,within the last five (5) years.
Mustmeet
requirement
Must meetrequiremen
t
Must meet25% of the
requirementor its share
percentagein the JV
whichever ishigher
Lead Partnermust meet
fifty one (51)percent of the
requirement orits share
percentage orits share
percentage inthe JV
whichever ishigher
Form FIN – 3.2
25
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 26/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
SECTION III – QUALIFICATION CRITERIA AND REQUIREMENT
ELIGIBILITY AND QUALIFICATION CRITERIA COMPLIANCE REQUIREMENTSDOCUMENTAT
ION
No.
Subject RequirementSingleEntity
Joint VentureSubmission
RequirementsAll PartiesCombined
Each PartnerOne
Partner4. EXPERIENCE
4.1 GeneralConstructionExperience
Experience in construction contractsas contractor, subcontractor ormanagement contractor for the lastten (10) years prior to theapplications submission deadline,and with activity in at least nine (9)months in each year.
Mustmeet
requirement
N/A Must meetrequirement
N/A Form EXP-4.1
26
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 27/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
4.2(a)
Specificconstructionexperience(contracts of similarsize andnature)
Participation as contactor,management contractor, orsubcontractor in at least two (2)hydropower projects of 5MW orhigher capacity within the last 10years. Or at least one (1)EPC/Turnkey hydropower project of 10 MW or more capacity within thelast ten (10) years in the Northernpart of Pakistan. The projects should
have been successfully andsubstantially completed and that aresimilar to the proposed plant andinstallation services. The similar shallbe based on the physical size,complexity, methods/technology orother characteristics as described inSection V, Scope of Works.
Must meetrequireme
nt
Must meetrequireme
nt
N/A N/A Form Exp 4.2(a)
SECTION III – QUALIFICATION CRITERIA AND REQUIREMENT
ELIGIBILITY AND QUALIFICATION CRITERIA COMPLIANCE REQUIREMENTS DOCUMENTATION
No.
Subject RequirementSingleEntity
Joint VentureSubmission
RequirementsAll PartiesCombined
Each PartnerOne
Partner
27
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 29/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
manufactures having at least 10years manufacturing experienceand ISO certification.
4.2(c)
Specificexperience (design&supervisory staff)
Technical staff of professionals withminimum experience requirementindicated as below on projects of similar nature.
Must meetrequireme
nt
Must meetrequireme
nt
N/A N/A Form EXP – 4.2(c)
4.2(d)
SpecificExperience(Availability of Equipment)
Should posses the minimum No. of equipment depicted in Form EXP – 4.2(d)
Must meetrequireme
nt
Must meetrequireme
nt
N/A N/A Form EXP –4.2(d)
29
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 30/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
The applicant shall provide details of the proposed personnel and their experiencerecords CV(s) duly signed by the concerned person(s) in the relevant informationForms included in Section 4 (Application Forms).
The minimum experience requirement of key technical staff shall not be less than
as noted below;
No. PositionTotal Work Experience
(years)
Experience onSimilar Works
(Years)1. Project Manger 20 102. Design Manager 15 53. Quality Control Engineer 15 54. Hydropower Engineer 15 55. Civil Engineer 15 56. Planning / Scheduling Engineer 15 57. Mechanical Engineer 15 5
8. Electrical Engineer 15 59. Geologist 15 510. Survey Engineer 15 5
30
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 31/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
The general inventory of required main equipment and tools are listed below. The
applicant must provide details of his equipment to be mobilized and proof of access
to the listed equipment or demonstrate its availability.
A – List of Main Equipment for Execution of Works
Sr.No.
Item Req. No.
