ppp - fdot teams update
TRANSCRIPT
P3 Teams Update:Procurement Team
Engineering and Operation TeamFinancing Team
July 11, 2007
Procurement Team
Ruth DillardDirector, Office of Administration
July 11, 2007
3
PPP Goals
• Procure services, not assets, from private sector
• Require output terms as part of each PPP Procurement providing opportunity for innovation and risk transfer
• Bundles include Design-Build-Finance at a minimum, and where appropriate, Operations-Maintenance, resulting in an Integrated, Efficient, Service Delivery
• Project partially or fully financed by private sector
• Risks allocated to party best able to manage them
4
FDOT Procurement Successes
• Outsourcing transportation projects since the 1960s
• Construction Outsourcing composed of:
Building roads and bridges – 100% outsourced
• Maintenance Outsourcing – 80% outsourced
• Engineering Service – 80% outsourced
5
PPP Foundation
Well-Established FDOT Procurement Processes
• Construction, Design/Build, Professional Services and Asset Maintenance
• Rules
• Procedures
• Refined and improved over the years as more and more processes have been done
• Input from internal and external customers
6
2 Triggers for P3s
• Solicited Proposals
• Unsolicited Proposals
7
Solicited PPP Proposals• Design/Build and Asset Maintenance procurement
processes solid foundations to build upon
• DOT will advertise projects utilizing established processes
- Contracts Administration website: http://www.dot.state.fl.us/cc-admin/
- Procurement website: http://www.dot.state.fl.us/procurement/
• Firms not prequalified may be qualified via the procurement process
8
Solicited PPP Proposals (continued)
• Transparent Process
• Sunshine Law applies, except:
10 days after Proposal is received
Exempt items such as company financial statements
• Time Added from Short-List and Issuance of RFP for Interaction Between Teams and FDOT on Draft Documents and Technical Issues
9
Solicited PPP Proposals (continued)
• One on Ones will occur during this time for discussion, not decision-making
• Fair, Open, and Competitive
• Best Value Approach
10
Unsolicited PPP Proposals
What is Different?
• Please talk to FDOT prior to a submittal of unsolicited proposal
• May submit a concept proposal, provided FDOT can determine the project being proposed
• When unsolicited proposals are submitted - $50,000 fee required
11
Unsolicited PPP Proposals (continued)
• DOT will publish notice in the Florida Administrative Weekly AND newspaper of general circulation at least once a week for 2 weeks and accept proposals for 120 days after initial publication
• Substantial deviation from project purpose requires permission
• Teams submitting proposals must meet minimum qualifications, which the Department will publish
12
Strict Procurement Process
• RFQ Issued
• “Cone of Silence”
Once RFQ is issued, FDOT will not talk about or take comments from one proposer about another proposer
“Cone” covers Evaluation Team members, Selection Team members, those “Up Line”
• DOT will evaluate the submitted information
13
Strict Procurement Process (continued)
• Firms will be short-listed
• Short-listed firms will be posted
• Request for Proposals will be issued to short- listed firms
• Proposals move to “Sunshine” after 10 days
14
Strict Procurement Process (continued)
• Once in the Sunshine, all non-exempt information subject to review
• Proposals will be evaluated
• Proposals will be ranked
• DOT will finalize the agreement
15
Ethics Policy Considerations
FDOT employees not allowed to take ANY gift or benefit from a company doing business with or seeking to do business with FDOT.
16
Final FDOT PPP Procurement Vision
• Open, Fair, Competitive Process
• Draft process today, open for input
• Evolution into standard process
• PPP Procurement Questions:
Ruth Dillard – [email protected]
Juanita Moore – [email protected]
Engineering and Operations Team
Ananth PrasadChief Engineer
July 11, 2007
18
Engineering and Operations Task Team
• Objective to “mainstream” P3s by
Developing Policies and Procedures
Boilerplate documents such as RFP, Technical Requirements.
• While recognizing that these documents are “living” documents and will change as we continue to learn from such projects.
19
Technical Requirements
• Being developed by the various disciplines within the Department (i.e. Roadway Design, Pavements, Structures, Construction, Maintenance, etc.)
• FDOT has extensive Design-Build and Warranty experience.
20
Technical Requirements
• Design Criteria
• Construction Criteria
• Alternative Technical Concepts
• Maintenance and Handback Requirements
• Oversight Role
Owner/FHWA
21
Technical Requirements
• General Philosophy is that our standards and specifications are the baseline.
