powerpoint presentation · 1/10/2014 3 7 aci committee 330 documents 330r-01, guide for design and...

29
1/10/2014 1 1 1 www.conexpoconagg.com Design and Construction of Concrete Parking Areas Session W59, CONEXPO CON/AGG 2014 Wednesday, March 5, 2013, 1:00 2:30 pm Tim Cost, PE, FACI Holcim (US) Inc. Amy Miller, PE National Ready Mixed Concrete Association 2 2 www.conexpoconagg.com Upkeep & maintenance Aesthetics Lighting & safety Construction scheduling Site soils, environmental considerations Economics of alternate designs Construction costs “Life cycle” costs Concrete vs. asphalt considerations 3 3 www.conexpoconagg.com Pavement selection trends, economics Concrete is no longer more expensive to construct Life cycle considerations further enhance this value for the owner Other facility costs and operating expenses can be reduced when pavements are concrete Sustainability and environmental concerns favor concrete

Upload: dangkhuong

Post on 14-Feb-2019

221 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

1

1 1 www.conexpoconagg.com

Design and Construction of

Concrete Parking Areas

Session W59, CONEXPO – CON/AGG 2014

Wednesday, March 5, 2013, 1:00 – 2:30 pm

Tim Cost, PE, FACI Holcim (US) Inc.

Amy Miller, PE National Ready Mixed Concrete Association

2 2 www.conexpoconagg.com

• Upkeep & maintenance

• Aesthetics

• Lighting & safety

• Construction scheduling

• Site soils, environmental

considerations

• Economics of alternate

designs

– Construction costs

– “Life cycle” costs

Concrete vs. asphalt considerations

3 3 www.conexpoconagg.com

Pavement selection trends, economics

• Concrete is no longer more expensive to construct

• Life cycle considerations further enhance this value

for the owner

• Other facility costs and

operating expenses can

be reduced when

pavements are concrete

• Sustainability and

environmental concerns

favor concrete

Page 2: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

2

4 4 www.conexpoconagg.com

Pavement economics have changed!

5 5 www.conexpoconagg.com

Topics for discussion

• Pavement Design

• Jointing & Reinforcement

• Planning & Construction

• What goes wrong & how can

it be avoided?

6 6 www.conexpoconagg.com

• Design loads are truck numbers and frequencies

• Required input: – Strength of subgrade / subbase

– Concrete strength

– Traffic (truck loads and frequencies)

– Design life

• Preferred references: – ACI 330 documents

– ACPA documents

• Caution is advised:

– AASHTO documents – oriented toward highway pavements, not generally appropriate

– Don’t address most details and options for parking lots

Design resources & considerations

Not Recommended!

Page 3: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

3

7 7 www.conexpoconagg.com

ACI committee 330 documents

330R-01, Guide for Design and Construction of Concrete

Parking Lots

330.1-03, Specification for Unreinforced Concrete Parking Lots

Under development:

330.X, Guide for Design and Construction of Concrete

Site Paving for Heavy Industrial and Trucking Facilities

8 8 www.conexpoconagg.com

General Scope of 330R: Traffic, 0 to 700 trucks/day

Pavement thickness, 4” to 9”

Load transfer requirements, moderate

9 9 www.conexpoconagg.com

Load

Load

Without load transfer: Excessive deflections and flexure, performs like free edge loading

With load transfer: Deflections and flexural stresses are reduced

Definition – load transfer

• Shear strength provided at joints (or cracks) by dowels or other features, aggregate interlock, or contact friction

• Significantly reduces load-related deflection

Page 4: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

4

10 10 www.conexpoconagg.com

Concrete pavement design

• Thickness determination, based on: – Design life

– Traffic loads & frequencies

– Subgrade (or subbase) support capacity

– Concrete strength

• Jointing / reinforcement – Load transfer considerations

– Prevention of uncontrolled crack issues

• Other design questions – Grades & drainage

– Edge effects

– Panel sliding

11 11 www.conexpoconagg.com

ACI 330R-08 thickness table (Table 3.4)