1. Transportation truck 5t *2. Loader *3. Truck crane 8t *4. Graders *5. Concrete Batching Plant *6. Concrete Vibrators *7. Vibratory Roller *8. Bulldozer *
9. Vibrating Plate Compactors *10. Form Work for Concrete *11. Jeeps (4WD) *12. Cable Car *13. Electric Welding Machine *14. Electric Air Compressor 6m3 *15. Diesel air compressor 6m3 *16. Concrete mixer *17. Concrete transit mixer *18. Vibrator *19. Hoist 3tx2, 2tx2 *
20. X-ray fault detector *21. Pipe Bender *22. Bulge Pump *23. Platform – mounted drill *24. Hand-held electric drill *25. Diesel generator 50-70 KW *26. Dewatering Pump 6”-8” *27. Pneumatic drill *28. C6210 type lathe *29. Z32 type planer *30. B650 type planer *31. Testing equipment for electric installation of
powerhouse*
32. Communication equipment *33. Diesel air compressor 20m3 *34. Hand hoist 10tx12m *35. Hand hoist 5t *36. Hand hoist 3t *37. Hand hoist 1-2t *38. Excavators *39. Mobile Crane 25 Ton *40. Form Work *41. Wire cable 50mm *
42. Wire cable 12.5 – 25.5mm *43. Laboratory Equipment for Concrete and Soil *
31
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 32/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
Testing44. Any other tools/equipment *
* Number and capacity to be quoted by the applicant with brand
32
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 34/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
SECTION IV. APPLICATION FORMS
TABLE OF FORMS
Application Submission
Form……………………………………………………………………….
…………………………….24
Applicant Information
Form……………………………………………………………………………………………………
….29
Applicant’s Party information
Form……………………………………………………………………………………………30
Historical Contract Non-
Performance………………………………………………………………………………….
……..31
Financial Status ………….
……………………………………………………………………………………………………………
..32
Average Annual Construction
Turnover…………………………………………………………………………………......33
General ConstructionExperience……………………………………………………………………………………………
…..34
Similar Construction
Experience……………………………………………………………………………………………
…….35
Specific Construction Experience in Key
Activities………………………………………………………………….……..37
Specific Experience – Design and supervisory
Staff……………………………………………………………………….40
Specific Experience – Availability of
equipment……………………………………………………………………………..41
34
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 35/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
APPLICATION SUBMISSION FORM
Date: ________________ EPC/Turnkey Contract for
4.8 MW Rilai-II Hydropower ProjectDistrict Muzaffarabad, A J & K
Contract No. RHPP-II/ICB-01
To: Project Coordinator/Manager,
DESIGNMEN Consulting Engineers (Pvt) Ltd.1st Floor, 9-West, Rizwan Plaza,
Jinnah Avenue,F-6, Islamabad, PakistanPh: +92-51-2828577, 2829002Fax.: +92-51-2307615
We, the undersigned, apply to be prequalified for bidding for the followingcontracts:
Contract No, RHPP-II/ICB-01
and declare that:
(a) We have examined and have no reservations to the PrequalificationDocument, including Addenda No, issued in accordance withITA .Clause 8: _______________________
___________________________________________________________________________ (b) we, including any subcontractors or suppliers for any part of the contract
subject to this prequalification process, are eligible applicants, in accordance
with ITA Sub-Clause 4.2:_________________________________________________________________
35
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 36/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
(c) we, including any subcontractors or suppliers for any part of the contractsubject tothis prequalification do not have any conflict of interest, in accordance withITA
Sub-Clause 4.4;
(d) we, including any subcontractors or suppliers for any part of the contractresultingfrom this prequalification, have not been declared- ineligible by theEmployer orunder execution of a Bid Securing- Declaration in accordance with ITA Sub-Clause4.6, 4.8 and 4.9 or under the Employer's Country Laws or official regulations,inaccordance with ITA Sub-Clause 4.7:
(e) we are duly licensed by the Pakistan Engineering Council in Category C-A.(NoLimit);
(f) we are not a dependent agency of the Employer;
(g) we, in accordance with ITA Sub-Clause 24.1, plan to subcontract the
following key activities and/or parts of the works
___________________
___________________
___________________
(h) We declare that the following commissions, gratuities, or fees have been
paid or are to be paid with respect to the prequalification process.
Name of
Recipient
Address Reason Amount
[If none has been paid or is to be paid, indicate “none”.]
(i) We understand that you may cancel the prequalification process at any time
and that you are neither bound to accept any application that you may
receive nor to invite the prequalified applicants to bid for any one or
more contracts subject of this prequalification, without incurring any
liability to the Applicants, in accordance with ITA Clause 26.
