ppt-mall 2 - accelerator · ppt-mall 2 med linje Åke andersson, slri thailand, 15 august, 2016 1...
TRANSCRIPT
PPT-mall 2
Med linje
Åke Andersson, SLRI Thailand, 15 August, 2016 1
MAX IV; 3 GeV ring commissioning & RF systems
Åke AnderssonAccelerator development group, MAX IV
Outline
• MAX IV overview
• A little history
• MAX IV – 3 GeV & 1.5 GeV Rings & RF systems
• Cavities – conditioning
• 3 GeV ring commissioning
2Åke Andersson, SLRI Thailand, 15 August, 2016
Conceptual Basis of the MAX IV
3Åke Andersson, SLRI Thailand, 15 August, 2016
• Scientific Case calls for high brightness radiation
over a wide spectral and time range: IR to Hard R-
rays, Short X-Ray Pulses.
• Need for high brightness: low emittance and
optimized insertion devices.
• This is hard to achieve in a single machine:
• higher electron beam energy harder photons
• lower electron beam energy softer photons
One size does not fit all !
The MAX IV Approach
• Different machines for different uses:• A high energy ring with ultra-low emittance for
hard X-ray users.
• A low emittance low energy ring for soft radiation users
• A LINAC based source for generating short pulses and allowing for future development of FEL source.
Åke Andersson, SLRI Thailand, 15 August, 2016
5
Inauguration was June 21, 2016
Åke Andersson, SLRI Thailand, 15 August, 2016
6
Photo Perry Nordeng
Aerial View of the MAX IV Site
Åke Andersson, SLRI Thailand, 15 August, 2016
7
Where is MAX IV Laboratory?
Åke Andersson, SLRI Thailand, 15 August, 2016
8
Inside the Linac building
Photo Annika Nyberg
Klystron gallery
Linear accelerator
Photo Annika Nyberg
Åke Andersson, SLRI Thailand, 15 August, 2016
Inside the 3 GeV building
9
The experimental hall with one of the beamline’s experimental hutch. Seven are already being built.
Ring tunnel, start ofcommissioning, September 2015.
Photo Annika Nyberg 140828
Åke Andersson, SLRI Thailand, 15 August, 2016
Inside the 3 GeV building
10
Photo Simon Leemann
Åke Andersson, SLRI Thailand, 15 August, 2016
Outline
• MAX IV overview
• A little history
• MAX IV – 3 GeV & 1.5 GeV Rings & RF systems
• Cavities – conditioning
• 3 GeV ring commissioning
11Åke Andersson, SLRI Thailand, 15 August, 2016
Overview ”MAX-IV Laboratory”
ESLS XIX, Aarhus University, November 23-24, 2011. Åke Andersson
Our new
laboratory
was named,
and the old
MAX-lab
became a
part of it.
Operation Schedule
ESLS XIX, Aarhus University, November 23-24, 2011. Åke Andersson
User operaton 38 weeks/year.
Each week 6 days
5472 hours per year
3 rings 16 416 h per year
However, MAX-I, after 25 years of
user operation, is now retireing from
Synchrotron Radiation operation:
We are only occationally serving the
remaining IR interferometer beam
line and two educational beam lines
since autumn 2011. 9 user beam
lines were in operation over the
years.
MAX-I will continue running as a
pulse strecher for nuclear physics
as scheduled.
The daily operation scheeme
ESLS XIX, Aarhus University, November 23-24, 2011. Åke Andersson
Injection routine
ESLS XIX, Aarhus University, November 23-24, 2011. Åke Andersson
•SC Wigglers ramp
down: 6 min
•Undulator gaps
opening
•Bem dump (RF
off)
•Magnets zero: 0.5
min
•Magnets up to
injection energy
•Injection: 3 min
•Energy ramp: 2
min
•SC Wigglers ramp
up: 6 min
•Undulator gaps
closing
•Landau cavity
towards nominal
tuning, while
SCWs ramping.
No major benefit from
ramping down with
beam (~ 160 mA).
