PPPs: Understanding their procurement option context Paul O’Connor Sessional Lecturer/Doctoral Candidate School of Property, Construction and Project Management

Upload: paul-oconnor

Post on 04-Jun-2015

1.418 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: PPPs as an infrastructure procurement option

PPPs: Understanding their procurement option context

Paul O’Connor

Sessional Lecturer/Doctoral Candidate

School of Property, Construction and Project Management

Page 2: PPPs as an infrastructure procurement option

Paul O'Connor 2RMIT University © 2011

Scope of this presentation

1. Where did PPPs come from?

2. What were the key drivers in Victoria?

3. What has been achieved in a decade?

4. The alphabet soup of procurement options…

5. Why choose PPPs for infrastructure?

6. Practical considerations for PPPs

7. Benefits of a long-term funding model

8. Are PPPs the future or a passing fad?

9. PPPs in action: sector case studies

Page 3: PPPs as an infrastructure procurement option

Paul O'Connor 3

Where did PPPs come from?

• PPPs have been around for hundreds of years–Perrier Brothers had a drinking water concession in 1700s

• Modern PPPs started with the UK’s Private Financing Initiative launched in 1992:–Policy to extend Thatcher’s near-complete privatisation push–Kept and embraced by ‘New Labour’ when elected in 1997

• Seen as a way to smooth out demands upon the capital account for developed economies with high deficits

• Seen as one of Tony Blair’s “third way” vehicles to engage with the private sector and achieve public goals

• Seen as a way to speed up social and economic infrastructure renewal & promote delivery effectiveness

RMIT University © 2011

Page 4: PPPs as an infrastructure procurement option

Paul O'Connor 4

What were the key drivers in Victoria?

•Two distinct periods–Pre-2000 – emerging PPP guidelines–Post-2000 – current PPP guidelines

•Pre-2000–Post recession period looking to kick start economy and

find “non-debt” capital methods

•Post-2000–Iconic and one-off complex projects–User pays (i.e. toll roads) and water treatment plants–Social infrastructure replacement and augmentation

(Refer to papers by Linda English and Maguire & Malinovich)

RMIT University © 2011

Page 5: PPPs as an infrastructure procurement option

Paul O'Connor 5

What has been achieved in a decade?

•UK has 500+ PFI projects with a capital value in excess of £28 billion

•Victoria has A$10.5 billion contracted in 21 projects (www.partnerships.vic.gov.au)

•Detailed policy and guidance suites have been developed in UK and Australia

•World Bank and ADB also promoting PPPs

•PPPs being adopted in emerging economies

RMIT University © 2011

Page 6: PPPs as an infrastructure procurement option

Paul O'Connor 6

Context: infrastructure & development (1)

•Wide range of public infrastructure demand is forecast for many sectors:–Transport–Education–Health–Government accommodation/facilities–Utilities (water, sewerage, telecoms, power)

• Infrastructure ‘deficits’ making larger calls upon scarce government capital

RMIT University © 2011

Page 7: PPPs as an infrastructure procurement option

Paul O'Connor 7

Context: infrastructure & development (2)

•Recurrent demands also increasing to fund essential citizen services

•Large and lumpy disbursements

•Debt/surplus funding raises fiscal issues:–Sovereign credit ratings linked to debt–‘Lazy’ balance sheets/inefficient allocations–Inter-generational equity of debt liabilities–Ongoing operations and maintenance liability plus depreciation and replacement funding

RMIT University © 2011

Page 8: PPPs as an infrastructure procurement option

Paul O'Connor 8

The alphabet soup of options…

•Many options to procure infrastructure available:–Build to design (B)–Design and build (D and B)–Managing contractor (D and B)–Alliance (D and B)–JV (D, B and O) (and maybe F)–PPP/PFI (D,B, F, M) (and maybe O)

•Analysis of the profile of the infrastructure should drive the procurement strategy

RMIT University © 2011

Page 9: PPPs as an infrastructure procurement option

Paul O'Connor 9

Why choose PPPs for infrastructure?

Value and size of the project

Technical complexity/novelty

Risk allocation profile (especially demand risk)

Scope for design/technical innovation

Maturity of the public sector project owner

Private sector interest/public sector need

Complementary projects to go with the PPP?

RMIT University © 2011

Page 10: PPPs as an infrastructure procurement option

Paul O'Connor 10

Practical considerations for PPPs

For…

–Fixed capital payments over life of the asset

–Asset will return to public ownership

–Contract ‘locks in’ O and M funding

–Output specification drives service and asset quality

–Value for money

Against…

–Finding a good partner

–Funding availability (esp. due to GFC)

–Transparency of risk transfer premiums

–Up-front and high transaction costs

–Long term monitoring regime to maintain expected standards

RMIT University © 2011

Page 11: PPPs as an infrastructure procurement option

Paul O'Connor 11

Benefits of a long term funding model

Smooth and predictable budget outlays

Promotes inter-generational equity

Embeds whole-of-life asset costing

Technology obsolescence better managed

Maintenance funding no longer discretionary

Operations can be kept contestable via regular market benchmarking or resets

Funding profile matches long-term institutional investors like pension or sovereign funds

RMIT University © 2011

Page 12: PPPs as an infrastructure procurement option

Paul O'Connor 12

Are PPPs the future or a passing fad?