Signed _________________________________
36
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 37/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
Name _________________________________ in the Capacity of _________________
Duly authorized to sign the application for and on behalf of;
Applicant’s Legal Name: _________________________________________________
Address ___________________________________________________________________
_________________________________________________________________________
Dated on _____________ day of _________________
FORM ELI – 1.1APPLICANT INFORMATION FORM
Date: ________________ EPC/Turnkey Contract for
4.8 MW Rilai-II Hydropower ProjectDistrict Muzaffarabad, A J & K
Contract No. RHPP-II/ICB-01
Page ______ of ________ pages
Applicant’s legal Name
Hyro Tech Pak(Pvt) Limited
In case of JV, legal name of each partner:i:Hydro Tech Pak(Pvt) Limitedii:Fuchun Industry
DevelopmentCo.,Shenzen , China
Applicant’s Actual or Intended country of constitution:
Applicant’s Actual or intended year of constitution:
37
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 38/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
Islamic Republic of Pakistan
Applicant’s Legal Address in country of constitution:105,Plot #21/28, Street# 19, New
Shami Road Peshawar Cantt. Phone No.091-5255201 , 091-5255205, Fax:091-5255202
Email: [email protected]’s authorized representative information
Name:
Address:
Telephone/Fax Numbers:
E-mail Address:
Attached are copies of original documents of :
1. In case of single entity, articles of Incorporation or Documents of Constitution of the legal entity named above, in accordance with ITA 4.1and 4.2
2. In case of JV, JV agreement, in accordance with ITA 4.13. In case of a government – owned entity, any additional documents not
covered under 1 above required to comply with ITA 4.7
FORM ELI – 1.2
APPLICANT’S PARTY INFORMATION FORM
[The following form shall be filled in for the Applicant’s parties including partner(s)
of a joint venture, subcontractors, suppliers and other parties]
Date: ________________ EPC/Turnkey Contract for
4.8 MW Rilai-II Hydropower ProjectDistrict Muzaffarabad, A J & K
Contract No. RHPP-II/ICB-01
Page ______ of ________ pages
JV applicant’s legal Name
Fuchun Hydrotech Pak(Pvt)Limited,Pakistan
Applicant’s Party legal name:
Fuchun IndustryDevelopmentCo.,Shenzen , China
38
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 39/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
Applicant’s Party country of constitution :
Peoples Republic of China
Applicant Party’s year of constitution:
Applicant Party’s Legal Address in country of constitution:
Fuchun IndustryDevelopmentCo.,Shenzen , China
Applicant Party’s authorized representative information
Name:
Address:
Telephone/Fax Numbers:
E-mail Address:
Attached are copies of original documents of :
1. Articles of Incorporation or Documents of Constitution and RegistrationDocuments of the legal entity named above, in accordance with ITA 4.22. In case of a government – owned entity, documents establishing legal
and financial autonomy and compliance with commercial law, inaccordance with ITA 4.7.
FORM CON - 2
HISTORICAL CONTRACT NON-PERFORMANCE
[The following table shall be filled in for the Applicant and for each partner of a Joint
Applicant’s Legal Name: Hyro Tech Pak(Pv) Ltd,Pakistan
Date:______________
Joint Venture Party Legal Name: Fuchun Industry DevelopmentCo.,Shenzen ,China
EPC/Turnkey Contract for4.8 MW Rilai-II Hydropower Project
District Muzaffarabad, A J & K Contract No. RHPP-II/ICB-01
Page ______ of ________ pages
Non-Performing Contracts in accordance with Section III, Qualification Criteria andRequirements
39
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 40/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
1. Contract non –performance did not occur during the last 10 yearsspecified under sub factor of 2.1 of Section III, Qualification Criteria andRequirements.
2. Contract(s) not performed during the last 10 years specified under sub
factor 2.2 of Section III, Qualification Criteria and Requirements.
Year
Non performedportion of contract
Contract Identification Total ContractAmount(currentvalue, Pak.Rs.)
N/A
Contract Identification:Name of Employer:Address of Employer:N/AReason(s) for non-performance:
Nil
Pending Litigation, in accordance with Section III. Qualification Criteria andRequirements
Nil
1. No pending litigation in accordance with Sub-Factor 2.3 of Section III,Qualification Criteria and Requirement.
2. Pending litigation in accordane with Sub-Factor 2.3 of Section III,Qualification Criteria and Requirements, Sub-Factor 2.2.