12 12 www.conexpoconagg.com

Type of soil Support k, psi/in. CBR R SSV

Fine-grained soils in

which silt and clay-

size particles

predominate

Low

75 to 120

2.5 to 3.5

10 to 22

2.3 to 3.1

Sands and sand-gravel

mixtures with

moderate amounts of

silt and clay

Medium

130 to 170

4.5 to 7.5

29 to 41

3.5 to 4.9

Sand and sand-gravel

mixtures relatively

free of plastic fines

High

180 to 220

8.5 to 12

45 to 52

5.3 to 6.1

Table 3.1 – Subgrade soil types and approximate support values

Estimating k value (ACI 330R-08)

Page 5: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

5

13 13 www.conexpoconagg.com

Table B.2—Soil characteristics pertinent to parking lot pavements

Typical Design

Values

Major Divisions Letter Name

Compressi-

bility and

Expansion

Drainage

character-

istics

Compaction

EquipmentCBR Subgrade

Modulus

k, pci

GW Well-graded gravels orgravel-sand mixtures, littleor no fines

Almostnone

Excellent

Crawler-type tractor,

vibratory compactor,rubber-tired roller,steel-wheeled roller

40-80 300-500

GP Poorly graded gravels orgravel-sand mixtures, littleor no fines

Almostnone

ExcellentCrawler-type tractor,vibratory compactor,rubber-tired roller,steel-wheeled roller

30-60 300-500

d Very slight Fair to poorRubber-tired roller,sheepsfoot roller; closecontrol of moisture

40-60 300-500GM

u

Silty gravels, gravel-sand-silt mixtures

SlightPoor to

practically

impervious

Rubber-tired roller,sheepsfoot roller

20-30 200-500

GravelandGravelly

Soils

GC Clayey gravels, gravel-sand-clay mixtures

SlightPoor to

practicallyimpervious

Rubber-tired roller,sheepsfoot roller

20-40 200-500

SWWell-graded sands orgravelly sands, little or nofines

Almostnone Excellent

Crawler-type tractor,vibratory compactor,rubber-tired roller

20-40 200-400

SPPoorly graded sands orgravelly sands, little or nofines

Almostnone Excellent

Crawler-type tractor,vibratory compactor,rubber-tired roller

10-40 150-400

d Very slight Fair to poorRubber-tired roller,sheepsfoot roller; closecontrol of moisture

15-40 150-400

SM

u

Silty sands, sand-siltmixtures Slight to

medium

Poor to

practicallyimpervious

Rubber-tired roller,

sheepsfoot roller

10-20 100-300

Coarse-grained

soils

Sand and

SandySoils

SCClayey sands, sand-claymixtures

Slight tomedium

Poor topracticallyimpervious

Rubber-tired roller,sheepsfoot roller

5-20 100-300

ML

Inorganic silts and veryfine sands, rock flour, siltyor clayey fine sands orclayey silts with slightplasticity

Slight tomedium Fair to poor

Rubber-tired roller,sheepsfoot roller; closecontrol of moisture

15 orless

100-200

CL

Inorganic clays of low tomedium plasticity,gravelly clays, sandyclays, silty clays, leanclays

MediumPracticallyimpervious

Rubber-tired roller,sheepsfoot roller

15 orless

50-150Silts andClays

LL<50

OL Organic silts and organicsilt-clays of low plasticity

Medium tohigh

Poor Rubber-tired roller,sheepsfoot roller

5 orless

50-100

MHInorganic silts, micaceousor diatomaceous finesandy or silty soils, elasticsilts

High Fair to poor Sheepsfoot roller,rubber-tired roller

10 orless

50-100

CH Inorganic clays of highplasticity, fat clays

High Practicallyimpervious

Sheepsfoot roller,rubber-tired roller

15 orless

50-150

Fine-GradedSoils

Silts andClaysLL>50

OHOrganic clays of mediumto high plasticity, organicsilts

HighPracticallyimpervious

Sheepsfoot roller,rubber-tired roller

5 orless

25-100

Highly Organic Soils Pt Peat and other highlyorganic soils

Very high Fair to poor Compaction notpractical

- -

Estimating

k value

Additional

guidance: ACI 330R-08, Appendix B

Table B.1 - Soil

characteristics pertinent to

parking lot pavements

14 14 www.conexpoconagg.com

Is a subbase layer needed?

