ppt-mall 2 - accelerator · ppt-mall 2 med linje Åke andersson, slri thailand, 15 august, 2016 1...

77
PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development group, MAX IV

Upload: others

Post on 11-Jul-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

PPT-mall 2

Med linje

Åke Andersson, SLRI Thailand, 15 August, 2016 1

MAX IV; 3 GeV ring commissioning & RF systems

Åke AnderssonAccelerator development group, MAX IV

Page 2: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Outline

• MAX IV overview

• A little history

• MAX IV – 3 GeV & 1.5 GeV Rings & RF systems

• Cavities – conditioning

• 3 GeV ring commissioning

2Åke Andersson, SLRI Thailand, 15 August, 2016

Page 3: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Conceptual Basis of the MAX IV

3Åke Andersson, SLRI Thailand, 15 August, 2016

• Scientific Case calls for high brightness radiation

over a wide spectral and time range: IR to Hard R-

rays, Short X-Ray Pulses.

• Need for high brightness: low emittance and

optimized insertion devices.

• This is hard to achieve in a single machine:

• higher electron beam energy harder photons

• lower electron beam energy softer photons

One size does not fit all !

Page 4: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

The MAX IV Approach

• Different machines for different uses:• A high energy ring with ultra-low emittance for

hard X-ray users.

• A low emittance low energy ring for soft radiation users

• A LINAC based source for generating short pulses and allowing for future development of FEL source.

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 5: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

5

Inauguration was June 21, 2016

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 6: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

6

Photo Perry Nordeng

Aerial View of the MAX IV Site

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 7: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

7

Where is MAX IV Laboratory?

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 8: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

8

Inside the Linac building

Photo Annika Nyberg

Klystron gallery

Linear accelerator

Photo Annika Nyberg

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 9: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Inside the 3 GeV building

9

The experimental hall with one of the beamline’s experimental hutch. Seven are already being built.

Ring tunnel, start ofcommissioning, September 2015.

Photo Annika Nyberg 140828

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 10: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Inside the 3 GeV building

10

Photo Simon Leemann

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 11: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Outline

• MAX IV overview

• A little history

• MAX IV – 3 GeV & 1.5 GeV Rings & RF systems

• Cavities – conditioning

• 3 GeV ring commissioning

11Åke Andersson, SLRI Thailand, 15 August, 2016

Page 12: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Overview ”MAX-IV Laboratory”

ESLS XIX, Aarhus University, November 23-24, 2011. Åke Andersson

Our new

laboratory

was named,

and the old

MAX-lab

became a

part of it.

Page 13: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Operation Schedule

ESLS XIX, Aarhus University, November 23-24, 2011. Åke Andersson

User operaton 38 weeks/year.

Each week 6 days

5472 hours per year

3 rings 16 416 h per year

However, MAX-I, after 25 years of

user operation, is now retireing from

Synchrotron Radiation operation:

We are only occationally serving the

remaining IR interferometer beam

line and two educational beam lines

since autumn 2011. 9 user beam

lines were in operation over the

years.

MAX-I will continue running as a

pulse strecher for nuclear physics

as scheduled.

Page 14: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

The daily operation scheeme

ESLS XIX, Aarhus University, November 23-24, 2011. Åke Andersson

Page 15: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Injection routine

ESLS XIX, Aarhus University, November 23-24, 2011. Åke Andersson

•SC Wigglers ramp

down: 6 min

•Undulator gaps

opening

•Bem dump (RF

off)

•Magnets zero: 0.5

min

•Magnets up to

injection energy

•Injection: 3 min

•Energy ramp: 2

min

•SC Wigglers ramp

up: 6 min

•Undulator gaps

closing

•Landau cavity

towards nominal

tuning, while

SCWs ramping.

No major benefit from

ramping down with

beam (~ 160 mA).

