ppc_tutorial_2.pdf

Upload: koriomlivecomau

Post on 14-Apr-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 PPC_tutorial_2.pdf

    1/21

    University of South Australia

    School of Advanced Manufacturing and Mechanical Engineering

    Project Planning and Control G

    Tutorial 2: Module 5

    Module 7 Set

    Akot B Akot

    5/17/2013

  • 7/30/2019 PPC_tutorial_2.pdf

    2/21

    i

    Declaimer

    I declare the following to be our own work, unless otherwise referenced, as defined by the

    Universitys policy on plagiarism.

  • 7/30/2019 PPC_tutorial_2.pdf

    3/21

    ii

    Contents

    Declaimer ................................................................................................................................................. i

    List of Figures ......................................................................................................................................... iii

    List of Tables .......................................................................................................................................... iv

    1. Introduction .................................................................................................................................... 1

    2. Solution and Explanation ................................................................................................................ 1

    2.1. Module 5 ............................................................................................................................. 1

    2.2. Module 6 ............................................................................................................................. 5

    2.3. Module 7 ............................................................................................................................. 8

    3. Conclusion ..................................................................................................................................... 15

    Reference .............................................................................................................................................. 16

  • 7/30/2019 PPC_tutorial_2.pdf

    4/21

    iii

    List of FiguresFigure 1: WBS of Automated system for welding bicycle frames ........................................................................... 2

    Figure 2: Organisational Breakdown Structure ...................................................................................................... 3

    Figure 3: Early and late starts project Gantt charts for Q7-1 ................................................................................. 8

    Figure 4: Project Network model for Q7-1 .............................................................................................................. 9

    Figure 5: Early Start Gantt chart for Q7-2............................................................................................................. 10

    Figure 6: Late Start Gantt chart for Q7-2 .............................................................................................................. 11

    Figure 7: Project Network model for Q7-2 ............................................................................................................ 11

    Figure 8: Early Start for Q7-3 ................................................................................................................................ 13

    Figure 9: Late Start Gantt chart for Q7-3 .............................................................................................................. 14

    Figure 10: Project Network for Q7-3. .................................................................................................................... 14

  • 7/30/2019 PPC_tutorial_2.pdf

    5/21

    iv

    List of TablesTable 1: Learning curve time computation ............................................................................................................. 6

    Table 2: Tabulation of Historical data for parametric estimation .......................................................................... 7

    Table 3: Data estimation table ............................................................................................................................... 7

    Table 4: Project Activities for Q7-1 ......................................................................................................................... 8

    Table 5: Legend of 3x3 matrix computation ........................................................................................................... 9

    Table 6: Computed 3x3 for Q7-1 ............................................................................................................................. 9

    Table 7: Project Activities for Q7-2 ......................................................................................................................... 9

    Table 8: Computed 3x3 Matrix for Q7-2 ............................................................................................................... 11

    Table 9: Project Activities for Q7-3 ....................................................................................................................... 12

    Table 10: 3x 3 Matrixes for Q7-3 .......................................................................................................................... 14

  • 7/30/2019 PPC_tutorial_2.pdf

    6/21

    1

    1. Introduction

    The tutorials are an integral part of Project Planning and Control (PPC) overall assessment.

    These are broken down into three parts. Tutorial 1 covers module 1 through module 4,

    tutorial 2 covers module 5 through module 7, and tutorial 3 covers module 8 through 11. In

    this tutorial set 2 some project techniques covered in module 5 module 7 are covered for

    course assessment in the form of tutorials. Consequently, these tutorial questions are

    answered under their respective modules.

    Module 5 deals with

    2. Solution and Explanation2.1. Module 55-1. A manufacturer of mountain bike will design and implement an automated systemfor welding bicycle frames. All works related to this project will be conducted within the

    company without any contracts to any outside organization. The system will be expected to

    handle about 100 frames per shift. Production is scheduled for two shifts per day. The system

    will be designed to weld the frame and then to check the quality of each weld using automatic

    machine vision systems. The welded frames will then be transported to the next cell for

    assembly using a conveyor system. The project should consider the training of the current

    workers as a part of the project. Most of components can be custombuilt in the company.However, some electrical and control parts should be purchased. Hence all Mechanical,

    Electrical, Electronic, Procurement, Purchasing, Human Resource, Manufacturing, Quality

    Control, Design, and other necessary departments should be involved in this project. Assume

    that you have unlimited number of staffs in all different departments/tasks for the project.