Statistics MAX-II
0
10
20
30
40
50
60
70
80
90
100
0 1 2 3 4 5 6 7 8 9 1011121314151617181920212223242526272829303132333435363738394041424344454647484950
Ava
ila
bil
ity [
%]
Week
Weekly availability MAX-II
2011
2010
ESLS XIX, Aarhus University, November 23-24, 2011. Åke Andersson
Power break
during weekend
Corrector PS
trouble during
weekend
Statistics MAX-III
0
10
20
30
40
50
60
70
80
90
100
0 1 2 3 4 5 6 7 8 9 1011121314151617181920212223242526272829303132333435363738394041424344454647484950
Ava
ila
bil
ity [
%]
Week
Weekly availability MAX-III, 2011
First week after installing the
Landau cavity
ESLS XIX, Aarhus University, November 23-24, 2011. Åke Andersson
Some ”dangerous” activities at the
lab
• MAX-IV Gun test stand
• MAX-IV Landau cavity test in MAX-III
• MAX-IV Cavity conditioning stand
Need some care not to interfere with the user
operation!
ESLS XIX, Aarhus University, November 23-24, 2011. Åke Andersson
ESLS XIX, Aarhus University, November 23-24, 2011. Åke Andersson
MAX-IV Landau cavity
Mechanical design, Elsayed Elafifi, MAX-lab
Conclusion from ”history section”:
Research & Development for future concepts and solutions, sometimes has a negative influence on present performance, but in the end it often pays off:
20Åke Andersson, SLRI Thailand, 15 August, 2016
020406080
100120140160180200220240260
2010 2011 2012 2013 2014 2015
Me
an c
urr
en
t [m
A]
Year
Mean current
Blue: MAX II Red:MAX III
70
75
80
85
90
95
100
2010 2011 2012 2013 2014 2015
Ava
ilab
ility
[%
]
Year
Availability
Outline
• MAX IV overview
• A little history
• MAX IV – 3 GeV & 1.5 GeV Rings & RF systems
• Cavities – conditioning
• 3 GeV ring commissioning
21Åke Andersson, SLRI Thailand, 15 August, 2016
MAX IV 1.5 GeV ring
-15 -10 -5 0 5 10 15
X[m]
-30
-25
-20
-15
-10
-5
0
Y[m]
E = 1.5 GeV
C = 96 m
12 double-bend achromats;
length 4.5 m
12 straight sections;
length 3.5 m
Qx = 11.22 ; corr. chroma +2
Qy = 3.14 ; corr. chroma +2
εx = 6.0 nmrad
Radiation losses / turn: 117 keV
Åke Andersson, SLRI Thailand, 15 August, 2016
MAX IV 1.5 GeV ring
Åke Andersson, SLRI Thailand, 15 August, 2016
MAX IV 1.5 GeV ring
Åke Andersson, SLRI Thailand, 15 August, 2016
Ring RF 1.5 GeV
-15 -10 -5 0 5 10 15
X[m]
-30
-25
-20
-15
-10
-5
0
Y[m]
One of the twelve SS is
”sacrified” for RF
Åke Andersson, SLRI Thailand, 15 August, 2016
Ring RF 1.5 GeV ringLund Krakow
100 MHz
60 kW
Åke Andersson, SLRI Thailand, 15 August, 2016
2 2
MAX IV 3 GeV Storage Ring
-100 -50 0 50 100
X[m]
-160
-140
-120
-100
-80
-60
-40
-20
0
Y[m]
E = 3 GeV
C = 528 m
20 multi-bend achromats; length 21.4 m
20 straight sections; length 5 m
Qx = 42.20 ; corr. chroma +1
Qy = 14.28 ; corr. chroma +1
εx = 0.326 nmrad (bare lattice)
Radiation losses / turn: 360 keV
(bare lattice)
MAX IV 3 GeV ring
One of the 20 achromats in the 3 GeV ring
• Relatively compact magnet structure, except for two ”matching” short straights.
Åke Andersson, SLRI Thailand, 15 August, 2016
MAX IV 3 GeV ring• The Multi-Bend Achromat gives hor. emittance in the
Intra Beam Scattering regime:
Main radio frequency [MHz] 99.931
Harmonic number 176
Circulating current [mA] 500 Circumference [m] 528
Horizontal emittance (bare lattice) [nm rad] 0.37 [0.326]
Horizontal emittance (with 4 d w and 10 in-vac. Und.) [nm rad] 0.23 [0.201]
Radiation losses per turn (bare lattice) [keV] 360
Radiation losses per turn (with 4 d w and 10 in-vac. Und.) [keV] 854
Natural energy spread (bare lattice) [%] 0.084 [0.077]
Natural energy spread (with 4 d w and 10 in-vac. Und.) [%] 0.094 [0.091]
Momentum compaction factor 3.0 x 10e-4
Required lattice momentum acceptance ± 4.5 %
Rms bunch length with Landau cavities [mm] 50
Vertical emittance [pm rad] 8
[ ] =
without
IBS
Landau cavities are essential in order to reach the design
horizontal emittance!