Page 16: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Statistics MAX-II

0

10

20

30

40

50

60

70

80

90

100

0 1 2 3 4 5 6 7 8 9 1011121314151617181920212223242526272829303132333435363738394041424344454647484950

Ava

ila

bil

ity [

%]

Week

Weekly availability MAX-II

2011

2010

ESLS XIX, Aarhus University, November 23-24, 2011. Åke Andersson

Power break

during weekend

Corrector PS

trouble during

weekend

Page 17: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Statistics MAX-III

0

10

20

30

40

50

60

70

80

90

100

0 1 2 3 4 5 6 7 8 9 1011121314151617181920212223242526272829303132333435363738394041424344454647484950

Ava

ila

bil

ity [

%]

Week

Weekly availability MAX-III, 2011

First week after installing the

Landau cavity

ESLS XIX, Aarhus University, November 23-24, 2011. Åke Andersson

Page 18: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Some ”dangerous” activities at the

lab

• MAX-IV Gun test stand

• MAX-IV Landau cavity test in MAX-III

• MAX-IV Cavity conditioning stand

Need some care not to interfere with the user

operation!

ESLS XIX, Aarhus University, November 23-24, 2011. Åke Andersson

Page 19: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

ESLS XIX, Aarhus University, November 23-24, 2011. Åke Andersson

MAX-IV Landau cavity

Mechanical design, Elsayed Elafifi, MAX-lab

Page 20: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Conclusion from ”history section”:

Research & Development for future concepts and solutions, sometimes has a negative influence on present performance, but in the end it often pays off:

20Åke Andersson, SLRI Thailand, 15 August, 2016

020406080

100120140160180200220240260

2010 2011 2012 2013 2014 2015

Me

an c

urr

en

t [m

A]

Year

Mean current

Blue: MAX II Red:MAX III

70

75

80

85

90

95

100

2010 2011 2012 2013 2014 2015

Ava

ilab

ility

[%

]

Year

Availability

Page 21: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Outline

• MAX IV overview

• A little history

• MAX IV – 3 GeV & 1.5 GeV Rings & RF systems

• Cavities – conditioning

• 3 GeV ring commissioning

21Åke Andersson, SLRI Thailand, 15 August, 2016

Page 22: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

MAX IV 1.5 GeV ring

-15 -10 -5 0 5 10 15

X[m]

-30

-25

-20

-15

-10

-5

0

Y[m]

E = 1.5 GeV

C = 96 m

12 double-bend achromats;

length 4.5 m

12 straight sections;

length 3.5 m

Qx = 11.22 ; corr. chroma +2

Qy = 3.14 ; corr. chroma +2

εx = 6.0 nmrad

Radiation losses / turn: 117 keV

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 23: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

MAX IV 1.5 GeV ring

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 24: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

MAX IV 1.5 GeV ring

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 25: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Ring RF 1.5 GeV

-15 -10 -5 0 5 10 15

X[m]

-30

-25

-20

-15

-10

-5

0

Y[m]

One of the twelve SS is

”sacrified” for RF

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 26: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Ring RF 1.5 GeV ringLund Krakow

100 MHz

60 kW

Åke Andersson, SLRI Thailand, 15 August, 2016

2 2

Page 27: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

MAX IV 3 GeV Storage Ring

-100 -50 0 50 100

X[m]

-160

-140

-120

-100

-80

-60

-40

-20

0

Y[m]

E = 3 GeV

C = 528 m

20 multi-bend achromats; length 21.4 m

20 straight sections; length 5 m

Qx = 42.20 ; corr. chroma +1

Qy = 14.28 ; corr. chroma +1

εx = 0.326 nmrad (bare lattice)

Radiation losses / turn: 360 keV

(bare lattice)

Page 28: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

MAX IV 3 GeV ring

One of the 20 achromats in the 3 GeV ring

• Relatively compact magnet structure, except for two ”matching” short straights.

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 29: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

MAX IV 3 GeV ring• The Multi-Bend Achromat gives hor. emittance in the

Intra Beam Scattering regime:

Main radio frequency [MHz] 99.931

Harmonic number 176

Circulating current [mA] 500 Circumference [m] 528

Horizontal emittance (bare lattice) [nm rad] 0.37 [0.326]

Horizontal emittance (with 4 d w and 10 in-vac. Und.) [nm rad] 0.23 [0.201]

Radiation losses per turn (bare lattice) [keV] 360

Radiation losses per turn (with 4 d w and 10 in-vac. Und.) [keV] 854

Natural energy spread (bare lattice) [%] 0.084 [0.077]

Natural energy spread (with 4 d w and 10 in-vac. Und.) [%] 0.094 [0.091]

Momentum compaction factor 3.0 x 10e-4

Required lattice momentum acceptance ± 4.5 %

Rms bunch length with Landau cavities [mm] 50

Vertical emittance [pm rad] 8

[ ] =

without

IBS

Landau cavities are essential in order to reach the design

horizontal emittance!