    (a)Develop an appropriate fourlevel WBSThe automated system is required to operate for than 16 hours a day assuming 8 hour/day

    work week and the operation is to produce 200 frames a day. The system therefore, is

    designed to carry out 2 operation processes assemble the frames and inspect for quality. This

    requires 3 subsystems including (1) welding module, (2) components and frames handling

  • 7/30/2019 PPC_tutorial_2.pdf

    7/21

    2

    and transfer module, and (3) quality control module. The components are to be transported to

    weld area and picked, positioned, placed and welded by welding mechanisms. After, another

    conveyor system transfers the assembled frame to QC area for quality of welds to be checked

    by machine vision system for quality control. Figure 1 shows the work breakdown structure

    (WBS) for this project.

    Figure 1: WBS of Automated system for welding bicycle frames

    (b)Develop an OBSDue to the availability of resources especially human capital, the company does not need to

    restructure its organisation and therefore project is to done

  • 7/30/2019 PPC_tutorial_2.pdf

    8/21

    3

    Figure 2: Organisational Breakdown Structure

    (c)Develop an LRCWBS

    COD

    E

    Projec

    t

    manag

    er

    Mechani

    cal

    engineer

    Design

    er

    Electri

    cal

    engine

    er

    Electron

    ics

    enginee

    r

    Softwa

    re

    engine

    er

    Purchas

    ing

    Receivi

    ng

    Human

    resour

    ces

    Fabricat

    ors &

    technici

    ans

    Quali

    ty

    contr

    ol

    Administra

    tion

    1.0 p p

    1.1 s p s s

    1.2 s p s s

    1.2.1 s p s s

    1.2.1

    .1

    p s s s

    1.2.1

    .2

    p s

    1.2.1

    .3

    s s s p

    1.2.1

    .4

    s p

    1.2.1

    .5

    p s

    1.2.2 s p s s s

    1.2.2

    .1

    p s s s s

  • 7/30/2019 PPC_tutorial_2.pdf

    9/21

    4

    1.2.3 s s s p s

    1.2.3

    .1

    p

    1.2.3

    .2

    p

    1.3 p s

    1.4 p

    1.4.1 P

    1.4.2 P

    1.4.2 P

    1.4.2

    .1

    P

    1.4.3 P

    1.5 p

    1.6 p

    5-2. Describe major guidelines for choosing an organizational structure for a project. Foreach guideline, give a good example.

    The factors for selecting an organisational structure can be outlined and explained as follow

    (Shtub et al, 2005 pp. 290 -291):

    i) Number of projects and their relative importance. The number of projects and relativeimportance of each project will determine which organisational structure to choose

    i.e. project organisational structure is suited for companies dealing with regular

    projects. Infrequent projects may be performed in traditional functional organisational

    structure.

    ii) Level of uncertainty in projects. When company is involved in a project with highlevel uncertainty a project organisational structure is advised where a project manager

    is able to control all of the resources

    iii) Type of technology used. When different technologies are used for a project withoutjustification for continuous effort throughout the project life-cycle then a matrix

    structure is preferred.

    iv) Project complexity. Projects with high complexities are carried out in goodcoordinated team environment and therefore project organisational structure is suited

    for this.

    v) Duration of projects. Short projects are handled within matrix organisation, whilelong projects can only be justified by using project organisational structure.

  • 7/30/2019 PPC_tutorial_2.pdf

    10/21

    5

    vi) Resources used by projects. Matrix organisation is well suited for projects whereresources are shared by many projects.

    vii) Overhead cost. Overheads cost can be spread over many projects that use the samefacilities and therefore a matrix organisational structure to reduce the overhead costs

    viii) Data requirements. Databases may be shared by many projects and the fact that theinformation generated is passed on the parts of organisation not involved in the

    projects, then matrix (weak) organisation structure is used.