The difference in
horizontal
emittance
with/without IBS is
kept low by diluting
the electron density
in the bunches.
Åke Andersson, SLRI Thailand, 15 August, 2016
Ring RF 3 GeV ring
One of the 20 achromats in the 3 GeV ring
• Relatively compact magnet structure, except for two ”matching” short straights.
None of the twenty SS is ”sacrified” for RF. Instead we will
use nine short matching straights upstream the SS.
ID light cannot
pass the cavity
Åke Andersson, SLRI Thailand, 15 August, 2016
Ring RF overview; 3 GeV Alternative I II
Energy loss with Ids 756keV 1020keV
Circulating current 0.5A 0.5A
Total beam power 378kW 510kW
Total RF voltage 1.5MV 1.8MV
Number of cavities 6 6
Cavity shunt impedance 3.2Mohm 3.2Mohm
Cu losses 117kW 169kW
Total RF power needed 495kW 679kW
Nr of RF stations 6 6
Nr of transmitters 12 12
Transmitter power 41.5kW 56kW
Power to cavity 83kW 113kW
Cu losses/cav 20kW 28kW
Coupling (beta) 4.2 4.0
Cavity voltage 250kV 300kV
Cavity gap 4cm 5cm
Bucket height 4.5 % 4.5 %
Alt I: Represents a solution for a 60% ID equipped ring, with the present MAX II/ MAX III cavities.
Alt II: Represents a solution for a fully ID equipped ring, with slightly modified MAX II/MAX III cavities.
60 kW60 kW
-φφ
120 kW Load
Circ.
Cavity
100 MHz
Åke Andersson, SLRI Thailand, 15 August, 2016
Chosen!
RF Rooms
Main Cavities
Harmonic Cavities
RF plants insidering
32
MAXIV Ring RF System
Energy 1.5 GeV 3.0 GeV
RF 99.931
MHz
99.931
MHz
Circumference 96 m 528 m
Harmonic
number
32 176
Current 500 mA 500 mA
No of cavities 2 6
RF station
power
60kW 120kW
Cavity voltage 280kV 300kV
Coupling
(beta)
2.3 4.0
Storage Rings Parameters
1 single 60 kW
transmitters
2 combined
60 kW
transmitters
Lars Malmgren, 19th ESLS RF Workshop Lund, 30 Sept. - 1 Oct., 2015
Ring RF System - 3 GeV Ring RF• The main cavities are
placed in the second short straight section of six consecutive achromats.
• Each RF-room contains two RF power plants.
33Lars Malmgren, 19th ESLS RF Workshop Lund, 30 Sept. - 1 Oct., 2015
Ring RF System - 1.5 GeV Ring RF
• Two Main Cavities and two Harmonic Cavities occupy one straight section
• Two 60 kW Power Plants are placed inside the ring.
34Lars Malmgren, 19th ESLS RF Workshop Lund, 30 Sept. - 1 Oct., 2015
Ring RF System – High Power Plants
• Contracts signed for– High power amplifiers (Electrosys, Italy).
The delivery time was delayed because of severe financial problems in the company. The risk was too large to continue so the contract was canceled (June 2014). A new contract has been signed (September 2014)for delivery of 60 kW liquid cooled solid state power amplifiers ( Rohde & Schwarz, Germany)
– Circulators (AFT, Germany)– Transmission Lines and Integration Work
(Exir Boadcasting AB, Sweden)
• Delivery of high power amplifiers: Two in December 2014 (January 2015) for test of circulators, two in February 2015 , two in March and finally two in June 2015 (1.5 GeV).