The difference in

horizontal

emittance

with/without IBS is

kept low by diluting

the electron density

in the bunches.

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 30: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Ring RF 3 GeV ring

One of the 20 achromats in the 3 GeV ring

• Relatively compact magnet structure, except for two ”matching” short straights.

None of the twenty SS is ”sacrified” for RF. Instead we will

use nine short matching straights upstream the SS.

ID light cannot

pass the cavity

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 31: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Ring RF overview; 3 GeV Alternative I II

Energy loss with Ids 756keV 1020keV

Circulating current 0.5A 0.5A

Total beam power 378kW 510kW

Total RF voltage 1.5MV 1.8MV

Number of cavities 6 6

Cavity shunt impedance 3.2Mohm 3.2Mohm

Cu losses 117kW 169kW

Total RF power needed 495kW 679kW

Nr of RF stations 6 6

Nr of transmitters 12 12

Transmitter power 41.5kW 56kW

Power to cavity 83kW 113kW

Cu losses/cav 20kW 28kW

Coupling (beta) 4.2 4.0

Cavity voltage 250kV 300kV

Cavity gap 4cm 5cm

Bucket height 4.5 % 4.5 %

Alt I: Represents a solution for a 60% ID equipped ring, with the present MAX II/ MAX III cavities.

Alt II: Represents a solution for a fully ID equipped ring, with slightly modified MAX II/MAX III cavities.

60 kW60 kW

-φφ

120 kW Load

Circ.

Cavity

100 MHz

Åke Andersson, SLRI Thailand, 15 August, 2016

Chosen!

Page 32: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

RF Rooms

Main Cavities

Harmonic Cavities

RF plants insidering

32

MAXIV Ring RF System

Energy 1.5 GeV 3.0 GeV

RF 99.931

MHz

99.931

MHz

Circumference 96 m 528 m

Harmonic

number

32 176

Current 500 mA 500 mA

No of cavities 2 6

RF station

power

60kW 120kW

Cavity voltage 280kV 300kV

Coupling

(beta)

2.3 4.0

Storage Rings Parameters

1 single 60 kW

transmitters

2 combined

60 kW

transmitters

Lars Malmgren, 19th ESLS RF Workshop Lund, 30 Sept. - 1 Oct., 2015

Page 33: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Ring RF System - 3 GeV Ring RF• The main cavities are

placed in the second short straight section of six consecutive achromats.

• Each RF-room contains two RF power plants.

33Lars Malmgren, 19th ESLS RF Workshop Lund, 30 Sept. - 1 Oct., 2015

Page 34: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Ring RF System - 1.5 GeV Ring RF

• Two Main Cavities and two Harmonic Cavities occupy one straight section

• Two 60 kW Power Plants are placed inside the ring.

34Lars Malmgren, 19th ESLS RF Workshop Lund, 30 Sept. - 1 Oct., 2015

Page 35: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Ring RF System – High Power Plants

• Contracts signed for– High power amplifiers (Electrosys, Italy).

The delivery time was delayed because of severe financial problems in the company. The risk was too large to continue so the contract was canceled (June 2014). A new contract has been signed (September 2014)for delivery of 60 kW liquid cooled solid state power amplifiers ( Rohde & Schwarz, Germany)

– Circulators (AFT, Germany)– Transmission Lines and Integration Work

(Exir Boadcasting AB, Sweden)

• Delivery of high power amplifiers: Two in December 2014 (January 2015) for test of circulators, two in February 2015 , two in March and finally two in June 2015 (1.5 GeV).