Use the Alternative Technical Concept Proposals to submit innovative ideas.
Be open minded on ATCs.
• Allow choices to be made on Life Cycle Analysis
Asphalt pavement vs. Concrete Pavement
Concrete Bridge vs. Steel Bridge
Median Guardrail vs. Median Concrete Barrier Wall
22
Alternative Technical Concepts (ATC)
• The ATC process allows proposers to incorporate innovation, flexibility, creativity and construction time and cost savings into the design and construction of a project and to obtain the best value for the public.
• ATC’s are accepted by the Department at their discretion.
23
Alternative Technical Concepts
• The RFP indicates ATC areas that are off limits. Any proposed changes shall provide a solution that is equal or better to what is required by the RFP as determined by the Department.
• A concept is NOT an ATC if it reduces quality, performance, or reliability.
• Strict confidentiality shall be maintained during the ATC review process through meetings.
24
ATC Submittals
• ATC Submittals need to include information such as:
Description
Usage – How being used?
Explain deviations from the RFP
Analysis justification
Impacts
Risks
Quality
Changes to Operations and Maintenance
25
ATC Advantages
• Promotes innovation and taps expertise
• Can result in reduction of project costs
• Justifies the stipend for unsuccessful proposers when their ideas can be incorporated
• Provides the Owner with new ideas, techniques, or materials to use in future projects
26
ATC Disadvantages
• Be careful not to accept proposals that cut the scope (i.e. drop lanes, reduce shoulder widths, delete components)
• Can make comparison of proposals somewhat difficult
• Typically adds an extra month to the proposal process
27
Concessionaire’s Oversight Role
• Complies with the Approved Project Management Plan (PMP)
• Complies with all Contract Requirements
• Signs and Seals all Engineering Drawings
• Self-Reports on Non-Compliance (monitoring compliance)
• Conducts Inspection Testing and Acceptance
28
Owner’s Oversight Role
• Monitors the Concessionaire’s Compliance with Concession Agreement
Conformance to the PMP
Public and End User Safety
Monitors Project Performance Over Term of Concession Agreement
Handback Standards (Residual Life Expectancy)
29
Owner Oversight Philosophy
• Owner will have oversight commensurate to the concession period
Every contract will have some oversight.
• Use Department’s process for Disputes Review Boards to resolve disputes.
30
Owner/FHWA Oversight Philosophy
• Materials Testing
DOT’s Contractor Quality Control (QC) Model
- Open to ATC such as ISO Accreditation, Different QC Model.
Owner reserves the right to perform independent tests
- No set frequency but commensurate with history of results and risk.
- Failing tests requires resolution.
31
Maintenance Requirements
• FDOT has extensive experience in Asset Management and Asset Maintenance Contracts.
• Asset Maintenance Contract criteria to be included
Criteria is performance based.
32
Maintenance Requirements• Should cover the following areas and more:
Customer Response
Incident Response
Roadway (Potholes, Raveling, Shoving, Depressions, etc)
Roadside (Unpaved Shoulders, Slopes, Fence, etc)
Traffic Services (Striping, Pavement Markings, Guardrail, Signs, Lighting, etc)
Drainage (Cross drains, ditch, inlets, sweeping, etc)
Vegetation and Aesthetics (Mowing, Litter, Tree Trimming, Turf, etc)
Bridge Condition
Signals
ITS
33
Major Repairs/Rehab
• Pavements
Pavement Conditions Surveys (every year)
- Flexible Pavement are rated for Rutting, Ride, and Cracking on a scale of 0 (worst) to 10 (best). Rigid Pavement are rated on defect and ride.
- Pavement segments with any rating of 6.4 or below are classified deficient and require replacement.
• Structures
Bridge Condition Survey (every 2 years)
- Bridge Condition Index should always be 6 (satisfactory) or higher
– Structural Elements shows minor deterioration
34
Handback Requirements
The terms, conditions, requirements and procedures governing the condition in which Concessionaire is to deliver the Project and Project Right-of-Way to the Owner upon expiration or earlier termination of the Agreement and Lease, as set forth in the Technical Requirements.
35
Handback Requirements• Renewal Work Schedule – each year before Handback
Concessionaire’s calculation of Residual Life
Estimates cost of the Renewal Work
• Major Residual Life Categories
Pavement
Structures
Building and Maintenance Facilities
Toll Collection and Traffic Management Facilities
Drainage
Safety Appurtenances
36
Handback Requirements
• Develop Residual Life Methodology
• Perform Residual Life Inspections
- First Inspection – Between 58 and 62 months before Handback.
