Page 1: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Casa 2020

Building plans for the new 2020 casitas

Recommend to print in color

Version 3.3 - 01 18 2020 11/18/2020

Page 2: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

About

Thanks for volunteering to serve in Mexico with TKA. Building homes is a transformational event for every family we serve and we’re very thankful that you have

decided to serve alongside us.

Our hope is the transformation will not only be economic and social but also spiritual. Spiritual transformation starts with intentionally making time to listen and interact with

the people of Tecate. When we do, we’ll all be continuously amazed by the results.

The families are not the only ones who will be transformed. Our students (and you) will be changed by this trip. Take time to interact with our students and one another as well.

God always creates special moments - be looking for them.

Our goal was to make these plans as simple as possible to free-up time for those meaningful interactions.

This document contains the plans for building the 2020 Casitas. For “how to instructions” see the “Casitas 2020 – How to Instruction Guide”.

For any suggestions or corrections please send an email to

Larry Ells ([email protected]) &

Rich Ghiossi ([email protected])

Rich Ghiossi and Larry Ells have developed these plans for TKA’s use

Version 3.3 - 01 18 2020 21/18/2020

Page 3: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Table of Contents

Version 3.3 - 01 18 2020 3

• Introduction• About

• Guideline and tips

• 4-Day build plan overview

• Work plan summary

• Detailed building plans

• Appendix

• Material list

• Nails

• 2-Day build plan overview

1/18/2020

Page 4: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Casa 2019: Guides and Tips “How to build your casa without going crazy”

Version 3.3 - 01 18 2020 4

Our goal with this guide is to make it as simple and as easy as possible to build this new Casa. We’ve taken a very basic step-by-step approach to keep the average group from

becoming overwhelmed with the task at hand. Most groups that build are just like yours, high on excitement and somewhat lower on construction experience. And that’s perfect,

these plans have been designed for you! They will help you finish your casa and have time to fellowship with the family and your students. As simple as the plans are, we highly

recommend that you study them before going to Mexico with your students. It’s better to be familiar with the plans and processes than to be learning in real-time. To help you better understand the plans be sure to check-out the pictures and videos of houses being build in previous years (available at www.tka.org/tecate20XX – XX=current year ). A picture is worth a 1000 words. Another helpful tip is to learn a few basic Spanish phrases. The words below

will get you started.

Helpful Spanish words

Hammer; “Martillo” (mar-TEE-yo) My name is _______: “Me llamo _______” (May-YAH-mo )

Nails: “Clavos” (KLAH-bos) Nice to meet you: “Mucho gusto” (moo-choh-goo-stow)

Door: “Puerta” (p’ware-tah) I don’t speak Spanish: “No hablo español” (No AH-blow )

Window: “Ventana” (Bain-tah-nah) What’s your name? : “Como se llama?” (ko-mo-say yah-mah)

Help! “Ayu’deme” (ah-you-da-may) Where’s the 1st Aid Kit? “ Donde’ esta el botiquin” (botee-keen)

1/18/2020

Page 5: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

4-Day Build Plan Overview

• Day One: 1. Meet the family you’re building for and pray together with everyone

2. Organize your materials and set up a safe jobsite for the next our days

3. Frame and install walls 1, 2, 3 and 4

4. Paint the exterior siding and the trim pieces (siding can be painted before or after it is installed)

• Day Two:1. Finish building all walls

2. Frame roof: Ridge, Rafters, Blocking, fascia and sheeting

3. Install rough electrical : Electrical boxes, and wiring

4. Begin Sheetrocking

5. Install windows

6. Start external trim

• Day Three: 1. Finish Sheetrock installation

2. Finish roof: Felt (black paper), sheet metal drip and shingles.

3. Close in the gable-ends of the house (the triangular panels on the front and rear walls)

4. Start internal trim

5. Mud and tape the sheetrock

• Day Four: 1. Finish taping and mudding sheetrock

2. Install front door and lockset

3. Touch-up external painting

4. Electrical trim out (switches, outlets, light fixtures and cover plates)

5. Jobsite cleanup

6. House Dedication CeremonyVersion 3.3 - 01 18 2020 5

The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different days. To be most effective, It’s important to keep everyone working (most of the time), which will require different groups working on different tasks simultaneously.

1/18/2020

Page 6: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Work plan summary 1of 3

1. ORGANIZE THE MATERIALS: (Everyone) When you get to your site, the lumber and materials are usually stacked on the cement slab. You need to clear the slab because that’s where you’ll be laying out and building the walls. This is a good job for everyone! Sort the materials by dimension and also by length (i.e., stack the 2x4 studs(8’) in a pile, and the 2x4x20 in a separate pile, siding, sheetrock, etc.). Be sure to keep the siding accessible – it will be used early on day one.

2. LOCATE THE NAILS/HARDWARE: (1 Person) Have someone talk to the Mexican family and find out where the nails are and the hardware box. Refer to hardware list for specifics.

3. SET UP SHOP: (2-3 People) Put the generator in a safe location from which 3 cords can be run to any spot in the project (typically it is near the chop saw stand).

4. PAINT THE EXTERIOR WALL PANELS: (3-6 People) Have the paint crew start painting the 4’x8’ siding. Once the siding is finished, start painting the external trim (1”x4” wood)

5. CUT THE STUDS: (2-3 people) Have the cutting crew start cutting 2x4’s to length (92 ½”) using 8’ 2X4’s (you’ll need about 50). Check the measurements of the studs. Some maybe are precut to this length. Save the 20’ and 16’ 2x4 for the top plates and sill plates.

6. LAYOUT THE WALLS AND FRAME: (Layout 1-2 People, Framing 8-12) Start with a couple of student who will serve as your layout group for the first 3-4 walls. Once the layout of the first wall is complete use most of the team (10-14 students) to build the wall, install siding and raise the wall.

7. CUT THE RAFTERS: (2-3 People) As soon as all the studs are cut, have the crew start cutting the rafters (you’ll need 26 total). Use the 10’ long 2x4. DON’T CUT THE 16’ or 20’ 2X4’s FOR RAFTERS. You’ll need these for the top plate, and fascia.

