power scenario in india · power scenario in india important for global competition. need of the...
TRANSCRIPT
M/S. NEERJA MATHUR
DIRECTOR (PLANNING WING)
CENTRAL ELECTRICITY AUTHORITY
POWER SCENARIO
IN
INDIA
important for global competition.
need of the day.
?POWER or ELECTRICITY critical infrastructural component for multidimensional growth and basic human need
?Reliable and quality power at competitive rates to Indian industry
?Clean and Green Sustainable Power
?Energy Security
POWER SCENARIO
19
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
20
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
POWER SECTOR - AN OVERVIEW
??Electricity - ‘Concurrent Subject’ : joint responsibility of State and Central Governments.
??Bulk of transmission and distribution functions with State Utilities.
??Private sector - small presence in Distribution and making entry into Transmission.
??Conventional Generation - blend of thermal, hydro and nuclear sources.
??Coal based thermal power plants and in some regions hydro power plants - mainstay of electricity generation.
??Oil, natural gas and nuclear power accounts for smaller proportion of power.
??Emphasis also on non-conventional energy sources i.e. solar, wind, biogas and tidal.
??Captive power plants being encouraged to supply surplus power to Grid.
POWER SECTOR - AN OVERVIEW
GROWTH OF INSTALLED GENERATING CAPACITY IN INDIA
(figs. in MW)
'47 '55 '61 '66 '74 '80 '85 '90 '95 '02 '03 '04 '06 '07 '12
(Projeced)
Source: CEA* includes Likely capacity Addition of 14000
MW from Renewables during 11 th plan period
Thermal Nuclear
Hydro Renewable
1,3
62
2,6
95
4,6
53
9,0
27
16,6
64
28,4
48
42,5
85
81,1
71
63,6
36
1,0
5,0
46
1,0
7,8
77
1,1
8,4
26
1,2
4,2
87
2,2
4,9
07
*
1,3
2,3
29
21
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
535759
61
68
7173
69
2000 2003 2005 2008
Year
% of Coal basedCapacity in TotalGenerating Capacity
% of Coal basedGeneration in TotalGeneration
Share in %
(app.)
COUNTRY’S SHARE OF COAL IN TOTAL POWER GENERATION AND
INSTALLED CAPACITY OVER YEARS
CENTRAL ELECTRICITY AUTHORITY
MINISTRY OF POWER
GOVERNMENT OF INDIA
ALL INDIA PLF (%) OF THERMAL POWER STATIONS(COAL AND LIGNITE BASED)
Source: CEA
56.555
56.5
53.955.3
57.1
60
64.6
67.369
69.9
72.7
74.374.8
72.2
6164.4 64.7
53.2
63
52.4
76.878.6
48
53
58
63
68
73
78
Years
CHART : 13
MAJOR LEGISLATIVE / POLICY INITIATIVES OF
GOVERNMENT
??1998- Electricity Regulatory Commission Act
??1998 - Electricity Laws (Amendment) Act
??2001-- Electricity Conservation Act
??2003- Electricity Act
??February ,2005- National Electricity Policy
??January 2006- National Tariff Policy
??August 23, 2006 - Rural Electrification Policy
??August 2006- Integrated Energy Policy.
??January 2007- Report submitted by Working Group on Power for 11th Plan constituted by Planning Commission.
??August,2007 - National Electricity Plan notified.
22
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
??Access to electricity for all households in next 5 years.
??Availability of power on demand to be fully met by 2012
??Energy shortage and peaking shortage to be overcome by providing adequate spinning reserves
??Reliability and quality of power to be supplied in efficient manner .
??Electricity Sector to achieve financial turnaround and commercial viability
??Consumers’’ interests to be accorded top priority.
–NATIONAL ELECTRICITY POLICY THE WAY FORWARD
NATIONAL ELECTRICITY POLICY - ENCOURAGING PRIVATE PARTICIPATION
NATIONAL ELECTRICITY POLICY -- ENCOURAGING PRIVATE PARTICIPATION
??Competition encouraged Competition encouraged -- to bring significant benefit to to bring significant benefit to consumersconsumers
??Guidelines for competitive bidding issued by Government in Guidelines for competitive bidding issued by Government in January,2005.January,2005.
??Role of private participation in generation, transmission and Role of private participation in generation, transmission and distribution to become increasingly critical in view of rapidly distribution to become increasingly critical in view of rapidly growing investment needs. growing investment needs.
??Central and State Governments to develop workable and Central and State Governments to develop workable and successful models for public private partnership.successful models for public private partnership.