Year Outcome as Percentof Total Assets Contract Identification Total ContractAmount(Currentvalue, inrupees)
N/A
Contract Identification:Name of Employer:Address of Employer: N/AMatter in dispute:
Nil
40
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 41/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
FORM FIN 3.1
FINANCIAL STATUS
Applicant’s Legal Name: Hyro Tech Pak(Pvt) Ltd ,PakistanDate_____________________
JV Party Legal Name : Fuchun Industry DevelopmentCo.,Shenzen , China
EPC/Turnkey Contract for4.8 MW Rilai-II Hydropower Project
District Muzaffarabad, A J & K Contract No. RHPP-II/ICB-01
Page of __________ of __________pages
To be completed by the Applicant and, if JV, by each party
Financial Information inPak Rupees
Historic information for previous five (5) year(Pak Rupees in 000s)
Year -1(latestyear)
Year-2 Year-3 Year-4 Year-5
Information from Balance Sheet Total Assets (TA) Total Liabilities (TL)Net Worth (NW)
Current Assets (CA)Current Liabilities (CL)Information from Income Statement
Total Revenue (TR)Profits Before Taxes (PBT)
• Attached are copies of financial statements (balance sheets, including allrelated notes, and income statements) for the years required abovecomplying with the following conditions:
a. Must reflect the financial status of the applicant or party to a JV, and notsister or parent companies.
b. Historic financial statements must be audited by a certified accountant.c. Historic financial statements must be complete, including all notes to the
financial statements.d. Historic financial statements must be correspond to accounting periods
already completed and audited (no statements for partial periods shallbe requested or accepted).
41
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 42/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
FORM FIN 3.2
AVERAGE ANNUAL CONSTRUCTION TURNOVER
Applicant’s Legal Name: Hyro Tech Pak(Pvt),PakistanDate___________________
JV Party Legal Name:Fuchun Industry DevelopmentCo.,Shenzen , China
EPC/Turnkey Contract for4.8 MW Rilai-II Hydropower Project
District Muzaffarabad, A J & K Contract No. RHPP-II/ICB-01
Page of __________ of _________pages
Annual turnover data (construction only) Year Amount
(Pak Rs.)12345
*average Annual Construction
Turnover
*Average annual construction turnover calculated as total certified paymentsreceived for work in progress or completed, divided by the number of yearsspecified in Section III. Qualification Criteria and requirements, Sub-Factor 3.2.
42
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 43/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
FORM EXP 4.1
GENERAL CONSTRUCTION EXPERIENCE
Applicant’s Legal Name: Hyro Tech Pak(Pvt)Ltd,PakistanDate________________
JV Party Legal Name: Fuchun Industry DevelopmentCo.,Shenzen , China
EPC/Turnkey Contract for4.8 MW Rilai-II Hydropower Project
District Muzaffarabad, A J & K Contract No. RHPP-II/ICB-01
Page of __________ of _________pages
StartingMonth/Yea
r*
EndingMonth/Ye
ar
Contract Identification Role of Applicant
Contract Name:Brief Description of the works performed bythe Applicant:Name of Employer:Address:Contract Name:Brief Description of the works performed bythe Applicant:Name of Employer:Address:
Contract Name:Brief Description of the works performed bythe Applicant:Name of Employer:Address:Contract Name:Brief Description of the works performed bythe Applicant:Name of Employer:Address:Contract Name:Brief Description of the works performed bythe Applicant:Name of Employer:Address:Contract Name:Brief Description of the works performed bythe Applicant:Name of Employer:Address:
*List of calendar year starting with earliest year.
43
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 45/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
FORM EXP 4.2 (a) (Cont’d)
SIMILAR CONSTRUCTION EXPERIENCE (CONT.)
Applicant’s Legal Name: Hyro Tech Pak(Pvt) Ltd,Pakista Date ____________________
JV Party Legal Name _ Fuchun Industry DevelopmentCo.,Shenzen , China
EPC/Turnkey Contract for4.8 MW Rilai-II Hydropower Project
District Muzaffarabad, A J & K Contract No. RHPP-II/ICB-01
Page of __________ of _________pages
Similar Contract Number _____ of _____ required
Information
Description of the similarly inaccordance with Sub-Factor (4.2 (a) of Section-III
1. Amount __________________________________
2. Physical Size __________________________________
3. Complexity __________________________________
4. Methods/Technology __________________________________
5. Other Characteristics __________________________________
45
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 46/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
FORM EXP 4.2 (b)
SPECIFIC CONSTRUCTION EXPERIENCE IN KEY ACTIVITIES
Applicant’s Legal Name: _ Hyro Tech Pak(Pvt) Ltd,Pakistan Date __________________
JV Party Legal Name Fuchun Industry DevelopmentCo.,Shenzen , China
EPC/Turnkey Contract for4.8 MW Rilai-II Hydropower Project
District Muzaffarabad, A J & K Contract No. RHPP-II/ICB-01
Specialized contractor’s Legal Name (as per ITA 24.1): ________________________________
Page of __________ of _________pages
Information
Contract Identification
Award date:
Completion date:
__________________________________
__________________________________
Role in Contract Contractor
Management
Contractor
Subcontractor
Total Contract Amount: __________________ Rs. _________
If party in a JV or subcontractor, specifyparticipation of total contract amount _______% __________ Rs. _________ Employer’s Name:Address:
Telephone/Fax Number:
Email:
_____________________________________
_____________________________________
____________________________________
____________________________________
46
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 47/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
FORM EXP 4.2 (b) (Cont.)