Lars Malmgren, 19th ESLS RF Workshop Lund, 30 Sept. - 1 Oct., 2015 35

Page 36: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Ring RF System – High Power Plants• Rohde & Schwartz 60 kW

CW solid state liquid cooled amplifiers based on two 30 kW transmitters/amplifiers with additional power combiner

• >64% overall powerefficiency

• High MTBF

• Compact: 2000 mm × 600 mm × 1100 mm (HxWxD)

• Coolant: glycol/water

Lars Malmgren, 19th ESLS RF Workshop Lund, 30 Sept. - 1 Oct., 2015 36

Image: Electrosys

One pump unit andheat exchanger per rack

Page 37: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Outline

• MAX IV overview

• A little history

• MAX IV – 3 GeV & 1.5 GeV Rings & RF systems

• Cavities – conditioning

• 3 GeV ring commissioning

37Åke Andersson, SLRI Thailand, 15 August, 2016

Page 38: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

ESLS-RF Trieste, September 29-30, 2010. Åke Andersson

Main cavity design

• MAX II & MAX III main cavity

Mechanical design:

Leif Thånell, MAX-lab (retired)

Page 39: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

ESLS-RF Trieste, September 29-30, 2010. Åke Andersson

Main cavity design

• What we need to do better!• Cu became too soft after soldering

• An ”in air” weld of the shell (Ø 82 cm)

had leaks.

• Water cooling of the shell

Page 40: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

ESLS-RF Trieste, September 29-30, 2010. Åke Andersson

Main cavity design

• What we need to do better!• Cu became too soft after soldering

• An ”in air” weld of the shell (Ø 82 cm)

had leaks.

Electron Beam Welding seems to be the solution, but we need to learn:

How stiff OFHC copper can we excpect to get for the end plates, from industry?

Rp0.2 of 180 MPa?

How much does an EBW soften the material around the weld?

Do we really need to stay in the elastic region when we tune the cavity?

Can we safely construct the shell out of two half shells?

For the final weld:

What is the weld shrinkage?

Do we get a decent inner RF contact at the weld stop?

Page 41: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

ESLS-RF Trieste, September 29-30, 2010. Åke Andersson

Main cavity design

Cavity profile modification for 250 kV 300 kV

100 MHz Capacity-loaded Cavity for MAX-II and -III, F = 100.08317 MHz

C:\LANL\EXAMPLES\RADIOFREQUENCY\MYONEEXAMPLES\PILL100.AF 9-22-2009 12:40:42

0

5

10

15

20

25

30

35

40

0

5

10

15

20

25

30

35

40

0 5 10 15 20 25 30 35 40 45 50 55

5 cm gap instead of 4 cm

sligthly larger capacitor plate

We want to improve the cooling of

the plate.

New Old

Difficult to avoid water-to-

vacuum joints! OK, or not?

Q = 21000

Rsh = 3.5

Mohm

Q = 21000

Rsh = 3.5

Mohm

Page 42: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Ring RF System - Cavities

42

• All main cavities including two for Solaris Poland• Was Delivered

October -December 2013

July2013

April 2013

Photo: RI

Old spare cavity for MAX-II & MAX-II

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 43: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Ring RF System - Cavities

43

• Ten Main (two for Solaris) and fiveHarmonic Cavities have beenconditioned at the old MAX-lab.

July2013

April 2013

Photo: RI

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 44: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Ring RF System - Cavities

44

• Ten Main (two for Solaris) and five Harmonic Cavities havebeen conditioned at the old MAX-lab.

July2013

April 2013

Photo: RI

100 MHz Tetrode tubetransmitter for conditioning

300 MHz Harmonic Cavities

Page 45: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Main Cavities - Conditioning

45

• The cavities were delivered baked (3 days, 120 degree), with power coupler attached (β = 1).• A 600 l/s ion pump is attached. All cavities in the low 10-10 mbar range.

• So far, 9 main cavities (7 for MAX-IV, 2 for Solaris) have been conditioned to ̴ 25 kW.• Prototype: ̴ 1 year (!)• 2nd Cav # 11: ̴ 3.5 months• 3rd Cav # 08: ̴ 3 months• The following 5 cavities: ̴ 5 * 1 month (now a computer code was used! Robert Lindvall)• 9th cavity # 06: 2 weeks• 10th cavity #09: was only conditioned to ̴ 3 kW (lack of time)

• When all surrounding systems work OK, ̴ 3 weeks of conditioning is sufficient.• ̴1 week up to 50 W (!). Pressure raises up to 5*10-6 mbar!• ̴1 week to pass multipacting regime 3-5 kW. Sometimes a need to attach a turbo!• Finally ̴1 week to reach 25 kW stable operation, without more than 1 ”glitch” per day.• ”Glitch” = Sudden high reflected power, however self extinguishing after ̴ 60 μs.