Version 3.3 - 01 18 2020 61/18/2020

Page 7: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Work plan summary 2 of 3

8. BUILD RIDGE POSTS AND RIDGE BEAM: (2 people) Have a crew cut and assemble ridge posts as per plans. Locate the 2x8x22’ (or the two 2x8, one 10’ or one 12’) the ridge beam.

9. RIDGE/RAFTER/BLOCK/FASCIA INSTALLATION: A substantial sized group can be installing rafters and the blocks between them. AFTER the blocks, install the 2x4 fascia.

10. OSB ROOF DECK INSTALLATION: (A crew of 4-6) Crew should be wearing shoes that aren’t too slippery.

11. ROOFING INSTALLATION: (6-8 People) Roofing install starts with the felt paper stapled in place…Don’t install this if you aren’t going to install shingles on the same day (wind over night may rip the sheeting off the roof)…Many a roofing crew has come back in the morning expecting to shingle over their previously installed felt paper, only to find the felt paper littering the hillside. If there is any rain or dew on the felt paper, it’s very, very slippery…

12. ROOF/GABLE OSB CUTTING: Have a crew of 2 ready to hand out OSB to your roofing crew. Cut as much as you can on the ground.

13. ELECTRICAL BOX AND ROUGH WIRING INSTALLATION: (3-4 People) This is a job to delegate to some go-getters. Have them locate all the electrical parts and install the outlet boxes as per electrical plans. You can have a secondary crew drill the holes for the wiring through the framing.

14. CUT OUT SIDING FOR WINDOWS AND INSTALL WINDOWS: Drill a pilot hole each corner of the window openings, and then connect the dots with a Sawzall! Have 2 or 3 people work together on this. The windows are installed on top of the plywood with 8d nails or screws through the flange… use caulking under the flange. Have somebody on the team on the opposite side of the wall for safety.

Version 3.3 - 01 18 2020 71/18/2020

Page 8: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Work plan summary 3 of 3

15. TRIM INSTALLATION: (2-4 people) The 1x4 trim (now painted) can be installed in the following order: Trim out the windows, put the horizontal trim on the 16’ long walls below the triangle plywood to cover the seam, install the vertical trim on the siding seams and the corners as per plan. (Leave the door trim for the door installation crew)

16. SHEETROCK INSTALLATION: (6-8 People): Don’t start until the wiring is run to the boxes! Sheet rock installation starts with the bedroom ceilings and works down the walls and out to the main room. Tape and mud the sheetrock as soon as the bedrooms are complete with sheetrock and metal corners.

17. WINDOW TRIM (INSIDE): (2-3 People); Cut and install the casing and trim aound the windows.

18. CRIPPLE STUDS/OSB INSTALL FOR GABLE ENDS OF HOUSE: (2 People) Angle-cut 2x4 for backing the OSB triangles on the 16’ long walls at the top.

19. ELECTRICAL TRIMOUT: (2-4 People) After the sheetrock is taped and mudded, install the light fixtures, light switches, outlets, circuit breaker box (if supplied) and install all the light bulbs and cover plates.

20. FRONT DOOR INSTALLATION: (2-3 people) After the sheetrock is 90% complete, install front door as per door installation guide. Install and test the lockset and give the keys to the site leader.

21. PAINT TOUCH-UPS: (2-3 PEOPLE)This is a good job for a couple of people that are getting a little burned out…it’s not hard and involved. The fascia should be painted on the outside and bottom edge. And the nails on the trim can be painted over. It’s a good idea to paint over exposed knots in the siding and on any unpainted cut ends of the trim.

22. JOBSITE CLEANUP: (1-3 People) This is a very overlooked and very necessary job. This can be done at all times especially toward the end of the workday. It allows others to work more safely and efficiently.

Version 3.3 - 01 18 2020 81/18/2020

Page 9: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Detailed Building Plans

Details Page

❑ Floor Plan 10

❑ Walls 1 & 2 framing 11

❑ U-Channel Construction 12

❑ Walls 1 & 2 with Channels 13

❑ Walls 1 & 2 Siding 14

❑ Wall 3 Framing & Siding 15-16

❑ Wall 4 Framing & Siding 17-18

❑ Wall 5 Framing 19

❑ Wall 6 Framing 20

❑ Top Plate Installation 21

❑ Ridge Post and Ridge Beam 22

❑ Ridge Beam bracket ass. 23

❑ Ridge Post Installation 24

Details Page

❑ Ridge Beam Installation 25

❑ Roof Rafter and Ceiling Joist 26

❑ Roof Blocking and Fascia 27-31

❑ Gable Installation 32-33

❑ Window Installation 34

❑ External Trim 35

❑ Roof Sheeting and Drip 36-38

❑ Roof Shingles 39

❑ Rough Electrical 40-41

❑ Sheetrock layout 42-45

❑ Finish Electrical 46-48

❑ Window & Door Trim (int) 49-50

❑ Door Installation 51-52

Version 3.3 - 01 18 2020 91/18/2020

Page 10: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 10

Top Plate

Door

Window

Window

Window

Opening

Opening

Notes:1. You’re free to move the windows or external door locations, but you will need to make those plan changes on

site. Changing the plans is not recommended, they will have a negative impact on our overall program.2. Measure the slab to ensure its 20’x16’. If it is NOT, you will need to make adjustments, but please do not

make any other changes.

Floor Plan20’

15’ 5”8’ 1”

1/18/2020

16’

Page 11: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 11

Walls 1&2

Siding side

Sheetrock side (inside) Notes:1. Use 13 studs (per wall) 92 ½” and top and bottom plates

(4 total – 2ea/wall) to exactly 20’2. Drill holes in the bottom plate for foundation bolts 3. Layout studs on 24” centers4. Create California corner on each end. Make sure the flat

side of the California corner is on the inside (sheetrock side).