SPECIFIC CONSTRUCTION EXPERIENCE IN KEY ACTIVITIES (CONT.)
Applicant’s Legal Name: Hyro Tech Pak(Pvt) Ltd,Pakistan Date __________________
JV Party Legal Name Fuchun Industry DevelopmentCo.,Shenzen , China
Specialized sub-contractor’s legal name (as per ITA 24.1)
EPC/Turnkey Contract for4.8 MW Rilai-II Hydropower Project
District Muzaffarabad, A J & K Contract No. RHPP-II/ICB-01
Page of __________ of _________pages
Information
Description of the key activities inaccordance with Sub-Factor 4.2(b) of Section-III.Civil works:
The No. of powerhouse building weirand allied structure penstocks or similarstructure has completed or have been inhis hand for last five (5) years.
Completion date:
__________________________________
__________________________________
Manufacturing Experience:Manufacturers of the majorcomponents of the plant, material andequipment shall have:
(i) Manufactured the majorcomponents i.e. Turbine, Shafts,Bearing, Governor, Generators, 11KV Switchgears, 132 kV Switchgear,Large Transformers and Protection
system and SCADA have beensupplied to at least three differentpower plants which are performingsatisfactorily for the last 5 years.and
(ii) demonstrated ISO 9001.2000Quality Management System orEquivalent.
(iii) If applicant is not the manufacturerit shall obtain from the
manufacturer its authorization tosupply.
47
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 48/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
48
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 49/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
FORM EXP 4.2 (c)
SPECIFIC EXPERIENCEDESIGN AND SUPERVISORY STAFF
Applicant’s Legal Name: _ Hyro Tech Pak(Pvt) Ltd,PakistanDate ________________
JV Party Legal Name:Fuchun Industry DevelopmentCo.,Shenzen , Chin
EPC/Turnkey Contract for4.8 MW Rilai-II Hydropower Project
District Muzaffarabad, A J & K Contract No. RHPP-II/ICB-01
Page of __________ of _________pages
SNo.
Name Description Age(Year
s)
Qualification TotalExperience (Years)
RelevantExperien
ce(Years)
Project ManagerDesign ManagerQuality Control
EngineerHydropower
EngineerCivil Engineer
Planning/Scheduling EngineerMechanicalEngineerElectricalEngineerGeologistSurvey
Engineer
49
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 50/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
FORM EXP 4.2 (d)
SPECIFIC EXPERIENCE -AVAILABILITY OF EQUIPMENT
Applicant’s Legal Name: Hyro Tech Pak(Pvt) Ltd Date _______________________
JV Party Legal Name:Fuchun Industry DevelopmentCo.,Shenzen , Chin
EPC/Turnkey Contract for4.8 MW Rilai-II Hydropower Project
District Muzaffarabad, A J & K Contract No. RHPP-II/ICB-01
Page of __________ of _________pages
SNo.
Item To beMobilized
Available with
Contractor
(Number
Type,Model,Make,Size
Year of Manufactu
re
Location
1. Transportation truck
5t.2. Loader3. Truck crane 8t.4. Graders
5. Concrete Batching
Plant6. Concrete Vibrators7. Vibratory Roller8. Bulldozer9. Vibrating Plate
Compactors10. Form Work for
concrete11. Jeep (4WD)
12. Cable Car13. Electric Welding
Machine14. Electric air compressor
6m3
15. Diesel air compressor
6m3
16. Concrete Mixer 0.8 m3
17. Concrete Transit mixer18. Vibrator
19. Hoist 3tx2, 2tx220. X-Ray fault detector
50
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 51/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
21. Pipe Bender22. Bulge pump23. Platform mounted drill24. Hand-held electric drill25. Diesel generator 50-70
KW.26. Dewatering Pump 6”-
8”27. Pneumatic drill28. C6210 type lathe29. Z32 type planer30. B650 type planer31. Testing equipment for
electric installation of powerhouse.