• “Subbase” is a layer of imported or improved

material between the natural site material

(subgrade) and the concrete

• Can result in higher k value for design and

slightly thinner section

– Probably can’t be justified on this basis

• May warrant consideration if:

– Construction platform is needed

– Subgrade is very poor quality

– Heavy truck traffic & load transfer concerns

– Pumping of subgrade is likely

• If used, k value for design can be adjusted

15 15 www.conexpoconagg.com

Concrete strength – MOR vs. f’c

• Compressive strength (f’c) recommended for

acceptance & QC

• Modulus of rupture (MOR, as per ASTM C78)

used in design

• Relationship can be documented for any mix via

lab testing or can be estimated:

• Use Eq. 3-1 with smooth, rounded aggregates or

when no data exists (4000 psi f’c ≈ 505 psi MOR)

• Use Eq. 3-2 when materials data supports higher

MOR’s – usually with crushed, angular

aggregates (4000 psi f’c ≈ 630 psi MOR)

MOR (psi) = cf '8 (in.-lb units) (3-1) 1

MOR (psi) = cf '10 (in.-lb units) (3-2) 1

Page 6: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

6

16 16 www.conexpoconagg.com

Traffic categories used in the thickness table

17 17 www.conexpoconagg.com

Axle-load

distributions used for

preparing Tables 3.3

and 3.4

ACI 330R-08

Appendix A, Table A.1

Axles per 1000 trucks Axle

load, kips Category A-1 Category B Category C Category D

Single axles

4 1693.31 1693.31 — —

6 732.28 732.28 — —

8 483.10 483.10 233.60 —

10 204.96 204.96 142.70 —

12 124.00 124.00 116.76 —

14 56.11 56.11 47.76 —

16 38.02 38.02 23.88 1000

18 — 15.81 16.61 —

20 — 4.23 6.63 —

22 — 0.96 2.60 —

24 — — 1.60 —

26 — — 0.07 —

Tandem axles

4 31.90 31.90 — —

8 85.59 85.59 47.01 —

12 139.30 139.30 91.15 —

16 75.02 75.02 59.25 —

20 57.10 57.10 45.00 —

24 39.18 39.18 30.74 —

28 68.48 68.48 44.43 —

32 69.59 69.59 54.76 2000

36 — 4.19 38.79 —

40 — — 7.76 —

44 — — 1.16 —

18 18 www.conexpoconagg.com

Using the thickness table

Page 7: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

7

19 19 www.conexpoconagg.com

Keeping thickness in perspective…

• “Rules of thumb” work fine for many small projects.

• Actual overload failures due to insufficient thickness are rare.

• Most thickness design is conservative for assumed loads.

• More critical issues: – Is heavier traffic channelized?

– Subgrade / subbase uniformity

– Drainage & maintenance

So what’s really important here?

20 20 www.conexpoconagg.com

Other design considerations

• Interior vs. edge loadings:

– Thickness table assumes interior loadings with moderate load transfer at joints

– Pavement edges or isolation joint sections may need thickening (or integral curbs) if they will receive wheel loads

– Thicken sections abutting flexible pavement (asphalt)

• Load transfer conditions:

– Higher levels of load transfer recommended for heavier design loads and higher truck volumes

• In-plane (sliding) forces:

– Special details suggested in areas of high vehicle turning or braking forces to prevent panel sliding

21 21 www.conexpoconagg.com

Jointing and Reinforcement

Page 8: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

8

22 22 www.conexpoconagg.com

Joint design and layout affects performance

23 23 www.conexpoconagg.com

Specimen stored in water

Drying Wetting / Drying, Heating / Cooling Shrinkage

S

welli

ng

Time

Typical concrete volume changes

24 24 www.conexpoconagg.com

Shrinkage + Restraint = Cracking

Cracking results from combined effects of restraint and

shrinkage (drying and/or thermal)…

…whenever resulting tensile stresses exceed tensile strength.