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 46: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Main Cavities - Conditioning

46

• Multipacting problem origin: Coupler or Cavity body?

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 47: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Main Cavity – Coupler loop

47Åke Andersson, SLRI Thailand, 15 August, 2016

Page 48: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

48

Achromat # 16 17 18 19 20 1

Resonant freq. N2-Vented & Force free [MHz] 100,112 100,019 99,93 100,13 99,973 100,042

Difference compared to FAT [MHz] -0,084 -0,001 0,014 -0,043 0,038

Unloaded Q 20500 20400 20400 20250 20450 19700 Theory cyl-symm: 20923

Degradation due to Ports & Surfaces [%] 2,1 2,5 2,5 3,2 2,3 5,8

Shunt Impedance (linac def.) [MΩ] 3,45 3,43 3,43 3,41 3,44 3,32 Theory cyl-symm: 3,52 MΩ

Required power to reach 300 kV [kW] 26,1 26,2 26,2 26,4 26,2 27,1

After conditioning we vented and turned coupler to β = 2 for installation.We then measured fr and Q0 carefully (by turning coupler to β = 0) :

Main Cavities - Conditioning

The two cavities for the 1.5 GeV ring: Unloaded Q were 20100 and 19300.(The last Q-value was surprisingly low, indicating a 7.6 % surface degradation.)

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 49: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Main Cavities - Conditioning

49

A tiny defect in the ceramic windowcaused a leak p 1̴*10-8 mbar

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 50: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Main Cavities - Conditioning

50

Three probe loop ceramics (out of 16) have started leaking.Only those we forgot to 50 Ω terminate! Heating problem?

The last halfyear, moreleaks haveappeared, eventhoughterminatedproperly!!!

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 51: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Harmonic Cavities - Conditioning

51

• The 7 series cavities (5 MAX-IV, 2 Solaris) were delivered non-baked, only leak tested.• We performed ourselves the bake-out, with an Århus-coupler at β = 1 attached.• Each cavity has two 100 l/s ion pumps. All cavities in the low 10-10 mbar range.

• So far, 5 harmonic cavities have been conditioned to ̴ 4 kW.• Prototype: Is situated in the MAX-III ring since ̴ 4 years. Used only at ̴ 0.5 kW.• The following 5 cavities: ̴ 5 * 2 weeks (manual conditioning from a 300 MHz transm. )

• ̴1 week up to 50 W. Pressure raises up to 5*10-7 mbar!• ̴1 week to pass multipacting regime 0.5-2 kW.• 4 kW without problems, and without ”glitches”.• ”Glitch” = Sudden high reflected power, however self extinguishing.

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 52: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Harmonic Cavities - Conditioning

52

Achromat # 13 14 15

Resonant freq. @ FAT [MHz] 299,89 299,749 299,575

Resonant freq. Pumped & Force free [MHz] 299,766 299,561 299,44

Unloaded Q 20800 20800 21000 Theory cyl-symm: 21656

Degradation due to Ports & Surfaces [%] 3,95 3,95 3,03

Shunt Impedance (linac def.) [MΩ] 5,32 5,32 5,37 Theory cyl-symm: 5,54 MΩ

After bake-out, conditioning, removal of coupler, and installationwe measured fr and Q0. A Δfr = -140 kHz is expected.

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 53: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Main Cav. – Transport to site

53Åke Andersson, SLRI Thailand, 15 August, 2016

Page 54: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Installed and baked in 3 GeV ring

Photo courtesy S. C. Leemann

Page 55: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Outline

• MAX IV overview

• A little history

• MAX IV – 3 GeV & 1.5 GeV Rings & RF systems

• Cavities – conditioning

• 3 GeV ring commissioning

55Åke Andersson, SLRI Thailand, 15 August, 2016

Page 56: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Outline

• MAX IV overview

• A little history

• MAX IV – 3 GeV & 1.5 GeV Rings & RF systems

• Cavities – conditioning

• 3 GeV ring commissioningFirst a few glances at magnet and vacuum techniqal solutions:

56Åke Andersson, SLRI Thailand, 15 August, 2016

Page 57: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Slide by Martin Johansson

MAX IV 3 GeV ring DC magnets• Each cell is realized as one mechanical unit containing all magnet elements. •Each unit consists of a bottom and a top yoke half, machined out of one solid iron block, 2.3-3.4 m long.