    2.2. Module 6

    6-1. So called the process industries petrochemicals, breweries and pharmaceuticals usethe following formula to estimate the cost of the proposed projects.

    Suppose a proposed plant is to have 1.2 million cubic meter capacity. Using the past project

    of a plant with 3.5 million cubic meter capacity and a cost of $540,000, find the cost for the

    proposed plant.

    Capacity (proposed) =1.2 million cubic meter

    Capacity (past) =3.5 million meter

    Cost (past) =$540,000

    []

    6-2. Experience indicated that the firm to build 20 devices would use 200 hours to buildthe first device. According to the past experience, the time will be shortened with the increase

    of number of machines to be built. In the bid, the company is assumed the learning rate to be

  • 7/30/2019 PPC_tutorial_2.pdf

    11/21

    6

    90% and the skilled labour cost to be $50 per hour. The company wants to have benefits

    equalling 50% of the labour cost. Find the followings.

    a) The total labour hours for the whole project of 20 machines to be completed (2922 hours)

    ()

    Table 1: Learning curve time computation

    b) If all material and design are already available free of charge within the company, whatprice would the company ask for the project? (Ans. $219,118)

    The companys bidding price for the project should be the sum of labour cost and profit i.e.

    T_1 b n T_n

    200 -0.152003093 1 200

    2 180

    3 169

    4 162

    5 157

    6 152

    7 149

    8 146

    9 143

    10 141

    11 139

    12 137

    13 135

    14 134

    15 133

    16 131

    17 130

    18 129

    19 128

    20 127

    Total 2922

  • 7/30/2019 PPC_tutorial_2.pdf

    12/21

    7

    6-3. The following table shows the historic data between the number of parts and the totalamount of time taken to produce the parts. Using this date, estimate how long it will take if

    the number of parts is 200. Use the least square method. Find the correlation coefficient first

    to see whether the linear relationship exists between two: time and the number of parts. (Ans.

    311.2 hours)

    Table 2: Tabulation of Historical data for parametric estimation

    Number of parts 50 80 130 180 210 250 310 350

    Time 130 210 195 270 280 380 450 525

    Table 3: Data estimation table

    ( )( ( ) () 50 130 -145 -175 25375 21025 30625

    80 210 -115 -95 10925 13225 9025

    130 195 -65 -110 7150 4225 12100

    180 270 -15 -35 525 225 1225

    210 280 15 -25 -375 225 625

    250 380 55 75 4125 3025 5625

    310 450 115 145 16675 13225 21025

    350 525 155 220 34100 24025 48400

    Total 1560 2440 98500 79200 128650

    Check for correlation coefficient R

    R is close to 1 and therefore is a linear relationship between x and y, hence parametric

    method can be used.

    Finding

  • 7/30/2019 PPC_tutorial_2.pdf

    13/21

    8

    If number of parts = 200 units then, time is given by function;

    2.3. Module 7In this module assessment questions covering the

    7-1. A project is defined by the list of activities in the table (Ans. Duration 19 days).Table 4: Project Activities for Q7-1

    Activity Immediate predecessors Durations (days)

    A --- 7

    B --- 3

    C B 1

    D A,C 2

    E D 2

    F E 7

    G E 2

    H G 1

    I F,H 1

    a) Draw early and late start Gantt chart

    Figure 3: Early and late starts project Gantt charts for Q7-1

    b) Draw the AON network

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    A A A A A A A A A A A A A A A A

    B B B B B B B B

    C C C C

    D D D D D D

    E E E E E E

    F F F F F F F F F F F F F F F F

    G G G G G G

    H H H H

    I I I I

    LATE STARTEARLY START

  • 7/30/2019 PPC_tutorial_2.pdf

    14/21

    9

    Figure 4: Project Network model for Q7-1

    c) Fill-out the 3x3 table in the node of AON for each activityTable 5: Legend of 3x3 matrix computation