Drying shrinkage and cracking

Page 9: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

9

25 25 www.conexpoconagg.com

Dry Wet

Differential shrinkage, warping / curling of slabs

• Can result from differential moisture created by

surface drying while the slab bottom remains wet

• Can also result from differential temperature

• Can cause loss of support near panel edges,

movement and faulting at joints, mid-panel cracking

26 26 www.conexpoconagg.com

• Control the location, width,

and appearance of expected

cracks

• Facilitate construction

• Accommodate normal slab

movements

• Provide load transfer where needed

• Minimize performance

implications of any random

(unexpected) cracks

Objectives of jointing

27 27 www.conexpoconagg.com

The extent of cracking due to key

influences is somewhat predictable;

joints can be spaced accordingly. RECOMMENDED

SPACING of JOINTS

FOR CRACK CONTROL

THICKNESS, IN. SPACING, FT.

4 8-10

5 10-12

6 12-15

7 14-15

8+ 15

Exception: good design may call for even closer

joint spacings due to load transfer considerations.

Spacing of joints based on cracking tendency

Page 10: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

10

28 28 www.conexpoconagg.com

Types of joints in concrete pavement

Control joint

Construction joint

Isolation joint

formed or slipped face

29 29 www.conexpoconagg.com

Aggregate Interlock

Keyways Dowels

TIEBARS ≠ DOWELS! (not used for load transfer)

Load transfer joint details

Not Recommended!

30 30 www.conexpoconagg.com

Round dowels – generally for 8”+ thickness

Page 11: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

11

31 31 www.conexpoconagg.com

Plate dowel systems

32 32 www.conexpoconagg.com

When used, the purpose of secondary steel reinforcement is to keep cracks from opening. To do this, it must be located above the mid-thickness.

Steel reinforcement

Not Recommended!

33 33 www.conexpoconagg.com

It is almost impossible to place

rolled wire mesh in the upper

thickness where it can function.

Rebar on chairs or welded rigid

mats perform better if steel is

called for.

Secondary steel reinforcement

is often misunderstood and can

rarely be justified in flatwork that

is properly jointed.

If steel is used, it should

generally be cut at all joints!

Steel reinforcement

Page 12: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

12

34 34 www.conexpoconagg.com

Today, unreinforced concrete is the most common design

for the majority of concrete pavements. Even heavy traffic

highways are built without steel reinforcement.

Unreinforced concrete pavement

35 35 www.conexpoconagg.com

Control joint options

Control joints can be made by tooling a groove or pushing an

insert into plastic concrete, or by sawing a slot in hardened

concrete. The depth of the void must be at least 1/4 of the

slab thickness to weaken the section enough to make it crack.

36 36 www.conexpoconagg.com

Tooled control joints

Advantages: • Simplest to make

• Most reliable crack initiation

Disadvantages: • Most noticeable joint

• Not smoothest for rolling wheels

• Not designed for sealers / fillers

Page 13: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

13

37 37 www.conexpoconagg.com

Saw-cut control joints

Advantages:

• Makes best sealant reservoir

• Not as noticeable

• Smooth ride

Disadvantages:

• Timing critical to success

• Least reliable crack initiation with gravel aggregates

• More expensive to make

38 38 www.conexpoconagg.com

Saw-cut joints must be

made within 4-12 hours

after final finishing

This joint was sawed soon enough

This one was sawed too late

Timing of joint sawing – a critical factor

39 39 www.conexpoconagg.com

Early entry “dry cut” saws

• Designed to initiate cracks

with a shallow cut made

much earlier than with

wet-cut saws

• Timing - the “window of

opportunity” is 1 to 2 hours

if shallow cuts are used

• Also used to cut t/4 or t/3

in normal timing windows

Page 14: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

14

40 40 www.conexpoconagg.com

Construction joints are used between separate concrete

placements, typically along placement lane edges. They may

use keyways or other features designed for load transfer.

