power quality during the late 90’s pq was dominated by fluke and lem power utilities has just...
TRANSCRIPT
Power Quality during the late 90’s PQ was dominated by Fluke and LEM Power Utilities has just started talking
about standards to be followed National Power Corporation, Meralco -
main proponents in the utility companies involved in setting up the standards
A very few manufacturing companies are aware of the need of PQ for their facilities
Power Quality in the 2000’s
More players came in (RPM, Dranetz-DMI, Hioki, EIG, AEMC, Unipower, etc)
Philippine Grid Code was published and started to be implemented (2001)
Philippine Distribution Code was published and started to be implemented (2001)
TransCo was separated from the National Power Corporation (2003)
National Power Corporation, TransCo, Meralco - became models in the PQ standardization
Power Quality in the 2000’s (cont..)
Privatization of the government owned Power Plants
TransCo became the National Grid Corporation of the Philippines (NGCP)
Models for PQ originates from NGCP and Meralco using the PGC and PDC as basis for the standards
Manufacturing facilities engineers became aware of the need to implement PM involving PQ
Grid Code PQ Requirements
Power Quality Performance (Article 3.2) System Frequency Deviation Voltage Magnitudes Variations Voltage Fluctuations Harmonic Frequencies Voltage Unbalance Transient Voltage Variations
Grid Code PQ Requirements
Frequency Variations
Nominal Frequency – 60 Hz
Maintain Frequency during normal conditions
Limits: 59.4 Hz ≤ f ≤ 60.6 Hz
Grid Code PQ Requirements
Voltage Variations Long Duration Voltage Variation
Duration greater than 1 minuteUndervoltage (RMS value is less than or
equal to 90% of the nominal value)Overvoltage (RMS value is greater than or
equal to 110% of the nominal value)95% ≤ RMS nominal voltage ≤ 105%
Grid Code PQ Requirements
Voltage Variations Short Duration Voltage Variation
Duration greater than ½ cycle but not exceeding 1 minute
Voltage Swell (RMS value increases between 110% and 180% of the nominal value)
Voltage Sag (RMS value decreases between 10% and 90% of the nominal value)
Grid Code PQ Requirements
Voltage Fluctuation Random amplitude changes of RMS value
between 90% to 110% of the nominal voltage
Voltage fluctuation shall not exceed 1% of the nominal voltage for every step change, which may occur repetitively
Large voltage fluctuation other than a step change maybe allowed up to 3% provided will not put risk to the Grid or any User system
Grid Code PQ Requirements Flicker Severity
Short Term Flicker Severity (PST) – short duty cycle fluctuation,shall be computed over a 10-minute period
Short Term Flicker Severity (PLT) – long and variable duty cycle fluctuation, derived from PST levels
Grid Code PQ Requirements Harmonics
Total Harmonic Distortion (THD) – ratio of the RMS value of the harmonic content to the RMS value of the fundamental quantity in percent
Grid Code PQ Requirements Harmonics
Total Demand Distortion (TDD) – ratio of the RMS value of the harmonic content to the RMS value of the rated or maximum fundamental quantity in percent
Grid Code PQ Requirements Voltage Unbalance
Refers to negative sequence unbalance factor or zero unbalance factor
Negative Sequence Unbalance Factor = Negative Sequence Components of Voltages
Positive Sequence Components of Voltages
Zero Sequence Unbalance Factor = Zero Sequence Components of Voltages Positive Sequence Components
of Voltages
Compliance:Voltage Unbalance ≤ 1% for 115 kV and aboveVoltage Unbalance ≤ 2.5% for 69 kV and below
Grid Code PQ Requirements
Transient Voltage VariationsHigh frequency overvoltages shorter in
duration compared to short duration voltage variations
In-frequent short-duration may exceed levels of harmonics limits provided such increases do not compromise service to End-users or cause damage to Grid equipment
In-frequent short-duration with a maximum value of 2% maybe permitted for Voltage Unbalance subject to terms of Connection Agreement
END OF PRESENTATION
THANK YOU