??Special mechanisms to be created to encourage private investmentSpecial mechanisms to be created to encourage private investmentin transmission sectorin transmission sector
NATIONAL ELECTRICITY POLICY - ENCOURAGING PRIVATE PARTICIPATION
NATIONAL ELECTRICITY POLICY - ENCOURAGING PRIVATE PARTICIPATION
??Private Sector participation in distribution encouraged for Private Sector participation in distribution encouraged for achieving requisite reduction in T&D losses and improving achieving requisite reduction in T&D losses and improving quality of service to consumerquality of service to consumer
??Multi Year tariff frameworkMulti Year tariff framework -- important structural incentive important structural incentive to minimize risks for utilities and consumers, promote to minimize risks for utilities and consumers, promote efficiency and rapid reduction of system losses.efficiency and rapid reduction of system losses.
??Competition through concept of multiple licensees in same Competition through concept of multiple licensees in same area through their independent distribution systemarea through their independent distribution system
23
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
??Electricity Act & National Electricity Policy mandates non--discriminatory open access in transmission and, in phases in distribution.
??Respective State Regulatory Commissions to facilitative framework for open access.
??Well planned and strong transmission and distribution system to ensure optimal utilization of transmission capacities
??Would facilitate achieving objective of cost effective delivery of power.
??Distribution reform - key to long term sustainability of the power sector.
OPEN ACCESS IN TRANSMISSION AND DISTRIBUTION
INSTALLED CAPACITY IN THE COUNTRY (as on 30th September, 2008)
TOTAL IC -1,45,627 MW
R.E.S.,
12195
8.4%
NUCLEAR
4120
2.8%
THERMAL
93115
64%
HYDRO,
36198,
24.8%
EVOLUTION OF UNIT SIZE OF EVOLUTION OF UNIT SIZE OF COAL BASED POWER PLANTSCOAL BASED POWER PLANTS
??Largest unit size in 1950-30 MW
??First 200 MW unit at Obra TPS in 1977
??First 500 MW unit at Trombay in 1984
??Committee constituted by CEA recommended 800 to 1000 MW unit size in future
??In 11th Plan and beyond 800/660 MW units planned
CENTRAL ELECTRICITY AUTHORITY
MINISTRY OF POWER
GOVERNMENT OF INDIA
Details of IC of renewable energy sources
(As on 31.03.2008)
11,125.41TotalTotal
87.87Solar power & othersSolar power & others
2034.07Small Hydro Power Small Hydro Power
1325.63Biomass Power & Biomass Power & Biomass Biomass Gasifiers
7666.84Wind PowerWind Power
Installed Capacity ( MW)Installed Capacity ( MW)Sources / SystemsSources / Systems
Total
Solar power & others
Small Hydro Power
Biomass Power & Biomass
Wind Power
Installed Capacity ( MW)Sources / Systems
TRANSMISSION & NATIONAL GRID TRANSMISSION & NATIONAL GRID
??Development in a phased manner – commensurate with
generation / load growth.
??Economy in generation through efficient transmission
??Conservation of Right-of-Way
??In forest areas with rich flora & fauna, construction of
lines with high towers / high voltage rating – leading
to reduced forest cutting.
??High capacity lines (HVDC & 765 kV)
24
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
38.6 38.6 538/538538/538170170500 500
38.4 38.4 535/535535/535150150250 250
37.8 37.8 535/535535/535150150210210
3535--36 36 535/535535/535130130110/120/140110/120/140
3232--33 33 53553590906060--100 100
~31 ~31 48248260603030--50 50
(%) (%) ooC C kg/cmkg/cm22
Gross Gross Efficiency Efficiency
(HHV )(HHV )
MS/RH MS/RH Temp Temp
MS. Pr MS. Pr Unit Size Unit Size
38.6 38.6 538/538538/538170170500 500
38.4 38.4 535/535535/535150150250 250
37.8 37.8 535/535535/535150150210210
3535--36 36 535/535535/535130130110/120/140110/120/140
3232--33 33 53553590906060--100 100
~31 ~31 48248260603030--50 50
(%) (%) ooC C kg/cmkg/cm22
Gross Gross Efficiency Efficiency
(HHV )(HHV )
MS/RH MS/RH Temp Temp
MS. Pr MS. Pr Unit Size Unit Size
PREVAILING UNIT SIZES IN INDIA
210/250 & 500 MW Units Constitute Over 80% of the Total Capacity
25
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
National Grid
1950-60’s
1970-80s
2000 onwards
Local
1950’s
EVOLUTION OF ELECTRIC GRID
State Grids by SEBs
Regional Grids with ATS of Central Generation
Shift from Regional self sufficiency concept to National level Planning
Interconnecting Regional Grids with HVDC
1990s
Towards National Grid System
778
3938
5787
9560
0
2000
4000
6000
8000
10000
12000
2004-05 2005-06 2006-07 2007-08
Number of Transactions
16441
22526
30000
23134
0
5000
10000
15000
20000
25000
30000
35000
2004-05 2005-06 2006-07 2007-08
Energy Traded
En
erg
yin
Millo
nU
nit
s
1129 % increase in number ofapproved transactions in Short -term Open Access at Inter State level
82% increase in volume of energy traded in Short-term Open Access at Inter State level
Encourage Competition and Choice by facilitating electricity trade
BENEFITS OF NATIONAL GRIDBENEFITS OF NATIONAL GRID
(Contd. ….)