Lars Malmgren, 19th ESLS RF Workshop Lund, 30 Sept. - 1 Oct., 2015 35
Ring RF System – High Power Plants• Rohde & Schwartz 60 kW
CW solid state liquid cooled amplifiers based on two 30 kW transmitters/amplifiers with additional power combiner
• >64% overall powerefficiency
• High MTBF
• Compact: 2000 mm × 600 mm × 1100 mm (HxWxD)
• Coolant: glycol/water
Lars Malmgren, 19th ESLS RF Workshop Lund, 30 Sept. - 1 Oct., 2015 36
Image: Electrosys
One pump unit andheat exchanger per rack
Outline
• MAX IV overview
• A little history
• MAX IV – 3 GeV & 1.5 GeV Rings & RF systems
• Cavities – conditioning
• 3 GeV ring commissioning
37Åke Andersson, SLRI Thailand, 15 August, 2016
ESLS-RF Trieste, September 29-30, 2010. Åke Andersson
Main cavity design
• MAX II & MAX III main cavity
Mechanical design:
Leif Thånell, MAX-lab (retired)
ESLS-RF Trieste, September 29-30, 2010. Åke Andersson
Main cavity design
• What we need to do better!• Cu became too soft after soldering
• An ”in air” weld of the shell (Ø 82 cm)
had leaks.
• Water cooling of the shell
ESLS-RF Trieste, September 29-30, 2010. Åke Andersson
Main cavity design
• What we need to do better!• Cu became too soft after soldering
• An ”in air” weld of the shell (Ø 82 cm)
had leaks.
Electron Beam Welding seems to be the solution, but we need to learn:
How stiff OFHC copper can we excpect to get for the end plates, from industry?
Rp0.2 of 180 MPa?
How much does an EBW soften the material around the weld?
Do we really need to stay in the elastic region when we tune the cavity?
Can we safely construct the shell out of two half shells?
For the final weld:
What is the weld shrinkage?
Do we get a decent inner RF contact at the weld stop?
ESLS-RF Trieste, September 29-30, 2010. Åke Andersson
Main cavity design
Cavity profile modification for 250 kV 300 kV
100 MHz Capacity-loaded Cavity for MAX-II and -III, F = 100.08317 MHz
C:\LANL\EXAMPLES\RADIOFREQUENCY\MYONEEXAMPLES\PILL100.AF 9-22-2009 12:40:42
0
5
10
15
20
25
30
35
40
0
5
10
15
20
25
30
35
40
0 5 10 15 20 25 30 35 40 45 50 55
5 cm gap instead of 4 cm
sligthly larger capacitor plate
We want to improve the cooling of
the plate.
New Old
Difficult to avoid water-to-
vacuum joints! OK, or not?
Q = 21000
Rsh = 3.5
Mohm
Q = 21000
Rsh = 3.5
Mohm
Ring RF System - Cavities
42
• All main cavities including two for Solaris Poland• Was Delivered
October -December 2013
July2013
April 2013
Photo: RI
Old spare cavity for MAX-II & MAX-II
Åke Andersson, SLRI Thailand, 15 August, 2016
Ring RF System - Cavities
43
• Ten Main (two for Solaris) and fiveHarmonic Cavities have beenconditioned at the old MAX-lab.
July2013
April 2013
Photo: RI
Åke Andersson, SLRI Thailand, 15 August, 2016
Ring RF System - Cavities
44
• Ten Main (two for Solaris) and five Harmonic Cavities havebeen conditioned at the old MAX-lab.
July2013
April 2013
Photo: RI
100 MHz Tetrode tubetransmitter for conditioning
300 MHz Harmonic Cavities
Main Cavities - Conditioning
45
• The cavities were delivered baked (3 days, 120 degree), with power coupler attached (β = 1).• A 600 l/s ion pump is attached. All cavities in the low 10-10 mbar range.
• So far, 9 main cavities (7 for MAX-IV, 2 for Solaris) have been conditioned to ̴ 25 kW.• Prototype: ̴ 1 year (!)• 2nd Cav # 11: ̴ 3.5 months• 3rd Cav # 08: ̴ 3 months• The following 5 cavities: ̴ 5 * 1 month (now a computer code was used! Robert Lindvall)• 9th cavity # 06: 2 weeks• 10th cavity #09: was only conditioned to ̴ 3 kW (lack of time)
• When all surrounding systems work OK, ̴ 3 weeks of conditioning is sufficient.• ̴1 week up to 50 W (!). Pressure raises up to 5*10-6 mbar!• ̴1 week to pass multipacting regime 3-5 kW. Sometimes a need to attach a turbo!• Finally ̴1 week to reach 25 kW stable operation, without more than 1 ”glitch” per day.• ”Glitch” = Sudden high reflected power, however self extinguishing after ̴ 60 μs.