Page 58: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

MAX IV 3 GeV ring magnets

Strong, 25 mm bore, sextupoles & achromatic octupoles for non-linear optics.All those carry auxiliary windingsthat can be used as:• Additional H/V correctors• Auxiliary sextupoles• Skew quadrupoles (coupling &

vertical dispersion correction)• Upright quadrupoles (calibrate

BPMs to the center of adjacentsextupole/octupole)

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 59: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

MAX IV 3 GeV ring vacuum

• First presentation

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 60: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

MAX IV 3 GeV ring vacuumBPM

Ion pump locationAbsorber location

Sector valve location

VC10VC1

VC2VC3

VC4

VC5

VC6

VC7

VC8

VC9

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 61: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

3 GeV ring, commissioning timeline

Page 62: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Commissioning 3 GeV Ring - RF

62

• During 2015 we had different difficulties to maintain all five cavities at nominal fields. ( The sixth cavity was removed from the ring because an early RF incident, that lead to a broken power coupler window). Mainlyvacuum trips even at low power was common. We would have neededeven longer conditioning time to remove multipacting regimes. Due to lack of time it was then easier to leave the power station off.

• However, for commissioning it was always enough with two or threecavities in operation. Injection was even more efficient at low total cavityvoltage, and 120 mA could easily be stored with three cavities in operation.

• The amplitude and phase loops were always regulating on the forward fields, from a directional coupler just before the power coupler. We found it not neccessary yet to regulate on the cavity fields.

• The frequency loops worked well. Still problems with the mechanical part, until it was found out that the bearings were not sufficiently greased.

• The frequency loop needs a delay of some hundred ms, to avoid regulatingon a mechanical vibration when the motor is moving. Alternatively an averaging of the signal over longer time can be used (low-pass filter).

Page 63: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

3 GeV ring, BPM offsets

-1.0

-0.5

0.0

0.5

1.0

Offset [m

m]

500400300200100

S[m]

Horizontal Vertical

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 64: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

3 GeV ring, integer tunes

-1.0

-0.5

0.0

0.5

1.0

DY

[mm

]

500400300200100

S[m]

Model Experiment

M1-COAY-01 changed by 0.1 mrad

-2

-1

0

1

2

DX

[m

m]

500400300200100

S[m]

Model Experiment

M1-COAX-01 changed by 0.1 mrad

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 65: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

3 GeV ring, bare vertical orbit

Plot by M. Sjöström

A random seed from our misalignmentmodel. Internal note 201211071, by S.C. Leemann

Page 66: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

3 GeV ring, vertical aperture

2011, simulations by S.C. Leemann2016-02-03, measurements by J. Sundberg

Measured vertical aperture scaled to center of LS: 2.3 mm

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 67: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

3 GeV ring, vacuum conditioning

5

6

7

8

910

-11

2

3

4

5

6

7

8

910

-10

Ave

rag

e N

orm

aliz

ed

Pre

ssu

re [

mb

ar/

mA

]

12 3 4 5 6 7 8 9

102 3

Dose[A.h]

P=P0*D^(power)power= -0.88 ± 0.004P0 = 1.78e-010 ± 1.28e-012

All vacuum gauges in S2except RF cavitiesI=50 to 55 mA

Page 68: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Commissioning – March 2016

68

• During 2016 we had a longer shutdown in February for installation of the two first IDs.

• From March to June the commissioning time was split between machine studies and BL commissioning at lowcurrents.

• During March to June 2016, we mostly operated with 4 or 5 main cavities at 270 kV each.

• In May –June, the phase and amplitude loops weremade to regulate on the cavity fields without problems.

• The machine studies mainly concentrated along twopaths: 1) Lattice/Optics investigations (low current), and 2) Instability studies with/without Harmonic Cavities(current up to 160 mA).

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 69: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

3 GeV ring, collective multibunch effects

• Possible to store >120 mA without feedback and without harmonic cavities. Predicted RW thresholdwas only ~ 40 mA !

• HOM driven longitudinal motion is evident at a fewmA in uniform fill.

• Harmonic Cavities not fully tested yet. Optimal settings at 150 mA and above.

• Preliminary BBB feedback tests using a short stripline showed a longitudinally stable beam up to 35 mA.