32. Communication
Equipment33. Diesel air compressor
20m3
34. Hand hoist 10x12 m.35. Hand hoist 5t36. Hand hoist 3t37. Hand hoist 1-2t38. Excavators39. Mobile Crane 25 Ton40. Form Work
41. Wire cable 50 mm42. Wire cable 12.5 – 2543. Laboratory Equipment
for concrete and soiltesting
44. Any other
tolls/equipment.
51
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 52/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
PART 2 – WORKS REQUIREMENTS
SECTION V. SCOPE OF WORKS
52
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 53/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
CONTENTS
1. Description of theWorks…………………………………………………………………………………………….46
1.1 General………………………………………………………………………………………………………………………46
1.2 Riali-II HydropowerProject…………………………………………………………………………………………46
1.3 Works under theContract…………………………………………………………………………………………..46
2. ConstructionPeriod…………………………………………………………………………………………………….47
3. Site and OtherData…………………………………………………………………………………………………….47
3.1 Location………………………………………………………………………………………………………………………47
3.2 Topography andGeology…………………………………………………………………………………………….47
3.3 Climate………………………………………………………………………………………………………………………..49
3.4 Language……………………………………………………………………………………………………………………..49
3.5 Religion………………………………………………………………………………………………………………………..49
3.6 Currency……………………………………………………………………………………………………………………….49
3.7 Availability of Labour…………………………………………………………………………………………………….49
3.8 Availability of Material………………………………………………………………………………………………….49
3.9 Availability of Construction
Equipment…………………………………………………………………………493.10 BiddingDocuments……………………………………………………………………………………………………… 50
3.11 Description of Salient Features of theProject……………………………………………………………… 50
53
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 54/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
1. DESCRIPTION OF THE WORKS
1.1 Riali-II Hydropower Project
Ghoriwala Katha is a right bank tributary of Neelum River with its confluence about
10 kms upstream of Muzaffarabad. The nullah has its origin in the glaciers lying at
an altitude of about 3800 masl. From its source to confluence with Neelum River, it
descends down to an altitude of about 750 masl. This steep drop in nullah bedoffers promising prospects of hydropower development downstream of Rajpayyan
village.
The area was initially studied by HEPO (WAPDA) in collaboration with GTZ and a
project site with an installed capacity of 3.0 MW was identified in the upper
reaches of the nullah. Subsequently, the lower reaches of the nullah were also
studied by a team of Korean experts who proposed layout for a 5 MW project
downstream of Bagh Bridge. This site was taken up in Private sector and an Letter
Of Interest (LOI) to carry out the feasibility study was issued to M/S Sachal
Engineering Works (Pvt) Limited, Islamabad in 2001. In Fulfillment of their
obligations under this LOI, a feasibility study was conducted by M/S PakistanEngineering Consultants -PES (Pvt.) Limited, Lahore & Engineering Consultants
International-ECIL (Pvt.) Limited, Karachi on behalf of the Sponsors. The feasibility
study report established design parameters and layout of a 4.9 MW project, which
was submitted to AJK PPC.
The feasibility study was further reviewed by M/S Renewable Energy Consultants-
RENCON in 2009. Based on the studies carried out, it was decided that the
development of 4.8 MW (net at site conditions) Power Plant is economically
feasible and M/S DESIGNMEN Consulting Engineers was contracted for preparation
of detailed design and EPC/Turnkey Bidding Documents for development of the
project under the proposed Power Purchase Agreement, which would be executed
54
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 55/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
between the Project Company and Peshawar Electric Supply Company (PESCO) or
any other buyer for a period of 25 to 30 years.
The Project is ideally located to help improve the electricity service and reliability
in the region.
Environmental impact assessment studies (EIA) have been conducted by the
consultants and Environmental Mitigation Plan has been prepared for
implementation of the proposed project. The project is expected to have immense
positive social impacts as the Project will provide job opportunities to the people of
the area.