Åke Andersson, SLRI Thailand, 15 August, 2016
Main Cavities - Conditioning
46
• Multipacting problem origin: Coupler or Cavity body?
Åke Andersson, SLRI Thailand, 15 August, 2016
Main Cavity – Coupler loop
47Åke Andersson, SLRI Thailand, 15 August, 2016
48
Achromat # 16 17 18 19 20 1
Resonant freq. N2-Vented & Force free [MHz] 100,112 100,019 99,93 100,13 99,973 100,042
Difference compared to FAT [MHz] -0,084 -0,001 0,014 -0,043 0,038
Unloaded Q 20500 20400 20400 20250 20450 19700 Theory cyl-symm: 20923
Degradation due to Ports & Surfaces [%] 2,1 2,5 2,5 3,2 2,3 5,8
Shunt Impedance (linac def.) [MΩ] 3,45 3,43 3,43 3,41 3,44 3,32 Theory cyl-symm: 3,52 MΩ
Required power to reach 300 kV [kW] 26,1 26,2 26,2 26,4 26,2 27,1
After conditioning we vented and turned coupler to β = 2 for installation.We then measured fr and Q0 carefully (by turning coupler to β = 0) :
Main Cavities - Conditioning
The two cavities for the 1.5 GeV ring: Unloaded Q were 20100 and 19300.(The last Q-value was surprisingly low, indicating a 7.6 % surface degradation.)
Åke Andersson, SLRI Thailand, 15 August, 2016
Main Cavities - Conditioning
49
A tiny defect in the ceramic windowcaused a leak p 1̴*10-8 mbar
Åke Andersson, SLRI Thailand, 15 August, 2016
Main Cavities - Conditioning
50
Three probe loop ceramics (out of 16) have started leaking.Only those we forgot to 50 Ω terminate! Heating problem?
The last halfyear, moreleaks haveappeared, eventhoughterminatedproperly!!!
Åke Andersson, SLRI Thailand, 15 August, 2016
Harmonic Cavities - Conditioning
51
• The 7 series cavities (5 MAX-IV, 2 Solaris) were delivered non-baked, only leak tested.• We performed ourselves the bake-out, with an Århus-coupler at β = 1 attached.• Each cavity has two 100 l/s ion pumps. All cavities in the low 10-10 mbar range.
• So far, 5 harmonic cavities have been conditioned to ̴ 4 kW.• Prototype: Is situated in the MAX-III ring since ̴ 4 years. Used only at ̴ 0.5 kW.• The following 5 cavities: ̴ 5 * 2 weeks (manual conditioning from a 300 MHz transm. )
• ̴1 week up to 50 W. Pressure raises up to 5*10-7 mbar!• ̴1 week to pass multipacting regime 0.5-2 kW.• 4 kW without problems, and without ”glitches”.• ”Glitch” = Sudden high reflected power, however self extinguishing.
Åke Andersson, SLRI Thailand, 15 August, 2016
Harmonic Cavities - Conditioning
52
Achromat # 13 14 15
Resonant freq. @ FAT [MHz] 299,89 299,749 299,575
Resonant freq. Pumped & Force free [MHz] 299,766 299,561 299,44
Unloaded Q 20800 20800 21000 Theory cyl-symm: 21656
Degradation due to Ports & Surfaces [%] 3,95 3,95 3,03
Shunt Impedance (linac def.) [MΩ] 5,32 5,32 5,37 Theory cyl-symm: 5,54 MΩ
After bake-out, conditioning, removal of coupler, and installationwe measured fr and Q0. A Δfr = -140 kHz is expected.
Åke Andersson, SLRI Thailand, 15 August, 2016
Main Cav. – Transport to site
53Åke Andersson, SLRI Thailand, 15 August, 2016
Installed and baked in 3 GeV ring
Photo courtesy S. C. Leemann
Outline
• MAX IV overview
• A little history
• MAX IV – 3 GeV & 1.5 GeV Rings & RF systems
• Cavities – conditioning
• 3 GeV ring commissioning
55Åke Andersson, SLRI Thailand, 15 August, 2016
Outline
• MAX IV overview
• A little history
• MAX IV – 3 GeV & 1.5 GeV Rings & RF systems
• Cavities – conditioning
• 3 GeV ring commissioningFirst a few glances at magnet and vacuum techniqal solutions:
56Åke Andersson, SLRI Thailand, 15 August, 2016
Slide by Martin Johansson
MAX IV 3 GeV ring DC magnets• Each cell is realized as one mechanical unit containing all magnet elements. •Each unit consists of a bottom and a top yoke half, machined out of one solid iron block, 2.3-3.4 m long.