- Second Inspection – Between 15 and 18 months before Handback.
- Final Inspection – Not later than 90 days before Handback.
37
PPP Guidelines
• The Guidelines will document
the Department’s activities with respect to implementing P3 projects.
• The manual will consist of sections that focus on the procurement process, from the planning phase through final award of the project.
• The goal is for the Department and the Industry to be aware of the major considerations involved in the process and to promote the consistency necessary to ensure the best value statewide.
38
PPP – Engineering Issues
Finally, we would like to hear your thoughts and comments.
Ananth Prasad
(850) 414-5240
Financing Team
Marsha Johnson, CPADirector, Office of Financial Development
July 11, 2007
40
Finance Presentation
• What’s “Not” New with P3
• Alphabet Soup
• What’s “New” with P3
• Summary
41
Cash Management
• FDOT utilizes various cash management techniques to manage revenues and expenditures
• Cash management techniques include INNOVATIVE FINANCE TOOLS
• We call it “The Tool Box”
42
Innovative Financing Tools
• Federal Flexibility
• Reasonable Level of BondingTurnpike Revenue Bonds
Right of Way and Bridge Bonds
GARVEE Bonds
Seaports Bonds
• State Infrastructure Bank
• P3 – Public-Private Partnerships• Other Innovative Financing Options
43
Public Private Partnership (PPP, P3)
• Contractual agreement between public and private partners which allows more private sector participation than traditional contracting.
• Alphabet soup construction D-B (design-build)
D-B-B (design-bid-build)
D-B-F (design-build-finance)
D-B-O-M-F (design-build-operate-finance)
44
HB 985 Financial Policies • Leasing of Existing Toll Facilities and P3s
Allows Existing FDOT Facilities to be Leased to a P3, except the Turnpike
Leases of Existing Toll Facilities must be approved by the Legislative Budget Commission Prior to Awarding a contract
Allows P3 to Deliver New Toll Facilities
45
HB 985 Financial Policies
• Policies on All Toll Facilities
Toll Rates Regulated by FDOT through Concession Agreement
Requires FDOT to Receive a Portion of the Excess Revenues as Part of the Agreement
Provide Investment Grade Traffic and Revenue Study and detail Finance as part of the Proposal
46
HB 985 Financial Policies
• Cost-effectiveness and Overall Public benefit Study
Value for Money analysis
Prior to moving forward with the procurement
Prior to awarding the contract
Independent Financial Advisor Will Perform
47
HB 985 Financial Policies
• Indexing of the Toll rates
Index to Annual Consumer Price Index or Similar Index
No more Frequently than Once a year and
No Less Frequently than once Every 5 years
48
HB 985 Financial Policies
• Availability Payments/Shadow Tolls
Allows for Payments based on Availability of Facility or based on the level of traffic using the facility
Payments included in the Work Program and Long-Range Plan ahead of New Capacity Projects
Subject to Annual Appropriation by the Legislature
49
HB 985 Financial Policies
• Link of Project Development and Financial Policies
P3 projects Must Meet All Planning and Environmental Requirements Before Moving Forward
FDOT will Normally develop Project to Completion of Environmental Clearance
Will Ensure Project is Supported and Well Developed
50
HB 985 Financial Policies
• Financial Security Package
Allows Use of Flexible Approach to Secure Delivery of Project
Includes Combination of Surety Bonds, Letters of Credit, Parent Company Guarantees and Related Items
Balance the Structure of the Security Package for the P3 that Ensures Performance and Payment of Subcontractors with the cost of the security to ensure the most efficient pricing.
51
HB 985 Financial Policies
• Terms at 50, or up to 75 Years
• Limit on FDOT Funds for P3s
• Clarifies FDOT may use innovative financing techniques such as hedges associated with P3s
52
Financial Advisor Update
Financial Advisory ExpertsSeven Short-listedWill Narrow to Three, then to One for Each
New P3 ProjectAlso, Advise on Overall ProcessWill Work Closely with Legal Team who will
be Experienced in P3 Transactions
53
Summary• The “Deal” must fit the project!
• Help develop an understanding and knowledge on P3s
• Help define common sense rules, bench mark on the best approaches for successful P3s
• Remain focused on what is “best” for the public
54
PPP – Finance Issues
Marsha Johnson
(850) 414-4647
presentations\p3\FTBA P3 Team Update.ppt
Questions or Comments?