The detailed technical specifications shall only be issued to Pre-Qualified Firms
interested to take part in bidding process for preparation of bids at next stage;
however salient features are described hereinafter for giving a tentative concept
of the scope of works.
1.2 Works under the contract
The proposed structure for the hydropower project includes design andconstruction of different civil structures Hydro Mechanical and Electricalequipments.
The proposed design and construction works under the Contract No. RHPP-II/ICB-01will include, but not limited to the following.
• Weir with lateral Intake
• Approach Channel
•
Desanders (sand trap)• Power channel
• Forebay
• Steel Penstock
• Surface Powerhouse
• Tailrace
• Horizontal shaft Pelton turbine
• Governors (PID-Type)
• Dewatering, Drainage, Cooling, Ventilation, and oil handling Systems
• Horizontal shaft Generators
• Transformers (Step-up/Auxiliary)
• 66kV interconnection line and switch yards/132kv• AC distribution system
• Control and Alarm system, generator protection, telecommunication andearthing systems
• Commissioning and joint operation
• Other Related works
2. Construction Period
The tendering and award phase for construction works is expected to start in April -May 2012 and likely to be completely by August 2012, while the contract is
expected to commence from September 2012. The duration of the constructionwork is 24 months.
55
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 56/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
3. Site and other Data
Location of the Project
The accessible length of valley formed by Ghoriwala Katha is about 16 kms. The
road distance from Muzaffarabad city to the mouth of valley at the right bank of Neelum River is about 10 kms. A metalled road branches off just after the RCCBridge on Kulsair Nullah from the Neelum valley road located on the right bank of Neelum River. This road passes through Ghori village enroute to Rajpayyan village.
The project layout is in the lower reaches of the valley with power house nearSteel trusses bridge on Ghoriwala Katha about 250 meters upstream of itsconfluence with Neelum River along its right bank. Power house site is about 10kms from Muzaffarabad City. The diversion weir is located about 350 metersupstream of Bagh Bridge on Ghori-Rajpayyan road. The road distance up to intakefrom main road is about 5 kms.
3.1 Topography and Geology The project site has topography typical of the region with steep slope and greenterraces along with torrential drains falling at places. Information available in thisoffice about the topography and geology of the area shall be shared throughbidding documents. However, the applicants are advised to visit the area of theproject as indicated on the project location map (figure-1) to acquaint themselveswith the site conditions.
56
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 57/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
57
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 58/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
In its 16 kms of stretch, the Ghoriwallah Nullah descends from an elevation of 3800 masl (12000 ft) to 750 masl (2500 ft) approx. at its confluence with NeelumRiver. The average slope of the Ghoriwallah katha bed is 9% and the catchmentarea is about 90 Km2 (35 miles2).
3.2 Climate
The project area lies within a mountainous region with surrounding peaks rising ashigh as 4000 meters. The regional climatic pattern is largely influenced by thistopography that acts as barriers between the region and Central Asia to the Northand main parts of Sub-Continent to the East. The project area is characterized bymild summers and cold winters. The summer Monsoons (July-Sept) caused byEasterly disturbance rarely penetrate beyond Makra and Ganja mountains nearMuzaffarabad and Punjal ranges of the Kashmir valley. Most of the Westerndisturbance (Dec–Apr) causes significant precipitation in winters and its intensitygradually decreases beyond Muzaffarabad and Rawalakote
The climate of the area surrounding the project is generally cold and dry. Summer
starts from March and continuous up to September. The mean annual precipitationof Muzaffarabad is 1550 mm. The temperature varies between 3 C to 38 C during⁰ ⁰ winter and summer seasons.
3.3 Language
Kashmiri is the local language and people generally well understand and speak thenational language Urdu, English is also spoken and understood among literates.
3.4 Religion
Islam is the religion of most of the people living in the area.
3.5 Currency
The currency is Pak Rupee
3.6 Availability of Labour
Skilled and unskilled labour is not easily available.
3.7 Availability of Material
Construction materials are locally available in the surrounding area of theproposed project site. However good quality sand and fine aggregate as well ascement and reinforcement steel will have to be procured from Lawrencepur,Margala and Rawalpindi/Islamabad respectively.
3.8 Availability of Construction Equipment/Plants
Excavators, vehicles, compressors, mixers, vibrators and generators can beprocured locally within Pakistan, Alternatively, the equipment may be hired fromvarious contractors/rental firms locally and down country.