• In Australia:–Still only account for about 10% of total public sector

asset investments (approx. $10.5 billion in Victoria in 10 years)

–Most are on balance sheet, so no accounting advantage–User pays model (i.e. toll roads) becoming difficult due to

problems with accuracy of traffic demand forecasting–Some states pursuing Alliances more aggressively–Marginal cost of capital issue – cost and availability of

private finance versus public sector debt raisings–Low hanging fruit exhausted? Iconic/innovative facilities

likely to be overtaken by more boring facilities (such as schools, water and sewerage)

RMIT University © 2011

Page 13: PPPs as an infrastructure procurement option

Paul O'Connor 13

SECTOR CASE STUDIES

PPPs in Action:

RMIT University © 2011

Page 14: PPPs as an infrastructure procurement option

1417-21 May 2010

PPPs in Action – Sector case studies

•Health

•Transport

•Education

Page 15: PPPs as an infrastructure procurement option

15

Health PPPs – some typical models

• DBFM – design, build, finance, maintain–Positive (refer to RWH

report and the RCH project summary)

–Negative (refer to PAC report on Paddington)

• DBFOM – design, build, finance, operate, maintain–(similar to privatisation?)

Page 16: PPPs as an infrastructure procurement option

1617-21 May 2010

Page 17: PPPs as an infrastructure procurement option

17-21 May 2010 17

Health PPPs – lessons & observations

•Transfer of design risk to private sector is only effective if State has clearly specified:–Present and future clinical models

–Present and future demand

–Expected functionality of the facility

–Non-negotiable building standards

•UK issues – quality of build in some facilities and fair profit share for refinancing gains

Page 18: PPPs as an infrastructure procurement option

17-21 May 2010 18

Transport PPPs

Page 19: PPPs as an infrastructure procurement option

17-21 May 2010 19

Road PPPs

Variety of models to consider

• ‘Toll road’ concession model–Successes: CityLink and EastLink in Melbourne –Failures: Sydney and Brisbane tunnels (over optimistic demand

forecasts and upfront payments to Government)

• HOT lane model–Augment existing corridor with express toll lane

• ‘Availability’ model–Used in UK with ‘shadow tolls’ –New PPP in Victoria – KPI not volume based

Page 20: PPPs as an infrastructure procurement option

Rail PPPs

• Infrastructure–London Underground

(refer to NAO reports)

•Rolling stock–(NSW)

•Facilities/interchange–Southern Cross Station

(refer to VAGO report)

Page 21: PPPs as an infrastructure procurement option

17-21 May 2010

Transport PPPs - observations

•For roads –don’t be greedy and demand upfront payments, as this is

passed on via higher tolls to the public who may then boycott the route. (Refer to NSW AG report on tunnels)

•For rail–Understand the value drivers of the business and focus on

using private sector expertise to increase operational efficiency and reliability, as well as contain costs over the long-term. (Refer NAO reports on the underground)

Page 22: PPPs as an infrastructure procurement option

Education PPPs - Variety of models

• New build–Single site schools–Multiple site schools (refer PV

schools summary)

• Tertiary research precinct–LaTrobe University (refer

Biosciences summary)

• Refurbishment–UK building schools for the

future (refer NAO report)–Southbank TAFE (Brisbane)

Page 23: PPPs as an infrastructure procurement option

17-21 May 2010 23

Education PPPs – some observations…

•Specify demand corridors and let private sector take site risk (PV schools)

•Multi-site deal is effective way to achieve quick build-out of many sites over a wide area

•Some risks of a “two class” system, due to poor asset maintenance in the State build sector

•Lock in of service payments reduces future flexibility (c.f. declining revenue base in Scotland)

Page 24: PPPs as an infrastructure procurement option

24

Other sectors?

• Prisons–Facilities only (DBFM)–Integrated correctional

services (DBFOM)

• Electricity–Independent power

producers

• Water–Town supply or desalination

plants

Page 25: PPPs as an infrastructure procurement option

Paul O'Connor 25RMIT University © 2011

Any questions?

• My contact details:

Paul O’Connor DipPer&OpsMgt, DipGovMgt, BA(AsianStudies), GradCertPPPs (Melb.), MPubInfra (Melb.)

School of Property, Construction and Project Management

RMIT University

E: <[email protected]>