Security and Reliability enhanced by reduction in number of griddisturbances
Grid Disturbances
74
53
72 1 0 03 4 0 0 0 0 0
0
20
40
60
80
100
2001-022002-032003-042004-05 2005-062006-072007-08
Year
Nos.
Minor Major
BENEFITS OF NATIONAL GRIDBENEFITS OF NATIONAL GRID (Contd. ….)
26
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
Development of Transmission Voltages Levels
??132 kV Highest level at the time of Independence
??Introduction of 220 kV in 1960
??400 kV in 1977
??HVDC back--to-back link in 1989,
??500kV, HVDC bi -pole line in 1990
??765 kV transmission line from 2000 onwards.
293,210197,927150,480119,290
79,601
36,142
3,138
409
At the end of VIIIth Plan i.e.
March ’97
96,993
49,378
3,138
971
At the end of IXth Plan i.e. March ’02
114,629
75,722
5,872
1,704
At the end of Xth Plan i.e. March ’07
ckm
ckm
ckm
ckm
Unit
150,000230/ 220 kV
125,000400 kV
11,078HVDC +/- 500 kV
7,132765 kV
Target at the end of XIth
Plan i.e. March ’12
Transmission lines
CUMULATIVE GROWTH IN TRANSMISSION SECTOR
119,290
150,477197,927 209,072
293,210
1997 2002 2007 2008 ( uptoFeb )
2012 (proj.)
GROWTH OF HIGH VOLTAGE TRANSMISSION LINKS
Source: CEA
Cumulative HT Lines 220 KV and above (in ckm)
27
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
PER CAPITA CONSUMPTION OF ELECTRICITY IN INDIA
Source: CEA
176
348
559632 672 704
1000
613
1980-
81
1990-
91
2000-
01
2004-
05
2005-
06
2006-
07
2007-
08
2011-
12
kWh/year
(Projected)
As per UN Methodology (Gross Electrical Energy Availability / Population)
Growth Pattern
??Country facing energy shortage of 9.8% and peak shortage of 16.6% (2007--08).
??As per Census 2001, only about 56% of households have access to electricity, with rural access being 44% and urban access about 82%.
??Annual per capita consumption about 704 kWh as against world average of about ~2400 KWh.
STATUS OF POWER SECTOR
ACTUAL POWER SUPPLY POSITION OF THE COUNTRY (2007-08)
Peak (MW)Peak (MW) Energy (MU)Energy (MU)
RequirementRequirement 1,08,8861,08,886 7,37,0527,37,052
AvailabilityAvailability 90,79390,793 6,64,6606,64,660
((--)Shortage/ )Shortage/ (+)Surplus(+)Surplus
((--)18,093)18,093 ((--)72,392)72,392
(%)(%) ((--)16.6)16.6 ((--)9.8)9.8
Peak (MW)Peak (MW) Energy (MU)Energy (MU)
RequirementRequirement 1,08,8861,08,886 7,37,0527,37,052
AvailabilityAvailability 90,79390,793 6,64,6606,64,660
((--)Shortage/ )Shortage/ (+)Surplus(+)Surplus
((--)18,093)18,093 ((--)72,392)72,392
(%)(%) ((--)16.6)16.6 ((--)9.8)9.8
28
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
ACTUAL POWER SUPPLY POSITION OF THE COUNTRY (April,08-September,08)
Peak (MW)Peak (MW) Energy (MU)Energy (MU)
RequirementRequirement 1,09,9621,09,962 3,81,9353,81,935
AvailabilityAvailability 93,04693,046 3,42,5493,42,549
((--)Shortage/)Shortage/
(+)Surplus(+)Surplus
((--) 16,916) 16,916 ((--)39,386)39,386
(%)(%) ((--) 15.4) 15.4 ((--) 10.3) 10.3
Peak (MW)Peak (MW) Energy (MU)Energy (MU)
RequirementRequirement 1,09,9621,09,962 3,81,9353,81,935
AvailabilityAvailability 93,04693,046 3,42,5493,42,549
((--)Shortage/)Shortage/
(+)Surplus(+)Surplus
((--) 16,916) 16,916 ((--)39,386)39,386
(%)(%) ((--) 15.4) 15.4 ((--) 10.3) 10.3
CAPTIVE POWER
??National Electricity Policy stipulates liberal provisions for setting up captive power plants
??Installed Capacity if Captive plants - 22,335 MW (10th Plan end)
??Open Access to be made effective
??Efforts underway to resolve crucial issues, which are– Cess on captive power generation not to be imposed.