3.9 Bidding DocumentsBidding Documents for the contractors shall be based on the STANDARD FORM OFBIDDING DOCUMENTS (EPC/TURNKEY CONTRACT First Edition July, 2010 published
58
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 59/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
by Pakistan Engineering Council. All payments to the contractor would be made inlocal currency.
3.10 Salient Features of the Project
The salient features of the project are tabulated as under:
SALIENT FEATURES
GENERAL
1 Location of project
a Diversion weir About 350 meters upstream of BaghBridge near Village Batal
b Powerhouse In the immediate vicinity of villageGhori, approximately 4 kilometerdownstream of Bagh Bridge.
2 Stream / Tributary Ghoriwala Katha, a right bank
tributary of River Neelum
3 Point of confluence About 10 kms upstream of Muzaffarabad along Muzaffarabad –Athmuqam Road
4 Access route to site
a Islamabad - Muzaffarabad 120 kms
b Muzaffarabad – Ghori village 10 Kms
c Ghori village - Intake 05 kms
Total 135 kms
5 Approximate travel time LTV
a Islamabad - Muzaffarabad 03 hrs
b Muzaffarabad – Ghori village ½ hrs
c Ghori village – Intake ½ hrs
Total 4 hrs
6. Surface Geological features Salkhala and Murree Formations
7. Stream Hydrology
a Catchment area at intake 68.6 km²
b Highest elevation in thecatchment area
3884 masl
c Average annual precipitation inthe catchment
1549.8 mm
d Minimum annual dry yearprecipitation in the catchment
1094 mm
e Maximum annual wet yearprecipitation in the catchment
2076 mm
f Long term mean flow 4.17 m³/s
g Design discharge 1.90 m³/s
h Head Available 320.94
59
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 60/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
i Net Head 285
j Flow available 50% of time (Q50) 2.50 m³/s
k Flow available 70% of time (Q70) 1.40 m³/s
l Flow available 90% of time (Q90) 0.81 m³/s
m Minimum recorded flow 0.38 m3/s
8. Structural features
Diversion weir
a Type Lateral Intake
b Structure RCC & Stone gabions
c Length of main spur 27 m
d Height of spur 3.5 m including. 2.0 meters in
foundationApproach channel
a X section (inside) Rectangular
b Bed Width (inside) 1.5 m
c Height of channel ( inside) 2.2 m
Desanders (Silt Excluder)
a Length 44 m
b Width 5 m
c Height 4.5 m
d Structure RCCPower channel
a X section (inside) Rectangular
b Bed Width (inside) 1.5 m
c Height of channel ( inside) 2.2 m
d Depth of water 1.25 m
e Free board 0.95 m
f Flow velocity 1.05 m/s to 2.3 m/s
g Bed slope 1:750 to 1:1000
h Length of headrace 4,046 mi Structure RCC
Forebay
a Length of main forebay 40 m
b Storage capacity 1415 m³
b Max depth of forebay 4 m
c Width of forebay 7.50 m
d Length of Spillway Cascading chute starting with a 50 msteel shaft dropping into a cistern and
then with drops varying from 2 metersto 4 meters over an approximate
60
8/2/2019 PQD_RIALI-II_HPP - Copy
http://slidepdf.com/reader/full/pqdriali-iihpp-copy 61/61
Prequalification Documents 4.8 MW Riali-II Hydropower Project
length of 150 meters.
e Structure RCC
Penstock
a No. of main Line 1
b Outside diameter 0.9 - 0.80 - 0.60 – 0.40 mc Thickness 8 mm – 10 mm – 12 mm
d Length of penstock 655 meters (excluding trifurcation)
e No. of main anchor blocks 12
g No. of expansion joints 6
Power house
a Floor area 40 m x 15.50 m
b No. of units 2 (with space for future extension of 1unit)
c Span of gantry crane 14.5 md Height of roof 10 m
e Structure RCC frame with brick filler panels
Tailrace
a Type Lined Channel
e Structure RCC with Steel lining
9 Electro-mechanical plant
a Type of turbine Single jet, Pelton Wheel
b Runner diameter 2.35 m
c Shaft Power 2510 kWd Number of units 2
e Power at flow Q95 per unit 2385 kW
f Voltage of generation 3300 V
g Speed 600 RPM
h Governor 6000 N-M
i Type Electro-pneumatic
j Power transformers 3300 / 11000 volts, 2000 kVA