5. Nail top and bottom plates to studs using 16d nails

Top Plate

California Corners

California Corners

Bottom PlateCalifornia Corners

92 ½”

1/18/2020

Sheetrock side

“A” is for view reference only

California corner (example)

Page 12: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 12

U–Channels (4 X)

Notes:1. Construct “4” U-Channels (one for each of walls 1,2,3 & 5) 2. Use 3 studs 92 ½” for each channel 3. Carefully align studs (stud bottoms should be all flush with one another)4. Nail sides with 16d nails

Side View

Bottom of studs are all flush

Nails

Nails

.

.

.

.

92 ½”

1/18/2020

Page 13: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 13

Walls 1&2 with Channel

Notes:1. Install pre-constructed U-channel into walls 1 & 2 as

shown2. Make sure the channel’s flat side is on the sheetrock

side (inside) of the wall

Top Plate

AA

AA

92 ½”

99”

1/18/2020

99”

Sheetrock side

“A” is for view reference only

Page 14: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 14

Walls 1&2 with Siding

Notes:1. Square wall before nailing siding2. Nail siding with overhang on bottom of the wall, aligning the top of the sheet with the top of

the top plate. Nail on 8 to 12” centers3. Starting at one end add one sheet at a time4. If ‘tongue and grove’ siding, ensure that the ‘tongue and grove’ overlap 5. Nail siding with 8d nails on 8-10” centers

92 ½”

1/18/2020

Page 15: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 15

Wall 3

Notes:1. Measure slab first, then cut 2, 16’ 2x4. The length should be ~185” (15’ 5”) for top and bottom plates 2. Drill holes for foundation bolts (‘hold downs’)3. Layout the wall starting from the center of wall (92 ½” for either wall end)4. Center the pre-built U-Channel on the wall’s center line5. Build the rest of the wall using 8 full length studs and frame the windows opening using the material from

the cut list

Center line

U-Channel

Top Plate

Cut list:(check window/s dimensions before cutting) Opening is designed to be ½” larger than window on all sides

4ea: 36 ½” 2ea: 42 ¾”2ea: 10 ¼”

92 ½”

10 ¼”

1/18/2020

Page 16: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 16

Wall 3

Center lineTop Plate

U-Channel

Nail sheets 2” from the edge along the center line

Notes:1. Square wall before nailing siding2. Nail 2 siding sheet to the center of the wall (grey area above) 3. Make sure the siding overhangs on bottom of the wall, aligning the top of the

sheet with the top of the top plate. 4. Nail siding sheeting on 8” to 12” centers5. Wait to install the remaining siding until later. This will allow more points of

entry into the building

92 ½”

1/18/2020

If you are using the optional metal ridge post plate don’t nail the siding in this areas yet.

Page 17: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 17

Wall 4

Notes:1. Cut 2, 16’ 2x4 to 185” (15’ 5”) for top and bottom plates2. Drill holes in the bottom plat for the foundation bolts (‘hold downs’)3. Start layout from center of wall (92 ½” for either side)4. Build the wall using 9 full length studs and frame the window and door opening using the

material from the cut list5. Door opening. Cut out bottom plate after wall is in place and secure to foundation

Top Plate

40 ¾”

36 ¼”

80 ½”

10 ½”

Cut list:(check window and door dimensions before cutting)

2ea: 80 ½”1ea: 39 ¼”1ea: 10 ½”1ea: 10 ¼”1ea: 42 ¾”2ea: 36 ½”

Door

Window

92 ½”

10 ¼”

1/18/2020

Page 18: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 18

Wall 4

Siding sheets

40 ¾”Nail sheets 2” from the edge along the center line

Notes:1. Square wall before nailing siding2. Make sure the siding overhangs on bottom of the wall, aligning the top of

the sheet with the top of the top plate Nail 2 siding sheet to the center of the wall (grey area above)

3. Nail siding sheeting on 8” centers4. Wait to install the remaining siding until later. This will allow more points of

entry into the building

92 ½”

1/18/2020

See Note on page 16

Page 19: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 19

Wall 5

Notes:1. Cut 2, 16’ 2x4 to 185” (15’ 5”) for top and bottom plates2. Start by placing the pre-built U-Channel in the center of the wall (flat part of “U” should face wall 3)3. Place all the full length studs (10 total) and nail (studs and channel)4. Frame out door openings using the material from the cut list. 5. After wall is in place, secure (nail) to walls 1&2, then secure to foundation with concrete nails provided.6. Cut out the bottom plate of the door openings after wall is in place and secure

U-Channel Centered on Wall

Door Opening

Door Opening

Cut list: (check window and door dimensions before cutting)

4ea: 80 ¾”2ea: 35”2ea: 10 ¼”

92 ½”

10 ¼” 10 ¼”

1/18/2020

~ 92 ½”

Page 20: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 20

Wall 6

Notes:1. Measure distance between walls 3 & 5. If not 97”, adjust as necessary2. Start layout from one end3. Layout studs on 24” centers (except for the far right) Install two studs on the

right end 4. Then secure to foundation with concrete nails provided.

92 ½”

1/18/2020

Wall 3Side

Wall 5Side

Double stud

Double stud

Page 21: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 21

Top Plates

Notes:1. Make sure walls are square, straight and plumb before nailing2. Install 2nd top plates in order (as shown above) starting with “1” through “7, then add others. 3. Use a 20’ 2x4 for top plate number “1”. 4. Note top plate number “1” it is not supported over the living room area

Cut list:(check dimension on building before cutting)

Wall

Second Top Plate

6ea: 94 ¼”2ea: 97”2ea: 130 ½”

20’

132 ½” ”

97”

94 ¼”

94 ¼”

3

1

2 4

5

6

7

Wall Top Plate

1/18/2020

Wall 4

Wall 3 Wall 5

Page 22: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 22

Ridge Post

Notes:1. Ridge beam is 22’ long. It’s cut from the 24’x 2”x 8” beam. 2. If you don’t have a 22’ or 24’ beam, see the appendix for how to use a 8’ and 12’ spliced together