– Wheeling charges for transfer of surplus power may not exceed 7% of the generation cost within the state.
Captive Power
• Very high electricity duty imposed on captive power generation by some states.
• Very high cross subsidies surcharge levied by some state. To be brought down
• Fixation of reasonable tariff by State Regulatory Commission for surplus power available from CPPs.
• To make available additional fuel required by CPPs
• SERC’s to promote arrangements between co-generator and concerned distribution licensee for purchase of surplus power from cogeneration plants.
29
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
MAJOR PROBLEMS OF POWER SECTOR
??Inadequate power generation capacity
??Lack of optimum utilization of the existing generation capacity
??Inadequate inter-regional transmission links
??Inadequate and ageing sub-transmission & distribution network
??High T&D losses, large scale theft and skewed tariff structure
??Slow pace of rural electrification
??Inefficient use of electricity by end consumer
??Lack of grid discipline
MAJOR PROBLEMS OF POWER SECTOR
10TH PLAN –TARGET AND ACTUAL CAPACITY ADDITION
6
(MW)
?Original Target 41,110
?Capacity Slipped / Dropped 21,281
?Net Capacity Addition from Original Target 19,829
?Additional Projects identified during the Plan 8,320
?Capacity Slipping from additional projects 6,969
?Net Capacity Addition from additional Projects 1,351
Net Capacity added during 10 TH Plan 21,180*
* Thermal -12,114 MW, Hydro – 7,886 MW, Nuclear – 1180 MW
30
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
6969*6969*650765072202201455414554TotalTotal
9191-- 990990Adjustment due to change of sizeAdjustment due to change of size1010
12201220Nuclear projects included on best effort Nuclear projects included on best effort basis(otherwisebasis(otherwisescheduled for XI plan)scheduled for XI plan)
99
6060500500Law & Order ProblemsLaw & Order Problems88
31553155Hydro Project Hydro Project -- delay in environmental clearance, delay in environmental clearance, geological surprises, natural calamities, R&R issues, geological surprises, natural calamities, R&R issues, delay in signing of delay in signing of MoUMoU, Court Cases, Court Cases
77
23912391Delay in clearance/investment decision (Hydro projects)Delay in clearance/investment decision (Hydro projects)66
232352785278Projects not taken up/Escrow cover not given/financial Projects not taken up/Escrow cover not given/financial closure not achieved/funds not tied upclosure not achieved/funds not tied up
55
83583522222214231423Delay in award of works mainly in state sector/NLCDelay in award of works mainly in state sector/NLC44
1450145017131713NonNon--availability of Gasavailability of Gas33
39603960Delay in tieDelay in tie--up super critical technology by BHEL (one up super critical technology by BHEL (one unit at unit at SipatSipat and one at and one at KahalgaonKahalgaon were replaced by 500 were replaced by 500 MW units)MW units)
22
3350335067967922022026702670Delay in supplies/erection by suppliers/ contractorsDelay in supplies/erection by suppliers/ contractors11
HydroHydroNuclearNuclearThermalThermal
Additional Additional ProjectsProjects--ThermalThermal
Original PlanOriginal Plan
Major Reasons for SlippageMajor Reasons for SlippageS.NoS.No
6969*650722014554Total
91-- 990Adjustment due to change of size10
1220Nuclear projects included on best effort basis(otherwisescheduled for XI plan)
9
60500Law & Order Problems8
3155Hydro Project -- delay in environmental clearance, geological surprises, natural calamities, R&R issues, delay in signing of MoU, Court Cases
7
2391Delay in clearance/investment decision (Hydro projects)6
235278Projects not taken up/Escrow cover not given/financial closure not achieved/funds not tied up
5
8352221423Delay in award of works mainly in state sector/NLC4
14501713Non--availability of Gas3
3960Delay in tie--up super critical technology by BHEL (one unit at Sipat and one at Kahalgaon were replaced by 500 MW units)
2
33506792202670Delay in supplies/erection by suppliers/ contractors1
HydroNuclearThermal
Additional Projects--Thermal
Original Plan
Major Reasons for SlippageS.No
MAJOR REASONS FOR SLIPPAGES FROM 10 th PLAN (MW)
Total slippage: 21,281MW* Out of a total additional capacity of 8320 MW identified during Mid –Term Review
Major Steps of Integrated approach
??Capacity Addition from Conventional fuel based plants complemented by Renewable Energy based plants to extent possible.