MAX IV 3 GeV ring magnets
Strong, 25 mm bore, sextupoles & achromatic octupoles for non-linear optics.All those carry auxiliary windingsthat can be used as:• Additional H/V correctors• Auxiliary sextupoles• Skew quadrupoles (coupling &
vertical dispersion correction)• Upright quadrupoles (calibrate
BPMs to the center of adjacentsextupole/octupole)
Åke Andersson, SLRI Thailand, 15 August, 2016
MAX IV 3 GeV ring vacuum
• First presentation
Åke Andersson, SLRI Thailand, 15 August, 2016
MAX IV 3 GeV ring vacuumBPM
Ion pump locationAbsorber location
Sector valve location
VC10VC1
VC2VC3
VC4
VC5
VC6
VC7
VC8
VC9
Åke Andersson, SLRI Thailand, 15 August, 2016
3 GeV ring, commissioning timeline
Commissioning 3 GeV Ring - RF
62
• During 2015 we had different difficulties to maintain all five cavities at nominal fields. ( The sixth cavity was removed from the ring because an early RF incident, that lead to a broken power coupler window). Mainlyvacuum trips even at low power was common. We would have neededeven longer conditioning time to remove multipacting regimes. Due to lack of time it was then easier to leave the power station off.
• However, for commissioning it was always enough with two or threecavities in operation. Injection was even more efficient at low total cavityvoltage, and 120 mA could easily be stored with three cavities in operation.
• The amplitude and phase loops were always regulating on the forward fields, from a directional coupler just before the power coupler. We found it not neccessary yet to regulate on the cavity fields.
• The frequency loops worked well. Still problems with the mechanical part, until it was found out that the bearings were not sufficiently greased.
• The frequency loop needs a delay of some hundred ms, to avoid regulatingon a mechanical vibration when the motor is moving. Alternatively an averaging of the signal over longer time can be used (low-pass filter).
3 GeV ring, BPM offsets
-1.0
-0.5
0.0
0.5
1.0
Offset [m
m]
500400300200100
S[m]
Horizontal Vertical
Åke Andersson, SLRI Thailand, 15 August, 2016
3 GeV ring, integer tunes
-1.0
-0.5
0.0
0.5
1.0
DY
[mm
]
500400300200100
S[m]
Model Experiment
M1-COAY-01 changed by 0.1 mrad
-2
-1
0
1
2
DX
[m
m]
500400300200100
S[m]
Model Experiment
M1-COAX-01 changed by 0.1 mrad
Åke Andersson, SLRI Thailand, 15 August, 2016
3 GeV ring, bare vertical orbit
Plot by M. Sjöström
A random seed from our misalignmentmodel. Internal note 201211071, by S.C. Leemann
3 GeV ring, vertical aperture
2011, simulations by S.C. Leemann2016-02-03, measurements by J. Sundberg
Measured vertical aperture scaled to center of LS: 2.3 mm
Åke Andersson, SLRI Thailand, 15 August, 2016
3 GeV ring, vacuum conditioning
5
6
7
8
910
-11
2
3
4
5
6
7
8
910
-10
Ave
rag
e N
orm
aliz
ed
Pre
ssu
re [
mb
ar/
mA
]
12 3 4 5 6 7 8 9
102 3
Dose[A.h]
P=P0*D^(power)power= -0.88 ± 0.004P0 = 1.78e-010 ± 1.28e-012
All vacuum gauges in S2except RF cavitiesI=50 to 55 mA
Commissioning – March 2016
68
• During 2016 we had a longer shutdown in February for installation of the two first IDs.
• From March to June the commissioning time was split between machine studies and BL commissioning at lowcurrents.
• During March to June 2016, we mostly operated with 4 or 5 main cavities at 270 kV each.
• In May –June, the phase and amplitude loops weremade to regulate on the cavity fields without problems.
• The machine studies mainly concentrated along twopaths: 1) Lattice/Optics investigations (low current), and 2) Instability studies with/without Harmonic Cavities(current up to 160 mA).