Bottom of 2x4’s are all flush

Make 3 ridge post sets

Side are aligned (Flush with one another)

Ridge Post Construction

Ridge Beam

Notes:1. Cut 3 – 2x4’s to the dimensions above (make 3 sets)2. Sandwich and carefully align three 2x4’s3. Optional: Add 6’ metal plate (picture on left) to one side of post on two post only (the middle post can

not use the plate)4. Optional: Hurricane bracket at top of tops (pictured on right)

Add plate to 2 of 3 post (optional)

1/18/2020

2”x 8” x 22’

New

16 ½”

18 ½”

Optional BracketOn top of Post

Page 23: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

23

Ridge Beam Brackets

Notes:1. Mark bracket locations on ridge beam, positions A-K 2. Dimension from the end of the beam to location A is 12 ¾” end to center (A). It’s the same

dimension for K to the end of the beam (12 ¾”). 3. Note the distance between A & B and J & K are 23 ¼” which is different that the dimensions of

(B-J) which are 24”, center to center.4. Double check all measurement before installing bracket 5. Install brackets on both sides of ridge beam in locations A- K (22 brackets – 11 on each side)

2”x 8” x 22’

24”24”24”24” 24” 24” 24” 24”12¾” 23¼” 12¾”23¼”

CB D E F G H I J KA

Center Line

Center Line

Bracket (22) Brackets Installed

New

1/18/2020 Version 3.3 - 01 18 2020

Page 24: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 24

Ridge Post Installation “Top down view”

Notes:1. Install the 3 Ridge Post on top of the 2nd / middle top plate

1. Position Ridge Post 1 (4 ½”side) flush with outside edge of the top plate and in the middle of wall 32. Position Ridge Post 3 (4 ½”side) flush with outside edge of the top plate and in the middle of wall 43. Position Ridge Post 2 directly above wall 5. Center the post 2 by running a line between post 1 & 3

2. Make sure Ridge Posts are plumb before securing3. Toenail and/or use right angle metal brackets to secure Ridge Posts to top plate

321

Wall 4Wall 3

1/18/2020

Ridge Post (optional) flat plate is installed on the outside and under siding (both ends 1 & 3)

Page 25: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 25

Ridge Beam installation“Top down view”

Notes:1. Rest the ridge beam on top of the ridge post and then adjust into to position. Starting at one end,

make sure the first post is plumb and the beam is positioned exactly 12” from the outer edge of the post to the end of the beam and then tack beam to the post.

2. Repeat the process on the 3rd post (beam over hang should be also 12”). 3. Move to the center post once the beam is tacked to the 1st & 3rd posts. Repeat the process, making

sure the first post and third posts are plumb and then tack beam to 2nd post. 4. Finally beam secure with screws or nails

12”12”

1/18/2020

New

Page 26: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 26

Notes:1. Cut 8 blocks to support the Wall 3 & 4

gable siding2. You will use these on page 32

Roof Rafters & Ceiling Joists

Wall 3 & 4 gable supports

Notes:1. Cut 26 Roof rafter from 10’ 2 X 4” with 12* angle on one end2. Make sure all roof rafters are the same length3. Cut 7 ceiling Joist from 16’ 2X4’s to exactly 16’ (or to the measured width between walls 1 & 2).

4x - Short Block

4x – Long Block

3 ½”

10’

1/18/2020

Page 27: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 27

Roof Rafter and Ceiling Joist Installation - Step 1a“Side view – as looking at wall 1 from the outside of house”

Notes:1. Before installing, mark both top plates on walls 1&2. Also mark the ridge beam if you haven’t already.2. Install rafter A (front side), then the opposite side rafter A back side) - (This process of installing front and

then back roof joist should be followed when installing all roof rafters).3. After installing roof rafters A, install ceiling joist A. You will repeat this pattern of installing roof rafters

followed by ceiling joists for locations B, C, D and E.4. Notice all the ceiling joists should be nailed to the side of roof rafters except for ceiling joist A (which is offset

by 3 ½” between the rafter and joist). To make nailing ceiling joist A easier, install a 2x4 on top of the top plate and nail the ceiling joist A to it.

5. All roof rafters will be installed using a metal bracket. See diagram on page 29 for specific bracket details.

1/18/2020

2nd Top PlateCeiling Joist

CB D

C

E

2’24”23 ¼” 24” 24” 24” 24” 24” 24” 24” 23 ¼”

Top part of Wall 1

Ridge BeamAll Dimension are Center to Center

Roof Rafters

A

Add 2x4 (easier to nail Joist)

Page 28: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 28

Roof Rafter and Ceiling Joist Installation - Step 1b“Side view – as looking at wall 1 from the outside of house”

Notes:1. Once you have installed rafters A-E and their corresponding ceiling joists, then install the remaining roof

rafters and celling joists. 2. Start by installing rafters F, using the same process used on rafters and ceiling joist A-E

1/18/2020

Ceiling Joist

CB D

C

E F G H I J

2’24”23 ½” 24” 24” 24” 24” 24” 24” 24” 23 ½”23 ¼” 23 ¼”

Top part of Wall 1

K

Roof Rafters

A

Ridge BeamAll Dimension are Center to Center

New

Page 29: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 29

Roof rafter and ceiling joist InstallationBracket details

Roof Rafters Brackets

Joist location - right side (example)

Notes:1. Install bracket on all rafters / joist combinations A-J2. Mount brackets on inside of wall / building

1/18/2020

Page 30: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 30

Roof fascia and outer roof rafters Installation

Notes:1. Install Roof rafter fascia, A-D 2. Then install rafters, 1-4

Wal

l 4

Wall 1

Wal

l 3

132”

132”

1

2

3

4

A B

C D

1/18/2020

Page 31: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 31

Roof Blocking Installation

Notes:1. Blocks can be installed

on each side independently

20 Blocks from 2x4’s - 4ea: 21 3/4” (A’s)- 16ea: 22 1/2“ (B’s)

Wall 1

Wal

l 4

Wal

l 3

132”132”