??National Electricity Plan based on Conventional Energy Sources with priority to Hydro and Nuclear plants
??Strategies/ Initiatives being taken/ required to be taken for low carbon growth i.e. Introduction of Clean Coal Technologies (Supercritical Technology, Ultra supercritical technology, IGCC),
??Other measures to reduce pollution i.e. Reduction in T&D losses, R&M of Old thermal power projects, Retirement of old and small size generating units, Coal quality improvement
??Large emphasis on hydro development. . Constraints restricting progress are large gestation period, high capital cost, Issues such as R&R, law & order etc. New Hydro Policy to encourage private participation in hydro power generation.
??Limited dependability on gas based capacity --Availability of gas at reasonable rates being a constraint for gas based projects. During 11th Plan only about 6,843 MW gas based capacity envisaged.
??Active steps to harness Nuclear energy on a larger scale being taken but contribution minor as yet. .
??Renewables.
POWER GENERATION POWER GENERATION -- STRATEGYSTRATEGY
CENTRAL ELECTRICITYAUTHORITY
MINISTRY OF POWERGOVERNMENT OF INDIA
31
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
??Renewable energy sources to be made economically viable-- At present can play dominant role in meeting remote located demands where not economic to extend the grid.
??Coal based power projects expected to be main stay of Indian Power Sector for next 50-70 years. Continuous efforts directed at generating maximum energy from each tonne of coal with minimum effect on environment
POWER POWER GENERATION GENERATION -- STRATEGYSTRATEGY
CENTRAL ELECTRICITY AUTHORITY
MINISTRY OF POWER
GOVERNMENT OF INDIA
Development of Hydro Power projects
147774364941414thth Plan (2022Plan (2022--23 to 23 to
2026 2026 -- 27)27)
111280310001313thth Plan (2017 Plan (2017 -- 18 18
to 2021to 2021--22)22)
80280300001212thth Plan (2012Plan (2012--13 to 13 to
20162016--17)17)
50280156271111 thth Plan (2007Plan (2007--08 to 08 to
2011 2011 -- 12)12)
Total Hydro Capacity Total Hydro Capacity at the end of plan at the end of plan
(MW)(MW)
Hydro Capacity Hydro Capacity
Addition (MW)Addition (MW)Plan PeriodPlan Period
14th Plan (2022--23 to 2026 - 27)
13th Plan (2017 - 18 to 2021--22)
12th Plan (2012--13 to 2016--17)
11th Plan (2007--08 to 2011 - 12)
Total Hydro Capacity at the end of plan (MW)
Hydro Capacity Addition (MW)
Plan Period
DEMAND AND CAPACITY REQUIREMENT
Year Energy Requirement
(BU)
Peak Demand
(MW)
Proposed Capacity Proposed Capacity Addition during 5 Addition during 5 year plan (MW)
Generation growth rate (CAGR)
20112011--1212 10381038 1,52,0001,52,000 77,070*77,070*
( 11( 11 thth Plan)Plan)
9.5% 9.5% (over (over
20062006--07)07)
20162016--1717 14701470 2,18,2092,18,209 94,00094,000
(12(12thth Plan)Plan)
7.4% 7.4% (over (over
20112011--12)12)
Proposed Capacity Addition during 5
2011-12 1038 1,52,000 77,070*
( 11th Plan)
9.5% (over 2006--07)
2016-17 1470 2,18,209 94,000
(12th Plan)
7.4% (over
2011--12)
* Feasible capacity as per latest assessment
32
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
26,783 MW36,874 MW
15,043 MW
CENTRAL SECTORSTATE SECTOR
47%(34%)
CAPACITY ADDITION TARGETTED FOR 11CAPACITY ADDITION TARGETTED FOR 11 thth
PLAN (PLAN (SECTORWISE)SECTORWISE)
11 PLAN –FEASIBLE CAPACITY ADDITION FOR
th – 77,070* MW
Thermal – 58,183 MW( Coal – 48,609 MW, Gas- 7,293 MW, Lignite- 2,280 MW)
Additional capacity expected : New Renewables – 14,000 MW: Captive – 12,000 MW
* Feasible capacity as per latest assessment
NUCLEAR,
3,380MW, 4.3%
THERMAL,
58,183MW,
75.5%
HYDRO,
15,507MW,
20.2%
11TH PLAN TARGET AND STATUS??10th Plan capacity addition only 21,180 MW. About 11,000 MW
slippages due to causes attributable to equipment suppliers and contractors.