Åke Andersson, SLRI Thailand, 15 August, 2016
3 GeV ring, collective multibunch effects
• Possible to store >120 mA without feedback and without harmonic cavities. Predicted RW thresholdwas only ~ 40 mA !
• HOM driven longitudinal motion is evident at a fewmA in uniform fill.
• Harmonic Cavities not fully tested yet. Optimal settings at 150 mA and above.
• Preliminary BBB feedback tests using a short stripline showed a longitudinally stable beam up to 35 mA.
• Longer striplines for BBB feedback were installed in february.
• Longitudinal Actuator (cavity) under design.Åke Andersson, SLRI Thailand, 15 August, 2016
3 GeV ring, Vacuum lifetime, May 2016
The beam was not stable longitudinally, nor vertically. Touschek lifetime fairly largeGas lifetime at 140 mA must be larger than 30 h!
Åke Andersson, SLRI Thailand, 15 August, 2016
Thank You for your attention!
71Åke Andersson, SLRI Thailand, 15 August, 2016
Extra slides
72
Digital Low Level RF
Lars Malmgren, 19th ESLS RF Workshop Lund, 30 Sept. - 1 Oct., 2015 73
• The DLLRF is based on the Perseus FPGA platform from Nutaq. Two units is in operation in the 3 GeV ring controlling two cavities each. The third will be taken into operation soon.
• It is possible to implement two independent loops besides the tuning loop. One controlling the amplitude of the cavity field and one the phase of the forward power. Either I / Q or polar loops can be selected.
• It has a fast data logger for post-mortem analysis.
Design by Angela SolomGUI by Antonio Milan
Lars Malmgren, 19th ESLS RF Workshop Lund, 30 Sept. - 1 Oct., 2015 74
Chopper for Ring Injection • Has two identical vertical kickers.• The kickers consist of a 15 cm long stripline pair
with a characteristic impedance of 50 Ω for odd TEM modes.
• Both electrodes are fed by RF• An aperture is located downstream. The
unwanted bunches will be dumped here. • The aperture can be selected so the wanted
bunches either passes a 1 mm iris, a 2 mm iris, or over an edge.
Aperture
0.84m0.24m
If φ1=-φ2 → Zo=49.9ΩIf φ1= 0 → Zo=63.8ΩIf φ1= φ2 → Zo=88.2Ω
2 D design
333 ps
10 ns
Lars Malmgren, 19th ESLS RF Workshop Lund, 30 Sept. - 1 Oct., 2015 75
Kicker system for ring injection
50 Ω
300 MHz~1 kW
100 MHz~400 W
Combining network
700 MHz~300 W
50 Ω
300 MHz~400 W
50 Ω
100 MHz~1 kW
Crosstalk <-31db
333 ps
10 ns
The MAX IV thermionic pre-injector will be covered by the talk of David Olsson
Lars Malmgren, 19th ESLS RF Workshop Lund, 30 Sept. - 1 Oct., 2015 76
MAX IV LinacThe linac should be used as an injector for both the 1.5 and 3 GeV storage rings and the SPF (Short Pulse Facility)• 18 klystrons• 18 SLEDS• 39 linac structures
Operating frequency 2998.5 MHzMaximum rep. rate 100HzMaximum RF power 35 MWRF pulse length 4.5µsLinac length 250 m
• Two Electron sources1. One klystron (7.5MW) feeding a
thermionic RF gun used for ring injections
2. A photo cathode gun for the SPF fed from the first linac klystron
Operating beam energy 3 GeV
Max. on-crest beam energy 3.6 GeV
44% RF power redundancy. Part of this has been reduced due to arcing at
some of the RF Power Units at high power. For safe operation two RF units
will be added later in 2016-2017. The linac tunnel is prepared for this change.
Lars Malmgren, 19th ESLS RF Workshop Lund, 30 Sept. - 1 Oct., 2015 77
MAX IV linac
Photo Perry Nordeng 130903
K00+K00TG K01 K02K19
• RF conditioning did take longer time than anticipated despite that everything except the waveguides is preconditioned by RI. Problems with the subsystems have limited the time for conditioning
• Only minor impact on the Linac commissioning time schedule. The personal safety system PSS was changed so that it is possible to accelerate electrons up to the first bunch compressor while RF conditioning could continue in the rest of the linac.
• 3 GeV was reached for the first time February 9, 2015
Two more RF units willbe added for safeoperation, August 2016