1’ ¾”1’ ¾”

BA A

A A

B B BB B B B

B B B BB B B B

Cut list:(check dimension between rafters before cutting blocks)

1/18/2020

Page 32: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Gable Siding

Version 3.3 - 01 18 2020 32

Notes:1. Cut 2ea (right sides for each end of building)2. Cut both from one sheet of roofing material (OSB material)3. When cutting make sure the smooth side of the OSB is up (the smooth side faces out)

Gable Left side

Gable right side

Notes:1. Cut 2ea (Left sides for each end of building)2. Cut both from one sheet of roofing (OSB material) or you can also use the siding material (but

this will be more difficult to cut if you want the grooves to line-up)3. When cutting make sure the smooth side of the OSB is up (the smooth side faces out)

4”

7’ 11”

24 3/8”

4”24 3/8”

7’ 11”

1/18/2020

Smooth Side

Smooth Side

Page 33: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Gable Construction

Version 3.3 - 01 18 2020 33

Notes:1. First Install the gable blocking (short and long) in 8 locations. 2 sets (short

and long) on left and right sides of wall 3 and 4.2. Nail roof sheeting using 8d nails

1. Top along the ridge rafter2. Bottom to the top plate3. To the short and long blocking

3. Install the smooth side of the OSB facing out

1/18/2020

2 X 8

Page 34: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 34

Window Installation

1/18/2020

External Siding

Window

Window DrainsHoles

1. Drill holes in the window frame as shown below (2 holes on the both sides of window) at positions “A”

2. Place the window into the opening making sure it fit easily (there should be about a ¼” gap around the window, which is typical).

3. Also make sure the window is right side-up (drain holes are on the bottom side and on the outside of the window) and that the outside face on the window frame is flush with external side of the siding.

4. Use screws to attached the window to the wall in 4 places (“A”) making sure the window is square and plumb. Do not over tighten the screws. This could pull the window out of plumb and break the window.

A

A A

A

A

Window Hole Detail

Drill through the side of the window frame in 4

locations

Notes:

Page 35: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

A B

External Siding

Version 3.3 - 01 18 2020

External Window Trim

Notes:1. Measure length A & B.

Measurements should be about ½” less than the height of the window frame. This allows for the trim to cover the gap between the window and the siding.

2. Using rough cut trim material (1”X4”) cut left and right trim to dimensions A & B.

Notes:1. Caulk the back side of the trim

with a bead along all the edges 2. Install left and right side trim

pieces using 8d nails making sure the trim is covering the window frame by at least ¼” on both sides.

3. Measure C and D dimensions.4. Using rough cut trim material

(1’X4”) cut top trim to dimension C Plus (+) 4”

Notes:1. Center and install top and

bottom trim using 8d nails2. Caulk the back side of the

trim with a bead along all the edges

3. Make sure caulk fills the slots in the siding above the trim (see points A above)

4. Run a bead of caulk between the edge of the window and trim

C

D

Step 1 Step 2 Step 3

Window

Point A

1/18/2020 35

Page 36: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Roof Sheeting Layout

Version 3.3 - 01 18 2020 36

Wall 2

Wall 1

Wall 3

Notes:1. Start with Row 1 on one side of building, positioning and nailing all three sheets2. Install row 2 and then row 3 all on the same side 3. Move to the opposite side installing Row 1, then row 2 and 3.4. Nail using 8d nails, 8” centers5. If you have a gap along the ridge beam, either cut filler strips or double paper the ridge area.

Cut List:4ea: 4’ x 7’ 4ea: 4’ x 3’ (cut 2 per sheet)2ea: 2’ x 8’ 4ea; 2’ x 7’

6ea: 4’ x 8’ (no cutting required)

cut from 3 sheets}

Ridge Beam

Row 1

Row 1

Row 2

Row 3

Row 3

Row 2

1/18/2020

See Note 6

Page 37: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 37

Roofing Paper

Row 1

Row 2

Notes:1. After all the roof material (OSB) is nailed the next step is to cover both sides with roofing felt (black paper).2. Start by rolling out and tacking the paper across the bottom of the roof (row 1).3. Progress by adding paper one row at a time until the one side is completely covered. Remember to overlap

by at least 30% as you add rows. Typically the paper has a line to help gauge overlap4. Complete the second side, starting at the bottom and moving up the roof as you did on the first side.5. At the ridge, overlap the paper from one to the opposite side

1/18/2020

Page 38: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 38

Roofing Drip Edge

Notes:1. After all the roof is complete covered with felt the next step is to add the drip edge around all

the roof edges. 2. Nail the drip edge using 8d nails staring near the end and then every 24’ to 30” 3. When adding additional piece, overlap the drip edges by at least 6” 4. Note: Once you have installed felt and drip on one side of the roof you can start shingling that

side.

Row 2

Paper

fascia

Small Gap

Drip Edge Detail

Drip Edge

1/18/2020

Page 39: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 39

Roofing Shingles

Notes:1. On the row first only, apply two shingle layers. First lay the shingles upside down as shown above. Once

completed then install the second layer right side up . 2. When starting additional rows, offset the start so that the joints in the singles don’t line-up. 3. Continue this process across and up until each side of the roof is completely covered. 4. On the top, cut shingles into three piece and apply to as shown in diagram above. Before using cutting full

shingles,, use the partial sheets that were cut-off the sides. Save the full shingles.