??11th Plan – 77,070 MW
??-- 11,404 MW capacity already commissioned (Till date)
??-- 65,666 MW (83%) under construction
-- 85% hydro capacity under construction
-- Coal Linkage available for 96% of projects
??-- All gas based projects under execution or gas tied up from local sources
??Additional 3,720 MW thermal projects under best effort category.
??Additional 13,000 MW gas based projects if gas available at reasonable price
33
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
INTERNATIONAL CONCLAVE ON KEY INPUTS
??On 4th-5th July,2007 organized by CBIP/MoP/CEA.
??Purpose-To discuss issues to be addressed to ensure timely Implementation of projects during 11th Plan and beyond .
MAJOR ISSUES AND CONSTRAINTS TO BE ADDRESSED
??Manufacturing Capability/ Availability of Main Plant and Balance Of Plant Equipment
??Constraints in supply of main equipment for thermal capacity as well as in supply of balance of plant like Coal Handling plant, Water treatment plants, Ash Handling, CW Pumps etc.
??Need to develop additional domestic players to adequately meet additional demand and promote competition.
MAJOR ISSUES AND CONSTRAINTS TO BE ADDRESSED
??Construction and Erection Agencies & Equipment
??Augmentation required in number of construction agencies undertaking Civil & E&M works at power plants - Limited contractors in erection of cooling towers, Chimneys , tunneling, dam construction etc.
??Serious efforts needed by major power companies to develop vendors for supply and erection of equipment and for taking up civil construction.
??New technologies and Use of latest construction machinery for hydro projects required for fast progress in construction.
34
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
MAJOR ISSUES AND CONSTRAINTS TO BE ADDRESSED
??Fuel Availability
??Requirement of coal for 11th Plan –– 550 MT; 40 MT equivalent of 68 MT of Indian coal to be imported
??Requirement of gas (90% PLF) –– 89 MMSCMD; Availability at present-- 36 MMSCMD; gas not sufficient
•• Transportation for fuel and equipment
??Establishment of new rail links for coal evacuation from coal mining blocks
??Railways, Coal , MoP to formulate Fuel Supply Transport Agreement
MAJOR ISSUES AND CONSTRAINTS TO BE ADDRESSED
??Transmission & Distribution Equipment??Need for capacity building for transmission and distribution system
including supply of equipment and execution of works -- Substantial augmentation in manufacturing capacity of transformers; Need for indigenous manufacturing capacity for 765 KV voltage level equipment, increasing test facilities, online test facilities and mobile repair facilities.
??Strengthening of erection and commissioning teams and development of new vendors
??Increase in demand of CRGO??Shortage of indigenous materials and Equipment viz. meters, single
phase distribution transformers and switchgears, OLTC and bushings.gs.??Franchisees to be developed in rural areas and local community to be
trained.??More agencies required for turnkey execution of projects. ??Installation of LT Capacitors to be speeded up.
MAJOR ISSUES AND CONSTRAINTS TO BE ADDRESSED
??Critical Key Inputs??To encourage domestic steel producers for production of CRGO
??Advanced planning for material to be imported
??CRGO to be exempt from custom duty
??Detailed analysis by Planning Commission to assess requirement of various key input considering requirement of all sectors of economy
•• Manpower Development & TrainingManpower Development & Training
??CEA has taken up with project developers and major EPC contractors to adopt ITI in vicinity of projects to build up skilled manpower pool for Power Sector to be utilized by them.
??Quick implementation of National Training Policy ’s recommendation --allocation of separate funds of 1.5% of salary budget -- gradually increase to 5% for meeting training needs
??Man power requirement during 11th Plan is 1 Million for Construction and O& M
35
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
MAJOR ISSUES AND CONSTRAINTS TO BE ADDRESSED
??Delays in clearances
??Testing facilities to be increased and CPRI to play a proactivee
role
??R & D??Power Utilities as well as manufacturing units to enhance budget
allocation for R&D
??To attract young talent
11th Plan tentative targets for grid interactive renewable power
14,000Total
1400Small Hydro (up to 25 MW)
2,100Biomass Power Baggasse Co-generation Biomass Gasifiers
10,500Wind Power
Target for 11 th
planSources / Systems
Total
Small Hydro (up to 25 MW)
Biomass Power Baggasse Co-generation Biomass Gasifiers
Wind Power
Target for 11 th
planSources / Systems
Targets for 12 th Plan likely to be at least 14,000 MW
Village Electrification
??Number of villages electrified increased from 3061 in 1950 to about 4,88,655 in 2008 (as on 31.07.08, 82.3% village electrification).