• Longer striplines for BBB feedback were installed in february.

• Longitudinal Actuator (cavity) under design.Åke Andersson, SLRI Thailand, 15 August, 2016

Page 70: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

3 GeV ring, Vacuum lifetime, May 2016

The beam was not stable longitudinally, nor vertically. Touschek lifetime fairly largeGas lifetime at 140 mA must be larger than 30 h!

Åke Andersson, SLRI Thailand, 15 August, 2016

Page 71: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Thank You for your attention!

71Åke Andersson, SLRI Thailand, 15 August, 2016

Page 72: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Extra slides

72

Page 73: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Digital Low Level RF

Lars Malmgren, 19th ESLS RF Workshop Lund, 30 Sept. - 1 Oct., 2015 73

• The DLLRF is based on the Perseus FPGA platform from Nutaq. Two units is in operation in the 3 GeV ring controlling two cavities each. The third will be taken into operation soon.

• It is possible to implement two independent loops besides the tuning loop. One controlling the amplitude of the cavity field and one the phase of the forward power. Either I / Q or polar loops can be selected.

• It has a fast data logger for post-mortem analysis.

Design by Angela SolomGUI by Antonio Milan

Page 74: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Lars Malmgren, 19th ESLS RF Workshop Lund, 30 Sept. - 1 Oct., 2015 74

Chopper for Ring Injection • Has two identical vertical kickers.• The kickers consist of a 15 cm long stripline pair

with a characteristic impedance of 50 Ω for odd TEM modes.

• Both electrodes are fed by RF• An aperture is located downstream. The

unwanted bunches will be dumped here. • The aperture can be selected so the wanted

bunches either passes a 1 mm iris, a 2 mm iris, or over an edge.

Aperture

0.84m0.24m

If φ1=-φ2 → Zo=49.9ΩIf φ1= 0 → Zo=63.8ΩIf φ1= φ2 → Zo=88.2Ω

2 D design

333 ps

10 ns

Page 75: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Lars Malmgren, 19th ESLS RF Workshop Lund, 30 Sept. - 1 Oct., 2015 75

Kicker system for ring injection

50 Ω

300 MHz~1 kW

100 MHz~400 W

Combining network

700 MHz~300 W

50 Ω

300 MHz~400 W

50 Ω

100 MHz~1 kW

Crosstalk <-31db

333 ps

10 ns

The MAX IV thermionic pre-injector will be covered by the talk of David Olsson

Page 76: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Lars Malmgren, 19th ESLS RF Workshop Lund, 30 Sept. - 1 Oct., 2015 76

MAX IV LinacThe linac should be used as an injector for both the 1.5 and 3 GeV storage rings and the SPF (Short Pulse Facility)• 18 klystrons• 18 SLEDS• 39 linac structures

Operating frequency 2998.5 MHzMaximum rep. rate 100HzMaximum RF power 35 MWRF pulse length 4.5µsLinac length 250 m

• Two Electron sources1. One klystron (7.5MW) feeding a

thermionic RF gun used for ring injections

2. A photo cathode gun for the SPF fed from the first linac klystron

Operating beam energy 3 GeV

Max. on-crest beam energy 3.6 GeV

44% RF power redundancy. Part of this has been reduced due to arcing at

some of the RF Power Units at high power. For safe operation two RF units

will be added later in 2016-2017. The linac tunnel is prepared for this change.

Page 77: PPT-mall 2 - Accelerator · PPT-mall 2 Med linje Åke Andersson, SLRI Thailand, 15 August, 2016 1 MAX IV; 3 GeV ring commissioning & RF systems Åke Andersson Accelerator development

Lars Malmgren, 19th ESLS RF Workshop Lund, 30 Sept. - 1 Oct., 2015 77

MAX IV linac

Photo Perry Nordeng 130903

K00+K00TG K01 K02K19

• RF conditioning did take longer time than anticipated despite that everything except the waveguides is preconditioned by RI. Problems with the subsystems have limited the time for conditioning

• Only minor impact on the Linac commissioning time schedule. The personal safety system PSS was changed so that it is possible to accelerate electrons up to the first bunch compressor while RF conditioning could continue in the rest of the linac.

• 3 GeV was reached for the first time February 9, 2015

Two more RF units willbe added for safeoperation, August 2016