Row 2

Shingle Detail

First row upside down Right side up covering first row

Ridge Beam

Shingles Right side up

Bottom Row

Ridge Cap Detail

Cut line

1/18/2020

Page 40: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 202040

Notes:1. Mount electrical breaker box and receptacle (plug) boxes. Layout /mark path of wires2. Drill holes ( ¾”) in studs and rafters as needed (place hole in middle of the studs) 3. Run wire between receptacle (plug) boxes4. Strip wires ( ½”) and bend into box. Plugs can be wired once sheetrock is installed

Wall 2

Wall 1

Wall 4Wall 3

Power In Breaker Box

Rough Electrical - Plug CircuitWires in diagram represent functional connections not

actual wire routing

1/18/2020

Page 41: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Porch Light

Version 3.3 - 01 18 202041

Rough Electrical - Lighting Circuit

Notes:1. Mount electrical boxes (lights and switches). Layout /mark path for wires.2. Drill holes ( ¾”) in studs and rafters as needed (place hole in middle of the studs) 3. Run wire to lights and switches4. Strip wires ( ½”) and bend into box. Installed the lights and switches once the sheetrock installed

Wall 2

Wall 1

Wall 4Wall 3

Light Switch

Power In Breaker Box

Light

Light

Light

Run wire across tops plates

48”

48”

Wires in diagram represent functional connections not

actual wire routing

1/18/2020

Power leg

Switch leg

Page 42: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 42

Sheetrock Step 1 - Ceilings in Bedrooms

Notes:1. Install full sheets first - (1) in each bedroom2. Cut out area for electrical box (light) – on the 44’’x96’’ sheet3. Screw sheet to ceiling joists on ~ 8” centers.

Wall 2

Wall 1

Wall 4Wall 3

Full Sheet

Partial Sheet

44” X 96”

44” X 96”

Electrical box

Electric Box

Electric Box48” X 96”

48” X 96”

1/18/2020

2 sheet44” X 48”

Cut list:(check dimensions before cutting sheetrock)

Page 43: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 43

Sheetrock Step 2 – Walls

Wall 2

Wall 1

Sheetrock Orientation:

H = Horizontal

Wall 4Wall 3H

H H

HH

H

1

2

7

4

5

9

1/18/2020

Wall 6

Wall 5

H

6

New

Measure first:Cut to 4’ x ~89”

Measure first:Cut to 4’ x ~89”

3 8

Notes:1. Install bedroom ceiling sheetrock before hanging any bedroom wall sheetrock2. Raise sheetrock off cement floor by ~1/2” off the slab (using shim)3. Nail sheet on 8” to 12” centers along top & bottom and along all studs4. Start with installing 4 sheets in position 1 & 2. All other sheets (positions 3 – 9) can be installed

without any cuts (use full sheets)

Cut around openings after installing

Cut around openings after installing

Sheetrock ledger:

Sheetrock cut areas

Sheetrock to be installed in this step

Page 44: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Wall 4Wall 3

H

Version 3.3 - 01 18 2020 44

Sheetrock Step 3 – Partial sheets (walls)

Notes:1. Recommend to install in order. Starting with 10 progress through 14

Wall 2

Wall 1

Sheetrock Orientation:

H = Horizontal

1/18/2020

Wall 6

Wall 5

Rough Cut to 5’

Measure first:Cut to 4’ x ~56”

Cut around door and window opening after installing.

H

11

H

10

H 14

H

Cut around openings after installing

Measure first:Cut to 4’ x ~62 ½”

New

Rough Cut to 5’

Cut around openings after installing

Sheetrock ledger:

Sheetrock install Previously

Sheetrock cut areas

Sheetrock to be installed in this step

13

12

Page 45: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Wall 4Wall 3

H

Version 3.3 - 01 18 2020 45

Sheetrock Step 4 – Partial sheets(walls)

Notes:1. Cut and install remaining sheet

Wall 2

Wall 1

Sheetrock Orientation:

H = Horizontal

Note A: Install sheetrock on either side of wall 6 after all the other sheetrock in the bedroom has been installed

1/18/2020

Wall 6

Wall 5

New

Measure first:Cut to size Install horizontality

Sheetrock ledger:

Sheetrock install Previously

Sheetrock to be installed in this step

Page 46: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020

Electrical (Breaker) Box

Power In(Power Leg)

Black White

House Circuits

Lights - white

Plugs - white

Plugs - black

Lights - black

Notes:1. Connect the black wire from power leg

to the input side (top) of the each breaker.

2. Connect the white wire from the power leg to the to the common plate as shown

3. Connect the black wire of the plug circuit to the output side of the breaker. Do the same for the light circuit but to the other breaker.

4. Connect the white wire of the plug and switch circuits to the common plate as shown.

5. Connect all the grounds to the grounding lugs as shown

Grounding Lugs

Common Plate

1/18/2020 46

Page 47: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 47

Finish Electrical - Lighting Circuit

Light Box Connections Switch Box Connections

Power In

Switch Leg

White Wire

Notes:1. Connect the black wire from power leg to the

white wire on the switch leg2. Connect the white wire from the power leg to

the light fixture (silver screw)3. Connect the black wire of the switch leg to the

light fixture (gold screw)4. Connect ground wires (bare copper wire)

Notes:1. Connect the black wire from the switch leg

to the switch (gold screw)2. Connect the white wire from the switch leg

to the switch (silver screw) 3. Connect the ground wire to the switch

(green screw)

Ground Wire

1/18/2020

Power Out

Page 48: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 48

Finish Electrical - Plug Circuit

Plug Connections – daisy chain Plug Connections – end

Power In Power OutPower In

Notes:1. Make-up (3) pigtails 6” long. (1) black, (1) white

and (1) ground (copper wire)2. Connect together the (2) black power wires

with the black pigtail3. Connect together the (2) white power wires

with the white pigtail4. Connect the pigtails to plug (black to gold

screw, white to silver screw and ground to green screw

Notes:1. Connect the white wire from the power leg

to the plug (silver screw)2. Connect the black wire of the power leg to

the plug (gold screw)3. Connect the ground wire of the power leg to

the plug (green screw)

White wires

Black wires Pigtails

1/18/2020

Page 49: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020

Indoor Window Trim – Part 1

Notes:1. Measure width from

sheetrock (outside surface) to window frame (~3 ½”)

2. Cut width (dimensions from step 1) from the OSB material to length of ~4’ (cut 4 pieces)

3. Measure length A & B. 4. Using the material from

step 2 cut A & B to the measured lengths

Notes:1. Install left and right side

trim using 8d nails2. Measure C and D

dimensions.3. Using the OSB material

from step 2 (Step A) cut C & D to the measured lengths

Notes:1. Install top and bottom trim

using 8d nails2.