36
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
Renewable Energy Sources during 12th Plan
??Capacity addition during 12th Plan expected to be more than 11th Plan due to incentives by MNRE for setting up of Solar and Wind power plants
??Considering at least 14,000 MW during 12thth
Plan also, by 12th Plan end about 38,000 MW Renewable power expected.
??Assuming PLF of 20 %, generation about 67 BU.
??This energy considered while planning for 12thth
Plan
12th Plan Tentative Capacity Addition ??Demand as per 17th EPS – Energy Requirement – 13,92,066
BU; Peak Demand- 2,18,209 MW
??Spinning Reserve – 5% as per National Electricity Policy. Capacity corresponding to 3000 MW and 1600 MW also worked out
??25,000 MW Hydro and 8,500 MW Nuclear as must run stations.
??As result of studies 12th Plan total Generating capacity 94,431 which includes 61,171 MW thermal.(28,190 MW PH, 15,495 MW LC, 14,800 MW Coastal)
??Capacity with 1600 MW S.R.-- 81,570 MW; 3000MW S.R. ––82,970 MW
??Fuel consumption(2016--17) – Coal 815 MT, Lignite 60 MT
??All India Studies for 5% S.R: LOLP – 0.18%; ENS – 0.00% (Norms – LOLP--1% & ENS-- 0.15%)
13th Plan Tentative Capacity Expansion
ASSUMPTIONS
??17th EPS Demand – Energy Requirement- 19,14,508 MU; Peak Demand- 2,98,253 MW
??Spinning Reserve - 5% .
??Beginning of 13th Plan 37,014 MW Coal & Lignite based capacity more than 27 yrs old. (5,634 MW capacity upto 100 MW unit size and 31,380 MW capacity greater than 100 MW unit t
size)
??Studies indicate 13th Plan capacity addition--1,05,060 MW (Hydro-34,500 MW, Nuclear --8,000 MW, Thermal --62,560 MW including 6000 MW gas)
??LOLP-0.18 % and ENS-0.007 %, Reliability Criteria met.
37
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
STRATEGIES FOR CLEAN
AND
GREEN ENVIRONMENT
4.5World
3.8China
9.9Japan
9.8U.K
16.2Australia
20.6USA
1.2India
Per capita CO2 emission in 2004 (tonnes/MWhr of CO2)Country
4.5World
3.8China
9.9Japan
9.8U.K
16.2Australia
20.6USA
1.2India
Per capita CO2 emission in 2004 (tonnes/MWhr of CO2)Country
?UNDP Human Development report 2007/08
Existing status of CO2 per capita emission – different countries
Strategies/ Initiatives for GHG
Mitigation
??Clean Coal technologies??Supercritical Technology –– 2% efficiency gain possible
??Ultra Supercritical Technology –additional efficiency 0.75% over 800 MW supercritical
??Integrated Gasification Technology – higher efficiency of 40-45%
•• Reduction in T & D losses – All India T&D losses--
28.65% in 2006--07. Aim to bring down to 15%
•• R & M of old thermal power stations – Benefits of CDM to be extended to overcome fund constraints
•• Energy Efficiency improvement
38
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
UNIT-WISE DETAILS OF I.C (coal +
lignite)( as on 31/3/2007)
38.638.6
38.338.3
35.6 to 35.6 to 37.0437.04
34.434.4
28.2 to 31.328.2 to 31.3
DESIGN DESIGN EFFICIENCY(%EFFICIENCY(%))
33,58033,580157157200/210200/210
4,2504,2501717250250
18,00018,0003636500500
844084407373>100 & >100 & uptoupto 199199
563456349595UptoUpto 100
Actual Actual Operating Operating Efficiency(Efficiency(%)%)
CAPACITY(MWCAPACITY(MW))
NO. OF NO. OF UNITSUNITS
UNIT SIZE UNIT SIZE IN MWIN MW
38.6
38.3
35.6 to 37.04
34.4
28.2 to 31.3
DESIGN EFFICIENCY(%))
33,580157200/210
4,25017250
18,00036500
844073>100 & upto 199
563495Upto
Actual Operating Efficiency(%)
CAPACITY(MW)
NO. OF UNITS
UNIT SIZE IN MW
UNIT--WISE DETAILS OF I.C (coal +
lignite)( as on 31/3/2007)
38.638.6
38.338.3
35.6 to 35.6 to 37.0437.04
34.434.4
28.2 to 31.328.2 to 31.3
DESIGN DESIGN EFFICIENCY(%EFFICIENCY(%))
33,58033,580157157200/210200/210