Use of construction joints

Butt joints are

recommended for

most parking lots

where load transfer

needs are minimal.

Keyways are now only

recommended for entrance

drive / street longitudinal

construction joints ≥ 10”

thick and should be tied.

41 41 www.conexpoconagg.com

Keyways as detailed in earlier documents

D

0.1D

0.2D

1:4 Slope

0.2D

Trapezoidal Half-round

This detail is no longer included in

ACI 330R or any ACPA references!

Not Recommended!

42 42 www.conexpoconagg.com

Typical keyway joint performance issues

Page 15: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

15

43 43 www.conexpoconagg.com

…are sometimes called expansion joints but should generally not be used to provide for expansion. They provide no load transfer and should not be used as regularly spaced joints in a joint layout. Their proper use is to isolate fixed objects, providing for slight differential settlement without damaging the pavement.

Isolation joints

44 44 www.conexpoconagg.com

Improper use of isolation joints

• If isolation joints are used as routine joints: – Slabs “crawl” as isolation

joints compress

– Adjacent control joints open

and fill with debris

– No load transfer

– Failure of sealants

– Water intrusion

• Common issue in construction practice

45 45 www.conexpoconagg.com

Common details for isolation of fixtures

Diagonal

Isolation joint

Inlet

Isolation joint

Circular

Isolation joint

Square with Fillets

Isolation joint

Inlet - Round

Isolation joint

Telescoping Manhole

No boxout or isolation joint necessary

None

Isolation joint around perimeter

Square

Isolation joint

Reinforcing bars recommended to hold cracks tight

Page 16: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

16

46 46 www.conexpoconagg.com

Examples - isolation of fixtures

47 47 www.conexpoconagg.com

• In many cases, control joints

and construction joints may

be used interchangeably,

depending on the preferred

direction of paving lanes.

• Load transfer requirements

must be considered.

• Isolation joints should be

avoided in traffic areas

except where differential

movement or settlement must

be accommodated (use

thickened edges).

The designer should prepare the jointing plan!

48 48 www.conexpoconagg.com

Joint layout guidelines

• Things to Do

– Match existing joints or cracks

– Cut at the proper time

– Place joints to meet in-

pavement structures

– Adjust spacings to avoid

small panels or angles

– Intersect curves radially,

edges perpendicular

– Keep panels square

• Things to Avoid

– Slabs < 1 ft. wide

– Slabs > 15 ft. wide

– Angles < 60º (90º is best)

– Creating interior corners

– Odd Shapes (keep slabs

square)

– Offset (staggered) joints

– Isolation (unthickened) joints

in traffic areas

Page 17: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

17

49 49 www.conexpoconagg.com

Jointing layout – dealing with corners, acute angles, edges with extreme curvature

50 50 www.conexpoconagg.com

Sealing of joints

• Topic of some debate

• Sealants must be maintained and drainage

design must be effective

• Low cost poured sealants not durable

• Some joint types difficult to seal

• Factors to consider in whether or not to

seal joints:

– Traffic level

– Soil types & local performance

– Subbase use

– Presence of wind blown debris

51 51 www.conexpoconagg.com

Concrete Materials

Page 18: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

18

52 52 www.conexpoconagg.com

Concrete materials – what to specify / order

• Strength – Consistent with design

– More is not necessarily better

• Durability – Entrained air for freeze/thaw

– Sulfates, AAR considerations if applicable

• Other performance requirements – Economy

– Workability

– Lowest shrinkage potential

• Water content, slump • Aggregate size & grading

53 53 www.conexpoconagg.com

Entrained air • Used to provide freeze-

thaw durability

• Requires extra QC attention, testing

Freeze-thaw

severity

zones severe

moderate

negligible

54 54 www.conexpoconagg.com

• Pozzolanic benefits – Lower heat of hydration, reduced slump loss – Consumption of COH, less efflorescence – Higher ultimate strengths – Greater overall cementitious efficiency

• Improved concrete rheology and paste density – Lower water demand – Improved pumping & finishing – Reduced porosity & improved pore character – Improved consolidation & formed finishes

• Other chemistry interactions, durability benefits – Lower permeability – Sulfate resistance – Mitigation of aggregate reactivity

• Environmental benefits – Recycled materials – LEED, etc. – Reduced consumed energy to produce – Lower related CO2 emissions – Enhanced reflectivity with GGBFS

Supplemental cementitious materials – “SCMs”

Page 19: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

19

55 55 www.conexpoconagg.com

Construction best practices, options

56 56 www.conexpoconagg.com

Pre-construction conference

• Indispensable in avoiding

problems and making the

project go smoothly

• Should cover all functions

and responsibilities

• Improves project quality

• Saves time and money

57 57 www.conexpoconagg.com

• Compact with proper moisture content

• Check density with testing or proof rolling

• Fine grading

• Remove and replace soft or unsuitable soils

• Consider subgrade stabilization when

extremely poor soils are encountered

• Insure adequate surface drainage

• Water table depth - well below subgrade

• Uniformity is the key!

Subgrade preparation

Page 20: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

20

58 58 www.conexpoconagg.com

Drainage and subgrade issues: #1 cause of failures

59 59 www.conexpoconagg.com

Compact granular

materials near

optimum moisture,

plastic soils slightly

above optimum.

106

103

94

97

100

109

8 10 12 14 16 18 20 22

Max. Density

Opt. Moisture

Density,

lb

/ft3

Moisture Content, %

95% Density

3% 1%

Compaction and moisture-density relationship

60 60 www.conexpoconagg.com

• Major projects – use a

qualified testing firm

• Small projects & quick

checks – proof rolling

– Use if testing is

unavailable or

impractical, or to

supplement testing

– Use a loaded truck

– Establish and enforce a

criteria

– Can help to locate soft

spots, stump holes

Monitoring density

Page 21: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

21

61 61 www.conexpoconagg.com

Grading tolerances for the subgrade / subbase

• Deviations contribute to variations in concrete thickness

and influence drag restraint & cracking

• Suggested tolerances: within + ¼”, - ½” of design grade

• Tight tolerances are more critical for thin slabs

62 62 www.conexpoconagg.com

Forming & placement sequencing

Of the different

sequencing options

used, the method of

paving in alternate

lanes (lower photo)

has been found most

efficient and also

helps minimize the

adverse effects of

shrinkage.

Not Recommended!

63 63 www.conexpoconagg.com

Alternate lane slip-formed placement

Page 22: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

22

64 64 www.conexpoconagg.com

Should the subgrade be dampened prior to

concrete placement?

• No longer recommended

• Drier subgrades help to

equalize concrete

moisture loss, minimizing

slab curling

• ACI 330R-08:

“normally dry” subgrade

• Consider circumstances

Not Recommended!

65 65 www.conexpoconagg.com

• Good strikeoff / screeding critical for surface tolerances

• Select slump based on paving equipment

• Avoid too much vibration in one place

• Limit use of bull float; straight-edging is preferred where vehicle speed > 5 mph

• Avoid: troweling, use of jitterbugs, any finishing steps while bleedwater is rising

• Jointing - saw within critical time window; make cuts / grooves at least 1/4 of thickness

• Texturing - use plenty!