Step A Step B Step C

1/18/2020 49

A B

Sheetrock

A B

D

C

A B

Page 50: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020

Indoor Window Trim – Part 2

Notes:1. Measure length A & B in

inches.2. Using the pine trim

material (1’X3”) cut left and right trim fascia to dimensions A & B.

3. Install left and right side using 8d nails

Notes:1. Measure C and D

dimensions.2. Using pine trim material

(1’X3”) cut top trim fascia to dimension C.

3. Using pine trim material (1’X3”) cut bottom trim fascia to dimension D Plus (+) 2”

Notes:1. Center and install top and

bottom trim fascia using finishing nails

A BWindow

Sheetrock

C

D

Step D Step E Step F

1/18/2020 50

Page 51: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Front Door Installation

Version 3.3 - 01 18 2020 51

Notes:1. Cut out bottom plate (2x4) of door opening and sweep

area before installing door.2. Remove all packing materials from the frame of the pre-

hung door before starting.3. Insert your pre-hung door into the house door opening,

aligning the door frame, flush with the inside and outside walls.

4. Insert shims along the top of the door frame at location E &F to set the door. This will help hold the door in place until the screws are installed. Once the shims are tightly installed, make sure the door frame is still flush with the inside and outside walls.

5. Drill holes ( ¼”) through the door frame into the 2x4 house framing at locations A-D, then using 3” screws anchor the door (lightly) to the house’s door frame.

6. Using a level, plumb the door on both sides (door frame on sides AB and CD exactly 90* to the floor) without stressing the door frame. You may need to loosen the screws slightly to achieve this task.

7. Once the door is plumb, insert shims tightly between the door frame and building to secure the left and right sides of the door frame.

8. Tighten the screws A-D to secure door to the house. Double check that the door is still plumb.

9. Test the door to make sure it opens easily, if you have an issue seek experienced help.

A

B

C

D

E F

1. Install the door locks per the packaged instructions

1/18/2020

Page 52: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Front Door Trim Installation

Version 3.3 - 01 18 2020 52

Notes:1. Using rough cut trim material (1”X4”)

measure and install as shown. 2. The door side of the trim should be

positioned in the middle of the door frame’s edge.

3. Caulk all trim, in the same matter as describe for the external window trim

Outside Inside

Sheetro

ck Sid

ing

Notes:1. Using pine internal trim, measure and

install as shown. 2. The door side of the trim should be

positioned in the middle of the door frame’s edge.

1/18/2020

Page 53: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Congratulations!

You have completed your house build and made a family very happy!

Version 3.3 - 01 18 2020 531/18/2020

Page 54: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Appendix

• Material list

• Nails

• 2-Day build plan overview

• Alternate designs• 2-pieces ridge beam

Version 3.3 - 01 18 2020 541/18/2020

Page 55: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Mat

eria

ls L

ist

Version 3.3 - 01 18 2020 551/18/2020

Quantity

Size

Description

Purpose

10

2x4

x20

Do

ug F

irP

late

s

22

2x4

x16

Do

ug F

irP

late

s

30

2x4

x10

Do

ug F

irR

aft

ers

104

2x4

x 8

Do

ug F

irstu

ds (

mis

c)

12x8

x22

Do

ug F

irR

idge

20

1x2

x8P

ine

Indo

or

Trim

20

4x8

x1/2

"P

lyw

oo

dS

idin

g

16

4x8

x1/2

"O

SB

Ro

of

Sheath

ing

40

1x4

x8P

ine

Outs

ide T

rim

40

4x8

x1/2

"S

heetr

ock

Sheetr

ock

1 c

om

po

und (

redi m

ix)

Mud

Sheetr

ock

2500' R

olls

: S

heet ro

ck

paper

tape

Tape

Sheetr

ock

150 lb

s B

ox:

Sheetr

ock

nails

1 5

/8"

nails

Nails

Sheetr

ock

16

Bundle

s: R

oo

fing s

hin

gle

s (>

32 s

q' /

bundle

---1

5-2

0 y

ear)

Shin

gle

sR

oo

f

3R

olls

- 3

0# f

elt

bla

ck

roo

fing p

aper

(200 s

q"/

roll)

Felt

Ro

of

150# B

ox:

1"

roo

fing n

ails

Nails

Ro

of

1B

ox

1 1

/4"

co

nstr

uctio

n s

cre

ws (

go

lds)

Ro

of

Bra

cke

tsR

oo

f

10

2x2

meta

l drip e

dge f

lashin

gD

rip e

dge

Ro

of

336"

x 36"

slid

ing w

indo

wW

indo

wW

indo

w

7G

allo

ns o

f pain

t -

blu

eP

ain

tW

alls

32 g

allo

n e

xterio

r pain

t -

white

Pain

tT

rim

1R

oll

(250'); 14/3

Ro

mex

ele

ctr

ic w

ire

Wire

Ele

ctr

ical

4P

lastic n

ail-

in r

ound b

oxe

s (

lights

)B

oxe

sE

lectr

ical

10

Sin

gle

-gang p

lastic e

lectical b

oxe

s (

outle

ts/s

witches)

Bo

xes

Ele

ctr

ical

1D

ouble

-gang p

lastic e

lectical b

oxe

s (

fro

nt do

or

sw

itches)

Bo

xes

Ele

ctr

ical

3S

ingle

-po

le/s

ingle

-thro

w e

lectr

ical s

witches (

lights

)S

witches

Ele

ctr

ical

6D

uple

x ele

ctr

ical o

utle

tsO

utle

sE

lectr

ical

7O

utle

t co

ver

pla

tes -

sin

gle

Co

vers

Ele

ctr

ical

3S

witch c

over

pla

tes -

sin

gle

Co

vers

Ele

ctr

ical

1S

witch c

over

pla

tes -

do

uble

Co

vers

Ele

ctr

ical

1bo

x ro

mex

sta

ple

s (

sm

all)