4,2504,25017250250
18,00018,0003636500500
844084407373>100 & >100 & uptoupto 199199
563456349595UptoUpto 100100
Actual Actual Operating Operating Efficiency(Efficiency(%)%)
CAPACITY(MWCAPACITY(MW))
NO. OF NO. OF UNITSUNITS
UNIT SIZE UNIT SIZE IN MWIN MW
38.6
38.3
35.6 to 37.04
34.4
28.2 to 31.3
DESIGN EFFICIENCY(%)
33,580157200/210
4,250250
18,00036500
844073>100 & upto 199
563495Upto 100
Actual Operating Efficiency(%)
CAPACITY(MW)
NO. OF UNITS
UNIT SIZE IN MW
Sub--critical units in 10th, 11th , 12th,
13th & 14th Plans
00
00
22
1414
44
125/13125/135 MW 5 MW ((nosnos))
00
00
00
66
99
200/2200/210 MW 10 MW ((nosnos))
96209620771111001010THTH PlanPlan
00
00
1212
6262
250/3250/300/3300/330 MW 0 MW ((nosnos))
18270182702020771212thth PlanPlan
00
88
4242
500 MW 500 MW
((nosnos))
000014th Plan14th Plan
40004000001313THTH Plan Plan
4547045470881111THTH Plan Plan
Total Total SubcriticaSubcritica
ll MWMW
600 600 MWMW
((nosnos))
0
0
2
14
4
125/135 MW ((nos))
0
0
0
6
9
200/210 MW ((nos))
962071101010THTH PlanPlan
0
0
12
62
250/300/330 MW ((nos))
182702071212thth PlanPlan
0
8
42
500 MW
((nos))
0014th Plan14th Plan
400001313THTH Plan Plan
4547081111THTH Plan Plan
Total Subcritica
ll MW
600 MW
((nos))
39
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
Super-critical units in 10th , 11th , 12th
, 13th & 14th Plans
96209620000000962010TH Plan
71,30071,300
52,56052,560
42,900
54205420
Total
Super critical MW
00
4000
18270
4547045470
Total Sub critical
MW
61,17061,1703333252512th Plan
5252
3636
11
800 MW
((nos))
71,30071,300454514th Plan
56,56056,560363613TH Plan
50890508907711TH Plan
Total MW
660 MW
(nos)
9620000
71,300
52,560
5420
0
45470
61,1703325
52
36
1
( )
71,30045
56,56036
508907
Comparison of Sub--critical/Super critical Capacity In Various Plans (MW)
9620
45470
18270
400000
5420
42900
52560
71300
0
10000
20000
30000
40000
50000
60000
70000
80000
10th Plan 11th Plan 12th Plan 13th Plan 14th Plan
Sub-Critical Super Critical
ALL INDIA EFFICIENCY AND EMISSION RATES
??All India thermal efficiency – 32.44% (2006--07)
(coal & lignite based plants)
??Present weighted average CO2 emission rate (t CO2 /MWh) (including imports) : 0.80 (2006-07)
40
International Seminar on Emerging Technologies & Strategies for Energy Management in Railways
Likely Coal Based Capacity Addition & Expected Emission
19611961
15071507
11521152
722722
Co2 Co2 EmissioEmissio
nn(MT)(MT)
0.960.96
0.97
0.990.99
1.021.02
Co2 EmissioEmissio
n per n per unit of unit of
Thermal Thermal GeneratiGenerati
onon
37.337.3
36.8536.85
36.4
35.335.3
Expected Expected TherThermal mal
EfficiEfficiencyency
303595303595
231595231595
175095175095
116610116610
CumulatiCumulativeve
Coal Coal BaseBase
ddCapacityCapacity
(MW)(MW)
20332033
15421542
11641164
708708
Total Total GenerGeneration ation from from Coal Coal
Based Based PlantsPlants
(BU)(BU)
13371337
10281028
785785
492492
CoalCoalConsumptiConsumpti
onon(MT)(MT)
7200072000
5650056500
5848558485
5024050240
CoalBasedCapacit
yAdditio
nn(MW)(MW)
1821821111thth PlanPlan
471471
363363
278278
Total Ash Total Ash GeneraGenera
tiontion(MT)(MT)
1414thth PlanPlan
1313thth PlanPlan
1212thth PlanPlan
End of End of The The PlanPlan
1961
1507
1152
722
Co2 Emissio
n(MT)
0.96
0.99
1.02
Emission per
unit of Thermal Generati
on
37.3
36.85
35.3
Expected Thermal
Efficiency
303595
231595
175095
116610
Cumulative
Coal Base
dCapacity
(MW)
2033
1542
1164
708
Total Generation from Coal
Based Plants
(BU)
1337
1028
785
492
CoalConsumpti
on(MT)
72000
56500
58485
50240
y
n(MW)
18211th Plan
471
363
278
Total Ash Genera
tion(MT)
14th Plan
13th Plan
12th Plan
End of
Plan