• Curing - timing and effectiveness are critical

Concrete placement & finishing precautions

66 66 www.conexpoconagg.com

Simple strikeoff equipment

Page 23: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

23

67 67 www.conexpoconagg.com

Basic vibrating screeds

68 68 www.conexpoconagg.com

More sophisticated placement equipment

69 69 www.conexpoconagg.com

Construction of “roll-over” integral curbs

Page 24: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

24

70 70 www.conexpoconagg.com

Bull floats vs. straight edges

71 71 www.conexpoconagg.com

Residential finishing methods – not for paving!

Not Recommended!

72 72 www.conexpoconagg.com

No power trowels!

Not Recommended!

Page 25: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

25

73 73 www.conexpoconagg.com

Thickened edges

Concrete at pavement edges or along isolation

joints that will support wheel loads should be

thickened to provide extra support.

74 74 www.conexpoconagg.com

Example – thickened edge

75 75 www.conexpoconagg.com

Providing surface texture

Page 26: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

26

76 76 www.conexpoconagg.com

Avoiding excessive cracking influences

• Monitor evaporation rate & take

appropriate steps when extreme

• Effective curing

• Repair subgrade ruts, minimize

other subgrade drag influences

• Effective curing

• Extra precautions in cool

weather or with slow strength-

gain mixes: apply curing sooner

and longer…

• Adequate strength before

opening to traffic

• Effective curing

77 77 www.conexpoconagg.com

Curing effects on performance

• Reduces cracking

– Delay of drying

shinkage

– Minimizes warping

• Improves durability and

lowers permeability

• Facilitates most rapid

strength gain

78 78 www.conexpoconagg.com

• Spray membrane curing

compound - ASTM C 309,

white pigmented preferred

• Timing is critical - spray

immediately after finishing

• Suggested application rate: – Maximum coverage: 200 ft2 / gal

– Higher rate (less coverage) for windy

or dry conditions

Curing compound – most common method

Page 27: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

27

79 79 www.conexpoconagg.com

• Rules of thumb:

– Automobile traffic in 3 days

– Truck traffic in 7 days

• Opening can be earlier if adequate strength has developed (2500+ psi)

• Fast track techniques can be used to open to traffic in just a few hours

Opening to traffic

80 80 www.conexpoconagg.com

Too soon.

Opening to traffic

81 81 www.conexpoconagg.com

Other information contained in ACI 330R

• Inspection and testing

• Maintenance and repair

• Suggested joint details

• Concrete overlays

– Over existing concrete

– Over asphalt

• Parking lot geometrics

Page 28: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

28

82 82 www.conexpoconagg.com

Parking lot geometrics

Small cars

Angle

Interlock

reduction Overhang

Vehicle

projection Aisle width Module widths

θ i o VP AW W1 W2 W3 W4 W5

45 deg 2 ft, 0 in. 1 ft, 5 in. 15 ft, 3 in. 11 ft, 6 in. 26 ft, 9 in. 42 ft, 0 in. 40 ft, 0 in. 38 ft, 0 in. 39 ft, 2 in.

50 deg 1 ft, 10 in. 1 ft, 6 in. 15 ft, 9 in. 12 ft, 0 in. 27 ft, 9 in. 43 ft, 6 in. 41 ft, 8 in. 39 ft, 10 in. 40 ft, 6 in.

55 deg 1 ft, 8 in. 1 ft, 8 in. 16 ft, 1 in. 12 ft, 10 in. 28 ft, 11 in. 45 ft, 0 in. 43 ft, 4 in. 41 ft, 8 in. 41 ft, 8 in.

60 deg 1 ft, 5 in. 1 ft, 9 in. 16 ft, 4 in. 13 ft, 4 in. 29 ft, 8 in. 46 ft, 0 in. 44 ft, 7 in. 43 ft, 2 in. 42 ft, 6 in.

65 deg 1 ft, 2 in. 1 ft, 10 in. 16 ft, 6 in. 14 ft, 0 in. 30 ft, 6 in. 47 ft, 0 in. 45 ft, 10 in. 44 ft, 8 in. 43 ft. 4 in.