    Early Start (ES) Node (ID) Early Finish (EF)

    Total Slack (TS) Free Slack (FS)

    Late Start (LS) Duration (L) Late Finish (LF)

    Table 6: Computed 3x3 for Q7-1

    0 START 0 0 A 7 0 B 3 3 C 4

    0 0 0 0 3 0 3 3

    0 0 0 0 7 7 3 3 6 6 1 7

    7 D 9 9 E 11 11 F 18 11 G 13

    0 0 0 0 0 0 4 0

    7 2 9 9 2 11 11 7 18 15 2 17

    13 H 14 18 I 19 19 END 19

    4 0 0 0 0 0

    17 1 18 18 1 19 19 0 19

    d) Critical Pathfrom the 3x3 matrix and the Gantt charts above the critical is determinedto A-D-E-F-I

    7-2. A project is defined by the list of activities in the table (Ans. Duration is 41 days).

    Table 7: Project Activities for Q7-2

  • 7/30/2019 PPC_tutorial_2.pdf

    15/21

    10

    ActivityImmediate

    predecessorsDuration (days)

    A -- 3

    B A 6

    C A 9

    D C 7

    E B 3

    F C 4

    G D,E 5

    H F 3

    I G,H 5

    J G 14

    K I 2

    L K 2

    M L 3

    N K 1

    O J,M 3

    a) Draw early and late start Gantt chart

    Figure 5: Early Start Gantt chart for Q7-2

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41

    A A A A

    B B B B B B B

    C C C C C C C C C C

    D D D D D D D D

    E E E E

    F F F F F

    G G G G G G

    H H H H

    I I I I I I

    J J J J J J J J J J J J J J J

    K K K

    L L L

    M M M M

    N N

    O O O O

  • 7/30/2019 PPC_tutorial_2.pdf

    16/21

    11

    Figure 6: Late Start Gantt chart for Q7-2

    Slacks

    A(0), B(7), C(0), D(0), E(7), F(7), G(0), H(7), I(2), J(0), K(2), L(2), M(2), N(9), O(0)

    b) Draw the AON network

    Figure 7: Project Network model for Q7-2

    c) Fill-out the 3 x 3 table in the node of AON for each activityTable 8: Computed 3x3 Matrix for Q7-2

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41

    A A A A

    B B B B B B B

    C C C C C C C C C C

    D D D D D D D D

    E E E E

    F F F F F

    G G G G G G

    H H H H

    I I I I I I

    J J J J J J J J J J J J J J J

    K K K

    L L L

    M M M M

    N N

    O O O O

  • 7/30/2019 PPC_tutorial_2.pdf

    17/21

    12

    d) Find the critical path

    The critical path is 41 days which is consistent with the two Gantt chart

    7-3. A project is defined by the list of activities in the table (Ans. Duration is 57 days)

    Table 9: Project Activities for Q7-3

    A --- 4

    B A 5

    C A 3

    D A 10

    E B 7

    F C 6

    G C 7

    H C 3

    I D 9

    J I 3

    K J 4

    L E 4

    0 Start 0 0 A 3 3 B 9 3 C 12 12 D 19 9 E 12

    0 0 0 0 7 0 0 0 0 0 7 7

    0 0 0 0 3 3 10 6 16 3 9 12 12 7 19 16 3 19

    12 F 16 19 G 24 16 H 19 24 I 29 24 J 38 29 K 31

    7 0 0 0 7 5 2 0 0 0 2 0

    19 4 23 19 5 24 23 3 26 26 5 31 24 14 38 31 2 33

    31 L 33 33 M 36 31 N 32 38 O 41 41 END 41

    2 0 2 2 9 9 0 0 0 0

    33 2 35 35 3 38 40 1 41 38 3 41 41 0 41

    Critical PathTo find the critical path we find the longest path by adding the duration of

