Project: Apartment project
Employer: TayLand Development Sdn Bhd
Contractor: PPBuilders Sdn Bhd
1.0 Original Contract Sum RM47,700,000.00
2.0 Less: P.C & Provisional Sums RM7,870,000.00
Total Builder's works RM39,830,000.00
3.0 Add: Variation works (V.O. Nos 1-4)
Total Additions 1,800,000.00RM
Total Omissions 1,196,000.00RM
Nett Additions 604,000.00RM RM604,000.00
RM40,434,000.00
4.0 Add: NSCs' final account
4.1 Lift Services 1,500,000.00RM
4.2 Air Conditioning Services 1,000,000.00RM
4.3 Electrical Services 2,100,000.00RM
4.4 Entrance Porch 1,050,000.00RM
5,650,000.00RM RM5,650,000.00
4.5 Profit and Attendance
a. Profit @ 2% of RM5,650,000.00 113,000.00RM
b. Attendance @ lump sum 111,000.00RM
224,000.00RM RM224,000.00
5.0 Contractual claims:
5.1 Loss and Expense 10,000.00RM
10,000.00RM RM10,000.00
FINAL CONTRACT VALUE RM46,318,000.00
STATEMENT OF FINAL ACCOUNT
SUMMARY OF ORIGINAL CONTRACT SUM
Item Description Omission Addition Nett Addition/
(RM) (RM) Omission (RM)
1 Preliminaries 2,250,000.00 2,250,000.00
2 Building Works 31,450,000.00 31,450,000.00
3 Local Infrastructure Works 6,130,000.00 6,130,000.00
4 P.C. and Provisional Sums 7,870,000.00 7,870,000.00
47,700,000.00 - 47,700,000.00
TOTAL CARRIED TO
STATEMENT OF FINAL ACCOUNT
SUMMARY OF VARIATION WORKS
Variation Description Omission Addition Nett Addition/
Item (RM) (RM) Omission (RM)
VO/1 Changes of toilet layout to suit 200,000.00 300,000.00 100,000.00
Employer's requirements
VO/2 New lift lobby at entrance - 400,000.00 400,000.00
VO/3 Changes from premix roads to precast 900,000.00 1,100,000.00 200,000.00
concrete paver blocks
VO/4 Omission of glass partitions 96,000.00 - (96,000.00)
1,196,000.00 1,800,000.00 604,000.00
TOTAL CARRIED TO
STATEMENT OF FINAL ACCOUNT
SUMMARY OF NSC FINAL ACCOUNTS
Varation Item Description Omission Addition Nett Addition/
(RM) (RM) Omission (RM)
NSC/1 Lift Services 1,700,000.00 1,500,000.00 (204,000.00)
Profit @ 2% 34,000.00 30,000.00
Attendance as item 34,000.00 34,000.00
NSC/2 Air Conditioning Services 1,200,000.00 1,000,000.00 (204,000.00)
Profit @ 2% 24,000.00 20,000.00
Attendance as item 24,000.00 24,000.00
NSC/3 Electrical Services 1,600,000.00 2,100,000.00 510,000.00
Profit @ 2% 32,000.00 42,000.00
Attendance as item 32,000.00 32,000.00
NSC/4 Entrance Porch 1,050,000.00 1,092,000.00
Profit @ 2% 21,000.00
Attendance @ 2% 21,000.00
TOTAL CARRIED TO
STATEMENT OF FINAL ACCOUNT 4,680,000.00 5,874,000.00 1,194,000.00
4,500,000.00 5,650,000.00
90,000.00 113,000.00
90,000.00 111,000.00
Total NSC Final Account
Total Profit
Total Attendance
SUMMARY OF LOSS & EXPENSES
Varation Item Description Omission Addition Nett Addition/
(RM) (RM) Omission (RM)
1 Additional expenses for 10,000.00 10,000.00
insurance premium
TOTAL CARRIED TO
STATEMENT OF FINAL ACCOUNT - 10,000.00 10,000.00