PowerSouth Energy Cooperative:

CCR RuleAugust 4, 2015

Page 2: PowerSouth Energy Cooperative: CCR Rule August 4, 2015

CCR Rule

• Signed by EPA Administrator December 19, 2014• Published in FR April 17, 2015• Effective date of the rule is 6 months after publication

in the FR (October 19, 2015)

Page 3: PowerSouth Energy Cooperative: CCR Rule August 4, 2015

Facilities Affected By this Rule

• New, Existing & Inactive CCR Impoundments• New and Existing CCR Landfills• Coal Combustion By-product Piles

Page 4: PowerSouth Energy Cooperative: CCR Rule August 4, 2015

6 months

• Fugitive Dust Control Plan• Weekly Impoundment Inspections• Monthly Instrumentation Monitoring• Recordkeeping, Notification, and Internet

Reporting Requirements

Page 5: PowerSouth Energy Cooperative: CCR Rule August 4, 2015

8 months

• Install a permanent ID marker adjacent to each CCR Unit

• Begin Annual Impoundment Inspections9 months

Page 6: PowerSouth Energy Cooperative: CCR Rule August 4, 2015

18 months

• Document if the Impoundment is lined with a minimum 2 foot compacted clay liner meeting a hydraulic conductivity of 1x10-7

• Prepare initial inflow design flood control system plan

• Prepare a written closure plan• Prepare a written post-closure plan

Page 7: PowerSouth Energy Cooperative: CCR Rule August 4, 2015

18 months

• Document the Initial Hazard Classification• Compile the History of Construction for each

Impoundment• Conduct Structural Stability Analysis• Safety Factor Assessments!!!

Page 8: PowerSouth Energy Cooperative: CCR Rule August 4, 2015

24 months

• Prepare an Emergency Action Plan

Page 9: PowerSouth Energy Cooperative: CCR Rule August 4, 2015

30 months

• Groundwater Monitoring and Corrective Action– Install GW monitoring system– Develop GW sampling and Analysis program– Initiate detection monitoring– Begin evaluating for SSI over background for

Appendix III constituents

Page 10: PowerSouth Energy Cooperative: CCR Rule August 4, 2015

42 months

• Complete Location Restriction Demonstration for:– Location above uppermost aquifer– Wetlands– Fault Areas– Seismic Impact Zones– Unstable Areas

Page 11: PowerSouth Energy Cooperative: CCR Rule August 4, 2015

Pressing Issues for PowerSouth

1. Closure of Ash Storage Area

2. Safety Factor Assessments for Ponds

3. Building for the Gypsum Pile??

4. Timing with the ELG Rule??

Page 12: PowerSouth Energy Cooperative: CCR Rule August 4, 2015

 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025

 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

ELG RULE & PERMIT

SCHEDULEFINAL RULE

ADEM BEGINS RENEWING PERMITS,

LITIGATION, NEW NPDES PERMIT CYCLE

w/ COMPLIANCE SCHEDULE FOR ELGsNEW NPDES PERMIT CYCLE

w/ ELG COMPLIANCE

CCR RULE COMPLIANCE

SCHEDULE

EFFECT. DATE

GROUNDWATER DATA COLLECTED AND

ANALYZED5 YEAR ALTERNATIVE CLOSURE TIMEFRAME

(CEASE PLACEMENT OF CCR) 5 YEAR CLOSURE TIMEFRAME(DEWATER AND CAP)

LOWMAN ELG/CCR COMPLIANCE TIMELINE

CCR/ELG Timeline