70 deg 1 ft, 0 in. 1 ft, 11 in. 16 ft, 7 in. 14 ft, 10 in. 31 ft, 5 in. 48 ft, 0 in. 47 ft, 0 in. 46 ft, 0 in. 44 ft, 2 in.

75 deg 0 ft, 9 in. 1 ft, 11 in. 16 ft, 6 in. 16 ft, 0 in. 32 ft, 6 in. 49 ft, 0 in. 48 ft, 3 in. 47 ft, 6 in. 45 ft, 2 in.

90 deg 0 ft, 0 in. 2 ft, 0 in. 15 ft, 6 in. 20 ft, 0 in. 35 ft, 6 in. 51 ft, 0 in. 51 ft, 0 in. 51 ft, 0 in. 47 ft, 0 in.

Large cars

Angle

Interlock

reduction Overhang

Vehicle

projection Aisle width Module widths

θ i o VP AW W1 W2 W3 W4 W5

45 deg 2 ft, 4 in. 2 ft, 1 in. 18 ft, 0 in. 13 ft, 0 in. 31 ft, 0 in. 49 ft, 0 in. 46 ft, 8 in. 44 ft, 4 in. 44 ft, 10 in.

50 deg 2ft, 1 in. 2 ft, 4 in. 18 ft, 8 in. 13 ft, 8 in. 32 ft, 4 in. 51 ft, 0 in. 48 ft, 11 in. 46 ft, 10 in. 46 ft, 4 in.

55 deg 1 ft, 10 in. 2 ft, 5 in. 19 ft, 2 in. 14 ft, 8 in. 33 ft, 10 in. 53 ft, 0 in. 51 ft, 2 in. 49 ft, 4 in. 48 ft, 2 in.

60 deg 1 ft, 8 in. 2 ft, 7 in. 19 ft, 6 in. 16 ft, 0 in. 35 ft, 6 in. 55 ft, 0 in. 53 ft, 4 in. 51 ft, 8 in. 49 ft, 10 in.

65 deg 1 ft, 4 in. 2 ft, 9 in. 19 ft, 9 in. 17 ft, 0 in. 36 ft, 9 in. 56 ft, 6 in. 55 ft, 2 in. 53 ft, 10 in. 51 ft, 0 in.

70 deg 1 ft, 1 in. 2 ft, 10 in. 19 ft, 10 in. 18 ft, 4 in. 38 ft, 2 in. 58 ft, 0 in. 56 ft, 11 in. 55 ft, 10 in. 52 ft, 4 in.

75 deg 0 ft, 10 in. 2 ft, 11 in. 19 ft, 9 in. 20 ft, 0 in. 39 ft, 9 in. 59 ft, 6 in. 58 ft, 8 in. 57 ft, 10 in. 53 ft, 8 in.

90 deg 0 ft, 0 in. 3 ft, 0 in. 18 ft, 8 in. 24 ft, 8 in. 43 ft, 4 in. 62 ft, 0 in. 62 ft, 0 in. 62 ft, 0 in. 56 ft, 0 in.

1

83 83 www.conexpoconagg.com

Summary – so what all is really important here?

• Subgrade support, subbase

• Proper thickness

• Jointing for crack control

• Load transfer design

• Pavement drainage design

• Materials & methods refined

to minimize shrinkage and

warping

• Special attention to curing

84 84 www.conexpoconagg.com

Page 29: PowerPoint Presentation · 1/10/2014 3  7 ACI committee 330 documents 330R-01, Guide for Design and Construction of Concrete Parking Lots 330.1-03, Specification for …

1/10/2014

29

85 85 www.conexpoconagg.com

Questions?

Tim Cost, PE, FACI Holcim (US) Inc.

[email protected]

Amy Miller, PE National Ready Mixed Concrete Association

[email protected]

Design and Construction of Concrete Parking Areas