Sta

ble

sE

lectr

ical

3S

imple

light fixt

ure

sF

ixtu

re

Ele

ctr

ical

1P

orc

h li

ght

Fix

ture

sE

lectr

ical

1E

ntr

y d

oo

r -

36"

pre

hung m

eta

l cla

dF

ront D

oo

rD

oo

r

1E

ntr

y lo

cks

et w

ith d

eadbo

ltLo

cks

et

Do

or

TK

A S

upplie

d

22

Rid

ge b

eam

hangers

M

eta

lR

idge

20

Hurr

icane c

lips

Meta

lC

eili

ng jo

ist

2/3

50# B

ox:

16d v

inyl-co

ate

d s

inke

r nails

Nails

Walls

/ R

oo

f

2/3

50# B

ox:

8d v

inyl-co

ate

d s

inke

r nails

Nails

Walls

/Ro

of

25

1/2

nuts

& w

ashers

- H

old

-do

wn b

olts

Bo

ltsW

alls

20

co

ncre

te n

ails

Nails

Inte

rnal W

alls

1M

ain

ele

ctr

ical b

ox

w/ 2 -

15 a

mp b

reake

rsM

ain

E

lectr

ical

Page 56: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Mat

eria

l Usa

ge

Version 3.3 - 01 18 2020 561/18/2020

Lu

mb

er

use R

efe

ren

ce

20'

2X

4X

20 (

10)

4ea

Top

/ B

ott

om

pla

tes o

n w

all 1

&2

3ea

2n

d T

op

pla

te

3ea

Ext

ra

16'

2X

4X

16 (

22)

6ea

Top

/ B

ott

om

pla

tes o

n w

all 3

&4&

5

10ea

Ceili

ng

Jois

t

3ea

2n

d t

op

pla

tes

2ea

Facia

1ea

Ext

ra

10'

2X

4X

10 (

30)

26ea

Roof

raft

ers

4ea

Ext

ras

8'

2X

4X

8 (

104)

71ea

Stu

ds (

all w

alls)

inclu

din

g U

-Ch

an

nels

2ea

Top

an

d b

ott

om

pla

tes o

n w

all 6

6ea

Win

dow

fra

min

g (

2/

win

dow

)

9ea

Door

fram

ing

(3/d

oor)

3ea

Rid

ge p

ost

2ea

Gab

le f

ram

ing

5ea

Blo

ckin

g (

4 b

locks /

2x4

x8's

)

2ea

Facia

6ea

Ext

ras

Sid

ing

4'X

8'X

1/2

" (2

0)

18ea

Sid

ing

on

walls 1

-4

1ea

Gab

les

1ea

Ext

ras

OS

B -

roofin

g4'X

8'X

1/2

" (1

6)

15ea

Roof

sh

eetin

g

1ea

Ext

ra's

Sh

eetr

ock

4'X

8'X

1/2

" (3

6)

34ea

Walls s

heetr

ock

2ea

Ext

ra's

Page 57: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Nails

Version 3.3 - 01 18 2020 571/18/2020

Page 58: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Change Log

• V1.0 – 3 13 2019 – First public version

• V2.0 • Fixed 2 dimensions

• Page 13, Fixed the left end point of the 99” dimension

• Page 21, Fixed the top plate dimension from 99” to 97”

• Page 25, change the length of roof rafter from 10” to 9’10”

• Added Notes to pages 16,18, 23 and 26

• Change diagram on page 45

• V3.0• Fixed / enhanced notes on pages 2,4,5,6,7,8,10,28,36,37,39,41

• Enhance diagram in page 20,

• Ridge beam change to one piece 8” wide and ridge post. Pages 22, 25

• Add roof rafter bracket detail to page 23 (new page) supplies by TKA

• Change roof rafter cut detail (from 9’10” to 10’) page 26

• Add additional ceiling joists on left side (living room), page 28

• Change the stud length from 92 ¾” to 92 ½” – pages 6,11-20

• Revised sheetrock instructions, pages 43-45 (added one additional page)

• Updated the Material List page 55 (added material usage list page 56)

1/18/2020 Version 3.3 - 01 18 2020 58

Page 59: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 59

Alternate 2-piece Ridge Beam design

Notes:1. Ridge beam consist of two 2X8’s spliced together – Make sure the total length is exactly 22’ and the joint

cut to exactly 90*. Also make sure the spliced 22’ beam is completely linear (no bend at the splice). With this splice location, the splice will end between roof rafters.

2. Splice 2x8’s together using two scrap pieces of siding ( from the window cut-outs) with dimensions of 16” x 8” centered on the splice point– one for each side.

3. Use either 8p nails of 2” screws to attached the splices, at least 5 nails/screws on each side of the splice

Bottom of 2x4’s are all flush

Make 3 ridge post sets

Side are aligned (Flush with one another)

Ridge Post Construction

Ridge Beam2”x 8” x 12’2”x 8” x 10’

Notes:1. Cut 3 – 2x4’s to the dimensions above (make 3 sets)2. Sandwich and carefully align three 2x4’s3. Add 6’ plate to one side of post as shown – Optional (only two of three)

16”

Splice support

Add plate to 2 of 3 post (optional)

1/18/2020

2 ½”

Page 60: PowerPoint Presentation...The plan below provides a general outline of the tasks to be completed each day. This is only a guideline. Each site will work at different paces on different

Version 3.3 - 01 18 2020 60

2-piece Ridge Beam installation“Top down view”

Notes:1. Rest the ridge beam on top of the ridge post and then adjust into to position Starting at one

end, make sure the first post is plumb and that the beam is positioned exactly 12” from the outer edge of the post to the end of the beam and tack beam to the post.

2. Repeat the process on the 3rd post (beam over hang should be also 12”). 3. Move to the center post once the beam is tacked to the 1st & 3rd posts. Repeat the process,

making sure the first post and third posts are plumb and tack beam to 2nd post. 4. Tack with a 2’ screw and final secure with screws or nails

12”12”8’

1/18/2020

14’