    each activity on that path

    A-C-F-H-I-K-L-M-O=34 days

    A-C-F-H-I-K-N=27 days

    A-C-D-G-I-K-N=32 days

    A-C-D-G-I-K-L-M-O=39 days

    A-B-E-G-I-K-L-M-O=29 days

    A-B-E-G-J-O=34 days

    A-B-E-G-I-K-N=25 days

    A-C-D-G-J-O=41 days

  • 7/30/2019 PPC_tutorial_2.pdf

    18/21

    13

    M F,G,H,I,L 9

    N M 4

    O M 8

    P N,O 3

    Q P 4

    R P 3

    S K 7

    T R,S 3

    U Q 4

    V T,U 2

    W V 4

    a) Draw early and late Gantt chart

    Figure 8: Early Start for Q7-3

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57

    A A A A A

    B B B B B B

    C C C C

    D D D D D D D D D D D

    E E E E E E E E

    F F F F F F F

    G G G G G G G G

    H H H H

    I I I I I I I I I I

    J J J J

    K K K K K

    L L L L L

    M M M M M M M M M M

    N N N N N

    O O O O O O O O O

    P P P P

    Q Q Q Q Q

    R R R R

    S S S S S S S S

    T T T T

    U U U U U

    V V V

    W W W W W

  • 7/30/2019 PPC_tutorial_2.pdf

    19/21

    14

    Figure 9: Late Start Gantt chart for Q7-3

    b) Draw the AON network

    Figure 10: Project Network for Q7-3.

    c) Fill out the table in the node of AON for each activity.Table 10: 3x 3 Matrixes for Q7-3

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57

    A A A A A

    B B B B B B

    C C C C

    D D D D D D D D D D D

    E E E E E E E E

    F F F F F F F

    G G G G G G G G

    H H H H

    I I I I I I I I I I

    J J J J

    K K K K K

    L L L L L

    M M M M M M M M M M

    N N N N N

    O O O O O O O O O

    P P P P

    Q Q Q Q Q

    R R R R

    S S S S S S S S

    T T T T

    U U U U U

    V V V

    W W W W W

  • 7/30/2019 PPC_tutorial_2.pdf

    20/21

    15

    d) Find the critical paththe critical path is determined from the 3x3 matrix with activitieswith zero total slacks (0 TS) and zero free slacks (0 FS) to be A-D-I-M-O-P-Q-U-V-W

    as in indicated above.

    3. ConclusionProjects are common in the business world are done within time and budget constraints, as

    well as within a level of uncertainties. These problems are minimised using a number of

    project management techniques such as those discussed in this report. These techniques

    include work breakdown structures & organisational breakdown structures, Gantt chart, cost

    and time estimation techniques as discussed in the report.

    0 Start 0 0 A 4 4 B 9 4 C 7 4 D 14 9 E 16

    0 0 0 0 3 0 9 0 0 0 3 0

    0 0 0 0 4 4 7 5 12 13 3 16 4 10 14 12 7 19

    7 F 13 7 G 14 7 H 10 14 I 23 23 J 26 26 K 30

    10 10 9 9 13 13 0 0 11 0 11 0

    17 6 23 16 7 23 20 3 23 14 9 23 34 3 37 37 4 41

    16 L 20 23 M 32 32 N 36 32 O 40 40 P 43 43 Q 47

    3 3 0 0 4 4 0 0 0 0 0 0

    19 4 23 23 9 32 36 4 40 32 8 40 40 3 43 43 4 47

    43 R 46 30 S 37 46 T 49 47 U 51 51 V 53 53 W 57

    2 0 11 9 2 2 0 0 0 0 0 0

    45 3 48 41 7 48 48 3 51 47 4 51 51 2 53 53 4 57

    57 END 57

    0 0

    57 0 57

  • 7/30/2019 PPC_tutorial_2.pdf

    21/21

    16

    Reference

    Dr. Lee, Sang-Heon, UniSA 2013, Project Planning and Control course materials

    Shtub, A., Bard, J.B., & Globerson, S., 2005, Project Management Processes, methodologies,

    and Economics, Prentice Hall